100% found this document useful (1 vote)
66 views

Coring Method Statement

The document provides a method statement for coring work at a construction site. It outlines the following key steps: 1. Identify and mark the point on the slab to be cored. 2. Use a coring machine and hand tools to make cores of various diameters (250mm, 200mm, 150mm, 50mm) at the marked locations. 3. Inspect installed pipes and sleeves, and apply firestop material as needed. Rectify any issues before finishing.

Uploaded by

Ilman Faiq
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
66 views

Coring Method Statement

The document provides a method statement for coring work at a construction site. It outlines the following key steps: 1. Identify and mark the point on the slab to be cored. 2. Use a coring machine and hand tools to make cores of various diameters (250mm, 200mm, 150mm, 50mm) at the marked locations. 3. Inspect installed pipes and sleeves, and apply firestop material as needed. Rectify any issues before finishing.

Uploaded by

Ilman Faiq
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

PIPELAND SDN BHD (785146-D)

NO.51-2F, JALAN 5/154D, TAMAN DESA CHERAS,


56000 KUALA LUMPUR.

METHOD STATEMENT - CORING

SEQUENCE OF WORK

Identify point to core at slab.

Mark point to core at slab.

Make 250mm/200 mm/150 mm/50 mm

Inspection Install 200 mm , 150mm , 50 mm pipe pipe


sleeve and
HILTY firestop.
Not

Rectification
Yes

Finish
PIPELAND SDN BHD (785146-D)
NO.51-2F, JALAN 5/154D, TAMAN DESA CHERAS,
56000 KUALA LUMPUR.

CADANGAN PEMBANGUNAN 2 BLOK SOHO 26 TINGKAT


(KEDIAMAN) YANG MENGANDUNGI: -
BLOK A:
1. 604 UNIT SOHO (450KPS) DI ARAS L6, L12 – L26
2. 190 UNIT SOHO MAMPU MILIK (450KPS) DI ARAS L7 –
L11
3. 1 UNIT KAFE DI ARAS L6
4. KEMUDAHAN – KEMUDAHAN DI ARAS L6 DAN ARAS
BUMBUNG
BLOK B:
1. 667 UNIT SOHO (450KPS) DI ARAS L6,L10 – L26
2. 128 UNIT SOHO MAMPU MILIK (450 KPS) DI ARAS L7 –
L10
3. KEMUDAHAN – KEMUDAHAN DI ATAS L6 DAN ARAS
BUMBUNG
TERMASUK 8 UNIT KEDAI DI ARAS 1, 1 UNIT STESEN
SUIS UTAMA, 1 UNIT PENCAWANG ELEKTRIK, 1
TINGKAT SUB BASEMENT DAN 5 TINGKAT PODIUM
TEMPAT LETAK KERETA DI ATAS LOT 1484, MUKIM
KAJANG, DAERAH HULU LANGAT, SELANGOR DARUL
EHSAN
UNTUK TENTUAN PACIFIC UNILAND SDN BHD

COLD WATER AND SANITARY SERVICES


PIPELAND SDN BHD (785146-D)
NO.51-2F, JALAN 5/154D, TAMAN DESA CHERAS,
56000 KUALA LUMPUR.

METHOD STATEMENTS FOR CORING REV 0

Method Statement for Coring

Equipment & Tools Required


 Coring Machine
 Hand Tools

Procedure of Coring

Before commencing any activity on site, the consultants must be notified. All the
related documents, shop drawings, method of statement, material approval must be
approved and readily available.

Employees regardless of position will be responsible for their own personal safety and
that of their fellow worker, this will be reinforced through the induction process and
toolbox talks. They will

 Understand the company’s safety policy and appreciate their individual


responsibility towards safety for themselves, for their co-workers and for the
company.

 Use the correct tools and equipment for the job. Use the protective clothing
and equipment provided.

 Refrain from horseplay and abuse of safety devices, equipment and welfare
facilities.

 Report any accident, near miss or hazardous condition to immediate


supervisor for correction purposes.

 Obey all posted warning signs.

 Cooperate with safety personnel


 Know emergency procedures (siren codes, assembly point, wind socks, etc.

Sequence of works
PIPELAND SDN BHD (785146-D)
NO.51-2F, JALAN 5/154D, TAMAN DESA CHERAS,
56000 KUALA LUMPUR.

 The slab to be cut should be clearly marked by contractor and approved by the
consultant before any cutting/coring works starts

 For area that Horizontal Prestressed cable installed, slab hacking were
proposed to prevent any unintentional cable break due to coring works.

 Using coring machine core will be done at center of each piece for lifting
purposes.

 The same procedure will be used for cutting vertical lines.

 The DB connected to the machine should be at least 10m away to avoid any
water spillage on it. The coring machine is using single phase power.

You might also like