AGES - Method Statement For PDA
AGES - Method Statement For PDA
Method Statement
for
PILE DYNAMIC
ANALYSIS
(PDA)
Pile Integrity Testing (PIT) Static Load Testing Cross-Hole (Ultrasonic) Testing
(ASTM D4945)
Page 1 of 7
I. INTRODUCTION
A Pile Driving Analyzer, Pak and/or latest 8G PDA-S Model (Manufactured by PDI, USA),
will be used for the high-strain dynamic testing. The test shall utilize the so-called Case
Method to obtain quick quantitative results at the site, such as Hammer transfer energy,
compressive and tensile stresses in the pile, estimated pile capacity during driving, etc.
Graphs of the Force and Velocity records will be continuously viewed from the PDA monitor
for each blow for on site appreciation and evaluation.
The Contractor shall provide for the test setup, which shall include the supply of all the
materials and equipment required to prepare the test pile, and dynamically load the test pile.
Page 3 of 7
10) An independent team of Surveyor with suitable surveying equipment (i.e., transit) to
measure pile sets during Restrike testing must be provided by the Client /
Contractor during testing.
11) Working area consisting of table and shade/shelter for the PDA Machine and test
crew in case of rain or extreme exposure to sun / heat must be provided during
testing.
12) Power Supply. 220 V AC uninterrupted and stable power supply during pile
preparation for hand drill and grinder.
13) The hammer impact causes noise and some minimal vibration. The distraction that
the noise creates is more of a concern than the effect to adjacent structures. A traffic
aide maybe engaged to direct traffic away from the PDA test area when hammer is
about to be dropped.
Prior to performing the dynamic test, AGES Team must be provided with soil borings
representing the actual pile location, driving records, pile construction records, detailed
excavation and concrete pouring records, concrete tests (strength, etc.) and other
pertinent details (design capacity, safety factor & etc.).
Pile shaft will have to be practically uniform just below the gauge location, or saying it in
another way, the gauges should not be placed just above the pile section where there are
abrupt changes in cross- section (bulges / necks) and/or material quality. This could mean
excavation to expose the pile shaft to show good concrete quality and shaft shape
uniformity.
Page 4 of 7
IV. GATHERING OF DYNAMIC DATA
During testing, the PDA machine processed the records almost instantaneously and
calculates values with some simplifying assumptions using the Case Method. The
calculated values can be viewed on the screen in real time. Among other data, information
such as 1) the maximum mobilized capacity for the specific blow, RMX; 2) the pile integrity
factor, BTA; 3) maximum average pile compressive stresses (CSX); 4) maximum delivered
energy (EMX), etc., can be obtained during actual testing.
For the Restrike Tests, the testing is normally conducted at least 24 days after concreting or
more depending on the diameter of the pile. The gauges shall be attached at diametrically
opposite sides of the pile, with 2 sets (1 set for driven piles)of strain and 1 set of
accelerometers, about 1.5-2 meters from the top. After attaching the gauges to the PDA
Machine, the test pile is then dynamically loaded using the drop hammer to activate and
measure the pile capacity. The drop height is normally started low, and raised higher for
higher energy until the required pile capacity is proven, or until the ultimate capacity is
achieved.
After the test, the data is electronically stored and back-up as part of the documentation
process for evaluation in the office.
The data obtained in the field is processed for a more detailed analysis using the Case Pile
Wave Analysis Program (CAPWAP®) for capacity determination. CAPWAP® program is an
iterative software tool that tries to match the measured force and/or velocity traces by
numerically modeling the soil and pile system. Among other things, pile properties such as
modulus, cross-sectional area and wavespeed, soil parameters such as skin and toe
quakes, damping factors, skin resistance distribution and end bearing, etc. are inputted to
the model to arrive at the desired match quality.
The CAPWAP analyses shall be performed at AGES Office by PDI/PDCA world certified
individual/s, and the report will provide the final bearing capacity evaluation for the selected
blow, and other calculated values by the Capwap such as stresses in the pile, hammer
transfer energy, detected damage if any, splice condition, etc.
Page 5 of 7
VII. SCHEMATIC DIAGRAM OF PDA FIELD TEST SYSTEM
Page 6 of 7
TYPICAL SET-UP OF PDA TESTING
Crane
(by client contractor)
Hammer Guide
(by client contractor)
Tripping mechanism
(by client contractor)
Drop Hammer
(by client contractor)
Plywood cushion, 25-50mm thick
(by client contractor)
The entire set-up will be done by the Client’s Contractor. AGES will provide the
testing equipment such as strain gauge, accelerometers, wires and PDA
machine.
Page 7 of 7