Bill of Quantities For Proposed Swimming Pool: S/No Item Description QTY Unit Rate Amount

The document provides a bill of quantities for a proposed swimming pool project. It includes items for excavation and filling, membrane, in-situ concrete works, reinforced concrete, formwork, reinforcement, rendering and screeding, floor and wall finishing, accessories, and provision for plumbing and electrical installation. The total cost for all items is estimated to be ₦3,363,670.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
135 views12 pages

Bill of Quantities For Proposed Swimming Pool: S/No Item Description QTY Unit Rate Amount

The document provides a bill of quantities for a proposed swimming pool project. It includes items for excavation and filling, membrane, in-situ concrete works, reinforced concrete, formwork, reinforcement, rendering and screeding, floor and wall finishing, accessories, and provision for plumbing and electrical installation. The total cost for all items is estimated to be ₦3,363,670.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 12

BILL OF QUANTITIES FOR PROPOSED SWIMMING POOL

S/NO ITEM DESCRIPTION QTY UNIT RATE AMOUNT

A EXCAVATION AND FILLING


Bulk Excavation, commencing 150mm below n.g.l ,average depth exceeding
1 108 m3 ₦500.00 ₦54,000.00
1500mm
2 Disposal of excavated materials off site, in spoil heap away from site 90 m3 ₦300.00 ₦27,000.00
3 Back filling to excavations, thickness exceeding 250mm, with imported laterite. 30 m3 ₦187.50 ₦5,625.00
4 Level and compact bottom of excavation 54 m2 ₦70.00 ₦3,780.00

B MEMBRANE
1 Damp proof membrane exceeding 500mm wide, ... thick 1 roll ₦22,000.00 ₦22,000.00
2 1.5mm thick hydrolyphic ''SIKA'' water bars 30 m ₦3,600.00 ₦108,000.00
Labour sum ₦5,000.00

C IN-SITU CONCRETE WORKS


1 Blinding beds (1:3:6), thickness not exceeding 50mm
2 Cement 9 bag ₦3,400.00 ₦30,600.00
3 Sand 0.1 trip ₦80,000.00 ₦8,000.00
4 Aggregate 0.2 trip ₦140,000.00 ₦28,000.00
5 Labour 2 m3 ₦3,000.00 ₦6,000.00

D REINFORCED CONCRETE
Base, Wall and Pool Deck
1 Cement 130 bag ₦3,400.00 ₦442,000.00
2 Sand 1 trip ₦80,000.00 ₦80,000.00
3 Aggregate 1.5 trip ₦140,000.00 ₦210,000.00
4 Labour 11 m3 ₦3,000.00 ₦33,000.00

E FORMWORK FOR INSITU CONCRETE


Plain vertical sawn formwork in bases and wall
1 1 x 12m Plank 100 pcs ₦1,400.00 ₦140,000.00
2 2 x 3 Wood 140 bag ₦350.00 ₦49,000.00
3 2 inch Nail 0.5 bag ₦12,500.00 ₦6,250.00
4 3 inch Nail 1 bag ₦12,500.00 ₦12,500.00
5 Concrete Nail 5 pkt ₦450.00 ₦2,250.00
6 Labour 105 m2 ₦495.00 ₦51,975.00

F REINFORCEMENT FOR CONCRETE


Mesh
Steel fabric reinforcement to B.S.4483; 2.22kg Weight per
1 1.5 roll ₦12,000.00 ₦18,000.00
m2; 150mm side and end minimum laps.
2 Labour 36 m2 ₦40.00 ₦1,440.00
High tensile bars to BS 4449
In Bases and Wall
4 10mm diameter 0.2 ton ₦380,000.00 ₦76,000.00
5 12mm diameter 1.4 ton ₦380,000.00 ₦532,000.00
7 Binding wire 1 roll ₦12,000.00 ₦12,000.00
8 Labour 1.6 ton ₦28,000.00 ₦44,800.00
Sub- total ₦2,009,220.00
S/NO DESCRIPTION QTY UNIT RATE AMOUNT
A RENDERING AND SCREEDING
1 Cement 20 bag ₦3,400.00 ₦68,000.00
2 Plaster Sand 0.1 trip ₦80,000.00 ₦8,000.00
3 Stone dust 5 ton ₦3,500.00 ₦17,500.00
4 Labour 53 m2 ₦350.00 ₦18,550.00

