0% found this document useful (0 votes)
115 views

Grid Code 2005

The document introduces the Grid Code established by the National Transmission and Dispatch Company (NTDC) of Pakistan. The Grid Code provides guidelines, rules, and procedures for all users connected to NTDC's transmission system to ensure its efficient, reliable and coordinated operation. It consists of several sub-codes covering areas like code management, data registration, operations, connections, planning, protection and metering, scheduling and dispatch. The Grid Code specifies interface requirements between NTDC and other licensees to facilitate the development of an efficient power system while avoiding discrimination. It aims to achieve performance standards and encourage competition in the power sector in Pakistan.

Uploaded by

Faisal Naeem
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
115 views

Grid Code 2005

The document introduces the Grid Code established by the National Transmission and Dispatch Company (NTDC) of Pakistan. The Grid Code provides guidelines, rules, and procedures for all users connected to NTDC's transmission system to ensure its efficient, reliable and coordinated operation. It consists of several sub-codes covering areas like code management, data registration, operations, connections, planning, protection and metering, scheduling and dispatch. The Grid Code specifies interface requirements between NTDC and other licensees to facilitate the development of an efficient power system while avoiding discrimination. It aims to achieve performance standards and encourage competition in the power sector in Pakistan.

Uploaded by

Faisal Naeem
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 249

·,


NATIONAl. TIt·\NSi\lISSION ANI) VESI'ATCII CO~II'AN\' LTD,

THE GRID CODE

June, 2005
GRID CODE

INTRODUCTION

Pursuant to Section 35 of NEPRA Act and Article 16 of ttle NTDC licence. the
National Transmission and Dispatch Company is required to ensure that there is in
force at all times a Grid Code. Consequently NTDC is required to submit a
comprehensive Grid Code for approval of the Authority in accordance with the
requirement of Article 16 of its licence. The Grid Code provides for the smooth and
effective functioning of NTDC and other NEPRA licensees that are or will be
connected to the NTDC's Bulk Transmission System.

The Grid Code is an essential requirement of the regulation of electric network


supply and delivery system. In accordance with 'Regulation of Generation.
Transmission and Distribution of Electric Power Act (XL of 1997)'. all existing and
future Users of the electric network supply and delivery system need a relevant
Licence from NEPRA; and register as Code Participants with NTDC as per the
provisions of Grid Code. One of the NTDC licence's requirements is that Users of
the NTDC's system must comply with the provisions of Grid Code at all times.
Failure to do so may result in their licence being suspended or revoked.

The Grid Code sets out the guidelines. rules and procedures to be adopted by all
Code Users. The sub-codes of trle Grid Code relate to technical and commercial
relationships between NTDC and its Users.

The purpose of Grid Code is to provide unambiguou!; gUloelines. ruies and


procedures. which ensure that all Users of Grid Code understand and abide by the
obligations and responsibilities placed upon them under this Grid Code. The Code
covers day-to-day and long-term principles. standards. procedures and guidelines for
Planning. Operation. Dispatch. and Connection purposes for normal and abnormal
NTDC transmission system conditions.

The Grid Code sets out the operating procedures and principles between the
National Transmission and Dispatch Company; and all authorised Electricity
Operators as defined in NTDC transmission licence collectively referred to as
"Users" in the context of this document.

The Grid Code is structured so as to ensure that the NTDC's transmission system
can be developed. operated. and maintained in an efficient. safe. reliable and co-
ordinated manner from technical and commercial aspects both. The Grid Code is
expected to encourage competition between Generators. Distribution Companies.
and SPCs as the Market Structure develops.

It seeks to avoid any undue discrimination between various Users themselves;


between the entiUes within a part'lcular User Group type; and in day-to-day working
relationship of NTDC with its Users.

Introduction
GRID CODE

Main Objectives of the Grid Code are:

a) To achieve the Performance Standards (Transmission) to be


prescribed under the Act;

b) To facilitate the development, operation, and maintenance of an


efficient, co-ordinated, safe, reliable and economical system for the
transmission of electric power;

c) To facilitate competition in the provision of electric power; and

d) To cover all material technical aspects relating to Connection, the


Operation and Use of the NTDC's transmission system including the
operation of electric lines and electric plants connected to the NTDC's
transmission system in so far as relevant to the Operation and Use of
NTDC's transmission system.

This Grid Code includes the following sub-codes:

a. Code Management

Code Management, which sets out procedures to be adopted by all


parties in the NTDC process of administering, updating, and amending
of the Grid Code.

b. Data Registration Code

Data Registration Code, which sets out a unified listing of all data
required by NTDC from Users; and by Users from NTDC, from time to
time under the Grid Code.

c. Operation Code

The Operation Code, which sets out the principles, standards,


procedures, and guidelines to be followed by NTDC and its Users to
ensure safe and an efficient operation of the NTDC transmission
system, for real-time, and for short-term planning of system operations,
and for normal and abnormal circumstances.

d. Connection Code

A Connection Code, which sets out the principles and procedures to be


applied to new connections to the NTDC bulk transmission system.
New connections may include new or existing Generators; Distribution
Companies, Consumers requiring a direct connection to the NTDC
transmission system known as transm'lssion-connected Consumers;
and Externally-connected Parties, and Externally-connected
Consumers.

Illtroduction 2

\ ,',
GRID CODE

e. Planning Code

The Planning Code, which deals with Principles, Standards,


Processes, and Procedures along with data information exchange
requirements between parties to ensure an efficient, economic, and
timely development of the NTDC bulk transmission system to meet the
forecasted Total System Demand and Margin of Operating Reserve
requirements. It also describes in detail the data needs which the
Users must fulfill in a timely· manner to meet the planning
responsibilities of NTDC in an effective manner.

f. Protection and Metering Code

The Protection and Metering Code, which places the Protection and
Metering requirements upon the Users and NTDC (particularl y with
reference to the Inter-connection Sites) in terms of Principles,
Standards, Design, and Procedures to ensure safe, reliable and
effective functioning of NTDC's bulk transmission system.

g. Scheduling and Dispatch Code

A Scheduling and Dispatch Code, which sets Out Principles,


Processes and Procedures to ensure minimum-cost generation
dispatch, the relationship between NTDC and Generators, including the
dispatch process and requ'lrements for ancillary services and
'provisions for frequency control. It also places an obligation upon
Users to supply certain data information to the NTDC in a timely
manner.

h. Code Definitions

The Code Definitions, which provides an explanation of the terms used


in this Grid Code.

The relationship between the Grid Code and the Distribution Code is shown on
Figure 1 (page 4) of this section.

The Grid Code specifies all the material, technical design, and operational aspects of
the interface requirements between NTDC, Distribution Licensees, SPCs,
Externally-connected Parties and Consumers, and Special Purpose Transmission
licensees (SPTLs).

The Distribution Code shall be consistent in material particulars with the Grid Code;
and it shall ensure strict compliance by the distribution compan'les and other Users
with the provisions of Grid Code including, without limitation, the instructions from
time to time of NTDC and/or the System Operator in respect of the Use and
Operation of their distribution systems.

Introduction 3
c;- ;;0
rn
o ------------------------------------------------------------.--------------------------------------...... r

~l
Q. ;J>
consume~
c ~

C'
n Transmission Connected
o NPCC 0
:J , Distriblltion Companies ~ ! Z
(/)
I

u ! Externally Connected Consumers ~ THE


-0
OJ
o m
I- Externally Connected Parties ~ GRID ~

Z CODE :!
m
m
Generators Connected to NTDC Sy~ z
~
Subject to Scheduling I
Special Purpose Transmission Licensee and Dispatch m
G)
;U
"
10

ution Systems
0
(")
.,C
It)
Subject to Scheduling 0 .....
r------------------,c./ and Dispatch

~
0
INFORMATION ,:' Generators Connected to 132kV m
System of Licensees (DISCOs) }>

en z
0
o Embedded Generators
THE ~
U Distribution ,, DISTRIBUTION I
en load Dispatch
m
o Centre / CODE 0
Small Power Producers (SPPs) Ul
~
;U
Consumers Externally Connected Parties ~Not subject to Scheduling OJ
C
including '-------------- and Dispatch ::j
BPes All other Distribution Licensees
-- -------------- ---- ----- - - -- - -- --------'-----
------------ - ---
------ - - ---
- - ----
==:J
- -- - -- - ------------------------
- ----
0
Z
(")
0
0
m
GRID CODE

CODE MANAGEMENT

CONTENTS

Sr. No. Subject Page No.

CM1 INTRODUCTION & SCOPE CM-6

CM2 UNFORESEEN CIRCUMSTANCES CM-6

CM3 THE GRID CODE REVIEW PANEL CM-6

CM4 COMMUNICATIONS BETWEEN NTDC


AND USERS CM-8

CM5 MISCELLANEOUS CM-8

CM6 OWNERSHIP OF FACILITIES, PLANT


AND/OR APPARATUS CM-9

CM 7 SYSTEM CONTROL CM-9

CM8 FORCE MAJURE CM- 9

CM9 MATTERS TO BE AGREED CM- 9

CM 10 INFORMATION DISSEMINATION CM-9

CM 11 INDEMNITY TO THE NTDC CM-10

CM 12 PRESERVATION OF CONTRACTS PRIOR


TO ENACTMENT OF NEPRA ACT CM -10

CM 13 CODE ADMINISTRATION CM -10

CM 14 NON-COMPLIANCE CM -10
GRID CODE

CODE MANAGEMENT

INTRODUCTION & SCOPE

C~.11.1 The Code Management section contains provIsions of general


application to all provisions of the Grid Code. Their objective is to
ensure that the various sections of the Grid Code work in conjunction
with each other for the benefit of all Users. This Code Management
section applies to all Users including NTDC.

UNFORESEEN CIRCUMSTANCES

C~.12.1 If unforeseen circumstances arise which are not included in the Grid
Code, NTDC shall promptly consult with all affected Users in an effort
to reach an agreement on what should and needs to be done under
such circumstances. If agreement cannot be reached in the available
time, NT DC shall determine the most appropriate course of action.
Whenever NTDC makes a determination, it shall do so having due
regard to the views expressed by the Users and, in any event, to what
is reasonable under the circumstances. Each User shall comply with
such instructions given by NTDC provided those instructions do not
contravene the technical parameters of a particular User's System as
registered in the Grid Code. NTDC shall promptly refer all such
unforeseen circumstances and any determination to the Review Panel
for consideration as per CM 3.1 of this sub-code.

THE GRID CODE REVIEW PANEL

cr.ll1 NTDC shall establish and maintain the Review Panel, which shall be a
standing body and shall undertake the functions detailed·iIl CM-3.3.

cr.112 The Panel shall consist of;

(a) a Chairman and up to 3 Members apPointed by NTDC;

(b) a person appointed by the Authority;

(c) the following Members;

(i) 2 Persons representing Generators with a total registered


capacity in excess of 1000MW;

(ii)
GRID CODE

(iii) 4 Persons representing Generators with a total registered


capacity of less than 500MW;

(iv) one representative from each Distribution Company


Licensed with NEPRA;

(v) a Person representing Transmission-connected


Consumers;

(vi) a Person representing Small Power Producers (SPP);

(vii) a Person representing Externally-connected Consumers;

(viii) one representative from Externally-connected Parties;


and

(ix) one Member from the Industry or an Academic Institution


or PEC.

The representation within each category shall be based on rotation and


mutual agreement.

CM 3.3 The Panel shall:

(a) keep the Grid Code and its workings under review;

(b) review all suggestions for amendments to the Grid Code which
the Authority or any User may wish to submit to NTDC for
consideration by the Panel;

(c) publish recommendations as to amendments to the Grid Code


that NTDC or the Panel believes are desirable and the reasons
for such recommendations;

(d) submit all the agreed recommendations to NEPRA for approval;

(e) issue guidance on the Grid Code and its implementation.


performance and interpretation. when asked to do so by any
User;

(f) resolve any matters of dispute between NTDC and its


Users/Code Participants;

(g) study and evaluate the suggestions received from different parts
of the power market participant; and

(h)
GRID CODE

0.1 34 The Panel shall establish and comply with at all times with its own rules
and procedures relating to the "Conduct of its Business", which shall be
approved by the Authority.

0.115 NTDC shall consult in writing all Users which are liable to be affected
by any proposed amendments to the Grid Code and shall submit all
such proposed amendments to the Grid Code to the Panel for
discussion prior to such consultation.

0.14 COMMUNICATIONS BETWEEN NTDC AND USERS

C~1141 All operational instructions issued by NTDC between NTDC and Users
shall be between the NTDC Control Engineer based at the NPCC, as
advised to Users before connection to the Transmission System, and
the Users Responsible Engineer based at a Regional Control Centre
notified to NTDC before connection to the Transmission System.

CM 4 2 Unless otherwise specified in the Grid Code, all operational


communications detailed in CM 4.1 shall be through Control Telephony
(dedicated telephone' network).

0,143 All non-operational communications (data information and notices)


between tHDC and Users shall be inwriting and issued to the
appropriate Officers of NTDC, the System Operator, and each User.

C~.14 4 If for any reason NTDC or a User re-Iocates its Control Centre, NTDC
or the User must inform the other Party in writing of the move and
advise the other party of any changes to their Control Telephony.

CM 45 All instructions and communications given by Control Telephony are to


be recorded by whatever means available, and shall be acceptable by
NT DC and Users as evidence of those instructions or communications.

C~.15 MISCELLANEOUS

C~.l 51 Data and Notices

0.15.1.1 References in the Grid Code to 'in writing' shall include typewriting,
printing, lithography and other modes of reproducing words in a legible
and non-transitory form such as electronic communications.

0.151.2 Where applicable all data items shall refer to Voltage and
Frequency.

CLl 8

\ \" ,
GRID CODE

CM 6 OWNERSHIP OF FACILITIES, PLANT ANDIOR APPARATUS

The Facilities, Plant and Apparatus of a User shall include Facilities,


Plant and Apparatus used by a User under an agreement with a third
party.

CM 7 SYSTEM CONTROL

Where a User's System (or part thereof) is, by agreement under the
control of the System Operator, for the purposes of operation in Real
Time, the User's System shall be treated as a part of the NTDC
Transmission System.

C~,18 FORCE MAJURE

The Force Majeure has been defined in the Section on "Definitions".


Code Participants (as defined in the Section on "Definitions") should
note that certain provisions of the Grid Code may be suspended in
whole or in part pursuant to any directive given by the Authority under
Force Majure. NTDC shall inform NEPRA within Seven days of the
initi3tion of Force MLljure to be claimed by ~HDC fOi the suspension of
some or all proVisions of the Grid Code.

Ctv19 MATTERS TO BE AGREED

Unresolved matters between NTDC and Users after a Review Panel


shall be referred to NEPRA for resolution whose decision shall be final
and binding on all parties. The Review Panel shall need to refer to the
Authority any matters requiring interpretation of the Grid Code
provisions.

