Grid Code 2005
Grid Code 2005
•
NATIONAl. TIt·\NSi\lISSION ANI) VESI'ATCII CO~II'AN\' LTD,
June, 2005
GRID CODE
INTRODUCTION
Pursuant to Section 35 of NEPRA Act and Article 16 of ttle NTDC licence. the
National Transmission and Dispatch Company is required to ensure that there is in
force at all times a Grid Code. Consequently NTDC is required to submit a
comprehensive Grid Code for approval of the Authority in accordance with the
requirement of Article 16 of its licence. The Grid Code provides for the smooth and
effective functioning of NTDC and other NEPRA licensees that are or will be
connected to the NTDC's Bulk Transmission System.
The Grid Code sets out the guidelines. rules and procedures to be adopted by all
Code Users. The sub-codes of trle Grid Code relate to technical and commercial
relationships between NTDC and its Users.
The Grid Code sets out the operating procedures and principles between the
National Transmission and Dispatch Company; and all authorised Electricity
Operators as defined in NTDC transmission licence collectively referred to as
"Users" in the context of this document.
The Grid Code is structured so as to ensure that the NTDC's transmission system
can be developed. operated. and maintained in an efficient. safe. reliable and co-
ordinated manner from technical and commercial aspects both. The Grid Code is
expected to encourage competition between Generators. Distribution Companies.
and SPCs as the Market Structure develops.
Introduction
GRID CODE
a. Code Management
Data Registration Code, which sets out a unified listing of all data
required by NTDC from Users; and by Users from NTDC, from time to
time under the Grid Code.
c. Operation Code
d. Connection Code
Illtroduction 2
\ ,',
GRID CODE
e. Planning Code
The Protection and Metering Code, which places the Protection and
Metering requirements upon the Users and NTDC (particularl y with
reference to the Inter-connection Sites) in terms of Principles,
Standards, Design, and Procedures to ensure safe, reliable and
effective functioning of NTDC's bulk transmission system.
h. Code Definitions
The relationship between the Grid Code and the Distribution Code is shown on
Figure 1 (page 4) of this section.
The Grid Code specifies all the material, technical design, and operational aspects of
the interface requirements between NTDC, Distribution Licensees, SPCs,
Externally-connected Parties and Consumers, and Special Purpose Transmission
licensees (SPTLs).
The Distribution Code shall be consistent in material particulars with the Grid Code;
and it shall ensure strict compliance by the distribution compan'les and other Users
with the provisions of Grid Code including, without limitation, the instructions from
time to time of NTDC and/or the System Operator in respect of the Use and
Operation of their distribution systems.
Introduction 3
c;- ;;0
rn
o ------------------------------------------------------------.--------------------------------------...... r
~l
Q. ;J>
consume~
c ~
C'
n Transmission Connected
o NPCC 0
:J , Distriblltion Companies ~ ! Z
(/)
I
Z CODE :!
m
m
Generators Connected to NTDC Sy~ z
~
Subject to Scheduling I
Special Purpose Transmission Licensee and Dispatch m
G)
;U
"
10
ution Systems
0
(")
.,C
It)
Subject to Scheduling 0 .....
r------------------,c./ and Dispatch
~
0
INFORMATION ,:' Generators Connected to 132kV m
System of Licensees (DISCOs) }>
en z
0
o Embedded Generators
THE ~
U Distribution ,, DISTRIBUTION I
en load Dispatch
m
o Centre / CODE 0
Small Power Producers (SPPs) Ul
~
;U
Consumers Externally Connected Parties ~Not subject to Scheduling OJ
C
including '-------------- and Dispatch ::j
BPes All other Distribution Licensees
-- -------------- ---- ----- - - -- - -- --------'-----
------------ - ---
------ - - ---
- - ----
==:J
- -- - -- - ------------------------
- ----
0
Z
(")
0
0
m
GRID CODE
CODE MANAGEMENT
CONTENTS
CM 14 NON-COMPLIANCE CM -10
GRID CODE
CODE MANAGEMENT
UNFORESEEN CIRCUMSTANCES
C~.12.1 If unforeseen circumstances arise which are not included in the Grid
Code, NTDC shall promptly consult with all affected Users in an effort
to reach an agreement on what should and needs to be done under
such circumstances. If agreement cannot be reached in the available
time, NT DC shall determine the most appropriate course of action.
Whenever NTDC makes a determination, it shall do so having due
regard to the views expressed by the Users and, in any event, to what
is reasonable under the circumstances. Each User shall comply with
such instructions given by NTDC provided those instructions do not
contravene the technical parameters of a particular User's System as
registered in the Grid Code. NTDC shall promptly refer all such
unforeseen circumstances and any determination to the Review Panel
for consideration as per CM 3.1 of this sub-code.
cr.ll1 NTDC shall establish and maintain the Review Panel, which shall be a
standing body and shall undertake the functions detailed·iIl CM-3.3.
(ii)
GRID CODE
(a) keep the Grid Code and its workings under review;
(b) review all suggestions for amendments to the Grid Code which
the Authority or any User may wish to submit to NTDC for
consideration by the Panel;
(g) study and evaluate the suggestions received from different parts
of the power market participant; and
(h)
GRID CODE
0.1 34 The Panel shall establish and comply with at all times with its own rules
and procedures relating to the "Conduct of its Business", which shall be
approved by the Authority.
0.115 NTDC shall consult in writing all Users which are liable to be affected
by any proposed amendments to the Grid Code and shall submit all
such proposed amendments to the Grid Code to the Panel for
discussion prior to such consultation.
C~1141 All operational instructions issued by NTDC between NTDC and Users
shall be between the NTDC Control Engineer based at the NPCC, as
advised to Users before connection to the Transmission System, and
the Users Responsible Engineer based at a Regional Control Centre
notified to NTDC before connection to the Transmission System.
C~.14 4 If for any reason NTDC or a User re-Iocates its Control Centre, NTDC
or the User must inform the other Party in writing of the move and
advise the other party of any changes to their Control Telephony.
C~.15 MISCELLANEOUS
0.15.1.1 References in the Grid Code to 'in writing' shall include typewriting,
printing, lithography and other modes of reproducing words in a legible
and non-transitory form such as electronic communications.
0.151.2 Where applicable all data items shall refer to Voltage and
Frequency.
CLl 8
\ \" ,
GRID CODE
CM 7 SYSTEM CONTROL
Where a User's System (or part thereof) is, by agreement under the
control of the System Operator, for the purposes of operation in Real
Time, the User's System shall be treated as a part of the NTDC
Transmission System.
Each Code Participant shall keep NTDC and the System Operator
indemnified at all times against any claim, action, damage, loss,
liability, expenses or outstanding liability which NTDC or the System
9
GRID CODE
CODE ADMINISTRATION
CM 14 NON-COMPLIANCE
C~.l 10
GRID CODE
CONTENTS
DRC 1.1 The Data Registration Code (DRC) presents a unified listing of all data
required by NTDC from Users and by Users from NT DC, from time to
time under the Grid Code. The data which is specified in each section
of the Grid Code is listed and collated here in the DRC. Where there is
any inconsistency in the data requirements under any particular sub-
code of the Grid Code, the provisions of the Data Registration Code for
that particular sub-code of the Grid Code shall prevail.
DRC1.2 The Scope of this Code applies to Users who in this DRC means:
(a) Generators
DRC 1.3 The DRC identifies the sub-code of the Grid Code under which each
Hem of data is required.
DRC1A The sub-code under which any item of data is required specifies
procedures and timings for the supply of such data, for routine
updating, and for recording temporary or permanent changes to that
data. All timetables for the provision of data are repeated in the DRC.
DRC 1.5 Various sub-codes of the Grid Code also specify information which the
Users shall receive from NTDC. This information is summarised in a
single Schedule in the DRC (Schedule 1-9).
DRC 1.6 The objective of the DRC is to list and collate all the data to be
provided by each category of User to NTDC under the Grid Code, and
to list all the data to be provided by NTDC to each category of User
under the Grid Code. I
~ ~()'~1E.~ R_tCu.
~ ~
~
v
DRC 12
GRID CODE
ORC 2.1 Within the DRC each data item is allocated to one of the following four
categories (DRC 2.2 & DRC 2.3, DRC 2.4, DRC 2.5, DRC 2.6).
ORC 2.2.1 The Standard Planning Data listed and collated in this DRC is that data
listed in Part 1 of the Appendix A to the Planning Code.
ORC 2.3.1 The Detailed Planning Data listed and collated in this ORC is that data
listed in Part 2 of the Appendix A to the Planning Code.
ORC 2.3.2 Detailed Planning Data shall be provided to NTOC in accordance with
PC 5 and PC A5 of Appendix A of Planning Code.
ORC 2.4.1 Operational Data is data, which is required by the Operation Codes
and the Schedule and Despatch Codes. Within the DRC, Operational
Data is sub-categorised according to the Code under which it is
required namely, OC3, OC4, OC5, OC6, OC?, OCg, and OC12.
DRe 13
GRID CODE
oRC 3.2.1 Wherever possible the data Schedules to the ORC are structured to
serve as standard formats for the data submission and such format
must be used for the written submission of data to NTOC.
oRC 3.2.2 Data must be submitted to the NTOC, National Power Control Centre
(NPCC) or to such other department or address as NTOC may advise
from time to time. The name of the person on the behalf of the User
who is submitting each schedule of data must be included.
ORe 3.2.3 Where a computer data link exists between a User and NTOC, data
may be submitted via this link. NTOC shall, in this situation, provide
computer files for completion by the User containing all the data in the
corresponding ORC Schedule.
oRC 3.24 Other modes of data transfer, through CO and other electronic means
of data transfer such as magnetic tape, may be utilised if NTOC gives
its prior written consent.
oRC 3.3.1 Whenever a User becomes aware of a change to an item of data which
is registered with NTOC, the User must notify NTOC in accordance
with each sub-code of the Grid Code. The method and timing of the
notification to NTOC is set out in each sub-code of the Grid Code.
ORC34.1
oRC
GRID CODE
that data ought to have been supplied, shall estimate (typical values) of
such data if and when, in that User's view, it is necessary to do so.
Such estimates shall, in each case, be based upon data supplied
previously for the same plant and apparatus or upon such other
information as NTOC or that User, as the case may be, deems
appropriate.
DRC 3.4.2 NTDC shall advise a User in writing of any estimated data it intends to
use pursuant to DRC 3.4.1 relating directly to that User's facility, plant,
and apparatus in the event of data not being supplied.
DRC 3.4.3 A User shall advise NTDC in writing of any estimated data it intends to
use pursuant to ORC 3.4.1 in the event of data not being supplied.
DRC 3.4.4 In the event the required data is consistently not supplied or is
incomplete or in-accurate by the User, the NTDC shall refer the matter
to the "Review Panel", which shall issue necessary instructions to the
defaulted party in writing.
Failure to obtain the required data within the specified timeframes from
the defaulted party, the NTDC shall consider the matter as a violation
of the Grid Code provisions. Suitable measures regarding Grid Code
non-compliance are covered in CM 14 of this Grid Code.
i
Comprising the Generating Plant parameters required for Operational
Planning studies and certain data required under Scheduling and
Dispatch Code (as covered in Appendix 5 of OC 4).
ORe 15
GRID CODE
{
ORe 16
,
GRID CODE
Notes:
ORC 17
,"\()
.
GRID CODE
ORC 18
GRID CODE
CONTENTS
OC 1.1 INTRODUCTION
, n." lel11 S,sternOperator refers to the system control functions being periormed by the National Power Conlrel Ce
plec~·:essor WAPOA system as defined in the NTOC IicenCtl '? ~ _--,
SJ
OC-l 20
GRID CODE
(m) The System Operator must ensure that all the thermal loadings,
voltages, system stability (both steady-state and dynamic) are
well within established limits as provided in the Operating
Code 4 of this sub-code.
OC-1 21
GRID CODE
DEMAN D FORECASTS
OC 21.2 This sub-code covers Active Demand and Reactive Demand forecasts
which are necessary to match generation output with system energy
requirements.
OC 21.4 For real-time operations, NTDC shall conduct its own demand
forecasting taking into account information supplied by all the Users,
and any other external factors that it may deem necessary.
OC 21.6 In this OC 2, Year 0 means the current NTDC Calendar Year at any
time, Year 1 means the next NTDC Calendar Year at any time, Year 2
means the NTDC Calendar Year after Year 1 and so on.
OC-2 23
i
I
GRID CODE
OC 2.3.1 For a period of 4 weeks ahead of the real-time day, the following shall
be supplied to NTDC in writing by 10.00 a.m. each Monday. The
4-week period is a rolling period.
Demand Management
OC 2.3.2 For the period of up to eight (8) days ahead of the real-time day, the
following shall be supplied to the System Operator in writing by
10:00 a.m. each Wednesday
Demand Management
OC 23.3 Each Generator shall, if required by NTDC, supply the System Operator
with MW schedules for the operation of power plants on an hourly basis
in writing by 10.00 a.m. each day (or such other time specified by
NTDC from time to time) for the next day.
OC-2 24
'. 7
W
GRID CODE
DEMAND MANAGEMENT
CONTENTS
OC 3 APPENDIX 1
Emergency Manual Demand Reduction/Disconnection
Summary Sheet OC3-31
,
'\()
'. I
GRID CODE
DEMAND MANAGEMENT
OC 3.1.1 Operation Code No.3 (OC3) deals with the provisions to be made for
the Users including Consumers directly connected to the NTDC
Transmission System to facilitate reduction in Demand as per the
instructions of NTDC for any reason.
OC 3.1.2 Similarly, the provisions given here apply to Unforeseen Events as well.
OC3.1.3 The objective of OC3 is to provide facilities and procedures which shall
enable NTDC to achieve a reduction in demand that will relieve
planned and unforeseen operating conditions on the NTDC
transmission system.
OC-3 27
i
GRID CODE
OC 33.1 By 10.00 a.m. of each day, distribution companies and other Code
Participants, as specified by the System Operator, shall provide the
System Operator with a summary of any demand reductions of 5MW or
greater during the last 24 hours, and of any planned demand
reductions within the next 24 hours.
OC 34.1 The System Operator shall provide as much warning as possible of any
unforeseen circumstances which are likely to result in demand
management procedures being implemented. This shall ensure that all
the distribution companies and all other relevant Code Participants
shall be in a state of readiness to implement their planned demand
management procedures.
OC344
OC-3 28
iI
GRID CODE
OC 3.5.2 Any low frequency disconnection scheme must take into account of all
embedded generation on the low voltage systems of the distribution
companies.
OC 3.6.1 Each distribution company shall provide the System Operator in writing
by week 40 in each calendar year, in respect of the next following year
beginning week 40, on each Transmission Connection Point basis the
information contained in the Appendix 1 of this sub-code.
OC 3.6.2
OC-3
GRID CODE
OC 36.4 Distribution companies are obliged to comply Wittl the System Operator
instructions when restoring supplies.
OC-3 30
GRID CODE
OC 3 APPENDIX 1
OC-3 31
GRID CODE
OPERATIONAL PLANNING
CONTENTS
OC 4 APPENDIX 4, 5, 6
(Oe 4.5.1, OC 4.5.2, OC 4.5.3)
NTDC Transmission Outages (Year 0-5) OC4-48
OPERATIONAL PLANNING
OC4.1.3 The scope of this Code applies to all Grid Code participants, i.e.
(b) Generators;
Restructured Network
The NTDC shall own and operate the assets of entire 500kV and
220kV transmission and substations.
OC·4
GRID CODE
OC-4 34
.\'
GRID CODE
OC 4.4.1.1 In this Code, short term is the financial current year, or Year 0 of the
NTDC Financial Year. The basis for Operational Planning for Year 0
shall be the revised Year 1 Final Generation Outage Programme
prepared by each Generator, and submitted to the System Operator
will be on the Financial Year basis.
OC-4 35
GRID CODE
OC 44.2.1 In this Code, medium term is the two financial years following Year 0,
or Years 1 & 2 of the NTDC Financial Year. The basis for Operational
Planning for Year 1 & 2 shall be the "revised Year 2 & 3" Final
Generation Outage Programme, agreed between each Generator, and
the System Operator.
OC 44.3.1 In this Code long term is for the three-year period covering Years 3, 4
& 5 of the NTDC Financial Year.
OC 44.3.2 At the beginning of Year 3 for the next three years, Year 3, 4 & 5, each
Generator shall provide, in writing, to the System Operator, a
provisional Generation Outage Programme showing the best estimate
of its Usable Output for the Years 3,4, and 5 (Appendix-3, P:47).
OC 44.3.3 The System Operator shall prepare the annual NTDC Forecast
Demand including values for the peak Summer Demand.
OC4.4.3.4 Every effort shall be made by the System Operator and each
Generator to agree on the Final Generation Outage Programme which
when summated will meet the NTDC Forecast Total System Demand
for the Financial Years 3 to 5. All agreements shall be recorded for
future reference. It is acknowledged that this agreement on the Final
Generation Outage Programme at this stage is not a commitment on
the part of the Generators. In the event that a Generator's outages
later on differ from those given in the Final Generation eR REG
~<.;/-
o
OC-4 36 lLJ ~
J BY ~
':} THE AUTHORITY ~
q ~
GRID CODE
In this Code short term is the current Financial year, or year 0 of the
NTDC Financial Year.
OC 45.1.3 The System Operator shall review the Final Outage Programme with
respective Code Participants at eighth week (8) before real-time. All
parties are obliged to co-operate at this stage in any outage changes
requested by the System Operator, Generators, distribution
companies, and transmission Consumers.
OC 45.1.4 This process of confirming and mutually amending the Final Outage
Programme continues in more and more detail right up to the real-time
operation. Appendix 4 (P: 48) of this Code details the time scales of the
NTDC Transmission Outages and obligations. which each Code
Participant must observe to achieve this objective.
OC 4.5.2.2
OC-4
GRID CODE
which the System Operator and each Code Participant must observe to
achieve this objective.
In this Code long term is for the three-year period covering Years 3, 4
& 5 of the NTDC Financial Year
OC 45.3.1 The System Operator shall plan the NTDC Transmission System
outages for Years 3-5 on the basis of construction and refurbishment
requirements; whereas the NTDC Transmission System outage
programmes for Years 1-2 are for maintenance requirements.