B FLOOR AND WALL FINISHING


1 33 x 33 mosaic tiles laid on screeded surface 45 m2 ₦6,000.00 ₦270,000.00
2 Swimming pool coping red tiles 8 m2 ₦5,800.00 ₦46,400.00

C ACCESSORIES
1 Aqua Rock Swimming Pool 2 Step Ladder 2 nr ₦48,000.00 ₦96,000.00
2 1.5hp swimming pool pump machine 1 nr ₦85,000.00 ₦85,000.00
3 15 L Astra pool skimmer 1 nr ₦65,000.00 ₦65,000.00
4 18 liters swimming pool filter 1 nr ₦130,000.00 ₦130,000.00
5 Swimming pool LED light 5 nr ₦30,000.00 ₦150,000.00

D Allow a provisional sum of ..... for Plumbing and Electrical installation sum ₦400,000.00 ₦400,000.00
₦1,354,450.00

TOTAL ₦3,363,670.00
S/NO ITEM DESCRIPTION QTY UNIT RATE AMOUNT
SUBSTRUCTURE

A SETTING OUT
1 Pegs 100 pcs ₦ 80.00 ₦ 8,000.00
2 Profile 20 pcs ₦ 200.00 ₦ 4,000.00
3 3 inch nail 0.3 bag ₦ 12,500.00 ₦ 3,750.00
4 Labour sum ₦ 5,000.00

B Exacavation
1 Trench Excavation 54 m3 ₦ 500.00 ₦ 27,000.00
2 Pit Exacavation 32 m3 ₦ 500.00 ₦ 16,000.00
3 Disposal of excavated materials 86 m3 ₦ 300.00 ₦ 25,800.00
4 Filling with imported laterite (30 tons) 5 trips ₦ 80,000.00 ₦ 400,000.00

C MEMBRANE
1 Damp proof membrane exceeding 500mm wide. (1x50m) 4 roll ₦ 22,000.00 ₦ 88,000.00
Labour 187 m2 ₦ 30.00 ₦ 5,610.00

D IN-SITU CONCRETE WORKS


Foundation concrete and 50mm thick Blinding 1:3:6 mix)
1 Cement 50 bag ₦ 3,400.00 ₦ 170,000.00
2 Sand 0.5 trip ₦ 80,000.00 ₦ 40,000.00
3 Aggregate 1.2 trip ₦ 140,000.00 ₦ 168,000.00
4 Labour 15 m3 ₦ 3,000.00 ₦ 45,000.00

E REINFORCED CONCRETE
Column base, Column, D.P.C(1:2:4)
1 Cement 190 bag ₦ 3,400.00 ₦ 646,000.00
2 Sand 1 trip ₦ 80,000.00 ₦ 80,000.00
3 Aggregate 2.5 trip ₦ 140,000.00 ₦ 350,000.00
4 Labour 38 m3 ₦ 3,000.00 ₦ 114,000.00
5 Concerete mixer hire with operator (3 times usage) 3 sum ₦ 20,000.00 ₦ 60,000.00

E FORMWORK FOR INSITU CONCRETE


Plain vertical sawn formwork in bases and wall
1 1 x 12m Plank (to be reused) 50 pcs ₦ 1,400.00 ₦ 70,000.00
2 2 x 3 Wood 20 bag ₦ 350.00 ₦ 7,000.00
3 2 inch Nail 0 bag ₦ 12,500.00 ₦ 0.00
4 3 inch Nail 0.5 bag ₦ 12,500.00 ₦ 6,250.00
5 Concrete Nail 1 pkt ₦ 450.00 ₦ 450.00
6 Labour (shuttering and removal) 55 m2 ₦ 495.00 ₦ 27,225.00

