WSP Final Report PS109832 ADV REP 003 RevD2
WSP Final Report PS109832 ADV REP 003 RevD2
INDEPENDENT REVIEW
OF ELECTRICITY
NETWORKS
FINAL REPORT
PUBLIC
Independent review of electricity networks
Final report
Aurora Energy
WSP
Level 15, 28 Freshwater Place
Southbank VIC 3006
Peter Walshe
Reviewed by:
Malcolm Busby
This document may contain confidential and legally privileged information, neither of which are intended to be waived,
and must be used only for its intended purpose. Any unauthorised use or reliance is done so at that parties own risk. If
you have received this document in error or by any means other than as authorised addressee, please notify us
immediately and we will arrange for its return to us.
PS109832-ADV-REP-003 RevD.docx Public
ABBREVIATIONS ........................................................................... VI
TABLE OF
CONTENTS EXECUTIVE SUMMARY .............................................................. VIII
PROJECT CONTEXT ........................................................................... VIII
REVIEW APPROACH ........................................................................... VIII
SUITABILITY OF ASSET DATA ............................................................ IX
KEY FINDINGS ....................................................................................... IX
1 PROJECT CONTEXT...........................................................1
1.1 OBJECTIVE ................................................................................ 1
1.2 PROJECT SCOPE ...................................................................... 1
1.3 EXCLUSIONS FROM SCOPE .................................................... 2
1.4 APPROACH AND METHODOLOGY ......................................... 2
1.5 STRUCTURE OF THE REPORT ................................................ 3
9 DISTRIBUTION SWITCHGEAR........................................74
9.1 ASSET DATA ............................................................................ 74
9.2 DESCRIPTION OF THE ASSET CLASS ................................. 75
9.3 DATA VALIDATION .................................................................. 78
9.4 PERFORMANCE AND CONDITION ........................................ 78
9.5 APPROACH TO RISK ASSESSMENT .................................... 84
9.6 RISK ASSESSMENT ................................................................ 84
9.7 KEY FINDINGS ......................................................................... 85
13 UNDERGROUND CABLES –
SUB TRANSMISSION..................................................... 118
13.1 ASSET DATA .......................................................................... 118
13.2 DESCRIPTION OF THE ASSET CLASS ............................... 119
13.3 DATA VALIDATION ................................................................ 123
13.4 PERFORMANCE AND CONDITION ...................................... 123
13.5 APPROACH TO RISK ASSESSMENT .................................. 125
13.6 RISK ASSESSMENT .............................................................. 126
13.7 KEY FINDINGS ....................................................................... 127
LIST OF APPENDICES
APPENDIX A ASSET SAMPLE SELECTION
APPENDIX B SUBSTATION INSPECTIONS
APPENDIX C RESILIENCE MAPS
APPENDIX D QUANTITATIVE MODELLING APPROACH DETAILS
APPENDIX E TRANSFORMER DATA TABLES
APPENDIX F PRIORITISED LIST OF RISKS
ABBREVIATIONS
ABS Air Brake Switch
AL Aluminium
CB Circuit Breaker
CU Copper
HV High voltage
LV Low voltage
OH Overhead
UG Underground
REVIEW APPROACH
To meet the terms of reference for the review, WSP developed an approach based on assessing the Aurora network from
several perspectives:
— Resilience: the ability of the network to withstand or recover from high impact, but very low frequency, events such
as earthquakes
— Security: whether the electricity network topology provides appropriate capabilities, such as capacity, redundancy
and switching capability, to maintain normal supply to consumers
— Performance: an indication of which assets and areas of the network pose the greatest risk to public safety,
reliability of supply and the environment based on historical rates and durations of asset outages
— Network risk: the combination of the probability that assets may fail and the consequence of the impact to public
safety, reliability of supply or the environment.
Examining security and performance allowed us to focus our review of network risk on key matters. Each of these
perspectives is discussed in detail below. The key outcome of the review is the prioritised list of network risk that Aurora
needs to consider in their future network management plans and investments.
The project was managed in two stages. The first stage of this project involved an assessment/gap analysis of the extent,
reliability and suitability of existing asset data (i.e. age, condition, defect, failure data) that could be used to undertake a
risk assessment of the network. Based on the data gaps identified, the second stage then involved scheduling of additional
testing and inspection programs in order to close the data / knowledge gaps and enable a risk assessment to be
undertaken.
The key tasks undertaken across the two stages were:
1 An investigation into the asset data available
2 Targeted and/or random testing of the asset fleets to validate existing data and to generate new data where gaps were
identified
3 Desktop investigation/analysis of all compiled asset data, including both existing data sets and new data gathered
4 Creation and population of asset risk profiles for each asset class.
It should be noted that this report is aimed at providing the current state of the Aurora network. It does not include
consideration on the interventions and future strategies planned by Aurora. In addition, any matters relating to Aurora’s
performance against quality standards are excluded from the review scope. The review does not include benchmarking or
commenting on improvement actions.
KEY FINDINGS
WSP’s review investigated Aurora Energy’s electricity network to assess the risks as they relate to network resilience,
network security, network performance, and each asset class.
NETWORK RESILIENCE
Network resilience relates to how well the network is designed, from the perspective of the supply chain, to ensure
continued supply following very high impact but very low frequency events, natural disasters in particular. Our
investigation identified that Aurora’s network is subject to several very high impact events, most notably earthquakes and
the resultant liquefaction of the ground.
WSP found that most key assets have been installed clear of earthquake fault lines, flood zones, landslide risk zones and
tsunamis risk areas. However, it is not possible to avoid these altogether as customers occupy these areas and require
electricity.
NETWORK SECURITY
Network security relates to how well the topology and design of Aurora’s network can maintain supply to consumers.
There are two key aspects to security:
— The ability of Aurora to isolate a faulted part of the network and resupply customers by operating switches to
reconfigure the network. Sufficient interconnection will minimise the number of customers experiencing long outage
times and, hence, improve performance.
— The ability to take assets out of service in order to undertake maintenance, without creating a large outage area
affecting more customers than necessary. Inability to do this means that maintenance of critical assets may be
deferred and result in assets not being sufficiently maintained, leading to shortened serviceable life or in-service
failure.
WSP found that:
— Zone substations are generally supplied radially from the Grid Exit Points, but by double circuits, so there is an
adequate level of redundancy.
— Urban feeders generally have good levels of interconnection with adjacent feeders to be able to transfer load,
however, some parts are radial with no interconnection. These arrangements do not appear different to most other
electricity businesses.
— Long rural feeders normally have limited ability to enable resupply via switching, and this is reflected in the security
and performance standards set for those feeders. We found that the topology of Aurora’s network was appropriate
for its geographical location and distribution of customers. To mitigate the risk of a prolonged outage should a single
transformer zone substation fail, Aurora has a mobile transformer that can be deployed to restore supply quickly.
NETWORK PERFORMANCE
The long-term network performance was analysed to identify any assets that are displaying an increasing trend in the
number of outages. Our assessment was not against performance standards but to identify where risk to the network was
materialising.
We found that overhead conductors, poles and crossarm assets were causing more than 50% of the network outages that
were attributed to asset deterioration. There was an upward failure trend evident, although it has ameliorated in the most
recent year, likely as a result of the accelerated pole program.
The analysis identified the following critical assets:
— Poles: an accelerated pole program has slowed a declining performance trend that started in 2013. The current state
of poles still appears to be in poor condition, indicating there is an elevated level of risk with this fleet
— Pole top structures: highly related to pole performance with respect to reliability
— Protection systems: our analysis of outages demonstrated instances when protection systems did not operate and,
therefore, did not mitigate the public safety risk as intended.
Safety performance of the network was generally found to be appropriate, except for risks associated with protection
systems. Data obtained from the safety registers identified 35 incidents in the period 2015 – 2018 where a conductor fell
to the ground and remained live. We identified that:
— some were on the LV network, with protection by a fuse that did not react to the fault
— some were due to a high impedance HV fault, where a back feed from the energised network circumvents the proper
operation of the protection relays
Our detailed review of the protection systems supports that there is an issue with appropriate functioning of the older
fleet of electromechanical protection relays.
NETWORK RISK
Overall, most assets pose a small risk to public safety, reliability or the environment. The risks posed by these assets are
no greater than WSP has observed in other networks in New Zealand and internationally.
WSP found some exceptions:
— Protection system assets: these assets are used to detect a failure that results in a flow of electrical current that is
larger than normal or a flow to ground (earth faults). Many of these assets are beyond their nominal life, employ
obsolete technology and maintenance is incomplete. Five types of electromechanical relays are now an obsolete
technology and are consistently losing calibration between maintenance cycles. These relays are used for earth fault
and over-current detection. The failure of these relays to operate as intended has resulted in live conductors on the
ground not being detected and de-energised. Most observed instances, where earth faults were not isolated, were
found to involve the identified relay types or older electromechanical relays more generally. This supports they are at
the end of their serviceable lives. Protection system assets pose a significant safety risk and should be prioritised.
— Zone substation circuit breakers: these assets are used to switch the network and are opened by protection systems
to isolate faults on the network. The inspection, testing and maintenance of these assets is incomplete. The
technology and specific models installed also pose an increased risk. Some oil insulated zone substation circuit
breakers were found to present an elevated risk to the network with respect to network reliability and the safety of
field crews due to their potential failure mode through arc fault and fire. Many of the specific types of circuit breaker
in-service on the Aurora network have been identified in the electricity industry as having an elevated risk of failure
— Zone substation transformers: these assets are located at bulk supply points (zone substations) and used to
transform voltage from the high voltage used on the sub transmission network to the medium voltages used on the
distribution network. The transformers at two zone substations are in poor condition, although we note that one is
currently in the process of being decommissioned. Additionally, transformer tap changers are showing signs of
deterioration and some are behind their maintenance schedule, increasing risk of an outage on the associated
transformers.
— Support structures: these assets consist of the poles, crossarms and insulators that are used to support conductors.
The pole inspection program has recently been improved but has not identified all poles that are in poor condition as
it has not yet covered the whole network. Crossarms are not inspected adequately and many are in poor condition.
Some are categorised as high risk due to their location relative to population and probability of failure. Note that
while our analysis focuses on a whole of fleet assessment and will identify expected quantities, individual assets
requiring remediation will be identified through Aurora’s normal inspection and testing program.
Overall, we found a high number of risks in the “Red” category, indicating network risk has not been reduced to as low
as reasonably practical.
A prioritised list of risks has been developed to provide guidance on where Aurora should focus their attention in
maintaining the safety and reliability of the network.
1.1 OBJECTIVE
The objective of the project is to undertake an independent risk assessment of the Dunedin and Central Otago electricity
distribution networks owned and operated by Aurora Energy. The risk assessment is to be undertaken with a consumer
focus, with explicit regard given to:
— public safety
— reliability
— resilience
— environmental risk
The output of the project is to establish an accurate and reliable risk profile for the current state of the Aurora networks,
within the bounds of accuracy of the sampling method, and with a particular focus on the identified critical assets. The
resulting prioritised risk to consumers will then be determined from this assessment.
Based on the agreed approach which includes the use of asset inspection by sampling a portion of the population and
extrapolation across the remainder of the fleet, it is probable that specific assets in poor condition may not be identified.
The intent of this assessment is to understand the situation of the entire fleet of assets in an efficient manner to enable
Aurora to most efficiently prioritise their maintenance and replacement activities where needed. The purpose is not to
necessarily identify each individual asset – that is the role of the recurrent inspection and testing tasks of the field crews
in business as usual operations.
— assessment of Aurora’s understanding of the performance and health of its assets (in the absence of hard evidence
what assumptions / judgment is being applied)
— identification of potential and probable failure modes, and the underlying potential consequences of failure
— assessment of the extent to which the network assets are constructed to appropriate design standards, taking into
account:
— consideration of the extent to which network topology mitigates (or otherwise) the risk of service failure in
significant urban areas of the network, and in rural zones:
— locations where changing land use is driving a need to convert infrastructure historically designed for rural use,
to urban levels of resilience and reliability.
— establishment of an accurate and reliable assessment of the current state of the Aurora networks with a particular
focus on identified critical assets
— having established the state of the network, determine the resulting prioritised risk to consumers.
This risk assessment is undertaken within the context of a consumer focus as described in section 1.1.
— format/availability of data (i.e. paper records or data base), including the usability of data in its current format
— completeness of data in databases, accuracy and consistency of the data (i.e. check for obvious errors, which may
include some limited visual inspections of nearby assets as sample testing for data accuracy)
— maintenance records availability, again with check for accuracy and completeness.
Electricity from high voltage circuits (lines and cables) is transformed, at numerous zone substations, to lower voltage
circuits that each serve anywhere between one and a few hundred customers. Often the transformation in voltage is 33kV
to 11kV; although in Wanaka, the conversion is from 66kV to 11kV, and then to the 400/230 volts used in homes and
businesses.
— Support structures, including poles and the crossarms and insulators that are affixed to poles
— Switchgear and circuit breakers that are used to switch and isolate parts of the network
— Transformers that are used to transform voltages from a high voltage to a lower voltage
— Protection systems that detect a failure of the network that results in a flow of electrical current that is larger than
normal or a flow to ground.
— Asset attributes: this includes basic asset information including the make, model, materials, ratings, age and
location. This data provides understanding of the segments of the asset fleet and allows monitoring of similar asset
classes.
— Condition and defect data: this includes the testing and inspection results of assets, a history of the types and
numbers of defects identified, and any failures to operate as intended for the asset type.
— Performance data: this includes how well the asset is performing its intended function against established criteria.
Commonly this includes reliability metrics (SAIDI, SAIFI, customer minutes off supply), public safety and
environmental requirements.
The use of these data sets enables asset managers to assess the probability and consequence of an asset failure using a
range of techniques. Unreliable or incomplete data reduces the insight that can be gained and limits the analytical
techniques that can be applied.
WSP undertook an assessment of Aurora’s data through a series of interviews with SMEs and analysis of the data sets
provided. We identified several areas where asset data was not available, not as complete or where data was not reliably
collected or stored in a useful format. Our assessment considered the level of data accuracy and completeness that would
be expected for each asset class based on how they are managed by Aurora and common industry practice.
The following sections describe the key elements of the asset data and systems used to gather and store the data.
Internal business network folders Scanned PDF reports and defect data
Protection Settings Database Protection relay makes and models, settings and dates
AMData database SQL Server based asset data repository (developed in-house)
DATA
FIELD VALIDATION CHECKS MADE APPLICABLE ASSETS
QUALITY
High / Audits of Aurora led Testing in accordance with testing Supporting structures - poles
Medium tests / maintenance procedures and training provided. Zone substations – all subclasses
procedures Consistency in testing across different Overhead lines – sub transmission
Independent visual testing staff or crews.
inspection Correct capture of data.
Any Limited field Ad hoc checks made during other Underground cables
validation inspection activities Distribution Transformers
Approach to sampling
In undertaking field work validation, WSP applied a sampling approach to gathering the asset information for those
assets with a large population (poles, distribution switchgear, etc). A sampling approach was required due to the costs
High: the data is sufficiently complete and can be relied upon. It is suitable for the management of the asset type.
Medium: there are gaps in the data but it may be appropriate for use, likely validation is required
Low: the data is materially incomplete and limits the analysis that can be undertake or creates uncertainty in the
results
Each criteria was ranked with the ‘overall’ data quality result reflecting the predominant assessment for the asset class.
This was a semi-qualitative assessment based on discussions with the subject matter expert, analysis of data sets provided
and our experience in the industry. The amount and reliability of the data was considered with respect to each type of
asset and normal approaches to asset management for that asset.
Table 3.3 Summary of initial data quality by asset class
OVERALL DATA
ASSET CLASS SUB CLASS ATTRIBUTES CONDITION PERFORMANCE
QUALITY
Structured Lines
Support structures – inspection approach
Poles Historical inspection
approaches
Fuses
Switches
Distribution switchgear -
Pole-mounted Reclosers
Sectionalisers
Ground-mounted
Voltage Regulators
Overhead lines –
All types
Sub transmission
Overhead lines – HV
Distribution LV
PILC
XLPE
HV cables1
Underground cables –
LV cables1
Distribution
Cast Iron Potheads
Transformers
Bunding
Zone substation –
All types
Circuit breakers
Protection relays
Instrument transformers
SCADA
(1) Although the condition and/or performance data is assessed as a ‘red’, the overall data quality is a ‘yellow’ as condition and
performance data is not generally kept on these assets in the electricity industry.
All data was found to be suitable for our review, except for Underground Cables – Distribution, where attribute data is
held in paper drawing records and, hence, not readily accessible and condition data was not available. We note that this is
not uncommon across the industry, given that the asset is buried. This is discussed further in section 14.1.
4.1 OVERVIEW
Our assessment is required to consider the risk posed by each asset class to identify where Aurora should focus their
efforts for mitigating the network risk to ensure network safety and reliability and to minimise the impact of network
assets on the environment.
Where:
— probability of failure is either a calculated quantitative probability or an assessment of asset condition as a proxy for
probability when the data does not enable a quantitative assessment.
— consequence of failure is either the calculated value of the asset failure or the criticality of the asset based on the
importance of the asset to network safety or operation.
PROBABILITY OF FAILURE
For most assets, the probability of failure can be quantified using data from asset failures as well as the data on assets that
have been replaced due to assessment as being at the end of their serviceable life (prior to failure). Analysis of the data
enables calculation of the probability of failure based on asset attributes and condition information.
Where data is not available to calculate quantified risk, an asset health index has been used as a proxy for probability.
The health of the asset is a good indicator of how well it is likely to perform its function. The calculation of the health
index has been determined with consideration to the method set out in the EEA Asset Health Indicator guide 1. The asset
health risk approach was used for 1 of the 11 asset classes we reviewed.
1 Electricity Engineers’ Association, Asset Health Indicator (AHI) Guide, Revision 1, January 2016
A B High
Moderate
Low
C Insignificant
— that item A has a comparatively higher probability of failure compared to item C, but the same consequence when it
fails
— that item B has a comparatively higher consequence when it fails compared to item A, but the same probability of
failure.
Item B has a very high risk. Where this is a safety risk, it should not be interpreted that item B will result in serious
public injury as there are several events that must align for the risk to materialise. Broadly, the events that must occur
include a) the failure of an asset, b) for the failure mode to be one which poses a risk to the public, and c) for a member
of the public or staff to be present at the time of failure. To assess each of these events in a deterministic manner requires
a number of assumptions to be made, which can result in the assessments not being comparable between asset classes and
difficulty in extrapolation across an entire fleet of assets. Further, it generally results in low probabilities with the effect
of grouping all assets into the same risk category, which does not enable differentiation between assets for the purpose of
prioritisation.
Item B should be interpreted as the failure of this asset has the potential to cause a serious public safety or reliability of
supply risk. As each asset with this level of potential could result in a serious consequence, each asset is assigned the
same serious consequence. In practice, not all assets will fail in a manner that has the potential to cause the highest
consequence and, hence, the asset risk represented by item B cannot be summed with other asset risks to obtain a network
wide risk.
Importantly, we have considered Aurora’s normal working practices when assessing the consequences but have not
considered the operation of safety on the network, or specific safety practices employed by Aurora staff and contractors
in response to the known risks.
The approach we have adopted, of using a comparative or relative ranking for the consequence, means that we can
provide a prioritised list of asset risks that has reasonable granularity. We can use and rely on the available asset data that
we have gathered and / or verified and minimise the assumptions made. All asset classes across both network regions can
be treated with the same method of assessment and using the same relative risk scoring approach. This ensures that the
results are comparable between the asset classes.
5 Almost certain Happened in last year in location >100% nominal life 40% to 100%
4 Likely Happened in last year in company 90% to 100% nominal life 10% to 40%
3 Possible Happened in last year in industry 80% to 90% nominal life 1% to 10%
4.3.1 SAFETY
When assessing public safety risk, we have used asset criticality as a relative measure of risk rather than using an
absolute measure of risk. The application of this approach for distribution assets and for ZSS assets is set out below.
DISTRIBUTION ASSETS
Assets that are above ground in publicly accessible locations can pose a risk to public safety. The assets that fall into this
category include:
— support structures (poles, crossarms, insulators and the top section of poles)
— overhead conductors
Protection systems are located in zone substations but their impact is on public safety in the distribution network.
Therefore, their risk has been modelled based on the same approach as distribution assets.
Sub transmission support structures and overhead conductors are also located in publicly accessible locations and can
pose a risk to public safety. Therefore, their risk has been modelled based on the same approach as distribution assets.
Population density
The physical location of the assets is a significant contributor to the criticality of an asset to public safety. Assets that are
located in areas with a higher population density will have a higher probability of a person being in close proximity when
it fails. Hence, the population density at an asset’s location is an appropriate proxy for the criticality of an asset and is a
consistent and independent measure across all asset types.
Our assessment considered population density based on population data obtained from the 2013 census. The data
provides the usually resident number of people down to the level of residential dwellings. The data is used as a GIS layer
that provided a contour map of population density as shown in Figure 4.1. Increases in population due to tourism have
not been explicitly taken into account due to a lack of available information, although such increases should mirror local
population to some extent. We also acknowledge that some residential growth areas will not be fully reflected in the 2013
data set, however, we consider that those areas are not material in area of the network and are likely to have newer assets
if they have been established since 2013 and, therefore, their exclusion from the analysis will not have a material impact
on the outcome.
As the population density is used as a criticality factor/index rather than as an absolute measure, use of population density
from the 2013 census is sufficient for the purposes of this review to prioritise assets risks.
— The impact area of an asset when it fails was calculated. The area was based on physical attributes such as the height
of a pole or evidence from other failures at Aurora or in the electricity industry.
— The population density of the area was multiplied against the impact area to calculate the impact on population
density.
The public safety consequence is, therefore:
Limitations
This assessment of safety risk is not an absolute measure but intended to be comparative between assets to enable
prioritisation between asset fleets. The method is only applicable to distribution assets, i.e. those that are installed outside
of zone substations, and protection relays.
Figure 4.1 Population density derived from the 2013 Census data2
For these assets, analysis of the asset type, calculation of parameters such as arc fault boundary, experience and
knowledge from recent events in the electricity industry, and engineering judgement is used to assess the criticality.
We note that Aurora implements a number of practices and procedures to safeguard personnel working within a zone
substation, however, as discussed in section 4.1.2, our review is of the asset risk. The effectiveness and consistent
implementation of the safety process have not been considered or assessed as part of this review. Hence, our assessment
does not consider the safety practices in assessing the asset criticality.
— the demand supplied by an asset (the amount of energy that would be interrupted if the asset was to fail)
— the value of customer reliability (VCR) also called the value of lost load (VoLL), typically expressed as $’000/MWh.
3 Electricity Authority, Investigation into the Value of Lost Load in New Zealand – Report on methodology and key findings, 23
July 2013
The approach to calculating the energy at risk has been undertaken using one of two methods based on the asset type and
the data available for the asset type.
DISTRIBUTION ASSETS
Distribution assets have a lower impact on unserved energy and can typically be replaced in a short period of time.
Aurora provided us with unserved energy values by using its GIS to calculate the impact of an asset failure for each
distribution asset. The approach found the nearest isolation point upstream of the asset being assessed and calculated the
SAIDI impact based on all customers downstream of that isolation point losing supply for a period of four hours to
represent an indicative outage duration. This calculated a SAIDI value that reflected the number of customers and
duration of time they would be affected. The assumption of four hours for each outage is appropriate based on their
historical performance and suitable when considering a fleet wide analysis.
WSP leveraged this analysis to convert the SAIDI value back to customer minutes off supply, then using the average
demand per customer calculated the unserved energy. This was then multiplied by the VoLL to derive an economic cost
of each asset failing.
ZONE SUBSTATIONS
Energy at risk is assessed at a zone substation level using demand data available from SCADA, transfer capacity
available at each individual zone substation, redundancy and nameplate capacity. The key information sources and how
they are used include:
— substation demand: extracted from SCADA and used to develop a load duration curve (LDC) for the substation. The
LDC is the arrangement of the hourly demand data from highest to lowest to show the proportion of time throughout
the year that a specific level of demand is experienced
— asset capacities: extracted from asset databases these include the nameplate rating, and redundancies (i.e. N-1
capacity if relevant)
— transfer capacity: based on engineering assessment of the substation and feeder configuration, this specifies the
amount of load that can be supplied from an adjacent substation
— time to restore supply: this was based on engineering judgement and Aurora’s plans for specific substations
The amount of energy that would not be supplied in the event of an outage is calculated using the LDC and the N, N-1 or
N-2 capacity of the substation as appropriate, allowing for the transfer capacity. The energy multiplied by the VoLL to
calculate an economic cost of the outage.
4.3.3 ENVIRONMENT
The Resource Management Act 1991 (RMA) sets out the requirements Aurora must meet with respect to environmental
management. The RMA also sets out penalties for failure to comply or meet the requirements The Penalties are separated
into three grades of severity and infringement notices. These are described below: 4
— Grade 1 offences carry a maximum penalty for a person of imprisonment for up to 2 years or a fine up to $300,000.
Entities are subject to a fine of up to $600,000 and there is provision for an additional penalty of up to $10,000 for
every day during which the offence continues. These offences relate to activities that make use of land or undertake
activities on land without consent or in contravention of a district plan
— Grade 2 offences carry a maximum penalty of $10,000 and, if the offence is a continuing one, a further fine up to
$1,000 for every day during which the offence continues. These offences relate to contravention of an order made by
the Environmental Court, particularly regarding protection of sensitive information and noise
— Grade 3 offences carry a maximum penalty of $1500. These offences related to wilful obstruction of people
exercising powers under the Act or contravention of a summons or an order to provide information
— As an alternative to criminal proceedings a Council may serve an infringement notice where an infringement offence
has been committed. The person culpable will required to pay an infringement fee of up to $1000.
SAFETY INDEX
SAFETY INDEX ECONOMIC CONSEQUENCE
CONSEQUENCE / (DISTRIBUTION,
(ZONE SUBSTATION (ENERGY AT RISK,
CRITICALITY RANKING SUBTRANSMISSION AND
ASSETS) ENVIRONMENT)
PROTECTION ASSETS)
— Landslides
— Flood areas.
Additionally, hoar frost and ice occur frequently in the inland regions and can occasionally impact the network to a
significant degree.
Our approach to assessment of resilience is based on a GIS view of the assets and the natural hazards to which they are
subject. These hazards are shown in Figure 5.1 with the two largest population centres, Dunedin and Queenstown, shown
as inserts to provide more detail.
Figure 5.2 shows a close up of the Dunedin city area to provide additional detail on the sub transmission cables that are
located in the area and the natural hazards. The figures highlight the number of assets that are located in each risk area
and the number of different risks that exist in the Dunedin and Central Otago regions 5. Dunedin supplies 56.5% of
5 The data used for the GIS risk layers was sourced from Otago Regional Council https://www.orc.govt.nz/managing-our-
environment/maps-and-data.
To demonstrate the significance of these hazards, a summary of major events has been provided in Table 5.1 and Table
5.2. Table 5.1 shows there have been 43 significant natural events in New Zealand in the past 155 years with 12 affecting
the South Island and in the proximity of the Otago region. Table 5.2 shows the annual average number and frequency of
earthquakes in New Zealand.
Table 5.1 Number of natural hazard events in New Zealand since 1843 (excluding earthquakes)
Weather 13 2
Landslide 9 4
Flooding 8 1
Tsunami 8 4
Volcanic 3 0
Wildfire 2 1
Total 43 12
Source: https://www.geonet.org.nz/about/earthquake/statistics
Of the hazards considered, Earthquakes, Landslide and Tsunami represent the greatest hazards. Of these, tsunamis and
landslides occur infrequently and have caused only minor damage in the Aurora network area. For example, the 9.5
Richter scale Chilean earthquake of 1960 resulted in a tsunami of 2.7 metres above the tide level of the time at the Port of
Lyttelton (near Christchurch) in the South Island, damaging boats and electrical gear. A hotel and several houses were
flooded, and 200 sheep drowned.6 To achieve resilience, key network assets and critical spares should not be located in
tsunami affected areas, or where landslides are possible.
Conversely, earthquakes occur frequently, with damaging earthquakes every 4 years on average. Network resilience will
be impacted by assets close to fault lines and the susceptibility of key assets, such as substations, to damage from earth
movement and vibration.
— Much of the damage was a result of a result of liquefaction and lateral spreading around watercourses rather than
peak ground accelerations7. Liquefaction occurs predominantly where geologically young soil (<10,000 years old),
consist of loose sediments that are fine grained and non-cohesive (coarse silts and fine sands) and are saturated
(below the water table). Areas in the Aurora network that are prone to liquefaction are shown in Section 5.2.
6 https://teara.govt.nz/en/tsunamis/page-3
7 K. Group, “Resilience Lessons: Orion's 2010 and 2011 Earthquake Experience, Independent Report,” September 2011.
— Breaks in cables included failure of couplings in tension, failure of cables in compression and damage resulting from
failure of concrete slabs used to support cables8. It was found that ducted cables survived these conditions better than
exposed cables, with the duct providing some level of protection, so while the duct itself was damaged the cable
remained undamaged. Installation and joining faults dominated buried electrical cables, some of which could be a
result of poor insulation practices.
— In the 11kV system modern cables with PE sheathing had lower break rates than older cables with PILC sheathing.
This indicates that in the long term there will be benefits from replacing older cables with newer cable types which
are more resilient.
— An earthquake affecting the Dunedin area could result in liquefaction of the ground that could make the Head Office
and main Dunedin control room inaccessible. This would:
— impact the ability to manage the network and coordinate network restoration
— impact control of the network to manage the network restoration process and ensure public safety
— potentially cause the loss of some asset or network information (note that electronic data is backed up on servers
located in Wellington).
