Fire PUMPS T&C Checklist

The document provides precommissioning, commissioning, and handing over checklists for fire pumps at a fisherman's wharf project in Abu Dhabi, UAE. It details inspection points for pumps, piping, controls, and accessories. The sequence of operation describes the jockey pump maintaining pressure between 9-10 bar, the duty pump starting at 8 bar and stopping after 10 minutes, and the standby pump starting at 7 bar if needed. Test results and sign-offs from contractors are documented.

Uploaded by

Umair BaBer
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
904 views

Fire PUMPS T&C Checklist

The document provides precommissioning, commissioning, and handing over checklists for fire pumps at a fisherman's wharf project in Abu Dhabi, UAE. It details inspection points for pumps, piping, controls, and accessories. The sequence of operation describes the jockey pump maintaining pressure between 9-10 bar, the duty pump starting at 8 bar and stopping after 10 minutes, and the standby pump starting at 7 bar if needed. Test results and sign-offs from contractors are documented.

Uploaded by

Umair BaBer
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 6

NAFFCO

PRECOMMISSIONING, COMMISSIONING & HANDING OVER CHECKLIST OF FIRE PUMPS, SEQUENCE OF OPERATION & FIELD TEST RESULTS

PROJECT: MINA ZAYED FISHERMAN’S WHARF FISH MARKET LOCATION: ABU DHABI, UNITED ARAB EMIRATES
OWNER: M/s MODON
CONSULTANT: M/s ARCADIS DESIGN & CONSULTANCY
MAIN CONTRACTOR: M/s AMANA CONTRACTING & STEEL BUILDING Co. FF CONTRACTOR: M/s AL RASHEEDIAH SAFETY & SECURITY EST.

DOCUMENT :- AL RASHEEDIAH – MINA ZAYED FISHERMAN’S WHARF- ABU DHABI 001 NAF - ASS - CL - PC TC - FP- AG - 1020 PAGE 1/6
PRE- C O M M I S S I O N I N G , COMMISSIONING &HANDING OVER CHECKLIST OF FIRE PUMPS
SL NO PRE-COMMISSIONING CHECK LIST REMARKS SL NO T&C CHECK LIST FOR JOCKY PUMP REMARKS
Check the installation is done as per the approved drawing Open the all the valves and check for any leakage from
1 1
pump/pipes
Check the Pump, Motor assembly for any physical damage Rotate the motor/pump manually to ensure for free rotating
2 2

3 Check the Foundation is made as per the drawing 3 Check the control panel for cleanness

Check the Suction, Discharge, Test, Pressure Sensing and Drain


4 4 Check the control cables inside panel for looseness
piping

5 Check all Valves, Fittings and Pipe s are leak tight 5 Switch on the isolator, MCB and check voltage

6 Check the packing glands are properly tightened 6 Check the manual start function

7 Check the controller for easy access, Height 7 Check for manual stop function
Check the pressure gauges installed in the Suction and Discharge
8 8 Check for motor Amps & Volts
side of fire pump
9 Check Pressure Relief valve free of damage 9 Check for pressure, Cut in & Cut out settings
Check and confirm strainer in Diesel engine raw water line is
10 10 Check for automatic start function
free from foreign particles.
Check the cabling, Ear thing from the controller to Motor
11 11 Check for automatic stop function

12 Check the termination of cables 12 Check for any leakage through Mechanical seal

13 Inspect, Check and Clean the controller / breakers

14 Check the incoming power supply


15 Check the water level in the tank
16 Check sufficient diesel available at diesel tank
17 Check safety wall provided for diesel tank
Check the exhaust line installation completed and proper
18
cladding provided

CHECKED BY WITNESSED BY - FF Cont. WITNESSED BY - Main Cont. APPROVED BY


NAME NAME NAME NAME
COMPANY M/s NAFFCO COMPANY M/s AL RASHEEDIAH COMPANY M/s AMANA COMPANY M/s ARCADIS DESIGN

SIGNATURE SIGNATURE SIGNATURE SIGNATURE


DATE DATE DATE DATE
Remarks :-

DOCUMENT :- AL RASHEEDIAH – MINA ZAYED FISHERMAN’S WHARF- ABU DHABI 001 NAF - ASS - CL - PC TC - FP- AG - 1020 PAGE 2/6
PRE- C O M M I S S I O N I N G , COMMISSIONING &HANDING OVER CHECKLIST OF FIRE PUMPS
SL NO T&C CHECK LIST FOR THE DUTY PUMP REMARKS SL NO T&C CHECKLIST FOR THE STAND BY PUMP REMARKS
Open the all the valves and check for any leakage Open the all the valves and check for any leakage
1 1
from pump/pipes from pump/pipes
2 Check the control panel for cleanness 2 Check the control panel for cleanness

Check the control cables inside panel for


3 3 Check the control cables inside panel for looseness
looseness

Switch on the isolator, MCB and check Incoming


Switch on the isolator, MCB and check Incoming
4 4 voltage, Power available indicator ON, Battery Voltage,
voltage.
Charging Amps,

5 Check the manual start function 5 Check the manual start function

6 Check for manual stop function 6 Check for manual stop function
7 Check for Flow, Pressure etc 7 Check for Pressure Relief Valve operation
Check the water flow through the Diesel engine raw water
8 Check for Cut in & Cut out settings 8
drain line .
9 Check for automatic start & stop function 9 Check for Oil Pressure, Water Temp.