0,110 INFORMATION DISSEMINATION

The System Operator (SO) shall establish, operate and maintain a


Web Site, providing necessary information about the transmission
system status, pricing, congestion, operating procedures, technical and
operational Committee meetings, and other relevant information and
data.

CM 11 INDEMNITY TO THE NTDC

Each Code Participant shall keep NTDC and the System Operator
indemnified at all times against any claim, action, damage, loss,
liability, expenses or outstanding liability which NTDC or the System

9
GRID CODE

Operator pays, suffers, incurs or is liable for in respect of any breach


by such person or any of its officer, agent or employee.

C~.112 PRESERVATION OF CONTRACTS PRIOR TO ENACTMENT OF


NEPRA ACT

During the implementation of agreements executed by the Participants


of this Code, prior to the enactment of NEPRA Act and carrying a
sovereign guarantee for their performance, nothing contained in this
Code shall be applicable to such Participants which is inconsistent with
the terms and conditions of their agreements or impairs the rights of
these participants thereunder.

CODE ADMINISTRATION

The NTDC shall be responsible for the enforcement and administration


of the Grid Code.

CM 14 NON-COMPLIANCE

Non-compliance of any of the prov'lsions of this Gr'ld Code by any of the


Code participants sh~1I be treated as a violation of the Grid Code and
shall be subject to penalties as per NEPRA Fees & Fines Rules
(2002)- The First Schedule (Part-I, Sr. No.5). Non-compliance by
NTDC of the Grid Code provisions applicable to NTDC shall be treated
as a violation of NTDC licence, and shall be subject to penalties as per
NEPRA Fees & Fines Rules (2002).

C~.l 10
GRID CODE

DATA REGISTRATION CODE

CONTENTS

Sr. No. Subject Page No.

ORe 1 INTRODUCTION, OBJECTIVE & SCOPE DRC-12

ORe 2 DATA CATEGORIES AND STAGES


IN REGISTRATION DRC-13

ORe 3 PROCEDURES AND RESPONSIBILITIES DRC-14

ORe 4 DATA TO BE REGISTERED DRC-15


GRID CODE

DATA REGISTRATION CODE

DRC1 INTRODUCTION, OBJECTIVE & SCOPE

DRC 1.1 The Data Registration Code (DRC) presents a unified listing of all data
required by NTDC from Users and by Users from NT DC, from time to
time under the Grid Code. The data which is specified in each section
of the Grid Code is listed and collated here in the DRC. Where there is
any inconsistency in the data requirements under any particular sub-
code of the Grid Code, the provisions of the Data Registration Code for
that particular sub-code of the Grid Code shall prevail.

DRC1.2 The Scope of this Code applies to Users who in this DRC means:

(a) Generators

(b) Distribution Companies

(c) Transmission Connected Consumers

(d) Any other person with a User System directly or indirectly


connected to the NTDC Transmission System to which Power
Plants and / or Consumers are connected.

(e) Externally-connected Parties

(f) Externally-connected Consumers

(9) Special Purpose Transmission Licence (SPTL)

DRC 1.3 The DRC identifies the sub-code of the Grid Code under which each
Hem of data is required.

DRC1A The sub-code under which any item of data is required specifies
procedures and timings for the supply of such data, for routine
updating, and for recording temporary or permanent changes to that
data. All timetables for the provision of data are repeated in the DRC.

DRC 1.5 Various sub-codes of the Grid Code also specify information which the
Users shall receive from NTDC. This information is summarised in a
single Schedule in the DRC (Schedule 1-9).

DRC 1.6 The objective of the DRC is to list and collate all the data to be
provided by each category of User to NTDC under the Grid Code, and
to list all the data to be provided by NTDC to each category of User
under the Grid Code. I
~ ~()'~1E.~ R_tCu.
~ ~
~
v
DRC 12
GRID CODE

ORe 2 DATA CATEGORIES AND STAGES IN REGISTRATION

ORC 2.1 Within the DRC each data item is allocated to one of the following four
categories (DRC 2.2 & DRC 2.3, DRC 2.4, DRC 2.5, DRC 2.6).

(a) Standard Planning Data (PC)

(b) Detailed Planning Data (PC)

(c) Operational Data (OC)

(d) Scheduling and Dispatch Code Data (SOC)

(e) Connection Code Data (CC)

ORC2.2 STANDARD PLANNING DATA (SPD) - PC DATA

ORC 2.2.1 The Standard Planning Data listed and collated in this DRC is that data
listed in Part 1 of the Appendix A to the Planning Code.

ORC 2.2.2 Standard Planning Data shall be provided to NT DC in accordance with


PC 5 and PC A1 - PC A4 of Appendix A of the Planning Code.

ORC2.3 DETAILED PLANNING DATA (DPD) - PC DATA

ORC 2.3.1 The Detailed Planning Data listed and collated in this ORC is that data
listed in Part 2 of the Appendix A to the Planning Code.

ORC 2.3.2 Detailed Planning Data shall be provided to NTOC in accordance with
PC 5 and PC A5 of Appendix A of Planning Code.

ORC2.4 OPERATIONAL DATA - OC DATA

ORC 2.4.1 Operational Data is data, which is required by the Operation Codes
and the Schedule and Despatch Codes. Within the DRC, Operational
Data is sub-categorised according to the Code under which it is
required namely, OC3, OC4, OC5, OC6, OC?, OCg, and OC12.

ORC 2.4.2 Operational Data is to be supplied in accordance with timetables set


down in the relevant Operational Codes.

ORC 2.5 SCHEDULING AND DISPATCH CODE DATA (SOC DATA)

DRe 13
GRID CODE

oRC26 CONNECTION CODE DATA (CC DATA}

This data is to be supplied in accordance with Schedules and


Appendices attached with the Connection code of the Grid Code.

oRC3 PROCEDURES AND RESPONSIBILITIES

oRC3.1 Responsibility for Submission and Updating of Data

In accordance with the provisions of the various sub-codes of the Grid


Code, each User must submit data as summarised in ORC 4 and listed
and collated in the schedules attached with each sub-code.

oRC 3.2 METHODS OF SUBMITTING DATA

oRC 3.2.1 Wherever possible the data Schedules to the ORC are structured to
serve as standard formats for the data submission and such format
must be used for the written submission of data to NTOC.

oRC 3.2.2 Data must be submitted to the NTOC, National Power Control Centre
(NPCC) or to such other department or address as NTOC may advise
from time to time. The name of the person on the behalf of the User
who is submitting each schedule of data must be included.

ORe 3.2.3 Where a computer data link exists between a User and NTOC, data
may be submitted via this link. NTOC shall, in this situation, provide
computer files for completion by the User containing all the data in the
corresponding ORC Schedule.

oRC 3.24 Other modes of data transfer, through CO and other electronic means
of data transfer such as magnetic tape, may be utilised if NTOC gives
its prior written consent.

oRC 3.3 CHANGES TO USER'S DATA

oRC 3.3.1 Whenever a User becomes aware of a change to an item of data which
is registered with NTOC, the User must notify NTOC in accordance
with each sub-code of the Grid Code. The method and timing of the
notification to NTOC is set out in each sub-code of the Grid Code.

ORe 34 DATA NOT SUPPLIED

ORC34.1

oRC
GRID CODE

that data ought to have been supplied, shall estimate (typical values) of
such data if and when, in that User's view, it is necessary to do so.
Such estimates shall, in each case, be based upon data supplied
previously for the same plant and apparatus or upon such other
information as NTOC or that User, as the case may be, deems
appropriate.

DRC 3.4.2 NTDC shall advise a User in writing of any estimated data it intends to
use pursuant to DRC 3.4.1 relating directly to that User's facility, plant,
and apparatus in the event of data not being supplied.

DRC 3.4.3 A User shall advise NTDC in writing of any estimated data it intends to
use pursuant to ORC 3.4.1 in the event of data not being supplied.

DRC 3.4.4 In the event the required data is consistently not supplied or is
incomplete or in-accurate by the User, the NTDC shall refer the matter
to the "Review Panel", which shall issue necessary instructions to the
defaulted party in writing.

Failure to obtain the required data within the specified timeframes from
the defaulted party, the NTDC shall consider the matter as a violation
of the Grid Code provisions. Suitable measures regarding Grid Code
non-compliance are covered in CM 14 of this Grid Code.

DRC 4 DATA TO BE REGISTERED

DRC 4.1 Schedules 1 to 9 attached cover the following data areas.

DRC4.1.1 SCHEDULE 1 - GENERATING UNIT TECHNICAL DATA. (Directly or


Indirectly Connected to NTDC System, Centrally Dispatched such as
connected to the NTDC system or 132 kV Transmission System of
distribution companies and subject to central dispatCh).

Comprising Generating Unit fixed electrical parameters (as covered in


respective appendices of the following sub-codes [(OC 4 Appendix 4,
Appendix 5, OC 5 Appendix 1, OC 6 Appendix 1, OC 7 Appendix 1);
(PC, Part 1 and 2 of Appendix A); and (Appendix 1 of CC 8.3, and
CC 8.5)].

DRC 4.1.2 SCHEDULE 2 - GENERATION PLANNING PARAMETERS AND


GENERATION OFFER DATA. (Directly or Indirectly Connected to
NTDC System, Centrally Dispatched such as connected to the NTDC
system or 132 kV Transmission System of distribution companies and
subject to central dispatCh).

i
Comprising the Generating Plant parameters required for Operational
Planning studies and certain data required under Scheduling and
Dispatch Code (as covered in Appendix 5 of OC 4).

ORe 15
GRID CODE

DRC4.1.3 SCHEDULE 3 - GENERATING PLANT OUTAGE PROGRAMMES.


OUTPUT USABLE AND INLFEXIBILITY INFORMATION (OC 4 -
Appendix 1. 2). (Directly or Indirectly Connected to NTDC System.
Centrally Dispatched such as connected to the NTDC system or 132
kV Transmission System of distribution companies and subject to
central dispatch).

Comprising Generation Outage Planning of the Generating Units


subject to central dispatch. Output Usable and inflexibility information
at timescales down to the daily Availability Declaration. Also contract
information need to be provided where External Interconnections are
involved.

DRC U.4 SCHEDULE 4 - INDEPENDENT GENERATING PLANT OUTPUT


FORECASTS (Indirectly Connected to NTDC system. not subject to
Central Dispatch such as embedded generation and SPPs).

Output predictions for Power Stations not subject to Central Despatch


(as covered in Appendix 1 and 2 of OC 4).

DRC41.5 SCHEDULE 5 - USER'S SYSTEM DATA (Directly connected to NTDC


System Transmission-connected Consumers. Distribution Licensees.
and other Externally-connected Consumers).

Comprising electrical parameters relating to facilities connected to the


NTDC Transmission System (as covered in Part 1 of Appendix A of
Planning Code).

DRC 41.6 SCHEDULE 6 - USERS OUTAGE INFORMATION

Comprising the information required by NTDC for outages on the Users


System (Directly or Indirectly Connected 10 NTDC System). including
outages at Power Plants (Indirectly Connected to NTDC System and
not subject to Central Dispatch).

ORe 4.1.7 SCHEDULE 7 - LOAD CHARACTERISTICS (Directly or Indirectly


Connected to NTDC System).

Comprising the estimated parameters of load groups in respect of. for


example. harmonic content and response to frequency (as covered
PC.A4.8 of Appendix A of Planning Code).

DRC 4.1.8 SCHEDULE 8 - CONNECTION POINT DEMAND AND ACTIVE


ENERGY DATA OF USERS DIRECTLY OR INDIRECTLY
CONNECTED TO NTDC SYSTEM AND GENERATION SUMMARY
(as covered in PC AA - Part 1, of the Appendix A of Planning Code).

Comprising information relating to Demand and Active Energy taken


from the NTDC Transmission System and a summary of the
Independent and Consumer Generating Plant connected to the

{
ORe 16

,
GRID CODE

Connection Point. (Indirectly Connected to NTDC System, and not


subject to Central Dispatch).

DRC4.1.9 SCHEDULE 9 - DATA SUPPLIED BY NTDC TO USERS (as covered


in PC A.4.3, PC A.4.6 of Part 1 of Appendix 1 of the Planning Code;
Appendix 3 and 3A, of OC 4, OC S.A.8 of OC 5, Appendix 1 of OC6,
Appendix 1 of OC7, Appendix 1-3 of OC9; and CC 6.1, CC 6.2, CC 8.7,
CC 8.8, CC 8.10.1, CC 8.12.4, CC 8.13.2, CC 8.17 of Appendix 1 of
Connection Code).
DRC 4.2 The Schedules applicable to each class of User are as follows:

SR. DESCRIPTION SUBJECT TO SCHEDULE


NO. DISPATCH
lDirectly Connected)
i. Generating Plants directly SO 1,2,3,9
connected to NTDC system and
subject to Central Dispatch.
ii. Generating Plants connected to SO 1,2,3,9
132/66kV system of Distribution
Companies subject to Central
Dispatch.
(Indirectly Connected)
i. Generators indirectly connected, NSO 1,2,4,6,9
and not subject to Central
Dispatch.
Users (Directly Connected)
i. Distribution Companies - 5,6,7,8,9
ii. Consumers directly connected to - 5,6,7,8,9
NTOC system.
iii. Externally-Connected Parties - 4,5,6,8,9
Users (Indirectly Connected)
i. BPCs connected to DISCOs - 6,7,8,9
distribution system and indirectly
connected to NTDC system.
ii. ExternallJ'-connected Consumers - 6,7,8,9

Notes:

1. Distribution Companies and Users with a User System directly


connected to the NTDC Transmission System must provide data
relating to Small Power Producers PlanUEmbedded Generators
and/or Customer Generating Plant within their Systems when
such data is requested by NTDC pursuant to PC A 3 or PC A 5.

2. The data in Schedules 1 and 3 need not be supplied in relation


to Small Power Producers (SPPs) connected to the System of a
User at a voltage level below the voltage level directly
connected to the NT DC Transmission System except in
connection with a Master Connection and Use of System
Agreement or unless specifically requested by NTOC.

ORC 17

,"\()
.
GRID CODE

ORC4.3 Confidentiality Obligations

Each Code Participant must use all reasonable endeavours to keep


any information confidential which comes into the possession or control
of that Code Participant or of which the Code Participant becomes
aware of. A Code Participant:

a) must not disclose confidential information to any person except


as permitted by the Grid Code;

b) must only use or reproduce confidential information for the


purpose for which it was disclosed or another purpose
contemplated by the Grid Code;

c) must not permit unauthorized persons to have access to


confidential information.

Each Code Participant must use all reasonable endeavours:

a) to prevent unauthorized access to confidential information which


is in the possession or control of that Code Participant; and

b) to ensure that any person to whom it discloses confid ential


information observes the provisions of Grid Code.

The Officers of the NTDC, distribution companies, and other


Authorised Electricity Operators and all other Users participating in
Transmission Service Pricing must not be involved in or associated in
any manner with Competitive Power Trading activities of any other
Code Participant.

