Api 570 199-352
Api 570 199-352
c. Inspection of inservice
piping.
a. Yes.
d. No.
Which of the following services c. Water, steam, boiler feed water, and Category D
is not included under the fluid services as defined in ASME B31.3.
requirements of API 570?
a. Catalyst lines.
a. The Inspector.
b. The Engineer.
c. The Owner-User.
d. The Jurisdiction.
a. The Inspector.
b. The Owner-User.
c. The Jurisdiction.
d. The API.
Under the requirements of API c. Other personnel are responsible for making the
570, what responsibilities do Inspector and Engineer aware of any unusual
personnel other than the conditions.
Inspector, Engineer, and
Repair Organization have?
a. None.
a. Appropriate safety
precautions should be taken
prior to opening any system for
internal inspection.
Prior to making an inspection b. Review the past inspection results and repair
of a piping system, the history of the system.
inspector should:
a. Require a hydrostatic
pressure test of the system.
a. Annual UT surveys.
b. Specific attention as
determined from past
inspections.
c. Elimination by redesign of
the system.
Injection point circuits should The greater of 12" or three pipe diameters.
extend how far upstream?
a. 12".
c. At intermediate locations
along longer straight runs.
Why are injection points more a. Due to accelerated or localized corrosion due to
of a concern than other areas normal or abnormal operating conditions.
of the piping system?
a. Due to accelerated or
localized corrosion due to
normal or abnormal operating
conditions.
d. Because of jurisdictional
requirements for handling the
toxic injection fluids.
a. The API.
b. The Owner-User.
c. The Jurisdiction.
d. The Engineer.
570 Study Guide
https://quizlet.com/113092609/570-study-guide-flash-cards/ 12/86
5/22/2021 570 Study Guide Flashcards | Quizlet
a. Yes.
d. No.
a. Visual Inspection.
b. RT or UT to establish the
minimum thickness.
c. Hammer Testing.
d. Internal Inspection.
a. The Inspector.
b. The Owner-User.
c. The Jurisdiction.
d. The API.
During periodic scheduled a. Extensive inspection of the area 12" above and 10
inspections, which of the pipe diameters downstream of the injection point in
following is recommended by
API
b. Recording thickness
readings at established TML's
only, unless further
investigation is required.
c. Full UT or RT inspection of
the entire injection point circuit.
The corrosion rate in deadlegs d. Different from the adjacent active piping.
is normally:
When taking thickness readings d. Along the entire length of the deadleg.
on deadlegs, thickness
readings should be taken at:
c. In the center.
b. Convective currents.
c. Steam accumulation.
b. Signs of CUI.
c. Sources of moisture.
Which of the following are the b. Localized corrosion of carbon steels and stress
most common forms of corrosion cracking of austenitic stainless steels.
corrosion under insulation?
b. Localized corrosion of
carbon steels and stress
corrosion cracking of austenitic
stainless steels.
d. Intergranular corrosion of
stainless steels and pitting of
carbon steels.
Which of the following c. Carbon steel piping systems operating over 350
examples of piping systems degrees F.
would be the least susceptible
to CUI
While inspecting a piping b. Moisture could enter the insulation and cause
system, you notice that the corrosion of the piping system.
insulation jacketing is damaged
and that the caulking at the
joints is damaged and the
insulation is damp. What would
you be concerned about
c. Product leakage.
a. The Inspector.
c. The Owner-User.
d. The Jurisdiction.
What would you suspect if b. Corrosion products have built up, thus bulging
while inspecting an insulated the insulation.
line you notice a bulged area?
b. Reinstalled immediately.
d. Discarded.
Buried piping without c. Requires that all air to soil interfaces be included
adequate cathodic protection in the scheduled external inspections.
requires:
a. Installation of a cathodic
protection system in
accordance with the
requirements of API 570.
d. Installation of wrapping to
protect the pipe.
a. At each scheduled
inspection.
a. The inspector.
b. The Engineer.
c. The Owner-User.