10 Check for Run status from controller 10 Check for Flow, Pressure, Rpm etc

11 Check for cooling water through gland packing 11 Check for Cut in & Cut out settings

12 Check for automatic start, manual stop function

13 Check for Run status from controller

14 Check for cooling water through gland packing

CHECKED BY WITNESSED BY - FF Cont. WITNESSED BY - Main Cont. APPROVED BY


NAME NAME NAME NAME
COMPANY M/s NAFFCO COMPANY M/s AL RASHEEDIAH COMPANY M/s AMANA COMPANY M/s ARCADIS DESIGN
SIGNATURE SIGNATURE SIGNATURE SIGNATURE
DATE DATE DATE DATE
Remarks :-

DOCUMENT :- AL RASHEEDIAH – MINA ZAYED FISHERMAN’S WHARF- ABU DHABI 001 NAF - ASS - CL - PC TC - FP- AG - 1020 PAGE 3/6
FIRE PUMP SEQUENCE OF OPERATION

DESCRIPTION ACTION REMARKS

The jockey pump will start and maintain the pressure until the
If the system pressure decreases to 9 Bar due to any demand.
pressure reaches 10 Bar. If the pressure reaches above 10 Bar, the
jockey pump will stop automatically.

If the system pressure decreases to 8 Bar due to the increase in The Duty pump will start and maintains the pressure above 10 Bar.
the demand Duty pump will stop after time delay (10 Minute)

If the system pressure decreases to 7 Bar due to the increase in the


The Stand by pump will start and maintain the pressure above 10
demand or the Duty pump fail to operate due to any failure
Bar. Stand by pump will stop Manually only

CHECKED BY WITNESSED BY - FF Cont. WITNESSED BY - Main Cont. APPROVED BY


NAME NAME NAME NAME
COMPANY M/s NAFFCO COMPANY M/s AL RASHEEDIAH COMPANY M/s AMANA COMPANY M/s ARCADIS DESIGN
SIGNATURE SIGNATURE SIGNATURE SIGNATURE
DATE DATE DATE DATE
Remarks :-

DOCUMENT :- AL RASHEEDIAH – MINA ZAYED FISHERMAN’S WHARF- ABU DHABI 001 NAF - ASS - CL - PC TC - FP- AG - 1020 PAGE 4/6
FIRE PUMP DETAILS

JOCKY PUMP SET DUTY PUMP SET STANDBY PUMP SET

PUMP PUMP PUMP


MODEL MODEL MODEL
SL NO SL NO SL NO
TYPE TYPE TYPE
MANUFACTOR MANUFACTOR MANUFACTOR
SUCTION SUCTION SUCTION
RATED RPM IMPELLER SIZE IMPELLER SIZE
RATED RPM RATED RPM
RATED GPM RATED GPM
RATED PSI RATED PSI
MAX PSI MAX PSI
150% PSI 150% PSI
MOTOR MOTOR ENGINE
MODEL MODEL MODEL
SL NO SL NO SL NO
TYPE TYPE TYPE
MANUFACTOR MANUFACTOR MANUFACTOR
VOLTS VOLTS VOLTS
RATED RPM RATED RPM RATED RPM
RATED POWER RATED POWER RATED POWER
F L AMPS F L AMPS
PHASE/CYCLES PHASE/CYCLES
CONTROLLER CONTROLLER CONTROLLER
MODEL MODEL MODEL
SL NO SL NO SL NO
TYPE TYPE TYPE
MANUFACTOR MANUFACTOR MANUFACTOR
STARTING TYPE STARTING TYPE

DOCUMENT :- AL RASHEEDIAH – MINA ZAYED FISHERMAN’S WHARF- ABU DHABI 001 NAF - ASS - CL - PC TC - FP- AG - 1020 PAGE 5/6
FIELD TEST RESULTS OF FIRE PUMPS

JOCKY PUMP
PRESSURE VOLTS AMPS CUT IN CUT OUT
PSI L1 L2 L3 L1 L2 L3 PSI PSI

DUTY PUMP
DISCHARGE
FLOW VOLTS AMPS CUT IN CUT OUT
PRESSURE
GPM PSI L1 L2 L3 L1 L2 L3 PSI PSI

STAND BY PUMP
DISCHARGE WATER
FLOW SPEED OIL PRESSURE WATER TEMP CUT IN CUT OUT
PRESSURE PRESSURE
GPM PSI RPM PSI PSI °C PSI PSI

CHECKED BY WITNESSED BY - FF Cont. WITNESSED BY - Main Cont. APPROVED BY


NAME NAME NAME NAME
COMPANY M/s NAFFCO COMPANY M/s AL RASHEEDIAH COMPANY M/s AMANA COMPANY M/s ARCADIS DESIGN
SIGNATURE SIGNATURE SIGNATURE SIGNATURE
DATE DATE DATE DATE
Remarks :-

DOCUMENT :- AL RASHEEDIAH – MINA ZAYED FISHERMAN’S WHARF- ABU DHABI 001 NAF - ASS - CL - PC TC - FP- AG - 1020 PAGE 6/6