Hj Hj Hj Hj End of ORC~i Iii ~i ~i

ORC 18
GRID CODE

OPERATION CODE No.1

OPERATING OBJECTIVES AND PRINCIPLES

CONTENTS

Sr. No. Subject Page No.

OC 1.1 INTRODUCTION OC1-20

OC 1.2 OPERATING PRINCIPLES OC1-20


GRID CODE

OPERATION CODE NO.1

OPERATING OBJECTIVES AND PRINCIPLES

OC 1.1 INTRODUCTION

The Operating Code specifies the Technical and Operating Criteria,


and Procedures to be followed by NTDC and the System Operator and
Code Participants in the operation of the power system. NTDC in the
capacity of the System Operator' shall be responsible for the safe,
secu re, openl y-accessible, cost-effective, eq uitable, environmen ta II y
acceptable, reliable and adequate operation and development of the
power system. The Code Participants shall have the obligation to
cooperate with the NTDC and the System Operator and follow the
technical, design, and operation Criteria and Procedures as identified
in this Grid Code necessary for an appropriate and stable operation
and protection of the power system.

The functions and responsibilities of NTDC as a System Operator are


subject to the conditions as specified in the NTDC licence, and
includes Operation, Control and Discipline of the NTDC bulk
transmission system (as defined below):

(a) Means one or more systems comprising electrical facilities


including, without limitation, electrical wires or circuits, electrical
plant, transformers, sub-stations, switches, meters,
interconnection facilities or other facilities operating at or above
minimum transmission voltage constructed, owned, managed,
controlled or operated by the Licensee or by one or more special
purpose transmission licensees and used for transmission of
electric power from the generation facility to sub-stations or to or
from other generation facilities or between sub-stations or to or
from any interconnection facilities or from the distribution
facilities of one licensee to the distribution facilities of another
licensee or from a generation facility to a distribution facility or a
bulk-power consumer. The Operating Code describes the
procedures by which the System Operator shall carry out its
responsibilities along with its performance obligations.

OC12 OPERATING PRINCIPLES

The System Operator shall prepare an Operating Plan prior to bringing


scheduled generation on-line for the next day to meet the forecasted
load demand. Procedures for implementation of the Plan are
described in the Scheduling and Dispatch Code.

, n." lel11 S,sternOperator refers to the system control functions being periormed by the National Power Conlrel Ce
plec~·:essor WAPOA system as defined in the NTOC IicenCtl '? ~ _--,
SJ

OC-l 20
GRID CODE

The Operating Plan shall include the following Operating Principles:

(a) Adequate margins for operating reserve, voltage regulation and


frequency control must be ensured at all times under normal
system conditions.
(b) Generation and Transmission facility outage co-ordination and
assessment of system security impacts should be carried out
prior to real-time operations.

(c) Frequency control and regulation requirements must be


provided by all the generators, selected distribution feeders, and
all BPCs connected to the NTDC system.

(d) Transmission congestion management and contingency event


management must be prOVided in accordance with the
Operating Criteria and Principles laid down in the Operating
Sub-Code (OC-4) of this sub-code.

(e) Appropriate and fair spinning reserve allocation must be made


among all the on-line generators.

(f) Adequate reactive reserve management and voltage regulation


must be carried to meet the Operating Standards stated in OC
4.9.1 of this Code.

(g) Procurement of adequate ft,nci!lary Serlices must be ensured


prior to real-time operations.

(h) Scheduling of generation utilizing economic dispatch principles,


and re-dispatch for transmission considerations must be carried
by the System Operator during generation scheduling process.

(i) Provision of adequate generation protection and control based


on the principles laid down in Protection & Metering Code (PMC)
must be provided by NTDC.

U) Functioning of dual communication systems during system


operation and dispatch must be ensured by the System
Operator/Grid Code Participants.

(k) Provision of pre-operational plans regarding black start facilities


and pre-tested system restoration plan under black out
conditions must be ensured by the System Operator.

(I) Minimization of energy imbalances at all times must be ensured


by the System Operator.

(m) The System Operator must ensure that all the thermal loadings,
voltages, system stability (both steady-state and dynamic) are
well within established limits as provided in the Operating
Code 4 of this sub-code.

OC-1 21
GRID CODE

OPERATION CODE No.2

DEMAN D FORECASTS

OC 2.1 INTRODUCTION, OBJECTIVE & SCOPE

OC 2.1.1 This sub-code is concerning Demand Forecasting as related to


Operational Timescales with the specific objective of ensuring that the
highest levels of security of power supply are maintained for
Consumers at all times. The scope of this sub-code applies to all
Users connected to the Transmission System, i.e. Generators,
Distribution Companies and Consumers directly connected to the
Transmission System of NTDC, and other Parties consuming power
from the NTDC system.

OC 21.2 This sub-code covers Active Demand and Reactive Demand forecasts
which are necessary to match generation output with system energy
requirements.

OC 21.3 In advance of real time operations, demand forecasting shall be


consolidated/developed by NTDC on the basis of demand forecasts
provided by individual Users.

OC 21.4 For real-time operations, NTDC shall conduct its own demand
forecasting taking into account information supplied by all the Users,
and any other external factors that it may deem necessary.

OC 21.5 In this OC 2, the Points of Connection of Users, Generators,


Consumers and External-connection shall be considered as a
Transmission Connection Points.

OC 21.6 In this OC 2, Year 0 means the current NTDC Calendar Year at any
time, Year 1 means the next NTDC Calendar Year at any time, Year 2
means the NTDC Calendar Year after Year 1 and so on.

OC 21.7 References in OC 2 to data being supplied on an hourly basis refers to


it being supplied for each period of 60 minutes ending on the hour.

OC 2.1.8 The term 'Operations' means operations in real time.

OC 2.2 DATA REQUIRED BY NTDC IN THE PRE·OPERATIONAL STAGE

OC 22.1 The data is to be supplied to NTDC by:-

Each User directly connected to the NTDC Transmission System in


relation to Demand Forecast. This data shall be supplied in writing to
~HDC by calendar week 40.

OC-2 23
i
I
GRID CODE

DC 2.3 DATA REQUIRED BY NTDC FOR THE OPERATIONAL STAGE

OC 2.3.1 For a period of 4 weeks ahead of the real-time day, the following shall
be supplied to NTDC in writing by 10.00 a.m. each Monday. The
4-week period is a rolling period.

Demand Management

Each distribution company and other Code Participants (as instructed


by NTDC) shall supply MW profiles, in relation to their peak demand, of
the amount and duration of their proposed use of demand management
which may result in a demand change of 5MW or more on any
Transmission Connection Point (averaged over an hour which may be
changed later by the Authority to !;2 hourly basis).

OC 2.3.2 For the period of up to eight (8) days ahead of the real-time day, the
following shall be supplied to the System Operator in writing by
10:00 a.m. each Wednesday

Demand Management

Each distribution company and other Code Participants (as instructed


by the System Opeiatoi) shall supply M'vV profile::;, in proportion to their
peak demand, of the amount and duration of their proposed use of
demand management which may result in a demand change of 5MW or
more (averaged over an hour which may be changed by the Authority
to ii hourly basis) on any Transmission Connection Point. The quantum
of load to be shed by each Distribution Company shall be at the
discretion of NTDC. However, the System Operator shall carryout Load
Management in fair manner.

OC 23.3 Each Generator shall, if required by NTDC, supply the System Operator
with MW schedules for the operation of power plants on an hourly basis
in writing by 10.00 a.m. each day (or such other time specified by
NTDC from time to time) for the next day.

OC 2.3.4 Under OC 3, each distribution company and other Code Participants as


specified by the System Operator shall not'lfy the System Operator of
any demand management proposed by itself which may result in a
demand change of 5MW or more averaged over an hour on any
Transmission Connection Point which is planned after 10.00 a.m. on an
operational day, and of any changes to the planned demand
management notified to the System Operator prior to 10.00 a.m. as
soon as possible after the formulation of the new plans.

OC-2 24

'. 7
W
GRID CODE

OPERATION CODE No, 3

DEMAND MANAGEMENT

CONTENTS

Sr. ~Jo Subject Page No.

OC 3.1 INTRODUCTION, OBJECTIVE & SCOPE OC3-27

OC 3.2 CODE CLARIFICATION OC3-27

OC 3.3 PROCEDURE FOR THE NOTIFICATION OF


DEMAND MANAGEMENT INITIATED BY DISCOS
(OTHER THAN FOLLOWING THE INSTRUCTION
OF NTDC) OC3-28

OC 3.4 PROCEDURE FOR THE IMPLEMENTATION OF


DEMAND MANAGEMENT ON THE INSTRUCTIONS
OF NTDC OC3-28

OC 35 AUTOMATIC LOW FREQUENCY DEMAND


DISCONNECTION OC3-29

OC 3.6 EMERGENCY MANUAL DISCONNECTION OC3-29

OC 37 OPERATION OF THE BALANCING MECHANISM


DURING DEMAND MANAGEMENT OC3-30

OC 3 APPENDIX 1
Emergency Manual Demand Reduction/Disconnection
Summary Sheet OC3-31

,
'\()
'. I
GRID CODE

OPERATION CODE NO.3

DEMAND MANAGEMENT

OC 3.1 INTRODUCTION, OBJECTIVE & SCOPE

OC 3.1.1 Operation Code No.3 (OC3) deals with the provisions to be made for
the Users including Consumers directly connected to the NTDC
Transmission System to facilitate reduction in Demand as per the
instructions of NTDC for any reason.

OC 3.1.2 Similarly, the provisions given here apply to Unforeseen Events as well.

OC3.1.3 The objective of OC3 is to provide facilities and procedures which shall
enable NTDC to achieve a reduction in demand that will relieve
planned and unforeseen operating conditions on the NTDC
transmission system.

OC 3.1.4 OC3 applies to NTDC and to Users:

(a) Distribution Companies;

(b) NTDC in relation to Consumers directly connecterl to the NTDC


Transmission System; and

(c) Externally-connected Consumers

OC 3.2 CODE CLARIFICATION

OC 3.2.1 Demand Management may be achieved by any of the following:

(a) Under-frequency load disconnection.

(b) Consumer Response to direct appeals to limit Demand.

(c) TIle System Operator Instructions in an Emergency.

OC 3.2.2 In all situations considered in OC3, demand management is


exercisable:

(a) by reference to distribution companies system directly


connected to the NTDC Transmission System; and

(b) by NTDC in relation to Consumers directly connected to the


NTDC Transmission System

OC-3 27
i
GRID CODE

OC 32.3 Demand management in all situations relates to the physical


organisation of the Total System Demand, and not to any contractual
arrangements.

OC 32.4 The application of demand management by a distribution company may


affect other Consumers of the distribution company within its
geographical boundary.

OC 32.5 Demand management shall be implemented by distribution companies


where the Consumers are within the distribution company's system
which are directly connected to the NTDC Transmission System; and
by NTDC where Consumers are directly connected to the NTDC
transmission System.

OC 33 PROCEDURE FOR THE NOTIFICATION OF DEMAND


MANAGEMENT INITIATED BY DISTRIBUTION COMPANIES
(OTHER THAN FOLLOWING THE INSTRUCTIONS OF NTDC)

OC 33.1 By 10.00 a.m. of each day, distribution companies and other Code
Participants, as specified by the System Operator, shall provide the
System Operator with a summary of any demand reductions of 5MW or
greater during the last 24 hours, and of any planned demand
reductions within the next 24 hours.

OC33.2 Any changes from the planned demand management shall be


communicated to the System Operator as soon as possible.

OC 3.34 In the above the summary of planned or historic demand reductions,


the information supplied to the System Operator shall include the
magnitude, time, location, date and details of the demand management
methods employed.

OC 34 PROCEDURE FOR THE IMPLEMENTATION OF DEMAND


MANAGEMENT ON THE INSTRUCTIONS OF NTDC

OC 34.1 The System Operator shall provide as much warning as possible of any
unforeseen circumstances which are likely to result in demand
management procedures being implemented. This shall ensure that all
the distribution companies and all other relevant Code Participants
shall be in a state of readiness to implement their planned demand
management procedures.

OC 34.2 All the relevant Code Participants participating in the demand


management are required to be able to respond at a short notice to the
System Operator instructions to implement demand management.

OC344

OC-3 28

iI
GRID CODE

Demand at the time of implementation of the demand reduction. The


System Operator shall, to the extent possible, formulate consistent and
fair policy of demand management among DISCOs and other Users.

OC 3.4.4 Distribution companies have an obligation to provide full details of their


demand reduction plans to the System Operator on an annual basis
ahead of time.

OC 3.4.5 Following the implementation of demand management, distribution


companies and any Consumers directly connected to the NTDC
Transmission System may only restore their systems to normal
operation upon the instructions of the System Operator.

OC 3.4.6 After restoration to normal operating conditions, distribution companies


are obliged to supply information to the System Operator, which shall
include the magnitude, date and time, location and details of the
demand management methods employed.

OC 3.5 AUTOMATIC LOW FREQUENCY DEMAND DISCONNECTION

OC 3.5.1 All Transmission Connection Points shall be provided with low


frequency disconnection facilities. This is necessary to ensure that in
the event of a large generating unit failure, there is a staged and
phased demand disconnection to enSUie system stability for connected
consumers.

OC 3.5.2 Any low frequency disconnection scheme must take into account of all
embedded generation on the low voltage systems of the distribution
companies.

OC 3.5.3 When there is a low frequency disconnection, distribution companies


and other Code Participants, as specified by the System Operator, are
obliged to follow the System Operator instructions when restoring
power supplies.

OC 3.6 EMERGENCY MANUAL DISCONNECTION

OC 3.6.1 Each distribution company shall provide the System Operator in writing
by week 40 in each calendar year, in respect of the next following year
beginning week 40, on each Transmission Connection Point basis the
information contained in the Appendix 1 of this sub-code.

OC 3.6.2

OC-3
GRID CODE

out demand management. This action may be necessary to protect life,


limit plant damage and to maintain supplies to the majority of
Consumers.

OC 36.3 The System Operator shall have a right of involuntarily disconnection of


any facility of the Code Participants in the case of system operational
emergency when it is determined by the System Operator tha t
transmission system of NTDC might or could become incapable of
providing the required services as mandated in its licence.

OC 36.4 Distribution companies are obliged to comply Wittl the System Operator
instructions when restoring supplies.

OC 3.7 OPERATION OF THE BALANCING MECHANISM DURING DEMAND


MANAGEMENT

To be provided as and when notified by the Authority.

OC-3 30
GRID CODE

OC 3 APPENDIX 1

EMERGENCY MANUAL DEMAND REDUCTIONIDISCONNECTION


SUMMARY SHEET

Name of Company/Code ParticipantiTransmission Connected Consumer: _ _ __


Peak Demand [Year} MW

(132 & 66kV Radial Lines, 132/11kV & 66/11kV Transformers)

Transmission Peak % of Load Demand Reduction or Remarks


Connection (MW) Discon nection with res12ect to Peak Duration of Load
Point MW at the Transmission Connection Management
Point (%) [Hours}

Note: Data to be provided annually by week 40 to cover the following NTDC


calendar year.