While inspecting a 20 year old a. Excavate the area to inspect for corrosion before
piping system without cathodic resealing the joint.
protection, you notice that the
caulking around the
pipe at the concrete has
deteriorated. What actions
would you recommend?
d. Recommend replacement of
the underground line with an
aboveground line.
a. No excavation is required if
there is no visible corrosion.
b. 6 to 12 feet should be
uncovered to look for hidden
damage.
c. 2 to 4 feet should be
uncovered to look for hidden
damage.
d. 6 to 12 inches should be
uncovered to look for hidden
damage.
c. Continuous inspection of
affected systems.
d. Communication from
operations personnel when
process upsets occur.
As an API 570 inspector,what c. The welds in the non post weld heat treated areas
action would you recommend should be inspected for cracking.
if you were inspecting a
carbon steel piping system in
which caustic could carry over
into non post weld heat
treated areas?
a. Localized corrosion.
As an inspector, to what area a. To any low flow areas where hot spots can
would you pay particular develop.
attention while inspecting a
carbon steel caustic system
with
steam tracing installed?
a. An electrochemical action
which dissolves the metal.
d. A combination of
electrochemical action and the
impact of solids.
b. Upstream of pump
discharges.
c. In turbulent areas.
d. Upstream of orifices.
b. Downstream of control
valves, pump discharges, or
orifices.
a. Corrosion.
b. Erosion.
b. UT scanning or profile RT of
areas suspected of having
localized corrosion.
Which of the following is not b. Cracking due to residual stress from fabrication.
classified as an environmental
cracking problem?
a. Embrittlement.
d. Intergranular corrosion.
https://quizlet.com/113092609/570-study-guide-flash-cards/ 36/86
5/22/2021 570 Study Guide Flashcards | Quizlet
a. Separation or disbonding.
b. Holes or breaks.
a. Loose refractory.
https://quizlet.com/113092609/570-study-guide-flash-cards/ 38/86
5/22/2021 570 Study Guide Flashcards | Quizlet
a. UT or RT of suspected
corrosion areas.
d. Borescope inspections of
the line
Upon which of the following c. Large diameter systems such as catalyst lines and
types of lines is it sometimes transfer lines.
possible or practical to
perform internal inspections?
a. Deadlegs.
b. Injection points.
d. When requested by
operations personnel.
570 Study Guide
https://quizlet.com/113092609/570-study-guide-flash-cards/ 40/86
5/22/2021 570 Study Guide Flashcards | Quizlet
b. Maintenance personnel.
c. Operations personnel.
When corrosion product a. Arrange to have the pipe lifted off the supports
buildup is noted at pipe for inspection.
supports, what action should
be recommended by the
inspector?
d. Recommend replacement of
the deteriorated pipe spool.
b. ASME B 31.3.
d. ASME B 16.5.
Which of the following is not d. Determining the load applied by the piping to the
normally checked when hangers.
making and external inspection
of piping?
b. Visual inspection.
c. Profile radiography.
a. The inspector.
b. Qualified maintenance
personnel.
c. Qualified operations
personnel.
c. An appropriate amount of
training.
d. An engineering degree is
required.
a. The inspector.
d. a or b.
a. No action as long as no
damage appears to have
occurred.
a. Radiography or
thermography.
b. Radiography or visual
inspection.
c. Radiography or ultrasonic
testing.
a. Thermography.
d. Acoustic emissions.
a. Thermography.
c. Acoustic emissions.
c. A thermal monitoring
location at which a
thermocouple is installed.
a. The inspector.
c. A person knowledgeable in
corrosion.
d. The jurisdiction.
570 Study Guide
https://quizlet.com/113092609/570-study-guide-flash-cards/ 51/86
5/22/2021 570 Study Guide Flashcards | Quizlet
a. Radiography or ultrasonic
testing.
a. No.
b. Yes.