8 Opus, “Technical Note 05 - Response of Buried Assets other than Water Pipelines (Part of Underground Utilities - Seismic
Assessment and Design Guidelines),” November 2016.
9 Aurora advise that the new system has now been commissioned.
A very small possibility exists that ground liquefaction could impact both control centres, but it is likely that such an
event would require the entire area to be evacuated and, hence, is not an unreasonable risk to take.
Asset MAX
# CUST DEMAND FLOOD LIQUEFACTION EARTHQUAKE LANDSLIDE
(MVA)
The table shows that Flood, Liquefaction and Earthquake are the greatest risks to the zone substations:
— For flood risk, we found that those zone substations that are in flood prone areas were located close to customers
and, hence, no reasonable alternative location was possible. We note that no precautions against possible flood are
evident at these substations.
— For liquefaction, we note that no additional precautions other than those required by building codes have been
undertaken.
— For Earthquake risk, we note that only two zone substations are affected (close to fault lines) and that these are
located close to customers and, hence, no reasonable alternative location was possible.
Severe damage to a substation could result in an extended outage. The typical lead time for a power transformer is around
9 months and the typical time from design to commissioning is close to 2 years. Although the process could be expedited,
the common risks amongst the zone situations means there is likely to be multiple zone substations damaged and,
therefore, there could be further constraints due to asset lead time or labour resources.
Other events can also occur, such as hoar frost where sustained low temperatures can cause the build-up of ice on
conductors, and the weight of ice can exceed the capacity of the conductor to support the additional strain resulting in
broken poles and/or conductors. Typically, such events have a low impact on safety and reliability when compared to
other events and, as such, have not been considered in our risk assessments.
— how the network topology is likely to impact the ability of the network to respond to asset failures
— assessment of how well Aurora is meeting their security of supply criteria guidelines.
This section is not a full review of the security of supply arrangements implemented by Aurora. It is only intended to
inform how the network topology mitigates, or otherwise, the impact of asset failure and how that affects the
consequence of asset failure and, hence, the risk posed by each asset class.
Urban
U1 Initially – nil Initially – nil
0 to 1 NA
100% GPD within 4 hrs 100% GPD within 4 hrs
Initially – nil
U2 1 to 3 (6.6kVA), or Initially – nil
100% GPD within NA
1 to 5 (11kVA) 100% GPD within 4 hrs
switching time
Initially – nil Initially – nil
U3 Initially – nil
3 or 5 up to10 100% GPD within 100% GPD within
100% GPD within 4 hrs
switching time switching time
Initially – nil
U4 Initially – nil
Over 10 Defined firm capacity 100% GPD within
100% GPD within 4 hrs
switching time
Rural
R1 Initially – nil
All
100% GPD within 6 hours
R2 0 to 3 (6.6kVA), or Initially – nil
0 to 5 (11kVA) 100% GPD within 6 hours
R3 Initially – nil
0 to 5MVA
100% GPD within 6 hours
10 Aurora is proposing and seeking feedback on a new Security of Supply standard in the 2018 Asset Management Pan. The new
standard was not available in sufficient time for this report. Note that a changed standard may impact our findings.
Cromwell GXP 6
Frankton GXP 8
Total 39
The sub transmission network in Dunedin is typically underground cable in the urban areas and overhead lines in the
rural areas. The sub transmission network in Central is typically overhead lines. This reflects the population density and
geography of the network areas.
The following items that impact on network security were identified:
— Most of the network is arranged in a dual radial line configuration to each substation. However, some of the smaller
zone substations are supplied by only a single radial sub transmission line, although all have some load transfer
capability via interconnections with adjacent feeders. These include:
— Ettrick ZSS
— Cardrona ZSS
— Berwick, Outram, Mosgiel and East Taieri are all connected to the A Line, B Line and C Line feeders that run
between Waipori and Halfway Bush GXP. There appears to be sufficient redundancy provided, given:
— Mosgiel ZSS has three connections from the three lines. Two of the overhead lines then run parallel to each
other with a separation of approximately 10m between the circuits for the majority of the route. This could
provide a common point of failure for the two circuits which reduces the security of both Mosgiel and East
Taieri. The third line is separated and is routed down an adjacent road
— East Taieri ZSS is connected via cable from Mosgiel ZSS, hence it is reliant on reliability/security of Mosgiel
ZSS and is not directly connected radially to Halfway Bush GXP
— Berwick ZSS and Outram ZSS have connections to all three lines.
We note that the A, B and C Lines are in poor condition, but Aurora has plans in place for remediation. Implications
to the protection scheme due to the complex feeder arrangement are discussed in section 17.
— The new Carisbrook ZSS will be supplied from South Dunedin GXP, whereas Neville St ZSS which it is replacing,
was supplied from Halfway Bush GXP. The existing interconnector from Ward Street (which is fed from Halfway
Bush GXP) will be reconnected to the new Carisbrooke ZSS. This arrangement will improve the ability of the
network to transfer load should one of the GXPs experience an outage.
— North East Valley is a HV spur line comprised of sections of overhead line and underground cable connected to the
Port Chalmers feeder originating from Halfway Bush GXP. The connection point is controlled by IRW-955 manual
switches. Hence, a fault at either North East Valley or Port Chalmers, upstream from the 33kV ZSS circuit breakers,
will reduce the security of supply to the other substation until manual switching can be undertaken.
— Sub transmission cable faults are difficult to locate and take time to repair or replace. Therefore, the condition of
these cables is important for ensuring that they provide the expected level of redundancy and each cable is capable of
supplying the full capacity of all connected zone substations. Sub transmission cable condition is discussed in section
13. Additionally, some underground cables forming dual circuits are installed in the same trench and pose a risk of
suffering damage from a common event, such as excavation.
— Ettrick ZSS is supplied by a single radial line from Roxburgh ZSS and Omakau ZSS and Lauder Flat ZSS are
supplied by a single radial line from Alexandra ZSS.
— Both circuits of the Wanaka to Queensberry line are located in relatively close proximity for a short section along
Wanaka Luggate Hwy.
— The transfer capacities within the Dunedin area (Neville St (will become Carisbrook), Smith St, Mosgiel, Kaikorai
Valley and Ward St) are, or greater than, the demand on those substations. As a result, even though some have high
probabilities of failure, such as Neville St, there is no impact if there is a transformer failure as the demand can be
completely transferred away via the distribution network.
— Aurora has plans to restore supply to a single transformer ZSS in the case of a transformer failure by a mobile
transformer that can be used for this purpose (where it is technically compatible and if not already deployed). We
note that Aurora also has a spare 5 MVA transformer on order and the transformers from currently planned
substation rebuilds will be retained as spares, facilitating the restoration of supply following an outage.
The sub transmission network would relate to outages that would be classed as U3, U4, R2 and R3 based on Table 6.1. In
general, the topology of the network at sub transmission level should provide sufficient redundancy to enable Aurora to
meet the security requirements. Ettrick, Omakau and Lauder Flat are radially supplied by a single sub transmission line,
however, these are small rural zone substations with peak loads of 1.9 MVA, 2.8 MVA and 0.7 MVA respectively
supplied by 33kV overhead lines so it is likely supply could be restored within the required 6 hour period.
6.2.2 DISTRIBUTION
Security of supply at the distribution level is driven by the redundancy of transformers at the zone substations and the
degree at which the distribution feeders are interconnected and able to switch to transfer load to other feeders. These
attributes are discussed in the following sections.
ZONE SUBSTATIONS
Review of the current load data and forecast growth rates indicate there are no capacity constraints currently on the
network that are resulting in demand not being supplied. All Aurora owned zone substation assets currently have
sufficient capacity to supply all connected load in normal circumstances and high growth areas have sufficient capacity to
meet future demand (based on current forecasts). The only substation where there is an approaching capacity constraint is
Remarkables: however, that is a customer connection point and is dependent on the customer requesting more capacity.
Table 6.3 shows the number of zone substations that have N-1 redundancy. All urban substations have two transformers
so that an outage on one transformer should not cause a long interruption to supply.
Almost all rural substations only have one transformer. This appears appropriate when considering the relatively small
number of customers supplied from these substations. Often the decision to install a sub transmission line and substation
is made for technical reasons (voltage drop and transfer capability) rather than for reasons of reliability of supply and,
hence, providing redundancy is not economic. We did not find any single transformer substations that should have been
provided with an N-1 redundancy (see energy at risk assessment in section 15.5). We note that Queensberry ZSS and
Lindis Crossing ZSS are located close together and Aurora considers them as one 2 transformer substation in terms of
demand security.
Table 6.3 Substation redundancy
Central RURAL 5 13 18
Central URBAN 3 - 3
Dunedin RURAL - 2 2
Dunedin URBAN 16 - 16
Total 24 15 39
We note, however, the peak demand at a number of zone substations with two transformers has exceeded or is
approaching the substation’s firm capacity (N-1 capacity plus load transfer capacity). These substations are shown in
Table 6.4. Only two have exceeded their firm capacity rating: Arrowtown ZSS and Cromwell ZSS. Peak demand at the
zone substations not listed is at 60% or less of firm capacity.
Arrowtown 155%
Cromwell 140%
Frankton 81%
Wanaka 80%
Alexandra 79%
The zone substation asset that limits the capacity of the substation is shown in Table 6.5. In the majority of cases, it is the
transformer that is limiting capacity.
Table 6.5 Zone substation constraints
Incomer CB rating 4
Transformer capacity 25
Total 39
Note: Riverbank ZSS and Carisbrook ZSS are not yet commissioned so are excluded from the list above
In summary, the network appears to be designed appropriately to meet the type and magnitude of demand at a zone
substation level. Arrowtown and Cromwell has exceeded their firm capacity, however we note that Aurora has work
underway to address these in 2018 and 2019 respectively.
The security of supply requirement for rural areas set a single requirement for all contingencies, which is to restore
supply within 6 hours following an outage. Although Aurora has a mobile substation to respond to transformer outages,
their ability to restore supply within the required timeframe may be limited should an outage occur while the mobile
substation is deployed elsewhere.
DISTRIBUTION FEEDERS
Designing the network with flexibility to transfer load onto adjacent feeders is important for managing supply and
facilitating the maintenance and inspection of distribution assets.
In the Aurora network, most distribution feeders in urban areas have good levels of interconnection with adjacent feeders.
Some parts of urban feeders are radial with no interconnection and rural feeders are predominately radial with no or
limited interconnections to other feeders. This means that there is no or limited possibility of switching to improve the
speed of resupply of customers. These arrangements do not appear different to most other electrical line utility
businesses.
AREA COMMENT
Arrowtown 11kV — The 11kV is arranged as interconnected ring distribution network, however some
parts are fed radially and do not have any redundant feeders or supply.
Fernhill substation — Complicated ring distribution arrangement, with some parts fed radially.
— The network is interconnecting with other areas, which makes it flexible during
outages.
Frankton Substation 11kV — The 11kV is arranged as interconnected ring distribution network, however some
parts are fed radially.
Glenorchy – Oxburn 11kV — The network is radially fed. Although Air Break Switches are connected along the
lines, it will not be possible to isolate part of the line for any reason (faults or
maintenance) without loss of supply to some parts of the line.
Queenstown and Commonage — Each zone substation is supplied by two sub transmission line originating from
11kV Frankton GXP, each supplying different sections of the 11kV bus bar. This provides
N-1 redundancy at each station.
— There is no specific approach to how the 11kV network is configured. This will
make it difficult during network operations and upgrades to account for all
scenarios to ensure feeders are able to provide backup feed for certain areas during
outages.
Alexandra 11kV — The distribution network is based on interconnected ring arrangement, however
some of the parts are radial. With this arrangement, network parameters knowledge
and database is essential to assess the backup feeding arrangement during
equipment or feeder outages.
Clyde-Earnscleugh 6.6kV — Most of the network is radial, therefore outage of any equipment or feeder section
will result in outage of parts of the feeder. Part of the network is connected through
an Auto transformer to Galloway-Crawford Hill 11kV network, this may provide
supply to that part of the feeder in case of an outage.
Ettrick (ETTR) 11kV — The system is fed from a single transformer at Ettrick and interconnected with
Roxburgh substation, Parts of the network are radial and outages of section of the
line will mean losing supply from that section.
Galloway, Omakau Roxburgh, — The network is interconnected which will allow feeding from different parts of the
Single Creek-Fruitlands, network to provide backup during outages. However, some parts are fed radially,
Roxburgh Hydro therefore sections of the 11kV lines will be isolated during outages.
— In general, the design of the network is likely to enable Aurora to meet the security of supply requirements by using
network switching at the 6.6kV distribution level in Dunedin. This would enable more rapid resupply of load in the
event of a zone substation level outage event.
— The ability to transfer load between feeders at the distribution level in central is more limited due to the geography of
the network. Switching between feeders from the same substation is possible, however, transferring load from one
substation to another via the distribution level is typically limited to the Queenstown area.
— the peak demand was calculated as the average peak demand per customer based on the zone substation peak
demand divided by the total number of customers supplied by that substation
— the number of customers affected by an outage was multiplied by the customer peak demand for that group of
customers, based on the feeder, number and summed together. If the feeder number was not known, the network
average peak customer demand was applied
— the feeder number was used also used to classify the outage as either urban or rural
— the group peak demand and urban or rural classification was used to allocate the outage to a security of supply
category as set out in Table 6.1
— To be categorised as U4, the Asset affected had to be identified as a zone substation, otherwise it was allocated to
U3. This was considered to align more closely to the definitions in Table 6.1. All other categories were based on the
Group Peak Demand of the customers affected by the outage and does not consider the type of asset that caused the
outage.
The distribution of the outages was calculated and plotted. The distributions were found to be exponential with high
occurrences of low duration outages and fewer occurrences of high duration outages. Figure 6.1 shows an example of the
results for the U1 category.
Figure 6.1 Example of the frequency distribution for the U1 category of outages (4 years to 30 June 2018)
PERCENTAGE OF
CATEGORY REQUIREMENT (HOURS) AVERAGE (HOURS)
OUTAGES WITHIN LIMIT
U1 4 79% 4.8
U2 4 83% 3.0
U3 4 82% 2.7
U4 4 93% 0.6
R1 6 90% 3.2
R2 6 84% 4.4
R3 6 88% 2.9
The ‘Unknown’ cause code is the most frequent category, followed by equipment deterioration and weather and
vegetation. Fuses and overhead line are the two most frequent asset classes affected followed by ‘Unknown’ and poles.
This prominence of ‘Unknown’ in the analysis of this data indicates that there is uncertainty and difficulty in accurately
identifying the cause and recording the data, but also identifies where improved data collection might add valuable
insight into assets and failure modes that should be prioritised to improve network security. It would be a difficult task to
improve security without first reducing the Unknown category.
The performance against the criteria is a combination of the response of the field crews to an outage as well as the
flexibility of the network to be able to enable quick restoration of supply through switching. Improvements can be made
through investment in network flexibility or via improved field crew response.
— Most distribution feeders in urban areas have good levels of interconnection with adjacent feeders. Some parts of
urban feeders are radial with no interconnection and rural feeders are predominately radial with no or limited
interconnections to other feeders. This means that there is no or limited possibility of switching to improve the speed
of resupply to customers. These arrangements do not appear different to most other electrical line utility businesses.
— Although embedded generation is connected to the sub transmission network, it does not provide security to the
network because when a sub transmission line outage occurs, the generation must be disconnected.
— There is no interconnection between ZSS’s supplied from different GXPs. If a GXP was lost, then it would affect all
connected ZSS’s. In the Dunedin area there is one sub transmission connection between GXPs and an ability to
transfer load at the distribution level for some feeders, but generally, there is geographical separation between ZSS’s
supplied by each GXP, making interconnection difficult.
— ZSS’s are supplied radially from the GXPs, but by double circuits, so there is a level of redundancy.
— Wanaka Cromwell line has a section where the two circuits are relatively close so could both be impacted by a
significant storm event.
— ZSS’s supplied by oil insulated cables are likely to be at higher risk due to the condition of the cables and higher
probability of a second contingency event (both cables out of service).
— 12 ZSSs are single transformer sites and do not have sufficient transfer capacity to off-load all load. However,
Aurora has a mobile transformer that can be deployed to mitigate the risk of a transformer failure.
— There are no emerging capacity constraints for Aurora owned ZSS’s when operating under normal (N) conditions.
— There are two substations, Arrowtown and Cromwell, with peak demand currently above their firm (N-1) capacity
rating.
— There are four substations approaching their firm (N-1) capacity at 70% to 81%. Of these, Frankton and Wanaka
have significant growth forecast, while Alexandra has slight growth forecast and Anderson’s Bay has a flat growth
forecast.
— The network is meeting its security of supply requirements between 79% and 93% of the time across the 7 security
of supply categories.
WSP concludes that the security of supply appears to be appropriate for the size and topography of the load supplied.
Security of supply could be significantly improved by adding more interconnections between ZSSs and HV distribution
feeders, but this is unlikely to be economic with the present network size.
— The data is only recorded to the nearest distribution transformer. This has the effect of reducing visibility of any
locational issues, such as from vegetation, and limits the ability to consistently identify a specific asset type that is
causing outages.
— 28% of outages have a cause code of “Cause Unknown” allocated and 17% of outages have an asset type code of
“Equipment Unknown” allocated. The cause of some types of faults and the initiating asset type, such as those
caused by conductor clashing or vegetation contacting conductors, are not always able to be identified.
— Description and comment fields are free text resulting in multiple variations of text for the same issue. This makes it
more difficult to analyse the data consistently. We note that recording outage information in free text fields
(unstructured data) is not a practice unique to Aurora, it is common with electricity distributors across Australia and
New Zealand.
— There is inconsistent recording of the feeder ID where the fault occurred. This makes it more difficult to analyse the
data consistently.
Despite the limitations of the asset data, we found that the outage data available was suitable overall and appropriate to
allow our analysis of the network risk. The data limitations highlighted above did however limit the insight that could be
gained.
A summary of the outages by equipment type, as reported to the Commerce Commission, is set out in Figure 7.2. The
charts highlight that the outages have been predominately caused by distribution lines, distribution cable and distribution
other. Sub transmission lines and sub transmission other have also caused unplanned outages.
11 The data for these charts was obtained from the Commerce Commission website: https://comcom.govt.nz/regulated-
industries/electricity-lines/electricity-distributor-performance/information-disclosed-by-electricity-distributors. The reliability data
included up to 2017. Data for 2018 was not available.
Based on SAIFI, which reflects the number of incidents, an average of 23% of outages between 2013 and 2017 are
identified to be the direct result of defective equipment based on the data reported to the Commerce Commission. As
shown in Figure 7.3, this has risen linearly from 16% of outages in 2013 to 28% in 2017. The high R 2 value indicates the
trend is well supported by the data. However, the data available from the published outage data on the Commission
website does not provide detail of the asset classes or asset types that are included in the defective equipment category.
The following sections further assess the historical performance of the network using the outage data recorded by Aurora
which provides a more granular level of detail for each outage.
Figure 7.4 Count of unplanned outages from all assets due to deterioration
Distribution substation – Fruitlands – It appeared that the distribution Aurora’s spill response protocol
Rural – remote – 2017 substation had been struck by a vehicle deployed, and clean-up of the site was
causing oil spillage. undertaken. Otago Regional Council
informed of the incident.
Pole top distribution substation struck The pole was knocked down and oil Aurora’s spill response protocol
by a car – Mosgiel 2018 escaped from the transformer. deployed, and clean-up of the site was
undertaken. Otago Regional Council
informed of the incident.
Pole top transformer hit by truck – An unidentified high sided vehicle has Delta replaced the transformer. Fulton
2018 made contact with a pole mounted Hogan cleaned up the spill
transformer, resulting in damage to the
transformer which resulted in the
release of the contents (Oil) to ground.
North City Underground Oil Filled Detection of loss of oil pressure which Contact was made with the Otago
Cable – 2015 suggested that oil was leaking from the Regional Council and they were
cable. advised of the issue. A programme of
testing was instigated to discover the
location of the leak. This included
thermal imaging.
Based on historical performance, Aurora appears to be managing the network assets to pose a low risk to the
environment. The environmental issues reported are limited to cables and distribution transformers but have not resulted
in any financial penalties.
— controls put in place to prevent an incident such as design standards, inspection and replacement programs
— control to mitigate the impact of an incident once it has occurred such as appropriate protection systems to de-
energise the assets and ensuring suitable response times by field crews.
Historically, the number, cause and impact of safety incidents has not been recorded consistently. In 2013 an issue
notification register was created and used for reporting of network issues, including public safety items. Based on
discussion with Aurora staff and review of the data, the register was actively used during 2014 and 2015, but ceased to be
used consistently during 2016 and early 2017 with significantly fewer incidents recorded. The register was re-established
in July 2017 and has been used consistently since with one person responsible for the data entry and reporting.
Cable - 1 - 20
Crossarms 2 12 - 16
Conductor 27 35 26 225
Miscellaneous - 3 2 63
Pole 6 46 - 88
Shock -- - - 2
Streetlight - 2 - 6
Table 7.2 sets out how many of these incidents were caused by equipment defects and failures. The total data set
indicates that 225 hazards relate to conductors, 88 to poles and 16 to crossarms. Serious hazards are categorised based on
where the text field indicated that there was an elevated risk to the public such as conductors remaining live on the
ground or starting a fire (protection failed to trip or was delayed) or poles falling on roads or footpaths. Descriptions that
stated the conductor was on the ground but did not specify the conductor was live or had caused a fire were excluded
from the serious hazards in Table 7.3 as it was considered more likely that the conductor would have been deenergised.
Table 7.3 Summary of public hazards
Cable - 1 - 20
Crossarms 2 12 - 16
Conductor 27 35 26 225
Miscellaneous - 3 2 63
Pole 6 46 - 88
Shock -- - - 2
Streetlight - 2 - 6
The table identifies 35 incidents in the period 2015 – 2018 where a conductor fell to the ground and remained live. We
identified that:
— some were on the LV network, with protection by a fuse that did not react to the fault
The analysis also identifies that an average of 11 poles per year have failed and fallen over as a result of asset
deterioration. This aligns with the data recorded in GIS and the outage data regarding poles that have failed in service.
— There is inconsistent data entry into some fields, particularly free text fields.
The network is showing an upward trend in the number of outages being experienced. This trend is evident in reliability
metrics of SAIDI and SAIFI reported to the Commerce Commission as well as when considering the number of asset
outages. The number and duration of planned outages increased in the 2017 financial year, from an average of 22% to
37% for SAIDI and an average of 10% to 20% for SAIFI. This reflects Aurora’s implementation of the accelerated pole
program and increased focus on asset replacement. We also note that Aurora has identified some changed work practices
relating to the operation of some fuse types and inhibiting auto reclose during summer that could have an impact of
increasing both SAIDI and SAIFI.
The outage data showed that there is an increasing trend in the outages caused by deterioration of support structures and
distribution switches and there is a large but steady contribution from overhead lines. In addition, review of the public
safety registers found that there have been 35 instances of live conductors on the ground that have not been deenergised
by fuses (LV) or protection (HV), although some were identified as high impedance faults that cannot always be
detected.
The analysis identified the following critical assets:
— Protection systems: our analysis of outages demonstrated multiple instances when protection systems did not operate
and, therefore, did not mitigate the public safety risk as intended.
— Support structures: including both poles and the pole top structures (i.e. crossarms and insulators) have demonstrated
a period of declining performance and have posed a high risk to public safety due to the number of pole failures. The
recent accelerated pole program appears to have slowed this declining trend.
— Overhead conductor (all voltages): demonstrated to have a steady performance based on asset deterioration driven
failures but is the most significant contribution to reliability performance based on defects relative to other asset
classes. It poses a high level of risk to the public when it fails and relies on the protection systems to detect the
failures and deenergise the section of the feeder.
— Distribution switches (all voltages): these have recently demonstrated an increasing trend in the number of asset
failures driven by deterioration.
Aurora’s network does not appear to pose as significant risk to the environment. Only four instances of environmental
impacts were identified during the last four years and all were minor with no financial penalty.
— poles
— crossarms
— insulators.
— pole data from GIS, Structured Lines, Xivic and older records
— performance data including outage data and the public hazards database
The poles data was split into three main spreadsheets. One for Structure Lines data, one for Xivic data and one for poles
not tested under Xivic or Structured Lines. Overall the attribute data for the poles inspected by Structured Lines was good
and mostly complete, but the level of completeness varied with the other two data sources. Crossarm and insulator data
was also found to be quite complete but did not appear to have been kept up to date. The key findings were:
Attributes (poles):
— 2.5% of poles were missing the location identifiers (i.e. Pole ID, Global ID, Facility ID, Object ID) were not
recorded, did not match across all data sets and there were some that were not unique
— 2.5% of poles did not have a material type, height or configuration recorded
— The status (in service or out of service) was not recorded for 2.0% of poles
— Where pole installation dates were not known, the data had been inferred based on assumptions, including the age of
associated plant. This is common practice in the industry and is considered an appropriate approach to fill in data
gaps for this asset class.
Attributes (crossarms):
— Crossarm data had fairly complete locational information but inconsistent use of inputs for attribute data and the
inputs did not always match the column heading which made it difficult to use
— The majority (73%) of condition data for crossarms was collected between 2010 and 2013 so was not up to date
information.
Performance:
— Performance data was available for all assets from the outage data and in the public hazards register.
OVERALL DATA
ASSET CLASS SUB CLASS ATTRIBUTES CONDITION PERFORMANCE
QUALITY
Crossarms All
Criticality is used to describe the consequence of an asset failing in service. The criticality segmentation for poles has
been based on safety to public as the assets are above ground, in close proximity to the public and have failure modes that
can result in unsafe situations. The consequence of failure on reliability is considered less as only a small number of
consumers are typically impacted. For the initial analysis WSP used the locations of Points in Interest (POI) provided by
Aurora. The POIs define a spatial location such as a school, social infrastructure, emergency services, or shopping
centres and are used as a proxy for volumes of foot traffic or population density. Aurora has used GIS to identify the
proximity of assets to approximately 18,000 POI’s.
CENTRAL DUNEDIN
MATERIAL TOTAL
CRITICAL NON-CRITICAL CRITICAL NON-CRITICAL
POLE TOPS
The distribution of the pole top fleet is shown in Table 8.3.This table shows the breakdown of the crossarms into the
material type. It shows that the majority of crossarms are hardwood, with only 1.7% steel. Typically, steel crossarms are
only installed on steel poles, although there are a few exceptions.
Table 8.3 Crossarm fleet
There have been different types of hardwoods used on the network but predominantly Australian hardwood and
Malaysian hardwood. The Malaysian hardwood has been found to be of lower durability and is often found to have a
specific type of fungal growth on it. It is also smaller cross-sectional dimension of 75mm rather than the standard
100mm. There are approximately 3,620 Malaysian hardwood crossarms on the network based on the GIS data
(extrapolating for the unknown proportion) which agrees with the numbers identified by staff during interviews.
The crossarms asset data shows that 60% of the crossarms are located in Dunedin and 40% are located in Central.
Comparing this to the percentages of pole in each location, we found that Dunedin has 1.9 crossarm levels per pole and
Insulators generally have a life that is longer than the crossarm and are replaced when the crossarm is replaced. Some are
damaged and replaced early but, for the purpose of this analysis, we consider the crossarms and insulators as a single
group when assessing performance, risk and drivers for replacement.
Table 8.4 shows the breakdown of the insulator fleet. It shows that 31% of the insulator types are not recorded in GIS. It
also shows that 45% of the fleet uses pin type insulators. This type is known to enable water ingress where the insulator
is attached to the crossarm and, therefore, enable deterioration of the crossarm.
Table 8.4 Insulator fleet
Post 360 0%
Shackles 1,628 2%
AGE PROFILES
The age profile in Figure 8.2 shows the relative age of the pole assets and material types. The age profile provides an
indication of the volumes of assets approaching the end of their expected lives. The pole profile has three large spikes in
1960, 1965 and 1970 and several smaller ones in five year increments from 1975 to 1990. Although the total volumes
installed each year are not excessive or unrealistic, the pattern indicates it is likely that default or calculated dates have
Similarly, Figure 8.3 shows the age of the crossarms assets by material type. The crossarm data did not contain an age for
the crossarms. We note that Aurora has a reconductoring program that was completed in 2004 which resulted in crossarm
replacements and there is evidence of ad hoc crossarm replacements, however, there has not been a dedicated program to
address crossarm condition. To address the uncertainty in the age data for crossarms, WSP assumed the crossarm was the
same age as the pole as there was no other more reliable data.
WEIGHTED NUMBER
WEIGHTED
EXPECTED LIFE AVERAGE EXCEEDING
AVERAGE AGE
REMAINING LIFE EXPECTED AGE
Table 8.6 shows the fleet statistics in relation to the expected life of the crossarms. It highlights that the fleet is quite old
with 44,244 crossarms are exceeding their expected age. Note, this analysis is based on the calculated age profile for
crossarms, so can only be viewed as an indication of the fleet status. It is likely that a number of crossarms have been
replaced and the fleet has fewer assets exceeding their expected lives.
Table 8.6 Fleet statistics – Crossarms
WEIGHTED NUMBER
WEIGHTED
EXPECTED LIFE AVERAGE EXCEEDING
AVERAGE AGE
REMAINING LIFE EXPECTED AGE
These tables provide an initial view of the potential risk to the network as it demonstrates that there is an expectation of a
need to address assets that are reaching or have exceeded their expected life. However, some assets can remain in good
condition well beyond their life, so condition assessment and examination of historical trends of the asset performance is
necessary to refine the view of risk and properly understand the network risk.
