Topic 6 - Network Analysis
Topic 6 - Network Analysis
Objectives
After completing this chapter, students will be able to:
1. Understand how to plan, monitor, and control
projects with the use of PERT and CPM.
2. Determine earliest start, earliest finish, latest start,
latest finish, and slack times for each activity, along
with the total project completion time.
3. Reduce total project time at the least total cost by
crashing the network using manual or linear
programming techniques.
4. Understand the important role of software in project
management.
Introduction
PERT/CPM
PERT/Cost
Project Crashing
Other Topics in Project Management
IMMEDIATE
ACTIVITY DESCRIPTION
PREDECESSORS
A Build internal components —
B Modify roof and floor —
C Construct collection stack A
D Pour concrete and install frame B
E Build high-temperature burner C
F Install control system C
G Install air pollution device D, E
H Inspect and test F, G
Table 6.1
AC 407 Management Accounting &
Control 1
Drawing the PERT/CPM Network
Figure 6.1
AC 407 Management Accounting &
Control 1
Activity Times
• In some situations, activity times are known with certainty.
• The CPM assigns just one time estimate to each activity and
this is used to find the critical path.
• In many projects there is uncertainty about activity times.
• PERT employs a probability distribution based on three time
estimates for each activity, and a weighted average of these
estimates is used for the time estimate and this is used to
determine the critical path.
– PERT often assumes time estimates follow a beta probability
distribution.
Figure 6.2
AC 407 Management Accounting &
Control 1
Activity Times
To find the expected activity time (t), the beta distribution
weights the estimates as follows:
a 4m b
t
6
ba
2
Variance
6
MOST EXPECTED
OPTIMISTIC, PROBABLE, PESSIMISTIC, TIME, VARIANCE,
ACTIVITY a m b t = [(a + 4m + b)/6] [(b – a)/6]2
A 1 2 3 2 4/36
B 2 3 4 3 4/36
C 1 2 3 2 4/36
D 2 4 6 4 16/36
E 1 4 7 4 36/36
F 1 2 9 3 64/36
G 3 4 11 5 64/36
H 1 2 3 2 4/36
25
Table 6.2
Figure 6.3
AC 407 Management Accounting &
Control 1
How to Find the Critical Path
To find the critical path, we need to determine the following
quantities for each activity in the network.
1. Earliest start time (ES): the earliest time an activity can begin
without violation of immediate predecessor requirements.
2. Earliest finish time (EF): the earliest time at which an activity
can end.
3. Latest start time (LS): the latest time an activity can begin
without delaying the entire project.
4. Latest finish time (LF): the latest time an activity can end
without delaying the entire project.
ACTIVITY t
ES EF
LS LF
A t=2
ES = 0 EF = 0 + 2 = 2
Start
B t=3
ES = 0 EF = 0 + 3 = 3
Figure 6.4
Figure 6.5
Table 6.3
AC 407 Management Accounting &
Control 1
How to Find the Critical Path
General Foundry’s Critical Path
Figure 6.6
AC 407 Management Accounting &
Control 1
Probability of Project Completion
Figure 6.7
Figure 6.8
Table 6.4
Figure 6.9
AC 407 Management Accounting &
Control 1
Budgeting for General Foundry
Activity costs for General Foundry, Inc.
EARLIEST LATEST TOTAL BUDGETED
START, START, EXPECTED BUDGETED COST PER
ACTIVITY ES LS TIME, t COST ($) WEEK ($)
A 0 0 2 22,000 11,000
B 0 1 3 30,000 10,000
C 2 2 2 26,000 13,000
D 3 4 4 48,000 12,000
E 4 4 4 56,000 14,000
F 4 10 3 30,000 10,000
G 8 8 5 80,000 16,000
H 13 13 2 16,000 8,000
Total 308,000
Table 6.5
WEEK
ACTIVITY 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 TOTAL
A 11 11 22
B 10 10 10 30
C 13 13 26
D 12 12 12 12 48
E 14 14 14 14 56
F 10 10 10 30
G 16 16 16 16 16 80
H 8 8 16
308
Total to date 21 42 65 90 126 162 198 212 228 244 260 276 292 300 308
Table 6.6
WEEK
ACTIVITY 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 TOTAL
A 11 11 22
B 10 10 10 30
C 13 13 26
D 12 12 12 12 48
E 14 14 14 14 56
F 10 10 10 30
G 16 16 16 16 16 80
H 8 8 16
308
Total to date 11 32 55 78 104 130 156 182 198 214 240 266 292 300 308
Table 6.7
Figure 6.10
VALUE OF
TOTAL WORK ACTIVITY
BUDGETED PERCENT OF COMPLETED ACTUAL DIFFERENCE
ACTIVITY COST ($) COMPLETION ($) COST ($) ($)
A 22,000 100 22,000 20,000 –2,000
B 30,000 100 30,000 36,000 6,000
C 26,000 100 26,000 26,000 0
D 48,000 10 4,800 6,000 1,200
E 56,000 20 11,200 20,000 8,800
F 30,000 20 6,000 4,000 –2,000
G 80,000 0 0 0 0
H 16,000 0 0 0 0
Total 100,000 112,000 12,000
Table 6.9
Figure 6.11
Figure 6.12