Construction of RCC Bridge No 1/1 On Kathalguri To Sh2 Viasipansila Pt-Iii

This document contains a bill of quantities for the construction of a 3 span RCC bridge with a total length of 102.38 meters and width of 8.45 meters. It includes estimates for excavation, reinforcement, concreting works for the well foundations and superstructure components. The foundation will consist of 2 abutment wells and 2 pier wells, with estimated concrete volumes of 148.15 cubic meters for the curb and 1008.58 cubic meters for well steining. Reinforcement quantities are also provided for the various RCC components.

Uploaded by

Hoque joynul
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
129 views

Construction of RCC Bridge No 1/1 On Kathalguri To Sh2 Viasipansila Pt-Iii

This document contains a bill of quantities for the construction of a 3 span RCC bridge with a total length of 102.38 meters and width of 8.45 meters. It includes estimates for excavation, reinforcement, concreting works for the well foundations and superstructure components. The foundation will consist of 2 abutment wells and 2 pier wells, with estimated concrete volumes of 148.15 cubic meters for the curb and 1008.58 cubic meters for well steining. Reinforcement quantities are also provided for the various RCC components.

Uploaded by

Hoque joynul
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 6

521329347.

xls

CONSTRUCTION OF RCC BRIDGE No 1/1 ON KATHALGURI TO SH2 VIASIPANSILA PT-III


Bill of Quantities for Bridge Proper :

Span Arrangement = 3 X 24.75 M DL 102.38 M


Soffit Lvl 99.50 M
Over all Length = 76.12 M VC 1.20 M
HFL 98.60 M
Width Of super Str = 8.45 M LWL 91.7 M
(Two Lane Bridge without footpath ) LBL 91.00 M
Clear Carriage way Width = 7.50 FL 71.70 M
OFL 98.00 M
Type of Foundation : Well RCC

Type of Super Structure : R.C.C Girder

( 3 Nos RCC Girder / Span )

No of Piers = 2

Approx. Angle of repose for soil below river bed,F= 30 0


( Hence Sandy Soil )

Item N0 1:( Dismantling of existing Structure……. )

Total Qnty = 72.0 RM

Foundation
Item No 2 : (Excavation for structure ………. )

Total Qnty = (HFL -LBL) / 4 X Length of Proposed Bridge X Width of proposed Bridge
= 1222.11 Cum

Item No 3 : (Providing Temporary Island)

Total Qnty = 2 Nos

Item No 4 (Providing and laying of Cutting Edge…...)

No. of Abut Wells 2

No. of Pier Wells 2

Total Qnty. = 4.68 MT 4.68

Item No 5 A:( Providing and casting of controlled concrete RCC of specefied grade in well Curb….)
Abutment Well Pier Well
Outer dia of curb 7.15 m Outer dia of curb 6.15 m
Inner Dia dia of curb 5.40 m Inner Dia dia of curb 4.60 m
Height of curb 2.00 m Height of curb 2.00 m
Abutment 2
2
Qnty. = 2 X [ p/4 X 7.15 X 2.00 - 24.41 _- p /4 X 5.4 X 0.6 ]
_
= 84.23 Cum
Pier 2
2
Qnty. = 2 p/4 X 6.15 2.00 17.45 _- p /4 X 4.6 0.6 ]
X [ X - X
_
= 63.92 Cum
Total = 148.15 Cum
521329347.xls

Item No 5 B : Well Steining


Abutment Well Pier Well
Outer Dia of Well = 7.00 M Outer Dia of Well = 6.00 M
Inner dia of Well = 5.40 M Inner dia of Well = 4.60 M
Depth of Well = 20.00 M Depth of Well = 21.00 M
Depth of steining = 18.00 M Depth of steining = 19.00 M
No of Wells = 2 Nos No of Wells = 2 Nos
Vol. Of concr. = 560.79 Cum. Vol. Of concr. = 442.77 Cum.

Total Volume Of Concrete = 1003.57 Cum.


Add 0.5 % for prob. Variation = 5.02 Cum.
Total Volume of concrete in Steining = 1008.58 Cum.