F REINFORCEMENT FOR CONCRETE


Mesh
1 B.R.C wire mesh (2.1 x 15m) 6 roll ₦ 12,500.00 ₦ 75,000.00
2 Labour 187 m2 ₦ 40.00 ₦ 7,480.00

High tensile bars to BS 4449


3 In Bases and Wall
4 10mm diameter 0.15 ton ₦ 380,000.00 ₦ 57,000.00
5 12mm diameter 0.5 ton ₦ 380,000.00 ₦ 190,000.00
6 16mm diameter 0.25 ton ₦ 380,000.00 ₦ 95,000.00
7 Binding wire 1 roll ₦ 12,000.00 ₦ 12,000.00
8 Labour 0.9 ton ₦ 30,000.00 ₦ 27,000.00

G BLOCK WORK
9'' block 1100 nr ₦ 240.00 ₦ 264,000.00
Cement 22 bag ₦ 3,400.00 ₦ 74,800.00
Sand 0.4 trip ₦ 80,000.00 ₦ 32,000.00
Labour 1100 per block ₦ 50.00 ₦ 55,000.00

H PLUMBING
4'' PVC Pipe 6 length ₦ 4,500.00 ₦ 27,000.00
4" X 45 Bend 9 pcs ₦ 800.00 ₦ 7,200.00
2'' PVC Pipe 3 length ₦ 1,800.00 ₦ 5,400.00
2" x 45 Bend 7 pcs ₦ 250.00 ₦ 1,750.00
2" x 90 Tee 3 pcs ₦ 450.00 ₦ 1,350.00
ABRO GUM (medium) 2 pcs ₦ 3,500.00 ₦ 7,000.00
Labour sum ₦ 10,000.00

Sub- total ₦ 3,316,065.00


S/NO ITEM DESCRIPTION QTY UNIT RATE AMOUNT
SUPERSTRUCTURE

FRAME WORK ( COLUMN, BEAM AND SLAB)

A REINFORCED CONCRETE
1 Cement 252 bag ₦ 3,400.00 ₦ 856,800.00
2 Sand 1.3 trip ₦ 80,000.00 ₦ 104,000.00
3 Aggregate 2.7 trip ₦ 140,000.00 ₦ 378,000.00
4 Labour 44 m3 ₦ 3,000.00 ₦ 132,000.00
5 Concrete mixer hire (twice) 2 sum ₦ 20,000.00 ₦ 40,000.00

E FORMWORK FOR INSITU CONCRETE


Plain vertical sawn formwork to column, beams and slab
1 1 x 12m Plank 320 pcs ₦ 1,400.00 ₦ 448,000.00
2 2 x 3 Wood 180 bag ₦ 350.00 ₦ 63,000.00
3 2 inch Nail 1 bag ₦ 12,500.00 ₦ 12,500.00
4 3 inch Nail 2 bag ₦ 12,500.00 ₦ 25,000.00
5 Concrete Nail 5 pkt ₦ 450.00 ₦ 2,250.00
6 Labour ( shuttering and removal) 387 m2 ₦ 600.00 ₦ 232,200.00

F REINFORCEMENT FOR CONCRETE


High tensile bars to BS 4449 in Column, Beams and Slab.
1 10mm diameter 1.5 ton ₦ 380,000.00 ₦ 570,000.00
2 12mm diameter 1 ton ₦ 380,000.00 ₦ 380,000.00
3 16mm diameter 2.5 ton ₦ 380,000.00 ₦ 950,000.00
4 Binding wire 3.5 roll ₦ 12,000.00 ₦ 42,000.00
5 Labour 5 ton ₦ 30,000.00 ₦ 150,000.00

Sub- total ₦ 4,385,750.00


S/NO ITEM DESCRIPTION QTY UNIT RATE AMOUNT
INTERNAL AND EXTERNAL WORKS

A REINFORCED CONCRETE (Lintel and Beams)