— At the base, just below ground level, the rot occurs from the inside and spreads upwards and outwards, so it is
difficult to detect. The poles also rot from the outside inwards, but this can be easily observed and measured.
The result is loss of strength of the pole until the forces it is subjected to (tensions and weight of the conductors,
wind) cause it to break
— At the top of the pole the rot spreads downwards and outwards. It can be seen when observed from above but is
generally not visible from the ground. It can result in weakening of the crossarm attachment point and splitting
of the pole.
— Concrete poles deteriorate due to corrosion of the steel reinforcement. As it corrodes, it expands which increases the
amount of moisture that can enter and accelerate the corrosion. An effect of this is spalling, which refers to lumps of
concrete falling off the pole and results in loss of structural strength.
— Steel poles deteriorate through corrosion at the base of the pole below ground level making it hard to detect. Once
sufficiently weak the forces it is subjected to (tensions and weight of the conductors, wind) can cause it to break.
— Crossarms typically rot due to moisture and fungi causing the wood to rot. Often this occurs from the top of the
crossarm where water can pool. It is also common to occur at the point where insulators are attached to the crossarm,
especially in the case of pin type insulators where increased deterioration as water can more easily enter the
attachment point. In particular, the Malaysian hardwood crossarms are thought to be a potential environmental risk
due to fungal growth and their lower durability than other types posing an increased risk of failure.
— Insulators are typically damaged through mechanical stress, such as being hit by objects or vibration. They normally
have longer lives than the crossarms and are replaced with the crossarm or pole. For sub transmission voltages,
deterioration of the insulators can be detected through the presence of corona.
Another key failure mode is external impact. This is typically the result of cars crashing into poles that are located
adjacent to roads. Since this is not a condition based risk, it has been excluded from this analysis.
In general, for poles in good condition, there is a low probability of failure and the risk of failure increases over time as
the poles age and are exposed to environmental conditions. The main consequences of failure are:
— the pole failure can result in a safety hazard as it can fall over and damage property or injure people
— as a consequence of a pole falling, the conductors can break and fall to the ground or remain suspended in the air but
low enough for people or vehicles to make contact with them
— the pole could start to lean over or break at the base but still be held upright by the conductors
— a crossarm failure can result in an outage due to a fault caused by the conductor falling onto the crossarm
— a crossarm failure can also result in a safety hazard if the conductor falls off the crossarm it will remain suspended
by the adjacent poles but at a lower height that may be low enough for people or vehicles to contact them.
As can be seen from the above statements, the majority of the consequences of a pole or crossarm failure are related to
public safety. There are no environmental impacts associated with a pole failure.
POLE TAGGING
Following testing of a pole by the Structured Line approach, a pole is tagged to identify its condition:
— a blue tag indicates that the pole is in an acceptable condition, but the associated assets (crossarms, insulators) or
other attached assets (distribution assets) are showing signs of defects. The severity of the defect is recorded in
Structured Lines
— an orange tag indicates that the condition of the pole is deteriorated and it is suspected to be incapable of supporting
structural design loads. It also is used as a cautionary warning for field crews not to climb. Orange tagged poles are
required to be remediated within 12 months
— a red tagged pole is in a more deteriorated state than an orange pole, is at risk of failure under normal design loads,
and is required to be remediated within 3 months. The red tag also requires an assessment of the probability of the
pole to cause damage to property or injury to a person.
In or around late 2014, Aurora’s approach to tagging poles changed. The change was to tag poles with a limited life (less
than 12 months) as well as those at end of life. Aurora decided to also tag poles with limited life as red as there was no
alternative process at the time. During the period of late 2014 to 2017, there was inconsistent application of red tag
POLE REPLACEMENTS
In 2017, Aurora implemented its Accelerated Pole Replacement (APR) Program which remediated approximately 2,800
poles over the course of a year. The program aimed to reduce network risk as quickly as possible and targeted poles with
known defects, older poles and new discoveries during scoping and investigation phases.
Aurora is also planning a testing program that will use a variety of inspection and testing techniques and technologies,
then testing the actual breaking strength of the poles to assess the accuracy of each method and applicability to Aurora’s
network.
The inspection and testing program being run by Aurora focused on the areas of the network that had high criticality
scores (close to POIs) and old poles. This was appropriate for most effectively managing risk. However, it meant that
some areas of the network had not been subjected to testing under the new regime.
— drone based high-resolution photography of crossarms (and other pole top assets) and overhead conductors with
associated assessment of imagery
— poles that were not tested and were separated from the nearest tested pole by 500m to 1000m
— Dunedin: 248
— Central: 339.
— correct application of the Traditional test, in particular, the aspects of the assessment that can be subjective
— the consistency of each crew as they applied tests using Deuar and Traditional methods across wood and concrete
poles
— the consistency across the different field crews in Dunedin and Central
— Dunedin: Four two-person Delta inspection teams were observed carrying out inspections over the period 13 – 17
August. 25 pole sites were inspected; 23 timber, 2 concrete. This included both Deuar and Traditional testing
procedures
— Central: Four one-person Delta inspection teams were observed carrying out inspections over the period 27-31
August. 14 pole sites were inspected; 9 timber, 5 concrete. This included both Deuar and Traditional testing
procedures.
— wood poles.
Figure 8.5 shows the pole failure data as recorded in GIS. Only the poles identified as having failed in service have been
included in the chart. The data shows that GIS indicates that more poles have failed in service than reflected by the
outage records prior to 2015, but fewer than the outage records since 2015. This indicates that there may have been a
change in the data recording process in GIS.
The GIS data may not be up to date or may have some mis-allocation of the reason for pole replacement, however it
contains the age of the pole when it was replaced so it can be used for analysis of the pole survival rate.
Both data sets indicate a long-term average of 10 poles failing in-service each year as caused by asset deterioration. This
excludes any poles that fail with the cause being identified as due to weather.
The distributions of asset failures were analysed to determine a suitable probability distribution to model the asset failure
rates and to calculate the parameters of those probability distributions. In both cases a Weibull function was found to fit
the curves well. The characteristic age of a Weibull distribution is where 63.2% of all assets have failed. The shape factor
sets how flat or peaky (and skewed) the distribution is. Weibull distributions are commonly used across Australia and
New Zealand in the electricity industry for asset end of life analysis.
The characteristics derived are shown in Table 8.7.
CHARACTERISTIC
POLE TYPE DATA SET SAMPLE SIZE SHAPE FACTOR
AGE
We note that for concrete poles the expected life was unexpectedly short. Based on discussions with Aurora, we
identified that historical replacements may have been undertaken earlier in the poles life than necessary due to the
previous methods applied for assessing pole condition. Based on revised assessment criteria and discussions with Aurora,
we applied a characteristic age of 80 years for concrete poles and 75 years for steel poles with a shape factor of 4.
DEFECTS IDENTIFIED
Table 8.8 shows a summary of the number of defects found on wooden poles that have been inspected using the
Structured Lines app (Deuar or Traditional testing). The percentage of poles with each defect tag is reflected as
proportion of the total poles inspected. The defect rating is based on the worst defect identified on the pole. All defects,
regardless of ranking, are allocated a blue tag.
Table 8.8 Number of wood poles found with defects by defect class
D2 High safety hazard – Does not require immediate action. 533 8.2%
COMPONENT D1 D2 D3 D4 NO TAG
The very top of a wood pole can allow water to be absorbed into the pole and cause rotting and deterioration. Pole caps
can be installed to help prevent this occurring. Table 8.10 sets out the number of poles that have and don’t have pole
caps. The table shows that 53% of poles did not have pole caps, and that without pole caps, poles are more likely to suffer
significant deterioration.
Table 8.10 Wood pole deterioration with and without pole caps
Further analysis shows that of all the defects categorised as D1, 38% are on poles tagged as either red or orange. This
means that 38% of poles with defects identified on the pole tops will be addressed due to other pole integrity issues.
However, there are 62% of poles with D1 graded defects that will remain on the network with an elevated level of risk
unless specifically addressed by Aurora.
LEANING POLES
Inspection of the network identified a large number of leaning poles. This was supported by analysis of the Structured
Lines data, as shown in Table 8.11. Poles that are leaning can indicate an issue with the footing of the pole and can result
in conductor sags being greater than designed reducing clearance to ground or adjacent structures. However, it does not
generally indicate an elevated risk of pole failure and is predominately aesthetic. There is no regulation that requires
poles leaning beyond a specific angle to be rectified and EDBs set their own thresholds.
All the poles that are identified to be leaning greater than 10 degrees were recorded as red tagged in the Structured Lines
data which indicates that Aurora is addressing this defect.
Table 8.11 Leaning poles
PERCENT OF
ANGLE NUMBER MARGIN OF ERROR
FLEET
REPLACEMENTS
As discussed in section 8.2.3, poles can fail testing and be tagged for replacement through three mechanisms:
Table 8.13 shows how many poles were replaced as a result of each of the methods. ‘Multiple’ indicates where more than
one of the inspection mechanisms resulted in a requirement for replacement.
Table 8.13 Driver for replacement
Visual 150 2% 5 1%
Deuar 69 1% 0 0%
Multiple 60 1% 1 0%
The table shows that there are a number of drivers for pole replacement and that the structural strength calculated by
Deuar testing is only one aspect. Further, poles have been more likely to be replaced due to above ground deterioration or
deterioration of the poles components than due to insufficient poles strength.
— The Deuar testing procedures were consistently applied by all teams both in Dunedin and Central for setup, testing
and process, with correct adherence to the training provided, except for one case in Dunedin. In this case, the
lineman used an alternative approach that is common in the electricity industry but is not according to Auroras
procedures. It is noted that the experience level of the teams carrying out assessments varied but was not thought to
affect the testing results.
— 8% of poles were tested using a non-standard procedure: 1 out of 25 the poles in the Dunedin area (4%) was tested
using a process that, although it is common in the electricity industry, was not in accordance with Aurora’s
procedures and 1 out of 25 poles (4%) had unknown issues with data inputs into the Deuar device.
— Inefficiencies were identified with the testing process that limited the number of poles tested per day, including
mobile reception so the Deuar device could operate, and did not take full advantage of reporting other defects
observed on the network, such as defects on nearby poles, while in the field which limits the potential effectiveness
of the inspections. However, the inefficiencies did not impact the procedure followed or create uncertainty with the
results of the testing and inspection.
— When crews were able to carry out the Deuar testing, no normal inspections were carried out post-test in the Dunedin
area, such as excavating around the pole to check for decay. This means potentially beneficial information is not
being opportunistically gathered, limiting the potential effectiveness of the inspections.
— An observation was made at one pole that the placement (orientation) of the Deuar testing device relative to the pole
had an impact on the results. We found that the initial test results were close to the threshold between Medium and
High priority and retesting from a different orientation produced a small change to the results which caused it to fall
Cross-arm 35 63 58 5 161
Cross-arm double LV 4 29 43 0 76
Pole Cap 0 1 4 2 7
The defect rate by tag type as a percentage of the number of crossarms inspected is shown in Table 8.15. The analysis
shows that there is a high defect rate in categories D2 and D3 which indicates poor condition but no immediate action
required.
D2 High hazard – Does not require immediate action. 374 31.2% ±2.2%
Total 876
Given the size of the sample observed compared to the size of the total asset fleet and the percentage of defects identified,
we can provide a confidence interval on a statistical basis. This provides a margin of error around the identified
percentage with a confidence level of 90% that the actual number of defects is within that error band.
Table 8.16 compares the results from the Structured Lines data to the results from the aerial survey. It shows that there is
a much higher defect rate identified from the aerial survey. This is likely to be due to most of the deterioration
mechanisms working from the top of the assets and would, therefore, not be visible from the ground. This result is
consistent with the experience of other electricity business that have changed from a ground-based assessment to using
aerial photography to assess the pole top condition.
We note that Aurora is investigating the use of pole mounted cameras for rollout and become part of the standard
inspection procedures.
Table 8.16 High level comparison between Structured Lines and Drone survey
— multivariate regression using machine learning to derive insights into the data
— conditional probability of failure using the Weibull parameters from Table 8.7
0 0 0 0 0
1409 641 391 155 0
7951 4815 2940 1137 0
3155 1333 758 272 0
1766 1111 1034 592 0
0 0 0 0 0
148 44 5 2 0
10981 2419 254 103 0
2429 607 47 13 0
5886 1410 154 87 0
0 0 0 0 0
1831 1096 817 378 0
7824 4684 3493 1617 0
7874 4714 3515 1628 0
7548 4519 3370 1560 0
0 0 0 0 0
2067 550 65 28 0
8833 2352 277 119 0
8890 2368 279 120 0
8522 2270 267 115 0
— The asset data available from Aurora’s systems and augmented by our field inspections was suitable for the purpose
of this review. We note that the data is not complete and improvements to consistency of the data recorded can be
made. Incomplete asset data presents a risk to effective asset management.
— There are 6,660 poles (12%) in service that exceed their expected life and there are 44,260 crossarms (47%) in
service that are estimated to exceed their expected life based on the age of the pole they are installed on. Crossarm
installation date information is not recorded by Aurora. The large number of support structures that exceed their
expected lives indicates an elevated risk of failure of these assets. Further modelling was undertaken to refine the
assessment of network risk and to identify quantities of high risk poles (2.6%) and crossarms (2.3%).
— A rising trend in supply outages from failed poles prior to 2016 has been arrested in 2017-2018, likely because of the
accelerated pole replacement program.
— The pole inspection program has recently been improved but has not identified all poles that are in poor condition as
it has not yet covered the whole network.
— Crossarms are not inspected adequately and many are in poor condition. Some are categorised as high risk due to
their location relative to population and the probability of failure. Probability of failure was based on results from our
field inspections.
— Malaysian Hardwood crossarms (3.8%) have a shorten life due to fungal growth and need to be replaced.
Note that our analysis focuses on a whole of fleet assessment and identifies expected quantities. Individual assets
requiring remediation will be identified through Aurora’s inspection and testing program.
WSP concludes that support structure poses a moderate to high risk to network reliability and specific assets pose a high
risk to public safety due to their location in populated areas.
Table 8.21 summarises the risks for the support structures fleet and indicates the priority for remediation. The risks
shown in the table cannot be allocated to individual assets and provide an indication of the scale of the risk only. For
instance, the locations and volumes of the Malaysian Hardwood crossarms are not known and the testing to ensure
accurate assessment of pole strength is a fleet wide risk.
We assessed the data availability of this asset class. In undertaking this assessment, we have considered all the
information we obtained from Aurora over the course of the project. Table 9.1 is the data quality summary of the
available information where we took into consideration the ease of available and accessibility of the information.
We found that the available data for distribution switchgear was adequate for the purpose of this review, however, the
accessibility of the data is not straight forward as it is spread over many separate documents and systems including GIS,
spreadsheets and PDF site inspection reports. Items to note are:
— an overall average of 77% of ground-mounted RMUs and switches attribute data was recorded
— no attribute data was available for pole-mounted fuses (i.e. manufacturer, configuration and switch type). Note that
WSP identified the fuse type through inspection for a sample of assets as part of our data validation (see section 9.3)
— across both ground-mounted and pole-mounted switchgear, switchgear type was unknown for 86% of the fleet
noting that approximately 21% of those switches were installed during that last 10 years
— 93% of all attribute data is recorded for reclosers, with 89% of reclosers having the manufacturer recorded and 66%
having the switch type recorded.
— there is inconsistency in the terminology used in the asset data making data harder to use effectively.
This missing information identified could be readily included in the asset register. This would enable improved recording
of fault and outage information as well as enabling Aurora to locate each asset type on the network. Having this
information would allow asset type issues that may emerge to be more easily identified and ensure appropriate
maintenance is undertaken.
In general, while we identified deficiencies in the data which pose a risk to effective asset management, we found that
there was sufficient information available to undertake this review based on a modelling approach.
Ground-mounted RMU
switchgear
Switches
Pole-mounted Fuses
switchgear
Switches
— Pole mounted switchgear, including fuses and air break switches (ABS)
Table 9.2 shows the fleet summary classified by switchgear type for each network. There is a total of 7,896 distribution
switchgear units installed on the network. Due to the larger geographical area, the Central network has 39% more
distribution switchgear compared to the Dunedin network.
Table 9.2 Fleet summary by type
Reclosers 44 16 60
Reclosers and sectionalisers
Sectionalisers 3 0 3
AGE PROFILE
Figure 9.1 and Figure 9.2 show the age profile of assets by switchgear type, which provides an indication of the volumes
of assets approaching the end of their expected lives. The fuses are shown on a separate chart due to the difference in
EXPECTED LIVES
Table 9.3 shows the fleet statistics in relation to expected asset life of the distribution switchgear, and average remaining
life for the different switchgear types. While we have provided the general expected life for the assets, the life achieved
depends on the specific installation location, with a longer life expected for switchgear located inside a building
compared to those located outdoor.
WEIGHTED NUMBER
WEIGHTED WEIGHTED
TYPE AVERAGE EXCEEDING
EXPECTED LIFE AVERAGE AGE
REMAINING LIFE EXPECTED AGE
— It is common for pole-mounted switchgear to fail due to rust, mechanical failure, missing bolts and nuts and loose
parts. Due to the failure modes, the risk of failure increases over time due to age and/or if they are not operated for
long periods. Insufficient or inadequate maintenance will also likely result in a higher probability of failure. WSP has
not seen any evidence to suggest that pole mounted switchgear experience catastrophic or explosive failures on
Aurora’s network. The most common failure mode identified is failure to operate due to seized mechanisms.
— For ground-mounted switchgear, including RMUs, oil-filled switchgear is most common. It is common for this type
of switchgear to fail due to oil leaks, aged fuses, oil ingress and internal arcing which could lead to a catastrophic
failure and has been recently experienced in the industry with specific types of switchgear, Long & Crawford (L&C)
and Statter in particular. In addition, other switchgear of similar vintages that are in the Aurora network have been
known to fail on other networks, including:
— Andelect
— ABB SD
— Reyrolle ROKSS
The main consequence of switchgear failure is typically loss of electricity supply to an area. If the mechanism is seized or
cannot be operated, then the next switch upstream must be operated which will result in a larger outage than necessary.
However, oil type RMUs have recently experienced explosive failures in Australia and New Zealand. The Long &
Crawford type switch contains a fuse that is housed in an oil filled container. Failure of the container can result in an
explosion. This has resulted in fatalities of field crews, but WSP is not aware of any in injury to the public as a result.
On Aurora’s network, the majority of the L&C and Statter type distribution switches are installed indoors. This provides
an improved safety outcome particularly with respect to the explosive failure mode as it provides a physical barrier for
protection of the public.
Equipment 36 78% 23 2 0 11
Deterioration
Equipment Imminent 3 7% 2 1 0
Failure
Unknown 3 7% 2 0 0 1
Weather Winds 2 4% 1 0 0 1
Equipment Faulty 1 2% 1 0 0 0
Manufacture
Weather Rain 1 2% 0 0 1 0
Total 46 100% 29 3 1 13
Figure 9.4 and Table 9.5 show the historical outages caused by fuses that were identified to have not operated correctly.
Fuses that were recorded as having operated as intended to stop the fault are excluded. For example, a cause description
of a ‘Blown fuse’ was excluded as that is the intended operation, however, a cause description of ‘Faulty fuse’ or ‘Burnt
fuse’ was included as it indicates the fuse did not operate as intended and is therefore a failure of the asset.
The chart and table show that there is a consistent number of fuses that fail to act as intended each year, with an average
of 20 per year, but displaying a decreasing trend. The data available does not have sufficient detail to undertake further
investigation to determine if there is a relationship between the fuses that fail and fuse attributes such as type or age,
although EDO type fuses make up 77% of fuses that fail in service.
NUMBER OF LV FUSE
CAUSE DESCRIPTION PERCENT DDO GLASS HRC
OUTAGES UNIT
Unknown 10 5% 7 2 1 0
Weather Rain 2 1% 2 0 0 0
Weather Winds 2 1% 1 0 1 0
Environment Fire 1 1% 1 0 0 0
Equipment Imminent
1 1% 1 0 0 0
Failure
HISTORICAL REPLACEMENT
Figure 9.5 shows the age of distribution switchgear, excluding fuses, at end of life replacement and at failure (replaced
once it has already failed in service). The chart shows that most distribution switchgear is replaced prior to failure
(indicated in the chart as “End of Life”). The in-service failure rate is approximately two distribution switchgear units in
every five-year period. We note that there is a backlog of ABS distribution switches that are tagged as ‘Do not operate’
that are not included in this list.
Although this is a small data set, it was used in the calculation of the survival curve characteristics. The calculated
characteristics were then reviewed against electricity industry experience of these asset types to confirm they were
appropriate for use.
SWITCHGEAR CONDITION
Historically there has not been a regular dedicated inspection and testing program for distribution switches. However
some adhoc testing has been undertaken and a specific program was undertaken in 2017 that inspected 155 RMUs. A
review of the inspection data, available test sheets and the public hazard register found:
— During testing in the last month, Aurora found approximately 50 additional distribution switchgear units that are not
operational. The large number of inoperable switches complicates network operations as it would result in an outage
of a larger area when the next operational upstream switch is opened and poses a risk to network reliability.
— Recloser batteries are built into the recloser and maintained or swapped out based on a programmed time slot. WSP
reviewed the recloser battery list and found 10 reclosers have yet to have their battery replaced as part of the
replacement programme. This poses a risk that the reclosers may not operate when required.
— We identified some evidence of auto-reclosers detecting faults, tripping lines and auto-reclosing, but then failing to
re-trip when the fault remained which can lead to a severe hazard. This was identified in the public safety hazard
register as a high impedance fault scenario that can be difficult for protection devices to detect.
— Inspection results were available for 87 ABB SD type distribution switches. No temperature stress was found, but
three units indicated partial discharge. One switch unit was found to be severely corroded and the external condition
of eight units was found to be moderately deteriorated.
— Inspection results were only available for 1 out of 26 Reyrolle type switches. The inspection results indicated that
there were no signs of partial discharge or problems with high temperatures and the external condition was only
moderately deteriorated. In addition, 23 of the switches have not yet exceeded their expected serviceable life.
— Inspection results were only available for 13 out of 208 L&C type switches. The inspection results indicated that
while there were no signs of partial discharge or problems with high temperatures, one unit had a severe oil leak and
most had low oil levels. The external condition was moderately deteriorated.
The findings above and incomplete inspection and test data related to the L&C, Statter and Reyrolle ROKSS type
switches indicates an elevated risk on the network with respect to distribution switchgear.
DISTRIBUTION FUSES
Aurora is aware of some type issues and deterioration of HV fuses and a number of fuses that have been identified as
unsafe for field crew to operate or remove from service unless de-energised. These fuses are:
— HRC fuses in the Dunedin network on FD-A mounts have been identified as having a type issue where the mount
can break when operated
— Low voltage JW Wedge and Lucy fuses have been identified to pose an elevated risk to worker safety and are
subject to operational controls specifying they cannot be operated while the line/asset is energised.
The failure of an individual fuse has a low consequence comparative to the other asset classes, posing a small risk to
reliability and safety.
— Galleria shopping centre, Morley, Western Australia: An explosion occurred which was associated with the private
electricity distribution network within the shopping centre. Several persons were injured and two died from their
injuries.
— Vector, Auckland: Due to ingress of oil, the L&C fuse switch exploded and oil and internal parts from inside the
switch were spread over 25 meters from the switch. No persons were harm in this event.
WSP note that ageing oil-filled non-arc fault rated distribution switchgear (where arc-fault rating is defined by IEC
62271) is considered to have potential safety impacts. We note that there are industry safety advice notices against this
asset type and recommendations for replacement of oil filled distribution switchgear from a number of industry sources,
including:
— Scottish Power13
12 http://www.hse.gov.uk/foi/internalops/ocs/400-499/oc483_27.htm
13 Scottish Power Express, refence EXP-11-180 – Operational restriction (Oil sludging) L&C t3GF3/T4GF3 and Scottish Power
Express, reference EXP-11-189 SOP 383 Long and Crawford GF3F et al
14 ENA, Autumn 2012 ENA SHE Managers – Review of past asset related incidents
The weight of evidence from in service failures across the electricity industry, and general industry practice, indicates
that this switchgear type is at or approaching its end of life.
Figure 9.6 shows Aurora has 208 L&C units, which is 18% of the RMU fleet
The Statter type switchgear has a similar construction to the L&C type switchgear of oil filled fuse units with cast iron
lids/casing. It is also of a similar age to the L&C units so are found to have the same risk profile. Aurora is aware of the
risk and have put in place a risk mitigation program to mitigate this risk.
INSPECTION FINDINGS
The visual assessment checked 73 units of distribution switchgear in Dunedin and Central Otago. Key findings from the
assessment include:
Ground-mounted distribution switchgear and RMUs:
— Seven ABB RMUs of the 23 inspected have signs of oil leakage with two units having oil below the level mark. we
identified that two of the seven RMUs were not recorded in Aurora’s GIS (used as the asset master data register).
— Some sites show subsidence on the foundation due to movement of soil, cracking in foundations and gaps occurring
between the foundation and the switchgear.
— For external earthing, there is no cable riser protection on the earthing cable which poses a safety hazard should the
earth be damaged. For internal earthing, WSP saw no evidence of improperly earthed equipment.
— Some switchgear that is in poor condition with signs of oil leakage was tagged for a partial-discharge test16.
— We were unable to inspect an L&C unit, however, we inspected two Statter units which are an early modular design
of RMU. They incorporate oil filled fuse compartments enclosed by a cast iron lid/casing which are similar to the
L&C unit. The two units 2 units were age in their mid-50s and had poor physical appearance even though they were
both installed inside a building which provide protection from the environment.
15 Urgent Attention Bulletin, Western Power, 6/2/2015 Operational restriction (L&C /GEC/ALSTOM)
16 We note that in 2017 there were 155 RMUs inspected, included partial discharge testing. Aurora has indicated that the partial
discharge tags may be a historical process and require assessment and removal. The current process requires all RMUs to be tested
for partial discharge prior to operation.
— 25 of the 50 switchgear units inspected have moderate to bad rust on the operating mechanism, especially at the U-
bolt connection on the operating pipe. If not addressed, this can result in the mechanism seizing and resulting in the
switch not operating correctly or becoming inoperable.
— Only 30% of switchgear have dual earthing conductor while the rest are single earthing. Although there is no
requirement for double earthing, it is now common practice for redundancy as broken earth connections have safety
consequences for the field crews. Our site inspection identified 2 locations out of the 50 inspected where the earthing
conductor was a smaller gauge compared to the sizes commonly used at the other locations. Smaller conductors are
not as mechanically strong and there is a slightly elevated risk that they may break, resulting in loss of the earth
connection.
Our inspection identified additional uncertainty regarding the completeness of Aurora’s asset data for this asset class, as
demonstrated by the discovery of two assets installed on the network that were not in Aurora’s asset systems. We also
found that, in general, the fleet appears to be worn and exhibiting end of life signs through the types of defects identified.
Our findings align with the information provided by Aurora that there has not been an established and periodic
maintenance program for this asset class.
In general, this fleet is considered to have an elevated risk of failure of failure, and the L&C and Statter types are found
to have an elevated consequence to safety and reliability when they fail, however, this is mitigated where these assets are
installed indoors which provides a physical barrier that protects the public.
Our site inspections did not identify any obvious deficiencies or faults with fuses and found they correctly installed at
appropriate locations such at distribution transformers and spur lines.
99 155 12 5 0
1754 686 55 15 0
276 49 3 0 0
157 73 0 0 0
70 1 0 0 0
2543 148 0 0 0
1174 57 0 0 0
625 7 0 0 0
— The asset data available from Aurora’s systems and augmented by our field inspections was suitable for the purpose
of this review. We note that the data is not complete and improvements to consistency of the data recorded can be
made. Incomplete asset data presents a risk to effective asset management.
— The distribution switchgear fleet has 1,678 units (21%) exceeding their expected life. This indicates that there is an
elevated probability of failure of these assets and provides an indication of the magnitude of risk on the network.
Further modelling was undertaken to refine the assessment of network risk and to identify quantities of high risk
assets.
— Distribution switchgear has only contributed 8% to the average number of outages on the network between 2013 and
2017 but is displaying an increasing trend.
— A significant portion of the RMU type switchgear inspected (40%) have oil leaks, indicating a deteriorated
condition.
— The L&C type switchgear are at or approaching their end of life and are found to have a high probability of failure.
They have been found to have an explosive failure mode and, hence, can pose a risk to safety. There are a number of
industry safety advice notices related to this asset type. The Statter type switchgear has a similar construction to the
L&C type switchgear of oil filled fuse units with cast iron lids/casing. It is also of a similar age to the L&C units so
are found to have the same risk profile.
— There are three types of fuses: HV HRC fuses, and LV JW Wedge and Lucy fuses, that have identified type issues,
but pose a low risk to reliability and safety. The need to deenergise the LV fuses prior to operation is a risk to
reliability, however, as LV fuses only impact a small number of people the risk is low.
— 77% of fuse failures are caused by DDO type fuses, indicating a possible type failure. However, the impact of
reliability and safety is immaterial
— Batteries in circuit reclosers do not have a regular replacement scheme. This poses risk that the reclosers may not
operate when required.
WSP concludes that distribution switchgear poses a low to moderate but increasing risk to network reliability and
specific assets pose a high risk to worker safety. Table 9.8 summarises the risks for the distribution switchgear fleet and
indicates the priority for remediation.
Table 9.8 Summary of general risks for the distribution switchgear fleet
ABB RMUs 3 Reliability and Safety ABB RMU’s with high and moderate risk.
