BASIC INFORMATION
The area for the construction and rehabilitation of drainage systems are thePoblacion Barangays of the
municipality – the Barangays of Libod Poblacion, IlawodPoblacion and Banawang.The completion of the
project will redound to the realization of a well-planned andaptly functional network of drainage
systems in the Poblacion area. It shall reducethe risk of infestation of diseases such as malaria and
dengue caused by stagnantand grimy canals. The resulting favorable conditions of drainage systems
willencourage the growth of entrepreneurial activities in the Poblacion Barangay,considering further the
finished construction of the Bato Public Market.
Scribd
Try Scribd FREE for 30 days to access over 125 million titles without ads or interruptions!
Cancel Anytime.
2
The Project is expected to further boost the living situation of the residents of thePoblacion Barangays.
As such, along with other priority poverty alleviation projects ofthe Municipal Government and other
National Government Agencies, povertyincidence in each Poblacion barangay is expected to reduce by
40% by the end of2017 – from 43.85% to 26.15% (57 to 34 HHs) in Barangay Banawang, 25.11% to
15.25%(56 to 34 HHs) in Libod Poblacion, and 22.73% to 13.64% (45 to 27 HHs) in BarangayIlawod
Poblacion.
2.
Project objective
In line with the National Government’s thrusts and the LGU’s goal of povertyreduction through more
improved infrastructure, the main objective of the project isto create a more conducive and business-
friendly environment within the Poblacionarea, thus, encourage the growth of entrepreneurial activities
that will help reducethe rate of poverty incidence.
3.
Expected Output
810 linear meter line open canal and 150 linear meter covered canal within thetarget barangays.
4.
Source of Fund Amount % ShareDepartment of the Interior and Local Government 2,400,000.00
96.64%Municipal Government of Bato, Catanduanes 62,500.00 2.52%Beneficiaries 21,000.00 0.85%
5.
Target Beneficiaries
The beneficiaries of the project are the whole residents of Barangays Libod Poblacionconsisting of 1016
individuals in 223 households, Ilawod Poblacion with 851 individualsin 198 households and Banawang
with 584 individuals in 130 households (September2014 CBMS Survey). The rest of the barangays in the
municipality are indirectrecipients of the Project since they will also benefit from the resulting growth
ofbusiness activity in the Poblacion area.
6.
Project Partners
The administration of the Project will be a joint undertaking of the Department of theInterior and Local
Government, the Municipal Government of Bato and theBarangays of Libod Poblacion, Ilawod Poblacion
and Banawang. In the barangaylevel, the direct partner during the construction phase is the Barangay
Council. Theyshall assist in ensuring the safety in traffic and disposal of waste material.
MunicipalGovernment shall facilitate all necessary undertakings to assure the soundimplementation of
the Project.
Approval and submission of SBResolution approving the list ofPoverty Reduction Projects andauthorizing
the LCE to enter intoMOA regarding ProjectimplementationDecember, 2015 Office of the
SangguniangBayan, Office of the Mayor4.
Preparation, submission andapproval of other necessarymaterialsFebruary, 2016 Municipal Planning
andDevelopment Office, DILGProvincial Office, DILG RegionalOffice No. 55.
MOA signing and transfer of fund February, 2016 Office of the Mayor, DILGProvincial Office, DILG
RegionalOffice No. 56.
Project Implementationa.
A.
Pre-Implementation Phase
1.
Sub-Total
B.
Implementation Phase
1.
Procurement and Deliveryof Supplies and Materials4,000.00 2,000.002.
Subtotal
C.
1.
Sub-Total
10,000.00 10,000.00
IV.
Project Management
The Municipal Engineering Office shall be the in-charge in implementation of theProject. Safety and
health in the undertakings shall be ensured at all times during theconstruction phase. The Project
Monitoring Committee of the Municipal DevelopmentCouncil and the CSO project monitoring team shall
also monitor the project in itsimplementation phase up to its completion to ensure the appropriateness
ofconstruction.
V.
Project Sustainability
Sharing Options
Share on Facebook, opens a new windowShare on Twitter, opens a new windowShare on LinkedIn,
opens a new windowShare with Email, opens mail clientCopy Text
reichelle
Request to Gov. Casimiro Ynares III for the construction of covered court in Baras-Pinugay National High
School
Request to Gov. Casimiro Ynares III for the construction of covered court in Baras-Pinugay National High
School
Melvin A. Almario
Magazines
Podcasts
Sheet Music
Excellent Example of a Project Proposal with Action Plan and Budget Proposal
Excellent Example of a Project Proposal with Action Plan and Budget Proposal
Rey Ty 郑 文华
rolandtrojas
rolandtrojas
Project proposal
Construction proposal
Leodigaria Reyno
Sustainability
Economies
Politics
Business
rolandtrojas
fcgomezjr
Abhishek Nayak
Show more
Footer menu
Back to top
About
About Scribd
Press
Our blog
Contact us
Invite friends
Gifts
Legal
Terms
Privacy
Copyright
Support
Help / FAQ
Accessibility
Purchase help
AdChoices
Publishers
Social
Instagram Instagram
Twitter Twitter
Facebook Facebook
Pinterest Pinterest
Books
Audiobooks
Magazines
Podcasts
Sheet Music
Documents
Snapshots
Directory
Language:
English
EXCLUSIVE OFFER
Read offline.