1 Cement 30 bag ₦ 3,400.00 ₦ 102,000.00
2 Sand 0.2 trip ₦ 80,000.00 ₦ 16,000.00
3 Aggregate 0.5 trip ₦ 140,000.00 ₦ 70,000.00
4 Labour 5 m3 ₦ 3,000.00 ₦ 15,000.00

B FORMWORK FOR INSITU CONCRETE


Plain vertical sawn formwork to lintel and beam
1 1 x 12m Plank 55 pcs ₦ 1,400.00 ₦ 77,000.00
2 3 inch Nail 0.5 bag ₦ 12,500.00 ₦ 6,250.00
3 Concrete Nail 3 pkt ₦ 450.00 ₦ 1,350.00
4 Labour (shuttering and removal) 60 m2 ₦ 495.00 ₦ 29,700.00

C REINFORCEMENT FOR CONCRETE


High tensile bars to BS 4449 in lintel and beam
1 10mm diameter 0.2 ton ₦ 380,000.00 ₦ 76,000.00
2 12mm diameter 0.35 ton ₦ 380,000.00 ₦ 133,000.00
3 Binding wire 0.5 roll ₦ 12,000.00 ₦ 6,000.00
4 Labour 0.55 ton ₦ 30,000.00 ₦ 16,500.00

D BLOCK WORK
1 9'' block 6600 nr ₦ 240.00 ₦ 1,584,000.00
2 6'' block 20 nr ₦ 230.00 ₦ 4,600.00
3 Cement 135 bag ₦ 3,400.00 ₦ 459,000.00
4 Sand 2.5 trip ₦ 80,000.00 ₦ 200,000.00
5 Labour 6600 nr ₦ 50.00 ₦ 330,000.00

Sub- total ₦ 3,126,400.00


S/NO ITEM DESCRIPTION QTY UNIT RATE AMOUNT
SUPERSTRUCTURE CONT'D
STAIRS CASE

A REINFORCED CONCRETE (STEP, WAIST, LANDING)


1 Cement 8 bag ₦ 3,400.00 ₦ 27,200.00
2 Sand 0.1 trip ₦ 80,000.00 ₦ 8,000.00
3 Aggregate 0.15 trip ₦ 140,000.00 ₦ 21,000.00
4 Labour 1.8 m3 ₦ 3,000.00 ₦ 5,400.00

B FORMWORK FOR INSITU CONCRETE


Plain vertical sawn formwork to Stair case
1 1 x 12m Plank 110 pcs ₦ 1,400.00 ₦ 154,000.00
2 2 x 3 Wood 30 bag ₦ 350.00 ₦ 10,500.00
3 2 inch Nail 0.5 bag ₦ 12,500.00 ₦ 6,250.00
4 3 inch Nail 1 bag ₦ 12,500.00 ₦ 12,500.00
5 Concrete Nail 5 pkt ₦ 450.00 ₦ 2,250.00
6 Labour 112 m2 ₦ 495.00 ₦ 55,440.00

C REINFORCEMENT FOR CONCRETE


High tensile bars to BS 4449 in Stairs
1 10mm diameter 0.6 ton ₦ 415,000.00 ₦ 249,000.00
2 12mm diameter 1.2 ton ₦ 415,000.00 ₦ 498,000.00
3 16mm diameter 0.84 ton ₦ 415,000.00 ₦ 348,600.00
4 Binding wire 1 roll ₦ 12,000.00 ₦ 12,000.00
5 Labour 2.64 ton ₦ 30,000.00 ₦ 79,200.00

D HANDRAIL
1 75 mm diameter balustrades hand rails to staircase and void area. 8 m ₦ 24,000.00 ₦ 192,000.00