OC-3 31
GRID CODE

OPERATION CODE No.4

OPERATIONAL PLANNING

CONTENTS

Sr. No. Subject Page No.

Oc 4.1 INTRODUCTION, OBJECTIVE & SCOPE OC4-33

Oc 4.2 NETWORK BOUNDARIES OF EXISTING


DISTRIBUTION COMPANIES OC4-33

OC 4.3 OUTAGE CO-ORDINATION OC4-35

OC 4.4 PLANNING OF GENERATION OUTAGES OC4-35

OC 4.5 PLANNING OF NTDC OUTAGES OC4-37

OC 4.6 DATA REQUIREMENTS OC4-38

OC 4.7 INSUFFICIENT POWER OPERATING MARGIN OC4-39

OC 4.8 FREQUENCY RESPONSE OC4-39

OC 4.9 CONTROL OF POWER SYSTEM VOLTAGE OC4-40

OC 4.10 POWER SYSTEM STABILITY CO-ORDINATION OC4-44

OC 4 APPENDIX 1 (OC 4.4.1.2)


Short Term Planning Timetable for Generation Outages (Year 0) OC4-45

OC 4 APPENDIX 2 (OC 4.4.1.2)


r,ledium Term Planning Timetable for Generation Outages (Year 1-2)OC4-46

OC 4 APPENDIX 3 (OC 4.4.3.2)


Long Term Planning Timetable for Generation Outages (Year 3-5) OC4-47

OC 4 APPENDIX 3 (OC 4.5.)


NTDC Transmission Outages OC4-47

OC 4 APPENDIX 4, 5, 6
(Oe 4.5.1, OC 4.5.2, OC 4.5.3)
NTDC Transmission Outages (Year 0-5) OC4-48

OC 4 APPENDIX 7 (OC 4.6.1)


Generator Performance Chart OC4-49

OC 4 APPENDIX 8 (OC 4.6.1)


Generation Planning Parameters
GRID CODE

OPERATION CODE NO.4

OPERATIONAL PLANNING

OC4.1 INTRODUCTION, OBJECTIVE & SCOPE

OC4.1.1 Operating Code No. 4 details the information including procedures


required by the System Operator and Users to ensure efficient
co-ordination and harmonisation of the dispatch of all Generation
facilities, and User's obligations to enable the NTDC transmission
System to operate under normal and emergency conditions, and/or
during construction, repair and maintenance outage periods.

OC 4.1.2 To plan ahead, Operational Planning is required for several timescales.


The data provided by Generators and DISCOs enables NTDC to match
Generation with NTDC Forecast Total System Demand together with
an operating reserve of generation to provide a margin to ensure that
the Standards of Security of Supply as set out in this Code and the
NTDC licence are properly achieved.

OC4.1.3 The scope of this Code applies to all Grid Code participants, i.e.

(a) National Transmission and Dispatch Company, NTDC;

(b) Generators;

(c) Distribution Companies;

(d) Transmission Connected Consumers;

(e) Externally-connected Consumers; and

(f) Externally-connected Parties.

OC4.2 NETWORK BOUNDARIES OF EXISTING DISTRIBUTION


COMPANIES

Restructured Network

The NTDC shall own and operate the assets of entire 500kV and
220kV transmission and substations.

All Code Participants, including generation connected to 132/66 kV


network shall be connected to the NTDC network; and embedded
generation shall be connected to the bulk power system through the
DISCO's 11 kV distribution network.

OC·4
GRID CODE

Bifurcation of network between NTDC and Generation Companies

The network bifurcation point between NTDC and a Generator's


substation shall be the line connections on the NTDC terminal structure
at the Generator substation. The NTDC's maintenance jurisdiction shall
be up to the tension strings of the same terminal structure towards the
line side.

In case a Generator does not own a generating sUbstation then the


bifurcation point shall be the line connection on the Generator's
terminal structure. In this case, the NTDC maintenance jurisdiction
shall be up to the tension strings of the same terminal structure
towards gantry side.

For the Generators connected to the 132/66 kV network of distribution


companies, the above Principle shall also apply. However, the
maintenance shall be carried out by the concerned distribution
company after the approval of the NTDC/System Operator.

Bifurcation of network between NTDC and Distribution Companies

The Network Bifurcation Point between NTDC and Distribution


Companies shall be the dropper from the terminal structure of 220 kV
grid station to the licensee's 132kV or 66kV line, which shall also be
the Connection Poini for that Licensee. The NTDC's maintenance
jurisdiction shall be up to the tension strings of the same terminal
structure towards gantry side.

From those NTDC substations where 11 kV feeders emanate which, in


additional to station auxiliary supply, also feed the Consumers of the
respective distribution companies, the point of bifurcation of such
feeders shall be the jumpers of 11 kV power cable coming from
outgoing panels and the 11 kV distribution line at the terminal structure.

Within next three years of the implementation of this Code efforts


j should be made that the distribution companies shift their 11 kV load
1 from 220 kV Grid Stations to 132 kV stations of the distribution
\. companies.

Bifurcation of Network between NTDC and KESC

The network bifurcation point between NTDC and KESC shall be


according to the principles established in Ulnterconnection Agreement"
between NTDC and KESC as and when finalized between the parties.

OC4.2.1 Point of Connection

These are points of Connection which shall be in conformance ~___


Clause (xiv) of Section 2 of the NEPRA Act, which sta '? CR f?~G
Connection of one company's electrical facilities to another c \J ny's u.
c...

OC-4 34

.\'
GRID CODE

electrical facilities. These are 220/132/66 kV substations where 132/66


kV lines originate into the User's network.

OC 4.3 OUTAGE CO-ORDINATION

OC 4.3.1 In order to ensure the uninterrupted, smooth and stable operation of


the NTDC Transmission System, several Parties need to interact with
each other. In summary these are: -

(a) Each Generator with the System Operator in respect of outages.


plant defects, availability etc.

(b) The System Operator with respective Generator in respect of


transmission outages and constraints relevant to that Generator.

(c) The System Operator with respective distribution company in


respect of outages and constraints on the transmission system,
Power Plants, and at Transmission Connection Points.

(d) The System Operator with respective distribution company and


each Transmission-connected Consumer in respect of outages
and constraints on the NTDC Transmission System, power
plants, and at each transmission Connection Point relevant to
that distribution company and the transmission connected
Consumer.

(e) Each distribution company and each transmission Consumer


connected with NTDC in respect of User system outages
relevant to NTDC

(f) Each External-connection Operator with the System Operator


for outages and constraints on their systems and vice versa.

OC 4.4 PLANNING OF GENERATION OUTAGES

OC 4.4.1 Short Term Planning (Year 0)

OC 4.4.1.1 In this Code, short term is the financial current year, or Year 0 of the
NTDC Financial Year. The basis for Operational Planning for Year 0
shall be the revised Year 1 Final Generation Outage Programme
prepared by each Generator, and submitted to the System Operator
will be on the Financial Year basis.

OC 4.4.1.2 The closer the prepared outage programme is to real-time operations,


the more accurate it must be to ensure there is adequate generation to
match demand. There shall be several timelines whereby there shall
be an exchange of information, on a quarterly basis. between each
Generator and the System Operator. In each case the Generator is
required to return their most up to date outage proposals. the~re..-r_~
enabling the System Operator to plan generation availability
~

OC-4 35
GRID CODE

forecast generation requirements. The precise timetable for the


provision and acknowledgement of this information is produced as
Appendix 1 (P:45) of this sub-code. Each Generator shall only
undertake the Outage Programme only as agreed to in writing by the
System Operator.

OC 4 4.2 Medium Term Planning (Year 1·2)

OC 44.2.1 In this Code, medium term is the two financial years following Year 0,
or Years 1 & 2 of the NTDC Financial Year. The basis for Operational
Planning for Year 1 & 2 shall be the "revised Year 2 & 3" Final
Generation Outage Programme, agreed between each Generator, and
the System Operator.

OC 4.4.2.2 At intervals specified in Appendix 2 (P: 46), there shall be an exchange


of information concerning the Final Generation Outage Programme
between each Generator and the System Operator on a Financial Year
basis.

OC 44.2.3 The process of iterative discussions and updating of the Final


th
Generation Outage Programme shall be concluded by April, 30 , of
st
each financial year to be notified by the System Operator by May 31 ,
of each financial year. Year 1 programme shall form the basis of the
Year 0 Final Generation Outage Programme.

OC 44.3 Long Term Planning (Year 3·5)

OC 44.3.1 In this Code long term is for the three-year period covering Years 3, 4
& 5 of the NTDC Financial Year.

OC 44.3.2 At the beginning of Year 3 for the next three years, Year 3, 4 & 5, each
Generator shall provide, in writing, to the System Operator, a
provisional Generation Outage Programme showing the best estimate
of its Usable Output for the Years 3,4, and 5 (Appendix-3, P:47).

OC 44.3.3 The System Operator shall prepare the annual NTDC Forecast
Demand including values for the peak Summer Demand.

The System Operator shall notify respective Generator of any


forecasted outages on the NTDC Transmission System, for
construction or maintenance work. The process of provisional
planning, between NT DC and each Generator, shall terminate by the
beginning of the tenth month of Financial Year 3.

OC4.4.3.4 Every effort shall be made by the System Operator and each
Generator to agree on the Final Generation Outage Programme which
when summated will meet the NTDC Forecast Total System Demand
for the Financial Years 3 to 5. All agreements shall be recorded for
future reference. It is acknowledged that this agreement on the Final
Generation Outage Programme at this stage is not a commitment on
the part of the Generators. In the event that a Generator's outages
later on differ from those given in the Final Generation eR REG
~<.;/-
o
OC-4 36 lLJ ~
J BY ~
':} THE AUTHORITY ~
q ~
GRID CODE

Programme, or they conflict with the NTDC Transmission System


Outage Programme, NTDC is not committed to alter its own NTDC
Transmission System outage programme for the sake of Generators.

OC 4.5 PLANNING OF NTDC OUTAGES

OC 4.5.1 Short Term Planning (Year 0)

In this Code short term is the current Financial year, or year 0 of the
NTDC Financial Year.

OC 4.5.1.1 Each Generator, distribution company or transmission Consumer may


at any time during Year 0 request in writing to the System Operator for
changes in the outages requested by them in future years. The System
Operator shall determine if the changes are acceptable, and shall reply
in writing to each Generator, distribution company or transmission
Consumer advising them if the proposed changes are acceptable to
the System Operator. However, the System Operator is not committed
to alter its own NTDC Transmission System Outage Programme due to
changes proposed by the Users.

OC 4.5.1.2 Depending on the NTDC response to OC 4.5.1.1, there may follow a


series of discussions between all Parties to determine a mutually
acceptable solution for all including the System Operator.

OC 45.1.3 The System Operator shall review the Final Outage Programme with
respective Code Participants at eighth week (8) before real-time. All
parties are obliged to co-operate at this stage in any outage changes
requested by the System Operator, Generators, distribution
companies, and transmission Consumers.

OC 45.1.4 This process of confirming and mutually amending the Final Outage
Programme continues in more and more detail right up to the real-time
operation. Appendix 4 (P: 48) of this Code details the time scales of the
NTDC Transmission Outages and obligations. which each Code
Participant must observe to achieve this objective.

OC 4.5.2 Medium Term Planning (Year 1·2)

In this Code, Medium-Term is the two financial years period following


Year 0, or Year 1-2 of the NTDC Financial Year.

OC 4.5.2.1 The System Operator is required to update the NTDC Transmission


System Outage programme, to take into account of outages, required
for NTDC transmission system maintenance purposes.

OC 4.5.2.2

OC-4
GRID CODE

which the System Operator and each Code Participant must observe to
achieve this objective.

OC 4.5.3 Long Term Planning (Year 3-5)

In this Code long term is for the three-year period covering Years 3, 4
& 5 of the NTDC Financial Year

OC 45.3.1 The System Operator shall plan the NTDC Transmission System
outages for Years 3-5 on the basis of construction and refurbishment
requirements; whereas the NTDC Transmission System outage
programmes for Years 1-2 are for maintenance requirements.

OC 45.3.2 For each of the three Years 3,4, and 5 there will be a number of
timelines whereby the System Operator and Users shall exchange
information. The time scales for the information exchange are detailed
in Appendix 6 (P: 48) to achieve this objective. This process should be
complete by the beginning of the eighth month of each Financial Year.

OC 4.5.3.3 At the end of the exchange of information period, the System Operator
shall prepare a draft NTDC Transmission System outage plan
(Appendix 6) Page 48 for Years 3 to 5. The System Operator shall
also issue, in writing, those aspects of the Plan which may cause
operational difficulties for Generators, DISCOs or Transmission
Connected Consumers. The System Operator shall also indicate where
[hey may need to issue Emergency Instructions to Users in accordance
with the Operation Code to allow that the security of supply of the
NTDC Transmission System remains within the requirements of the
Transmission Licence.

OC 4.6 DATA REQUIREMENTS

OC 46.1 The Generators are required to submit to NTDC/the System Operator


technical information on each of their generating units. The information
must include a realistic performance chart for each unit. The
information required shall be as set out in Appendix 7 for Generator
Performance Charts; and as set out in Appendix 8 for Generation
Planning Parameters.

OC 4.6.2 The Generation Planning Parameters supplied to the System


Operator/NTDC shall only be used by NTDC/the System Operator for
planning purposes and not in connection with the operation of the
Balancing Mechanism (to be notified by the Authority).

OC4.6.3 By 10.00 a.m. one week prior the operational day, each User must
inform the System Operator of any changes to circuit details as
specified in Planning Code PC A 2.2.4, PC A 2.2.5, PC A 2.2.6,
PC A 2.3, PC A 2.4 which may apply on that operational day.

OC-..) 38
GRID CODE

OC 4.7 INSUFFICIENT POWER OPERATING MARGIN

OC 4.7.1 Annually, the System Operator shall calculate the required Active
Power Operating Margin required to support the NTDC forecasted
Demand. The System Operator shall advise Generators in writing of
any periods when there is likelihood of having insufficient power
operating margin.

OC 4.7.2 Generators and the System Operator shall review proposed outages at
times of inadequate Active Power Operating Margins to ensure that the
required Active Power Operating Margin can be achieved.

OC 4.7.3 Outage adjustments required to avoid inadequate Active Power


Operating Margin shall be given by the System Operator in writing to
Generators.

OC 4.8 FREQUENCY RESPONSE

OC 4.8.1 From 2 to 6 weeks ahead of the operational day, the System Operator
shall assess whether there will be sufficient plant mix to operate in
"Frequency Sensitive Mode".

(a) Automatic Generator Control Action

All Generators (thermal) above 100 MW and reservoir-based


Hydro shall provide free Governor Control Action (AGe control)
to maintain system frequency within the prescribed limits
provided in this Grid Code and the NEPRA Transmission
Performance Standards Rules.

