SPE-122006-MS-P Heavy Oil Using ESP
SPE-122006-MS-P Heavy Oil Using ESP
Increased Rates, Reserves, and Revenues from Heavy Oil Reservoir Using
ESP Technology: A Suriname Case Study
E. Anthony, SPE, G. Grauwde, Staatsolie Maatschappij Suriname N. V., Michael Domangue, Weatherford Artificial
Lift Systems
This paper was prepared for presentation at the 2009 SPE EUROPEC/EAGE Annual Conference and Exhibition held in Amsterdam, The Netherlands, 8–11 June 2009.
This paper was selected for presentation by an SPE program committee following review of information contained in an abstract submitted by the author(s). Contents of the paper have not
been reviewed by the Society of Petroleum Engineers and are subject to correction by the author(s). The material does not necessarily reflect any position of the Society of
Petroleum Engineers, its officers, or members. Electronic reproduction, distribution, or storage of any part of this paper without the written consent of the Society of Petroleum Engineers
is prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300 words; illustrations may not be copied. The abstract must contain conspicuous
acknowledgment of SPE copyright.
Abstract Introduction
Wells producing heavy oil (16° API), completed in The first oil discovery in Suriname was in 1964. After the
shallow, high permeability, low-dipping, and very establishment of Staatsolie Maatschappij Suriname N.V.
unconsolidated reservoirs experienced very early water (State Oil Company of Suriname) in 1980, the first test
breakthrough, short-circuiting significant reserve potential. well was drilled 19811 which proved the producibility of
Wells were completed as vertical open-hole gravel packs the field. Full scale development started in November
and produced ‘water-free’ at rates 150 – 300 bopd for a 1982 in the Tambaredjo field, when the production was
few months, then plummeted to 25 – 50 bopd when water 250 BOPD from 5 wells. As field development moved
broke through. Progressing Cavity Pumps were the further north, the terrain gradually changes from partial
primary Artificial Lift method used in 5.5” casing swamp to full-scale swamp. Location preparation, inter-
completions. In an attempt to restore some of the lost oil connecting roads, and facility foundations all required land
production after water breakthrough, efforts to reduce the fill, driving up infrastructural costs sigfnificantly. In 2003,
flowing BHP were made by using high-volume PC pumps. appraisal wells were drilled in an adjacent field, Calcutta.
Fluid withdrawal rates were increased from ±350 bpd to In 2006, full-scale development of this field started as a
±700 bpd with no significant change in fluid level ‘Wet Operation’, where wells were drilled and completed
(FBHP), watercut, or oil production. using pontoon-based drilling equipment. Well locations
The Electrical Submersible Pump (ESP) was then used to are connected by waterways rather than roadways. All
reduce the FBHP sufficiently to stimulate increased oil pipelines, electric poles, metering and collection facilities,
production to the wellbore. Fluid withdrawal rates were however, are constructed on land-fill dykes.
taken to ±2200 bpd which achieved approximately 100 As of December 2008, the average oil production from
psi(25%) reduction in FBHP. both fields was 16,000 BOPD from 1188 production wells
Sustained oil production increases between 100% and (Fig. 1)
400% were realized. Watercuts increased by no more than
3%. Dynamic fluid levels in surrounding wells showed a Production Profile - Staatsolie Maatschappij Suriname N.V.
12000 100
date indicating no deterioration of the gravel pack at these 8000 Developm ent
60
6000
elevated extraction rates. At prevailing oil prices, project 40
4000
investments were recovered within 4 months. 20
2000
0 0
Under the conditions of low GOR, low dipping, high
82
84
86
88
90
92
94
96
98
00
02
04
06
08
19
19
19
19
19
19
19
19
19
20
20
20
20
20
increased fluid extraction rates can result in significant Fig.1 – Production history of Staatsolie Oilfield
increase in oil production rates and producible reserves,
even though wells may have experienced early water A third field has been appraised and is scheduled for full
breakthroughs. scale development in 2010. Several other field
development strategies are being investigated to further
reduce infrastructural and operational costs.
2 SPE 122006
and/or high in-situ oil viscosity. Wells with high recovery 25 100
07
08
08
09
7
07
08
7
8
7
8
l-0
l-0
-0
-0
-0
-0
v-
v-
n-
n-
p-
p-
ar
ar
ay
ay
Ju
Ju
No
No
Ja
Ja
Se
Se
M
M
M
M
Due to the pressure support from the edgewater drive in Time
the region being considered, recoveries greater than 20% Fig.5(a) – ESP Prodution response for well 9D05
within 4 – 5 yrs of production was not uncommon. This
actually confirms greater potential for higher recovery 9D15 realized an initial average raet of 109 bopd (185%)
with additional drawdown than wells with lower from pre-installation average of 38 bopd. After 1 year,
recoveries in the same period. These lower recoveries with production rates are 68 bopd (80% above the pre-
similar STOOIP’s indicate wells with formation damage, installation rate). However, it shold be noted that the
and/or too close to the OWC. FBHP also increased even though the gross fluid rate did
From all the wells fitted with the large volume pumps not change. See Fig X (b). No sand production detected in
(approximately 20 wells), 5 wells met all the criteria listed any samples taken.