E FINISHING TO STAIRS
Granite slab installation to Stairs and Entrance
1 Granite marble 15 m2 ₦ 14,000.00 ₦ 210,000.00
2 Cement 2.5 bag ₦ 3,400.00 ₦ 8,500.00
3 Tile gum 2 bag ₦ 2,000.00 ₦ 4,000.00
4 Labour 15 m2 ₦ 1,200.00 ₦ 18,000.00
Plastering to sides and soffit ot stairs
5 Cement 2 bag ₦ 3,400.00 ₦ 6,800.00
6 Plaster sand 0.1 trip ₦ 80,000.00 ₦ 8,000.00
7 Sharp sand 0.02 trip ₦ 80,888.00 ₦ 1,617.76
8 Labour 10 m2 ₦ 350.00 ₦ 3,500.00
Painting to sides and soffit of Stairs
9 Dulux Emulsion Paint 0.25 drum ₦ 8,500.00 ₦ 2,125.00
10 Labour 10 m2 ₦ 250.00 ₦ 2,500.00

Sub- total ₦ 1,946,382.76


S/NO ITEM DESCRIPTION QTY UNIT RATE AMOUNT
ROOF COVERING AND STRUCTURES

A REINFORCED CONCRETE (ROOF BEAM AND GUTTER)


1 Cement 96 bag ₦ 3,400.00 ₦ 326,400.00
2 Sand 0.5 trip ₦ 80,000.00 ₦ 40,000.00
3 Aggregate 1 ton ₦ 140,000.00 ₦ 140,000.00
4 Labour 25 m3 ₦ 3,000.00 ₦ 75,000.00

B FORMWORK FOR INSITU CONCRETE


Plain vertical sawn formwork to roof beam and gutter
1 1 x 12m Plank 250 pcs ₦ 1,400.00 ₦ 350,000.00
2 2 x 3 Wood 30 pcs ₦ 350.00 ₦ 10,500.00
3 2 inch Nail 0.5 bag ₦ 12,500.00 ₦ 6,250.00
4 3 inch Nail 1.5 bag ₦ 12,500.00 ₦ 18,750.00
5 Concrete Nail 5 pkt ₦ 450.00 ₦ 2,250.00
6 Labour 255 m2 ₦ 495.00 ₦ 126,225.00

C REINFORCEMENT FOR CONCRETE


High tensile bars to BS 4449 in roof beam and gutter
1 10mm diameter 0.22 ton ₦ 380,000.00 ₦ 83,600.00
2 12mm diameter 0.8 ton ₦ 380,000.00 ₦ 304,000.00
3 16mm diameter 0.84 ton ₦ 380,000.00 ₦ 319,200.00
4 Binding wire 1.5 roll ₦ 12,000.00 ₦ 18,000.00
5 Labour 1.86 ton ₦ 30,000.00 ₦ 55,800.00

D COVERING
1 Aluminium roof sheet 0.55mm thick 158 m2 ₦ 3,800.00 ₦ 600,400.00

E MEMEBERS
2 x 4 x 12 (Hard Wood) 64 pcs ₦ 800.00 ₦ 51,200.00
2  X 6 x 12 (Hard Wood) 62 pcs ₦ 1,650.00 ₦ 102,300.00
2 x 2 x 12 (Hardwood) 160 pcs ₦ 450.00 ₦ 72,000.00
2 x 3 x 12 (Hard Wood) 70 pcs ₦ 600.00 ₦ 42,000.00
4” CHINESE ROOFING NAIL (carton) 2 cartons ₦ 12,000.00 ₦ 24,000.00
3” CHINESE ROOFING NAIL (carton) 3 cartons ₦ 12,000.00 ₦ 36,000.00

F TREATMENT
Solignum 2 gallon ₦ 3,500.00 ₦ 7,000.00
Condemned Oil 10 litres ₦ 250.00 ₦ 2,500.00

Labour
1 Treatment of woods sum ₦ 8,000.00 ₦ 8,000.00
2 Wood Installation sum ₦ 250,000.00 ₦ 250,000.00
3 Roofing sheet installation 158 m2 ₦ 200.00 ₦ 31,600.00

sub-total ₦ 3,102,975.00
S/NO ITEM DESCRIPTION QTY UNIT RATE AMOUNT
DOORS AND WINDOWS

A WINDOWS ( with buglary and 5mm thick glass)


