Coring Method Statement
Coring Method Statement
SEQUENCE OF WORK
Rectification
Yes
Finish
PIPELAND SDN BHD (785146-D)
NO.51-2F, JALAN 5/154D, TAMAN DESA CHERAS,
56000 KUALA LUMPUR.
Procedure of Coring
Before commencing any activity on site, the consultants must be notified. All the
related documents, shop drawings, method of statement, material approval must be
approved and readily available.
Employees regardless of position will be responsible for their own personal safety and
that of their fellow worker, this will be reinforced through the induction process and
toolbox talks. They will
Use the correct tools and equipment for the job. Use the protective clothing
and equipment provided.
Refrain from horseplay and abuse of safety devices, equipment and welfare
facilities.
Sequence of works
PIPELAND SDN BHD (785146-D)
NO.51-2F, JALAN 5/154D, TAMAN DESA CHERAS,
56000 KUALA LUMPUR.
The slab to be cut should be clearly marked by contractor and approved by the
consultant before any cutting/coring works starts
For area that Horizontal Prestressed cable installed, slab hacking were
proposed to prevent any unintentional cable break due to coring works.
Using coring machine core will be done at center of each piece for lifting
purposes.
The DB connected to the machine should be at least 10m away to avoid any
water spillage on it. The coring machine is using single phase power.