0% found this document useful (0 votes)
117 views1 page

Turnover and Load Cycle - Transloading Station 2xK3030 + SUL

This document calculates the load cycle, crane cycle, and turnover for a project involving two K3030-4 HD standard cranes used to load coal from barges onto a transloading station hopper. It finds that each crane can achieve a turnover of 664 tons per hour, or 1,329 tons per hour combined. Over a typical work year of 5,000 hours with 250 working days, the two cranes would provide an annual turnover of 6,643,862 tons.

Uploaded by

afandybaharuddin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
117 views1 page

Turnover and Load Cycle - Transloading Station 2xK3030 + SUL

This document calculates the load cycle, crane cycle, and turnover for a project involving two K3030-4 HD standard cranes used to load coal from barges onto a transloading station hopper. It finds that each crane can achieve a turnover of 664 tons per hour, or 1,329 tons per hour combined. Over a typical work year of 5,000 hours with 250 working days, the two cranes would provide an annual turnover of 6,643,862 tons.

Uploaded by

afandybaharuddin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Load-cycle and Turn-over calculation

Project: 1145137 PT BBS - Transloading station


Crane type: K3030-4 HD std
Number of cranes: 2
Load cycle: Loading coal from barge, unload to hopper on TL station
Hoisting speed 50 m/min
Lowering speed 55 m/min
High speed hoisting / lowering 75 m/min
Luffing time 75 sec
Slewing speed 1,2 r/min
Closing of grab 12 sec
Opening of grab 10 sec

Crane Cycle Calculation Distance Time Simult.


Closing of grab 12,0 sec 0 12 0
Hoisting 14 m 18,8 sec 12 19 0
Slewing 90 deg 16,5 sec 0,0 31 17 9,5
Luffing 10 % 9,5 sec 9,5 38 10 0
Lowering 0m 0,0 sec 0,0 47 0 0
Opening of grab 10,0 sec 0,0 47 10 0
Hoisting empty grab 0m 0,0 sec 57 0 0
Slewing empty grab 90 deg 16,5 sec 57 17 9,5
Luffing empty grab 10 % 9,5 sec 9,5 64 10 0
Lowering empty grab 14 m 13,2 sec 0,0 74 13 0
Total cycletime 87,0 sec 87 s
Cycles per hour 41,4 cycles
0 10 20 30 40 50 60 70 80 90 100
Closing of grab
Hoisting
Slewing
Luffing
Lowering
Opening of grab
Hoisting empty grab
Slewing empty grab
Luffing empty grab
Lowering empty grab

Factor of efficiency
Turnover calculation 100% 90%
theoretical practical
Grab volume 22,30 22,30 m3
Density 0,80 0,80 ton/m3
Pay load 17,84 16,06 tonnes
Cycles per hour 41,4 41,4
Turnover per crane per hour 738 664 tph
Turnover per 2 cranes per hour 1 476 1 329 tph
Hours per shift 10,0 10,0 hrs
Shifts / day 2 2 shifts
Turnover per day, 2 cranes 29 528 26 575 tpd
Working days per year 250,0 250,0 days
Working hours per year 5 000 5 000 hrs
Turnover per year, 2 cranes 7 382 069 6 643 862 tpy