1 900 x 1800 mm 5 nr ₦ 38,800.00 ₦ 194,000.00
2 1200 x 1800 mm 9 nr ₦ 52,000.00 ₦ 468,000.00
3 1200 x 1200 mm 1 nr ₦ 32,000.00 ₦ 32,000.00
4 600 x 750 mm 7 nr ₦ 10,800.00 ₦ 75,600.00
5 2700 x 1800 mm 1 nr ₦ 116,000.00 ₦ 116,000.00
B CURTAIN WALL
1 3000 X 5700 mm 1 nr ₦ 769,500.00 ₦ 769,500.00
2 1200 x 4800 mm 1 nr ₦ 144,000.00 ₦ 144,000.00
3 1200 x 3600 mm 1 nr ₦ 108,000.00 ₦ 108,000.00

C DOORS nr
1 1200 x 2100 Turkey security door 1 nr ₦ 130,000.00 ₦ 130,000.00
2 900 x 2100 mm panel door 9 nr ₦ 25,000.00 ₦ 225,000.00
3 750 x 2100 mm panel door 6 nr ₦ 21,000.00 ₦ 126,000.00
4 1800 x 2100 mm sliding door 1 nr ₦ 110,000.00 ₦ 110,000.00

sub-total ₦ 2,498,100.00
S/NO ITEM DESCRIPTION QTY UNIT RATE AMOUNT
FINISHES

WALL, FLOOR, CEILING FINISHING

A FLOOR
Floor Screeding
Cement 52 bag ₦ 3,400.00 ₦ 176,800.00
Sand 2 trip ₦ 80,000.00 ₦ 160,000.00
Gum tile fix 12 pcs ₦ 1,500.00 ₦ 18,000.00
Grouting
White cement 4 bag ₦ 7,500.00 ₦ 30,000.00
Tiles
60 x 60 275 m2 ₦ 4,500.00 ₦ 1,237,500.00
40 x 40 28 m2 ₦ 2,400.00 ₦ 67,200.00
Labour 303 m2 ₦ 400.00 ₦ 121,200.00

B WALL
Plastering
Cement 142 bag ₦ 3,400.00 ₦ 482,800.00
Plaster sand 2 trip ₦ 75,000.00 ₦ 150,000.00
Sharp sand 1 trip ₦ 80,000.00 ₦ 80,000.00
Labour (gauging + plastering) 1132 m2 ₦ 350.00 ₦ 396,200.00
Tile
60 X 30 wall tiles in bathrooms and kitchen 140 m2 ₦ 3,800.00 ₦ 532,000.00
Genesis tile edge trimmer 7 length ₦ 1,600.00 ₦ 11,200.00
Backing
Cement 24.00 bag ₦ 3,400.00 ₦ 81,600.00
Sand 0.40 trip ₦ 80,000.00 ₦ 32,000.00
Gum tile fix 5.00 pcs ₦ 1,500.00 ₦ 7,500.00
Grouting
White cement 1.5 bag ₦ 7,500.00 ₦ 11,250.00
Labour 140 m2 ₦ 400.00 ₦ 56,000.00

C PAINTING
1 Wall satin (internal) 9 drum ₦ 32,000.00 ₦ 288,000.00
2 Colored Emulsion Paint ( internal + external) 28 drum ₦ 8,500.00 ₦ 238,000.00
2 Labour 1132 m2 ₦ 250.00 ₦ 283,000.00

D CEILING FINISHES
Pop ceiling finishes 300 m2
1 Cement (ABS) 150 bag ₦ 4,200.00 ₦ 630,000.00
2 Fillers (100kg) 1.5 bndle ₦ 115,000.00 ₦ 172,500.00
3 Binding wire 1.5 rolls ₦ 8,000.00 ₦ 12,000.00
4 Ground nut oil 7.5 ltrs ₦ 800.00 ₦ 6,000.00
5 Premier Soap 8 pcs ₦ 150.00 ₦ 1,200.00
6 1.5" Conc nail 10 pkt ₦ 450.00 ₦ 4,500.00
7 2" Conc nail 8.0 pkt ₦ 450.00 ₦ 3,600.00
8 3" nail 0.5 pkt ₦ 8,000.00 ₦ 4,000.00
9 Screeding Paint (Acurate) 15 drum ₦ 4,500.00 ₦ 67,500.00
10 Labour 300 m2 ₦ 1,000.00 ₦ 300,000.00