When ultrasonics are used to c. By using either the thinnest reading or the
make minimum thickness average of the readings obtained.
determinations at TML's, how is
the minimum thickness
determined?
a. To allow repetitive
measurements at the same
TML's.
d. To demonstrate compliance
with OSHA CFR 1910.119.
What determines the number c. The past experience and corrosion patterns.
and locations of TML's?
b. ASME B31.3.
d. The jurisdiction.
c. Localized corrosion.
The TML selection for each d. The nature of the corrosion expected.
system is determined by:
a. API 570.
c. Jurisdictional requirements.
b. Less TML'S.
c. More TML's.
a. No TML's.
b. Fewer TML's.
a. Yes.
b. No.
a. Radiography.
b. Ultrasonics.
c. Hammer Testing.
d. Eddy Current
570 Study Guide
https://quizlet.com/113092609/570-study-guide-flash-cards/ 57/86
5/22/2021 570 Study Guide Flashcards | Quizlet
b. To prevent heating or
cooling of the piping contents.
a. UT.
b. RT.
c. VT.
d. PT.
a. 150 degrees F.
b. 250 degrees F.
c. 500 degrees F.
d. 650 degrees F.
a. Improper calibration.
d. Couplant viscosity.
d. b or c.
b. Taking thickness
measurements on castings,
forgings, and valve bodies.
a. Yes.
b. No.
d. Yes, if calibrated.
a. Yes.
b. No.
a. API 570.
b. API 574.
c. ASME B31.3
d. API 920.
a. ASME B31.3
b. API 570.
a. Freezing is a consideration.
a. 70 degrees F.
b. 100 degrees F.
c. 120 degrees F.
d. 150 degrees F.
a. Diesel fuel.
b. Lubricating oil.
d. Salt water.
b. Water with a pH of 8 or
more.
d. a or c.
d. No.
a. Removed.
b. Blanked.
c. Gagged.
a. Yes.
b. Yes, if performed by a
maintenance technician.
c. Yes, if performed by a
certified valve shop.
d. No.
Why should thickness readings c. Because this is any area of high turbulence and
be thin between the seats on stress.
gate valves?
Where should particular care b. The body and piping downstream of the orifice.
be taken when taking thickness
measurements on control
valves or other valves?
a. API 570.
b. API 574.
c. API 620.
d. API 598.
b. Determine if caused by
original construction or
environmental cracking.
a. The inspector.
c. The owner-user.
d. The jurisdiction.
a. Inspector judgement.
b. CWI judgement.
a. Yes.
b. No.
a. 5%
b. 10%
c. 25%
d. A representative sample.
a. None is required.
Before replacing bent flanges a. Their markings and thickness should be checked
installed in a piping system, against engineering requirements.
what should be done?
a. Leakage.
b. Corrosion.
c. Cracking.
a. Yes.
d. No.
a. Class 1.
b. Class 2.
c. Class 3.
d. Class 4.
a. Risk of fire.
b. Risk of leaks.
d. Economic loss.
a. Yes.
b. No.
b. Hydrofluoric acid.
c. Hydrogen.
a. Fuel gas.
c. Anhydrous hydrogen
chloride.
When should thickness c. At the half corrosion rate life whichever is less.
measurements be scheduled
on piping systems?
a. Annually.
a. 1 year.
b. 3 years.
c. 5 years.
d. 10 years.
a. Annually.
b. Every 3 years.
c. Every 5 years.
d. Every 10 years.
For first time CUI inspection on c. At least 50% of all suspect or damaged insulation
class 1 and 2 lines, what is the areas.
minimum amount if inspection
recommended by API
570?
For first time CUI inspection of a. At least 10% of all suspect or damaged insulation
class 3 systems, what is the areas.
minimum amount of inspection
required?
a. An additional 10%.
b. An additional 25%.
c. Up to 100%.
For piping systems with a d. The system insulation system or outer jacketing
remaining life over 10 years or should be observed periodically by operating or
that are protected against other
external corrosion, what personnel.
inspection requirements apply
https://quizlet.com/113092609/570-study-guide-flash-cards/ 86/86