Item No. 5 C Bottom Plugging


2 2
( 3.14 x 1.40 / 6 ) X ( 0.75 x 7.00 + 0.75 x 5.40 + 1.4 2
)) +
p/4 X 5.40 2 X 0.6 + 3.14X2.00 ( 7.00^2/8 + 2.00 ^2/6 )
= 44.38 + 13.74 + 10.66

= 68.79 Cum
2 2 2
( 3.14 x 1.40 / 6 ) X ( 0.75 6.00 + 0.75 + 4.60 X 1.4 )) +
p/4 4.60 2 X 0.6 + 3.14X1.71 ( 6.00^2/8 + 1.71 ^2/6 )
X
= 32.85 + 9.97 + 9.14

= 51.95 Cum

Total for 4 Nos Well = 241.48 Cum


Add 0 % Prob Variation = 0.00 Cum
Total Concreting in Bott. Plug = 241.48 Cum

Item No.5 E ( Top plug ):


2 2
qnty = 2 X p/4 X 5.4 X 0.50 + 2 X p/4 X 4.6 X 0.50

22.90 + 16.61589 = 39.51 Cum

Add 0.5 % Prob Variation = 0.20 Cum

Total qnty of Top plug = 39.7 Cum

Item No.5 F ( Well cap ):


2
Qnty = 2 X( 0.50 X p/4 X 7.0 X 1.20 + 1.00 X 3.20 X 8.45 X1.20 )
2
1.20 + 2 X p/4 X 6.0 X 1.20

= 178.91 Cum
Add 0.5 % Prob Variation = 0.89 Cum
Total = 179.81 Cum

Item No 6 / 7 : Sinking of well


Abutment Pier

I) Depth below bed level up to 3.00 m : Qnty = 6.00 m 6.00 m

II) Beyond 3.00 m up to 10.00 m : Qnty = 14.00 m 14.00 m

III) Additional depth beyond 10 m up to 20 m: Qnty = 20.00 m 20.00 m

IV) Additional depth beyond 20 m up to 30 m: Qnty = 0.00 m 2.00 m


521329347.xls

Item No.8 ( Sand filling ):


2
2
Qnty = 2 X p/4 X 5.4 X 17.20+ 2 X p/4 X 4.6 X18.20

= 787.60 + 604.8 = 1392.35 Cum

Total Depth of sand filling = 19.20 M 18.20 M

Item No 13 (Supplying,fitting and fixing HYSD reinforcement in provision for all RCC components in foundation…...)

a. Reinf. In Well curb = @ 75 Kg/m3 = 11.11 MT

b. Reinf. In Well steining @ 0.50 % of conc. vol.) = 39.59 MT

c. Reinf. In Abutment Well cap @ 1.50 % of vol.) = 13.19 MT

d. Reinf. In Pier Well cap @ 1.50 % of vol.) 10.87

Total = 74.76 MT

Add 1 % for wastage and laps = 0.75 MT

G.T. = 75.51 MT

Item No 14 (Supplying,fitting and fixing M.S. reinforcement in provision for all RCC components in foundation…...)

a. Lum Sum = MT

Substructure

Item No.15 ( R.C.C work in Substructure) Quantity = 317.44


Add 5 % for Pedestal, Tie, stiffener Column 15.87
Total Quantity = 333.31
I) Dirt wall =
Qnty. = 2 X ( 8.45 X 0.04 X 2.78
= 1.8759 m3

ii) Return Wall


Qnty. = 4 X 0.2 X 0.5 ( 0.6 + 2.78 ) 3.70
= 5.00 m3

iii) Abutment cap


Qnty. = 2 1.25 X 0.40 X 8.45
= 8.45 m3

iv) Abutment Shaft


Qnty. = 2 X 0.5 X( 1.25 + 2.52 ) + 8.45 X 6.20
= 197.25 m3

v) Pier Cap
Qnty. = 2 X [( 1.8 X 0.5 X 6.1 ) + 0.5 ( 1.8 + 1.6 ) ] X 0.5 X 6.1
.= 21.35 m3

vi) Pier Shaft


Qnty. = 2 X 5.80 X 1.6 X 4.50
= 83.52 m3
521329347.xls

Item No 16 (Supplying,fitting and fixing HYSD reinforcement in provision for all RCC components in Substructure…...)