OC 45.3.2 For each of the three Years 3,4, and 5 there will be a number of
timelines whereby the System Operator and Users shall exchange
information. The time scales for the information exchange are detailed
in Appendix 6 (P: 48) to achieve this objective. This process should be
complete by the beginning of the eighth month of each Financial Year.
OC 4.5.3.3 At the end of the exchange of information period, the System Operator
shall prepare a draft NTDC Transmission System outage plan
(Appendix 6) Page 48 for Years 3 to 5. The System Operator shall
also issue, in writing, those aspects of the Plan which may cause
operational difficulties for Generators, DISCOs or Transmission
Connected Consumers. The System Operator shall also indicate where
[hey may need to issue Emergency Instructions to Users in accordance
with the Operation Code to allow that the security of supply of the
NTDC Transmission System remains within the requirements of the
Transmission Licence.
OC4.6.3 By 10.00 a.m. one week prior the operational day, each User must
inform the System Operator of any changes to circuit details as
specified in Planning Code PC A 2.2.4, PC A 2.2.5, PC A 2.2.6,
PC A 2.3, PC A 2.4 which may apply on that operational day.
OC-..) 38
GRID CODE
OC 4.7.1 Annually, the System Operator shall calculate the required Active
Power Operating Margin required to support the NTDC forecasted
Demand. The System Operator shall advise Generators in writing of
any periods when there is likelihood of having insufficient power
operating margin.
OC 4.7.2 Generators and the System Operator shall review proposed outages at
times of inadequate Active Power Operating Margins to ensure that the
required Active Power Operating Margin can be achieved.
OC 4.8.1 From 2 to 6 weeks ahead of the operational day, the System Operator
shall assess whether there will be sufficient plant mix to operate in
"Frequency Sensitive Mode".
When the system frequency falls below 49.4 Hz, requisite load
shedding (automatic) must be carried out to stabilize the system
frequency to an acceptable level (Frequency Sensitive Mode).
OC-4
GRID CODE
OC 4.8.3 If the System Operator determines that the procedures of OC 4.7 and
OC 4.8 are required for the same operating period, then the order shall
normally be OC 4.7 first followed by OC 4.8. For the avoidance of
doubt, there is nothing in this paragraph which shall prevent either
procedure following the other or operating independentIY'~
r~-
n\'IER "C-
'-'_
d/,- Gc'
~I (-Y;'"
i...:...: 1 ,.,....... 0
'-'".1 . ,.., ..'ED ;0
_I BY
OC-4 40 '.. \ ~"I- ,\
~':,'; ~:... UTIiG;{ I ry
.... \
\' \.
GRID CODE
OC-4 41
'\ll '"
GRID CODE
The System Operator shall have available and shall implement when
required, generation re-dispatch plans and schedules for likely (N-1)
contingency events so that, if the system moves to an expected
contingency (N-1) state, the System Operator can follow the
re-dispatch and return the system to a Normal State. The System
Operator shall have available and shall implement; emergency-
operating procedures to deal with system contingencies. The System
Operator shall have available at all times and be in a position to
implement, system restoration plans for the situation in which the
system moves to an islanded state or suffers a cascading break up
resulting in a Black Out condition.
NTDC shall establish loading limits for each 500 kV and 220 kV
transmission circuit and selected 132 kV circuits that are operated in
parallel with NTDC 500 kV and 220 kV lines for reliability reaSDl~__
'? O:--'-'- -
\~
,,~G
OC-.J 42
GRID CODE
TABLE 4- 2
Ratin~
Parameters For Overhead Conductors
Summer Winter Rating
Rating Bases Bases
Maximum Conductor Temp. 0
90 C 90° C
Outdoor Ambient Temp. 40 0 C (d)
(avg.)
Conductor Temp. Rise * .
Max. Emergency Conductor None Allowed None Allowed
Temp.
Wind Velocity 3 FeeVSecond 3 FeeVSecond
Age of the Transmission
Circuit I
Transmission Line Sag
Design
Notes to Table:
(a) Summer Months = April through October
(b) Winter Months = November through March
(c) Emergency ratings are limited to (8) hours of continuou s
operation. Conductors shall not be operated above 100 0 C
conductor temperature for more than 960 cumulative hours.
(d) The following average temperature of Winter shall be used fro
the respective provinces:
1. Lahore (Punjab) 6.S0C
2. Peshawar (NWFP) SO C
3. Quetta (Balochistan) _7° C
4. Karachi (Sindh) +SoC
OC-4
GRID CODE
Grid station transformers including three phase and single phase banks
tha t are normally operated at the voltage levels of 220/132kV and
500/220kV shall be loaded under normal and contingency conditions
according to applicable lEe, ANSI/IEEE standards and as specified by
the respective manufacturers.
Each year, NTDC/ the System Operator shall prepare transient stability
studies for expected system event scenarios that could lead to
unsatisfactory system dynamic performance and loss of power angle
stability (transient instability). The System Operator shall maintain and
be able and ready to implement, when required, emergency operating
procedures designed to mitigate the extent of disturbance resulting
from a system event.
OC-4 45
GRID CODE
46
GRID CODE
OC-4 47
GRID CODE
OC 4 APPENDIX 4, 5,6
(OC 4.5.1, OC 4.5.2, OC 4.5.3)
OC-4 48
~y
GRID CODE
1':; ----~----------_;r--;_I--,"7,- - - : -
'.Ii:::; :
I- - - _ -
~..:.~.- - -
. ___.;,
-=-.
",
,
I
i .-
Il
.(
.v
I /
/
./"
. :.:.
,,
..
I .
I
" i /
~ i
i I
.,.,,..., :....._ - L I _ _ ~ _ _ _ _?,-....:;"
c..o
u
'"
.:>
..:)
1
\1 t.tV/
30 100 t20
I __
,( O.Sh::;
OC-4 49
GRID CODE
OC·4
50
GRID CODE
OC-4 51
GRID CODE
OPERATING MARGINS
CONTENTS
Sr N~o.,--_....:::S~u~b:J.:::ie!..::::c.!....t_ _ _ _ _ _ _ _ _ _ _ _ _ _ _...!...P~a~qe:::...!..!.N.=o.
OC 5 APPENDIX 1
Response Data for Frequency Changes OC5-56
GRID CODE
OPERATING MARGINS
OCS.1.1 Operating Code NO.5 sets out the types and amounts of Reserve,
which make up the Operating Margin that the System Operator may
make use of under certain operating conditions to cover for the
uncertainties in Demand Forecasting and power plant
availability/unavailability or sudden outages of generation and
transmission facilities.
OC 5.1.2 This sub-code applies to NTDC and to Code Participants which in OC5
means:
Spinning Reserve
oc-s
GRID CODE
OC 52.3 The amount of Contingency Reserve that is required at the day ahead
stage is determined by the System Operator. Time scales may be
increased by the System Operator in the light of historical data
available as to changes in power plant availability and changes in load
demand up to real time. The System Operator shall agree time scales
with the Operators of power plants where Contingency Reserve is held
on thermal Generators to reach synchronous speed.
OC-5 54
1\
~/
GRID CODE
OC 5.5.1 By 1500 hours (3 p.m.) each Wednesday the System Operator shall
issue each Generator in respect of its power plants a Weekly
Operational Policy for the week commencing 10.00 a.m. for the
following Monday. The Weekly Operational Policy shall cover
Generators that are available from standstill to start by low frequency
relay settings of which will be determined from time to time by the
System Operator. The Weekly Operational Policy shall specify the
location of the Gensets and take into account the low frequency setting
of these Gensets. By 10.00 a.m. on the Friday following the receipt of
the document, the Generator shall confirm as appropriate, its
availability, and seek any changes it wishes to instigate in the
document. The System Operator shall update availability in real time in
respect of notifications received.
OC 5.5.2 The Weekly Operational Policy shall include an indication of the level of
Operational Reserve to be used in connection with operation of the
Balancing Mechanism (to be notified by the Authority) in the times
scale defined in OC 5.5.1. The document shall also include details of
Operational Reserve that may be provided by Externally-connected
systems and also indicate the possible level of High Frequency
Response to be utilised by the System Operator in connection with the
operation of the Balancing Mechanism.
OC~ 55
~'
GRID CODE
OC 5 APPENDIX 1
As provided
As provided
OC-5 56
GRID CODE
OPERATIONAL LIAISON
CONTENTS
Appendix 1 OC6-62
OC-6
GRID CODE
OPERATIONAL LIAISON
OC 6.1.1 Operating Code No.6 sets out the requirements for the exchange of
information relating to Operations and Events on the Total System that
may have, or have had, an operational effect on the System of NTDC,
Ge'nerators, transmission-connected Consumers, distribution
companies or the Externally-connected Parties and Consumers.
Exchange of information also includes the requirement to advise on
equipment, plant. and apparatus tests. The System Warnings shall be
issued relating to inadequate plant availability, subsequent load
demand control, and to advise of a risk of major system disturbance.
OC-6 58
GRID CODE
NTDC shall operate, maintain, expand and upgrade from time to time,
this Supervisory Control and Data Acquisition (SCADA) system and a
supporting dedicated communication system.
NTDC shall provide all Code Participants wittl specifications for RTU's,
communications system requirements and protocols, and technical
assistance required to connect and functionally integrate Code
Participants' facilities into the SCADA system.
OC 6.4.1 Information regarding "Operations" and "Events", that have taken place
or about to take place or are being planned to take place are to be
assessed by the System Operator to identify appropriate and
necessary actions to be taken by the owner or respective Operator of a
part of the sub-system or the System Operator to eliminate or to
minimise their adverse effects, if any. The reason for the Operation or
the Cause of an Event need not be communicated to the Parties or
Code Participants or Users.
OC 6.4.3 Some of the Operations and Events that are required to be reported
under this sub-code are:
(a) Operations that form part of a planned outage which has been
arranged in accordance with OC 4.
aC·6 59
GRID CODE
OC 6.4.6 Notification of the details of an Event, Major Event and Operation, must
be restricted to Parties governed by the Grid Code. Details shall not be
passed on to any other third party.
OC 6.4.7 OC 7 deals with the upgrading of an "Event" to a "Major Event' and the
subsequent exchange of information.
OC 6.5.2 All Parties shall agree on the office locations to which Notices shall be
issued and the means of transmission of the System Warning.
OC 6.5.3 The System Operators System Warnings shall be issued in the form of:
OC-6 60
\~-y
GRID CODE
OC 6.6 TESTING
OC-6 61
GRID CODE
OC 6 Appendix 1
OC·6 62
GRID CODE
CONTENTS
APPENDIX 1 OC7-65
Report of a Major Event
GRID CODE
OC 7.1.1 Operation Code No. 7 details the procedure for formal exchange of
written reports relating to Events that have already occurred on the
System. Events on the System formally reported between the System
Operator, distribution companies, Operators of Power Plants,
transmission-connected Consumers, and Operators of Externally-
connected System Parties, are those initially reported as required
under Operation Code No 6.
OC 7.2.1 Following an Event on the System which has, in the opinion of any
Code Participant is likely to have an effect on its system, the affected
Code Participant can declare the Event as a "Major Event".
OC 7.3.1 Following such a declaration, the owner of the system on which the
Major Event occurred is required to provide a written report to the
requesting party confirming information given orally under Operation
Code No 6.
OC 7.3.3 The recipient of the report shall not pass it on to a third party. The
recipient may, however, use the information to prepare a report for
another party
OC 7.4.1 The recipient of a report of a Major Event may request that a joint
investigation be carried.
64
OC-7
GRID CODE
DC 7 APPENDIX 1
2 Location
65
OC-7
GRID CODE
SYSTEM RECOVERY
CONTENTS
SYSTEM RECOVERY
OC 8.1.1 This sub-code deals with the procedures for the restoration of power
supplies following a Total Shutdown or a Partial Shutdown of the
System and the re-synchronisation of specific parts of the System that
have been Islanded.
OC 8.1.3 In order to mitigate the effects of any national emergency, the Federal
Government may require NTDC, Operators of power plants and
distribution companie s to take action to safeguard electric power
supplies. Such action may be contrary to the principles and
procedures laid down in the Grid Code, and as such, the appropriate
section of the Grid Code shall stand suspended.
67
OC-8
GRID CODE
OC 8.2.6 During the restoration of Load Demand, the System Operator may
issue instructions that conflict with a local procedure for the restoration
of power supplies. In such an event the System Operator instruction
shall override any agreed local procedure.
OC 8.2.7 Procedures for the restoration of power supplies may include the
requirement for the Operators of Generators to communicate directly
with the distribution companies so that the restoration of blocks of local
power supplies can be carried out in a controlled manor to ensure the
Generator's stability.
1
OC 8.2.8 Frequency sensitive automatic load disconnection schemes may be
taken out of service during the restoration of Load Demand to prevent
unwanted disconnection of load demand.
~
68
OC-B
GRID CODE
OC 82.10 During the restoration of supplies, the System Operator shall agree the
reconnection of the System to any Externally-connected Party with the
operations of those systems, as allowed for under the relevant licences.
OC 8.3.1 In the event of a part of the System becoming disconnected from the
complete System (islanded), but there has been no resultant Total
Shutdown or Partial Shutdown of the system, the System Operator
shall instruct the regulation of generation and or Load Demand in the
group to enable it to be re-synchronised to the complete System
OC8.3.4
OC-8
GRID CODE
OC 8.4 INCIDENTS
OC8.4.1 When an event occurs, that in the opinion of the System Operator or a
distribution company, may have, or have had, a widespread effect on
the System, which is outside the normal functions of system control, an
incident procedure shall be invoked.
OC 8.4.2 The incident procedure shall not take over any function of control of the
System. The procedure shall allow for communication between the
management bodies of various affected Code Participants, and the
distribution of information within their organisations.
70
OC-8
GRID CODE
CONTENTS
OC 9 APPENDIX 1 (A)
Record of Inter-System Safety Precautions (RISSP-R)
For Requesting Safety Co-ordinator's Record OC9-76
OC 9 APPENDIX 1 (8)
Record of Inter-System Safety Precautions (RISSP-R)
For Implementing Safety Co-ordinator's Record
OC9-78
GRID CODE
OC 91.2 To ensure safe conditions for eQ:h and every foreseeable situation
during system operation, it is essential that NTOC and the Code
Participants operate in accordance with safety rules and procedures as
laid down in their approved Safety Codes, and other NEPRA applicable
documents.
OC 9.1.3 In this document, only the following terms have the following meanings:
72
OC-9
GRID CODE
OC 9.1.4 The rules for achieving and maintaining isolation and earthing at every
site where this Operating Code NO.9 applies shall be agreed to by all
concerned Parties with respect to Connections at that Site. Local safety
instructions shall be exchanged by all concerned Entities having an
interest in the Connections at a Site.
OC 9.2.1 Safety Co-ordinators shall be available at all times for all Sites where
this section of the Operation Code is applicable. These Persons are
required to be authorised by their employer to achieve Safety
Precautions on their Systems, as may be required by other Entities.
OC 9.3.1 80th Code Participants and other concerned Entities shall record the
request for Safety Precautions in their system logbooks and the
implementing Safety Co-ordinator shall arrange for the Safety
Precautions to be made. The implementing Safety Co-ordinator shall
confirm when the requested Safety Precautions have been taken to the
requesting Safety Co-ordinator.
OC 9.3.2
i
If earthing is required, both Code Participants shall record the request
and the implementing Safety Co-ordinator shall record details in his
syslem logbook of Ihe aclions laken 10 comply requesl.
73
OC-9
GRID CODE
OC 93.3 Details of the isolation and earthing achieved shall be formally
recorded by both Entities and the agreement timed and recorded on
the appropriate form. Following issue of the form, the requesting
Safety Co-ordinator may proceed to issue safety documentation at the
agreed point of the system interface between the Code Participants.
Neither Entity may issue a safety document which permits the removal
of earth connections nor the application of any source of energy for
testing purposes without the agreement of implementing Safety Co-
ordinator and then only one such safety document may be issued on
that part of the System at anyone time.
OC 94 UNFORESEEN CIRCUMSTANCES
74
OC-9
GRID CODE
OC 9 Appendix 1 (A)
Inter-System Safety
Record of Inter-Safety Precautions (RISSP - R)
(For Requesting Safety Co-ordinator's Record)
RISSP No. _ _ _ _ _ __
PART 1
1.1 (a) Identification of HV Apparatus where isolation and safety from the
system is to be aChieved.
(i)
D D D D
(ii)
D D D
(iii)
D D D
75
OC-9
GRID CODE
Para 1.2 have been established and will not be removed until this RIS SP is
cancelled.
Signature: _ _ _ _ _ _ _ _ _ __
Dated _ _ _ _ _ __ Name:
Time - - - - - - - -----------
(Requesting Safely Co-ordi nator)
PART2
CANCELLATION
Signature:
Name:-----------
(Requesting Safety Co-ordinator)
Dated: _ _ _ _ _ __
Time - - - - - - -
76
ac-g
GRID CODE
DC 9 Appendix 1 (8)
Inter-System Safety
Record of Inter-Safety Precautions (RISSP - R)
(For Implementing Safety Co-ordinator's Record)
RISSP No.
-------
Name and location of the Control Centre: _ _ _ _ _ _ _ _ _ _ _ _ _ __
,
Name of Control Centre Operator: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __
PART 1
1.1 (a) Identification of HV Apparatus where isolation and safety from the
system is to be achieved.
(i)
D D D D
(ii)
(iii)
D
D
D
D
D
D
Di
D. "CNlCP. R':~0
./ ('.>
':j' 0·
--------------~=__----------_f_--...-__r,.~: r-ROVED .~:
77
EY
OC-9
~
GRID CODE
identified in Para 1.2 have been established and will not be removed until this
RISSP is cancelled
Signature: _ _ _ _ _ _ _ _ _ __
Name:
-~-~~~~-~-~
(Implementing Safety Co-ordinator)
Dated: - - - - - - - -
Time
--------
PART 2
CANCELLATION
Para 1.2 are no longer required and hence the RISSP is cancelled.
Signature: _ _ _ _ _ _ _ _ _ __
Name:
-~-~~~~---~
(Implementing Safety Co-ordi nator)
Date _ _ _ _ _ _ __
Time: _ _ _ _ _ _ __
78
OC-9
\ft:/
GRID CODE
PLANT IDENTIFICATION
CONTENTS
PLANT IDENTIFICATION
OC 10.1.1 Operation Code No. 10 sets out the requirements for the numbering of
HV Apparatus at Sites where the System Operator and a distribution
company, transmission-connected consumer or Generator are
responsible for the Operation and maintenance of HV Apparatus. The
sub-code applies to all Sites where there is a Transmission Connection
Point.
