Construction of RCC Bridge No 1/1 On Kathalguri To Sh2 Viasipansila Pt-Iii
Construction of RCC Bridge No 1/1 On Kathalguri To Sh2 Viasipansila Pt-Iii
xls
No of Piers = 2
Foundation
Item No 2 : (Excavation for structure ………. )
Total Qnty = (HFL -LBL) / 4 X Length of Proposed Bridge X Width of proposed Bridge
= 1222.11 Cum
Item No 5 A:( Providing and casting of controlled concrete RCC of specefied grade in well Curb….)
Abutment Well Pier Well
Outer dia of curb 7.15 m Outer dia of curb 6.15 m
Inner Dia dia of curb 5.40 m Inner Dia dia of curb 4.60 m
Height of curb 2.00 m Height of curb 2.00 m
Abutment 2
2
Qnty. = 2 X [ p/4 X 7.15 X 2.00 - 24.41 _- p /4 X 5.4 X 0.6 ]
_
= 84.23 Cum
Pier 2
2
Qnty. = 2 p/4 X 6.15 2.00 17.45 _- p /4 X 4.6 0.6 ]
X [ X - X
_
= 63.92 Cum
Total = 148.15 Cum
521329347.xls
= 68.79 Cum
2 2 2
( 3.14 x 1.40 / 6 ) X ( 0.75 6.00 + 0.75 + 4.60 X 1.4 )) +
p/4 4.60 2 X 0.6 + 3.14X1.71 ( 6.00^2/8 + 1.71 ^2/6 )
X
= 32.85 + 9.97 + 9.14
= 51.95 Cum
= 178.91 Cum
Add 0.5 % Prob Variation = 0.89 Cum
Total = 179.81 Cum
Item No 13 (Supplying,fitting and fixing HYSD reinforcement in provision for all RCC components in foundation…...)
Total = 74.76 MT
G.T. = 75.51 MT
Item No 14 (Supplying,fitting and fixing M.S. reinforcement in provision for all RCC components in foundation…...)
a. Lum Sum = MT
Substructure
v) Pier Cap
Qnty. = 2 X [( 1.8 X 0.5 X 6.1 ) + 0.5 ( 1.8 + 1.6 ) ] X 0.5 X 6.1
.= 21.35 m3
Item No 16 (Supplying,fitting and fixing HYSD reinforcement in provision for all RCC components in Substructure…...)
Total = 40.63 MT
G.T. = 41.04 MT
Item No 17 (Supplying,fitting and fixing M.S. reinforcement in provision for all RCC components in Substructure…...)
Item No 18 ( Supplying fitting and fixing in position Cast steel Rocker bearing ……. )
= 0 X 3 = 0 Nos
= 0 Ton
Item No 19 ( Supplying fitting and fixing in position Cast steel Roller bearing ……. )
Total Nos = 18
Item No 21 ( Furnishing and placine Reinforced / Pre stressed Cement concrete in Super Structure ….. )
Item No 22 (Supplying,fitting and fixing HYSD reinforcement in provision for all RCC components in superstructure…...)
Total = 53.81 MT
Item No 23 ( Suppllying Fitting and fixing High Tensile steel wire / Strand………. )
Quantity /Span = 0 MT
Total Quantity = 0 MT
Item No 24( Providing and laying cement concrete wearing coat M 30 ………..)
= 42.82 Cum
= 2 X ( 76.12 + 7.40 )
= 167.04 Rm
= 5.55 Cum
521329347.xls
= 16.65 Cum
= 30.00 Rm
Qnty = 1 No
Weep hole
2 6.20 8.45 .@ 2 per m2
Qnty. 57 nos