(b) Net Drawls of Power from the Grid

When the system frequency falls below 49.4 Hz, requisite load
shedding (automatic) must be carried out to stabilize the system
frequency to an acceptable level (Frequency Sensitive Mode).

The System Operator shall provide automatic load shedding


groups, amounts of load to be shed at each Transmission
Connection Point, along with the timing of operation of the
relays, and pre-set frequency thresholds.

(c) Operating System Freguency Criteria

OC-4
GRID CODE

(i) Declared or Target System Frequency shall be 50Hz.

(ii) Frequency Sensitive Mode shall be 49.8 Hz----50.2 Hz.


Such a variation is permissible to allow frequency
variations while ramping up generation and load pick-up.

(iii) Protected periods of operation of the system at the


frequency in the range of 49.S Hz----- SO.S Hz (Tolerance
Frequency Band).

(iv) Minimum/Maximum Acceptable Frequency Band shall be


49.4 Hz-----SO.S Hz (Load Shedding Threshold or
Contingency Frequency Band), which is well within the
applicable IEC Standards.

(v) Instantaneous frequency excursions are to be handled in


the following manner:

• In the event of a single contingency, the power


system frequency must be maintained within
"Tolerance Frequency Band" within 5 minutes of
the excursion, and to within the "Frequency
Sensitive Mode" within 10 minutes of the
contingency.

• Instantaneous frequency excursions outside the


·Contingency Frequency Band" shall be handled in
such a manner that:

System frequency returns to "Contingency


Frequency Band" within 60 seconds.

System frequency returns to "Tolerance


Frequency Band" within S minutes, and
within the "Frequency Sensitive Mode"
within 30 minutes.

OC 4.8.2 If the System Operator foresees that there will be insufficient


generation operating in Frequency Sensitive Mode, it shall discuss this
problem with the Generators, and seek to change the plant mix to
ensure there shall be sufficient generation operating in Frequency
Sensitive Mode at the forecasted time.

OC 4.8.3 If the System Operator determines that the procedures of OC 4.7 and
OC 4.8 are required for the same operating period, then the order shall
normally be OC 4.7 first followed by OC 4.8. For the avoidance of
doubt, there is nothing in this paragraph which shall prevent either
procedure following the other or operating independentIY'~
r~-
n\'IER "C-
'-'_
d/,- Gc'
~I (-Y;'"
i...:...: 1 ,.,....... 0
'-'".1 . ,.., ..'ED ;0
_I BY
OC-4 40 '.. \ ~"I- ,\
~':,'; ~:... UTIiG;{ I ry
.... \

\' \.
GRID CODE

OC4.9 CONTROL OF POWER SYSTEM VOLTAGE

The System Operator (SO) shall maintain System Operating Voltage


of the Total System within the Target Voltage Levels (limits) specified
in Table 4-1 (P:41). The System Operating Voltage shall be maintained
within these specified limits for both normal operating conditions and
contingency conditions excluding transient and abnormal system
conditions.

These limits shall be maintained by the System Operator at 500 kV,


220 kV, and selected 132 kV busses of the Total System.

(a) Under (N·O) Normal Operating Conditions; The bus voltages


shall be within the bandwidth of +8% and -5% of Nominal
System Voltage (Highest and Lowest Voltages of the Total
System under Normal Steady-state Operating Conditions).
(b) Under (N·1) Contingency Operating Conditions; The bus
voltages shall be within the bandwidth of !,10% of Nominal
System Voltage (Highest and Lowest Voltages of the Total
System under (N-1) Contingency Operating Conditions
excluding Transient Conditions).
TABLE 4·1
OPERATING VOLTAGE LlMTS

Vo Ita ge L eve I I----=....:N...::,o.:..,:rm...:..:...:.:a.:....1. :;.C. .: ,o. :. :n. . :. d. :.t..:..:i


:i 0::.,:c"-'---+...l.:...:.--L-=--=-':"':-:;:":"':":"'::"':":_ _- I
Max Min Max
500 kV 540 475 550
220 kV 238 209 245
132 kV 143 125 145

These limits of System Operating Voltage are provided strictly for


voltage regulation purposes. These limits are not to be construed as
NTDC transmission system operating voltages at the Points of
Connection, distribution system voltages of the DISCOs/KESC or
consumer-end voltages (NTDC/DISCOs/KESC).
OC 4.9.1 Reactive Power Management

Distribution companies, KESC, SPC's, and other power consuming


entities, as applicable, shall all be responsible for the maintenance of
power factor at 132 kV Connection Point grid station busses; such that
the power factor at 132 kV busses in the NTDC portion of Connection
Point sUbstations shall be maintained within the range of 95% and
better during steady-state operating conditions.
Distribution companies, including KESC, shall require SPCs within their
Service Territory to install shunt capacitors and/or other power factor
correction facilities so that the power factor at their Point of Connection
is 95% or better.
In no case, DISCOs and SPCs shall offer leading
NTDC.

OC-4 41

'\ll '"
GRID CODE

OC 4 9.2 Absolute Minimum Steady State Voltages

Under extreme system conditions, the situation may arise in which


substation voltages can not be increased to the required steady state
levels. In this case, an absolute minimum voltage level (90% of
Nominal System Voltage) is defined and shall be used as a threshold
for the initiation of automatic load shedding. The following minimum
voltages shall be followed for the consideration of extreme system
conditions, and prevent system Voltage Instability conditions.

500 kV system 450 kV


220 kV system 198 kV
132 kV system 119 kV

OC 49.3 Operating Procedures

The System Operation shall be divided into two states as follows:

OC 4 9.3.1 Base Operating Case

Each day the System Operator shall establish a generation schedule


and shall dispatch generation units and transmission resources on an
hour by hour basis as per the provisions of Scheduling and Dispatch
sub-code. Dispatch Schedule shall provide adequate generation
capacity to meet expected load, total operating reserves as per OC5
and ancillary services requirements; and shall not result in transmission
congestion or voltage violations during the normal (N-O) state, and in
the emergency (N-1) state; and shall not violate voltage level criteria or
emergency loading limits on transmission lines or transformers or
manifest stability problems.

OC 49.3.2 Emergency Operating Case

The System Operator shall have available and shall implement when
required, generation re-dispatch plans and schedules for likely (N-1)
contingency events so that, if the system moves to an expected
contingency (N-1) state, the System Operator can follow the
re-dispatch and return the system to a Normal State. The System
Operator shall have available and shall implement; emergency-
operating procedures to deal with system contingencies. The System
Operator shall have available at all times and be in a position to
implement, system restoration plans for the situation in which the
system moves to an islanded state or suffers a cascading break up
resulting in a Black Out condition.

OC 4 9.4 Overhead Conductors Loading Criteria

NTDC shall establish loading limits for each 500 kV and 220 kV
transmission circuit and selected 132 kV circuits that are operated in
parallel with NTDC 500 kV and 220 kV lines for reliability reaSDl~__
'? O:--'-'- -
\~

,,~G

OC-.J 42
GRID CODE

Loading limits shall be established according to normal (N-O) and


emergency (N-1) states as well as for Summer and Winter.

Table 4-2 lists the climatic condition parameters to be used in


establishing transmission circuit loading capabilities. In addition, the
line loading capability shall take into account the required safe
minimum clearance above grade at mid span.

Each year, the System Operator shall submit to NEPRA, for


information, a list of all transmission circuits under its control. The list
shall state the Summer and Winter line loading capacity limits for
Normal and Emergency states both.

TABLE 4- 2
Ratin~
Parameters For Overhead Conductors
Summer Winter Rating
Rating Bases Bases
Maximum Conductor Temp. 0
90 C 90° C
Outdoor Ambient Temp. 40 0 C (d)
(avg.)
Conductor Temp. Rise * .
Max. Emergency Conductor None Allowed None Allowed
Temp.
Wind Velocity 3 FeeVSecond 3 FeeVSecond
Age of the Transmission
Circuit I
Transmission Line Sag
Design

Criteria stated in the table above apply to NTDC and KESC


transmission line conductors designed for operation at 132kV,
220kV and SOOkV voltage levels.

Notes to Table:
(a) Summer Months = April through October
(b) Winter Months = November through March
(c) Emergency ratings are limited to (8) hours of continuou s
operation. Conductors shall not be operated above 100 0 C
conductor temperature for more than 960 cumulative hours.
(d) The following average temperature of Winter shall be used fro
the respective provinces:
1. Lahore (Punjab) 6.S0C
2. Peshawar (NWFP) SO C
3. Quetta (Balochistan) _7° C
4. Karachi (Sindh) +SoC

OC-4
GRID CODE

OC 49.5 Transformer Loading Criteria

Grid station transformers including three phase and single phase banks
tha t are normally operated at the voltage levels of 220/132kV and
500/220kV shall be loaded under normal and contingency conditions
according to applicable lEe, ANSI/IEEE standards and as specified by
the respective manufacturers.

OC 49.6 Transmission System Components Loading Criteria

Transmission system components listed below, that are normally


operated at the voltage levels of 220/132kV and 500/220kV, shall be
loaded under normal and contingency conditions according to
applicable IEC, ANSI/IEEE standards and as spec'ified by the
respective manufacturers.

Circuit breakers Current tra nsformers


Circuit switchers 2 Potential transformers
Capacitors Wave traps
Shunt reactors Substation power buses
Disconnect Substation power cables
switches

OC4.10 POWER SYSTEM STABILITY CO-ORDINATION

Each year, NTDC/ the System Operator shall prepare transient stability
studies for expected system event scenarios that could lead to
unsatisfactory system dynamic performance and loss of power angle
stability (transient instability). The System Operator shall maintain and
be able and ready to implement, when required, emergency operating
procedures designed to mitigate the extent of disturbance resulting
from a system event.

NTDC as a System Operator shall make stability studies to develop


emergency operating plans to deal with the consequences of the
occurrence of the most probable faults including the following:

(a) Permanent three-phase fault on any primary transmission


element; including: transmission circuit, substation bus section,
transformer, or circuit breaker. It is assumed that such a fault
shall be cleared by the associated circuit breaker action in
5 cycles.

(b) Failure of a circuit breaker to clear a fault ("Stuck Breaker"


condition) in 5 cycles, with back up clearing in 9 cycles after fault
initiation.
GRID CODE

OC 4 APPENDIX 1 (OC 4.4.1.2)

Short Term Planning Timetable for Generation Outages (Year 0)

This appendix should be completed by NTDC in consultation with the Generators.

OC-4 45
GRID CODE

DC 4 APPENDIX 2 (OC 4.4.2.1)

Medium Term Planning Timetable for Generation Outages (Year 1-2)

This appendix should be completed by NTDC in consultation with the Generators

46
GRID CODE

DC 4 APPENDIX 3 (oe 4.4.3.2)

Long Term Planning Timetable for Generation Outages (Year 3-5)

Thisappendix should be completed by NTDC in consultation with ttle Generators

OC-4 47
GRID CODE

OC 4 APPENDIX 4, 5,6
(OC 4.5.1, OC 4.5.2, OC 4.5.3)

NTDC Transmission Outages (Year 0-5)

This appendix should be completed by NTDC in consultation with the generators.

OC-4 48

~y
GRID CODE

OC 4 APPENDIX 7 (OC 4.6.1)

Generator Performance Chart

Rated Apparent Power SN = 151.5MVA Rated Frequency fN= 50 Hz


Rated Active Power
Rated Aimature Voltage
PN = 128.8 MW
VN = 11.0 to 1.1 kV
Power Factor =
P.F. 0.85
Speed . nN =505° 1
Rated Aimature Current IN = 7.951 kA Cold Air Temperature TK = 41°C
,j .~!1
...
1:1 O.::G ,J.";",

1':; ----~----------_;r--;_I--,"7,- - - : -

'.Ii:::; :
I- - - _ -
~..:.~.- - -
. ___.;,
-=-.

",
,
I

i .-
Il

.(
.v
I /

/
./"
. :.:.

,,
..
I .
I
" i /
~ i
i I
.,.,,..., :....._ - L I _ _ ~ _ _ _ _?,-....:;"

c..o
u
'"
.:>
..:)

1
\1 t.tV/

30 100 t20

I __
,( O.Sh::;

.... , '_._ .. - .. --... ----------~----...:---.:~__7"(~~~~-


~~ .... " ... " J.cu Q. il)

OC-4 49
GRID CODE

OC 4 APPENDIX 8 (OC 4.6.1)

Generation Planning Parameters

OC 4 A.S Generation Planning Parameters

The following parameters are required in respect of each Gensel.

OC 4AS.1 Regime Unavailability

Where applicable the following information must be recorded for each


Gensel.

(a) Earliest synchronizing time; and

(b) Latest de-synchronizing time.

OC 4A.S.2 Synchronizing Intervals

The Synchronizing intervals between Gensets.

OC 4A5.3 De-Synchronizing Interval

A fixed value de-synchronizing interval between Gensets.

OC 4AS.4 Synchronizing Generation

The amount of MW produced at the moment of Synchronizing


OC 4A.S.S Minimum on Time

The minimum period on-load between synchronizing and De-


synchronizing.

OC 4A5.6 Run-Up Rates

A run-up characteristic consisting of different stages from


SynchrOnizing Generation to Output Usable.

OC 4AS.7 Run-Down Rates

A run down characteristic consisting of different stages from Output to


De-synchronising.

OC 4A5.8 Notice to Synchronise (NTS)

The period of time required to Synchronize a Genset.

OC·4
50
GRID CODE

OC 4.A.5.9 Minimum NPCC Shutdown Time

The minimum interval between De-synchronizing and Synchronizing a


Gensel.

OC 4.A.5.10 Maximum Shifting limit

The maximum number of times that a Genset may De-synchronize per


Operational Day.

OC 4.A.5.11 Gas Turbine Units Loading Parameters

(a) Loading rate for fast starting

(b) Loading rate for slow starting

OC-4 51
GRID CODE

OPERATION CODE No.5

OPERATING MARGINS

CONTENTS

Sr N~o.,--_....:::S~u~b:J.:::ie!..::::c.!....t_ _ _ _ _ _ _ _ _ _ _ _ _ _ _...!...P~a~qe:::...!..!.N.=o.

OC 5.1 INTRODUCTION, OBJECTIVE AND SCOPE OC5-53

OC 5.2 OPERATING MARGIN AND CONTINGENCY


RESERVE OC5-53

OC 5.3 OPERATING MARGIN IN REAL TIME OC5-54

OC 5.4 DATA AVAILABILITY OC5-54

OC 5.5 TIME SCALES AND PLANNING OC5-55

OC 5 APPENDIX 1
Response Data for Frequency Changes OC5-56
GRID CODE

OPERATION CODE No.5

OPERATING MARGINS

OC 5.1 INTRODUCTION, OBJECTIVE & SCOPE

OCS.1.1 Operating Code NO.5 sets out the types and amounts of Reserve,
which make up the Operating Margin that the System Operator may
make use of under certain operating conditions to cover for the
uncertainties in Demand Forecasting and power plant
availability/unavailability or sudden outages of generation and
transmission facilities.

OC 5.1.2 This sub-code applies to NTDC and to Code Participants which in OC5
means:

(a) Generators under Central Dispatch of NTDC.

(b) Other Users/Code Participants bound by the Grid Code.

DC 5.2 OPERATING MARGIN AND CONTINGENCY RESERVE

OC 5.2.1 The Operating Margin consists of:

(a) Contingency Reserve. This is the level of generation over the


forecasted Demand which is required in the time scale from real
time to real time plus 24 hours so as to cover for uncertainties in
Power plant availability and variations in load demand forecast.
Contingency Reserve is provided by Generators which are not
required to be synchronised, but they can be synchronised
within 30 Minutes of the initiation of the Contingency and the fall
in frequency.

This is equal to at/east the capacity of largest thermal Generator


in the system.

(b) Operating Reserve. It is the additional output beyond


Contingency Reserve that is available in real time to respond
immediately to help correct and contain the falling system
frequency following a contingency or loss of generation or the
loss of an External connection or any Mismatch between
generation and load demand. The Operating Reserve consists
of the following:

Spinning Reserve

oc-s
GRID CODE

contingency event of loss of generation or loss of an external inter-


connection or mismatch between generation and load demand
resulting in fall of frequency.

This is equal to "one-third" of the largest Generator in the System.

OC 5.2.2 The Operating Margin consist of all reserves (Spinning and


Contingency Reserve both) avnilable in the Grid, to ensure reliable grid
system operation. Enough back-up power should be made available, at
all times, to maintain the system frequency within the specified ranges
as provided in this Grid Code and NEPRA Rules on Transmission
Performance Standards. In case of sudden increase in demand or loss
of generation, which cannot be absorbed by the Spinning ReseNe, the
Contingency Reserve equal to the shortfall shall be brought in service
within 30 minutes.

The Spinning Reserve is available in distinct timescales. 1) Primary


Response in short-term, following the fall in frequency, is fully
sustainable for 30 seconds after achieving its maximum value within 10
seconds following the fall in frequency, 2) Secondary Response is the
increase in Active Power output of the on-line Generators that can be
increasingly applied in the short-term, following the fall in frequency,
and is fully sustainable for 30 minutes after achieving its maximum
value within 30 seconds following the fall in frequency.

OC 52.3 The amount of Contingency Reserve that is required at the day ahead
stage is determined by the System Operator. Time scales may be
increased by the System Operator in the light of historical data
available as to changes in power plant availability and changes in load
demand up to real time. The System Operator shall agree time scales
with the Operators of power plants where Contingency Reserve is held
on thermal Generators to reach synchronous speed.

OC 5.3 OPERATING RESERVE IN REAL TIME

OC 53.1 The amount of Operating Reserve required in real time shall be


pre-determined by the System Operator. Any shortfalls in power plant
availability, demand level, and the loss of the largest Generator in a
power plant and the effect of the loss of or the increase in load demand
on an external interconnection are to be taken into account when
determining the total amount of Operating Reserve.

OC 5.4 DATA AVAILABILITY

OC 5.4.1 Data relating to the response capability of Generator which is used to


provide Operating Reserve, and Frequency Response shall be made
available to the System Operator by the Operators of power plants.
The needed information is detailed in the appendix 1 of this sub-code.

OC-5 54
1\

~/
GRID CODE

OC 5.5 TIME SCALES AND PLANNING

OC 5.5.1 By 1500 hours (3 p.m.) each Wednesday the System Operator shall
issue each Generator in respect of its power plants a Weekly
Operational Policy for the week commencing 10.00 a.m. for the
following Monday. The Weekly Operational Policy shall cover
Generators that are available from standstill to start by low frequency
relay settings of which will be determined from time to time by the
System Operator. The Weekly Operational Policy shall specify the
location of the Gensets and take into account the low frequency setting
of these Gensets. By 10.00 a.m. on the Friday following the receipt of
the document, the Generator shall confirm as appropriate, its
availability, and seek any changes it wishes to instigate in the
document. The System Operator shall update availability in real time in
respect of notifications received.

OC 5.5.2 The Weekly Operational Policy shall include an indication of the level of
Operational Reserve to be used in connection with operation of the
Balancing Mechanism (to be notified by the Authority) in the times
scale defined in OC 5.5.1. The document shall also include details of
Operational Reserve that may be provided by Externally-connected
systems and also indicate the possible level of High Frequency
Response to be utilised by the System Operator in connection with the
operation of the Balancing Mechanism.

OC~ 55

~'
GRID CODE

OC 5 APPENDIX 1

OCSA Response data for Frequency Changes

(a) Actual Frequency Response Capability Profile; and

(b) Response values at specific MW loading points in the range of


0-3 seconds, 3-10 seconds, and 10-30 seconds following the fall
in frequency.

OCSA.1 Primary Response to Frequency Fall

Primary Response (within 0 - 3 seconds, 3-10 seconds of frequency


fall) values for a -0.5Hz upto all the loading points identified in OC
5.A.b.

OCSA2 Secondary Response to Frequency Fall

Secondary Response (within 10- 30 seconds of frequency fall) values


for a -0.5Hz upto all the loading points identified in the OC 5.A.b.

OCSA3 High Response to Frequency Rise

High Response values for a +0.5Hz up to all the loading points as


detailed in OC 5.A.b.

OCSA4 Generator, Governer and Droop Characteristics

OCSA.5 Unit Control Options

As provided

OCSA6 Control of Load Demand

As provided

OC-5 56
GRID CODE

OPERATION CODE No.6

OPERATIONAL LIAISON

CONTENTS

Sr. No. Subject Page No.

OC6.1 INTRODUCTION, OBJECTIVE & SCOPE OC6·58

OC 6.2 POWER SYSTEM SECURITY SUPPORT OC6-58

OC6.3 COMMUNICATION SYSTEM OC6-58

OC 6.4 OPERATIONS AND EVENTS OC6-59

OC 6.5 NTDC WARNINGS OC6-60

OC6.6 TESTING OC6-61

Appendix 1 OC6-62

OC-6
GRID CODE

OPERATION CODE No.6

OPERATIONAL LIAISON

OC 61 INTRODUCTION, OBJECTIVE & SCOPE

OC 6.1.1 Operating Code No.6 sets out the requirements for the exchange of
information relating to Operations and Events on the Total System that
may have, or have had, an operational effect on the System of NTDC,
Ge'nerators, transmission-connected Consumers, distribution
companies or the Externally-connected Parties and Consumers.
Exchange of information also includes the requirement to advise on
equipment, plant. and apparatus tests. The System Warnings shall be
issued relating to inadequate plant availability, subsequent load
demand control, and to advise of a risk of major system disturbance.

OC62 POWER SYSTEM SECURITY SUPPORT

Code Participants shall have facilities for exchange of information in


real time. This information may include:

(a) Status and positioning of circuit breakers.

(b) Tap changer position of 500/220 kV and 220/132 kV power


transformers.

(c) Measured values of current, voltage, active and reactive power.

(d) Status and positioning of disconnect and isolating switches.

OC63 COMMUNICATION SYSTEM

NTDC shall provide at least dual high-speed network-wide


communication system, to provide for the communications facilities,
installed on its system, and the Code Participants facilities.

Communication systems shall provide channels for direct telephone,


facsimile and SCADA links (Remote Terminal Unit) between the SO
and Code Participants. NTDC communication facility shall be used for
communicating with NTDC work crew and grid substation personnel.
An electronic recording device shall be provided at th e SO to record all
dispatch transactions and communication with the work crews.

under its jurisdiction.

OC-6 58
GRID CODE

NTDC shall operate, maintain, expand and upgrade from time to time,
this Supervisory Control and Data Acquisition (SCADA) system and a
supporting dedicated communication system.

NTDC shall provide all Code Participants wittl specifications for RTU's,
communications system requirements and protocols, and technical
assistance required to connect and functionally integrate Code
Participants' facilities into the SCADA system.

The SCADA and SCADA Communication System shall be used by


NTDC and Code Participants to monitor and control the NTDC
transmission network, including 500 kV and 220 kV grid stations, and to
dispatch Generators connected to the transmission network. The
SCADA system shall also include data from Generators and other
Code Participant facilities as required by NTDC.

OC 6.4 OPERATIONS AND EVENTS

OC 6.4.1 Information regarding "Operations" and "Events", that have taken place
or about to take place or are being planned to take place are to be
assessed by the System Operator to identify appropriate and
necessary actions to be taken by the owner or respective Operator of a
part of the sub-system or the System Operator to eliminate or to
minimise their adverse effects, if any. The reason for the Operation or
the Cause of an Event need not be communicated to the Parties or
Code Participants or Users.

OC 6.4.2 Operation is a planned or unplanned action; by the System Operator;


and Operational Effect is the effect that an Operation or an Event, on
one part of the System, may have on the Total System or on another
part of the System.

OC 6.4.3 Some of the Operations and Events that are required to be reported
under this sub-code are:

(a) Operations that form part of a planned outage which has been
arranged in accordance with OC 4.

(b) Events which cause plant or apparatus to operate beyond its


rated design capability, and present a hazard to personnel.

(c) Adverse weather conditions being experienced.

(d) Failures of protection, control or communication equipment.

(e) Risk of trip on apparatus or plant.

This list is not exhaustive.

OC 6.4.4 Notification of an Operation or Event shall be sufficient for the recipient


to assess the effect on its individual System. When it is necessary for

aC·6 59
GRID CODE

the System Operator to pass on to other Users the information it has


received from a particular User relating to an Operation or Event; it
shall only pass on the information that it has received, and the name of
the source of the information. The Giver of the original information may
receive request clarification.

OC 6.4.5 Notification of Operations and Events may be passed on to the


Operators of Embedded Generation subject to Central Dispatch when
the Operation or Event may have an effect on their System.

OC 6.4.6 Notification of the details of an Event, Major Event and Operation, must
be restricted to Parties governed by the Grid Code. Details shall not be
passed on to any other third party.

OC 6.4.7 OC 7 deals with the upgrading of an "Event" to a "Major Event' and the
subsequent exchange of information.

OC 6.5 NTDC WARNINGS

OC 6.5.1 The System Operator System Warnings are required to give


information relating to System conditions and Events. They are
intended to alert Operators of Power Plants, transmission-connected
Consumers, distribution companies and the Operators of Externally-
connected Parties of possible or actual shortages of power generation,
and the likely duration to enable these Entities to prepare for
subsequent instructions that may be issued by the System Operator. A
Warning relating to Demand reduction shall only be issued to Entities
that shall receive subsequent Load Demand reduction instructions. If
the System Operator considers that the reason for issuance of a
System Operator's System Warning shall be restricted to a geographic
area or a part of the sub-system, the circulation of the Warning may be
appropriately limited.

OC 6.5.2 All Parties shall agree on the office locations to which Notices shall be
issued and the means of transmission of the System Warning.

OC 6.5.3 The System Operators System Warnings shall be issued in the form of:

(a) Inadequate system power Operating Margin Warnings which


shall detail the period of the warning, the shortfall and the
foreseen consequences.

(b) High risk of Load Demand reduction Warnings shall be issued


following the issuance of an inadequate system Power
Operating Margin Warnings when the need to actually reduce
load demand is foreseen. The possible level of load demand
reduction shall be indicated.

OC-6 60

\~-y
GRID CODE

(c) Load Demand control imminent warnings (and may be issued


when no other warnings have been issued) shall be issued
when Load Demand reduction is expected within next 30
minutes. A Load Demand control imminent Warning is valid for
two hours unless rescinded or re-issued.

(d) Risk of system disturbance warning shall be issued when there


is a widespread risk of system disturbance. On receipt of such a
warning, the recipients shall take action to ensure a rapid
response to any problems.

NT DC System Warning procedure is reflected in Appendix 1 of this


sub-code.

OC 6.6 TESTING

OC 6.6.1 If the System Operator or a transmission-connected Consumer, an


Operator of a Generator, or a distribution company or the Operator of
an Externally-connected Party intend to carry out testing that may
affect NTDC, or testing that the System Operator proposes may cause
an Operation or Event, prior agreement must be reached between all
Entities concerned. The Notification must include full detail of the
testing and dates and timing.

OC-6 61
GRID CODE

OC 6 Appendix 1

NTDC SYSTEM WARNINGS (TO BE IMPLEMENTED THROUGH FAX OR ANY


OTHER ELECTRONIC MEDIA)

NTDC TO: FOR ACTION CONSEQUENCE RESPONSE FROM


WARNING RECIPIENTS I
TYPE CODE PARTICIPANTS
Inadequate Generators, • Less Generation as • Increase of
System Margin (Centrally compared to Demand Generation by the
Dispatched) of the system and Generators.
Operating Margin .

• Instruction for reduci ng • To initiate additional


DISCOs the Demand Demand Management
NTDC Transmission if conditions are not
Connected improved.
Consumer,
Externally-connected
Consumers
High risk of Generators, DISCOs, ----do---- ----do----
Demand NTDC Transmission
Reduct/on Connected
Consumers, ----do---- ----do----
Externally-connected
Consumers.
Demand Control DISCOs, NTDC Possibility of reduction in ----do----
Imminent Transmission Demand within a
Connected specified time as per
Consumers, instructions of NTDC ----do----
Externally-connected
Consumers.
Risk of System Generators, DISCOs, Risk of possible Operational staff to be
Disturbance NTDC Transmission disturbance on whole or made alert to be able to
Connected partially NTDC system. withstand the
Consumers, disturbance.
Externally-connected
Consumers.

OC·6 62
GRID CODE

OPERATION CODE No.7

EVENT INFORMATION EXCHANGE

CONTENTS

Sr. No. Subject Page No.

OC 7.1 INTRODUCTION, OBJECTIVE AND SCOPE OC7-64

OC 7.2 DECLARATION OF A MAJOR EVENT OC7-64

OC 7.3 THE REPORT OC7-64

OC 7.4 FURTHER ACTION OC7-64

APPENDIX 1 OC7-65
Report of a Major Event
GRID CODE

OPERATION CODE No.7

EVENT INFORMATION EXCHANGE

OC 7.1 INTRODUCTION, OBJECTIVE & SCOPE

OC 7.1.1 Operation Code No. 7 details the procedure for formal exchange of
written reports relating to Events that have already occurred on the
System. Events on the System formally reported between the System
Operator, distribution companies, Operators of Power Plants,
transmission-connected Consumers, and Operators of Externally-
connected System Parties, are those initially reported as required
under Operation Code No 6.

OC 7.2 DECLARATION OF A MAJOR EVENT

OC 7.2.1 Following an Event on the System which has, in the opinion of any
Code Participant is likely to have an effect on its system, the affected
Code Participant can declare the Event as a "Major Event".

OC 7.3 THE REPORT

OC 7.3.1 Following such a declaration, the owner of the system on which the
Major Event occurred is required to provide a written report to the
requesting party confirming information given orally under Operation
Code No 6.

OC 7.3.2 The report shall contain as a minimum the information detailed in


Appendix 1 of this sub-code. The report shall also include any
additional information that has come to light following the initial verbal
report of the Event.

OC 7.3.3 The recipient of the report shall not pass it on to a third party. The
recipient may, however, use the information to prepare a report for
another party

OC 7.4 FURTHER ACTION

OC 7.4.1 The recipient of a report of a Major Event may request that a joint
investigation be carried.

64
OC-7
GRID CODE

DC 7 APPENDIX 1

Report of a Major Event

Information (where relevant) to be given

Time and date of Major Event

2 Location

3 Plant I Apparatus involved

4 Description of the Major Event

5 Demand I Generation lost

6 Generating Unit Frequency

7 Generating Unit MVAr performance

8 Estimated duration of non-availability of Power Plant or that of Demand


interruption.

65
OC-7
GRID CODE

OPERATION CODE No.8

SYSTEM RECOVERY

CONTENTS

Sr. No. Subject Page No.

OC 8.1 INTRODUCTION, OBJECTIVE & SCOPE OC8-67

OC 8.2 TOTAL AND/OR PARTIAL SHUTDOWN OC8-67


OF SUPPLIES

OC 8.3 ISLANDED NETWORK OC8-79

OC 8.4 INCIDENTS OC8-70


GRID CODE

OPERATION CODE NO.8

SYSTEM RECOVERY

OC 8.1 INTRODUCTION, OBJECTIVE & SCOPE

OC 8.1.1 This sub-code deals with the procedures for the restoration of power
supplies following a Total Shutdown or a Partial Shutdown of the
System and the re-synchronisation of specific parts of the System that
have been Islanded.

OC 8.1.2 This sub-code requires that effective channels of communications must


be established between senior management of the NTDC and the
System Operator and the Generators, Distribution Companies,
Transmi ssion-connected Consumers, Externally-connected
Consumers, which are additional to those used for day-to-day system
opera lions.

OC 8.1.3 In order to mitigate the effects of any national emergency, the Federal
Government may require NTDC, Operators of power plants and
distribution companie s to take action to safeguard electric power
supplies. Such action may be contrary to the principles and
procedures laid down in the Grid Code, and as such, the appropriate
section of the Grid Code shall stand suspended.

OC 8.1.4 OC 8 applies to the System Operator, NTDC, distribution companies,


Operators of power plants, and Users of the System. Contingency
arrangements are required to be established by the System Operator
with each Externally-connected Party/Consumers.

OC 8.2 TOTAL AND I OR PARTIAL SHUTDOWN OF SUPPLIES

OC 8.2.1 A Total Shutdown of the System is a situation when there is no internal


generation online and operating; and there is no power supply
available from external-connections. The restoration of power supply
from such a situation is a Black Start Recovery. A Partial Shutdown is
when a there is no on-line operating generation or External Connection
to a part of the system that has become shutdown; and it is necessary
for the System Operator to instruct Black Start Recovery procedures to
restore supplies to that part of the system.

OC 8.2.2 During the restoration of power supplies following a Total Shutdown or


Partial Shut Down of the System, it may be necessary to operate the
system outside normal frequency and voltage limits as stated in OC 4.
It may also be necessary for the System Operator to issue instructions
that are contrary to the Balancing Mechanism or Code, and also to

67
OC-8
GRID CODE

normal contractual obligations in order to ensure restoration of


supplies.
OC 82.3 Following a Total Shutdown of the System designated power plants
that have the ability to Start Up without any External Connection to the
system shall be instructed to commence Black Start recovery
procedures. These procedures, which are to be agreed in advance,
may include the restoration of blocks of local load demand that can be
restored in agreement with the local distribution company. Local
procedures may include the restoration of power supplies via
Embedded Generators. The System Operator has the responsibility for
the re-energisation of the interconnected transmission system, and the
re-synchronisation of the system blocks of islanded blocks of locally
restored supplies.

OC 82.4 Where system configuration prevents a Generator restoring blocks of


Load Demand without the use of the interconnectable transmission
system, adjacent distribution companies shall reconfigure their
system(s) to provide discrete blocks of local load demand, which shall
then be restored on the instruction of the System Operator in liaison
with Generator, using segregated parts of the interconnected
transmission system.

OC 82.5 The complexities and uncertainties relating to the restoration of power


supplies following a Total Shutdown or Partial Shutdown of the System
dictate that any internal NTDC or the System Operator procedure and
any local procedure agreed between NTDC, the System Operator,
distribution companies, transmission-connected Consumers and
Generators allows for a flexible approach to be adopted in the light of
actual circumstance rather than rigid procedure involving prescribed
actions.

OC 8.2.6 During the restoration of Load Demand, the System Operator may
issue instructions that conflict with a local procedure for the restoration
of power supplies. In such an event the System Operator instruction
shall override any agreed local procedure.

OC 8.2.7 Procedures for the restoration of power supplies may include the
requirement for the Operators of Generators to communicate directly
with the distribution companies so that the restoration of blocks of local
power supplies can be carried out in a controlled manor to ensure the
Generator's stability.

1
OC 8.2.8 Frequency sensitive automatic load disconnection schemes may be
taken out of service during the restoration of Load Demand to prevent
unwanted disconnection of load demand.

~
68
OC-B
GRID CODE

OC 82.9 The System Operator shall instruct the interconnection of islanded


networks to form progressively larger and resilient sUb-systems until
the complete System has been interconnected.

OC 82.10 During the restoration of supplies, the System Operator shall agree the
reconnection of the System to any Externally-connected Party with the
operations of those systems, as allowed for under the relevant licences.

OC 8.3 ISLANDED NETWORK

OC 8.3.1 In the event of a part of the System becoming disconnected from the
complete System (islanded), but there has been no resultant Total
Shutdown or Partial Shutdown of the system, the System Operator
shall instruct the regulation of generation and or Load Demand in the
group to enable it to be re-synchronised to the complete System

OC 8.3.2 In order to achieve conditions to permit the re-synchronisation of the


islanded network, the System Operator may adopt one of the following
approaches: -

(a) The System Operator; the Operators of Generators in the


islanded network that have Generators that are connected to the
System, or able to be synchronised and connected to the
System; and the distribution companies in whose area the
islanded network is located may exchange information to enable
the System Operator to issue emergency instructions until the
islanded network has been re-synchronised. Until the System is
re-synchronised, there can be no transfer of Load Demand
between the synchronised and un-synchronised parts of the
System.

(b) The System Operator shall issue an emergency instruction to the


Operator (s) of power plants in the islanded network to float local
Load Demand to maintain Target System Frequency until the
islanded network has been re-synchronised. During this period,
the distribution company is required to advise the System
Operator of any anticipated changes in load demand. Transfers
into or out of the islanded system are impracticable.

(c) If the supply to a part of the System becomes de-synchronised,


then that part of the network may be shutdown and power
supplies restored for the synchronised part of the System.

OC 8.3.3 Local procedures of the distribution companies may be agreed to for


the each relevant part of the Total System between the System
Operator; Operators of Power Plants, in the relevant part of the
network, and the relevant distribution companies.

OC8.3.4

OC-8
GRID CODE

Power Plants, and the local distribution companies shall agree on a


procedure.

OC 8.4 INCIDENTS

OC8.4.1 When an event occurs, that in the opinion of the System Operator or a
distribution company, may have, or have had, a widespread effect on
the System, which is outside the normal functions of system control, an
incident procedure shall be invoked.

OC 8.4.2 The incident procedure shall not take over any function of control of the
System. The procedure shall allow for communication between the
management bodies of various affected Code Participants, and the
distribution of information within their organisations.

70
OC-8
GRID CODE

OPERATION CODE No.9

WORK SAFETY AT THE INTERFACE

CONTENTS

Sr. No. Subject Page No.

OC 9.1 INTRODUCTION, OBJECTIVE AND SCOPE OC9-72

OC 9.2 SAFETY CO-ORDINATORS OC9-74

OC 9.3 PROCEDURE FOR SAFETY AT THE INTERFACE OC9-74

OC 9.4 UNFORESEEN CIRCUMSTANCES OC9-75

OC 9 APPENDIX 1 (A)
Record of Inter-System Safety Precautions (RISSP-R)
For Requesting Safety Co-ordinator's Record OC9-76
OC 9 APPENDIX 1 (8)
Record of Inter-System Safety Precautions (RISSP-R)
For Implementing Safety Co-ordinator's Record
OC9-78
GRID CODE

OPERATION CODE No.9

WORK SAFETY AT THE INTERFACE

OC 9.1 INTRODUCTION, OBJECTIVE & SCOPE

OC 9.1.1 The Operation Code 9 (OC-9) specifies the standard procedures, to be


used by NTOC and Users, for the co-ordination. establishment, and
maintenance of necessary Safety Precautions, when work is to be
carried out at or near the system of NTOC and/or a User/Code
Participants. Moreover, it specifies the standard procedures, when
there is a need for Safety Precautions on HV apparatus on the other
User's System for the work to be carried out safety. It does not apply at
the interface points between the Code Participants where Safety
Precautions need to be agreed upon solely between the Users or Code
Participants. It does not replace the safety rules of any Code
participants or Users already approved by the Authority. OC-g does not
seek to impose a particular set of Safety Rules on NTOC or Users or
Code Participants. The Safety Rules to be adopted by NOTC or Users
shall be developed by themselves and approved by the Authority.

OC 91.2 To ensure safe conditions for eQ:h and every foreseeable situation
during system operation, it is essential that NTOC and the Code
Participants operate in accordance with safety rules and procedures as
laid down in their approved Safety Codes, and other NEPRA applicable
documents.

NTOC shall have a comprehensive approved Power Safety Code in


place and available at all times.

OC 9.1.3 In this document, only the following terms have the following meanings:

HV Apparatus means High Voltage electrical circuits forming part of a


system, on which safety From the System is required or on which
safety precautions are required to allow work to be carried out on the
System.

The words mentioned above are defined as follows:


"Safety From the System" means that condition which safeguards the
persons, when work is being carried-out at or near a System, from the
dangers which are inherent to the System.
"System" means any User System and/or the NTOC
case may be.
"Safety Precautions" means isolation and/or Earthing.

72
OC-9
GRID CODE

Isolation means the disconnection of apparatus from the remainder of


the System in which that apparatus is connected. The integrity of the
Isolation being achieved and maintained by the use of an approved
isolation device, on which all of the procedures to maintain safety from
the System have been carried out. The means of Isolation shall be
maintained in accordance with the rules of the owner of the Isolation.

Earthing means the application of a connection between the isolated


system and the general mass of earth, by an approved means that is
adequate for the purpose, and isre'quired to be in place in a secure
condition in accordance with the rules of the owner of the Isolation.

OC 9.1.4 The rules for achieving and maintaining isolation and earthing at every
site where this Operating Code NO.9 applies shall be agreed to by all
concerned Parties with respect to Connections at that Site. Local safety
instructions shall be exchanged by all concerned Entities having an
interest in the Connections at a Site.

OC 9.2 SAFETY CO-ORDINATORS

OC 9.2.1 Safety Co-ordinators shall be available at all times for all Sites where
this section of the Operation Code is applicable. These Persons are
required to be authorised by their employer to achieve Safety
Precautions on their Systems, as may be required by other Entities.

OC 9.2.2 When a request is received by an Entity requiring that it make Safety


Precautions on its System to enable the requesting Entity to carry out
work or testing, the details of the request shall be recorded (a model
form has been provided in Appendix 1). The form shall be uniquely
numbered. The party making the request shall also record details of the
request and subsequent confirmation on a uniquely numbered form.
The suffixes shall indicate the appropriate function - (I) for
Implementing and (R) for Requesting Safety Precautions. The recoding
of details relating to the request shall only be undertaken by a person
authorised to act as a Safety Co-ordinator at that Site

OC 9.3 PROCEDURE FOR SAFETY AT THE INTERFACE

OC 9.3.1 80th Code Participants and other concerned Entities shall record the
request for Safety Precautions in their system logbooks and the
implementing Safety Co-ordinator shall arrange for the Safety
Precautions to be made. The implementing Safety Co-ordinator shall
confirm when the requested Safety Precautions have been taken to the
requesting Safety Co-ordinator.

OC 9.3.2

i
If earthing is required, both Code Participants shall record the request
and the implementing Safety Co-ordinator shall record details in his
syslem logbook of Ihe aclions laken 10 comply requesl.

73
OC-9
GRID CODE
OC 93.3 Details of the isolation and earthing achieved shall be formally
recorded by both Entities and the agreement timed and recorded on
the appropriate form. Following issue of the form, the requesting
Safety Co-ordinator may proceed to issue safety documentation at the
agreed point of the system interface between the Code Participants.
Neither Entity may issue a safety document which permits the removal
of earth connections nor the application of any source of energy for
testing purposes without the agreement of implementing Safety Co-
ordinator and then only one such safety document may be issued on
that part of the System at anyone time.

OC 93.4 It is the responsibility of the implementing Safety Co-ordinator to


ensure that all Safety Precautions are maintained in place until it is
confirmed by the requesting Safety Co-ordinator that they may be
removed.

OC 93.5 On completion of work and the cancellation of all safety documentation,


the requesting and implementating Safety Co-ordinators shall agree to
the cancellation of the form; shall co-ordinate the restoration of the
system as appropriate; and shall ensure all requests and subsequent
confirmations have been recorded in their logbooks.

OC 94 UNFORESEEN CIRCUMSTANCES

OC 9.4.1 In the event of unforeseen circumstances, where for example due to


broken conductor or connection on one system infringing safe working
cle~3r~3nCcS on another system. the Safety Co-ordinators for the
systems involved shall agree a procedure following reports from their
local Safety Co-ordinators as to the exact point of the problem.

Details in the form of "Record of Inter-system Safety Precautions" Procedures-


RISSP-R (Model Form) are provided in Appendix 1.

74
OC-9
GRID CODE

OC 9 Appendix 1 (A)
Inter-System Safety
Record of Inter-Safety Precautions (RISSP - R)
(For Requesting Safety Co-ordinator's Record)

RISSP No. _ _ _ _ _ __

Name and location of the Control Centre: _ _ _ _ _ _ _ _ _ _ _ _ _ _ __

Name of Control Centre Operator: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __

Name and Location of Grid StationlWork Station: _ _ _ _ _ _ _ _ _ _ _ __

PART 1

1.1 (a) Identification of HV Apparatus where isolation and safety from the
system is to be aChieved.

(b) Details of work to be done. _ _ _ _ _ _ _ _ _ _ _ _ _ __

(c) Any other instructions or safety measures to be taken: _ _ _ _ __

1.2 Identification and Safety Precautions Established

(Whether on the implementing safety co-ordinator's system or any other users


system connected to implementing safety co-ordinator system) Tick mark ./ in
the relevant box.