In undertaking this assessment, we have considered all the information we obtained from Aurora over the course of the
project. Table 10.1 is the data quality summary of the available information where we took into consideration the ease of
available and accessibility of the information.
We found that the available data for distribution transformers was generally good, however, the accessibility of the data
is not straight forward as it is spread over many separate documents and systems including GIS, spreadsheet and PDF site
inspection reports. Items to note are:
— key attributes (service date and ratings) are well populated but 21% of transformers have an unknown manufacturer
associated with them
— condition information is available but spread over a combination of spreadsheets and PDF hand written site
inspection reports making it difficult to use and analyse
— there is inconsistency in the terminology used in the asset data making data harder to use effectively.
This missing information identified could be readily included in the asset register. This would enable improved recording
of fault and outage information as well as enabling Aurora to locate each asset type on the network. Having this
information would allow asset type issues that may emerge to be more easily identified and ensure appropriate
maintenance is undertaken.
In general, we found that there was sufficient information available to undertake this review, although there is
opportunity for improvement that would facilitate good asset management practices.
Table 10.1 Summary of data quality
Ground-mounted Transformer
Pole-mounted Transformer
Voltage Regulators
— ground-mounted transformers
— pole-mounted transformers
— voltage regulators.
Aurora’s network comprises of 7,029 distribution transformers and 13 voltage regulators. Due to the larger geographical
area, the Central network has 65% more distribution transformers compared to the Dunedin network, which has a smaller
number of larger capacity transformers to supply a higher population density. Table 10.2 shows the fleet summary
classified by transformer type for each network. These figures were based on currently in-service distribution
transformers.
Table 10.2 Fleet summary by type and location
Voltage regulators 8 5 13
AGE PROFILE
Figure 10.1 shows the age profile of the transformers and voltage regulators by type and it provides an indication of the
number of assets approaching the end of the expected life.
— For ground-mounted distribution the expected OEM life is typically 35 years and operate at 40% capacity, however
the life of the transformers can be extended with oil maintenance and refurbishment at 40 years and we can expect an
asset life ranging from 55 to 60 years. For our analysis, we would assume an asset life of 55 years.
— With pole-mounted transformers, they are usually much smaller and typically feed farms and smaller local
installations. They are usually operated from 60% to 80% capacity and seldom maintained and are normally replaced
after failure. We expect this type of transformer to have an asset life between 45 to 60 years. For our analysis, we
would assume an asset life of 55 years.
— For voltage regulators, the life is dependent on the technology and the original manufacturer. The life span can be
variable as it may have moving parts (e.g. voltage taps) and the capacitors have a finite life. Typically, they have an
expected life between 35 to 40 years. For our analysis, we would assume an asset life of 35 years.
Table 10.3 Fleet statistics
WEIGHTED NUMBER
WEIGHTED WEIGHTED
TYPE AVERAGE EXCEEDING
EXPECTED LIFE AVERAGE AGE
REMAINING LIFE EXPECTED AGE
Ground Mounted
55 19.9 35.1 79
Transformer
Pole Mounted
55 34.8 20.2 647
Transformer
— For ground-mounted transformers, the common failure mode is usually insulation failure or external factors e.g.
falling debris, ground subsidence or damaged foundation.
— For pole-mounted transformers, the common failure mode is usually insulation failure or external factors e.g. vehicle
collision into the pole, ground subsidence or damaged pole foundations.
Although distribution transformers are robust, the consequence of failure could potentially lead to
— oil spillage
— permanent disability to people in the public, employees or contractors. Distribution transformers are not expected to
explode and internal faults are typically contained within the transformer tank
REPLACEMENT HISTORY
Distribution transformers are replaced at failure and at occasions, depending on condition, aged-transformers are replaced
at the time when the poles are replaced.
The findings from the review of inspection and our on-site inspections are discussed in the following sections.
Approach:
The on-site inspections were a visual inspection on a selected sample of both the pole-mounted and ground-mounted
transformers. Specifically looking for oil leaks, unusual sounds and overheating, ground subsidence, access to the unit
and to ensure the transformer is not covered or a hole dug underneath it.
Inspection of pole-mounted transformers was limited to what could be seen from the ground. We did not conduct
transformer testing as this requires certain parts of the network to be isolated and customers to be interrupted.
Table 10.4 shows the number of outages for each cause since 2009. Asset deterioration contributes 59 (62%) of the 95
outages and a further 9 (9%) were attributed to an imminent failure in the transformer.
Table 10.4 Cause of outages
Unknown 14 15%
Weather Winds 3 3%
Environment Fire 2 2%
Environment Flooding 2 2%
Weather Rain 1 1%
Total 95 100%
UNDERGROUND SUBSTATION
Underground substation assets are often installed in public places and as such can pose a public safety risk. There is also
a safety risk for field crews due to the confined spaces and the older asset types installed, as well as a general risk of
minor flooding because they are located underground.
Calibre Consulting conducted an inspection on 18 underground substations and assigned a condition grade to each
substation between 1 (excellent) to 5 (very poor). Table 10.5 is a summary of the underground substation condition
scores assigned.
17 Note that the data for 2018 is an estimate based on half a year of data for January to July.
Number of Substation 0 14 4 0 0
In March 2018, AECOM18 completed a report with the purpose of assessing the design and cost of replacing the
underground substations. The report referenced the assessments undertaken by Calibre and expanded on those findings to
include a condition assessment of the main electrical equipment of the underground substations. The condition
assessment focused on the age of the equipment but also identified some visual defects including rust, evidence of
flooding and oil leaks. No electrical test results were included. The overall assessment of the electrical equipment
indicated the substations were in good to reasonable condition.
Based on this review, all of the underground substations are perceived to be in good or reasonable condition. For the four
underground substations that are in reasonable condition, there is deterioration evident, however, failure is considered
unlikely in the near future. We note the dissolved gas analysis testing of the transformers in 2017 shows no abnormal gas
generation in these transformers which provides some validation of the inspection.
Aurora has established a program to replace the underground substations to remove the field crew risk caused by
confined spaces which is in line with actions being undertaken by other EDBs in New Zealand.
DISTRIBUTION EARTHING
WSP reviewed a number of test and remediation reports for distribution assets. The reports indicate the that Aurora has
undertaken earthing testing and remediation across distribution asset fleets in both the Dunedin and Central networks
since 2013, with evidence of a large program of works (testing and remediation) from 2014 to 2016.
WSP examined details of distribution earthing during its site inspections around the network. All inspected transformers
have earthing but there is a need for the earth conductor to be fixed to the pole. This is a similar issue with pole-mounted
switchgear. No other issues were identified.
INSPECTION FINDINGS
Distribution transformers are not considered high risk and are generally robust. The visual assessment has checked at
random 25 distribution transformers in Dunedin and Central Otago. Most transformers in rural areas are rated at less than
100 kVA. Higher rating transformers are found in Dunedin and occasionally, mounted on a platform supported by two
poles.
Key findings from the assessment include:
Ground-mounted transformers:
— While some of the inspected transformers have some minor damage to cooling fins, they are generally in good
condition with not much rust.
— Some of the transformers have evidence of oil leakage and it is advisable to monitor them.
— There were no issues with temperature or unusual sounds on the transformers inspected.
Pole-mounted transformers:
— Some of the transformers have oil leakage and it is advisable to monitor them.
0 0 0 0 0
987 577 297 57 0
304 99 26 2 0
171 90 32 6 0
Table 10.7 shows the risk for distribution transformers in the Central network. Two distribution transformers are
considered a high risk to safety due to their age and proximity to the public. There are no transformers in the Central
network that are a high risk to reliability.
10 0 0 0 0
1447 195 20 2 0
1509 393 39 3 0
694 69 4 0 0
— The asset data available from Aurora’s systems and augmented by our field inspections was suitable for the purpose
of this review. We note that these are predominantly run to failure assets so less data is expected to be captured on
asset condition.
— There are 727 distribution transformers (10%) that have exceeded their expected life and, therefore, pose an elevated
risk to the network. Further modelling was undertaken to refine the assessment of network risk and to identify
quantities of high risk assets.
— About 10 distribution transformers (0.1%) fail in-service each year. There is a gradual increasing trend of
transformer failures, which indicates these assets pose an increasing risk to network reliability and safety.
— With some exceptions, distribution transformers are a run to failure asset and present small risks to safety, reliability
or the environment.
— There are 57 distribution transformers in the Dunedin network considered to have a high safety risk due to their age
(as a proxy for condition), capacity and proximity to the public. In the Central network, two distribution transformers
are considered a high risk to safety. There are no transformers in either the Dunedin or Central networks that are a
high risk to reliability.
— There are 328 distribution transformers (4.7%) with a moderate level of risk.
Note that while our analysis focuses on a whole of fleet assessment and identifies expected quantities, individual assets
requiring remediation will be identified through Aurora’s normal inspection and testing program.
WSP concludes that distribution transformers pose a low to moderate risk to network reliability and safety, except for a
few aged transformers in the Dunedin network that pose a high risk. Table 10.8 summarises the risks for the distribution
transformer fleet and indicates the priority for remediation.
Table 10.8 Summary of general risks for the distribution switchgear fleet
— Attributes: We found that the quality of the attribute information for sub transmission lines was good overall. Over
99% of conductor types were recorded in GIS.
— Condition: There were few investigation reports or periodic surveys, but this is not inconsistent with Aurora asset
management approach of 5 yearly detailed inspections and does not indicate poor data.
— Performance: Up to date performance information was available where outages had occurred, however, the sub
transmission line availability records (database of sub transmission lines that had been taken out of service but
without causing an interruption to supply) data was less consistently recorded. Availability data was available from
2000 to 2003 and 2012 to 2017 for Dunedin and 2003, 2012 and 2013 for Central.
Table 11.1 Summary of data quality
OVERALL DATA
ASSET CLASS SUB CLASS ATTRIBUTES CONDITION PERFORMANCE
QUALITY
Criticality is used to describe the consequence of an asset failing in service. The criticality segmentation for sub
transmission lines has been based on safety to public (and linked to that of the nearest pole) as the assets are above
ground, in close proximity to the public and have failure modes that can result in unsafe situations. The consequence of
failure on reliability is considered less due to redundancy on most sub transmission circuits, customers are not affected by
a single incident.
WSP has used a GIS layer for POI provided by Aurora to determine the criticality. The POIs define a spatial location
such as a school, social infrastructure, emergency services, or shopping centres and are used as a proxy for volumes of
foot traffic or population density. Aurora has used GIS to identify the proximity of assets to approximately 18,000 POI’s
identified on their network (residential areas are not included in the analysis).
— copper (CU)
— aluminium (AL)
Figure 11.1 Overhead lines sub transmission age profile by conductor type
EXPECTED LIFE
Table 11.3 shows the weighted average age of the sub transmission lines by type. The expected life of the conductor
varies depending on the material type, the cross-sectional area and distance from the coast line. Table 11.3 shows the
weighted average life and ages summarised by the conductor material type and voltage.
It shows that 33kV copper has the greatest volume exceeding its expected life, driven by 74 km related to the A, B and C
Lines and the remainder predominantly the Port Chalmers/North Valley lines. The ACSR is only slightly older than its
expected life - a third located in Central and two thirds in Dunedin where it is predominately related to the Green Island
and Port Chalmers/North Valley lines. Since many condition deterioration drivers are age related, this provides an initial
view on the risk associated with each asset.
Table 11.3 Fleet statistics
WEIGHTED NUMBER
WEIGHTED WEIGHTED
CONDUCTOR TYPE AVERAGE EXCEEDING
EXPECTED LIFE AVERAGE AGE
REMAINING LIFE EXPECTED AGE
19 The data provided had an age of 111 years for A Line and B Line. This was considered a data error and updated to the same age as
C Line.
— conductor material
— conductor size
The first program was general for all overhead ones and included some sub transmission lines. A second program was set
up to focus on the sub transmission lines for which 20 locations, covering approximately 70 poles, were selected in
Central where the majority of sub transmission overhead lines are located.
In total, approximately 759 poles and approximately 660 spans were inspected.
CORONA SURVEY
Corona surveys were undertaken in Dunedin in 2016 and in Central in 2017 by TransNet. The surveys focused on the
detection of corona discharge. Corona is an indication of deterioration of assets and can cause radio frequency
interference, audible noise and can create corrosive substances when in humid conditions, further damaging the insulators
and conductors. The results from two corona surveys were reviewed by WSP 21,22,23.
RELIABILITY PERFORMANCE
The sub transmission network is in most cases designed to an N-1 level of security, meaning the there are two separate
lines that supply most zone substations. As a result, the network is highly reliable and there are not too many failures
attributed to the asset class. Figure 11.2 shows the performance of Aurora’s fleet. It shows that Dunedin has had one
outage on the sub transmission network that resulted in loss of supply since 2009. For Central, the outages are infrequent
with an increase to 16 outages in 2017.
Note that the value for 2018 is only half a year of outage data from January to July.
AVAILABILITY
While reliability performance examines the number of outages that result in a fault, availability provides insight on how
much time of the year the network is available for supplying energy. The higher the availability the more secure the
network, but networks are typically not 100% available as maintenance must be carried out.
Due to the N-1 arrangement of the sub transmission conductor, a fault on a conductor does not necessarily result in an
outage as the load is transferred to the other conductor and supply is maintained. Therefore, sub transmission conductor
faults are not contained in the outage data records. Availability data was available for 2000 to 2003 and 2012 to 2017 for
Dunedin and 2003, 2012 and 2013 for Central. This provides some insight into the risk of both circuits being out of
service at the same time.
The Dunedin overhead sub transmission had an average availability of 99% with the lowest average being 82% for one of
the lines to Mosgiel ZSS due to a fault in 2001 and extended maintenance in 2014. However, since there are three lines
supplying Mossgiel ZSS there was no outage.
The Central overhead sub transmission lines had an availability of over 99% with the lowest being 97% for the
Cromwell – Wanaka No 1 line due to the upgrade to 66kV.
The data showed that the typical duration required to rectify a fault on the overhead sub transmission network ranges
between a few hours and up to 4 days.
SAFETY
There was a total of 11 instances where the sub transmission lines caused either a safety incident by falling to the ground
or were reported in the public hazard register. These all occurred between 2006 and 2017.
— six instances in the outage data (from 2000 to 2018) regarding lines falling to the ground and causing an outage
— five instances in the public safety register (from 2015 to 2016 and mid-2017 to mid-2018) involving 33kV lines
causing fires.
VERTICAL SEPARATION
The survey results from the vertical separation survey described in section 11.3 are shown in Table 11.4
Table 11.4 Sub transmission circuit separation distance
NZECP 34:2001 requires the separation between 11kV and 66kV circuits to be a minimum of 2 metres. It also allows for
circuit separations to be lower than the specified minimum if a detailed engineering study of the maximum over voltages
and conductor motion establishes that there will be no adverse effect from an installation with less clearance.
Table 11.4 shows that the 66kV line does not comply with the current minimum requirement of 2m and an engineering
study to support the reduced separation was not available from Aurora. It is noted that Circuit UC66 was originally a
33kV circuit that was uprated to 66kV. The 33kV circuits comply with the requirement of minimum 1.2m clearance.
GROUND CLEARANCE
As part of the inspection the height above ground of the lowest point of 10 spans on the UC66-1 sub transmission line
were measured. The measurements were to the 66kV line, but no measurement was taken for the 11kV line strung
underneath the 66kV line.
The assessment found that the 66kV line height varied from 8.0m to 10.3m. We note that the vertical separation of the
66kV and 11kV lines at the crossarm is 1.8m, so it is likely the lowest point of the 11kV line is 6m above ground. The
locations measured to be 8m were not accessible by a vehicle, so they are likely to comply with the minimum height
requirements of 5.5m in this situation.
However, upon review of the pole heights on the sub transmission line support structures, we found that 3.9% have a
height above ground of 8m or less. This data indicates it is likely the sag in the span between poles will result in the line
having a clearance of less than 6.5m and possibly less than 5.5m in some cases. This was not quantified through surveys
as part of this review.
In the area, changing land use has meant that land previously used for farming animals is now being converted to other
forms of agriculture that utilise different types of larger machinery. Hence, the height of conductors above ground may
present a risk.
CONSTRUCTION ISSUES
The Cromwell to Wanaka 66kV lines (UC66-1 and UC66-2) both have construction issues from when they were
upgraded from 33kV to 66kV lines. For example, the pins are not centred in the insulator, hole bores may not be vertical
(possibly due to being bored on site), the base of the insulator is wider than the crossarm, and crossarms are not square.
This has resulted in insulators leaning over which is likely to reduce their serviceable life. This issue is known to Aurora.
CORONA
The TransNet Corona survey identified that 27% of sub transmission poles across the network had corona present:
— 89% of poles showed corona present, and 9% have strong corona present in Central
— 10% of poles showed corona present, and 1.5% showed strong corona present in Dunedin
— deterioration mode identified as Aeolian vibration of Line Guard/Armour Rods, and Hand Ties at connection to
insulators
The survey shows general deterioration of parts of the sub transmission network. The rate of deterioration is not
identified.
VEGETATION MANAGEMENT
Evidence was provided to support active identification, notification and action taken to address situations where trees
infringe on sub transmission line clearance zones. This included a sample of first cut notices as well as follow up notices
of the hazard posed by the customers’ vegetation. The dates of notices sighted ranged from 2006 to 2018 and covered
both Central and Dunedin. The notices identified a range of clearances of the trees from touching the conductor in some
cases up to encroaching in the clearance zone.
ENERGY AT RISK
Sub transmission lines are generally configured in an N-1 arrangement, so loss of a single line will not result in loss of
supply. The probability of a dual contingency, where both sub transmission lines are lost concurrently, is very low, as
seen in the outage data and availability data.
The availability data shows that the fault restauration times for overhead sub transmission lines has typically required a
duration of several hours to restore supply with a maximum of 4 days. Hence, the consequence of a dual supply outage is
very low due to the quick restoration.
SAFETY
Ensuring network safety is an important driver for the sub transmission lines. Overhead lines are located in publicly
accessible places and there is evidence of sub transmission lines falling to the ground. However, the overhead sub
transmission network is predominately located in rural areas in the Central network, which reduces the possible safety
impact of the line.
Due to the limitations of the data available, the safety risk for overhead conductors was determine based on the average
population density of the feeder to determine a relative risk index.
ENVIRONMENT
Overhead sub transmission lines do not pose a risk to the environment. The risk was not assessed.
23 0 0 0 0
48 0 0 0 0
67 0 0 0 0
6 0 0 0 0
0 0 0 0 0
0 0 0 0 0
3 0 0 0 0
147 0 0 0 0
115 0 0 0 0
117 0 0 0 0
— The asset data available from Aurora’s systems and augmented by our field inspections was suitable for the purpose
of this review. Only performance data was found to be incomplete, i.e. sub transmission line availability is not
recorded.
— On average, one sub transmission line per year causes either a safety incident by falling to the ground or is reported
in the public hazard register. This indicates that, although these assets can pose a risk to public safety, the events are
infrequent and the information available indicates that the protection operated for the incidents where the conductor
made contact with the ground.
— The A, B and C sub transmission lines in Dunedin are in poor condition and there is a higher probability of failure on
some sections (the A and B Lines that are in closer proximity to the coast and 111 years old). However, the
consequence of failure is low due to the redundancy in the network and because the sub transmission lines are
located away from highly populated areas.
— The Cromwell to Wanaka lines have a number of issues including vertical separation between the 11kV and 66kV
circuits of 1.8 m compared to the requirement for separation of 2m. In addition, there are a number of issues relating
to its construction.
— It is likely there are spans of the sub transmission lines that do not comply with the minimum height requirements.
This was not quantified as part of this review but is indicated by the asset data.
WSP concludes that sub transmission lines pose a low risk to network reliability and safety. Table 11.8 summarises the
sub transmission line risks and indicates the priority for remediation.
— Outage database
In undertaking this assessment, we have considered all the information we obtained from Aurora over the course of the
project. Table 12.1 is the data quality summary of the available information where we took into consideration the ease of
available and accessibility of the information.
We found that there is generally good information regarding the distribution line attributes and information from GIS,
however:
— There is no condition data available for this asset class as there is no dedicated inspection or testing program
— Performance data is captured in the outage management system, however, the fault locations are allocated to the
nearest distribution transformer and feeder numbers are not consistently recorded. This limits the ability to use the
performance data to identify the risk on the network by different conductor types. Important items to note are:
— key attributes for both distribution line and LV lines are largely populated with 0.2% (17) and 5.8% (2,076)
entries without a conductor type respectively
To assess the risk of this asset we applied a modelling approach to utilise the data available. By taking this approach, we
found that there was sufficient information available to undertake this review.
Table 12.1 Summary of data quality
Criticality is used to describe the consequence of an asset failing in service. The criticality segmentation for distribution
overhead lines has been based on safety to public (and linked to that of the nearest pole) as the assets are above ground,
in close proximity to the public and have failure modes that can result in unsafe situations. The consequence of failure on
reliability is considered less with only a small number of consumers typically impacted for LV and HV circuits. Due to
redundancy on most sub transmission circuits, customers are not affected by a single incident.
WSP has used a GIS layer for POI provided by Aurora to determine the criticality. The POIs define a spatial location
such as a school, social infrastructure, emergency services, or shopping centres and are used as a proxy for volumes of
foot traffic or population density. Aurora has used GIS to identify the proximity of assets to approximately 18,000 POI’s
identified on their network (residential areas are not included in the analysis).
— Aluminium (AL)
— Copper (CU)
— Steel (ST).
The fleet comprised of 49% (2,313 km) distribution lines, 22% (1,045 km) LV lines and 28% (1,326 km) LV street
lighting. Majority of distribution lines are made from ACSR whereas Aluminium is predominantly found in LV line.
Table 12.212 shows the composition of the network by conductor type and length.
Table 12.212. Fleet summary (length, km)
LV STREET
MATERIAL HV LINE LV LINE TOTAL
LIGHTING
AGE PROFILE
Figure 12.1 shows the age profile for distribution lines and LV with the majority of the conductors within their expected
life of 60 years, which is common in the industry. The expected life is dependent on the installation condition and the
location of the cable from marine environments.
EXPECTED LIFE
Table 12.4 shows the weighted average age of the distribution lines by material type. The expected life of the conductor
varies depending on the material type, the cross-sectional area and distance from the coast line.
It shows that copper conductors have the greatest volume exceeding its expected life, driven predominantly by
conductors located in the Dunedin network with a total length of 309 km. ACSR also has a large proportion, 162km, that
is exceeding its expected life. Approximately 15% of the steel conductor fleet has exceeded its expected life.
24 The permanent elongation of the conductor caused by the tension it experiences due to its installation.
— conductor size
— age of conductors
In total, approximately 759 poles and approximately 660 spans were inspected.
RELIABILITY PERFORMANCE
Figure 12.2 shows the historical outages caused by the failure of overhead distribution lines. The data shows an
increasing trend in outages caused by overhead distribution conductor. The trend line has a reasonable fit to the data.
The overhead distribution conductor class has the largest impact to network performance, contributing an average of 33%
of the outages from 2013 to 2017. The outage data shows evidence of an increasing trend in the number of outages
caused by this asset class. This indicates that modelling the asset based on a metric related to reliability is appropriate for
assessing the risk of this asset class.
There were 166 incidents recorded in the outage records where a conductor was identified as having fallen to the ground
because of deterioration. When the impacts of weather and vegetation are included, the number increases to 404. This is
an average of between 10 and 25 incidents per year. The public safety register, that was in use consistently from 2014 to
2015 and then re-established in mid-2017, also identified as similar number of incidents annually.
Bare 3 2 2 12 19
Ins 1 0 0 1 2
Unknown 0 2 53 68 123
PVC 0 0 25 56 81
VEGETATION MANAGEMENT
The trend analysis in Figure 12.2 only shows the impact of asset deterioration on the asset performance. However,
vegetation causes the majority of outages related to overhead distribution line. Evidence was provided to support active
identification, notification and action taken to address situations where trees infringe on distribution line clearance zones.
This included a sample of first cut notices as well as follow up notices of the hazard posed by the customers’ vegetation.
The dates of notices sighted ranged from 2006 to 2018 and covered both Central and Dunedin. The notices identified a
range of clearances of the trees from touching the conductor in some cases up to encroaching in the clearance zone.
AL Heavy 0.2 0%
AL Light 2.1 0%
CU Heavy 0.8 0%
ST Light 34.6 7%
The failure rates observed also align with the sub class of conductors that are make up the volume of conductor
exceeding its expected life, with the dominant types of conductor that exceed their expected lives are light copper (60%)
and light ACSR (31%). This supports an age-based modelling approach by asset material type and weight for assessing
risk of failure.
DRONE SURVEY
Our drone survey was undertaken to assess for any excessive damage that would indicate high risk of failure and external
visible deterioration. The results of the drone survey demonstrated that there were no major external/visible defects on
the conductors. Some signs of external rusting were observed and some minor damage to conductors at the attachment
point to the insulator was observed.
Minor rust 9
Deteriorated connector 4
Weathering on conductor 1
2 3 0 0 0
72 108 2 2 0
512 689 13 7 0
289 308 14 11 0
182 195 4 4 0
0 0 0 0 0
43 27 0 0 0
769 159 0 0 0
541 163 0 0 0
397 163 0 0 0
— The asset data available from Aurora’s systems and augmented by our field inspections was suitable for the purpose
of this review and the assessment approach undertaken. We note that the data is not complete as inspections are not
undertaken consistently and outage data does not capture specific conductor material types. Incomplete asset data
presents a risk to effective asset management.
— There are 10 to 25 public safety incidents per year related to distribution overhead line conductors. This asset class
also contributes the largest impact to network performance, with an annual average of 33% of the outages from 2013
to 2017. The outage data indicates an increasing trend in the number of outages caused by this asset class.
— The HV network consists of mainly ACSR conductor while the LV network consists mainly of copper conductor.
There are 309 km (12%) of copper conductor, 162 km (11%) of ACSR conductors and 35 km (15%) of steel
conductor that are currently exceeding their expected life.
— A common failure mode for this asset class is failure of the conductor by way of corrosion or fatigue, both of which
are related to age. Aurora does not have a dedicated inspection and testing program for overhead conductors but
undertakes visual inspection on an opportunistic basis when inspecting other assets as part of other maintenance
tasks. The evidence examined suggests that ACSR and copper conductor with a cross sectional area of less than
100 mm2 have the highest failure rates.
— Aurora has recorded 225 instances where conductors did not meet the minimum safe heights above ground outlined
in NZECP 34:2001.
WSP concludes that distribution overhead lines pose a moderate risk to network reliability and safety, mostly due to their
relatively high failure rate but low consequences to public safety when they fail. There are some conductors located in
Dunedin with a higher consequence due to their location in densely populated areas. Table 12.10 summarises the
distribution overhead line risks and indicates the priority for remediation.
Table 12.10 Summary of distribution overhead line risk
We found that the quality of the information varied depending on the source. The GIS data contained cable attribute
information for all cables and was found to be complete. However, the inspection and testing data did not contain a
comprehensive set of cable test results or records of oil leaks. The performance of the cables was not captured in the
outage data due to the redundancy of the network, so outage and fault records were not available.
Important data deficiencies:
— Condition: there were no testing records for Neville Street, Willowbank or Smith St zone substations. Inspection
records were completed
— Condition: all historical test and inspection data is only available in scanned pdf format and it is not well organised
in a structured manner. This makes it difficult to identify issues or trends across the fleet
— Performance: there were no inspection or issue investigation records available for faults or specific failure modes
that have been identified by Aurora. Data has been captured at a high level in some reports such as the AMP. Due to
the N-1 configuration, a cable outage does not necessarily result in an outage and, hence, the fault data is not
captured in the outage records
— Performance: circuit availability data was not complete or up to date. Data was available from 2000 to 2003 and
2012 to 2017 for Dunedin and 2003, 2012 and 2013 for Central.
A summary of our findings in regard to data quality is reflected in Table 13.1
PILC
Oil insulated
Zone substation
Gas insulated
XLPE
The older oil and gas insulted cables reflect the technology of the day and require fluid pressure to ensure insulation
properties are maintained. Leaks can result in loss of insulation performance and can lead to failure. PILC is a proven
technology that has been commonly used in electricity networks since around the 1950’s and XLPE is a more modern
design of cable. Neither PILC or XLPE use fluid to maintain insulation properties.
While oil insulated and gas insulated cables are a type of PILC cable, the need to maintain fluid pressure separates the
type of construction, failure modes and expected serviceable life. For clarify, we refer to them as Oil and Gas insulated
cables to clearly separate them from PILC cables which do not require fluid pressure.
Table 13.3 shows the location (zone substation) of the each of the gas and oil insulated cables by type and length.
Total 60.8
AGE PROFILE
The age profile of assets in Figure 13.1 shows the relative age of cable by type and the periods of time where each
technology was dominant. It highlights the large volume of gas and oil cables compared to PILC and XPLE.
PILC cables generally have a long life. The cables installed to supply Kaikorai Valley ZSS and Ward St ZSS make up
80% of all PILC cables and are the oldest cables on the network. The younger PILC cables are predominantly short
sections installed to replace deteriorated or faulted parts of these circuits.
25
Note: total may not appear to add up due to rounding
EXPECTED LIFE
Table 13.4 shows the weighted average age of the sub transmission fleet by cable type. The expected life is based on
nominal design life and Aurora’s current expectations.
Table 13.4 Cable fleet statistics
— Oil and Gas insulated cables: damage to the external sheath allows the insulating medium to leak out which reduces
the cable insulation and enabling the cable to fault. The damaged sheath also allows water ingress which can cause
further deterioration
— Gas insulated: water ingress at joints causes the bronze tape to corrode and exposing the lead sheathing to high
pressures. The lead eventually punctures allowing the gas or oil to escape, with the potential for moisture to be
absorbed into the cable. Eventually the insulation will deteriorate and result in failure
— PILC: PILC uses oil (wax) impregnated paper as insulation. This is different to oil insulated cables that require oil to
be pumped in under pressure. Aurora has identified a failure mode where oil drains from the paper insulation of
PILC cables where the cables have been installed on steep hills. This reduces the insulation properties and has led to
fault on the sub transmission cables to Kaikorai Valley.
— Joints (including terminations): these are a common location of failure for cables and there are multiple causes of
failure including: ground movement exerting physical stress on a joint; moisture ingress damaging insulation; poor
workmanship when installing the joint; overheating due to overloading or the joint conductor connection becoming
loose. The failure can be a phase to phase or a phase to ground fault which in some circumstances can result in fire.
An alternative driver is cause by a sudden electrical shock to the cable when it is already in a deteriorated state. This can
occur when a cable experiences a fault current or when there is a sudden increase in load, such as when a second circuit is
taken out of service. Aurora has identified this to be the cause of damage to joints of gas cables. The implication of this is
that the probability of a second contingency event, where both cables suffer an outage at the same time and supply is lost,
could be higher than expected due to this failure mode being triggered by the outage of the first circuit.
The third main failure mode is external impact. This is typically the result of cables being dug up due to excavation
works and is normally mitigated through separate cable routes. However, the sub transmission cables in Aurora’s
network have both cables installed in the same trench with concrete slabs on top for mechanical protection. This
arrangement results in a slightly elevated risk of both cables being taken out of service at the same time. In this case,
cables are primarily vulnerable to common mode failure due to soil liquefaction during earthquakes.
In general, for cables in good condition, there is a very low probability of both circuits losing supply at the same time.
The main consequences are:
— possible momentary loss of supply during changeover/switching if the primary bus of the zone substation is run as
two separate sections
— should a second contingency occur, there could be loss of supply for extended periods of time. This is mitigated
through load transfers at the distribution voltage level
— minor environmental risk from leaking oil. The insulating oil used is not classified as hazardous, it is insoluble in
water and is biodegradable.
— visual inspection and monitoring of the gas and oil pressure of cables and condition of alarms. Evidence was
provided to support a consistent program with a cycle of approximately 6 weeks
AVAILABILITY
While reliability performance examines the number of outages that result in a fault, availability provides insight on how
much time of the year the network is available for supplying energy. The higher the availability the more secure the
network, but networks are typically not 100% available as maintenance must be carried out.
Due to the N-1 arrangement of the sub transmission cables, a fault on a cable does not necessarily result in an outage as
the load is transferred to the other cable and supply is maintained. Therefore, sub transmission cable faults are not
contained in the outage data records. Availability data was available for 2000 to 2003 and 2012 to 2017 for Dunedin and
2003, 2012 and 2013 for Central. This provides some insight into the risk of both circuits being out of service at the same
time.
The Dunedin underground sub transmission had an average availability of 98% across all circuits from 2000 to 2003 and
2012 to 2017. There was volatility in the annual availability per circuit, but no distinct trend was identified. The
predominant reason for unavailability was maintenance and testing. There were 29 faults recorded between 2000 and
2003 and two faults recorded in 2012 and 2013. The N-1 arrangement means there has not been any outages attributed to
the sub transmission cables.
The Central sub transmission network has predominantly overhead lines with only small sections of underground cable.
The performance of the underground cable sections was not separable from the overall circuit information and, therefore,
the availability of these asset could not be assessed.
The restoration times for faults were an average of 5 days with a maximum time of 33 days.
TESTING RESULTS
WSP undertook a review of the inspection and testing records available for the sub transmission cables. In total, 14 out of
66 (21%) of the cable test records identified some level of defect with the cables. Of these some were major defects,
including severe oil leaks at North City No 2 cable and failed sheath tests, and minor defects such as minor items
requiring replacement. Table 13.5 sets out the defects identified in the sub transmission cable fleet.
Alarms and gauges Multiple Minor defects requiring minor asset maintenance or replacement
Gas cable joints Multiple Gas Corrosion of bronze tapes used for the joints of gas insulated cables as
a result of moisture ingress. This has resulted in annual failure of gas
pressure cables during the past 20 years.
North City No 2 Multiple Oil Oil leak identified at rate of 57 litres per month, total of 4,274 over the
6 year period 2009 to 2015. The leak has stopped, however, the
location and cause of the leak were not found or identified.
Kaikorai Valley Multiple PILC Oil draining from paper, decreasing insulation and resulting in a fault
(identified by Aurora)
Kaikorai Valley Multiple PILC Evidence of 10 defects which required replacement of a cable segment
on KV No 1 and 12 defects on KV No 2 over a long period of time.
St Kilda No 1 and 2 2013 Oil Required 5 minute ‘dry out’ before passing sheath test
St Kilda No 1 and 2 2018 Oil Required 15 minute ‘dry out’ before passing sheath test.
East Taieri 2017 Oil Low oil identified, indicating an oil leak in the cable
SAFETY RISK
These cables are buried underground and not accessible to the public. There have not been any identified instances of the
sub transmission cables causing a public safety hazard, nor of excavators digging up the sub transmission cables.
The safety risk is found to be Insignificant.
ENERGY AT RISK
The consequence of a cable failure has been determined by the energy at risk. The energy at risk was calculated using the
load characteristics for the zone substation and calculating the energy that would not be supplied to customers if both
sub transmission cables failed at the same time and required one month to be repaired, based on maximum repair time
identified in the availability data. The total energy was then multiplied by the VoLL. The analysis took into account the
zone substation load and transfer capability.
Five of the Dunedin zone substations are located in areas where there is sufficient capacity to transfer load away via the
distribution (6.6kV) network to restore supply and mitigate the extent of the outage experienced. The transfer capacities
for those substations is equal to, or greater than, the demand on those substations. This reduces the consequence of failure
of these circuits which reduces the total risk and, therefore, reduces the priority for remediation. These substations are:
Neville St, Smith St, Mosgiel, Kaikorai Valley and Ward St.
The probability of failure is a quantitative assessment based on the cable type and age using a survival curve based on the
Weibull probability distribution. Due to history of defects and recent performance of these cables, the expected life was
reduced to reflect that these cables are exhibiting end of life signs through sheath test failures, leaking of oil and
problems with joints. The expected life for PILC, Oil and Gas type cables was reduced to 70 years, based on experience
in other electricity businesses and evidence obtained from the investigation into the asset defects. The issues associated
with individual cables were considered when assessing the prioritisation of the risks
Since the network is built with N-1 redundancy, a second contingency event is required to cause any actual loss of
supply. However, as noted in section 13.2.2, experiencing a fault current or the full load of the substation can cause
damage to the aged cables, particularly those with gas or oil insulation. This results in the probability of a second
contingency being increased as a result of the initial event.
Table 13.6 Unweighted energy at risk assessment by cable
ENERGY AT
ZONE SUBSTATION TYPE VOLTAGE LENGTH (KM) AGE
RISK ($’M, 2018)
ENVIRONMENTAL RISK
The environmental impact of these cables is caused by oil leaking through damaged sections of the sheath or at joints and
terminations. Examination of the inspection and test records identified that a significant amount of oil can leak out of the
cable and into the environment. Between 2009 and 2015 4,274 litres leaked from North City No. 2 cable. Currently this
cable is not leaking.
Although only one oil leak event was identified by Aurora as having been deemed an environmental incident, the
response to the incident as descried in Table 13.7 highlights the significance of the impact and how seriously it is taken.
Any financial penalties of the incident have not been provided to WSP.
We note that the current type of insulating oil used is not classified as hazardous, it is insoluble in water and is
biodegradable, hence minimising the environmental impact. However, there is no information regarding the types of oil
that have previously been used and that may still be contained within the cables.
Table 13.7 Environmental incidents
North City Underground Oil Detection of loss of oil Contact was made with the Otago Regional Council and
Filled Cable - 2015 pressure which suggested they were advised of the issue. A programme of testing
that oil was leaking from the was instigated to discover the location of the leak. This
cable. included thermal imagining. The leak stopped by itself,
however the location or cause of the leak were not
identified.
0 0 0 0 0
0 0 0 0 0
44 17 5 0 0
2 3 0 0 0
5 0 0 0 0
Table 13.9 Sub transmission underground cable risk matrix for Central
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
7 0 0 0 0
9 0 0 0 0
— The asset data available from Aurora’s systems was suitable for the purpose of this review and the assessment
approach undertaken. We note that underground cables are not routinely inspected as they are directly buried in the
ground, but testing has been undertaken on the oil and gas cables on a regular basis. There were no test records for
XLPE and PILC cables.
— No loss of supply has been attributed to a failure of a sub transmission underground cable. Since the sub
transmission underground cable network is built with N-1 redundancy, a second contingency event is required to
cause any actual loss of supply. Average availability of the cables is 98%, with the predominant reason for
unavailability being maintenance and testing.
— There have not been any identified instances of the sub transmission underground cables causing a public safety
hazard.
— The available test records identified a number of recurrent sheath integrity failures, indicating a deteriorated
condition.
— 17 km of cable that has been assessed as having a higher risk of failure is comprised of the connection to Neville St
(10.7 km) and Smith Street (6.2 km) zone substations. As part of the Neville St decommissioning project, the
associated cables (10.7 km) will be decommissioned, removing this risk.
— North City cables pose a moderate risk due to the limited load transfer available and the condition of the cable
increasing risk of failure. There was a significant oil leak on the North City No. 2 cable, however, the leak stopped in
2015.
Kaikorai Valley (PILC with history PILC cable with evidence of a high number
5.7km Reliability
of faults) of historical failures. This is a Low risk.
— defect data
In undertaking this assessment, we have considered all the information we obtained from Aurora over the course of the
project. Table 14.1 is the data quality summary of the available information where we took into consideration the ease of
available and accessibility of the information.
We found the attribute data for underground distribution cables was generally quite good, however the accessibility of the
data is not straight forward as it is spread over many separate documents and systems including GIS and spreadsheets.
Important items to note are:
— key attributes for both HV and LV underground cables are largely populated with 0.2% (16) and 8.2% (2,262)
entries without an insulation type respectively
— there is no age data available for cast iron pothead, including installation and removal dates, but they all have GIS
coordinates and 70% of them also have the street name recorded.
Distribution cables are not considered a critical asset for this review. As a result, we found that there was sufficient
information available to undertake this risk assessment based on a modelling approach.
Table 14.1 Summary of data quality
HV cables1
ASSET
ASSET GROUP ASSET CATEGORY UNITS DUNEDIN CENTRAL TOTAL
CLASS
The asset fleet also includes potheads, which are used where cables exit the ground and transition to overhead lines. They
are located at the top of poles. Cast iron potheads are a sub category of the pothead fleet. There are 455 cast iron potheads
on the network, 385 high voltage and 70 low voltage, and are all located on the Dunedin network.
The age profile of assets in Figure 14.1 shows the relative age of assets and cable types. It provides an indication of the
volumes of assets approaching the end of their expected lives.
Table 14.3 shows that 9.5% of the PILC type HV cable and the entire section of HV submarine cable exceed their
expected lives, indicating an elevated risk of failure of this asset type. There is also 4% of LV cable that has exceeded its
expected life.
— XLPE: water ingress into the cable at points of electrical stress and where the external sheath has been damaged
causes ‘treeing’. The treeing extends along the cable and damages the insulation until it is insufficient and results in
a failure
— PILC: PILC uses oil (wax) impregnated paper as insulation. This is different to oil insulated cables that require oil to
be pumped in under pressure. Aurora has identified a failure mode where oil drains from the paper insulation of
PILC cables where the cables have been installed on steep hills.
— Joints (including terminations): these are a common location of failure for cables and there are multiple causes of
failure including: ground movement exerting physical stress on a joint; moisture ingress damaging insulation; poor
workmanship when installing the joint; overheating due to overloading or the joint conductor connection becoming
loose. The failure can be a phase to phase or a phase to ground fault which in some circumstances can result in fire.
The second main failure mode is external impact. This is typically the result of cables being dug up due to excavation
works and is normally mitigated through separate cable routes and mechanical protection or identification.
The main consequences of distribution cable failures are loss of supply until the cable is repaired. In urban areas, supply
may be able to be restored through network switch in some cases.
Where cables are dug up during excavation, there is the risk of electrocution if the excavation equipment penetrates or
damages the external sheath and insulation.
Cast iron potheads have been identified to have an explosive failure mode that can result in parts of the cast iron housing
falling to the ground, posing a safety risk to the public. The failure mode is age related and caused by moisture ingress
into the unit following planned outages. We note that Aurora has an established program to remove cast iron pothead
from the network.
RELIABILITY PERFORMANCE
Figure 14.2 shows the number of historical outages caused by the failure of underground distribution lines. The data was
filtered to only include underground distribution lines that had failed in service due to defective equipment, including
both cables and potheads. The chart shows that there is very volatile performance and there is no clear trend. However,
the HV cables asset class was identified to make the fourth highest contribution to network performance.
Figure 14.3 shows the performance of the pothead fleet. It demonstrates that there isn’t a strong trend of outages, but
there is a long-term average of 2 outages per year. Only one of the faults was specifically attributed to a cast iron pothead
and only one was due to a cause other than defective equipment.
26 Note that the data for 2018 is an estimate based on half a year of data for January to July
Table 14.4 shows the number of outages for each cause since 2009. Equipment deterioration contributes 89 (85%) of the
105 outages and a further 5 (5%) were attributed to equipment imminent failure. Potheads are included in this outage data
Table 14.4 Cause of outages
Unknown 7 7%
Environment Flooding 1 1%
Environment Vibration 1 1%
0 0 0 0 0
3 0 0 0 0
234 31 0 0 0
100 16 0 0 0
166 40 0 0 0
0 0 0 0 0
0 0 0 0 0
68 7 0 0 0
227 53 0 0 0
754 304 0 0 0
Table 14.7 Distribution cable cast iron pothead risk matrix for Dunedin
0 0 0 0 0
127 55 127 145 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
— The asset data available from Aurora’s systems was suitable for the purpose of this review and the assessment
approach undertaken. No regular testing or maintenance program exists for distribution underground cables and,
therefore, there is very little asset health information, specifically in the areas of condition and performance data. A
modelling approach was applied to assess the probability of failure using the best asset data available.
— HV distribution cables asset class causes 11% of the network outages, the fourth highest contribution out of the asset
classes. Most outages in this asset class are recorded as being caused by asset deterioration.
— Approximately 10% of PILC cables and the entire section of HV submarine cables exceed their expected life and,
therefore, represent an elevated risk of failure for this asset type.
— Cast iron potheads were identified to present a public safety risk because they are installed on poles and is it possible
for their failure mode to affect public safety. Aurora has a program in place to remove these from the network.
— The dominant risk posed by distribution cables is related to network reliability. However, each cable generally
supplies a small number of customers so the impact of each individual cable failure is low.
WSP concludes that distribution underground cables pose a low risk to network reliability and an insignificant risk to
public safety and the environment. However, cable terminations in the form of cast iron potheads pose a moderate to high
risk to public safety in the Dunedin network area. Table 14.8 summarises the distribution underground cable risks and
indicates the priority for remediation.
Table 14.8 Summary of distribution underground cable risk
We found that the data held by Aurora for transformers is good. However, the accessibility of the data is not straight
forward as it is spread over many separate documents and systems including GIS, spreadsheets and PDF site inspection
reports. Important items to note are:
— transformer attributes are all known, but spread over several data sources
— condition information is available, but spread over a combination of spreadsheets and PDF hand written site
inspection reports
— the maintenance schedule does not include four tap changers (two zone substations)
— Bushing attributes are not recorded, making the identification of any systemic issues difficult (issues being oil seal
failure in 33kV solid core bushings, base condition reference for 66kV bushings). Considered a low to modest risk.
— load duration data was not available for all zone substations due to the recent change of system. We do not consider
this a significant issue as it is a temporary result of changing systems. The data will become available with the new
system
— attribute and condition information about the bushings was not recorded.
Overall, we found the information for transformers to be appropriate for the analysis undertaken and to allow us to
identify and prioritise the areas of risk on the network. Table 15.1 summarises the data quality.
Transformers
Tap changers
Zone substation
Bushings
Bunding
— tap changer
— bushings
— bunding.
The impact on network risk of each of these components are discussed below.
TOTAL TOTAL
NETWORK REDUNDANCY 0-5 5-10 10-15 15-20 20-25
ZSS TF’S
Central N 11 2 - - - 13 13
Central N-1 1 2 2 1 2 8 16
Dunedin N 2 - - - - 2 2
Dunedin N-1 - 2 4 2 8 16 32
Total 14 6 6 3 10 39 63
AGE PROFILES
Age is generally a good proxy for asset condition and, therefore, risk of failure. Transformers are highly reliable assets
and have long lives if well maintained. The expected life of a transformer is typically around 60 years for most
distribution businesses. If transformers are loaded above their rated capacity for extended periods of time, or are operated
in hot and humid environments, then the heat generated accelerates their aging process. However, the transformers on
Aurora’s network are not heavily loaded and are in a temperate environment which will help their longevity.
Figure 15.1 shows the age profile for Aurora’s transformer fleet. It shows a number of transformers are at or approaching
their expected life and this is an indication of increasing risk on the network. It demonstrates that a large proportion of the
transformer fleet will be approaching its expected serviceable life over the next 10 years and is likely to result in
increasing risk to reliable supply and appropriate planning for mitigation of the risk is required.
Figure 15.1 Transformer age profile by zone substation and distribution type
EXPECTED LIFE
Table 15.3 shows a summary of the asset fleet, comparing the average age to the expected life by capacity. This provides
a view on which segment of the fleet is likely to pose higher risk to the network. The table shows that 10 transformers
have already exceeded their expected life.
WEIGHTED NUMBER
RATINGS WEIGHTED
EXPECTED LIFE QUANTITY AVERAGE EXCEEDING
(MVA) AVERAGE AGE
REMAINING LIFE EXPECTED AGE
— oil sampling has been done on a one or two-year cycle for all transformers
— visual zone substation checks have been undertaken frequently including all assets, including specific checks on the
transformers
— tap changers are inspected monthly as part of the zone substation checks but the schedule to meet overhaul
maintenance requirements has not been maintained.
WSP reviewed the inspection and testing results to assess the risk that these assets pose to the network.
— Oil bunding containment and fire walls / separation from other assets
The audits were undertaken by an experienced engineer with strong background in transmission and distribution
networks including asset management and condition assessment.
Much of this information was available from the Aurora asset data and provided us with a high degree of confidence for
our assessment of asset condition and the risks associated with ZSS transformers.
— North City zone substation in Dunedin where the transformer radiators are suffering from spot rusting in several
locations with a slow leak of oil on the radiators of T2. Temporary repairs are evident in several locations on T1 and
T2 indicating this is an ongoing issue
— Fernhill zone substation in Central has sign of oil leakage, identified by a light coating of oil around the transformer
controls enclosure, however the source is suspected to be the tank sensor cable glands.
— Arrowtown T1 OLTC gasket has a minor leak which has a temporary patch repair. Minor transformer leaks are
common across electricity businesses.
Remarkables and Outram transformers data indicate it is indicative of reaching the end of their service life, followed by
Cromwell. It is noted that a plan is in place to upgrade parts of the Outram substation.
Eight zone substations shown in Table 15.4 do not have DP results. This does not appear to be an issue for most of the
transformers as they are quite young and the paper strength deteriorates with age and heat. However, Port Chalmers has
two old transformers which would be considered to have a higher risk of failure due to being past their expected lives.
Table 15.4 Transformers without estimated DP test results
Camphill 1 3
Cardrona 1 8
Commonage 2 10
Lindis Crossing 1 3
Port Chalmers 2 63
Queensberry 1 15
Wanaka 2 15
Ward St 2 8
The results indicate that all zone substation transformers currently in service have satisfactory internal condition and are
suitable for normal operation, although some are shown to be at or near the end of their service life. As the general
condition of transformers is satisfactory, we have used transformer age as a proxy for future condition in the risk
analysis.
Most of the inspection and test reports were from a period between 2014 and 2017, however there some from 2010 and
2002. Each tap changer type has its own maintenance cycle based on the number of operation or the time elapsed since
the last inspection. Table 15.5 shows a summary of the tap changers that are behind on their required maintenance
schedule. It shows that half the switches overdue based on the time requirement are also overdue based on the number of
operations since the overhaul. A complete list is shown in Appendix E.
The maintenance schedule did not contain Willowbank ZSS or Earnscleugh ZSS.
Table 15.5 Tap changers behind maintenance schedule
4 to 5 1 1
3 to 4 1 1
2 to 3 12 4
1 to 2 7
Based on switching 8
Total 24 16
15.4.1.4 BUSHINGS
Information about the type and condition of bushings is not recorded by Aurora. Evidence was found in the inspection
and test sheets of inspections identifying issues and resulting in the asset being repaired with a defect repair report. This
indicates that defects are likely to be found as part of routine inspections of the zone substations and raise for appropriate
action.
However, since Aurora only records asset data in PDF inspection sheets, identifying issues or trends across the fleet is
difficult. Understanding the type of assets that are installed on the network is important for effective asset management.
— Arrowtown ZSS
— Dalefield ZSS
— Earnscleugh ZSS
— Ettrick ZSS
— Omakau ZSS.
Cromwell is a substantial ZSS and has no transformer bunding. A catastrophic event has the potential to spill oil into the
adjacent main road stormwater system.
Of these unbunded sites, Omakau was located close to a small stream in the Manuherikia catchment which is a sensitive
catchment. This presents a possible environmental risk should a significant leak develop in this transformer. We note that
the transformer is currently assessed to be in acceptable condition (viewed externally) and no leaks or significant rust was
identified.
Plastic drainage pipework is satisfactory for oil containment but not suitable if a fire is burning within the transformer
bund. This is considered a particular issue at Fernhill (bunds interconnected and no flame trap).
— Drawing records at most ZSS include construction red mark-up prints in their folders and some Single Line
Diagrams were still showing decommissioned assets. These records need to be brought up to date at all sites, to
reduce the risk of operational error.
— Fire detection in all ZSS building should be reviewed from the perspective of risk. Typically, smoke detectors are
only found in the main switchgear room and no fire detection in adjoining rooms. There is no evidence of any testing
of the alarm system.
— North City ZSS has been fitted with an Inergen gas flood fire protection system. Room air tightness needs to be
reviewed for this system to be effective.
— Intruder security at Mosgiel ZSS control building is compromised from the fact it is outside the switchyard security
fence and glass louver windows into the switchgear room are easily accessed. The building is next to a main rural
road.
— Roxburgh ZSS appears to have incomplete construction works, with unidentified control cable cores in a switchyard
CB mechanism cabinet and a duplicate 110 V DC battery in a switchyard hut.
The deficiencies identified during onsite inspections at the zone substations are of a minor nature and pose an
insignificant risk to safety, reliability and the environment.
27 Fire walls between transformers are not installed at Arrowtown, Clyde-Earnscleugh (though one unit not in service), Cromwell.
Queenstown has a modest separation between transformers, but the T2 fire risk is the adjoining outdoor feeder switchgear. Should
a fire occur, all these transformers are located under significant overhead busbar / switchgear assemblies, which would be
significantly compromised during a catastrophic event.
SAFETY RISK
This is based on a qualitative assessment of the zone substation transformers.
ENERGY AT RISK
This is a quantitative assessment of the value of energy that would not be supplied should either one or both of the
transformers (in a two transformer station) experience an outage. In undertaking this assessment, we considered the
following:
— The conditional probability of failure was calculated (the probability of failing in year t+1 given that it has survived
to year t). The probabilities of only one transformer failing and the probability of both transformers failing together
was considered. The probability was based on a Weibull distribution with parameters set appropriately for the age
characteristics of Aurora’s fleet.
— The time to restore supply has been based on Aurora’s mitigation plans, which include the use of the mobile
transformer in rural areas and the use of a spare transformer, or relocation of a transformer from another substation,
for urban areas.
— In the inner part of Dunedin, there is sufficient transfer capacities to fully offload a substation using switching of the
6.6kV network. As a result, even though some transformers have relatively high probabilities of failure, such as
Neville St, there is minimal impact as the demand can be completely transferred away via the distribution network.
These substations are: Neville St, Smith St, Mosgiel, Kaikorai Valley and Ward St. Once commissioned, Carisbrook
will also have this ability.
— The Value of Lost Load (VoLL) has been used as $12/kWh for Central and $20/kWh for Dunedin to reflect the
different customer demographics.
— The model incorporates the cost to restore supply. This means that there is an expected cost due to the probability of
failure and need to repair that failure, even though the energy can be transferred away. This indicates an increasing
risk, even though there is redundancy for the supply through load transfers.
The probability of failure was adjusted to reflect the lack of maintenance and identified deteriorated condition of the tap
changers by increasing the probability of a minor transformer outage.
The energy at risk was calculated for one year as we are only assessing the current state of the network and not
forecasting forward to assess future scenarios.
ENVIRONMENTAL RISK
This is based on a qualitative assessment of the locations and physical protection provided at each zone substation.
SAFETY
East Taieri is the only substation identified to have a public safety risk due to its location adjacent to a petrol station and
no physical barrier or fire protection between the transformers and the petrol station. However, the DP value of the
transformers are close to 700 indicating it is in satisfactory internal condition, the external inspection did not reveal any
significant deterioration that would indicate end of life, and the tap changer is due for an overhaul this year, but otherwise
ENERGY AT RISK
Figure 15.3 shows the energy at risk. Substations in Capital letters are located in the Dunedin network and lower case
names are located in the Central network. The figure shows a snapshot of the current risk for a single year at each
substation. It does not consider how the risk will change over time as a result of deterioration of assets, load growth or
planned asset replacements. Additional detail for each substation is provided in Appendix E.
We note that there is a project in progress to construct Carisbrook ZSS to replace Neville St ZSS, which is addressing the
greatest risk on the network posed by zone substation transformers.
The energy at risk values in Figure 15.3 are probability weighted based on the condition of the transformer and tap
changers. Therefore, the values are different to the consequence rank of the risk matrix which is based on the unweighted
consequence.
ENVIRONMENT
There were six zone substation transformers identified to not have any bunding for oil containment. Omakau ZSS was the
only one to be located adjacent to a water way. Omakau is an old transformer and, hence, presents an elevated risk of oil
leaks. We note that there is a stop bank in place that may contain the oil, however, this zone substation transformer is
considered a Moderate environmental risk.
The remaining five transformers are located away from waterways, hence, the consequence is lower and the risk score is
insignificant.
Table 15.6 shows the risk matrix for the transformer fleet. It identifies a number of transformers with elevated risk of
failure, predominately as a result of the tap changer condition. The transformer with the highest risk of failure is Outram
as it is old, past test and inspection reports for the tap changer identify condition issues, and the tap changer is outside its
required inspection schedule.
1 0 0 0 0
7 0 4 1 0
6 0 2 4 2
7 2 4 2 1
6 3 3 3 5
— The asset data available from Aurora’s systems and augmented by our field inspections was suitable for the purpose
of this review. We note that the data on tap changers and bushings is not complete and improvements to consistency
of the data recorded can be made. Incomplete asset data presents a risk to effective asset management.
— External deterioration that has resulted in minor oil leaks was identified on three transformers (4.7%).
— Internal condition is assessed by analysis of the oil which is common industry practice. This shows the transformers
to be in serviceable condition. However, we note that the oil has been filtered and there has not been a physical
sample taken from inside the transformers to provide a baseline for the oil tests. This presents a risk that the oil test
results may indicate a better than actual internal condition.
— Test reports showed that the tap changer fleet was in acceptable condition, except for five tap changers (7.9%). There
have also been three tap changer failures during the past year indicating an elevated level of risk from this
transformer component. There are 24 tap changers that are overdue for maintenance by between 1 and 7 years.
— Bunding around each transformer to contain oil leaks was established at all but 6 substations. The main risk related
to a lack of bunding was at Omakau, which is located adjacent a small waterway. The environmental risk was
classified as Moderate.
— Aurora has a mobile substation with connection points at most of the single transformer substations to provide
support in case of a transformer failure.
— East Taieri was the only zone substation identified to pose a safety risk, classified as Moderate. It is located adjacent
to a petrol station but does not have any physical protection in place to protect the petrol station in case of a serious
failure and/or fire.
— The transformers at two zone substations are in poor condition, although we note that one is currently in the process
of being decommissioned. Additionally, transformer tap changers are showing signs of deterioration and some are
behind their maintenance schedule, increasing risk of an outage on the associated transformers.
— There were 8 transformers (12.7%) identified as high risk to reliability, predominately due to the transformer internal
condition and tap changers.
WSP concludes that ZSS transformers currently pose a moderate risk to network reliability and a low risk to public
safety, except for East Taieri where no physical protection is in place to protect the adjacent petrol station in case of an
explosive failure or fire. Transformers at Omakau are not bunded and pose a small risk of environment damage from an
oil leak. Table 15.7 summarises the ZSS transformer risks and indicates the priority for remediation.
We assessed the data availability of this asset class. In undertaking this assessment, we have considered all the
information obtained from Aurora over the course of the project. In our assessment, we took into consideration the ease
of availability and accessibility of the information.