a Reinf. In Abutment = @ 1.25 % of volm.) = 19.35 MT

b Reinf. In Pier shaft = @ 1.25 % of volm.) = 16.39 MT

c Reinf. In Abut. cap = @ 1.50 % of volm.) = 0.99 MT

d Reinf. In piercap = @ 1.00 % of volm.) = 3.35 MT

e Reinf. In Dirtwall = @ 1.00 % of volm) = 0.15 MT

f Reinf. In Returnwall = @ 1.00 % of volm) = 0.39 MT

Total = 40.63 MT

Add 1 % for wastage and laps = 0.41 MT

G.T. = 41.04 MT

Item No 17 (Supplying,fitting and fixing M.S. reinforcement in provision for all RCC components in Substructure…...)

a. Lum Sum = 0.00 MT

Item No 18 ( Supplying fitting and fixing in position Cast steel Rocker bearing ……. )

Total Nos = No of Span X No of girder / Span

= 0 X 3 = 0 Nos

Capacity of Each = Ton

Capacity of all = 0 X 0 Ton

= 0 Ton

Item No 19 ( Supplying fitting and fixing in position Cast steel Roller bearing ……. )

Total Nos and Capacity of all is same as Rocker bearing

Capacity of all = 0 Ton

Item No 20 ( Supplying fitting and fixing in position Elastomer bearing ……. )

Total Nos = 18

Volume Each = 17820 Cucm

Total Volume = 320760 Cucm

Item No 21 ( Furnishing and placine Reinforced / Pre stressed Cement concrete in Super Structure ….. )

B. RCC Grade M25

For solid Slab

Quantity / Span = 0 Cum

Total Quantity = 0 Cum


521329347.xls

For T Beam & Slab

Quantity / Span = 114.5 Cum

Total Quantity = 343.5 Cum

D. RCC / PSC grade M35

For T Beam & Slab


$=if(E7<4.38,11
Quantity /Span = Cum ###

Total Quantity = Cum

Item No 22 (Supplying,fitting and fixing HYSD reinforcement in provision for all RCC components in superstructure…...)

a. Reinf in Superstructure = @ 175.00 Qtl/span ) = 52.50 MT ###

b. Reinf in Approach Slab = @ 1.00 % of volm) = 1.31 MT

Total = 53.81 MT

Add 1 % for wastage and laps = 0.54 MT

Grand Total = 54.35 MT

Item No 23 ( Suppllying Fitting and fixing High Tensile steel wire / Strand………. )

Quantity /Span = 0 MT

Total Quantity = 0 MT

Item No 24( Providing and laying cement concrete wearing coat M 30 ………..)

Volume = Length of Bridge X Carriage way of X Thickness of W.C.

= 76.12 X 7.50 X 0.075

= 42.82 Cum

Item no 25 (Construction of pre cast RCC railing of M30 Grade ………………)

Length = 2X ( Over all length of Bridge + Length of Return wall )

= 2 X ( 76.12 + 7.40 )

= 167.04 Rm

Item no 26 ( Providing drainage spout complete……………. )

Considering drainage spout at @ 5.00 M Interval at both side of the Bridge

Total Nos = 32 Nos


Item No 27 (Levelling course bellow Approach Slab)

Qnty = 2 X 3.7 X 7.50 X 0.10

= 5.55 Cum
521329347.xls

Item No 27 (Approach Slab)

Qnty = 2 X 3.7 X 7.50 X 0.30

= 16.65 Cum

Item No 28 ( Providing Strip seal expansion Joint ………….. )

= (No of span + 1) X Carriage way width

= 30.00 Rm

Item No 29 ( Load Testing of one unit of Super structure …….)

Qnty = 1 No

Item No 30 ( Back filling behind abutment wing wall …….)

Qnty = 278.92 cum

Weep hole
2 6.20 8.45 .@ 2 per m2
Qnty. 57 nos

Asst. Executive Engineer , PWD Executive Engineer , PWD


Bongaigaon Rural Road Sub Division Bongaigaon Rural Road Division
Bongaigao Bongaigaon