OC 102.1 The numbering and nomenclature at all Sites shall comply with NTDC
standards by the date of Transfer. Users of Sites are responsible to
ensure that the HV Apparatus conforms to NTDC standards.
OC 10.2.2 The System Operator shall provide Users with details of its numbering
and nomenclature standards on request.
i
Operation Diagram and included in a draft Connection Agreement for
the Site. Agreement to the proposed changes to the numbering and
nomenclature shall be agreed in writing within one month of receipt of
the notification of change.
?O'-N ER RtGu.
~G ~
(j 1:>
--------------------------~8~0------------------~~~~~D ~
OC-l0
GRID CODE
OC 10.4.1 The numbering and nomenclature used at a Site must be clear and
unambiguous. No alterations to the HV Apparatus and its numbering
and nomenclature that would result in confusion relating to the identity
of the HV Apparatus shall be permitted.
81
OC-10
~
GRID CODE
SYSTEM TESTS
CONTENTS
SYSTEM TESTS
OC11.1.1 Operating Code No. 11 details the procedure for carrying out system
tests which involve creation of Unusual, extreme or abnormal system
conditions on the Total System, and excludes commissioning or re-
commissioning tests, which are carried out on a small defined part of
the System. The sub-code covers the System Operator, Transmission-
connected Consumers, Operators of Power Plants, distribution
companies and the Operators of Externally-connected
Parties/Consumers. A system test proposed by a User that shall have
no effect on the Transmission System of NTDC is not subject to this
sub-COde. A system test proposed by the System Operator shall
always to subject to this sub-code.
OC 11.1.2 The purpose of this sub-code is to ensure that the safety of the general
public and the personnel of the Users is not jeopardised and that the
risk to power supplies and facilities of the NTDC and Users, and the
integrity and security of the system are maintained at the highest levels
possible under such specified conditions.
OC-11
GRID CODE
OC 11.2 NOTIFICATION
OC 11.2.1 When a User has decided that it needs to perform a system test, it
shall issue a proposal notice to the System Operator detailing the
nature, extent and purpose and the plant and or apparatus involved.
The proposal notice shall be issued at least 12 months in advance of
the proposed system test. The System Operator shall be satisfied that
it has received sufficient time to give full consideration to the proposal.
OC 11.3.2 The test panel shall consider the test proposal in relation to the
possible safety, economic and operational risks; the possibility of
combining the proposed test with other tests and proposed system
outages. The test panel shall produce a proposal report which shall
include details of the proposed test and the manner in which the
proposed system test shall be undertaken and monitored. The proposal
shall also consider the cost implications and propose the allocation of
costs. The proposal report shall be circulated to all Users affected by
the proposed system test. Objections to the proposal report shall be
considered to determine if the proposal can be modified to
accommodate their objections. In the case of failure to agree, the
matter shall be referred to the Grid Code Review Panel whose decision
shall be binding upon all the concerned Parties.
OC 114.1 Following agreement, the test panel shall prepare a test programme,
which shall detail the procedure to be used on the day of the test. If
system conditions on the day of the test are not as envisaged or if after
consideration of other factors such as severe weather the test
co-ordinator may delay, postpone or cancel the system test.
OC 114.2 A final report shall be prepared by the Entity proposing test and
circulated to members of the test panel detailing the tests carried out,
the results and conclusions.
84
OC-11
GRID CODE
CONTENTS
(a) Generators:
OC 12.2 MONITORING
OC 12.2.2 If there are any persistent failures of OC 12.2.1, (a). (b) & (c) by Users,
the System Operator shall notify the User in writing requesting an
explanation of the action, the User shall have to
obligations.
OC-12 86
. '
\'. \ I
GRID CODE
OC 12.2.3 The System Operator and the User shall discuss the proposed action
and endeavour to reach an agreement on the proposed action. If
agreement cannot be reached within 10 working days of notification of
the failure by the System Operator to the User. the System Operator or
the User shall be entitled to require a test as detailed in OC 12.3.
OC 12.3.1 NTDC may issue an instruction requiring the User to test anyone or
more of the User's Generators to demonstrate its performance subject
to the notification giving the User not less than 48 hours notice to
conduct the test if any of the following apply:
(c) Meet the reactive power or fast start capability as registered with
the System Operator under Scheduling and Dispatch Code and
Operating Code.
OC 12.3.3 The results of the performance of the User's Generator under test shall
be recorded at NPCC Control Centre using voltage and current signals
provided to the System Operator by the User.
OC 12.3.4 If the results are recorded on Site chart recorders are to be used and
representatives appointed and authorised by the System Operator shall
wHness the test.
OC 12.3.5 The test shall be initiated by the issue of instructions under SDC2 for
the Generator submitted by the User for the day of the test.
OC 12.3.6 In the event that the Generator fails to meet the test criteria specified in
the table given below. the User is required to provide the System
Operator with a written explanation of the reasons for failure. If the
System Operator and the User are unable to agree, the System
Operator may require the User to perform are-test.
OC-12 87
The Generator will Pass the Test if the Following Criteria Below is Met
o
()
Parameter to be Grid Code Pass Criteria
tested Reference
Reactive CC Generating Unit will pass the test if it is within ±5% of the capability registered with NTOC
~ ~ Capability under OC 4.
""0 nI
nI0
0"_ The duration of the test will be 60 minutes with System voltage at the Transmission
=< Connection Point being maintained by the Generator by adjustment of Reactive Power on
-<ct>
the remaining Generating Units, if necessary.
Primary. ASA IThe measured response in MW/Hz is within ±5% of the level of response specified in the
Secondary and iAnciliary Services Agreement for that Genset.
High Frequency
G)
Response
Q~~~~~-~---------+-----------------------------------------------------------~ :::0
co
o
<
Governor CC Measurements indicate that the Governor parameters are within the criteria set out o
co ~ Compliance in the appropriate governor standard. (")
::J
~ ~-------------r--------------+_--------------------------------------------------------------------~
o
High SOC 3 The measured response is within the requirements of SOC 3.
o
en Limited m
~ Frequency
ct> Response
3r-------r--------+------------------------------~
Output at CC For variations in System Frequency exceeding 0.1 Hz within a period of less than
Reduced SOC 10 Seconds, the Active Power output is within ±O.2% of the requirements of
System CC xxx when monitored at prevailing external air temperatures of up to 25°C.
Frequency
Fast Test ASA The Fast Start Capability requirements of the Ancillary Services Agreement
or that Genset are met
~'-
,
)-~p,.-L-E-L..L~C.. r---t-------r-------t----------------------------------l
~ a,
...(') Black Start OC 12.5.1 The relevant Generating Unit is Synchronised to the System within two hours
~ .~
... \'. of the Auxiliary Supplies being required to start.
m ~
>"1: ~
~m~ fm+-~L--------------L--------------~--------------------------------------------------------------------~
:x:-<o :.0
o <: ~
~ m ~
=f 0 ~
-< ~<::-
. ;} nT>..'CO}.
The Generator will Pass the Test if the following Criteria is Met
Export and OC 12 The Export and Import, OPN, Joint BM Unit Data and Dynamic Parameters
Import Limits, Under test are within 2i'2% of the declared value being tested
QPN, Joint
Generator data
and Dynamic
Parameters
o
'<
~
3mr--------------+--------------;---------------------------------------------------------------------~ G')
(") Synchronisation SDC Synchronisation takes place within ±5 minutes of the time it should have achieved ::u
\J time Synchronisation. o
m
...,
OJ ("')
3 o
CD
r--------------r--------------+---------------------------------------------------------------------~
o
CD
en Run-up Rates OC 12 ~chieves the instructed output and, where applicable, the first and or/second
m
intermediate breakpoints, each within ±3 minutes of the time it should have reached
such output and breakpoints from Synchronisation calculated from the run-up rates
in its Dynamic Parameters.
Run-down OC12 Achieves the instructed output within ±5 minutes of the time, calculated from the
Rates run-down rates in its Dynamic Parameters.
.I" The following conditions will apply to each of the above tests:
{ '--
--~-~l-E-Lf'~:r~The duration of the test will be consistent with and sufficient to measure the relevant expected input or output derived from the Final Physical
~~ ~ ~ Notification Data.
:t: C'
m > -0
> ~~~--------------------------------------------------------------------------------------------------------~
C ~ -
-i[D;;tJrn
:t:-<O ;.0
0<;0
~ ~ !f
~ ~~
~~}..~O~
GRID CODE
OC 12.3.7 If in the opinion of the System Operator the Generator again fails the
re-test, every effort should be made to resolve the mailer. In the event
that a dispute arises between the User and the System Operator, either
Entity may approach the Review Panel for a determination of the
dispute which shall be binding on both Entities.
OC 12.4.2 If the Generator fails the test, the User shall submit revised limits and
other data as may be relevant in the case of a Generator as per
Revised GSDP Notice for the period of time until the Generator can
achieve the Parameters previously registered or demonstrated under
SOC 1 (GSDPs).
OC 12.4.3 When the User advises the System Operator that the Generator is able
to achieve the previously Generation Scheduling and Dispatch
Parameters (GSDPs): the System Operator shall either accept this
information or require the User to re-test the Generator to confirm the
stated capability. The System Operator shall give 48 hours Notice to
the User for a re-test. The test shall be conducted in accordance with
OC 12.3, and the provisions of OC 12.4 shall apply to this further test.
OC-12 90 (j
~
1.>':;0
~ APPROVED ~
~ BY
~\THr=. AUTHORITY
GRID CODf;
(c) Normally any Generator shall not be tested more than once in
any year and a Black Start Station test shall not be requested
by the System Operator more frequently than once every two
years.
(b) All auxiliary supply sources in the Black Start plant where the
Generator is located shall be shuidown.
(d) The auxiliary supplies in (b) shall be re-started and energise the
unit board of the relevant Generator, thereby enabling the
Generator to return to synChronous speed.
(a) All Generators at the Black Start Station other than the
Generator on which the Black Start Test is to be undertaken,
and all auxiliary supplies to the Back Start Station shall be
shutdown.
(e) The auxiliary supply generator at the Black Start Station shall be
started and shall re-energise either directly or via the station
board, the unit board of the relevant Generator.
OC-12 91
"
GRID CODE
oc 12,5.4 In the event of such failure, the Generator must provide the System
Operator with a written report detailing the reasons for the failure within
ten working days of the failed Black Start Test. If a dispute arises
between the System Operator and the Generator, they shall seek to
resolve their differences. In the event that there is no resolution, the
Generator may require the System Operator to permit a further Black
Start Test on 48 hours notice, The relevant test procedures, as set out
in OC 12.5.2.1 and OC12.5.2.2 shall apply to the re-test.
OC 12,5,5 If the Black Start plant fails the re-test and a dispute arises between the
Generator and the System Operator, either Code Participant may use
the disputes resolution procedure as provided through the Review
Panel. The findings of the dispute resolution procedure shall be binding
on both Code Participants.
OC 12,5,6 If, a Black Start station fails the Black Start Test and subsequent re-
test, the Generator shall, within fourteen working days, advise the
System Operator in writing of the date and time by which the Generator
shall restore the Black Start Capability to that Black Start station. The
System Operator shall not unreasonably withhold approval to the
Generator's proposal. Should NTDC not approve the Generator's
proposal, the Generator shall re-submit the proposals by taking into
account the System Operator's comments.
OC 12,5.7 When the Generator advises the System Operator that the Black Start
station has been restored to Black Start Capability status, the System
Operator shall either accept this information or require a further Black
Start Test to demonstrate the validity of the Generator's information.
Any further test shall be in accordance with test procedures detailed in
OC 12.5.2,1 and OC 12.5.2.2
Hi Hi ~~ ~~ End of OC 12 IH H~ H~ H~ H~
OC-12 92
GRID CODE
PLANNING CODE
CONTENTS
Appendix A Part-1
General
STANDARD PLANNING DATA PC-106
Appendix A Part-2
STANDARD PLANNING DATA
GENERATING UNIT DATA PC-112
Appendix A Part-3
STANDARD PLANNING DATA
DEMAND AND ACTIVE ENERGY DATA PC-114
Appendix B
SINGLE LINE DIAGRAM PC-116
PC
GRID CODE
PLANNING CODE
(c) To specify the planning data required from Users seeking new
Connection or a modification in their existing Connection to the
NTDC Network;
The Planning Code provides the basis for system reliability goals that
are to be achieved and maintained by NTDC and the System Operator.
The reliability goals need to be coordinated with policy objectives for
the electric power sector as well as with short-term and long-term
system planning objectives.
PC
GRID CODE
PC 1.1 The scope of this Code applies to all NTDC Transmission System
Users, i.e.
(a) NTDC;
(b) Generators;
(c) DISCOs;
PC 2 PLANNING CRITERIA
PC 95
GRID CODE
PC 21 Contingency Conditions
There shall be two base case scenarios for each year; Summer-peak
(High-Water) and Winter-peak (LOW-Water). In each case, the (N-O)
condition shall be adjusted to account for planned and scheduled
generation and transmission facility maintenance Outages. As required
by maintenance scheduling requirements, NTDC shall prepare several
(N-O) base cases to account for Summer and Winter base cases in a
given year.
Single contingency cases (N-1) shall be studied for each base case
scenario; an (N-1) contingency shall be defined as the unplanned
Forced Outage of any single transmission and grid system facility,
plant, or apparatus. For planning studies, a single transmission facility
Outage shall be defined to be anyone of the following:
--P-C-------------------------9-6--------------------~--vn~lr~~
--- ~~~
filO't-JE.~ Rfc
::J ~-<.
~/ %>.rHEAu~~ORITY t
UJ
APPROVED
GRID CODE
studies for steady state load flow studies shall be deemed acceptable if
they do not result in any voltage violations or overloads based on pre-
determined loading limits for Normal (N-O) and Emergency (N-1)
contingency conditions.
(c) Within 15 minutes following the change from the (N-D) state to
the (N-1) state, after Spinning Reserve (ten minute reserve) has
been deployed, the System shall have the capability to first
change generation d'lspatch and second shed load to reduce
any transmission line and transformer loading from the
Emergency Rating to below the Normal Continuous Maximum
Ratings.
In some cases, line loading limits may be adjusted for unique
geographical regions. All loading limits shall be determined in
accordance with applicable IEC Standards and updated from time to
time as new and revised standards are issued. In the event that an
IEC Standard with necessary scope does not exist, then applicable
standards such as: ANSI, IEEE, JEC, or other internationally
recognized institution may be used. In the event of a dispute as to
wh'lch planning and design Standards are to be used, Review Panel
shall have the final decision.
PC
(d) Allowable over load for 15 minutes; and
97
J
GRID CODE
PC 98
GRID CODE
TABLE 2-1
Substation Transformer Capacity Adequacy
Ratio of
Sub-station Number of Transformer Firm Estimated Peak
Name Transformers Voltage Sub-station Peak Substation
and Ratio Capacity (1) Substation Demand to
Total Name (2) Demand Firm
plate (3) Transformer
Capacity
MVA KV/kV MVA MVA %
Elimination of Congestion
NTDC shall make load flow studies and develop improvement plans to
eliminate the congestions that existed in the past year. The description
of the plan shall include estimated cost and required commissioning
date for the improvement plan.
PC
GRID CODE
NTDC shall make transient stability studies for the existing as well as
future System as planned for the following most likely fault conditions.
Transient stability studies shall be prepared for Summer (High Water)
and Winter peak (Low Water) load conditions for each of the next five
years following the Calendar Year.
PC 2.2.3 Voltage
1 Timings of 5 and 9 cycles are based on the sum of relay action, communication time, and circuit
bre3ker operating time. Timings may be re'/ised to reflect technology improvements. _ _~
PC 100
GRID CODE
Short circuit calculations shall be prepared for each study year, and
adequacy of fault interrupting capability and short circuit withstand
capacity shall be ensured.
PC 3 RESPONSIBILITY
Each year, the NTDC shall prepare and deliver to NEPRA a Ten-Year
"Indicative Generation Capacity Expansion Plan (IGCEP)" covering 0-
10 Year timeframe. NTDC shall provide this IGCEP or NTDC Plan.
PC 10 1
GRID CODE
NTDC shall submit to NEPRA for information its proposed plan for its
planning process on or before the year of enforcement of the Grid
Code. The Plan shall as a minimum address the following points:
Load Forecasting
PC 102
GRID CODE
High Growth; (2) Medium Growth and (3) Low Growth projections.
Factors that are to be taken into account when preparing the load
forecasts are: economic activity, population trends, industrialization,
weather, distribution companies forecasts, demand side management,
load shedding etc.
Project Identification
PC 5 PLANNING DATA
(a)
PC 103
GRID CODE
PC 104
"()
\~/
'. ' \.
GRID CODE
Appendix A
PART·1
PC.A.1 GENERAL
PCAA.2.1.1 Each User shall provide a Single Line Diagram, depicting both its
existing and proposed arrangement(s) of load current carrying
apparatus relating to both existing and proposed Connection Points.
PCA2.1.2 The Single Line Diagram must include all parts of the User System
operating at EHV and those parts of its sub-transmission system at any
NTDC Site. In addition, the Single Line Diagram must include all parts
of the User's sUb-transmission system operating at a voltage 66kV &
above.
At the User's discretion, the Single Line Diagram can also contain
additional details of the User's sub-transmission System not already
included above, and also details of the transformers connecting the
User's sub-transmission system to a lower voltage. With NTDC's
agreement, the Single Line Diagram can also contain information about
the User's System at a voltage below the voltage of the sub-
transmission system.
1
PC 105
GRID CODE
PC A2.2.4 For each circuit shown on the Single Line Diagram, the User shall
provide the following circuit parameters details relating to that part of its
system:
Circuit Parameters
PC.A 2.2.5 For each transformer shown on the Single Line Diagram, the User shall
provide the following details:
PC 106
GRID CODE
PC.A.2.2.7 User shall supply the following information about the User's equipment
installed at a Connection Site which is owned, operated or managed by
NTDC: -
(a) Switchgear: User shall provide the following parameters for the
circuit breakers.
(c)
Detailed short circuit data for single-point or multi-point connection
sites.
PC 107
GRID CODE
For all parts of the User's Sub-transmission System which are not
included in the Single Line Diagram provided under PC.A.2.1.1, each
User shall provide the equivalent lumped shunt susceptance at Nom'lnal
frequency.