We found that the data available for zone substation circuit breakers was generally quite good. Two key data sources
were GIS and the maintenance schedule spreadsheet. There was a net difference of two circuit breakers between these
two data sources, however, GIS contained three circuit breakers that were not in the maintenance schedule (WK2758,
LF6576, SC) and the maintenance schedule contained five that were not in GIS (AB6, PC2, NS9, OT2 (twice))
The number of operations and condition was well documented, although using site inspection sheets in pdf form made
assessment difficult. The performance data for circuit breakers was recorded in the outage database, although not all zone
substation circuit breaker outages had the feeder identified. Important data deficiencies:
— the manufacturer and model were not complete in either the GIS system or maintenance schedule, 87% and 91%
complete respectively, and 8% had neither the manufacturer nor model recorded
— 83% of circuit breakers had the zone substation location or feeder ID recorded. We used the latitude and longitude
coordinates to fill in the missing zone substation information
— some vacuum circuit breakers were identified to be older than 60 years which was identified to be an error, however,
no other information is available to update the installation date.
This missing information would be easy to update in GIS and would enable improved recording of fault and outage
information as well as enabling Aurora to locate each asset type on the network to identify any asset type issues that may
emerge and ensure appropriate maintenance is undertaken.
In general, we found that there was sufficient information available to undertake this review.
Table 16.1 Summary of data quality
OVERALL DATA
ASSET CLASS SUB CLASS ATTRIBUTES CONDITION PERFORMANCE
QUALITY
— circuit breakers: these are the actual switches that turn on and off supply to a feeder
— switchboard: the frame/housing for the circuit breakers that enables circuit breakers to be inserted or extracted and
provides protection to the field crews from live high voltage components
— switchgear: commonly used to refer to a complete switchboard or group of circuit breakers in one location.
For this section, we refer to circuit breakers in a broad sense, unless specifically discussing the switchboard.
6.6 SF6 13 - 13
VAC 35 4 39
OIL 11 18 29
11 SF6 - 6 6
VAC 30 64 94
OIL 7 11 18
33 SF6 6 2 8
VAC 9 15 24
66 SF6 - 6 6
The circuit breakers cover four voltages; 33kV and 66kV circuit breakers connect the sub transmission network to the
primary side of zone substation transformers, while the 6.6kV and 11kV circuit breakers connect from the secondary side
of the zone substation transformers to the bus and from the bus to the distribution feeders.
The circuit breakers can be located indoors or outdoors and have three different insulating mediums, as shown in Table
16.3. The combination of indoor or outdoor type and the insulation medium creates a different risk profile for each
installation. Information on failure modes and consequences is set out in section 16.2.2.
OIL Outdoor 9 9 18
SF6 Indoor 12 13 25
SF6 Outdoor 7 7
VAC Outdoor 15 9 24
Note: the difference between the data sources has resulted in three circuit breakers not being captured in the analysis for this table.
Circuit breakers are highly reliable assets and have long lives. The expected life of a circuit breakers is typically around
50 years for most distribution businesses. The actual life achieved is impacted by the operational conditions, including
the number of switching operations experienced, the fault currents it is subjected to, and the environment it is housed in
including heat and humidity.
However, the circuit breakers on Aurora’s network are not heavily loaded, generally have fairly low fault levels
compared to the switchgear nameplate ratings and are located in a cool environment which will help their longevity. In
such circumstances, age is generally a good proxy for asset condition and, therefore, risk of failure.
Figure 16.1 shows the age profile for Aurora’s circuit breakers fleet. It shows several circuit breakers are at or
approaching their expected life and this is an indication of increasing risk on the network. The figure demonstrates that a
large proportion of ZSS circuit breakers are likely to have an elevated risk with respect to reliable supply and appropriate
planning for mitigation of the risk is required. The data showing recently installed oil circuit breakers and vacuum circuit
breakers older than 45 years demonstrate likely data errors in the asset data base.
Table 16.4 shows a summary of the asset fleet, comparing the average age to the expected life by capacity. This provides
a view on which segment of the fleet is likely to pose higher risk to the network. The table shows that 129 circuit
breakers (31% of the fleet) have exceeded their expected life, of which 117 are indoor type and oil insulated.
NUMBER
CIRCUIT BREAKER AVERAGE WEIGHTED
REMAINING LIFE EXCEEDING
TYPE EXPECTED LIFE AVERAGE LIFE
EXPECTED LIFE
INDOOR
OUTDOOR
Oil insulated circuit breakers (OCBs) are an older technology and have a higher risk associated with them. When circuit
breakers fail, they can cause an arc which can be an ignition source for a fire. Since OCBs use oil as the insulating
medium, there is a risk that the oil will catch alight and the fire could propagate through the switchboard. This failure
mode can destroy the entire switchboard and the associated devices and cabling attached to it.
The zone substations where the circuit breakers that have exceeded their expected life are located are shown in Table
16.5. Note, Neville St ZSS is about to be decommissioned and replaced by Carisbrook ZSS. This will remove 34 OCBs
from the network.
Table 16.5 Circuit breakers exceeding their expected life
Willowbank OIL 15
Alexandra OIL 3
Ettrick OIL 1
Clyde-Earnscleugh OIL 1
Roxburgh VAC 4
Queenstown1 VAC 5
Wanaka1 VAC 3
Total 129
When assessing risk, age is a useful proxy for condition, but actual condition assessments, historical performance,
redundancy in the network, and other mitigation plans need to be considered as well to assess which assets are likely to
pose the highest risk to the network. These are discussed in the following sections.
— For vacuum circuit breakers, occasionally a loss of vacuum can occur at its contact bottle but is uncommon. For
Viper and NOVA brand vacuum CBs, there is no combustible material to ignite should the vacuum contact bottle fail
- this type of breaker is considered robust. However, some CBs use a combination of vacuum bottle contacts
immersed within an oil filled tank (type VWVE, KFME, KFE, KF). Should the vacuum bottle fail in and allow the
ingress of oil into the vacuum chamber, the CB will fail catastrophically when the oil ignites from the switching arc.
An additional issue was the modification of the VWVE CBs when retrofitting CTs around their bushings, which has
been reported that the modified imperfect seal can allowed moisture into the oil. These circuit breakers are
considered have a low to modest risk of failure.
— Oil circuit breakers: older traditional technology and requires additional maintenance with inspection of load
carrying contacts, filtration of the oil insulation medium and removal of carbon contamination within the arc
chamber.
— SF6 circuit breakers are considered maintenance free, although periodic testing of the SF6 gas should be analysed for
contamination. It is understood that Aurora have not tested their SF6 and it is assumption that the SF6 gas had no
contamination at the time of installation. However, other EDBs in have found that the manufacturer supplied SF6
CBs were filled with impure gas. This could lead to early failure.
Oil insulated circuit breakers have the potential to fail catastrophically, and the resultant fire could propagate through an
indoor /outdoor switchboard assembly as the circuit breakers are adjacent to each other. In outdoor situations where CBs
are discrete assemblies, there is a large distance between each circuit breaker and consequential damage beyond the
faulted breaker is potentially low.
Circuit breakers can fail through an arc flash fault 28 which creates a pressure wave that propagates outwards from the
switchgear. Indoor switchboards should be arc fault rated to safely vent this energy. It can occur for all type of circuit
breakers.
Insulator flash over within indoor circuit breakers is possible where the busbars are not continuously insulated and dust
ingress has accumulated over time across busbar insulator supports. This would typically apply to older oil switchgear as
we found no evidence of internal inspection and cleaning. Early failure detection is possible from insulation resistance
and partial discharge tests.
An additional source of failure can arise from the interface with the cable termination. This failure can be caused through
mechanisms such as overheating or deterioration of the cable joint/termination and the failure can damage the circuit
breaker and result in a fire.
28 Arc flash fault – energy released when an arc is generated whilst opening a circuit breaker/isolator
— observing the maintenance crews undertake a zone substation inspection at Green Island (Dunedin) and Alexandra
(Central) zone substations. Testing was only observed at two substations due to the maintenance cycle being
followed by Aurora and the duration required for the testing
It was not possible to observe any more as substation testing requires taking a zone substation out of service and can
involve significant load transfers or outages and require a long lead time for planning.
The on-site inspection identified consistent inspection practices and found no issues with the data provided by Aurora,
however, the test sheets used by the Delta contractor were not the latest version as issued by Aurora. Testing observed at
Green Island was satisfactory, however at Alexandra all the tasks were not completed due to lack of time, resources and
spare parts.
Further analysis into the cause of the failures shows that 11 of the 26 (42%) were attributed to asset deterioration. A
further 12 (46%) were attributed to human error. Of the human error related outages, 6 (23%) were identified as operator
error in what appears to be a response to a single instance of a sub transmission line tripping in 2017, while the other 6
had no further information. The high rate of human error, particularly human switching error, indicates that there is a
higher probability that field crews will be present at the switchgear at the time of the fault. As stated in section 16.2.2, the
highest probability of an arc fault is when racking in or out circuit breakers or when switching. We note that Aurora has
safety procedures in place for field crews, including protective clothing and a requirement for non-essential crew to exit
the room, However, as stated in section 4, operational controls have not been considered in the assessment of risk.
Table 16.6 Cause of outages
Equipment Deterioration 11
Unknown 2
Total 26
Table 16.7 examines the location and type of circuit breaker that has caused and outage. It shows the prevalence of
indoor oil insulated circuit breakers involved in these outages, in particular the outages identified as caused by equipment
deterioration.
The human switching error outages involving oil insulated indoor circuit breakers indicate an elevated risk due to the
failure mode of these assets. This is increased as none of the switchboards are rated to contain arc faults like modern
switchboards.
Total 20
— Arrowtown
— Clyde-Earnscleugh
— Dalefield
— Earnscleugh
— Ettrick
— Omakau
— Remarkables
— Mosgiel (2)
— Outram (2)
— Queenstown (5)
— Roxburgh (4)
— Wanaka (3).
A further legacy concern at Alexandra ZSS is that the outdoor 33kV busbar clearance to ground does not meet industry
practice. WSP would advise Aurora to consider this matter further.
— minor parts that required replacement (including Andersons Bay ZSS and Berwick ZSS)
— significant amounts of carbon in the oil that indicates high load or fault clearances (including East Taieri which is
approaching its expected serviceable life and Corstorphine)
— slow operating times or phases operating at significantly different speeds (including Andersons Bay ZSS and some
of the old circuit breakers at Mosgiel ZSS).
These findings support our analysis of risk based on the asset age, type and frequency of operations.
— Bulk oil 11kV CBs (Brush, Cooke & Ferguson, Reyrolle, South Wales) have records that indicate that satisfactory
maintenance procedures have been undertaken with the exception of their protection CTs (refer protection section of
this report) which have not been tested as part of past maintenance and inspection practices. This elevates the risk
that the CTs are not functioning as expected.
— Green Island 6.6kV indoor ZSS switchgear (over the two days on-site inspection observation was made of only two
CBs):
— CB contacts were being disassembled for inspection, oil filtered, all parts cleaned of carbon contamination. Test
records were being completed
— CB protection relays functional tests undertaken and results recorded. New testing requirements of the CT
protection circuit identified a failed CT secondary circuit (this test had never been previously undertaken) and
had the potential to negate the operation of the CB under fault conditions and possibly cause a fire at the CT.
Following CB checks identified a second similar fault. Repairs undertaken, but this highlights the risks around
old (60 yrs plus) switchgear.
— Inspection and test sheets used by Delta were not the latest version published by Aurora.
— Alexandra 11kV ZSS switchgear (visits over two days provided test observation of one CB and associated
transformer tests):
— Alexandra outdoor 11kV ASEA CBs. Four yearly test procedures were being undertaken using outdated test
sheets. The contacts of the minimum oil CB and arc chamber were not inspected for carbon contamination. This
aspect has not been inspected since installation in the 1980’s. These CBs are an indoor breaker installed in a
locally build outdoor enclosure. This type of CB is installed in outdoor shelters mounted on top of the
transformer at Clyde-Earnscleugh, Ettrick and Omakau ZSS. It is likely these substations will have same issues.
— Alexandra outdoor 33kV minimum oil CBs were not part of the observed tests, but it is understood that their
contacts and arc chamber have not been inspected since installation (1950’s and 1980’s) for the same reason of
not having a replacement seal available to return the unit to service.
— Alexandra’s 33kV outdoor overhead busbar (legacy asset) is very low with current design clearances not met.
Due to the age in installation arrangement, it is likely that there will be dust contamination across bushings in the indoor
busbar chamber and possible degradation of older pitch filled cable terminations. This is particularly important for the 40
to 60 year old oil CB switchgear.
SAFETY RISK
This is based on a qualitative assessment of the likely number of field crew present at the time of maintenance, calculated
arc fault boundaries, type of circuit breakers, types of enclosures and fault current.
ENERGY AT RISK
This is a quantitative assessment of the value of energy that would not be supplied should the switchgear fail and the
probability of it failing in a catastrophic manner that would cause a zone substation outage. In undertaking this
assessment, we considered the following:
— The energy at risk based on an N-1 or N-2 event at a zone substation as the worst-case scenario. The scenario was
selected based on the layout of the substation and ability of a circuit breaker failure to result in the loss of either one
or both switchboards. Oil insulated circuit breakers have a higher ability for this to occur due to the risk of fire.
— In the inner part of Dunedin, there is sufficient transfer capacities to fully offload a substation using switching of the
6.6kV network. As a result, even though some zone substations have relatively high likelihood of failure, there is
minimal impact as the demand can be completely transferred away via the distribution network. These substations
are: Neville St, Smith St, Mosgiel, Kaikorai Valley and Ward St. Once commissioned, Carisbrook will also have this
ability.
— The Value of Lost Load (VoLL) has been used as $12/kWh for Central and $20/kWh for Dunedin to reflect the
different customer demographics.
— The model incorporates the cost to restore supply. This means that there is an expected cost due to the probability of
failure and need to repair that failure, even though the energy can be transferred away. This indicates an increasing
risk, even though there is redundancy for the supply through load transfers.
The unweighted energy at risk was calculated based on a three month time to repair. The analysis does not consider load
growth or future deterioration of asset condition as we are only assessing the current state of the network and not
forecasting forward to assess future scenarios.
In addition to the energy at risk, specific findings from the onsite audits have been accounted for by adjusting the risk
ranking of certain circuit breaker types. The identified types were given an increased likelihood of failure to reflect
unknown/poor internal condition of the assets and industry experience with the same or similar circuit breaker types.
ENVIRONMENTAL RISK
This is based on a qualitative assessment of the locations and type of environmental impact at each zone substation.
Ward St 6 11.32
Corstorphine 5 8.37
Alexandra 16 6.11
Wanaka 4 5.16
(1) Note: arc fault boundary indicative only with simplified condition for ranking of risk. It is calculated as the distance where the
energy is 1.2cal/cm2.
(2) The number of fault operations is the sum for all CBs at the zone substation since the last known maintenance was carried out
ENERGY AT RISK
From the analysis of the transformer fleet, we have identified that five of the substations in Dunedin have sufficient load
transfer capacity to transfer away all load via the 6.6kV network. This means that if a single circuit breaker fails, the load
at risk is low as load can be transferred away to restore supply. This does not apply in other areas, where a loss of supply
would occur until the circuit breaker can be repaired or swapped out for a spare
However, the risk is with older OCB type arrangements where a failure can result in a fire and which can then propagate
through the switchboard (for indoor types) and destroy the switchboard and all secondary wiring and associated
equipment. This can be an N-2 event depending on the arrangement of the switchboards in the substation. In this case the
rebuild time would be significantly longer.
The consequence is a function of the insulation type (oil) to enable the catastrophic event to occur, the switchboard type
(indoor) to enable propagate of the fire, and the unsecured demand at the substation.
The probability of failure is a function of the age of the circuit breaker, the type and configuration (indoor, outdoor and
insulating medium), its condition and number of operations under fault conditions.
The consequence shown in Table 16.10 below is the unmitigated total risk (the sum of N-1, N-2 and Minor) based on the
energy at risk modelling approach. For this risk to materialise, it requires the circuit breaker to fail and the failure mode
to initiate a fire. The zone substations listed only include where the insulation medium includes oil, the switchboards are
indoor type which will enable the propagation of a fire, the expected life has been exceeded, and there have been three or
more fault operations since the most recent recorded maintenance. Neville St is excluded as it is about to be
decommissioned. This identifies Outram and Anderson Bay as the largest risks based on switchgear type.
Note that the table only shows the circuit breakers at the zone substation that have exceeded their serviceable life, it may
not include all circuit breakers located at that substation.
We note that the zone substations in Table 16.10 below largely align to the same zone substations identified in Table
16.9.
Table 16.10 Unweighted reliability consequence at zone substations
UNWEIGHTED
ZONE SUBSTATION TYPE # OF OCBS FAULT OP’S AVERAGE AGE
RISK
ENVIRONMENT RISK
The environmental risk associated with ZSS circuit breakers is predominantly due to:
— SF6 gas leaks (which is a high impact greenhouse gas and is also a toxic gas to people). Most switchgear will
eventually leak small amounts into the atmosphere which has a negative impact on the environment, or
— oil leaks, however, each circuit breaker only contains a small quantity of oil and are not located in close proximity to
water ways.
The risk is rated as Insignificant.
For zone substation circuit breakers, the risk in the risk matrix is shown as this highest risk out of safety and reliability
based on the mapping set out in section 4.
Table 16.11 Zone substation circuit breaker risk matrix
1 5 1 15 0
9 1 32 60 15
2 20 66 0 11
12 39 15 0 3
11 25 48 17 0
— There are 129 circuit breakers (31%) have exceed their expected lives.
— The inspection, testing and maintenance of ZSS circuit breakers is incomplete with 25 circuit breakers not been
maintained within the required maintenance schedule. In addition, the internal mechanisms of HLC and HKK type
circuit breakers have not been maintained. This elevates the probability of these assets failing.
— Some oil insulated zone substation circuit breakers were found to present an elevated risk to the network with respect
to network reliability and the safety of field crews due to their potential failure mode through arc fault and fire.
— Some of the specific types of circuit breaker in-service on the Aurora network have been identified in the
electricity industry as having an elevated risk of failure, in particular the HLC, HKK and LMT models.
— The switchboards are not rated to contain an arc fault and, hence, pose an elevated risk to field crews.
— The VWVE type switchgear was modified at installation which has enabled moisture ingress and deterioration
of the assets.
— A number of indoor circuit breakers have been installed in custom built outdoor enclosures which, upon site
inspection, did not appear to be fully sealed from the environment. This is likely to result in an increased rate of
deterioration and an increased probability of failure.
WSP concludes that ZSS circuit breakers pose a moderate risk to network reliability and worker safety. They have no
impact on public safety or the environment. Table 16.2 summarises the ZSS circuit breaker risks and indicates the
priority for remediation.
Table 16.12 Summary of ZSS circuit breaker risk
Kaikorai Valley ZSS 15 Reliability/Safety Oil insulated circuit breakers. Moderate risk.
— analysis of relay type, age, settings and function information provided in the protection asset database
— analysis of protection schemes and co-ordination data from protection schematics and instrumentation diagrams
We assessed the data availability of this asset class. In undertaking this assessment, we have considered all the
information we were able to obtain from Aurora over the course of the project. In our assessment, we took into
consideration the ease of availability and accessibility of the information.
We found that there were significant data gaps in the information provided. The protection relay database contained
information for all relays but varied greatly with between 19% and 100% complete depending on the field. For some
attributes, this is not material and not uncommon for electricity business to not have the information. However, others
such as the settings or reference to the calculation sheet were considered material. Settings not captured in the setting
database were found to be captured in site based records (assessed by sample). Overall, the important fields were
sufficiently complete and provided sufficient information for this review.
Important data deficiencies:
— 47 (4.1%) relays do not have a type and 52 (4.6%) do not have a location recorded
— CT current rating and winding ratios are only recorded for 64% of protection schemes
— Most of the battery and charger information is available for most zone substations and evidence is available of
periodic inspection and testing. The information available regarding battery and charger alarms via SCADA is not up
to date.
We also note that there were inconsistent naming conventions used throughout the data sets which makes analysis of the
data more difficult and time consuming. In general, where information was available, we found that it was not always
well organised and structured in a manner that would facilitate good asset management practices.
Table 17.1 Summary of data quality
Protection relays
Zone substation
Setting information N/A N/A
Instrument
transformers
SCADA
— protection relays which have settings calculated and set to detect specific events and take appropriate action, such as
trigger an alarm or open a circuit breaker
— instrument transformers provide a signal to the protection relay that is a scaled down representation of the current
and voltage on the network at that location
— battery banks and chargers ensure reliable DC supply is maintained to the protection relays.
UNKNOWN
TYPE CENTRAL DUNEDIN TOTAL
LOCATION
Static 44 36 4 84
Microprocessor 17 6 41 64
Table 17.3 show a summary of the age of the asset fleet. It shows that approximately 382 (55%) of the electromechanical
relays and 106 (28%) of the electronic relays have exceeded their expected life. This does not mean that those relays
must be replaced but given age is often a good proxy for condition, and the old relays will not have vendor support and
spares are not held in store and will become increasingly difficult to source elsewhere. For modern digital relays,
firmware upgrades for security or compatibility purposes may no longer be available once they are out of vendor support.
Note: unknown relay types did not have an installation date recorded so data is not available for the table above.
Figure 17.1 demonstrates that there was a clear change in technology that occurred in the 1980’s where
electromechanical relays were superseded by digital relays. The age profile is reflective of relays being installed as large
groups when substations are established or switchboards or protection schemes replaced. The high volumes of
electromechanically relays compared to digital relays is reflective of the single function provided by elector mechanical
relays meaning multiple electromechanically relays are required for each digital relay to provide the same protection.
Microprocessor 23 41 64
Static 12 34 38 84
— Cromwell Substation.
In addition, protection schematics were used to form an overview of the protection system covering both areas networks.
A summary of the key findings is provided:
— We could not define a common/specific protection scheme/strategy for the applied protection in the network. i.e.
There are no specific criteria used to protect different assets. It was found that the protection of same assets at
different locations have been implemented differently. Therefore, we did not have reference, standard or bench mark
to assess against.
— The protection setting calculation documents show that that most of these settings were calculated during the 1980’s
and 1990’s. Since then there has been significant growth and change in the network. It was observed that changes
have been applied to the protection of some of the zone substations for various reasons, including to resolve nuisance
tripping or address increased load. However, there was no evidence that these changes have been coordinated with
overall protection scheme of the network. Therefore, a review of the overall network protection is considered critical
for the safe and reliable operation of the network.
— The dates on the protection setting calculations sheets are old and there does not appear to have been a recent
protection system study/review to ensure the protection schemes and settings are still appropriate given changes in
the network since the original settings were calculated, including review of the protection settings and asset ratings
(including distribution switches) against fault currents and loading present on the network now.
— We could not clearly verify the primary and secondary protection of the assets (feeders and transformers). Some
locations have unit protection installed as primary and non-unit protection installed as secondary, however some
locations have only one form of protection and some have used only fuses. Therefore, it was not possible to identify
the reasoning behind selecting specific primary and secondary protection for feeders and transformers.
— Within the sample of substations reviewed, we noted that the incoming feeders at Mosgiel Zone substation do not
have protection relays associated with them and they rely on distance protection relays located at the upstream of the
feeder (Halfway Bush GXP). Further, there is no interlock associated with the three incomer scheme to prevent the
circuit breaker on the third line (normally open) from closing onto a fault if the other two circuit breakers have been
tripped. Similar arrangements that do not have a local protection relay and instead rely on the distance protection of
the upstream feeder were also identified at Outram.
— Within the sample of substations reviewed, we noted that busbar protection schemes (differential or frame leakage
protection) were not applied in all zone substations and flash arc protection was also only implemented in a few
locations. We note that busbar protection is not always applied in distribution systems where the network conditions
allow, for example if fault levels are low or when other adequate fast operating protections cover the bus bar.
However, there does not appear to be a consistent approach applied at Aurora.
— We noted that the protection settings sheets at zone substations contained some hand-written mark ups identifying
different settings in the relay than recorded on the sheet. There was no evidence provided to indicated why the
settings were changed or reference to a calculation sheet. There were few instances of this identified.
— The earth fault protection of the feeders is either instantaneous or definite time, which could be difficult to
coordinate without affecting the sensitivity of the protection. Faults that involve conductors that fall to the ground
often have high fault impedance, which sometimes makes it difficult to detect if the setting is not sensitive enough.
On the other hand, settings that are too sensitive can result in spurious tripping and impact on network reliability.
WSP reviewed calculations to coordinate earth fault settings at two of the five zone substations that were reviewed in
detail and found them to be adequate. The other three zone substations showed coordination between the settings, but
the calculations were not provided in the protection setting calculation documents.
— Due to the age of the protection relays, availability of spares to enable quick change over for failed or defective
relays could become a major issue as the relays reach end of life.
— The Alexandra to Clyde sub transmission line has areas not currently covered by a protection scheme. A new scheme
is being implemented for the end of this year.
Additional findings with more detail specific to each of the substations reviewed are included in Appendix B.
— Central includes eight 33kV to 11 or 6.6kV transformers that have capacities of 3 MVA and 5 MVA that are
protected by fuses on the 33kV side. This is not a standard approach for this size of transformers. The use of fuses
for this type of protection increases the difficulty of coordinating the protection scheme with downstream protection
devices
— The Omakau transformer is protected by fuses and does not have a circuit breaker for protection. Any planned
outage requires the line to be isolated first from Alexandra, which will also result in an outage at Lauder Flat, while
the fuses are removed. This will increase the difficulty in removing the transformer from service for maintenance.
Arrowtown T1 5
Arrowtown T2 5
Clyde-Earnscleugh T2 5
Dalefield 3
Earnscleugh 3
Ettrick 3
Remarkables 3
Omakau 3
Electromechanical 45 23 47.3
Static 35 20 32.4
Numerical 32 16 23.8
Unknown 20 19 16.0
Microprocessor 19 16 8.8
Table 17.6 shows that there are 23 types of electromechanical relays and 16 types of numerical relays that do not have
spares and have an average age that is approximately their expected life. This increases network risk as it will not be
possible to replace the relay quickly should it be found to have failed. Replacement requires significant design work to
install a modern microprocessor-based relay. This will increase the duration that the feeder will need to be out of service.
17.4.4 SCADA
Since the SCADA IT and software system is new, our focus was on the assets in the field, namely the RTUs. We
undertook the review by on site field inspections and review of historical inspection and test reports.
— The test records provided do not indicate that there is a specific maintenance plan (TMP) that has been followed. The
dates of the testing show periodic inspection and testing has been undertaken but did not appear to be based on a
fixed cycle or according to relay type and age. WSP has observed that other electricity businesses generally increase
the frequently of inspection and testing as the relay ages. This is because Electromechanical relays lose calibration
over time and more quickly when they are old and worn. Therefore, the maintenance frequency is expected to be
higher for older electromechanical relays. However different cycles of inspection and testing was not evident in the
data provided. While most relays have been inspected within the past four years, dates on the inspection sheets
identify that some relays have not been inspected for much longer.
— Timing and pick up values consistently required adjustment. Recalibration was required on 513 test sheets covering
51 relays tested. The adjustments required ranged up to 65% for timing and 20% for pick-ups. The large adjustments
required has implications for coordination of the protection schemes and the duration of faults on the system prior to
being cleared, hence having a safety impact.
— Notation on the testing sheets identify that a range of electromechanical relays required cleaning to prevent contacts
from sticking/not functioning, relay flags not operating, noisy components indicating that there was an internal
mechanical problem and other condition related problems.
— The FGL earth fault, PBO overcurrent and AKA earth fault time delayed relays manufactured by AEI appear to
consistently require more maintenance and recalibration, with larger percentage adjustments, than other relay types,
notably at Anderson Bay and Green Island zone substations. There are 207 of these relays on the network. All of
We note that Neville St is in the process of being decommissioned, which will result in 37 of these relays being removed
from service.
WSP notes that earth fault detection on feeders is an issue due to the high impedance of conductor on ground faults. This
may be compounded by relays that are not operating as intended as a result of settings drifting over time and without a
regular inspection program to ensure the settings remain within tolerance.
The desktop analysis was supported by on-site inspection of the zone substation. WSP visited 38 of the 39 zone
substations (Remarkables was not visited) to undertake a visual inspection and also witness inspection and testing at
Green Island (Dunedin) and Alexandra (Central) zone substations. The key observations were:
— The inspection and testing identified that the relays and protection systems appeared functional but approaching end
of life.
— Some relays were found with elements turned off, most likely due to incomplete procedures after testing the relays.
— The relays for all the feeder protection at Alexander ZSS were in one cubicle. This increases the risk that damage to
the cubicle, e.g. from a fire, can cause outage to all the feeders. It is recommended that Aurora investigate splitting
these protection relays into two panels to avoid a single point of failure.
— Some relays were not housed inside a building, though they are in an enclosed box mounted to the transformer. This
subjects the relatively delicate protection relays to vibration, moisture and large temperature variations.
In summary, the protection relay fleet is aged and at end of life. Electromechanical relays are often out of specification
and pose a risk of maloperation of the protection schemes. The maintenance program does not ensure that all relays are
tested at appropriate intervals.
— There is no age data available for the charger, but in general about a third appeared old and at or approaching the end
of their serviceable life.
— The attribute data for the chargers is incomplete and does not appear to be accurate, for example, there are only 19
substations listed with chargers that support protection scheme.
— Most substations only have one charger for protection, SCADA and communications, noting that the voltages
required for each are different. Hence, there is a single point of failure and no redundancy.
— Aurora confirmed that all substations except Fernhill and Earnscleugh have battery and charger monitoring and
alarms implemented via the SCADA system.
— Fernhill and Earnscleugh zone substations do not have battery and charger monitoring and alarms implemented via
SCADA. This means that if the charger was to fail, then the control room will not know that they need to send a field
crew to investigate and rectify the situation and the protection, communications or SCADA may cease to work when
the battery voltage becomes too low without prior warning.
