S Curve Cash Flow Manpower Equip
S Curve Cash Flow Manpower Equip
MONTH
CATEGORY
1 2 3 4 5 6 7 8 9 10 11 12
Project Manager 1 1 1 1 1 1 1 1 1 1 1 1
Project Engineer 1 1 1 1 1 1 1 1 1 1 1 1
Project Architect 1 1 1 1 1 1 1 1 1 1 1 1
Structural Engineer 1 1 1 1 1 1 1 1 1 1 1 1
Safety Engineer 1 1 1 1 1 1 1 1 1 1 1 1
Sanitary Engineer 1 1 1 1 1 1 1 1 1 1 1 1
Electro-mechanical Engineer 1 1 1 1 1 1 1 1 1 1 1 1
Field Engineer 1 1 1 1 1 1 1 1 1 1 1 1
Project Admin 1 1 1 1 1 1 1 1 1 1 1 1
Office Engineer 1 1 1 1 1 1 1 1 1 1 1 1
Surveyor 1 1 1 1 1 1 1 1 1 1 1 1
Instrument Man 1 1 1 1 1 1 1 1 1 1 1 1
Foreman 1 1 1 1 1 1 1 1 1 1 1 1
Equipment Operators 6 6 6 6 6 6 6 6 6 5 4 3
Skilled Workers
Steel man 5 5 10 10 10 10 10 5 5 3 3
Welder 2 2 2 2 2 2 2 2 2 2
Mason 5 5 10 10 10 10 10 10 5 5
Carpenter 3 3 5 5 5 5 5 5 2 2 2
Plumber 3 3 6 6 6 6 6 3 3
Electrician 2 2 4 4 4 4 4 4 2
Laborers 10 20 40 60 60 60 60 60 60 60 20 10
Submitted by:
MONTH
CATEGORY / EQUIPMENT
1 2 3 4 5 6 7 8 9 10 11 12
Backhoe with breaker 1 1 1 1 1 1 1 1 1 1
Wheel Loader 1 1 1 1 1 1 1 1 1 1 1
Dump Truck 2 2 2 2 2 2 2 2 2 1 1 1
One Bagger Mixer 3 3 3 3 3 3 3 3 2 1
Concrete Vibrator 2 2 2 2 2 2 2 2 2 1
Bar Cutter 2 2 2 2 2 2 2 2 2 2
Bar Bender 2 2 2 2 2 2 2 2 2 2
Vibratory Plate Compactor 2 2 2 2 2 2 2 2 2 2 1
Oxy-acetylene 1 1 2 2 2 2 2 2 2 2
Welding Machine 1 1 2 2 2 2 2 2 2 2
6 6 6 6 6 6 6 6 6 5 4 3
Submitted by:
NO. OF MONTHS
DESCRIPTION OF WORK TOTAL COST (Php) Wt. %
1ST 2nd 3rd 4th 5th 6th 7th 8th 9th 10th 11th 12th
100%
DESIGN AND DETAILED 8.04%
A. 16,051,200.00 8.04%
ENGINEERING
87.5%
2.70% 2.70% 0.81% 0.81% 0.81% 0.81% 0.81% 0.81% 0.81% 0.81% 0.81% 0.81%
B. GENERAL REQUIREMENT 26,922,883.20 13.48%
75%
0.19% 0.58%
C. SITE LANDSCAPING 1,546,752.00 0.77%
62.5%
OVERHEAD WATER
0.27% 1.86% 2.66% 3.32% 3.99% 3.99% 3.99% 2.66% 1.99% 1.33% 0.53%
D. CIVIL WORKS 53,083,915.48 26.58%
50%
0.65% 1.96% 2.62% 4.45% 5.24% 4.45% 3.93% 1.96% 0.92%
E. ARCHITECTURAL WORKS 52,306,928.25 26.19%
0.16% 0.33% 0.33% 0.49% 0.49% 0.65% 0.65% 1.14% 1.14% 1.14% 37.5%
F. SANITARY /PLUMBING WORKS 13,030,393.34 6.52%
0.33% 0.67% 0.67% 1.00% 1.00% 1.00% 1.34% 2.34% 2.34% 2.68% 25%
G. ELECTRICAL WORKS 26,720,232.38 13.38%
12.5%
0.50% 0.88% 1.26% 1.26% 1.13%
H. COVERED TERMINAL 10,075,583.34 5.04%
MONTHLY 10.73% 2.96% 3.17% 5.12% 7.09% 8.91% 10.74% 12.19% 10.79% 11.47% 9.04% 7.79%
SCHEDULED PROGRESS (%)
CUMULATIVE 0.00% 10.73% 13.69% 16.86% 21.98% 29.07% 37.97% 48.71% 60.91% 71.70% 83.17% 92.21% 100.00%
MONTHLY 10.86% 3.82%
ACTUAL PROGRESS (%)
CUMULATIVE 0.00% 10.86% 14.68%
ADVANCE (SLIPPAGE) % 0.13% 0.98%
MONTHLY 21,435,776.64 5,915,415.79 6,325,012.72 10,218,969.03 14,161,413.33 17,789,950.07 21,451,435.05 24,353,961.06 21,554,232.00 22,917,961.23 18,054,531.72 15,559,229.35
SCHEDULED ACCOMP. AMOUNT
CUMULATIVE 21,435,776.64 27,351,192.43 33,676,205.15 43,895,174.19 58,056,587.52 75,846,537.59 97,297,972.63 121,651,933.69 143,206,165.69 166,124,126.92 184,178,658.64 199,737,888.00
MONTHLY 21,692,467.20 7,624,320.00
ACTUAL ACCOMP. AMOUNT
CUMULATIVE 21,692,467.20 29,316,787.20
Submitted by: