Fire PUMPS T&C Checklist
Fire PUMPS T&C Checklist
PRECOMMISSIONING, COMMISSIONING & HANDING OVER CHECKLIST OF FIRE PUMPS, SEQUENCE OF OPERATION & FIELD TEST RESULTS
PROJECT: MINA ZAYED FISHERMAN’S WHARF FISH MARKET LOCATION: ABU DHABI, UNITED ARAB EMIRATES
OWNER: M/s MODON
CONSULTANT: M/s ARCADIS DESIGN & CONSULTANCY
MAIN CONTRACTOR: M/s AMANA CONTRACTING & STEEL BUILDING Co. FF CONTRACTOR: M/s AL RASHEEDIAH SAFETY & SECURITY EST.
DOCUMENT :- AL RASHEEDIAH – MINA ZAYED FISHERMAN’S WHARF- ABU DHABI 001 NAF - ASS - CL - PC TC - FP- AG - 1020 PAGE 1/6
PRE- C O M M I S S I O N I N G , COMMISSIONING &HANDING OVER CHECKLIST OF FIRE PUMPS
SL NO PRE-COMMISSIONING CHECK LIST REMARKS SL NO T&C CHECK LIST FOR JOCKY PUMP REMARKS
Check the installation is done as per the approved drawing Open the all the valves and check for any leakage from
1 1
pump/pipes
Check the Pump, Motor assembly for any physical damage Rotate the motor/pump manually to ensure for free rotating
2 2
3 Check the Foundation is made as per the drawing 3 Check the control panel for cleanness
5 Check all Valves, Fittings and Pipe s are leak tight 5 Switch on the isolator, MCB and check voltage
6 Check the packing glands are properly tightened 6 Check the manual start function
7 Check the controller for easy access, Height 7 Check for manual stop function
Check the pressure gauges installed in the Suction and Discharge
8 8 Check for motor Amps & Volts
side of fire pump
9 Check Pressure Relief valve free of damage 9 Check for pressure, Cut in & Cut out settings
Check and confirm strainer in Diesel engine raw water line is
10 10 Check for automatic start function
free from foreign particles.
Check the cabling, Ear thing from the controller to Motor
11 11 Check for automatic stop function
12 Check the termination of cables 12 Check for any leakage through Mechanical seal
DOCUMENT :- AL RASHEEDIAH – MINA ZAYED FISHERMAN’S WHARF- ABU DHABI 001 NAF - ASS - CL - PC TC - FP- AG - 1020 PAGE 2/6
PRE- C O M M I S S I O N I N G , COMMISSIONING &HANDING OVER CHECKLIST OF FIRE PUMPS
SL NO T&C CHECK LIST FOR THE DUTY PUMP REMARKS SL NO T&C CHECKLIST FOR THE STAND BY PUMP REMARKS
Open the all the valves and check for any leakage Open the all the valves and check for any leakage
1 1
from pump/pipes from pump/pipes
2 Check the control panel for cleanness 2 Check the control panel for cleanness
5 Check the manual start function 5 Check the manual start function
6 Check for manual stop function 6 Check for manual stop function
7 Check for Flow, Pressure etc 7 Check for Pressure Relief Valve operation
Check the water flow through the Diesel engine raw water
8 Check for Cut in & Cut out settings 8
drain line .
9 Check for automatic start & stop function 9 Check for Oil Pressure, Water Temp.
10 Check for Run status from controller 10 Check for Flow, Pressure, Rpm etc
11 Check for cooling water through gland packing 11 Check for Cut in & Cut out settings
DOCUMENT :- AL RASHEEDIAH – MINA ZAYED FISHERMAN’S WHARF- ABU DHABI 001 NAF - ASS - CL - PC TC - FP- AG - 1020 PAGE 3/6
FIRE PUMP SEQUENCE OF OPERATION
The jockey pump will start and maintain the pressure until the
If the system pressure decreases to 9 Bar due to any demand.
pressure reaches 10 Bar. If the pressure reaches above 10 Bar, the
jockey pump will stop automatically.
If the system pressure decreases to 8 Bar due to the increase in The Duty pump will start and maintains the pressure above 10 Bar.
the demand Duty pump will stop after time delay (10 Minute)
DOCUMENT :- AL RASHEEDIAH – MINA ZAYED FISHERMAN’S WHARF- ABU DHABI 001 NAF - ASS - CL - PC TC - FP- AG - 1020 PAGE 4/6
FIRE PUMP DETAILS
DOCUMENT :- AL RASHEEDIAH – MINA ZAYED FISHERMAN’S WHARF- ABU DHABI 001 NAF - ASS - CL - PC TC - FP- AG - 1020 PAGE 5/6
FIELD TEST RESULTS OF FIRE PUMPS
JOCKY PUMP
PRESSURE VOLTS AMPS CUT IN CUT OUT
PSI L1 L2 L3 L1 L2 L3 PSI PSI
DUTY PUMP
DISCHARGE
FLOW VOLTS AMPS CUT IN CUT OUT
PRESSURE
GPM PSI L1 L2 L3 L1 L2 L3 PSI PSI
STAND BY PUMP
DISCHARGE WATER
FLOW SPEED OIL PRESSURE WATER TEMP CUT IN CUT OUT
PRESSURE PRESSURE
GPM PSI RPM PSI PSI °C PSI PSI
DOCUMENT :- AL RASHEEDIAH – MINA ZAYED FISHERMAN’S WHARF- ABU DHABI 001 NAF - ASS - CL - PC TC - FP- AG - 1020 PAGE 6/6