— Site inspection found some batteries thought to be past their used by date (East Taieri, North East Valley, North City.
— 15 were identified to be LV cables/conductors which are difficult to detect due to fault currents being not much
different to normal supply currents.
— 4 were on feeders from Port Chalmers which has SEL 351S relays which should have cleared the fault
— 2 were on Mosgiel feeders which had SEL751A relays which should have cleared the fault
— 14 faults were found to be protected by electromechanical relays of which, from the information available, AEI
FGL type, AEI PBO type and AEI AKA type were the predominate types. Form5 and Reyrolle B1 relays were
also identified as having failed to operate.
Some of these incidents were due to a high impedance HV fault, where a back feed from the energised network
circumvents the proper operation of the protection relays.
The failure of the Sensitive Earth Leakage (SEL) relays to operate may indicate that the Port Chalmers and Mosgiel
distribution area have either changed characteristics and require a review of settings, have high impedance earth fault
characteristics, or another component of the protection system failed such as the current transformers.
The failure of the electromechanical relays to operate aligns with the findings from our assessment of the test and
inspection sheets showing that the settings are drifting and may no longer be suitable to detect the fault.
A non-functioning ASEA RI electromechanical relay at Clyde-Earnscleugh was identified during WSPs site visit and was
subsequently replaced.
ENERGY AT RISK
Managing energy at risk is not the primary function of relays, but supply outages can be extended by the failure of the
primary protection scheme. The risk was not assessed as there is insufficient evidence regarding the number of spurious
trips occurring on the network that this calculation would rely on.
— the functionality of those relays, for example, earth fault and over current are more critical to public safety than
transformer unit protection
— the location, including population density and load growth/network configuration changes
Based on the information available about these attributes, the assets were ranked and an assessment made on the risk.
ENVIRONMENT
Protection systems pose an insignificant risk to the environment.
0 110 76 384 0
0 1 32 86 0
0 7 63 17 0
0 17 41 58 0
0 41 54 79 0
— The asset data available from Aurora’s systems and augmented by our field inspections was suitable for the purpose
of this review. However, we note that the data is not complete and improvements to consistency of the data recorded
can be made. Incomplete asset data presents a risk to effective asset management.
— There are 382 electromechanical relays (36% of the relay fleet) and 106 electronic relays (10% of the relay fleet) that
are exceeding their expected life. This indicates an elevated risk of failure of these assets. Further modelling was
undertaken to refine the assessment of network risk and quantities.
— In a four-year period, 20 faults on the HV network were not cleared by the immediately up-stream protection asset.
— The dates on the protection setting calculations sheets are old and there does not appear to have been a recent
protection system study/review to ensure the protection schemes and settings are still appropriate given changes in
the network sine the original settings were calculated. This poses a risk that the settings are not appropriate for the
current loading and fault current characteristics of the network.
— Five types of electromechanical relays are now an obsolete technology and are consistently losing calibration
between maintenance cycles. These relays are used for earth fault and over-current detection. The failure of these
relays to operate as intended has resulted in live conductors on the ground not being detected and de-energised. Most
observed instances where earth faults were not isolated were found to involve the identified relay types or older
electromechanical relays more generally. This supports they are at the end of their serviceable lives. Protection
system assets pose a significant safety risk and their remediation should be assigned a high priority.
— Most substations only have a single battery and charger configuration resulting in a single point of failure that could
impact the protection systems should they fail. Approximately half of these do not have an alarm via SCADA to alert
the control room to a charger failure.
— Historically instrument transformers have not been tested during maintenance. Testing was implemented this year for
current transformers (2018) and a high rate of failure was found. Voltage transformers are still not tested as part of
the inspection and maintenance procedures. The high failure rate and incomplete testing indicates an elevated level
of risk on the network. The extent of the risk was not quantified as part of this review as testing requires an outage of
the associated protection system and substation.
— Asset attributes have generally been captured in GIS. While this has been made to work for many assets, there is no
link to financial data and or any functional workflow and maintenance management systems incorporated into the
software. This limits the functionality applicable to asset management.
— Supply outage information is attributed to the nearest distribution transformer which limits the information that can
be extracted from the data set. There is a reliance on free text fields which increases the difficulty of analysing the
data.
— There was inconsistency in naming conventions across different data sources and no unique identifier for each asset
which increased the difficulty in analysing data across different data sources.
The quality of the data varied across asset classes and was generally found to be better for the high value low volume
assets, particularly zone substation assets, as well as for assets where there have been recent efforts to improve the asset
management, in particular for support structures. We modified our approach to the risk assessment to make the best use
of the data available for each asset class and to model the asset class in a manner that is reflective of its characteristics.
We conclude that despite data deficiencies adequate data and information was available for the review.
NETWORK SECURITY
WSP found that the level of security in the network was similar to that observed in other electricity business. We note
that:
— Urban feeders generally have good levels of interconnection with adjacent feeders to be able to transfer load,
however, some parts are radial with no interconnection. These arrangements do not appear different to most other
electricity businesses.
— Long rural feeders normally have limited ability to enable resupply via switching, and this is reflected in the security
and performance standards set for those feeders. We found that the topology of Aurora’s network was appropriate
for its geographical location and distribution of customers. To mitigate the risk of a prolonged outage should a single
transformer zone substation fail, Aurora has a mobile transformer that can be deployed to restore supply quickly.
WSP concludes that the security of supply appears to be appropriate for the size and topography of the load supplied.
Security of supply could be improved by adding more interconnections between ZSSs and HV distribution feeders, but
this is unlikely to be economic with the present network size.
NETWORK RISK
The long-term network performance was analysed to identify any assets that are displaying an increasing trend in the
number of outages. We found that overhead conductors, poles and crossarm assets were causing more than 50% of the
network outages that were attributed to asset deterioration.
We found that most assets pose a small risk to public safety, reliability or the environment. The risks posed by these
assets are no greater than WSP has observed in other networks in New Zealand and internationally. WSP found some
exceptions which are set out in the following conclusions by asset class:
Support structures
The key components of support structures are poles, crossarms and insulators. Information on insulator defects and
condition is not separately recorded but they are generally replaced with the crossarm; hence, the review assessed
insulators and crossarms together. We found:
— A rising trend in supply outages from failed poles prior to 2016 has been arrested in 2017-2018, likely because of the
accelerated pole replacement program.
— A significant number of poles (12%) and crossarms (47%) exceed their expected lives. The large number of support
structures that exceed their expected lives indicates an elevated risk of failure of these assets. Modelling indicates
2.6% of the pole fleet and 2.3% of the crossarm fleet are in poor condition and have a high risk of failure.
— The pole inspection program has recently been improved but has not identified all poles that are in poor condition as
it has not yet covered the whole network.
— Crossarms are not inspected adequately and many are in poor condition. Some (2.3%) are categorised as high risk
due to their location relative to population and the probability of failure. Probability of failure was based on results
from our field inspections.
— Malaysian Hardwood crossarms (3.8%) have a shorten life due to fungal growth and need to be replaced.
WSP concludes that the support structures pose a moderate to high risk to network reliability and specific assets pose a
high risk to public safety due to their location in populated areas.
Distribution switchgear
The key assets in the distribution switchgear fleet are pole mounted air break switches, pole mounted auto reclosers,
ground mounted switchgear and RMUs.
Distribution switchgear has only contributed 8% to the average number of outages on the network between 2013 and
2017 but is displaying an increasing trend.
— Two types of switchgear (L&C and Statter) are at end of life and have a high risk of explosive failure.
— A significant portion of the RMU type switchgear inspected (40%) have oil leaks, indicating a deteriorated
condition.
This indicates that there is an elevated probability of failure of these assets.
WSP concludes that distribution switchgear poses a low to moderate but increasing risk to network reliability and
specific assets pose a high risk to worker safety. The exception to this are the L&C and Statter switchgear, a portion of
which (20 units) represent a high risk to public safety.
Distribution transformers
Distribution transformers are a run to failure asset, with about 10 (0.1%) failing each year. Failures of distribution
transformers present small risks to safety, reliability and to the environment. Due to their age and location, there are 328
distribution transformers (4.7%) with a moderate level of risk.
While only a small portion of the fleet is aged, with 10% exceeding their expected lives, there is a gradual increasing
trend of transformer failures, which indicates these assets pose an increasing risk to network reliability and safety. In
particular,
— There are 57 distribution transformers in the Dunedin network considered to have a high safety risk due to their age,
capacity and proximity to the public. In the Central network, two distribution transformers are considered a high risk
to safety. There are no transformers in either the Dunedin or Central networks that are a high risk to reliability.
WSP concludes that distribution transformers pose a low to moderate risk to network reliability and safety, except for a
few aged transformers in the Dunedin network that pose a high risk.
Overhead Lines – sub transmission
The key components of overhead sub transmission lines are conductors and connectors.
Overall, the sub transmission network is performing well. Several issues are identified, but they are not yet adversely
affecting network performance. We found:
— On average, one sub transmission line per year causes either a safety incident by falling to the ground or is reported
in the public hazard register. This indicates that, although these assets can pose a risk to public safety, the events are
infrequent and the information available indicates that the protection operated for the incidents where the conductor
made contact with the ground.
— The A, B and C sub transmission lines in Dunedin are in poor condition and there is a high probability of failure on
some sections (specifically the A and B Lines that are in closer proximity to the coast and 111 years old). However,
the consequence of failure is low due to the redundancy in the network and because the sub transmission lines are
located away from highly populated areas.
— The Cromwell to Wanaka lines have a number of issues, including vertical separation between the 11kV and 66kV
circuits of 1.8 m compared to the requirement for separation of 2 m. In addition, there are a number of issues relating
to its construction.
— It is likely there are spans of the sub transmission lines that do not comply with the minimum height requirements.
This was not quantified as part of this review but is indicated by the asset data.
WSP concludes that sub transmission lines pose a low risk to network reliability and safety.
— The available test records identified a number of recurrent sheath integrity failures.
— 17 km of cable that has a higher risk of failure is comprised of the connection to Neville St and Smith Street zone
substations. As part of the Neville St decommissioning project, the associated cables (10.7 km) will be
decommissioned, removing this risk.
— North City cables pose a moderate risk due to the limited load transfer available and the condition of the cable
increasing risk of failure. There was a significant oil leak on the North City No. 2 cable, however, the leak stopped in
2015.
— There is a low risk of environmental damage through oil leaks, although the type of oil used reduces this risk.
WSP concludes that sub transmission underground cables pose a low to moderate risk to network reliability and an
insignificant risk to public safety. Oil leaks can pose a risk to the environment, but none were identified currently.
We note, however, that replacement of a sub transmission cable can be a lengthy process and the lack of good condition
information poses a risk that a cable needing replacement may not be identified with sufficient lead time. The impact is a
potential reduction in network security while cables are replaced.
Underground cables - Distribution
The distribution underground cables fleet is comprised of largely XLPE and PILC type cables. Overall, the underground
cable fleet is performing well but there are some condition issues that have emerged during the past few years. We found:
— HV distribution cables asset class causes 11% of the network outages, the fourth highest contribution out of the asset
classes. Most outages in this asset class are recorded as being caused by asset deterioration.
— Approximately 10% of PILC cables and the entire section of HV submarine cables exceed their expected life and,
therefore, represent an elevated risk of failure for this asset type.
— The transformers at two zone substations are in poor condition, although we note that one is currently in the process
of being decommissioned. Additionally, transformer tap changers are showing signs of deterioration and some are
behind their maintenance schedule, increasing risk of an outage on the associated transformers.
— There were 8 transformers (12.7%) identified as high risk to reliability, predominately due to the transformer internal
condition and tap changers.
— There are 24 tap changers that are overdue for maintenance by between 1 and 7 years.
— Bunding around each transformer to contain oil leaks was established at all but 6 substations. The main risk related
to a lack of bunding was at Omakau, which is located adjacent a small waterway. The environmental risk was
classified as Moderate.
— East Taieri was the only zone substation identified to pose a safety risk, classified as Moderate. It is located adjacent
to a petrol station but does not have any physical protection in place to protect the petrol station in case of a serious
failure and/or fire.
WSP concludes that ZSS transformers currently pose a moderate risk to network reliability and a low risk to public
safety, except for East Taieri where no physical protection is in place to protect the adjacent petrol station in case of an
explosive failure or fire. Transformers at Omakau are not bunded and pose a small risk of environment damage from an
oil leak.
ZSS circuit breakers
The zone substation circuit breaker fleet is comprised of indoor and outdoor circuit breakers that are insulated by using
oil, vacuum and gas (SF6) technologies.
Failures of zone substation circuit breakers occur infrequently and, hence, have a small impact on network reliability. As
they are located within a ZSS, they have no impact on public safety.
We found:
— A significant portion (31%) of ZSS circuit breakers have exceeded their expected lives.
— The inspection, testing and maintenance of ZSS circuit breakers is incomplete. This elevates the probability of these
assets failing.
— Some oil insulated zone substation circuit breakers were found to present an elevated risk to the network with respect
to network reliability and the safety of field crews due to their potential failure mode through arc fault and fire:
— Some of the specific types of circuit breaker in-service on the Aurora network have been identified in the
electricity industry as having an elevated risk of failure, in particular the HLC, HKK and LMT models.
— The switchboards are not rated to contain an arc fault and, hence, pose an elevated risk to field crews.
— The VWVE type switchgear was modified at installation which has enabled moisture ingress and deterioration
of the assets.
— There are 382 electromechanical relays (36% of the relay fleet) and 106 electronic relays (10% of the relay fleet) that
are exceeding their expected life. This indicates an elevated risk of failure of these assets.
— Five types of electromechanical relays are now an obsolete technology and are consistently losing calibration
between maintenance cycles. These relays are used for earth fault and over-current detection. The failure of these
relays to operate as intended has resulted in live conductors on the ground not being detected and de-energised. Most
observed instances where earth faults were not isolated were found to involve the identified relay types or older
electromechanical relays more generally. This supports they are at the end of their serviceable lives.
— Most substations only have a single battery and charger configuration resulting in a single point of failure that could
impact the protection systems should they fail. Approximately half of these do not have an alarm via SCADA to alert
the control room to a charger failure.
— Historically instrument transformers have not been tested during maintenance. Testing was implemented this year
(2018) and a high rate of failure was found. This indicates an elevated level of risk on the network.
WSP concludes that ZSS protection systems are in poor condition and pose a high to very high risk to network reliability
and public safety. Protection system assets pose a significant public safety risk and their remediation should be assigned a
high priority.
SUMMARY OF RISKS
We used Aurora’s risk management approach to classify the identified risks. The chart below shows a summary of the
result.
Overall, we found a high number of risks in the “Red” category, indicating network risk has not been reduced to as low
as reasonably practical.
A prioritised list of risks has been developed to provide guidance on where Aurora should focus their attention in
maintaining the safety and reliability of the network.
29 For the purpose of this chart, the distribution cables have been calculated based on number of cables rather than length to enable
addition of the cast iron potheads into the same category. This makes each cable and pothead a single unit and, therefore, can be
added on a ‘like for like’ basis for the purpose of displaying risk.
— location of assets to account for public safety (i.e. proximity to points of interest or density of population)
— location of assets to account for environmental conditions (i.e. Central v Dunedin Inland v Dunedin Coastal)
— asset type or material type where it could result in sufficiently different deterioration rates or criticality assessment
Once the population had been segmented to improve the targeting of our sampling, an appropriate sample size was
calculated as discussed below.
For assets with a large population (e.g. poles, distribution switchgear) WSP took a statistical approach to calculating the
sample size based on the Confidence Level and Margin of Error required for each population segment criticality. The
formulas used are shown below with the parameters defined in Table A.1.
𝑍 2 ∗ 𝑝 ∗ (1 − 𝑝)
𝑆𝑎𝑚𝑝𝑙𝑒 𝑆𝑖𝑧𝑒 =
𝐶2
Normalising for population size gives:
𝑆𝑎𝑚𝑝𝑙𝑒 𝑆𝑖𝑧𝑒
𝑁𝑒𝑤 𝑆𝑎𝑚𝑝𝑙𝑒 𝑆𝑖𝑧𝑒 =
𝑆𝑎𝑚𝑝𝑙𝑒 𝑠𝑖𝑧𝑒 − 1
1+
𝑃𝑜𝑝𝑢𝑙𝑎𝑡𝑖𝑜𝑛
Table A.1 Sample size calculation variable descriptions and values
Standard deviation of the condition of the 0.5 assumed since not yet 0.5 assumed since not yet
p
population assessed assessed
Population Number of assets in the fleet segment Varied per asset class Varied per asset class
SUBSTATION INSPECTIONS
B1 SITE INSPECTION FINDINGS BY
SUBSTATION
This section lists the key findings per substation based on our on-site inspections.
— Switchgear: no evidence of any insulation resistance testing of protection CTs or indoor busbar. CT and busbar IR
testing needs to be done to assess the condition of the protection circuits and the busbar chamber from the
perspective of their integrity. The need for this was highlighted by the failure of protection CTs at Green Island.
— Surge arrestors: installation of SAs to protect cables, transformers from vacuum CB switching pulses, lightning etc
seems to be patchy and a review is recommended. Many instances of rigid copper strap looking to block off SA arc
vent.
— Bund gratings or metal trench covers are typically not earthed. Aurora should consider this under their earthing risk
assessment requirements.
— Fire detection observation: one, sometime two smoke detectors are in the main switchgear room(s). No fire detectors
in other building rooms. No evidence of any maintenance of the smoke detectors. Should a fire occur in any of the
substations (the main risk is from within a control panel) its detection is uncertain. As the buildings are not occupied
fire detection is not a NZBC requirement but very desirable from a risk perspective. Lack of complete building fire
detection could be considered a fatal single point of failure within all substation buildings.
— Drawing folders: Most of the site drawing folders contain red pen mark-up prints. The accuracy and completeness of
these drawing folders needs to be reviewed.
— Mercury switches within some transformer temperature relays have been identified as a false trip risk during a
seismic event. It is also probable that these types of switch contact will exist within older Buchholz relays,
something that has not been investigated.
— Arc flash assessment notification re PPE requirements if operating switchgear was not seen at all sites. Given the HV
assets are existing (and not covered under AS/NZS 3000, EEA Guidelines 2011).
— Building signage: Bar a few sites, Health & safety notices re CPR/first aid are out of date, no first aid fire
extinguisher.
— Seismic restraint: not formally considered, but a suitable qualified person should review this aspect independently of
this report. As an observation, not all cells in battery banks are secured to their stands. Overhead gantry structure
doesn’t appear to be braced in all directions.
BERWICK
Outdoor switchyard: four feeder cast iron cable potheads observed.
EAST TAIERI
Fire wall to adjacent petrol station (newer development). Transformer temperature relays use mercury switch contacts.
Battery charger is original and batteries beyond end of life (dated 2005).
KAIKORAI VALLEY
It was observed new 33k V feeder and transformer Differential protection has been installed but not put into service
/requires completion.
MOSGIEL
Substation building at approximately 60 years old and considered near end of life. Remedial works to reinforce its
structure are evident, glass louvre windows facing the State highway are not considered secure and there is no security
fence along this boundary. Some switchyard surge arrestor arc vents blocked by rigid copper earth strap.
NORTH CITY
Outdoor switchyard: The two power transformers radiators look to have had patch repairs over their life. Pressing issues
are:
1. T2 radiators are rusting and an oil catch bottle and drip tray is placed under one leak. Several temporary leak
repairs plus new rust areas are evident. All radiators require the thorough refurbishment.
2. Winding temperature relays use mercury switches. In an earthquake the transformers may spuriously trip losing
the hospital and university loads.
3. It is suggested the Silica gel breathers are replaced with a nontoxic desiccant.
110 Vdc batteries look to be beyond their service life and their replacement needs to be investigated.
PORT CHALMERS
Switchyard security fence over grown in places. Transformers are 60+ yrs old and require a review of remaining service
life. Review of spark gap (surge arrestor) performance recommended to validate protection of primary assets. 24 Vdc
SCADA charger, protection, alarm unit installed but no battery.
SMITH ST
Transformers, switchgear are 60+ yrs old and require a review of remaining service life.
ARROWTOWN
Whilst this is listed as being n-1, one transformer does not have the capacity to take all the load. A third unit needs to be
considered. T1 leaking oil from a temporary repair. No oil bunding.
CARDRONA
Switchgear building: Labelling of the SEL 787 protection relay required. No transformer differential protection seen –
required confirmation. Water in the 11 kV switchgear cable trench observed and may have a long term effect of the
switchgear?
CLYDE EARNSCLEUGH
Transformer T1: ASEA RI protection relay not working on one phase. Temperature relay uses mercury switch contacts.
Cabinet door opens to eye level. No oil bunding.
11 kV ASEA HKK CBs atop the transformer require contact inspection.
CB192 cable screens not run back through CTs. Review Raychem BØ termination clearance to earthed metal. Insulation
tape around screen disintegrating
CORONET PEAK
No surge arrestors or spark gaps seen – requires review. Cooling fans use three phase motors – with a single phase local
service supply an electronic convertor has been used to provide three phase power. It is understood this requires manual
resetting if power is lost.
No room at present to park the Aurora mobile substation should a failure occur.
CROMWELL
Transformers are adjacent to each other with no fire wall between. No oil bund with any oil leakage having the potential
to drain onto the adjacent main road stormwater.
Surge arrestor performance details should be reviewed due to copper earth strap blocking their vents.
CROMWELL GXP
No surge arrestor protection observed. VTs earther via galvanised mild steel frame – should be earther direct to ground.
Whilst new 24 Vdc charger and batteries have been installed, the old units have not been removed.
DALEFIELD
Observations: 33 kV conductors into and out of Dalefield look to be of a small cross sectional area. Guy on last pole into
ZSS does not has an insulator break or PVC sleeve. Dirty 11 kV insulators from birds roosting on the transformer.
EARNSCLEUGH
No oil bunding. 11 kV ASEA HKK CBs atop the transformer require contact inspection. CB cable screens not run back
through CTs.
ETTRICK
Understand this sub has been on the refurbishment list for some years. No oil bunding. Broken sheds on 33 kV AIS. 11
kV ASEA HKK CBs atop the transformer require contact inspection. SA installed but copper strap blocking arc vent.
FRANKTON
Transformer bunding – no flame trap to protect drainage into the oily separator. Connection via a PVC pipe will not be
fire rated.
FRANKTON GXP
This was a Transpower structure that is now part of Aurora’s assets. There are multiple 33 kV air break switches – it is
not known if their insulators are of a two part construction, as their cement joint is known to fail.
LAUDER FLAT
Transformer bund drain fitted with SPI Petrochem oily water barriers. Sediment build up and a filter screen is missing –
their maintenance arrangement need to be reviewed as they drain into an open road side sump/drain. Emergency trip
buttons should have trip covers. Transformer panel cabinet doors not earthed.
QUEENSBERRY
Installation of SAs need reviewing. As an unfounded observation, the control cabinet has no forced cooling and will
potentially get very hot during summer.
QUEENSTOWN
Both T1 and T2 are within a very compact switchyard, and a fire in either transformer would have a significant impact on
the overhead 33 kV bus structure. A T2 fire would have a significant impact on the immediately adjacent 11 kV feeder
CBs. No details on the 11 kV SF6 gas sited – purity should be verified.
Surge arrestor performance details should be reviewed due to copper earth strap blocking their vents. SAs on 11 kV
cables required review.
110 Vdc batteries due for replacement 2017.
RIVERBANK RD
Switching station under construction. Relay room has heat detectors fitted which is fine, however, they will take a long
time to respond to a fire event. As a suggestion, early warning would be better detected with smoke detectors.
WANAKA
Protection for T1 Differential protection earth fault element LED found not to be illuminated, indicating that this element
has not been enabled (element enabled on T2).
Restricted one way access behind 11 kV indoor switchgear.
Outdoor surge arrestor requirements require review (rigid copper strap used, SAs at cable terminations etc). Deteriorating
PVC tape on CB 3232 cable termination is unravelling and bridging its termination insulator.
Photo 1: Alexandra ZSS – 33/11 kV T2; live 33 kV terminals Photo 2: Alexandra ZSS – 11 kV feeder CBs; indoor ASEA HKK
approx. 2.1 m agl. ASEA CB type HPL on left CBs in an outdoor enclosure; Flammable Pinex lined internally;
11 kV bus generating partial discharge
Photo 3: Clyde Earnscleugh ZSS – non-functioning protection Photo 3: Cromwell ZSS – T1 & T2 adjacent to each other; no fire
relay (one phase) on right hand side of cabinet wall between units (impractical because of overhead bus), no oil
bund; main road adjacent
Photo 5: Fernhill ZSS: subject to verification, bund drainage from T1 looked to flow into T2 bund using a PVC
drainage pipe; non fire retardant, no flame trap. Tee joint in T2 bund, connection T1 and the drainage sump
Photo 6: Fernhill ZSS T1 – oil leaking from sensor cable glands; Photo 7: Willowbank ZSS – observed encroachment of residential
VT fuse caps on to of transformer incorrectly fitted apartments looking directly into ZSS assets over the top of
boundary wall
— None of the three lines have dedicated protection associated with them at Mosgiel substations. It is not recommended
to rely on zone 2 of distance protection at the remote substation as primary protection for busbar faults.
— No busbar protection scheme is implemented for the 33kV busbars, therefore both Line 1 and Line 2 incomers as
well as the busbar are protected by zone 2 distance protection between Waipori generation and Halfway Bush GXP.
Any 33kV bus fault would operate the distance element.
— No information provided regarding coordination between zone 2 protection of the incoming feeders and the
downstream feeders and transformer protection.
— The latest updated calculation provided is 1992, this is significant amount of time, where many changes of the
network loading, configuration and fault levels could have occurred. The setting file of the zone substations indicate
that there are 2 calculations reference 88 and 170 dated 2004, to calculate backup earth fault for both transformer
11kV incomers in the substations 11kV busbar. These calculations are not included in the provided documents.
— The primary side of the two 10 MVA transformers is protected by Instantaneous Earth fault and IDMT overcurrent.
The main protection for the secondary side is Restricted Earth Fault/leakage relay. Transformers of this size would
typically have transformer differential protection as primary protection and IDMT overcurrent and earth fault to
properly coordinate with the 11kV feeders.
— Only distance protection covers Alexandra ZSS’s two incoming feeders (the Rox-Alex lines). From Alexandra ZSS,
a single line supplies Omakau ZSS and Lauder Flat ZSS. The Omakau-Lauder is protected by over current and earth
fault protection is installed, but there is no distance protection, so there is no backup scheme for this line. This is not
uncommon for distribution lines, but this is acting as a sub transmission line.
— There is no 33kV or 11kV busbar protection. There may be protection provided by overcurrent at Transpower-Clyde
substation, but details of this were not available.
— The transformer is properly protected by differential protection as primary protection, and overcurrent and earth fault
protection as a backup on the 11kV side. However, the 33kV side of the transformer was not provided with
overcurrent or earth fault as a backup for faults on the 33kV side of the transformer. If the differential protection
failed to clear faults on the 33kV of the transformer, then the supply will be lost for the whole zone substation as the
second line of protection is overcurrent and earth fault at the main incomers. The setting file does not include setting
for feeder the incomers CB 3142 and CB 3122, also the protection coordination calculations does include these two
feeders as part of the coordination study.
— The 6.6kV panel incoming feeders are protected by over current and earth fault protection. This protection serves as
a backup protection for the 6.6kV feeder and the restricted earth fault protection of the transformer secondary.
— The protection scheme at Smith Street zone substation seems adequate, however no protection coordination
calculation was provided.
— The setting of the earth fault includes instantaneous setting and time delayed elements, for all incomers and feeders.
It is not clear how coordination is achieved between the 6.6kV feeders and the incomers with such low setting
currents. No protection calculation records were available for the substation, therefore it is not possible to assess the
coordination.
— Only two test records were provided. Protection test records for all feeders and transformers were carried out in 2005
and only one feeder and one transformer in 2008. The records indicate that some adjustment was required for the
earth fault protection pickup time.
CROMWELL SUBSTATION
Aurora distribution network around Cromwell receives power from Transpower through several 33kV connections at the
Cromwell GXP. However, these Transpower connections seems to be omitted from the ‘High Level Network Protection
SLD - 20727’. This makes it difficult to follow the SLD. Generally, all connections to bus bars at all substations should
be shown or referred to in the SLD, regardless of who owns those assets. The ownership boundaries, if any, should also
be shown in these SLDs, which is also seen to be missing in the 20727 SLD.
As per the ‘Aurora Energy Asset Management Plan 2006-2016’, the power received from Transpower is used to supply
the Cromwell Zone substation and the two stepup auto transformers at the Cromwell GXP, which supplies power to the
Wanaka Area. All these supply connections and a high level description of the protection scheme adopted to protect these
connections are shown in the SLD 20727 provided by Aurora. As part of this review, the protection arrangements at the
Cromwell zone substation and its 33kV incomer connections only will be analysed.
— At the Cromwell GXP end, these two 33kV connections (CB 1032 and CB 1092) are protected by two old
electromechanical over current and earth fault relays owned by Transpower. However, at the Cromwell zone
substation end, the 33/11kV transformers and the 11kV feeders are all protected by numerical protection relays that
are installed around 2003- 2006. The Meg generation feeder, which contains a 33/6.6kV, 4 MVA transformer seems
to have no protection on the 33kV side as per the SLD 20727. There is also a ripple injection unit, a couple of step
down transformers and a mobile substation connected on the 33kV side of the Cromwell zone substation. The step
down transformers are seen to be protected by fuses, and the mobile substation seems to be protected by transformer
differential protection (as per the setting data base). However, the protection equipment protecting the ripple
injection unit is not clear.