General
(a) To allow NTDC .to calculate fault currents, each User is required to
provide data and short circuit analysis of its system; calculated in
accordance with good industry practice, as set out in the following
paragraphs.
(b) The data should be provided for the User's system with all
Generating Units synchronized to the User's System. The User
must ensure that the pre-fault network conditions reflect a credible
system operating arrangement.
(c) The list of data items required, in whole or part. under the following
provisions. Each of the relevant following provisions identifies
which data items in the list are required for the situation with which
that provision deals.
The fault current in sub-paragraphs (a) and (b) of the data list
should be based on an ac load flow that takes into account any
pre-fault current flow across the Point of Connection being
considered. Measurements made under appropriate system
conditions may be used by the User to obtain the relevant data. ~__
ool/'J ER R~G
---------------------------------------------r--~~~~ ~~
PC 108 1:>
APPROVED ~
GRID CODE
(d) NTDC may at any time, in writing, specifically request for data to
be provided for any alternative system condition, for example
minimum plant, and the User will insofar as such request is
reasonable, provide the information as soon as reasonably
practicable following the request.
(e) Root mean square of the pre-fault voltage at which the maximum
fault currents were calculated.
PC.A.2.2.12 If the Power Plant has separate Station Transformers, data should be
provided for the fault current contribution from each transformer at its high
voltage terminals, assuming a fault at that location, as follows: -
Data for the fault in feeds through both Step-up Transformers and
Stations Transformers shall be provided for the normal running
arrangement when the maximum number of Generating Units in the
Power Station are synchronized to the System.
Data Items
(a) The following is the list of data utilized in this part of the Planning
Code.
PC 109
GRID CODE
(v) The positive sequence X/R ratio at the instant of fault; and
PC 110
GRID CODE
Appendix A
PART·2
(ii) Rated MW
PC 111
~
GRID CODE
(a) Exciter and power system stabilizer data including block diagrams
and parameters such as gain, time constraints etc to be used in
Standards PSS/E format.
PC 112
GRID CODE
Appendix A
Part 3
(a) Time of Peak, and Maximum Load Demand (Active Power and
Active Energy Data);
PC.A.4.3 NTDC's Load Forecast (System Peak Demand and Active Energy
Requirements)
(b) The Total Active Energy of the NTDC in the preceding NTDC
Financial Year alongwith a Forecasted Active Energy
Requirements for the Current Financial Year.
(b)
PC
GRID CODE
PCA4.5 Connection Point Demand (Active and Reactive Power and Power
Factors)
PCA4.6 NTDC System Demand and Energy Forecast Incorporating All the Data
Supplied by the Network Users and Network Operators.
Each User to provide load and its characteristics which can have
adverse impact on the NTDC system vis-a-vis Power Quality.
PC 114
GRID CODE
Appendix B
The Single Line Diagrams showing the Details of the User's Connection to the NTDC
Transmission System are included in the Appendix E of the Connection Code.
HI HI HI HI End of PC ~.~.~.~.~.
PC 115
GRID CODE
CONNECTION CODE
CONTENTS
Appendix A
Format, Principles and Procedures to be
used in the Preparation Site Responsibility
Schedules (SRS) CC-139
Appendix A (ATTACHMENT)
Proforma for Site Responsibility
Schedule (SRS) CC-140
Appendix B (PART-I)
Principles and Procedures Relating to
Operation Diagrams CC-141
Appendix B (PART-II)
Principles and Procedures Relating To
Gas Zone Diagrams CC-142
Appendix B (PART-III)
List of all apparatus to be shown on Operation and
Gas zone diagrams CC-143
Appendix C
Minimum Frequency Response Requirements CC-144
Appendix D
Technical Requirements for Low Frequency
Relays for The Automatic Load Shedding
cc
GRID CODE
CONNECTION CODE
CONTENTS
Appendix E (Scheme 1)
Interconnection Configuration for Generators CC-146
Appendix E (Scheme 2)
In terconnection Configuration for Generators CC-147
Appendix E (Scheme 3)
Interconnection Configuration for Generators CC-149
Appendix E (Scheme 4)
Interconnection Configuration for Generators CC-151
Annexure F (Figure-1 )
Connection Procedure for New Connection or Modification
Of Existing Connection CC-152
CC ii
~
GRID CODE
CONNECTION CODE
CC 1 INTRODUCTION
(a) Generators
(c) to manage and prepare the System and the Point of Connection
for the applicant seeking connection to the NTDC's present and
future Transmission System;
(d) to identify
connection.
technical and financial requirements of the
---
CC 118
APPROVED
\~)
~r
\
BY
GRID CODE
CC 3 PRINCIPLES
cc 119
GRID CODE
(b) Magnitude of Load Demand for the facility and load profile;
(c) Linear Load Flow analysis and fault level studies in accordance
with the Planning Code by NTDC on behalf of applicant;
CC 120
GRID CODE
(b) The preliminary estimate for connection fee and registration fee.
Fees shall be determined and shall be payable on submission of
application for connection, and shall cover the following:
CC 121
W
GRID CODE
NTDC shall use its reasonable endeavor to advise the applicant of all
risks and obligations in respect of the proposed connection associated
with planning and compliance with environmental laws of the
Environmental Protection Agency (EPA) of Pakistan not contained in
this Code
The costs of assets (these assets do not include the existing assets of
Transmission Connection Points) at the Point of Connection including
material, civil works, cost of land and other ancillary costs shall be
borne by the applicant. However, the NTDC shall provide a preliminary
cost estimate for the new connection.
(b) Detailed design of the facility that the applicant intends to install;
(f) Copies of all safety rules and local safety instructions applicable
at applicant's Sites; and
CC 122
A?PRO'JED
B'f L
." ~ORIi'f:;-t
GRID CODE
Users, the affected Code Participants and Users shall also be invited to
evaluate the impacts and negotiate an agreement with the applicant.
The applicant shall pay registration and connection fees to the NTDC;
and the remaining information and data required should be submitted
to NTDC as soon as possible.
(c) copies of all safety rules and local safety instructions applicable
at the User's Sites which will be used at the NTDC/User
interface. These instructions must be to the satisfaction of
NTDC as set out in OC 9, CC 5.4 below;
CC 123
GRID CODE
(f) the proposed name of the User Site, which shall not be the
same as the name of any NTDC Site, or any other User Site;
(h) a list of Managers who have been duly authorised to sign Site
Responsibility Schedules on behalf of the User;
(k) NTDC shall provide written confirmation to the User that the
Safety Coordinators acting on behalf of NTDC are authorised
and competent pursuant.
(c) Must agree to comply with all the provisions of the Grid Code,
and Distribution Code (if applicable).
(d) Must abide by all related rules and regulations already issued or
to be promulgated in the future by the GOP or the relevant
authorities.
(e) Must agree to abide by all bindings, which are set out by the
environmental agencies.
cc 124
GRID CODE
The Generator shall follow the same procedure for seeking connection
to the NTDC Transmission System as mentioned in CC 4. However,
as a basis for negotiation for the connection agreement, the
Generators:
CC 125
GRID CODE
Prior to any disconnection, the NTDC shall inform NEPRA about the
disconnection proposal and its expected impact on the network.
(a) The Code Participant has rectified all such circumstances, which
were the cause of disconnection; and NTDC has agreed and
reasonably satisfied with the corrected status of the Code
Participant's facility.
(b) Abide by the obligations under Grid Code and Distribution Code
(if applicable).
(g) The Code Participant must maintain the Ouality of Supply (OoS)
and technical standards set out for the Point of Connections as
CC 127
GRID CODE
NTDC shall ensure that NTDC Transmission System complies with the
following technical, design and operation criteria at the Connection Site
with a User.
cc 128
GRID CODE
• Harmonic Content
Total Harmonic Distortions (THO) level should be
in accordance with IEEE Standard 519-1992
• Phase Unbalance
Under Planned Outage conditions, the maximum
negative phase sequence component of the phase
voltage on the NTDC Transmission System should
remain below 1% unless abnormal conditions
prevail.
• Voltage fluctuations/Dips
• Design of Connections
• Earthing Requirements
• Voltage Conditions
•
proposed Connection.
CC 129
GRID CODE
• Relay SeWngs.
• Equipment to be provided.
• Protection of Inter-connections.
cc 130
GRID CODE
• Lightning Protection
CC
GRID CODE
• Neutral Earthing
At Nominal System Voltage of 132kV and above
the higher voltage windings of a transformer of a
Generating Unit must be star-connected with the
star pOint suitable for connection to earth.
This part of the Grid Code describes the technical and design
criteria and performance requirements for authorized electricity
operators and Transmission connected Consumers.
CC 132
GRID CODE
• Connection Sites
(iii) Site Responsibility Schedules
• Format, Principles and Procedures to be used in
the preparation Site Responsibility Schedules
(SRS) (Appendix A)
CC 133
GRID CODE
• Appendix B (Part-I)
Principles and Procedures Relating to Operation
Diagrams.
• Appendix B (Part-II)
Principles and Procedures Relating to Gas Zone
Diagrams.
• Appendix B (Part-III)
List of all Apparatus to be shown on Operation and
Gas Zone Diagrams.
• Operation Diagrams
134
CC~
GRID CODE
U) Ancillary Services
The NTDC or the distribution company, as the case may be, who owns
the assets at the Point of Connection shall carry out the maintenance
of the equipment, including the equipment used for connection. All the
costs incurred in this respect shall be borne by the owner of the assets.
Open Access
Open Access requires that NTDC shall develop a set of procedures for
the receipt and management of requests for new connection to its
Transmission System. NTDC shall prepare and maintain a list of the
names of all persons requesting a connection to the system along with
pertinent data including: date of request, location of connection, MW
capacity of connection, name of line or substation to which the
connection is requested and expected in-service date. NTDC shall
provide NEPRA with a revised list whenever there is a change to the
list of applicants.
CC
~
GRID CODE
NTDC shall prepare load flow and short-circuit studies for each
proposed new connection and the study results shall distinguish in a
clear and impartial way between impact of a new connection on the
steady state power flow, and short circuit impacts of a proposed new
connection during summer and winter peak load conditions for the year
of proposed in-service date. Such studies shall not be made for a
given proposed new connection for years after the year of the proposed
new connection. NTDC shall advise each new connection of the
transmission and substation facilities to be added to allow the output
from the proposed new connection to flow onto the NTDC
Transmission System.
NTDC shall not require new connection to pay for upgrades and
improvements of the Transmission System that are beyond the
immediate Open Access Point of Connection. In the case of an Entity
being aggrieved by any determination of the Code Administrator
(NTDC), the decision shall be referred to Review Panel for arbitration.
cc 136
~/
GRID CODE
CC
GRID CODE
CC 72 Network Conditions
Parameters
{Based on I2revailing 500kV 220kV 132kV
Standards}
Frequency 50 Hz 50 Hz 50Hz
Configuration 3 phase, tri and 3 Phase single 3 Phase single
quad and twin and twin
bundle/phase bundle/phase bundle/phase
Neutral arrangement Solidly earthed Solidly earthed Solidly earthed
Nominal vOltage 500kV r.m.s 220kV r.m.s 132kV r.m.s
Highest voltage for 550kV r.m.s 245kV r.m.s 145KV r.m.s
equipment
Three phase 40 kA r.m.s 40 kA r.m.s 31.5/40 kA r.m.s
symmetrical short
circuit curren t
Three phase 100kAl125 kA 100 KPJ 125 kA 80/100 KA r.m.s
symmetrical peak r.m.s r.m.s
withstand current
Insulation
Coordination
Lightening impulse
with stand 1.2/50 us
a- To earth and 1550 kV peak 1050 kV peak 650 kV peak
between phases
b- Between open 1550 kV peak 1200 kV peak 750 kV peak
isolator contacts (+315)kV peak
One minute power
frequency withstand
a-To earth and 620 kV r.m.s 460 kV r.m_s 275 kV r.m.s
between phases
b- Between open 800 kV r.m.s 530 kV r.m.s 315 kV r.m.s
isolator contacts
CC 138
/
GRID CODE
APPENDIX A
OF
CONNECTION CODE
CC.A.1 Principles
Principles which form the basis of developing SRS
CC 139
GRID CODE
APPENDIX A
OF
CONNECTION CODE
(ATTACH MENT)
3. Identification of Apparatus.
12. Remarks
cc 140
GRID CODE
APPENDIX B
OF
CONNECTION CODE
(PART-I)
(The Operation Diagram shall include all HV Apparatus and the Connections to all
external circuits including Numbering, Nomenclature, Labeling as set out in OC 10).
CC
GRID CODE
APPENDIX B
OF
CONNECTION CODE
(PART-II)
cc 142
GRID CODE
APPENDIX B
OF
CONNECTION CODE
(PART-III)
List of all apparatus to be shown on the Operation and Gas Zone Diagrams that is
installed at the Connection Sites including its present status as it pertains to the
System Operation.
CC 143
GRID CODE
APPENDIX C
OF
CONNECTION CODE
CC.C.1 Scope
144
GRID CODE
APPENDIX D
OF
CONNECTION CODE
CC 145
~
GRID CODE
Annexure E
Scheme 1
INTERCONNECTION CONFIGURATIONS FOR GENERATORS
Connections at 11 kV
The Generators may adopt any of the configurations depending on its location with
reference to the substation and existing feeders and loading and operating condition
of the feeders.
To Consumers
Licensee's
Substation
Generator Substation
To Consumers
Licensee's
Substation
Generator Substation
CC 146
\\l,;
GRID CODE
Annexure E
Scheme 2
INTERCONNECTION CONFIGURATIONS FOR GENERATORS
Connections at 66kV
For connection of Generators at 66kV, two configurations have been indicated which
may be adopted according to the system conditions. The new Generators may opt
for new configurations, which NTDC/System Operator may accept after carrying out
necessary system studies.
66kV 66kV
Licensee's Licensee's
Substation Substation
Generator Substation
CC 147
GRID CODE
Annexure E
Scheme 2A
INTERCONNECTION CONFIGURATIONS FOR GENERATORS
Connections at 66kV
66kV 66kV
Licensee's Licensee's
Substation Substation
Generator Substation
cc 148
GRID CODE
Annexure E
Scheme 3
INTERCONNECTION CONFIGURATIONS FOR GENERATORS
Connections at 132kV
132kV 132kV
Licensee's Licensee's
Substation Substation
Generator Substation
cc 149
GRID CODE
Annexure E
Scheme 4
Interconnection Configurations for Generators
Connections at 220kV and 500kV
151
GIRD CODE
Annexure F
Figure-1
CONNECTION PROCEDURE
for New Connection or Modification
of Existing Connection
t t
DISCO NTDC APPLICANT
I I I I I I
Provide Additional
Information if Required
t Submit Fonnal
Application for
Final Evaluation of Connection
Application
~
Ik.u""lE..!3
t'-.Iake Connection
ReG
,,-,,c...)/ u(
CC 152
u
~
ll1
APPROVED
BY
~ ~~):t-
0
~ ~. THE AUTHORITY ~
9-<'A.. . .'-~
.:
GRID CODE
CONTENTS
PMC
\\\J. ~
GRID CODE
n) CT VA Burden test
PMC 154
GRID CODE
a. Purpose
PMC 155
GRID CODE
d. Principles
PMC 156
.~
GRID CODE
e. Metering Requirements
f. Standards
• IEC 61107
PMC 157
GRID CODE
g) Performance Requirements
PMC 158
GRID CODE
h) Installation
~
c~
THE AUTHORITY
,S)"
.7
GRID CODE
(ix) Active and Reactive Energy Import and Export (MWh and
MVARh)
j) Settlement of Accou nt
k) Access
NTDC. shall have the right to enter a distribution company and BPC
switchyards for the purpose of installing, checking, testing and
maintaining metering and related equipment and wires. Distribution
Companies and BPCs shall accommodate requests by the NTDC for
access on demand, and shall not prevent NTDC from making
unscheduled inspections on short notice.
a. General
PMC 162
GRID CODE
c. Generator Protection
(ii) In the event the fault clearance times are not met as a
result of a failure to operate the primary or main
protection system, a back-up or secondary protection
system shall be provided. Sack-up protection shall be
coordinated with the primary protection so as to provide
discrimination.
PMC 163
GRID CODE
d. Substation Protection
(i)
PMC
GRID CODE
--------------------------------------------------------~~--
PMC 165 i ~c... <?
APPROVED ~
~<.,;
~
~~.
'. ~~ THE AUTHORITY
BY
_y~
. r)
GRID CODE
f. SCADA
PMC 166
GRID CODE
NTDC shall have the right to' inspect 132 kV substations and
transmission lines that are connected to the Transmission
System of NTDC, and which are owned by DISCOs, SPCs,
SPTLs or any other Code Participant.
a. General
PMC 167
GRID CODE.
b. Switching Procedures
PMC 168
GRID CODE
PMC 31 Introduction
(c) Transformers
(d) Generators
where applicable
PMC 169
GRID CODE
(i i) Ground relays
(e) Generators
PMC
~
170
~
GRID CODE
PMC 171
~
GRID CODE
The line relaying system shall be arranged to allow for single pole
tripping of selected 220 kV and 500 kV transmission lines. One-shot
re-closing of the tripped line shall be allowed according to studies
designed to establish the best re-closing time. If the tripped phase fails
to re-close, all three phases will be tripped accordingly.
PMC 172
GRID CODE
PMC 173
GRID CODE
GENERATION SCHEDULING
CONTENTS
APPENDIX A
SCHEDULING AND DISPATCH CODE 1
Generation Scheduling and Dispatch Parameters
(GSDPs) SDC-192
APPENDIX B
Power plant, Daily Scheduling, Availability Notices SDC-194
APPENDIX C
GSDP Revision Notice SDC-198
APPENDIX 0
Notification of Revised Availability SDC-199
APPENDIX E
Power Plant, Daily Scheduling, Notices SDC-200
APPENDIX F
Notification of Revised, Availability/Range Availability SDC-201
APPENDIX G (Part 1)
Trading Data: Participating Generators SDC-202
APPENDIX G (Part 2)
Supplemental Energy Bids SDC-203
SDC-1
GRID CODE
GENERATION SCHEDULING
SOC 1.1.1 Scheduling and Dispatch Code ·No. 1 ("SOC 1") sets out the ..,., :
Procedure for:
(b) The daily Notification to the System Operator of whether there are
any Parameters which differ from the Contracted Generation
Scheduling and Dispatch Parameters (GSDPs) in respect of the
following schedule day by each Generator in a GSDP Notice;
(d) In the case of all Generators under Central Dispatch with PPA I
and/or PSODA as applicable, the submission to the System i
Operator of any revisions to fuel rates (or energy purchase prices, :
as the case may be) by such Generators as per the provisions of,
their PPA and/or PSODA as applicable. .
?
Notification" on the day before the Schedule Day as a
"Statement" of which of the Available Generators may be required
for the next Schedule Day.
SOC-1 175
GRID CODE
GENERATION SCHEDULING
,I
.'.:
'::
" ,
(b)
(c)
Ancillary Services Scheduling and Dispatch
Generator Outage Co-ordination
I~.
SOC 1.1.1 Scheduling and Dispatch Code 'No. 1 ("SOC 1") sets out the
Procedure for:
(b) The daily NoUfication to the System Operator of whether there are
,:
any Parameters which differ from the Contracted Generation
Scheduling and Dispat9h Parameters (GSDPs) in respect of the
following schedule day by each Generator in a GSDP Notice;
(d) In the case of all Generators under Central Dispatch with PPA
and/or PSODA as applicable, the submission to the System
Operator of any revisions to fuel rates (or energy purchase prices,
as the case may be) by such Generators as per the provisions of
.
their PPA and/or PSODA as applicable .
?
SDC-1 175
GRID CODE
SOC 1.1.2 The System Operator shall take into account the impacUeffects of power
transfers across any External Interconnection when preparing its
Generation Schedule (including taking into account the cost of any such
transfers when compiling the "Generation Schedule"); and any power
transfers across the NT DC's Transmission System.
SOC 1.1.3
(a) This sub-code (SOC 1) requires that each Generator under
Central Dispatch to submit an Availability Notice, the form of
which is set out in, Appendix B, which needs to be submitted in
writing or through telephone; and the required information is to be
submitted in full in such a notice.
SDC 1.1.4 In this SOC 1, the term "Notice Submission Time" shall mean,
10.00 a.m.
SDC 1.1.5 For the purposes of this SOC 1, any reference to the fuel used for a
CDGU shall, in the case of a PPA CDGU (regardless of the entity it is
contracting with) be construed as a reference to the Des'lgnated Fuel.
SDC-1 176
GRID CODE
SOC 1.4.1.1.a
(a) Each Generator including those at a Power Station with multiple
Generating Units shall, by no later than the notice submission
time each Schedule Day, notify the System Operator by means of
an Availability Notice, in the form set out in Appendix B to this
SOC 1 or in such other form as the System Operator/NTDC may
specify with the approval of NEPRA, notify to each Generator,
from time to time, the Availability of each of its COG Us.
(b) The Availability Notice shall state the Availability of the relevant
CDGU for each period in the following Schedule Day (subject to
revision under SOC 1.4.2.5(a)).
SOC 1.4.1.1.b In the case where a PPA CDGU (with/without PSODA) is capable of
firing on different fuels, then the Generator must submit an Availability
Notice in respect of each Designated Fuel for the CDGU, each
containing the information set out in SOC 1.4.1.1.a above for each
Designated Fuel and each marked clearly to indicate for which
Designated Fuel the Availability Notice applies to.
SOC 1.4.1.1 .c
(a) Notwithstanding that a CDGU has been declared unavailable. the
Generator shall submit all the information that it would have
submitted under this SOC 1 had the CDGU been declared
Available.
SDC-1
GRID CODE
(c) NTDC shall waive the rebate of Availability Payments for late
declaration of Availability under relevant schedule to the relevant
Power Purchase Agreement (PPA) and/or Power Station
Operation & Dispatch Agreement (PSODA) as applicable if the
Overburn Notice is issued by NTDC less than 24 hours in
advance of the start of the relevant settlement period.
SDC1.4.1.1.f
(i) The Availability Notice issued by the Generator at a Power Plant
where CDGUs can be operated Singly or in pairs, in accordance
with SOC 1.4.1.1 (a) Shall, in addition to the information required
by SOC 1.4.1.1 (a), state the CDGUs, that have been declared to
be Available for the next following Schedule Day, shall be
operated in pairs; and which CDGUs shall be singly operated.
For this purpose;
SOC-1 178
GRID CODE
(b) All the Generators under Central Dispatch Power Station with
multiple Generating Units shall use all reasonable endeavours to
ensure that it does not at any time declare by issuing or allowing
to remain outstanding an Availability Notice, or a GSDP Notice
which declares the Availability or GSDPs of the CDGU at levels or
values different from those that the CDGU could achieve at the
relevant time under its Purchase Agreement (PPA) and/or Power
Station Operation & Dispatch Agreement (PSODA) with NTDC
as applicable except under unavoidable circumstances with the
prior consent of the System Operator.
(c) Provided that nothing contained in this Grid Code shall require the
Generator to declare levels or values better than the Contracted
Capacity and the Contracted GSDPs in respect of a PPA CDGU.
SOC 1.4.1.3 If at any time when the Availability of a CDGU is zero, an Availability
Notice shall be given increasing the Availability of the CDGU with effect
from a specified time, such Notice shall (in the case of a steam turbine
CDGU) be construed as meaning that the CDGU is capable of being
synchronised with the NTDC's System at that specified time or, (in the
case of a gas turbine PPA CDGU), capable of being started at that
specified time. A dispatch instruction issued by the System Operator to
synchronise the CDGU to the NTDC's System or, as the case may be,
start the CDGU, at or after the specified time shall be a valid dispatch
instruction (regardless of the minimum time to synchronise specified in
the GSDPs).
SOC 1.4.1.4 If at any time when a CDGU is synchronised with the NTDC's System,
the Generator issues an Availability Notice increasing the level of
Availability of the CDGU from a specified time, such notice shall be
construed as meaning that the CDGU is capable of being dispatched to
increase generation to levels greater than the previously prevailing level
of Availability up to the level specified in the new Availability Notice but
commensurate with the maximum loading rate declared for the CDGU
as a GSDP from the specified time. ~
SOC-1 179
GRID CODE
SOC 14.1.5 If at any time when a COGU is synchronised with the NTDC's System,
the Generator issues an Availability Notice decreasing the level of
Availability of the COGU from a specified time, such Notice shall be
construed as meaning that the COGU is capable of maintaining output at
the level of the prevailing Availability until the time specified in the Notice
and thereafter, shall be capable of maintaining output to the level which
would have been achieved if a dispatch instruction had been given to
de-load, with effect from the specified time, at the maximum de-loading
rate declared for the COGU in the GSOP Notice at such time down to
the level of Availability specified in the new Availability Notice.
(a) (i) By no later than the notice submission time each Schedule
Day, each Generator shall in respect of each of its COGU
that has been declared Available in an Availability Notice
submit to the System Operator in a revised GSDP Notice, in
the form set out in Appendix C to this SOC 1 or in such other
form as the System Operator may notify to each Generator
from time to time.
(d) A Generator must notify NTDC in writing in the form set out in
Appendix C of this SOC 1 as soon as it becomes aware, acting in
accordance with prudent operating practices, if (whether due to a
defect in the CDGU or in its associated Power Plant equipment)
any of its CDGUs is unable to meet the Spinning Reserve
capability set out [in the case of a PPA CDGU (with/without
PSODA)] in the Sustained Load Diagram attached to relevant
Schedule of the Power Purchase Agreement (PPA) and/or
Power Station Operation & Dispatch Agreement (PSODA) as
applicable, and submitted pursuant to the Planning Code or
Connection Code or in the relevant applicable documents.
(a) By no later than the notice submission time each Schedule Day,
each Generator shall in respect of each CDGU which has been
declared Available in an Availability Notice under SOC 1.4.1.1 in
respect of the following Schedule Day submit to the System
Operator in writing (in the form set out in Appendix B to this SDC1
or in such other form as the System Operator may notify to each
Generator from time to time) details in relation to the following
Schedule Day of any "newly arisen special factors" which in the
reasonable opinion of the Generator may have a material effect
on the likely output of its Generating Unit. The notice must be
consistent with the Generator's obligations under the provisions of
SOC 1.4.1.2(b).
(b) In so far as not revised or if the fuel rate in the energy bid price
notice is higher than that deemed to have been submitted under
(a) above, the. most recently submitted generation or energy
prices shall apply for the relevant week.
SDC-1 182
GRID CODE
Excess Output
Unit Nominations
(b) Each Generator shall a day prior to the notice submission time
submit to the System Operator a Unit Nomination in accordance
with approved commercial arrangements as specified in the
approved Commercial Code.
(c) Before the notice submission time for each schedule day, each
Generator must give the System Operator the information
referred to in paragraph (c) below. The information must be in
the form set out in Appendix G to this SOC 1 or such other form
as the System Operator may specify from time to time. All Unit
Nominations are assumed to be expressed as "Generator Sent
Out Energy", and it is the responsibility of the Generators
concerned to take that into account when submitting Unit
Nominations.
(d) Each Generator must notify the System Operator of the number
of kWh of active electric energy each of its Generating Units
wants to deliver to the NTDC's System as power supply by the
Generator for each settlement period during the Schedule Day.
Unit Nominations must include:
SDC-1 183
GRID CODE
Once per week, on a day and time specified by the System Operator
from time to time but not less than two (2) hours before the occurrence
of maintenance outage, each Generator must, in respect of each of its
Power Plants, unless the data is supplied in some other agreed and
approved form, submit to the System Operator, in writing, details of the
Generating Unit Works Units for that Power Plant consumed by that
Power Plant since the last submission under this SOC 1.4.2.4, together
with such other information as the System Operator may require in order
to calculate the Generating Unit Works Units consumed by each COGU
at ttlat Power Plant.
(b) If any of the data submitted to the System Operator under SOC
1.4.2.1 and SOC 1.4.2.2 changes, a Generator must (in the case
of data submitted under SOC 1.4.2.1 by means of a GSOP
Notice) make revisions to such data and must notify the System
Operator of any revisions to any previously revised data by
submitting another Revised GSOP Notice (in the form set out in
Appendix C to this SOC 1 or in such other form as the System
Operator may reasonably notify to each Generator from time to
time) and must notify the System Opera tor of any Other
Generation Relevant Oata of which it becomes aware at any time
after any original submission in writing. The System Operator
shall, insofar as it is reasonably possible, take account of such
revisions or notifications. The provisions of SOC 1.4.2.1 (b) shall
SDC-1 184
,\9,/
GRID CODE
SOC 1.4.2.6 (a) (i) Insofar as any data submitted or deemed to have been
submitted on any particular day in any Availability Notice,
GSOP Notice, or Notice of Other Generation Relevant Data
or any revision thereto is inconsistent with any other data in
any other such notice, then the most recently submitted
data which, if substituted for the inconsistent data, would
make the data in such notices consistent, shall apply for the
next following Schedule Day.
(a) Sixty days prior to 1 April of each year, all bilateral contracts
shall be submitted to NEPRA, NTDC, CRPEA and the System
Operator for review and approval.
SDC-1 185
GRID CODE
SDC 1.4.3.1 A Generation Schedule shall be compiled daily by the System Operator
as an "Internal Statement" of which CDGUs and/or power transfer
across any External Interconnection may be required for the next
following Schedule Day.
If there is more than one Merit Order Price Set offered, then the CDGU
shall appear in the Merit Order for each Merit Order Price Set submitted.
SDC 14.3.3 In compiling the "Final Generation Schedule", the System Operator shall
take account of, and give due regard and weightage to the following
factors:
SDC-1 186
,\r!",) "
GRID CODE
(f) The need to provide the required Operating Margin by using the
various categories of Reserve as specified in OC4 and OC5), as
determined by the System Operator;
(i) System tests being carried out or to be carried out under OC11;
(m) The inability of any COGU to meet its full Spinning Reserve
capability; and
(n) The availability and cost of power transfers across any External
Interconnection.
SOC 1.4.3.4 Taking into account of and applying the factors referred to in SOC
1.4.3.3 above, the "Final Generation Schedule" shall be compiled by the
System Operator to Schedule such COGUs which have been declared
Available in an Availability Notice, and are the subject of a Unit
Nomination, and power transfers across any External Interconnection:
(a) The System Operator shall ensure that all COGUs are Scheduled
in accordance with their Unit Nominations;
(b) In accordance with the Merit Order, starting with the least-cost
COGU at the head of the Merit Order; and taking into account the~_ _
cost of power transfers across any External Interconnection; '(O\"JER RtG
~iV GI(:
......~ ~/'
----------------------------------------------------~~~~- 0
SDC-1 187 ~
GRID CODE
SOC 1.4.3.5 After the completion of the scheduling process, but before the issuance
of Day-ahead Notification, the System Operator may consider it
necessary to make adjustments to the output of the scheduling process.
Such adjustments may be required to be necessary due to any of the
following factors:
(b) There is a high risk to the whole or part of the NTDC's System;
(c) Load demand management and control has been instructed by
the System Operator;
SOC 1.4.3.7 (a) The synchronising and de-synchronising times shown in the Day Ahead
Notification are Indicative only; and it should be borne in mind by all the
Generators that the actual dispatch instructions may reflect more or
different COGU requirements than in the Day Ahead Notification.
although they should (subject to SOC 2) reflect Unit Nominations. The
System Operator may issue dispatch instructions in respect of a COGU
which may not have been declared "Wholly Unavailable" in an
Availability Notice. The Generators with CDGUs must ensure that their
Generating Units are available, able and ready to be synchronised at the
times scheduled but only if so dispatched by the NT DC by issue of a
dispatch instruction. The Generators shall, as part of a revision to the
GSDPs. indicate to the System Operator the earliest time at which a
dispatch instruction is required to meet the scheduled synchronising
time. o\~ER Rt:-
<? C"G
<i!v ~<.;
--------------------------------------------------~~~~~~.
SDC-1 189 PPROVE 0
~~ -.J
lU .
~ BY ~
\~~t7A ~o THE AUTHORITY J
V,
f;. "
k'
GRID CODE
SOC 14.3.10 The Day Ahead Notification received by each Generator shall contain
information relating to its CDGUs only.
Appendix A sets out the GSDPs for whiCh values are to be supplied by a )
Generator in respect of each of its CDGUs by no later than the notice,
submission time on the day prior to the Schedule Day. :,
\
For the purpose of Verification, the NTDC shall provide accurate active
and reactive power measuring instruments at the Points of Connection
between NTDC and Code Participants. For billing purposes and
account settlement, the NTDC shall provide revenue metering at the
Points of Connection, as specified in the Protection and Metering
Code. The information shall be collected by the NTDC SCADA System
and communicated to the NTDCI System Operatorl as appropriate.
The System Operator has the sole authority to Schedule and Dispatch
generation, manage and discipline a secure and safe operation of the
NTDC's Transmission System. The Code Participants who are
contracted to supply generation power supplies must comply with the
dispatch instructions of the System Operator, in totality, regardless of
their circumstances or prevailing conditions. Any Failure of Code
Participant to comply with dispatch instructions of the System Operator
shall be subject to penalties, in accordance with the provisions of the
Grid Code under Code Management sub-code.
SDC-1 191
GRID CODE
APPENDIX A
(b) in the case of gas turbine CDGUs, the time from initiation
of a start to achieving dispatched load.
2. Basic data:
4. Minimum on time;
6. Maximum loading rates for the various levels of warmth and for
up to two output ranges.
SDC-1 192
GRID CODE
14. Settings of the Unit Load Controller for each CDGU for which a
Unit Load Controller is required under CC7.5.5.
15. in the case of gas turbine CDGUs only, ttle declared peak
capacity.
In the case of a Gas Turbine Unit, only the data applicable to Gas
Turbine Units should be supplied.
SDC-1 193
GRID CODE
APPENDIX B
FACSlf.IILE
TO Page 1 of 4
FAX
FROM
AVAILABILITY NOTICE
Tne ayailabllity of each CDGU at [ ] Power plant for the schedule day to which this notice refers is shown on page
2 attached.
2. ENERGY BID PRICE NOTICE (Rs/MWHr· enter bid price where appropriate)
[ Power Limited] offers NTDC the following energy prices (which are lower than the contracted prices) for the
Schedule Day to which this notice refers.
[Fuel) (Fuel)
[Fuel\ (Fuel)
[Fuel]
3 GSDP NOTICE
Tne Generation Scheduling and Dispatch Parameters for each CDGU at [ ) Power Plant for the Schedule Day to
which this notice refers are as given in Schedule 1 of the relevant Power Purchase Agreement (PPA) or
Power Station Operation & Dispatch Agreement (PSODA)
(11110, each GSDP which varies from Schedule 1 must be shown on page 3 at1ached
If 'rES. page 3 shall be omitted)
5 DECLARATION
Tnese notices are issued by ( Power Limited) in respect of the Centrally Dispatched Generating Units (C DGUs)
al [ ] Power Plant in accordance with the requirements of SOC 1.
We declare that the figures and other information given in the notices fully renect the actual capability of the CDGUs.
Dale!Time of Issue:
SDC-1 194
,\(]
GRID CODE
AVAILABILITY NOTICE
Paqe 2 of 4
Settlement [UNITS ON OIL] [UNITS ON GAS] GAS TURBINES
Period REDUCTION
2 2 2
Contracted
Capacity
0000· 0030
0030· 0100
0100·0130
0130·0200
0200·0230
0230·0300
0300·0330
0330·0400
0400·0430
0430 ·0500
0500 ·0530
0530·0600
0600· 0630
0630·0700
0700·0730
0730 ·OBOO
0800·0B30
0830· 0900
0900·0930
0930 ·1000
1000 ·1030
1030 ·1100
1100 ·1130
1130 ·1200
1200 ·1230
1230 ·1300
1300·1330
1330 ·1400
1400·1430
1430·1500
1500·1530
1530·1600
1600·1630
1630 ·1700
1700 ·1730
1730·1BOO
1800 ·1830
1830 ·1900
1900 ·1930
1930·2000
2000 ·2030
2030 ·2100
2100·2130
2130·2200
2200 ·2230
2230·2300
2300·2330
2330·2400
/
I
~
SDC·1 195
GRID CODE
GSDPNOTICE Page 3 of 4
Power Limitedl declares that the undermenlioned CDGUs are presently unable to perform to the
characteristics stated in [Schedule 1 of the relevant Power Purchase Agreement (PPA) or Power Station
Operation & Dispatch Agreement (PSODA)I and that the affected characteristics are mentioned below with
revised values that shOuld be used for the purposes of Scheduling and Dispatch.
S,gnalure: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __
SDC-1 196
GRID CODE
Page 4 of 4
Noles
1. All Availabilities shall be expressed in MW. Alongside the MW figure shall be placed
the unit operating status (in brackets) as defined by the Final Generation Outage
Programme: 1 = Normal Availability, 2 = Innexible Outage, 3 = Flexible Planned
Outage, 4 = Advanced Flexible Planned Outage, 5 = Deferred Flexible Planned
=
Outage, 6 = Short Term Planned Maintenance Outage, 7 Return to Service, 8 =
Notified Unplanned Outage, 9 = Forced Outage.
2. For each CDGU, an Availability figure must be entered for the first settlement period.
Where the CDGU is completely unavailable, a zero shall be entered. Thereafter, an
Availability figure shall only be entered where the Availability for the CDGU is changed
from the previously expressed value.
3. This Availability Notice shall include all planned Outages agreed with NTDC and all
Unplanned/Forced Outages already notified to NTDC. It shall not include
Unplanned/Forced Outages not yet notified to NTDC unless the appropriate Outage
Notice is attached.
Signature: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __
SDC-1 197
\\()
GRID CODE
APPENDIXC
FACSlf.lIlE Page 1 of 1
TO/FRCI.I NTDC Control Centre. X)o()(XJOO<. XXXXXXXXXXXXXXXXJ<XX:O.X
FAX { ]
FROf.110 { Power Limited]
Signalure _ _ _ _ _ _ _ _ _ _ _ _ Name: _ _ _ _ _ _ _ _ _ _ _ _ _ _ __
(in block capitals)
pC\llion: Commercial Engineer/Control Engineer (delete as 'lpplicable)
OalelTime of Issue· _ _ _ _ _ _ _ _ _ _ _ _ _ __
SDC-1 198
GRID CODE
APPENDIX D
(SCHEDULING AND DISPATCH CODE 1)
Page 1 of 1
NOTIFICATION OF REVISED AVAILABILITY
Settlement UNITS ON OIL UNITS ON GAS GAS TURBINES
Period 1 2 2 2
Conlracted
Capacrty
0000 ·0030
0030 ·0100
0100 ·Ot30
0130 ·0200
0200·0230
0230 ·0300
0300·0330
0330·0400
0400·0430
0430 ·0500
0500 ·0530
0530 ·0600
0600 ·0630
0630 ·0700
0700·0730
0730 ·0800
0800 ·0830
0830 ·0900
0900 ·0930
0930 ·1000
1000 ·1030
1030· I 100
1100 ·1130
1130· t200
1200 ·1230
1230 ·1300
1300 ·1330
1330·1400
1400· 1n0
1430 ·1500
1500 ·1530
1530·1600
1600 ·1630
1630 ·1700
1700 ·1730
1730 ·1800
1800 ·1830
1830 ·1900
1900 ·1930
1930·2000
2000·2030
2030·2100
2100·2130
2130·2200
2200·2230
2230 ·2300
2300·2330
2330 - 2400
Notes
I. An Availabilities shall be expressed in MW. Alongside the MW figure shall be placed the unit operating status (in
brackets) as defined by the Final Generation Outage Programme: 1 = Normal Ayailability. 2 = Inflexible Planned
Outage. 3 = Flexible Planned Outage. 4 = Advanced Flexible Planned Outage. 5 = Deferred Flexible Planned Outage.
6: Short Term Planned Maintenance Outage. 7 = Relurn to Service.
2 For each CDGU. an Availability figure shall be entered in respect 01 the releyant settlement period(s) where the
Availability of the CDGU is changed Irom a value notified preYiousty in an Availability Notice. Where the Change in
Availability occurs otherwise than at the commencement 01 an Availabitity period. an appropriate annotation must be
made. stating the exact time 01 the change. II the CDGU is unavailable. a zero shall be entered.
SDC-1 199
GRID CODE
APPENDIX E
Page 1 of 1
(SCHEDULING AND DISPATCH CODE 1)
FACSIMILE
FAX: [
FROM : [
1 AVAJLABILITY NOTICE
The A,a1labllity of each CDGU for the schedule day 10 which this nolice refers is shown on page 2 attached.
2 ENERGY BID PRICE NOTICE [£.x.xlUxlGJ • enter bid price where appropriate)
[ I oHers NTDC the following energy prices (whiCh are lower Ihan Ihe
contracted prices) tor the week commencing the Monday following this notice.
(Fuel)
3 GSDP NOTICE
Ttle G.neration Scheduling and Dispatch Parameters for each COGU at [ I Power plant for the SChedule day to which this
notice relers are as given under Contracted Operating Characteristics In the respective Schedule at the relevant Power Purchase
Agreement (PPA) or POwer Station Operation & Dispalch Agreement (PSODA)
(If NO. each GSDP which varie strom Schedule 1 contracted operating characleristics must be
on page 3 attached If YES page 3 Shall be omitted)
5 DECLARATION
We declare thai the figures and other infonmalion given in Ihe notices fully renect the actual
capab~ty of the CDGUs and Ranges.
Slgnalure· _ _ _ _ _ _ _ _ _ _ _ __
Name __~-----------------
(in block capitals)
OatelT:me of Issue' _ _ _ _ _ _ _ _ _ _ _ _ __
SDC-1 200
GRID CODE
APPENDIX F
FACSIMILE
TO : NTDC Control Centre, XJ()()(lO(X)OU(, ~ Page 1 of 1
FAX: [
FROM : [
Nole: where Availability is being increased, the time to be slated for the
increase to take effect shall be staled in accordance with the Grid Code.
This notice confirms the telephone notice issued at (insert time of telephone notice, if
applicable). If this notice contradicts the information given in the telephone notice it shall be
disregarded and NTDC shall so inform the Generator.
Signature: _ _ _ _ _ _ _ _ _ _ _ __ Name:
(in block capitals)
SDC-1 201
\\C)y
GRID CODE
APPENDIX G
Page 1 of 2
(SCHEDULING AND DISPATCH CODE 1)
PART 1
UNIT NOMINATIONS
Unit
Settlement
Nomination
Period
(Totals)
(kWh)
Start End
06.00 06.30
06.30 07.00
07.00 07.30
07.30 08.00
08.00 08.30
08.30 09.00
09.00 09.30
09.30 10.00
10.00 10.30
10.30 11.00
11.00 11.30
11.30 12.00
12.00 12.30
12.30 13.00
13.00 13.30
13.30 14.00
14.00 14.30
14.30 15.00
05.00 05.30
05.30 06.00
SDC-1 202
GRID CODE
APPENDIX G
Page 1 of 2
(SCHEDULING AND DISPATCH CODE 1)
PART 2
SOC-1 203
\\1/
GRID CODE
CONTENTS
SDC-205
SOC 2.1 INTRODUCTION
SDC-205
SOC 2.2 OBJECTIVE
SDC-205
SOC 2.3 SCOPE
SDC-206
SOC 2.4 PROCEDURE
APPENDIX A SDC-214
DISPATCH INSTRUCTIONS FOR CDGUS
GRID CODE
SOC 2.1.1 Scheduling and Dispatch Code No.2 ("SOC 2") sets out the procedure s
for the System Operator to issue dispatch instructions to Generators in
respect of their COGUs (in relation to their Unit Nominations) as per
"Final Generation Schedule" concluded in SOC 1. This sub-code is
supplemental to SOC 1 and SOC 3.
SOC·2
GRID CODE
SOC 24.1.1 The information which the System Operator shall use in assessing as to
which CDGU to dispatch, shall be the 1) Availability Notice; 2) Unit
Nominations; 3) Merit Order as derived under SOC 1; 4) Other factors to
be taken into account as listed in SOC 1 (SOC 1.4.3.3); 5) Generation
Scheduling and Dispatch Parameters (GSOPs); 6) Operating Reserve
Characteristics, and; 7) Other Generation Relevant Data in respect of
that COGU, supplied to it under SOC 1 (and any revisions under SOC 1
and this SOC 2 to the date).
SOC 2.4.1.2 Subject as provided below, the factors used in the dispatch phase in
assessing which COGUs to dispatch in conjunction with the Merit Order
as derived under SOC 1, and the other matters identified in SOC 1.4.3,
SOC 1.4.3.3 and SOC 1.4.3.5 and SOC 1.4.3.6 shall be those used by
the System Operator to compile the Generation Schedule under SOC 1.
SOC 2.4.1.3 Additional factors which the System Operator shall, however, also take
into account are those Generators who have not complied with dispatch
instructions or; "special actions requests" which the System Operator
has (in its absolute discretion) granted for the early synchronisation of a
COGU to the NTDC System; requests which System Operator has made
and to which the Generator has agreed to for an early or late
synchronisation of a CDGU to the NTOC's System; and variation
between forecasted and actual NTDC system demand, as these can
have an impact on the overall dispatch. The System Operator shall also
take into account the need to dispatch CDGUs for monitoring, testing or
investigation purposes under OC11, or for testing at the request of a
User, under OC11.2.
SOC 2.4.1.4 In the event of two or more COGUs having the same "Merit Order Price
Set" and the System Operator not being able to differentiate on the basis
of the factors identified in SOC 1.4.3.2, SOC 1.4.3.3 and SOC 1.4.3.4,
the System Operator shall select for dispatch first the Generator which in
System Operator's best reasonable judgement is most appropriate
under the circumstances and prevailing conditions of the Scheduling
Day.
206
GRID CODE
SOC 2.4.2.2 (a) The System Operator shall issue dispatch instructions direct to
the Generator for the dispatch of each of its CDGU. Subject to
the provisions of this SOC 2, the System Operator shall issue
dispatch instructions with respect to information submitted by
each Generator. The System Operator may issue dispatch
instructions for any CDGU which has been declared Available in
an Availability Notice even if that COGU was not included in the
Day Ahead Notification subject to Its availability later on.
i
Notice". The System Operator may, however, use a
separate dispatched fuel notice and which may be issued
separately from any dispatch instruction, containing the
above information.
,?O\fJER REo
____________________________________________________~~~~G---- CL~~
1JJ 0
SOC-2 207 ~ ~
llJ -<
BY
~
-l l>
~ THE AUTHORITY $
9 ~
"''1- * . .... ,,-.,;~
-~~------------------------~
GRID CODE
208
SDC·2
\\n
..J-., .. F
GRID CODE
(b) Dispatch
MW (at
SDC·2 209
\\G
GRID CODE
SOC 2.4.2.8 The form, manner, and the terms to be used by System Operator in
issuing dispatch instructions together with their meanings are set out in
the attached appendices ..
SOC2.4.2.9 Subject only to SOC 2.4.2.8, and as provided below in the SOC 1 and
SOC 2, dispatch instructions shall not be inconsistent with the
Availability, Unit Nominations, Contracted GSDPs, and Other Generation
Relevant Data notified to the System Operator under SOC 1 (and any
revisions under SOC 1 or this SOC 2 to that data). A dispatch instruction
may be subsequently cancelled or varied (including an instruction for a
cancelled start) at any time. The dispatch instructions may, however, be
inconsistent with the Availability and/or Unit Nominations and/or GSDPs
and/or Other Generation Relevant Data so notified to the System
Operator for the purposes of carrying out a test at the request of the
relevant Generator under OC12.3 or a system test at the request of the
relevant Generator under OC11.2, to the extent that such dispatch
instructions are consistent with the procedures agreed (or otherwise
determined) for conducting the test or system test (as the case may be).
For the avoidance of doubt, any dispatch instructions issued by the
System Operator for the purposes of carrying out a test at the request of
the relevant Generator under OC 12.3 or a system test at the reques t of
O.i
the relevant Generator under OC11.2 shall not be deemed to be
d ispal ch ins Iruelions given pur suanl 10 S DC 2 4 .2.1
SDC-2 210
\\Ct
GRID CODE
Each Generator shall comply in accordance with SOC 2.4.2.13 and their
Power Purchase Agreement (PPA) or Power Station Operation &
Dispatch Agreement (PSOOA) as applicable with all dispatch
instructions properly given by the System Operator unless the Generator
has given a notice to System Operator under the provisions of SOC
2.4.2.10 regarding non-agreement of dispatch instructions. A Generator
shall not, however, be in default in complying with the dispatch
instructions, if. subsequent to the issuance of the dispatch instruction,
the Generator and the System Operator agree on an early
'\l()=--:-<-'~
~G
"
SOC·2 211
GRID CODE
SOC 2.4.2.14 Subject to the exception set out below in th'ls SOC 2:4.2."4. the
Generators shall only synchronise or de-synchronise COGUs tD 1he
dispatch instructions of the System Operator or unless it occurs
automatically as a result of fntertrip schemes or low-frequency relay
operations. De-synchronisation may otherwise only take place lM#lout
the System Operator's prior agreement if it is done to avoid. iA-1t'1e
Generator's reasonable opinion, an imminent risk of injury to persons or
material damage to property (including the COGU) exists_ If 1hat
happens, the System Operator must be informed that it has done so
within ten (10) minutes of the de-synchronization of the Unit.
SDC 24.2.15 The System Operator may suspend the issuance of the Dispatch
instructions to a particular Generating Unit in a plant in accordance with
the Merit Order (having taken account of and applied the factors referred
to in SOC 1.4.3.3 to the extent that the conditions in SOC 1.43_5 ~se.
When necessary, the System Operator shall issue dispatch instruclions
for a Black Start.
SOC 2.4.2.17 Each Generator at its Power Plant shall operate its syndlronised
COGUs with AVRs and VAR limiters in service at all times (where
required pursuant to generator control arrangements contained in
PPNPSODA or Connection Code) unless released from this obligation
in respect of a particular CDGU by the System Operator.
SOC-2 212
GRID CODE
SOC·2 213
GRID CODE
SOC 2 • APPENDIX A
(iii) If the start time is different from the time the instruction is
issued, the start time shall be included;
(vi) The Designated Fuel and/or declared fuel (or fuel), as the
case may be;
soc 2A21 If the time of the dispatch instruction is 1400 hours, the unit is unit 1 and
the Output to be achieved is 205 MW, the relevant part of the instruction
would be, for example:
"Time 1400 hours. Unit 1 to 205 MW"
GRID CODE'
SOC 2.A.2.2 If the start time is 1415 hours, it would be, for example:
"Time 1400 hours. Unit 1'to 205 MW, start at 1415 hours"
SOC 2.A.2.3 Loading and de-loading rates are assull!ed to be in accordance with
Generation Scheduling and Dispatch Parameters (GSOPs) unless
otherwise stated. If differE;1nt loading or de-loading rates are required,
the time to be achieved shail be' stated, for example:
"Time 1400 hours. Unit 1 to 205 MW by 1420 hours"
SOC 2.A.3.1.1 In this instance, for COGUs, the dispatch instruction issue time shall
always have due regard for the synchronising time declared to System
Operator by the Generator as a GSOP.
SOC 2.A.3.1.2 Unless a loading programme is also given at the same time it shall be
assumed that the COGU(s) are to be brought to minimum generation
level and on the Generator reporting that the Generating Unit has been
synchronised, a further dispatch instruction shall be issued.
soc 2.A.3.2.1 The dispatch instruction shall normally follow the form, for example:
"Time 1300 hours. Unit 1, Shutdown".
If the instruction start time is for 1400 hours the form shall be. for
example:
"Time 1300 hours. Unit 1, Shutdown, start at 1400 hours"
SOC·2 215
GRID CODE
SOC 2A4.1 All the above dispatch instructions shall be deemed to be at "Target
System Frequency" (50 Hz), i.e. where a COGU is in the Frequency
Sensitive Mode, instructions refer to target Output at Target System
Frequency. Target System Frequency changes shall always be given to
the Generator by telephone and shall normally only be 49.95, 50.00,
50.05Hz (at an interval of 0.05 Hz).
SOC·2 216
Wr
GRID CODE
'0
When the System Operator wishes to instruct a Generator operate its
Gas Turbine PPA COGU at a level in excess of its Availabl'rty in
accordance with SOC 2.4.2.4U>, the instruction shall follow the form, for
example:
SDC·2 217
GRID CODE
SDC-2 218
GRID CODE
FREQUENCY CONTROL
CONTENTS
INTRODUCTION SDC-217
SOC 3.1
OBJECTIVE SDC-219
SOC 3.2
SCOPE SDC-219
SOC 3.3
PROCEDURE SDC-220
SOC 3.4
FREQUENCY CONTROL
soc 3.1.1 SOC 3 sets out the procedure by which the System Operator shall use to
direct frequency control. The NTOC System Frequency shall be
controlled by:-
soc 31.2 The requirements for frequency control are determined by the
consequences and effectiveness of generation scheduling and dispatch;
and by the effects of power transfers across any External
Interconnection; and therefore, SOC 3 is supplemental to SOC 1 and
SOC 2.
SOC·3 219
GRID CODE
SOC 3.4.1.1 (a) All CDGUs must be capable of operating at all times in Frequency
Sensitive Mode (including, wh~He applicable, with the Unit Load
Controller in Operation) which means an automatic incremental or
decremental generation response (Primary Response) to contain
the initial system frequency change together with a sustained
generation and load response (Secondary Response) which can
contribute to correcting and containing the system frequency within
the requirements for frequency control contained in this Grid Code
and NEPRA Transmission Performance Standards Rules.
SOC 3.4.1.2 A System Frequency induced change in the Active Power Output of
COGUs which assists the recovery to Target System Frequency must
not be manually overridden by a Generator except where it is necessary,
in the Generator's reasonable opinion, to avoid an imminent risk of injury
to persons or material damage to property (including the CDGU) with the
consent of the System Operator.
SOC 3.4.2.2
SOC·3
GRID CODE
SOC 3.4.3 Low frequency relay initiated response from Gas Turbine PPA CDGUs.
SOC 3.4.3,1 The System Operator may allocate a part of the requirements for
Operating Reserve to Gas Turbine PPA CDGUs with the capability of
low frequency relay initiated response for start-up to a pre-determined
output level which have not been sCheduled for dispatch in accordance
with SOC 1, altt)ou'gh the System Operator may, in the event, decide to
issue a dispatch- instruction in respect of any of such CDGU in
accordance with SOC 2. Alternatively, Gas Turbine PPA COGUs of this
type may be scheduled for dispatch by the System Operator in
accordance with SOC 1. .
SOC 3.4.3,2 The System Operator shall periodically specify, within the range
established pursuant to the Connection Agreement, low frequency relay
settings to be applied to the CDGUs pursuant to SOC 3.4.3.1 and shall
instruct the low frequency relay initiated response to be placed in and
out of service.
SOC 3.43.3 All Generators and Users/Code Participants shall comply with System
Operators instructions issued under SOC 3.4.3.2 for low frequency relay
settings. The Generators shall not alter such low frequency relay settings
or take low frequency initiated response out-of-service without the
System Operator authorization, except where necessary, in the
Generator's reasonable opinion, to avoid an imminent risk of injury to
persons or material damage to property (inc!~ding the CDGU) with the
authorization of the System Operator.
SOC 3.5,1 (a) If the NTOC System Frequency falls to or below 49.8 Hz, each
Generator at its Power Plant shall be required to check that each
of its COGUs is achieving the required levels of response
including that required from the Unit Load Controller, where
applicable, in order to contribute to containing and correcting the
low System Frequency.
SOC 3,5.2 In order that the System Operator can deal with emergency conditions
effectively, it needs as much up-to-date information as possible and
accordingly, the System Operator shall be informed of the action taken
as soon as possible after the fall in the System Frequency directly by
telephone from the Power Plant.
SOC 3.6,1 If the NTOC System Frequency rises to or above 50.2 Hz, each
Generator at its Power Plant shall be required to ensure that each of its
COGUs has responded in order to contribute to correcting and
containing the high System Frequency by automatically or manually
SDC-3 221
\\~/
. ,
,
GRID CODE
SOC 3.6.2 This reduction shall have to be made without reference to the System
Operator: and must be maintained until the NTOC System Frequency
has returned to Target System Frequency or receipt of revised dispatch
instructions from the System Operator under SOC 2. In order that the
System Operator can deal with the emergency conditions effectively, it
needs as much up-to-date information as possible and accordingly, the
System Operator must be informed of the action taken as soon as
possible after the rise in System Frequency directly by telephone from
the generating plant.
SOC 3.7.1 The System Operator shall endeavour (in so far as it is able to) control
electric clock time to within plus or minus 10 seconds of Standard Time
by specifying changes to target the NTOC's System Frequency, and by
dispatch taking into account Merit Order and forecast Power PlanULoad
Demand margins. Errors greater than plus or minus 10 seconds may be
temporarily accepted at the System Operator's reasonable disaetion.
The System Operator shall give 15 minutes notice to each generator of
variation in Target System Frequency.
SDC·3 222
~/.
GRID CODE
The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached). -
G&D 223
1"fir"~
t,
~
UJ
~.~
'"
BY
..
APPROVE 0
I~
0
The Terms Not Contained here have been Defined in Various Applicable
Documents.of NEPRA and li.sted as Annexure-A (attached).
The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached).
The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached).
The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached).
Grid Entry Point SOC A point at which a Generator connects to the NTDC
System.
Grid Exit Point SOC A point at which electricity may be delivered from the
NTDC System to a Bulk Power Consumer. Distribution
Company or to a Tie-line or to Externally-connected
Parties/Consumers.
GSDP Notice SOC 1 A Notification given by a Generator to NTDC stating the
Appendix B GSDPs of a CDGU to apply for the next following
Schedule Day which, if given by not later than the Notice
Submission Time. shall be in the form set out in
Appendix B to SDC1 or in such other form as
NTDC/System Operator may reasonably notify to each
Generator from time to time. and which, if given after the
Notice Submission Time, shall be in the form set out in
Appendix C to SDC1 (which is headed "GSDP Revision
Notice") or in such other form as NTDC may reasonably
notify each Generator from time to time. I
Half Hour OC 4 Means any 30-Minute period ending on the Hour or Half
Hour
Hot Standby SOC A condition of readiness to be able to synchronize and
attain an instructed output in a specified time period that
must be maintained b~ Generator.
IGeEP OC Indicative Generation Capacitl'" Ex~ansion Plan
Incidents OCB An event of external or internal origin. affecting
equipment or the supply system, and which disturbs the
normal operation of the System.
Incremental Price SOC 1 The marginal price (i.e. incremental price for each MWh
AppendixG produced) between zero and Normal Full Load (NFL)
Capacity of a Generator.
Independent SOC A Generator not owned by any public sector entity which
Generating Plant mayor may not be sut&ect to Central Dispatch.
Independent Power PC 3 A private power generating company not owned/
Producer (IPP) controlled by any public sector organization but subject
to Central Dispatch.
Initial Response SOC The device by which NTDC can issue a signal by way of
Instructor dispatch relating to the loading of CDGUs from the
National Power Control Centre (NPCC) to the
Generators.
Instrument SOC A transformer intended to transmit an information signal
Transformer to measuring instruments, meters and protective or
control devices. The term "instrument transfonner"
encompasses both current transformer and voltage
transformers.
Inter tripping Scheme PMC The tripping of circuit-breaker(s) by signals initiated from
protection at a remote location indepen en~\'$rat~
G&D
\\~/
of the local ~rotection.
232 It 'y
rC."V
V.J
c;j
F---I_I
<,
....
APPROVED
BY
GL(
~.0"5.
:t>
fHE: A!lTI!,"""TV C
GRID CODE
The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached).
~
G&D 233 ~ '::i APPROVED .~
l~ TUC ~t~~nnITv s)
GRID CODE
The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached).
\\~/
G&D 234
~ UJ BY :t>
_J c:
.:i I!~ r. ~ ! I T ~ () Q f TV" ,
GRID CODE
The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached). "
'1 !J:7:,
J..
Peak Capability SOC In relation to a -.9,as turbine COGU.j1fe ca ~';I~~ I
~ ,',
3 ," APPROVED -~
,(..~ ()
~
G&0 235 .
, 1~~1
'.J" BY- 1:> I
~\ THE AUTHORITY I~
GRID CODE
The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached).
Po'mt of Con nection CC 5.4 An electrical Connection Point between the NTDC bulk
power transmission system and a User's/Code
Participant System as defined in OC 4.2 of the Grid
Code.
Power Line Carrier OC6 Communications system of radio frequency generally
(PLC) under 600 kHz, which transmits infonnation using high
voltage transmission lines.
Power Plant SDC 1 An installation comprising one or more Generating Units
Appendix A & B owned and controlled by the same Generator.
CC 1
Power Purchase SDC 1 Power Purchase Agreement is between the Seller
Agreement (PPA) ("Generator" in this case) and the Buyer [licensed
distribution companies, Bulk Power Consumers whether
directly or indirectly connected to the NTDC's bulk
transmission system and other Persons as stated in
DRC 1.2 (d)], other externally-connected Parties and
Consumers, for the purpose of purchase of electric
power and energy.
The Power Purchase Agreement mayl contain
operational, control, dispatch, outage and maintenance
procedures and requirements of the power station,
technical limits, GSDPs, Generation Performance
Charts, and other Generator data requirements stated in
various sub-codes of this Grid Code or it may refer to the
Grid Code for such requirements.
Power Station SDC 1 Not withstanding anything contained in the PPA between
Operation & Dispatch a Generator and Purchaser of electric power and
Agreement (PSODA) energy, each Generator having a bilateral contract shall
have in place, at all times, a Power Station Operation &
Dispatch Agreement (PSODA) with NTDC for the
purposes as follows:
The PSODA shall contain operational, control, dispatch,
outage and maintenance procedures and requirements
of the power station, technical limits, GSDPs, Generation
Performance Charts, and other Generator data
requirements stated in various sub-codes of this Grid
Code.
G&D 236
GRID CODE
The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached).
The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached).
The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached).
239 ~I (09'
j..-
4[
ILl
..§..C
APPROVED
BY
t;
.~9~
~
;: TUt: 'ItTUnOITV 5
GRID CODE
The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached).
The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached).
G&D 241
(Annexure-A)
DEFINITION
Sr. Item Definition Reference
No.
1. Act Means the Regulation of Generation, Transmission and Application and
Distribution Electric Power Act, 1997 (XL of 1997). Modification Procedure
Rules-1999
2. Affiliate In relation to any person, means any person who owns licensing Rules
or controls, or is owned or controlled by, or is under (Distribution) 1999
common ownership or control with, the person, and for licensing Rules
that purpose of this definition. (Generation) 1999
(a) Control Means the right, power or ability to influence or Transmission Licence to
NTDC
determine any decision in respect of the conduct of
affairs of the person under control.
(b) Ownership Means the ownership or the right to own the shares or
voting securities of the persons owned.
3. Agreement and Means the fuel Supply Agreement, the Implementation Generation Licence to
Agreements Agreement, the Power Purchase Agreement and any IPP
or all them"
• Securit y Package
• Project Co-ordination Agreement
4. Ancillary Services Means the services ancillary 0 incident to the safe, Licensing Rules
reliable, stable and efficient availability and utilisation of (Generation) 1999
electrical energy and net capacity and include without Transmission Licence to
limitation, the following, namely:- NTDC
(a) energy imbalance service;
(b) spinning reserve service;
(c) supplemental reserve service;
(d) reactive supply voltage control service; and
(e) regulation and frequency response service.
5. Applicable Documents Means the distribution licence, the second-tier supply Licensing Rules
authorisation, NERPA rules and regulations, the grid (Distribution) 1999
code, the distribution code and any documents issued Licensing Rules
under any of the foregoing or pursuant to the exercise (Generation) 1999
of the Authority's powers under the act, in each case of
a binding nature applicable to the Licensee or where Transmission Licence to
NTDC
applicable, to its affiliates and to which the Licensee or
any of its affiliates may be subject.
r-..- .. - .. - .. - .. - •. - .. - .. - .. - .. - .• - .. - .. - .. - .. - .. - .. - .. - •. -
Means the rules and regulations issued in pursuance of Feel Rules 2002
the Act by the Authority, from time to time, relating to
the generation, distribution and transmission licenses,
the grid and distribution codes and any documents,
instruments, approvals or authorizations issued or
granted by the Authority in exercise of its power under
the Act
6. Applicant Means any person who applies for a distribution Eligibility Criteria for
licensee for provision of electric power service or Consumers of
Distribution Companies
modification thereof.. 2003
7. Application Means an application made by a person in accordance Application and
with the provisions of these regulations and shall, Modification Procedure
Rules-1999
where the context so admits, include the documents-in-
support, and Happlication" shall be construed
accordingly.
8. Auditors Means the licensee's auditors for the
t-~
& AP?ROVED ~'O\
-~.\
d B't' ~I
\;1.,TH£ f.1.JTHORIT't'j!,
Sr. Item Definition Reference
No.
holding office in accordance with the requirements of
the Companies Ordinance, 1984 (XLVII of 1984), or licensing Rules
(Generation) 1999
such other auditors as may be appointed in respect of
the licensee by the Authority from time to time in
accordance with these or the distribution/generation
licence.
9. Authorised/Authorized Means in relation to any maller, authorised in writing by licensing Rules
the Authority. (Distribution) 1999
10. Authorised Etectricity Means any person other than the Licensee, who is Transmission Licence to
Operator authorised by the Authority through a licence or NTDC
otherwise for the purpose of using the Licensee's
transmission system.
11. Authority Means the National Electric Power Regulatory Transmission licence to
Authority constituted under section 3 of the Act. NTDC
12. Authority Proposed Means a modification to a licence proposed by the Application and
Modification Authority. Modification Procedure
Rules-1999
13. Authorized Officer Means the authorized by the Authority to perform NEPRA Service
functions under these Regulations. Regulations 2003
14. Availabte Means a generating unit or tie-line transfer that is both Transmission licence to
(a) available in accordance with the Grid Code and (b) NTDC
declared as available for the generation of electricity.
15. Average Energy For the purpose of Article 23 means energy charges Transmission licence to
Charge calculated on the basis of the average of the month NTDC
uniformly for the 24 hour period of each day of the
month.
16. Balancing Services For the purpose of Article 8 means services to be Transmission licence to
rendered under a ba!ancing arrangement frv.... the NTDC
purpose of bilateral contracts for dispatching plants,
access to additional generation for system needs and
establish a price for each operating time period at
which differences between contractual and real time
positions are settled.
17. Bulk Power Consumer Means in respect of and within the Service Territory, licensing Rules
(BPC) such consumer who receives or purchases, electric (Distribution) 1999
power in the amount, voltage level and frequency equal
to or grater than the characteristics of supply set out in
the distribution licence, provided that, the Authority may
change he characteristics 0 supply for bulk-power
consumers located within the Service Territory at the
time and in the manner set out in the distribution
licence. ._._._. ___ 0_0_'_ ..
Means a-eonS-urn 'who purchases or
er -recelve-s' et"eciiTc
NEPRA Act 1997
power, at one premises, in an amount of one megawatt
or more or in such other amount and voltage level and
with such other characteristics as the Authority may
determine and the Authority may determine different
amounts and voltage levels and with such other
characteristics for different areas.
18. Capacity Charge For the purpose of Article 23 means monthly capacity Transmission licence to
charge for the distribution companies, proportional to NTDC
the maximum demand recorded at each metering
points on the basis of a per kW demand charge
determined by dividing the total capacity transfer
charge by the summation of the peak demand of each
distribution compa'ny recorded at feed points.
19. Common Distribution
System
Means the distribution system as defined in the
~ttH~~
distribution licence other than the dedicated distriputio~ t-~UIlIt:I~0
i
f,.<.J'I Z\~~
(tl APPROVED %
.-J BY I~
\\Ch/ ~\THEAUTHOR'rY IS
Sr. Item Definition Reference
No.
system. Distribution Companies
2003
20. Communication Means any information, comment, representation, TariH Standards and
pleadings, correspondence, or evidence filed with the Procedures Rutes 1998
Registrar, the presiding officer or the Authority in
connection with any proceedinqs.
21. Competent Authority Means the Authority, the appointing authority or any NEPRA Service
officer/senior employee of NEPRA who is designated Regulations 2003
by the Authority to exercise the powers of the
Competent Authority.
22. Competitive Market Means a date on which the first competitive trading Transmission Licence to
Operation Date period of a bilateral contracts market shall commence. NT DC
f--_I~MOD)
23. Concession Territory Means the territory outside Ihe Service Territory of the Distribution licence
licensee defined by the administrative/geographical
boundaries as delineated in Schedule-I to this Licence.
Means the territory outside the Service Territory of the Eligibility Criteria for
Consumers of
distribution licensee defined by the
Distribution Companies
administrative/geographical boundaries as delineated 2003
in a distribution licence.
24. Connecting Point For the purposes of this Consumer Eligibility Criteria Eligibility Criteria for
Consumers of
means the pOint where the dedicated distribution
Distribution Companies
system of the applicant is connected with the existing 2003
common distribution system.
25. Connection Means the provision of electric power supply services. Perlormance standards
(Distribution) Rules 2003
26. Connection Charges Means the charges made or levied or to be made or Licensing Rutes
(Distribution) 1~~~
levied for the carrying out of works and provisions and
installation of electrical plant, electric lines and circuits
and ancillary distribution system together with charges
in respect of maintenance and repair of such items in
so far as not otherwise recoverable as use of system
charges and in respect of disconnection and the
removal of electrical plant, electric lines and circuits,
and ancillary meters following disconnection, or such,
other charges as may be specified in or pursuant to the
distribution licence.
~~ ff: APPRO'lED)~~~.
w
I
pv
•
~
c:
Sr. Item Definition Reference
No.
Manual licensee and approved by the Authority detailing
instructions and guidance to the consumers other than
bulk-power consumers occupying domestic,
agricultural, industrial or commercial premises for
obtaining electric power distribution services, as more
fully described in rule 9.
31. Core Business Means each of the transmission business and tie-line Transmission Licence to
NTOC
business.
32. Cost per Unit of For the purpose of Article 20 means the cost per kilo Transmission Licence to
NTOC
Energy watt-hour (kWh) of electricity as determined and
verified by an independent assessor.
33. Dedicated Distribution Means that part of the distribution system, required to Eligibility Criteria for
Consumers of
System supply power for the sole consumption of an applicant
Distribution Companies
and not for supplying power to any other consumer and 2003
shall comprise of the distribution system from the
connecting point upto the interconnection point of the
applicant including the metering and service wire and
such other connection arranQements.
34. Dispatch Means the issuance of instructions to the licensee by licensing Rules
(Generation) 2000
the national grid company, the relevant national power
control center or any other entity established under the
pooling and settlement arrangement, as may be
decided from time to time in this regard by the
Authority, to schedule and control the operation of the
generation facilities in order to make available or
commence, increase, decrease or cease the delivery of
electric power or the ancillary services, in accordance
with the applicable documents.
35. Distribution Means the ownership, operation, management or NEPRA Act 1997
control of distribution facilities for the movement or
deliver or sale to consumers of electric power but shall
not include he ownership, operation, management and
control of distribution facilities located on private
property and used solely to move or deliver electric
power to the person owning, operating, managing and
controlling those facilities or to tenants thereof.
36. Distribution Business Means the business of distribution of electric power Licensing Rules
(Distribution) 1999
carried on or to be carried on by the licensee pursuant
to and in accordance with the terms of the distribution
licence Qranted to the licensee.
37. Distribution Code Means the distribution code referred to in rule 15. Licensing Rules
(Distribution) 1999
38. Distribution Company Means a person engaged in the distribution of electric NEPRA Act 1997
power.
39. Distribution Facilities Means electrical facilities operating at the distribution NEPRA Act 1997
voltage and used for the movement or delivery of
electric power.
40. Distribution System Means the distribution facilities situated within the Licensing Rules
(Distribution) 1999
Service Territory owned or operated by the licensee for
distribution of electric lines or circuits, electric plant,
meters, interconnections facilities or other facilities
operating at the distribution voltage, and shall also
include any other electric lines, circuits, transformers,
sub-stations, electric plant, interconnection facilities or
other facilities determined by the Authority as forming
part of the distribution system, whether or not operating
at the distribution voltage.
41. Distribution Voltage Means any voltage below the minimum transmisslon N~~~
~
I
~ rr~
f "PP~~VED_ •. \
Sr. Item Definition Reference
No.
voltage.
42. Document-in-Support Means the documents to be provided with the Application and
application for the licence of subsequently, in Modification Procedure
Rules·1999
accordance with regulation 3.
43 Economic· Dispatch Means system of establishing economic precedence of Transmission Licence to
electric power from available generating units or tie-line NTDC
transfers directed by the Licensee or any other entity
established under competitive trading arrangements.
licensing Rules
Means the allocation of demand to individual (Generation) 1999
generation plants or units to effect the most economical
production of electricity for optimum system economy,
security and reliability with due consideration of
incremental generation costs, incremental power
purchase costs, incremental transmission and
distribution losses, load flow considerations and other
operational considerations as determined solely by the
national grid company, the relevant national power
control center or any other entity established under the
pooling and settlement arrangement, as the Authority
may, from time to time in this regard, decide.
44. Electric Power Means electrical energy or the capacity for the NEPRA Act 1997
production of electrical power. .
45. Electric Power Means the generation, transmission or distribution of NEPRA Act 1997
Services electric power and all other services incidental thereto.
46. Emergency Means cases where the patient requires immediate NEPRA Service
medical attention and any delay may be detrimental to Regulalions 2003
his/her health.
4 (. Encumbrance Means any mortgage, charge, right of possession, Transmission licence to
assignment by way of security, right of possession or NTDC
other form of security interest.
48. Energy Imbalance Means the provision of electrical energy for any hourly licensing Rules
Service or half-hourly mismatch between the supply and (Generation) 1999
demand at any given point of delivery.
49. Financial Year Means a consecutive period of twelve calendar months Fee Rules 2002
commencing on the first day of July 0 any year and
1n
ending on the 30 day of June of the following year.
50. Fuel Supply Means the Fuel Supply Agreement dated as Generation licence to
Agreement mentioned, modified, updated, revised or restated IPP
between the Licensee and the Fuel Supplier thereofY)
51. Generation Means the ownership, operation, management or NERPA Act 1997
control of generation facilities for delivery or sale of
electric power and not solely for consumption by the
person owning, operating, managing, and controlling
those facilities.
52. Generation business Means the business of availability and provision of licensing Rules
electric power or ancillary services or other related (Generation) 2000
business through the construction, ownership,
management, control or operation of the generation
facilities or the licensee interconnection facilities carried
out, or to be carried out, by the licensee, whether itself
or through an agent or sub-contractor approved in this
behalf by the Authority, pursuant to and in accordance
with the terms of the generation licence granted to the
licensee and, where applicable, includes the second-
tier supply business carried out by the licensee.
53. Generation company Means a person engaged in the generation of electrjc NEX\Nt:R"d'~
power. / /I(~~ ~'.E..!!..u/"
Sr. Item Definition Reference
No.
54. Generation facility Means the electrical facility used for the production of NEPRA Act 1997
electric power.
55. Glossary of Standards Means as provided in Schedule-I of Performance Perfonnance Standards
Standards (Distribution) Rules 2003 (Distribution) Rules 2003
56. Grid Code Means the grid code prepared by the national grid licensing Rules
company or in the absence of the national grid (Distribution) 1999
company by the transmission licensees pursuant to the
transmission licenses and approved by the Authority,
as from time to time revised with the approval of the
Authority.
Means the grid code prepared by the national grid licensing Rules
company with the approval of the Authoritv. (Generation) 1999
57. Hydro licensee Means a generation licensee constructing, owning, licensing Rutes
operatinQ or manaQinQ hydel generation facilities. (Generation) 1999
58. Implementation Means the Implementation Agreement dated as Generation licence to
amended, modified, updated, revised or restated IPPs
Agreement
between the Licensee and the President of Pakistan.(;')
59. Incremental generation Means the additional cost that would be incurred by licensing Rules
cost producinQ the next available unit of electrical enerQY. (Generation) 1999
60. Information Includes documents, accounts, reports, records, data, Application and
returns or estimates of any description. Modification Procedure
Rules-1999
61. Information direction Means a direction issued by the authority or the Tariff, Standards and
presiding officer to any person to provide information to Procedures 1998
the Authority
62. InterConnection Point Means the point where the metering installation and Eligibility Criteria for
protection apparatus of the consumer is connected to Consumers of
Distribution Companies
the dedicated distribution system. 2003
63. Interconnection Means the equipment, including, without limitation, licensing Rules
Facility/Facilities electrical lines or circuits, transformers, switch-gear, (Distribution) 1999
safety and projective devices, meters or electrical plant,
used for interconnection services.
~ ~~PPROVE~~~~
I~( ~) BY
\~;., THE AUTHORITY;;
Sr. Item Definition Reference
No.
facilities
72. Licensee proposed Means a modification to the licence proposed by the Application and
modifications licensee. Modification Procedure
Rules-1999
73. Licensee's investment Means the licensee's investment programme referred Licensing Rules
programme to in rule 17. (Distnbution) 1999
74. Licensee's power Means the licensee's power acquisition programme Licensing Rules
acquisition referred to in rule 12. (Distribution) 1999
programme
75. Load Shedding Means the process of deliberately removing either Performance Standards
(Distribution) Rules 2003
manually or automatically pre-selected consumer's
load demand from the power system as per scheduled
programme on a rotating and proportionate basis for
each class of consumers notified earlier by the DISCOs
76 Long Duration Power Means loss of electric supply to one or more Performance Standard s
Supply Interruption (Distribution) Rules 2003
consumers for a duration of more than three minutes.
77. Metering Installation Means the metering and associated equipment Eligibility Criteria tor
installed for recording Consumers of
required to be
Distribulion Companies
consumption/usage of electric power of an applicant. 2003
78. Minimum transmission Means sixty-six kilovolts or such other voltage that the NEPRA Act 1997
voltage Authority may determine to be the minimum voltage at
which electrical facilities are operated when used to
deliver electric power in bulk.
79. Motion Means any oral or, if so directed by the Authority, Tariff, Standards and
Procedures 1998
wrHten application in relation to any matter of
procedure undt:r tht::;8 rui!!:;.
80. National grid company Means the person engaged in the transmission of NEPRA Act 1997
electric power and granted a licence under section 17.
81. NEPRA (Fees and Means the rules developed by the Authority in respect Application and
Penalties) rul es Modification Procedure
of the payment of fees by the licensees and the
Rules·1999
procedure for impOSition and payment of fines and
penalties levied by the Authority.
82. NEPRA rules and Means the relevant rules and regulations made by the Licensing Rules
regulations (Distribution) 1999
Authority under the Act.
licensing Rules
(Generation) 1999
83. Net capacity Means the aggregate of the maximum rating of the licensing Rules
(Generation) 1999
generation facilities constructed, owned, managed,
controlled or operated by the licensee under its
generation licence, modified for ambient limitations,
which is established in the manner specified in the grid
code, the generation licence or a power acquisition
contract entered into by the licensee, less the capacity
used to supply the auxiliary needs.
84. NTDe Means National Transmission and Dispatch Company Performance Standards
(Distribution) Rules 2003
85. Operator Means a person authorized by the distribution company Performance Standards
to operate its electrical facilities. (Distribution) Rules 2003
86. Ordinance Means the Companies Ordinance, 1984. Application and
Modification Procedure
Rules-1999
87. Penalty Means a penalty, which may be imposed under these NEPRA Fee and Fine
Regulations. Rules 2002
88. Person Shall include an association of persons, conc rn,
~1~
\\Q,/
company, firm or undertaking
1)~t ~[
~
GY~ ~(.
lLJ
,:1. THE
AP?RO'lEb
BY
J\
.~UTHOR.ITY, .~
.~
l>
Sr. Item Definition Reference
No.
89. Petition Means a petition made to the Authority for the Tariff, Standards and
determination, modification or revision of tariff Procedures 1998
90. Planned Power Supply Means planned or scheduled outage of electrical Perfonnance Standards
supply to one or more consumers. In the event of (Distribution) Rules 2003
Interruption
Planned Power SupplY Interruption, notice shall be
served to all affected consumers at least forty-eight
hours in advance of any such planned outage
excluding defense establishments where Planned
Power Supply Interruptions will only be taken through
mutual aqreement.
91. Pleadings Means the petition, the replies to the petition and Tariff, Standards and
rejoinders to replies. Procedures 1998
92. Point of Outag e Means the point in the distribution system of a Perfonnance Standards
distribution company beyond which electric service is (Distribution) Rules 2003
interrupted including without limitation: Grid station, 11
kV feeders, 400/230 volts line, and transformer.
93. Pooling and settlement Means any arrangements implemented by or under the Licensing Rules
arrangements directions of the Authority for the spot or market based (Distribution) 1999
sales and purchases of electric power through an
electric power exchange or other means .
. _.-.-._.-.-._.-.-.-._._._._._._._._.-.-._.- . . _._.-.-.-._.-.- ..
tJ /;j~APPROVE~~~
(} .....
"r
\~ ~ .-IBY
~ TH2 AUTHORITY S
l'>
Sr. Item Definition Reference
No.
iii) the facility or the system in respect of which the
licence is sought;
iv) the proposed investment; and
v) the social and environmental impact of the
proposed facility or system in a non-technical and
commonly understood language.
101. Prudent utility Means the practices of an operator of an electric power Licensing Rules
practices undertaking seeking in good faith to perform its (Distribution) 1999
obligations and in the conduct of its undertaking
exercising that degree of skill, diligence, prudence and
foresight which would reasonably be expected from a
skilled and experienced operator and complying with
the relevant Laws and codes.
Licence
Transll1is~iUI1 10
NTDC
104. Public sector project Means generation, transmission or distribution facilities NEPRA Acl1997
constructed, owned, managed or controlled by the
Federal Government, a local authority or any body
owned or controlled by any such Government or
Authority.
105. Reactive supply and Means the provision of reactive power through changes licensing Rules
voltage control service to the generator reactive output to maintain (Generation) 1999
transmission line or distribution line voltage.
106. Regulation and Means the provision for moment-to-moment variations Licensing Rules
frequency response in the demand or supply for maintaining scheduled (Generation) 1999
ser'Jice interconnection frequency.
107. Regulations Means regulations made under this Act NEPRA Act 1997
108. Rules Means the National Electric Power Regulatory Transmission Licence to
Authority rules made under section 46 of the Act. NTDC
111. Schedul e Means the Schedule to these rules. Fee Rules 2002
112. Second-tier Supplier Means any licensee authorized to carry out the second- Licensing Rules
(Distribution) 1999
tier supply business.
113. Second-tier supply Means an authorization to engage in the second-tier Licensing Rules
(Distribution) 1999
authorization supply business.
114. Second-tier supply Means the authorised business, if any, of the licensee Licensing Rules
(Distribution) 1999
business or any of its affiliates as a supplier, whether or not
carried out pursuant to a power acquisition contract, of
electric power to one or more bulk-power consumers
_._._._._.-._.-
~it~.!n.9f ~itl1q,~,-,~~ .~~ry!~~ J.e!~iLo.ry. _ . _ . _ . _ . _ . _ . _ . . ..
Means the authorized business, if any, of the licensee
Licensing Rules
or any of its affiliates as a supplier of electric power or (Generation) 1999
ancillary services to a bulk power consumer.
115. Separate business Means each of the transmission business of the Transmission Licence to
NTDC
Licensee, tie-line business of the Licensee, the
provision of settlement services and any other business
of the Licensee, undertaken separately. ._._.-._.-.-._._ ..
Means- each' of the 'disiributTon h-u'slriess,' fh'e- secona: Licensing Rules
tier supply business or any other business taken (Distribulion) 1999
separately from one another and from any other
business of the licensee or any affiliate of the licensee .
. _._._._._._._._._._._._._.-._._._._._._.-.- . . _._._._.-.-._._ ..
Maans each of th~ gtln~ration business, the second- licensing Rules
tier supply business, the provision of ancillary services (Generation) 1999
or any other business taken separately from one
another and from any other business of the licensee or
any affiliate of the licensee.
116. Service territory Means the area specified in the distribution licence Licensing Rules
(Distribution) 1999
within which the licensee is authorised to conduct the
distribution business and, subject to the provisions of
rule 7, the second-tier supply business.
117. Short Duration Power Means loss of electric supply to one or more Performance Standards
consumers for a duralion of three minutes or less (Distribution) Rules 2003
Supply Interruption
excluding momentary interruptions of duration less than
one second.
118. SHYDO Means the Sarhad Hydel Development Organization, NEPRA Act 1997
established under the Sarhad Hydel Development
Orqanization Act, 1993 (NWFP Act No.1 of 1993).
119. Small Power Means owner of a generation facility of below 100 MW Transmission licence to
Producers gross capacity, who was engaged in generation and NTDC
nd
sale of electric power as on 22 April, 2000 and who Distribution Licence
has not signed any power purchase agreement with
WAPDA or KESC or an implementation agreement with
the Government of Pakistan.
120. Spinning reserve Means the provision of additional capacity from licensing Rules
(Generation) 1999
service generating units thai are on-line, loaded to less than
their maximum output, and available to serve system
demand immediately should be contingency occur.
121. Step Potential Means difference of voltage between the steps of an Performance....Standards
operator, human being or animal coming in contract or
operalinq electrical facilities of the distribution
~
I~~~
rn~/
lui
~
~(
~~
AP?ROVED10 ~.
~
J\
W B'f
~_ THe AUTHORITY ;...i!,
Sr. Item Definition Reference
No.
company.
. .
122. Supplemental reserve Means the provIsion of additional capacity from Licensing Rules
service generating units that can be used to respond to a (Generation) 1999
contingency within the period defined in this behalf in
the grid code.
123. System Average Means the average duration of consumer Power Performance Standards
Interruption Duration Supply Interruptions per consumer occurring in a given (Distribution) Rutes 2003
Index (SAlOl) year. SAlOl is the average time the consumers of a
distribution company who remained without power. It is
determined by dividing the aggregated sum of all
consumers power supply interruption durations in
minutes by the total number of consumers served by a
distribution company in a given year.
124. System Average Means the average frequency of consumer Power Performance Standards
Interruption Frequency Supply Interruptions per consumer occurring in a given (Distribution) Rules 2003
Index (SAIFI) year. SAIFI is calculated by dividing the total annual
number of consumer Power Supply Interruptions by the
total number of consumers served by a distribution
company in a given year.
125. Tariff Means the rates, charges, terms and conditions for Tariff, Standards and
Procedures 1998
generation of electric power, transmission, inter-
connection, distribution services and sales of electric
power to consumers by a licensee
126. Technical limits Means the limits and constraints relating to the licensing Rules
operation, maintenance and dispatch of a generation (Generation) 1999
faciiity, as agreed to between an applicant for a licence
and the Authority at the time of grant of the generation
licence or subsequently as determined by the Authority,
or between the licensee and any purchaser, procurer or
recipient of electric power or ancillary services from the
licensee, consistent with the technical functional
specifications set out in the schedule to the generation
licence pursuant to sub-rule (2) of the rule 3, the grid
code and any applicable distribution code and not
inconsistent with the applicable documents.
127. Tie·line Means interconnection facility for the transfer of electric Transmission lice,)ce to
power between the Licensee and other utilities not N70C
governed by the Act.
128 Total system Means the Licensee's transmission system and the Transmission licence to
transmission and distribution systems of all authorised NTOC
electricity operators located in Pakistan.
129. Transmission Means the ownership, operation, management of NEPRA Act 1997
control of transmission facilities.
130. Transmission Means the business of transmission of electric power Transmission licence to
Business carried on or to be carried on by the Licensee pursuant NTOC
to and in accordance with the terms or this Licence in
planning, development, construction and maintenance
of the Licensee's transmission system and operation of
such system for the transmission and dispatch of
electric power including the balancing services and
inter-connection services.
131. Transmission facilities Means electrical transmission facilities including NEPRA Act 1997
electrical circuits, transformers and sUb-stations
operating at or above the minimum transmission
voltage but shall not include: l@\~~~
-
~<.-;
J\
a. electrical circuits forming the immediate conne~tion (<po/
\\Q-/ ~ rr ~
LU
, TW
APPROVED
'.UTHO~1TY. _~~)
BY \I
~.
>
Sr. Item Definition Reference
No.
between generation facilities and the transmission
grid to the extent that those circuits are owned by a
generation company and are directly associated
with that company's generation facilities; and
b. specified facilities operating at or above the
minimum transmission voltage which the Authority,
upon an application by a licensee under section 20
determines, shall be owned and operated by a
distribution licensee.
132. Transmission System Means one or more systems comprising electrical Licensing Rules
(Distribution) 1999
facilities including. without limitation, electrical wires or
circuits. electrical plant. transformers, sub-stations. Licensing Rules
switches, meters, interconnection facilities or other (Generation) 1999
facilities operating at or above minimum transmission
Transmission Licence 10
voltage constructed, owned, managed, controlled or
NTOC
operated by the licensee or by one or more special
purpose transmission licensees and used for
transmission of electric power from the generation
facility to SUb-stations or to or from other generation
facilities or between sub-stations or to or from any
interconnection facilities or from the distribution
facilities of one licensee to the distribution facilities of
another licensee or from a generation facility to a
distribution facilityor a bulk-power consumer.
133. Unit commitment Means turning-on and bringing up to speed anyone or licensing Rules
(Generation) 1999
more of the generation units comprised in the
generation facilities of the licensee and synchronizing
and connecting st;ch units' to the transmission sl"stem
for the deliver of electric power or ancillary services
and, where the context so admits, includes the process
by which the determination as to which units are to be
committed is made.
134. Urban area Means the area falling within the jurisdiction of all urban Performance Standards
(Distribution) Rules 2003
local bodies or development authorities, including
without limitation, town committees, municipal
committees, municipal corporations, metropolitan
corporations and cantonment boards.
135. Use of system Means the use of the distribution system for the Licensing Rules
(Distribution) 1999
transport of electric power by and for and on behalf of
the licensee and, in relation to a second-tier supplier
other than the licensee, for and on behalf of such
second-tier supplier.
Sr.
No.
.
Item . Definition Reference
137. WAPDA Means the Pakistan vVater and Power Development NEPRA Act 1997
Authority established under the Pakistan Water and
Power Development Authority Act, 1958 (W.P .Act XXXI
I of 1958)
138... ~APDA rele~~f1~ ________ t-Ji1e- instructions, manuals or __ guidelines used by Licensing Rules
- ---
(Distnbuticn) 1999
--~
139. Year
. instructions, manuals or guidelines relate.
Means a financial year.
•
Licensing Rules
(Generation) 1999
NEPRA SerJice
ReQulations 2003
140. Year or Annual For the purpose of these Rules means the period of Performance Standards
st
twelve months beginning on 1 July and ending on 30
th (Distribution) Rules 2003
June.
13