above. Since budget allocation limited this pilot to 3 Bopd
ESP - 9D15 - Oil Production
wells, wells 9D05, 9D15 and 10A12 were selected. Fbhp
200 600
175
500
ESP Design Considerations
Production Rate (bopd)
08
07
08
09
7
8
7
8
07
08
7
8
-0
-0
l-0
l-0
-0
-0
v-
v-
n-
n-
n-
p-
p-
ar
ar
ay
ay
Ju
Ju
No
No
Ja
Ja
Se
Se
M
M
M
Time
device was necessary since average GOR per well was
approximately 50 scf/bbl. Fig.5(b) – ESP Prodution response for well 9D15
A Variable Speed Controller was required to minimize the
start-up surge on the already heavily loaded electrical 10A12 realized an initial average rate of 155 bopd (450%)
distribution system in the field. Minimum and maximum from pre-installation average of 28 bopd. After 1 year,
flow rates anticipated were 1500 bpd and 2500 bpd average production rate is 90 bopd (320% of the pre-
respectively. Since no well in the field had ever been installation rate). See Fig X (c). No sand production
produced at rates > 700 bpd, it was not known if the open- detected in any samples taken.
hole gravel pack completion would withstand the elevated E S P - 1 0 A 1 2 - O il P ro d u c tio n
B opd
F bh p
drag forces under the higher flow rates. Hence the reason 30 0 60 0
20 0 40 0
optimum cooling. 50 10 0
0 0
Performance Results Ja
n-
07
M
ar
-0
7
ay
-0
7
Ju
l-0
7
ep
-0
7
N
ov
-0
7
Ja
n-
08
M
ar
-0
8
ay
-0
8
Ju
l- 0
8
ep
-0
8
N
ov
-0
8
M S M S
Installation – Notwithstanding that this was the first T im e
Reserves Acknowledgements
From a combined baseline production of 87 bopd, the The authors would like to extend their gratitude to the
average combined incremental oil gain within the first 3 Staatsolie Board of Executive Directors and their
months combined was 240 bopd. After 12 months management team for their support and permission to
production, the incremental oil gain declined to 116 bopd. publish this paper. Contributions from Calcutta Asset
Using decline curve analysis and extrapolating to normal Team, Field Evaluation & Development Team, and the
abandonment, the incremental reserves for each well is ESP project team are also greatly appreciated.
9D15 (14,470 bbl), 9D05 (41,330 bbl), and 10A12 (67,000
bbl). Combined incremental reserves are 122,800 bbl, Nomenclature
approximately equivalent to 15% of original recoverable OD - Outside Diameter
reserves determined from decline curve analysis. ID - Internal Diameter
ESP - Electrical Submersible Pump
Economics OWC - Oil Water Contact
The 3 ESP units were identical 35 HP 48 stage pumps, BPD - Barrels per day
each fitted with Variable Speed Controllers on surface. WOR - Water Oil Ratio
The cumulative cost for all 3 ESP systems was THP - Tubing Head Pressure
approximately $350,000 inclusive of equipment and GOR - Gas Oil Ratio
services. Accounting for water treatment costs, FBHP - Flowing Bottom Hole Pressure
incremental operating expenses from additional power STOIIP - Stock Tank Oil Initially In Place
requirements, and oil decline rates of 50%, 40%, 30%, and PCP - Progressing Cavity Pump
20% in subsequent years post-installation, the project NPV NPV - Net Present Value
was $1.68 MM with an IRR of 310%. Oil price used was IRR - Internal Rate of Return
a very conservative $35/bbl. For a low tier operation,
these are excellent economic returns.
References
Conclusions and Observations 1. H. Kartoredjo, K. Moe Soe Let, G. Nadeson, SPE, and
Despite the average 350% increase in gross fluid B. Nandlal, Staatsolie Maatschappij N. V., “Heavy
production, watercut increases were marginal (no Oil Field Development and Reservoir Management
more than 3%), which resulted in the attractive oil Challenges in Producing Onshore Shallow Reservoirs
production increases realized. To date a combined in Suriname”: SPE 104068, First International Oil
incremental of 40,500 bbl has been produced from all Conference and Exhibition, Cancun, Mexico, 31
three wells August–2 September 2006.
When watercuts are ≥ 95%, the WOR is a more 2. Brouwer, G. K., “ Reservoir Simulation Tambaredjo
effective parameter to use in evaluating the inflow Field (TA-45 & TA-58 area), TNO report # B-380,
performance and potential of a well, rather than the Internal Report (November 2004)
watercut. 3. Mc Clung W.J., SPE, Johnsosn J.A., SPE, Electric
Except for well 10A12, initial decreases in FBHP Submersible Pump Application and Operation in
after ESP start up was short-lived, apparently due to Small Openhole Completions: SPE-9213, 1980
the strong pressure support at the water source. Annual Technical Conference & Exhibition, Dallas,
The openhole Gravel Pack completions withstood the Sept 21 - 24
higher drag forces at the higher production rates much
better than suspected.
The PI’s observed at the increased drawdown,
indicate significant potential for further oil gains.
Increase in water separation, treatment and disposal
costs must be considered if significantly more wells
are converted to ESP and produce at higher rates.
Not one mechanical or electrical problem has
occurred with any of the ESP installations since start-
up date.
9D10, the well directly between 9D05 and 9D15,
showed negligible response to the increased
drawdown in the adjacent wells except for a marginal
reduction in FBHP.
Recoverable reserves amount to approximately 15%
more than if nothing had been done.
Project economics show a payback period of 2 months
with a favorable ROR of 310% an NPV of $1.68MM
USD
6 SPE 122006
Appendix 1
T1 OWC
SPE 122006 7
Appendix 2