This document contains 3 statements of time elapsed and work accomplished for the construction of a 10-storey headquarters building by ABC Corporation. As of September 2018, 26 calendar days had elapsed, reported completion was 22.1% and actual completion was 19.2% with a 2.9% slippage. By December 2018, elapsed time was 3.8 months, reported completion was 38.2% and actual completion was 32% with a 6.2% slippage. As of April 2019, elapsed time was 7.15 months, reported completion was 67% and actual completion was 54% with a 13% slippage, and the project had stopped due to issues between parties.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
530 views10 pages
Progress Billing
This document contains 3 statements of time elapsed and work accomplished for the construction of a 10-storey headquarters building by ABC Corporation. As of September 2018, 26 calendar days had elapsed, reported completion was 22.1% and actual completion was 19.2% with a 2.9% slippage. By December 2018, elapsed time was 3.8 months, reported completion was 38.2% and actual completion was 32% with a 6.2% slippage. As of April 2019, elapsed time was 7.15 months, reported completion was 67% and actual completion was 54% with a 13% slippage, and the project had stopped due to issues between parties.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 10
Jones Ave.
, Cebu City Tel no. 14334455
Project Title: Construction of 10-Storey Headquarters
Location: IT Park, Lahug, Cebu City Contractor: ABC Corporation Contractor ID: 21DN657
CWD STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED
As of September 25, 2018
Original Contract time 150 calendar days
Date of Effectivity of Contract May 18, 2018 Commencement of project August 30, 2018 Original Contract Amount 80,000,000.00 Contract time elapsed 26 CD Percentage of reported completion 22.1% Percentage of Actual Completion 19.2% Slippage 2.9%
Remarks: Project on going
Prepared by: Approved by:
Engr. Michael Reyes Engr. Emilio Narra
Engineer II General Manager Jones Ave., Cebu City Tel no. 14334455
Project Title: Construction of 10-Storey Headquarters
Location: IT Park, Lahug, Cebu City Contractor: ABC Corporation Contractor ID: 21DN657
CWD STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED
As of December 22, 2018
Original Contract time 150 calendar days
Date of Effectivity of Contract May 18, 2018 Commencement of project August 30, 2018 Original Contract Amount 80,000,000.00 Contract time elapsed 3.8 mos Percentage of reported completion 38.2% Percentage of Actual Completion 32% Slippage 6.2%
Remarks: Project on going
Prepared by: Approved by:
Engr. Michael Reyes Engr. Emilio Narra
Engineer II General Manager Jones Ave., Cebu City Tel no. 14334455
Project Title: Construction of 10-Storey Headquarters
Location: IT Park, Lahug, Cebu City Contractor: ABC Corporation Contractor ID: 21DN657
CWD STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED
As of April 15, 2019
Original Contract time 150 Calendar days
Date of Effectivity of Contract May 18, 2018 Commencement of project August 30, 2018 Original Contract Amount 80,000,000.00 Contract time elapsed 7.15 mos Percentage of reported completion 67% Percentage of Actual Completion 54% Slippage 13%
Remarks: Project stopped due to issues between the parties.
Prepared by: Approved by:
Engr. Michael Reyes Engr. Emilio Narra
Engineer II General Manager Attachment for progress billing No. 1 Attachment for progress billing 2: Attachment for progress billing 3: