Lecture 1 - Introduction - Chapter 1
Lecture 1 - Introduction - Chapter 1
Introductory Lecture
J. Fisher
Significance of Power System Planning
To determine a minimum cost strategy for long-
range expansion of the generation, transmission and
distribution systems adequate to supply the load
forecast within a set of technical, economic, and
political constraints.
Realistic and Reliable Power System
The consumers should get the requested power (e.g.
a 60 W bulb), when they push the on-button. This
should work no matter outages in power stations.
The consumers should get an acceptable voltage,
e.g. 230 V, in the outlet.
A power system should be kept with a realistic
reliability
A power system should be kept in an economic and
sustainable way.
The Challenge
To Keep the balance:
Production = consumption (PGen = PLoad)
Electricity cannot be stored!
At the instant a light bulb is switched on,
some generators MUST deliver the power
Whenever that power plant generator is stopped,
the corresponding power will be delivered from
another plant instead to maintain reliabilty.
Evolvement of Power Systems
The electric power industry has evolved over many decades,
from a low power generator, serving a limited area, to highly
interconnected networks, serving a large number of countries,
or even continents.
Free market
Many nations are going through transitions from a
centrally controlled electric grid (Vertically Integrated
System) —with one-way delivery of power from central-
station power plants—into one (Horizontally Integrated)
that features both distributed generation and
distributed control systems based on advanced
communications, new approaches to enhance reliability
and efficiency.
• The term planning to denote the actions required for the future.
• The past experiences are always used for efficient operation and
planning of the system.
11 kV 11 kV/415 V 240 V
132 kV/11 kV
415 V for Heavy Industries A mobile phone operate
from a 4V battery
PNG Future Scenario
Asynchronous operation
To discuss, briefly, the points mentioned above, suppose from ten
generators of a system, in the coming week, three are not available
due to scheduled maintenances (see Figure next slide)
• The decision maker should decide on using the available plants for
serving the predicted load for each hour of the coming week.
Loads
Loads
Loads Loads
Normal operation
A and B open
System Outage – Line goes off
• Looking at transmission and sub-transmission levels, these are
generally interconnected.
• Normally both may be treated similarly, in terms of, the studies
required and involved.
• As seen, both transmission and distribution networks comprise of
lines/cables, substations and generations.
• However, due to specific characteristic of a distribution system (such
as its radial characteristics), its planning is normally separated from
a transmission system.
Long-term Versus Short-term Planning
There is no golden rule in specifying short-term or long-term
planning issues.
Normally,1 year falls into the operational planning and operational
issues in which the aim is typically to manage and operate available
resources in an efficient manner.
Any studies beyond 1 year falls into the planning stages.
If installing new equipment and predicting system behaviour are
possible in a shorter time (for instance, for distribution systems, 1–3
years), the term of short-term planning may be used.
More than that (3–10 years and even higher) is called long-term
planning (typically transmission planning) in which predicting the
system behaviour is possible for these longer periods.
Basic Issues in Transmission Planning
• Load Forecasting
A short-term load forecasting, for predicting the load for instance,
of the next week, we come across predicting the load for each hour
of the coming week.
It is obvious that the determining factors may be weather
conditions, special TV programs and similar.
In a long-term load forecasting, we normally wish to predict the
peak loading conditions of the coming years.
Obviously, the determining factors are different here.
Population rate increase, GDP (Gross Domestic Product) and similar
terms have dominant effects.
https://www.matec-conferences.org/articles/matecconf/pdf/2017/01/matecconf_encon2017_05003.pdf
Generation Expansion Planning (GEP)
After predicting the load, the next step is to determine the
generation requirements to satisfy the load.
An obvious simple solution is to assume a generation increase equal
to load increase.
If, for instance, in year 2021, the peak load would be 40,000 MW
and at that time, the available generation is 35,000 MW, an extra
generation of 5,000 MW would be required.
Unfortunately, the solution is not so simple at all. Some obvious
reasons are:
• What types of power plants do we have to install (thermal, gas
turbine, nuclear, etc.)?
• Where do we have to install the power plants (distributed among 5
specific buses, 10 specific buses, etc.)?
• What capacities do we have to install (5 x 1000 MW, or 2 x 1000 MW
and 6 x 500 MW, or …)?
• As there may be an outage on a power plant (either existing or
new), should we install extra generations to account for these
situations?
• If yes, what, where and how?
Substation Expansion Planning (SEP)
Once the load is predicted and the generation requirements are known,
the next step is to determine the substation requirements, both, in terms
of
Expanding the existing ones,
Installing some new ones.
This is referred to as Substation Expansion Planning (SEP).