— The protection scheme at Cromwell GXP is arranged so that if the CB 1032 or 1092 opened manually or due to a
protection operation, the corresponding 33/11kV transformer downstream in the Cromwell zone substation is tripped
out.
— At Cromwell zone substation, the transformer 1 is protected by a single SEL 351S relay, plus Buchholz, pressure
relief and winding temperature protections. The SEL 351S relay contains over current, earth fault, switch on to fault,
restricted earth fault (11kV winding) and circuit breaker failure. All these protections are provided on the 11kV side,
and no protections are provided on the 33kV side other than the Transpower 33kV protections upstream.
— Arc flash protection is provided at the 11kV bus bar and at the 11kV circuit breakers at the Cromwell zone
substation, while SEL 351S relays are provided at all the 11kV feeders and the 11kV bus coupler. All feeders are
provided with over current, earth fault, switch on to fault and circuit breaker fail protection functions together with
single shot auto reclose.
Review summary:
The following high level comments can be made regarding the protection scheme at the Cromwell GXP and the
Cromwell zone substation based on the evidence in the documents mentioned above:
— The protection single line diagrams do not describe all associated details in sufficient detail. Examples: the drawing
20727 do not show the Transpower network connections or ownership boundaries in detail, the drawing 3C/03E/047
do not adequately cross reference to related drawings.
— The over current protection setting at transformer 1 is set at 800 A at the 11kV incomer (15.3 MVA), while the same
setting at transformer 2 incomer is 600 A (11.43 MVA). These numbers correspond to significantly high MVA
ratings compared to each transformer’s rated capacity, which are 10 MVA and 7.5 MVA respectively. The setting
calculation provided seems to have considered the capacity of the 11kV feeder cables, however, it is not clear
whether the transformer’s over load capabilities are considered when selecting these settings. It is recommended that
these setting calculations be revisited, as significant overloading of the transformers could affect the life of the
transformers in the long term.
— From the information provided it is not clear whether the two 33kV incomers are paralleled through the isolators /
switches 3837 and 3824 on the 33kV side. If these are operated in parallel, then there is a risk that both the 33kV
incomers could trip (through the instantaneous setting at the Transpower 1032 and 1092 over current relays) for a
fault, resulting in an outage at the Cromwell zone substation.
— At transformer 1, only the Transpower electromechanical relay is provided to protect the transformer against 33kV
winding / side faults. If this relay is failed, then there is no dedicated protection on the transformer 33kV side, and
the upstream Transpower protection at the Cromwell GXP (at feeder 1082 or 1042) will need to operate to clear the
fault. However, this won’t initiate the intertripping scheme at Transformer 1 and, hence, the 11kV circuit breaker at
the Cromwell zone substation (CB 830) will remain closed. This could ultimately trip the other transformer also
because of back feeding to the fault if the two transformers are operated in parallel from the 11kV side. Similar risk
also exists for breaker failure conditions at the 1032 and 1092 circuit breakers also, since there is no breaker failure
protection at the 1032 and 1092 circuit breakers.
— No dedicated protection is provided at the 33kV Meg generation feeder. This reduces the reliability of the Cromwell
zone substation transformer 2 33kV incomer, as it can be lost due to a fault on the 33kV Meg generation transformer
unnecessarily.
— The protection setting calculation 103 does not consider the protection coordination with the fuses and other
protections installed at the ripple injection unit (connected to 33kV side through isolator 3827). It is recommended to
analyse these settings also as there could be potential coordination issues with these protections and the upstream
instantaneous Transpower over current protections at the 1032 and 1092 circuit breakers.
— The protection setting calculation no: 103 provided by Aurora dates back to 2006. Subsequently, there has been an
arc flash protection retrofit at around 2011 at the Cromwell zone substation. Aurora has modified the protection
— All Aurora owned protection relays at the Cromwell zone substation are numerical type. If these relays don’t have
self-monitoring, they need to be tested every 4 years, however if they have self-monitoring, the testing only need to
be carried out every 10 years (as per NZ electricity code - Schedule 8.3, Technical Code A, Appendix B). However,
the measurement circuits of these relays need to be tested every 4 years as per the same code. From the evidence that
Aurora provided, these maintenance tests seems not done in line with these time frames.
— The protection setting calculation discussed in calculation no: 103 seems to follow a nonstandard approach referring
to fault MVA rather than the fault current. It should be noted that analysis with reference to fault current is the
standard practice when analysing current based relays like over current and earth fault protections. The protection
coordination analysis also seems to be based on bus fault levels rather than contributions through the individual
circuits, which on some occasions can lead to misleading conclusions.
— As with Cromwell, the protection single line diagrams do not describe all associated details in sufficient detail. In
SLD 3C/04E/073, the circuit breaker numbers are missing, and also the Transpower connections.
— As per the Access setting database, a number of static ASEA relays (overcurrent and earth fault) are in service at
Queenstown zone substation (some of these ASEA relay settings seems not complete in setting data base). However,
these relays are not seen in the SLD 3C/04E/073. As per the older setting calculation sheet provided (calculation no:
49), these settings seem to be associated with the three 33kV incoming feeds from Transpower upstream. On the
other hand, the setting database does not seem to have the settings related to any of the transformer protection relays
(RACID / SPAD 346C).
— As per the SLD 3C/04E/073, the current transformer ratios used with protection relays seems not selected in a logical
manner. For example, the CT1 on the 33kV side of transformer 1 have a maximum ratio of 200/1A, while some of
the 11kV feeders have CT ratios of 1200/1A. Note that the transformer 1 has a maximum rating of 20 MVA, which
means the maximum load current on the 33kV side could be in the order of 350A. This means the CT1 may be
overload by about 175% under normal operation even if the 200/1A ratio is used, which could cause damage to the
CTs (There was no clear information to determine what is the maximum service load on the transformer based on the
supplied data. However, the setting database shows that the over current function on the 11kV side of the same
transformer is set at 1200A, which is approximately 120% of the 20 MVA rating of the transformer. This is seen to
be about 400 A on the 33kV side of the transformer).
— The setting calculation sheets provided by Aurora dates back to 1994 – 2005. Nevertheless, the setting database
shows that with the upgrade of protection systems on the transformer 1 side, a setting revision was also carried out
on all the feeders with upgraded protection relays in 2013-14. However, the settings on the older protection relays
seems to be still based on the calculations performed around 2005. Also, the protection calculation sheets provided
doesn’t seem to verify the CT requirements as part of the setting calculation process. Considering that 5P10 CTs are
used in some circuits with very low CT ratios compared to the fault level (As per the data provided, the 3ph fault
level on the 33kV side is 5.14 kA in 2013 for example), it is recommended to revisit all the CT requirements at the
substation to verify whether they are sufficiently sized to work with the protection relays. Note that the similar type
of CTs are also used for restricted earth fault and transformer differential protections also.
— At transformer 1 and 2, only the SPAD346C relays are provided to monitor faults on the 33kV winding. Therefore, if
this relay fails, then the transformer 33kV faults are only detected by the relays on the Transpower 33kV incoming
feeders. The setting calculation 49 shows that all these three protection relays are set identically and, therefore, could
trip at the same time under such a scenario. This could cause an outage at the Queenstown zone substation. It is
recommended to have a separate relay on the 33kV side (an OC relay) to minimize the possibility of this occurring.
— Some of the protection settings and calculations at the Queenstown substation are old (>13 years). Note that the NZ
Electricity code requests each AC system asset owner to check the protection settings and coordination every 4 years
(Schedule 8.3, Technical Code A, Appendix B).
— All Aurora owned protection relays at the Queenstown zone substation are either numerical type or static type. Some
of these relays seems to have self-monitoring as per the SCADA point list provided, however some relays (especially
the static relays) seems to have no self-monitoring. The relays that don’t have self-monitoring, need to be tested
every 4 years, however the ones that have self-monitoring, only need to be tested every 10 years (as per NZ
electricity code - Schedule 8.3, Technical Code A, Appendix B). However, the measurement circuits of these relays
Project No PS109832 WSP
Independent review of electricity networks
Final report Page B-14
Aurora Energy
need to be tested every 4 years as per the same code. From the evidence that Aurora provided, these maintenance
tests seems not done in line with these time frames.
— Year: the year substation capacity will be exceeded based on current demand and growth forecasts. We note demand
forecast are currently being revised.
— N-1 and Pr(N-1): the value of energy at risk should one transformer fail excluding and including application of
probabilities of failure, respectively. Failure of a transformer is expected to result in a 1 month outage until supply is
restored.
— N-2 and Pr(N-2): the value of energy at risk should two transformers fail excluding and including application of
probabilities of failure, respectively. Failure of a transformer is expected to result in a 1 month outage until supply is
restored.
— Minor and Pr(Minor): the value of energy at risk of a minor repairable failure excluding and including application
of probabilities of failure, respectively. A minor (repairable failure) outage is assumed to be 1 week.
NORTH EAST VALLEY >2040 $- $254.5 $5.3 $0.06 $0.00 $0.00 $0.06
Lauder Flat >2040 $0.1 N/A $0.0 $0.02 N/A $0.00 $0.02
Coronet Peak >2040 $23.4 N/A $1.0 $0.01 N/A $0.00 $0.01
Lindis Crossing 2030 $253.5 N/A $10.6 $0.00 N/A $0.00 $0.00
WEIBULL MODEL
Weibull survivor curve analysis has been undertaken based on historical replacement data and the current asset age
profile. This approach used historical replacement data to calculate a Weibull distribution function. The Weibull
distribution parameters are then used to calculate the cumulative distribution function and subsequently the conditional
probability of failure, that is, the probability of failing in year (t+1) given that it has survived until year (t).
The calculation of the Weibull curve was undertaken using historical asset failure data to calculate a probability density
function that is then applied to calculate the conditional probability of an assets failure in a given year. The Weibull curve
is used as it is accepted and commonly used in industry to model asset failures.
Figure D.1 shows the calculated Weibull distribution plotted against the corresponding asset failure data set. A goodness
of fit test is undertaken to ensure the distribution is appropriate for use.
Where historical asset data isn’t available, we use the expected life of the asset and set the shape factor to provide a
reasonable probability of failure based on engineering judgement. If historical replacement volumes are known, we use
them to calibrate the curve.
Figure D.1 Weibull distribution plotted against the data sample – Hardwood poles
The conditional probability (shown as the failure rate in the curve below) was then applied to assess the Probability of
Failure for each asset.
— The end of life assessment undertaken by Aurora was reasonably accurate and resulted in replacement of
appropriately deteriorated assets that had reached their end of life. The Weibull parameters that were derived
(characteristic age and shape factor) are reasonable when compared to industry guidelines and common practice in
electricity businesses in Australia and New Zealand.
— The age of assets is reasonably accurate. Most businesses have some uncertainty in the age of assets.
— The analysis results derived for assets are not affected by past decisions. Past decision to undertake targeted
replacement programs can skew the calculation of the Weibull parameters.
— The asset data is sufficiently complete to provide a reasonable estimate within the limitation of the accuracy of our
report.
ADVANCED TECHNIQUES
Exploratory descriptive data analysis was the first step of the process in which relationships between key variables were
examined. Based on the initial steps, it was evident that the data was noisy, and that pole age alone would not be able to
explain all the variance in the data. This process was repeated with several variables such as pole diameter and timber
strength.
ZONE SUBSTATION T1 T2
Berwick 953
Dalefield 743
Earnscleugh 663
Ettrick 731
Fernhill 777
Omakau 695
Remarkables 480
Roxburgh 413
Cromwell T1 -5.4 1
Cromwell T2 -4.8 1
Dalefield T1 -3.4 1
Outram T2 -2.9 1
Clyde-Earnscleugh T2 -2.9 1
St Kilda T1 -2.5
Fernhill T1 -2.5
Fernhill T2 -2.5
Outram T1 -2.4
Queenstown T2 -1.7
Mosgiel T1 -1.7
Mosgiel T2 -1.7
Wanaka T2 -1.7
Queensberry T1 -1.6
Arrowtown T1 -0.9
Arrowtown T2 -0.9 1
Wanaka T1 -0.6
Neville St T2 -0.4
Cardrona T1 -0.4
Corstorphine T1 -0.1
Corstorphine T2 -0.1
Smith St T1 0.0
Ettrick T1 0.2
Frankton T1 0.3 1
Smith St T2 0.4
Queenstown T1 1.3
Alexandra T1 1.3
Alexandra T2 1.3
Neville St T1 1.5
Commonage T1 6.1
Commonage T2 6.1
Frankton T2 7.8
Berwick T1 8.4
Ward St T1 8.6
Roxburgh T1 9.7
Camphill T1 12.1
— Year: the year substation capacity will be exceeded based on current demand and growth forecasts. We note demand
forecast are currently being revised
— N-1 and Pr(N-1): the value of energy at risk should one transformer fail excluding and including application of
probabilities of failure, respectively. Failure of a transformer is expected to result in a 1 month outage until supply is
restored
— N-2 and Pr(N-2): the value of energy at risk should two transformers fail excluding and including application of
probabilities of failure, respectively. Failure of a transformer is expected to result in a 1 month outage until supply is
restored
— Minor and Pr(Minor): the value of energy at risk of a minor repairable failure excluding and including application
of probabilities of failure, respectively. A minor (repairable failure) outage is assumed to be 1 week
North East Valley >2040 $- $254.5 $5.3 $0.06 $0.00 $0.00 $0.06
Lauder Flat >2040 $0.1 N/A $0.0 $0.02 N/A $0.00 $0.02
Coronet Peak >2040 $23.4 N/A $1.0 $0.01 N/A $0.00 $0.01
Lindis Crossing 2030 $253.5 N/A $10.6 $0.00 N/A $0.00 $0.00
8 4 2 1
7 3 2
8 5 4
7 5
8 7
The prioritisation list in Table F.1 sets out the preferred approach based on information available and the network
configuration at the time of issuing this report. Should new information become available or should an outage force
reconfiguration of the network, it may be necessary to reassess the prioritisation of the risks.
When considering the prioritisation, we note that there are interdependencies between the options. For example,
accepting the risk of sub transmission cables, means that the risk resulting from a transformer failure needs to be
reassessed as the assumption regarding available spare capacity in the network may not be valid.
A further prioritised list for Distribution Switchgear and specifically the risk around L&C and Statter RMU’s is provided
in Table F.2. Refer section 9 of this report for details on this risk area.
Zone substation Alexandra ZSS HKK and HLC circuit breakers RELIABILITY/
circuit breakers Circuit Breakers are not maintained internally. 14 SAFETY 2
Zone substation Arrowtown ZSS HKK circuit breakers are not RELIABILITY/
circuit breakers Circuit Breakers maintained internally. 2 SAFETY 2
Statter
Distribution distribution RELIABILITY/
switchgear switchgear List provided 5 SAFETY 3
Transformer condition
modelled to be poor. Tap
changer has not been
maintained within the required
Zone substation schedule resulting in elevated
transformers Green Island T1 risk. 1 RELIABILITY 3
Long and
Crawford
Distribution distribution RELIABILITY/
switchgear switchgear List provided 15 SAFETY 5
Transformer condition
Zone substation Andersons Bay modelled to have elevated
transformers T1 and T2 probability of failure. 2 RELIABILITY 5
Statter
Distribution distribution RELIABILITY/
switchgear switchgear List provided 23 SAFETY 7
Neville Street
Zone substation ZSS Circuit Oil circuit breakers. About to be RELIABILITY/
circuit breakers Breakers decommissioned 31 SAFETY 7
Transformer condition
modelled to be poor. Tap
changer on T2 has not been
maintained within the required
schedule resulting in elevated
Zone substation Port Chalmers risk. No DGA results, so no
transformers T1 and T2 internal condition data. 2 RELIABILITY 7
Distribution RELIABILITY/
switchgear ABB RMUs List provided 3 SAFETY 8
Long and
Crawford
Distribution distribution RELIABILITY/
switchgear switchgear List provided 44 SAFETY 8
Subtransmission
underground North City (oil Oil insulated cable with
cable insulated cable) significant historical leaks 5.0km RELIABILITY 8
Clyde-
Zone substation Earnscleugh ZSS HKK circuit breakers are not RELIABILITY/
circuit breakers Circuit Breakers maintained internally. 1 SAFETY 8
C83B3638-A2E2-
4AEE-8E6F-
9BF41C045200 3.3/6.6/11/22kV RMU Dunedin 1961 STATTER 3
F2519C81-DB7C-
4911-841F-
A62EF2450066 3.3/6.6/11/22kV RMU Dunedin 1961 STATTER 3
8297B7FA-A450-
47F1-9030-
95AAA0264B31 3.3/6.6/11/22kV RMU Dunedin 1961 STATTER 3
82A0FB5F-A0AA-
4860-ACDD-
9F2AC528300B 3.3/6.6/11/22kV RMU Dunedin 1961 STATTER 3
AFADEA10-77CD-
4422-8B9A-
4428EBE1C55E 3.3/6.6/11/22kV RMU Dunedin 1961 STATTER 3
080D7827-F384-
429B-82DC-
286B3FF88164 3.3/6.6/11/22kV RMU Dunedin 1973 L&C 5
B343FE68-7453-
4AB5-8738-
3DDB8D2A76DE 3.3/6.6/11/22kV RMU Dunedin 1973 L&C 5
23AE15CF-A5C3-
4095-991B-
0E6A2619F4FD 3.3/6.6/11/22kV RMU Dunedin 1973 L&C 5
8CF4331D-B954-
4A7D-A81E-
13BFEA5CF7FA 3.3/6.6/11/22kV RMU Dunedin 1976 L&C 5
05E61AAA-73DD-
4731-820D-
FE02C30B5E80 3.3/6.6/11/22kV RMU Dunedin 1976 L&C 5
336B1A9C-EDC4-
4A8E-BF31-
0A7164706666 3.3/6.6/11/22kV RMU Dunedin 1982 L&C 5
BAD70A40-FAE2-
4104-A48B-
33E48B423DB6 3.3/6.6/11/22kV RMU Dunedin 1982 L&C 5
644B02BB-C58B-
4BE4-9FAD-
2DC96769B8B2 3.3/6.6/11/22kV RMU Dunedin 1987 L&C 5
6B2F2342-BD41-
4BFE-834A-
E64CFEEA17BC 3.3/6.6/11/22kV RMU Dunedin 1987 L&C 5
60C61DD5-0ACC-
4808-9901-
6636E7B75670 3.3/6.6/11/22kV RMU Dunedin 1988 L&C 5
56B8CBFF-7530-
4F68-A42C-
11579C297572 3.3/6.6/11/22kV RMU Dunedin 1988 L&C 5
2BDB6944-DD2B-
4FA5-8F79-
BE4B6AD0E1C9 3.3/6.6/11/22kV RMU Dunedin 1989 L&C 5
1B3D6B6C-5333-
41E9-94D7-
FA646976951A 3.3/6.6/11/22kV RMU Dunedin 1988 L&C 5
C62456A5-BE25-
4F89-8A24-
2809771C6C99 3.3/6.6/11/22kV RMU Dunedin 2000 L&C 5
0DFF9BB7-5BEF-
48EE-B6BC-
1EA1E72C2E2D 3.3/6.6/11/22kV RMU Dunedin 2004 L&C 5
2C530302-18DD-
4277-87E6-
FA90556D35F2 3.3/6.6/11/22kV RMU Dunedin 1959 STATTER 7
D9655233-47A4-
4A4C-B939-
79B1AA565337 3.3/6.6/11/22kV RMU Dunedin 1959 STATTER 7
70816C72-E91B-
42E5-B354-
1360ED0E5EEB 3.3/6.6/11/22kV RMU Dunedin 1959 STATTER 7
C10E7C5F-5DB4-
49CF-817E-
984561829302 3.3/6.6/11/22kV RMU Dunedin 1959 STATTER 7
B9679D65-2A0B-
47EA-BB7D-
9BAB6CE20320 3.3/6.6/11/22kV RMU Dunedin 1959 STATTER 7
C521CCE0-6C3E-
40AE-98F0-
3C4E73EE7EAB 3.3/6.6/11/22kV RMU Dunedin 1959 STATTER 7
8012C580-ADA0-
4DD3-A13B-
6F45CE38DF66 3.3/6.6/11/22kV RMU Dunedin 1959 STATTER 7
9FEC5228-D020-
4232-B1E4-
19E951775C9A 3.3/6.6/11/22kV RMU Dunedin 1959 STATTER 7
6A77D9D0-E689-
4A93-94A8-
CD2B750FA9B0 3.3/6.6/11/22kV RMU Dunedin 1959 STATTER 7
DE0141C4-0DF2-
4EBE-98A0-
1127BC461EBA 3.3/6.6/11/22kV RMU Dunedin 1961 STATTER 7
F82EA162-AA5C-
4468-9DFC-
18CE66267BCF 3.3/6.6/11/22kV RMU Dunedin 1961 STATTER 7
AA6F196B-40AF-
496B-9D53-
9F82E12783A8 3.3/6.6/11/22kV RMU Dunedin 1961 STATTER 7
C12D36FD-745F-
4536-898C-
F7FD1C4133FD 3.3/6.6/11/22kV RMU Dunedin 1967 STATTER 8
31F44D0B-8A24-
418E-8182-
73BD9A44E943 3.3/6.6/11/22kV RMU Dunedin 1967 STATTER 8
431DFF79-6E80-
4424-B3D8-
5D3FA007928C 3.3/6.6/11/22kV RMU Dunedin 1967 STATTER 8
3D0A65C9-929A-
42E5-B4AF-
32BCF4630AEE 3.3/6.6/11/22kV RMU Dunedin 1967 STATTER 8
D129DA1A-0AA3-
488B-A903-
6DE6061BED4B 3.3/6.6/11/22kV RMU Dunedin 1967 STATTER 8
5F02A4FE-45C7-
4068-9E4E-
77F9D5B1C317 3.3/6.6/11/22kV RMU Dunedin 1967 STATTER 8
8BA33168-45D0-
40CE-A774-
6582BA7872D1 3.3/6.6/11/22kV RMU Dunedin 1967 STATTER 8
B885425B-7B12-
4B22-8295-
F42EB33C7E8D 3.3/6.6/11/22kV RMU Dunedin 1967 STATTER 8
6C7B4BEC-69D8-
4FF9-ACFD-
BC12F247D45B 3.3/6.6/11/22kV RMU Dunedin 1967 STATTER 8
E814D1CF-69DB-
43D2-8FEC-
750509CBF721 3.3/6.6/11/22kV RMU Dunedin 1968 STATTER 8
7039439B-5856-
44B2-85A5-
1BA95F56EF22 3.3/6.6/11/22kV RMU Dunedin 1968 STATTER 8
5DB506F8-D7DD-
42DE-89EC-
C87256373E05 3.3/6.6/11/22kV RMU Dunedin 1971 L&C 8
2BCC42CC-521A-
404E-8567-
3F723F932A1B 3.3/6.6/11/22kV RMU Dunedin 1972 L&C 8
34F05AB6-0692-
4625-A61D-
82FAF1B1AA09 3.3/6.6/11/22kV RMU Dunedin 1972 L&C 8
CD606C65-8DE2-
4CC2-B72A-
D79E73CF58D6 3.3/6.6/11/22kV RMU Dunedin 1972 L&C 8
13750305-70B5-
4CD0-982A-
BC42A2959E08 3.3/6.6/11/22kV RMU Dunedin 1972 L&C 8
9E24EAB2-8C3F-
47EB-8E70-
1509D688A233 3.3/6.6/11/22kV RMU Dunedin 1972 L&C 8
5448A46A-2C26-
403A-BA03-
7CCBAA5E647E 3.3/6.6/11/22kV RMU Dunedin 1972 L&C 8
E13FADD5-E001-
4F7D-B8BA-
DA5AFB6C3BC9 3.3/6.6/11/22kV RMU Dunedin 1973 L&C 8
19EA21CE-8B7B-
4FE4-A114-
39109BB0F279 3.3/6.6/11/22kV RMU Dunedin 1976 L&C 8
FD32DC34-ADDC-
4413-83DB-
E558F3970309 3.3/6.6/11/22kV RMU Dunedin 1977 L&C 8
10EC2FDF-59F9-
4E5B-A366-
61619D9D8A44 3.3/6.6/11/22kV RMU Dunedin 1977 L&C 8
C8A8D633-BECA-
4BDC-BC83-
DA16A438257E 3.3/6.6/11/22kV RMU Dunedin 1977 L&C 8
AB9C755C-7E98-
42DE-8DA7-
BA22E5BB362B 3.3/6.6/11/22kV RMU Dunedin 1976 L&C 8
23D864BF-16C4-
4CEE-8903-
E896C153C6D3 3.3/6.6/11/22kV RMU Dunedin 1977 L&C 8
12CB3FC3-CA51-
4691-882A-
32486C666B73 3.3/6.6/11/22kV RMU Dunedin 1976 L&C 8
35A1F352-CBC9-
407D-8BD1-
A6AE2EB22FFD 3.3/6.6/11/22kV RMU Dunedin 1977 L&C 8
35F01376-30BF-
4209-A56A-
35AC65CFC0BC 3.3/6.6/11/22kV RMU Dunedin 1976 L&C 8
D3A37958-DEBC-
489B-A1C9-
6BFE47DF2605 3.3/6.6/11/22kV RMU Dunedin 1977 L&C 8
F1DDDDE6-E497-
4453-AB01-
63A198C221F7 3.3/6.6/11/22kV RMU Dunedin 1977 L&C 8
A8715E14-65C0-
4626-9C50-
4749BBDDBF8C 3.3/6.6/11/22kV RMU Dunedin 1977 L&C 8
126DB235-98C0-
46CA-ADCC-
8B06372CBE92 3.3/6.6/11/22kV RMU Dunedin 1977 L&C 8
78361FD1-0A5F-
47FD-91A0-
9A70C9B32F1E 3.3/6.6/11/22kV RMU Dunedin 1978 L&C 8
349537A9-6307-
40E8-9546-
6B03DCAAFF3D 3.3/6.6/11/22kV RMU Dunedin 1979 L&C 8
30D2C132-0FBB-
4B3F-A5C2-
C22CBA30A193 3.3/6.6/11/22kV RMU Dunedin 1979 L&C 8
0E8DBBF9-0EB5-
4FA7-961A-
B0FA05C3B508 3.3/6.6/11/22kV RMU Dunedin 1980 L&C 8
C046D345-2EF6-
4AC6-9D7E-
AECC141E5A9B 3.3/6.6/11/22kV RMU Dunedin 1980 L&C 8
689F8031-03D3-
4707-8B4E-
5A7EE66587C9 3.3/6.6/11/22kV RMU Dunedin 1980 L&C 8
15135BF1-31D0-
47D7-9618-
90C4FBAE9FAF 3.3/6.6/11/22kV RMU Dunedin 1982 L&C 8
BED939B4-5D41-
4797-AA51-
712A5D2AD8B6 3.3/6.6/11/22kV RMU Dunedin 1983 L&C 8
238BD63F-1868-
4E60-90A3-
B545315608C1 3.3/6.6/11/22kV RMU Dunedin 1983 L&C 8
BFB00732-21F4-
4E99-8C12-
D5CE69140AA2 3.3/6.6/11/22kV RMU Dunedin 1983 L&C 8
319FBC86-4218-
4825-9AC4-
54432C67CCCA 3.3/6.6/11/22kV RMU Dunedin 1985 L&C 8
8A6FA777-4AE2-
4DE1-BE2C-
6518B902524F 3.3/6.6/11/22kV RMU Dunedin 1985 L&C 8
E82B9B54-5336-
4EB2-B909-
DDDB9DEB4A7C 3.3/6.6/11/22kV RMU Dunedin 1984 L&C 8
47FE385A-9EB7-
42E7-AFD1-
D97874D147B6 3.3/6.6/11/22kV RMU Dunedin 1984 L&C 8
50FF8644-87BB-
4D7A-B4CE-
88088F358542 3.3/6.6/11/22kV RMU Dunedin 1984 L&C 8
F2E9BBCB-E552-
4CAA-9960-
A8EC282F1D44 3.3/6.6/11/22kV RMU Dunedin 1984 L&C 8
9E8A74FF-E508-
41DE-871D-
11996334B545 3.3/6.6/11/22kV RMU Dunedin 1985 L&C 8
ABE3D0D2-77FD-
47F6-8049-
47ECBCE9FEBE 3.3/6.6/11/22kV RMU Dunedin 1988 L&C 8
BE67C427-DCAB-
4D9E-9AD3-
A82A9B67B0D2 3.3/6.6/11/22kV RMU Dunedin 1987 L&C 8
D6EB1BD4-2BF6-
444F-A8DD-
46238CE1CFD0 3.3/6.6/11/22kV RMU Dunedin 1989 L&C 8
10B4BD9B-ED87-
4060-8515-
BF9DE58F4D9C 3.3/6.6/11/22kV RMU Dunedin 1988 L&C 8
E5DBE9D2-79A1-
4A3F-8C8E-
2F5A60C9009B 3.3/6.6/11/22kV RMU Dunedin 1989 L&C 8
96CE12FE-4876-
4762-918A-
52FA62DAA6ED 3.3/6.6/11/22kV RMU Dunedin 2005 L&C 8
F8A44BF5-AFD8-
4952-B6DC-
CFB733A7D396 3.3/6.6/11/22kV RMU Dunedin 2007 ABB 8
4F7FC46F-0231-
4E98-8A10-
7EC4084AA64B 3.3/6.6/11/22kV RMU Dunedin 2007 ABB 8
E84BF420-B5C6-
415B-9E2C-
9FD0BC2935D8 3.3/6.6/11/22kV RMU Dunedin 2007 ABB 8