sub-total ₦ 5,661,550.00

S/NO ITEM DESCRIPTION QTY UNIT RATE AMOUNT


MECHANICAL, PLUMBING AND ELECTRICAL

PLUMBING
A Fittings
1 Water Closet complete with Wash Hand Basin 3 pcs ₦ 70,000.00 ₦ 210,000.00
2 W.C Aquaflex 3 pcs ₦ 34,000.00 ₦ 102,000.00
3 Pressing tap 6 pcs ₦ 2,500.00 ₦ 15,000.00
4 Basin mixer tap 6 pcs ₦ 4,500.00 ₦ 27,000.00
5 Water heater 5 pcs ₦ 35,000.00 ₦ 175,000.00
6 Floor drain 6 pcs ₦ 800.00 ₦ 4,800.00
7 Shower Tap 5 pcs ₦ 35,000.00 ₦ 175,000.00
8 Kitchen Tap 1 pcs ₦ 8,500.00 ₦ 8,500.00
9 Kitchen Sink complete with traps 1 pcs ₦ 25,000.00 ₦ 25,000.00
10 Angle valve 24 pcs ₦ 3,000.00 ₦ 72,000.00
11 Non return valve 12 pcs ₦ 1,200.00 ₦ 14,400.00
12 Control valve 6 pcs ₦ 3,500.00 ₦ 21,000.00
13 Flexible waste 7 pcs ₦ 700.00 ₦ 4,900.00
14 Flexible pipe 18 pcs ₦ 1,000.00 ₦ 18,000.00
15 Thread tape 8 pcs ₦ 1,500.00 ₦ 12,000.00
16 Silcon gum 6 pcs ₦ 1,600.00 ₦ 9,600.00
17 Abro gum 1 pcs ₦ 5,500.00 ₦ 5,500.00

B Waste pipe (6 bar)


1 4'' PVC PIPES 6 length ₦ 4,500.00 ₦ 27,000.00
2 4" X 45 BEND 3 pcs ₦ 800.00 ₦ 2,400.00
3 4'' Tee 3 pcs ₦ 800.00 ₦ 2,400.00
4 2'' PVC PIPES 18 length ₦ 1,800.00 ₦ 32,400.00
5 2" x 45 BEND 9 pcs ₦ 250.00 ₦ 2,250.00
6 2" x Tee 7 pcs ₦ 250.00 ₦ 1,750.00
7 Abro gum (big) 2 pcs ₦ 5,500.00 ₦ 11,000.00

C Allow a provisional sum of … for water reticulation, chamber, soak away and sum ₦ 750,000.00
other plumbing works.

D ELECTRICAL
Allow a provisinal sum of … for electrical piping, fittings and fittings sum ₦ 1,800,000.00
installation

sub-total ₦ 3,528,900.00
SUMMARY

A SUBSTRUCTURE ₦ 3,316,065.00

B FRAMEWORK ₦ 4,385,750.00

C INTERNAL AND EXTERNAL WALL ₦ 3,126,400.00

D STAIR CASE ₦ 1,946,382.76

E ROOF COVERING AND STRUCTURES ₦ 3,102,975.00

F DOORS AND WINDOWS ₦ 2,498,100.00

G CEILING, WALL AND FLOOR FINISHES ₦ 5,661,550.00

H MECHANICAL, PLUMBING AND ELECTRICAL ₦ 3,316,065.00

J Allow a provisional sum of … as contigency ₦ 500,000.00

TOTAL ₦ 27,853,287.76

K SUPERVISION FEE 10% ₦ 2,785,328.78

TOTAL PROJECT COST ₦ 30,638,616.54