Identification Location Isolation Earthing Confirm Locking


ofHV Notices Arrangements
Apparatus Displayed Provided

(i)
D D D D
(ii)
D D D
(iii)
D D D
75
OC-9
GRID CODE

1.3 Confirmation and Issues

Mr. _ _ _ _ _ _ _ _ _ _ _ _ _ implementing Safety Co-ordinator at

location ______ has confirmed that the safety precautions identified in

Para 1.2 have been established and will not be removed until this RIS SP is

cancelled.

Signature: _ _ _ _ _ _ _ _ _ __
Dated _ _ _ _ _ __ Name:
Time - - - - - - - -----------
(Requesting Safely Co-ordi nator)

Date and Time of Commencement of Work

Date and Time of Completion of the Work

Name & Signature of


Incharge of work
(Authorised Person)

PART2
CANCELLATION

I have confirmed to Mr. implementing Safety Coordinator


at location that all men working on the HV apparatus as identified in
Para 1.2 have been withdrawn, and the safety precautions set out in Para 1.2 are no
longer required and hence the RISSP is cancelled.

Signature:
Name:-----------
(Requesting Safety Co-ordinator)
Dated: _ _ _ _ _ __
Time - - - - - - -

Date and Time of Re-energizing of Apparatus _ _ _ _ _ _ _ _ __

76
ac-g
GRID CODE

DC 9 Appendix 1 (8)
Inter-System Safety
Record of Inter-Safety Precautions (RISSP - R)
(For Implementing Safety Co-ordinator's Record)

RISSP No.
-------
Name and location of the Control Centre: _ _ _ _ _ _ _ _ _ _ _ _ _ __
,
Name of Control Centre Operator: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __

Name and Location of Grid StationlWork Station: _ _ _ _ _ _ _ _ _ _ __

PART 1
1.1 (a) Identification of HV Apparatus where isolation and safety from the

system is to be achieved.

(b) Details of work to be done. _ _ _ _ _ _ _ _ _ _ _ _ _ __

(e) Any other instructions or safety measures to be taken: _ _ _ _ __

1.2 Identification and Safety Precautions Established

(Whether on the 'Implementing safety co-ordinator's system or any other users

system connected to implementing safety co-ordinator system) Tick mark ./ in

the relevant box.

Identification Location Isolation Earthing Confirm Locking


ofHV Notices Arrangements
Apparatus Displayed Provided

(i)
D D D D
(ii)

(iii)
D
D
D
D
D
D
Di
D. "CNlCP. R':~0
./ ('.>
':j' 0·
--------------~=__----------_f_--...-__r,.~: r-ROVED .~:
77
EY
OC-9

~
GRID CODE

1.3 Confirmation and Issues

I, _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ implementing Safety Co-ordinator

at location has confirmed that the safety precautions

identified in Para 1.2 have been established and will not be removed until this

RISSP is cancelled

Signature: _ _ _ _ _ _ _ _ _ __
Name:
-~-~~~~-~-~
(Implementing Safety Co-ordinator)

Dated: - - - - - - - -
Time
--------

PART 2
CANCELLATION

Mr. requesting Safety Coordinator at

location _ _ _ _ _ _ _ _ has confirmed that the safety precautions set out in

Para 1.2 are no longer required and hence the RISSP is cancelled.

Signature: _ _ _ _ _ _ _ _ _ __
Name:
-~-~~~~---~
(Implementing Safety Co-ordi nator)
Date _ _ _ _ _ _ __
Time: _ _ _ _ _ _ __

Date and Time of Re-energizing of Apparatus _ _ _ _ _ _ _ _ _ __

78
OC-9

\ft:/
GRID CODE

OPERATION CODE No.1 0

PLANT IDENTIFICATION

CONTENTS

Sr. No. Subject Page No.

OC 10.1 INTRODUCTION, OBJECTIVE & SCOPE OC10-80

OC 10.2. EXISTING SITES OC10-80

OC 10.3 MODIFICATIONS TO SITES OC10-80

OC 10.4 OVERRIDING PRINCIPLE OC1O-81


GRID CODE

OPERATION CODE No.1 0

PLANT IDENTIFICATION

OC 10.1 INTRODUCTION, OBJECTIVE & SCOPE

OC 10.1.1 Operation Code No. 10 sets out the requirements for the numbering of
HV Apparatus at Sites where the System Operator and a distribution
company, transmission-connected consumer or Generator are
responsible for the Operation and maintenance of HV Apparatus. The
sub-code applies to all Sites where there is a Transmission Connection
Point.

OC 10.1.2 The numbering and nomenclature standards to be used for HV


Apparatus for each Site where more than one User has an operational
interest shall be defined by the System Operator. The System Operator
shall apply a common standard to all such Sites that are connected to
the System. The numbering to be used at each such location shall be
confirmed on the Operation Diagram and in the Connection Agreement
for each such Site. The adoption of a common numbering and
nomenclature standard shall reduce the risk of human error when
instructing operations on the system.

OC 10.2 EXISTING SITES

OC 102.1 The numbering and nomenclature at all Sites shall comply with NTDC
standards by the date of Transfer. Users of Sites are responsible to
ensure that the HV Apparatus conforms to NTDC standards.

OC 10.2.2 The System Operator shall provide Users with details of its numbering
and nomenclature standards on request.

OC 10.3 MODIFICATIONS TO SITES

OC10.3.1 When modifications are planned to the HV Apparatus at a Site, which


shall involve modifications or additions to the numbering and
nomenclature, at which more than one Code Participant has an
operational interest, the Code Participant instigating the modification
shall give the other Code Part'lcipants atleast six months advance
notice of the proposed changes. The proposed modifications to the HV
Apparatus and numbering and nomenclature shall be shown on a draft

i
Operation Diagram and included in a draft Connection Agreement for
the Site. Agreement to the proposed changes to the numbering and
nomenclature shall be agreed in writing within one month of receipt of
the notification of change.

?O'-N ER RtGu.
~G ~
(j 1:>
--------------------------~8~0------------------~~~~~D ~

OC-l0
GRID CODE

OC 10.4 OVERRIDING PRINCIPLE

OC 10.4.1 The numbering and nomenclature used at a Site must be clear and
unambiguous. No alterations to the HV Apparatus and its numbering
and nomenclature that would result in confusion relating to the identity
of the HV Apparatus shall be permitted.

81
OC-10

~
GRID CODE

OPERATION CODE No. 11

SYSTEM TESTS

CONTENTS

Sr. No. Subject Page No.

OC 11 .1 INTRODUCTION, OBJECTIVE & SCOPE OC11-83

OC 11.2. NOTIFICATION OC11-84

OC 11.3 TEST CO-ORDINATOR AND TEST PANELS OC11-84

OC 11.4 THE TESTS AND FOLLOW UP ACTION


GRID CODE

OPERATION CODE NO. 11

SYSTEM TESTS

OC 11.1 INTRODUCTION, OBJECTIVE & SCOPE

OC11.1.1 Operating Code No. 11 details the procedure for carrying out system
tests which involve creation of Unusual, extreme or abnormal system
conditions on the Total System, and excludes commissioning or re-
commissioning tests, which are carried out on a small defined part of
the System. The sub-code covers the System Operator, Transmission-
connected Consumers, Operators of Power Plants, distribution
companies and the Operators of Externally-connected
Parties/Consumers. A system test proposed by a User that shall have
no effect on the Transmission System of NTDC is not subject to this
sub-COde. A system test proposed by the System Operator shall
always to subject to this sub-code.

OC 11.1.2 The purpose of this sub-code is to ensure that the safety of the general
public and the personnel of the Users is not jeopardised and that the
risk to power supplies and facilities of the NTDC and Users, and the
integrity and security of the system are maintained at the highest levels
possible under such specified conditions.

OC 11.1.3 Tests for distribution company and transmission-connected Consumers


facilities

The System Operator shall test distribution company's equipment


including 132 kV facilities and protective relaying system for
compliance with the Connection Code at the Point of Connection. Test
shall include the following:

(a) Verification of equipment ratings at the substation;

(b) Calibration of under-frequency relay used for load shedding;

(c) Operation of circuit breakers, switches and controls;

(d) Verification of relay co-ordination and settings; and

(e) Calibration of electrical transducers used for measurements

OC-11
GRID CODE

OC 11.2 NOTIFICATION

OC 11.2.1 When a User has decided that it needs to perform a system test, it
shall issue a proposal notice to the System Operator detailing the
nature, extent and purpose and the plant and or apparatus involved.
The proposal notice shall be issued at least 12 months in advance of
the proposed system test. The System Operator shall be satisfied that
it has received sufficient time to give full consideration to the proposal.

OC 11.2.2 Following consideration of the information on the proposal notice, the


System Operator shall determine which other Users are likely to be
affected by tt1e system test and shall, after consultation with the
affected Users appoint a suitably qualified test co-ordinator. The same
actions shall be taken if the proposal notice has been issued by the
System Operator.

OC 11.3 TEST CO-ORDINATOR AND TEST PANELS

OC 11.3.1 A preliminary notice shall be issued to all Users affected by the


proposed system test, and shall include an invitation to nominate
members of a test panel. Time schedules shall be agreed to which are
consistent with the System involved, and the nature of the testing to be
carried out.

OC 11.3.2 The test panel shall consider the test proposal in relation to the
possible safety, economic and operational risks; the possibility of
combining the proposed test with other tests and proposed system
outages. The test panel shall produce a proposal report which shall
include details of the proposed test and the manner in which the
proposed system test shall be undertaken and monitored. The proposal
shall also consider the cost implications and propose the allocation of
costs. The proposal report shall be circulated to all Users affected by
the proposed system test. Objections to the proposal report shall be
considered to determine if the proposal can be modified to
accommodate their objections. In the case of failure to agree, the
matter shall be referred to the Grid Code Review Panel whose decision
shall be binding upon all the concerned Parties.

OC 114 THE TESTS AND FOLLOW UP ACTION

OC 114.1 Following agreement, the test panel shall prepare a test programme,
which shall detail the procedure to be used on the day of the test. If
system conditions on the day of the test are not as envisaged or if after
consideration of other factors such as severe weather the test
co-ordinator may delay, postpone or cancel the system test.

OC 114.2 A final report shall be prepared by the Entity proposing test and
circulated to members of the test panel detailing the tests carried out,
the results and conclusions.

84
OC-11
GRID CODE

OPERATION CODE No. 12

TESTING AND MONITORING

CONTENTS

OC 12.1 INTRODUCTION, OBJECTIVE & SCOPE OC12-86

OC 12.2. MONITORING OC12-87

OC 12.3 PROCEDURE FOR TESTING OC12-88

OC 12.4 DISPUTE RESOLUTION PROCEDURE OC12-91

OC 12.5 BLACK START TESTING OC12-91


GRID CODE

OPERATION CODE NO. 12

TESTING AND MONITORING

[Alilhe references in this sub-code to Balancing Code, and Balancing Mechanism


shall be interpreted later when the Balancing Mechanism is Notified by the Authority]

OC 121 INTRODUCTION, OBJECTIVE & SCOPE

OC 12.1.1 This sub-code details the procedures to be followed by the System


Operator to monitor and assess the validity of any Generator's
generation capability, and frequency declarations. The System
Operator is also reqUired to monitor ancillary services which Users
have agreed to provide under their Agreement with NTDC as and when
requested by the System Operator.

OC 12.1.2 The System Operator is required, subject to system conditions


prevailing on a given day to test any generator to ensure that it
complies with the requirements, specifications and obligations of the
Connection Code (CC), Power Purchase Agreement (PPA) and/or
Power Station Operation & Dispatch Agreement (PSODA) as
applicable, to ensure that they are available and comply with their
notified procedures and related provisions. The System Operator shall
also undertake Black Start Test procedures to ensure satisfactory
operation in the event of an Emergency.

OC 12.1 .3 OC 12 applies to NTDC and to Users:

(a) Generators:

(b) Distribution Companies with Non-Embedded and Embedded


Generations;

(c) NTDC in relation to Consumers directly connected to the NTDC


Transmission System; and

(d) Other distribution licensees having Embedded Generation.

OC 12.2 MONITORING

OC 12.2.1 NTDC is required to monitor the performance of: -

(a) Users compliance with the Scheduling and Dispatch Code;

(b) Users providing the ancillary services they have agreed to


provide; and

(c) Evaluate Generators against their expected input or output


obtained from the final notification

OC 12.2.2 If there are any persistent failures of OC 12.2.1, (a). (b) & (c) by Users,
the System Operator shall notify the User in writing requesting an
explanation of the action, the User shall have to
obligations.

OC-12 86
. '
\'. \ I
GRID CODE

OC 12.2.3 The System Operator and the User shall discuss the proposed action
and endeavour to reach an agreement on the proposed action. If
agreement cannot be reached within 10 working days of notification of
the failure by the System Operator to the User. the System Operator or
the User shall be entitled to require a test as detailed in OC 12.3.

OC 12.3 PROCEDURE FOR TESTING

OC 12.3.1 NTDC may issue an instruction requiring the User to test anyone or
more of the User's Generators to demonstrate its performance subject
to the notification giving the User not less than 48 hours notice to
conduct the test if any of the following apply:

(a) If the Generator is unable to operate within the given parameters


stated in its Power Purchase Agreement (PPA) and/or Power
Station Operation & Dispatch Agreement (PSODA). as
applicable and GSDP Notice such as Input/output performance;

(b) Meet the requirements to operate in the Frequency Sensitive


Mode; and

(c) Meet the reactive power or fast start capability as registered with
the System Operator under Scheduling and Dispatch Code and
Operating Code.

OC 12.3.2 The System Operator instruction detailed in OC 12.3.1 can only be


issued if the User has submitted import and export limits for the
relevant Generator for the operational day current at the time the
System Operator notification is issued. The User is then obliged to
submit to the System Operator import and export limits with a
magnitude greater than zero for that Generator for the time and
duration for the requested test.

OC 12.3.3 The results of the performance of the User's Generator under test shall
be recorded at NPCC Control Centre using voltage and current signals
provided to the System Operator by the User.

OC 12.3.4 If the results are recorded on Site chart recorders are to be used and
representatives appointed and authorised by the System Operator shall
wHness the test.

OC 12.3.5 The test shall be initiated by the issue of instructions under SDC2 for
the Generator submitted by the User for the day of the test.

OC 12.3.6 In the event that the Generator fails to meet the test criteria specified in
the table given below. the User is required to provide the System
Operator with a written explanation of the reasons for failure. If the
System Operator and the User are unable to agree, the System
Operator may require the User to perform are-test.

OC-12 87
The Generator will Pass the Test if the Following Criteria Below is Met

o
()
Parameter to be Grid Code Pass Criteria
tested Reference

Reactive CC Generating Unit will pass the test if it is within ±5% of the capability registered with NTOC
~ ~ Capability under OC 4.
""0 nI
nI0
0"_ The duration of the test will be 60 minutes with System voltage at the Transmission
=< Connection Point being maintained by the Generator by adjustment of Reactive Power on
-<ct>
the remaining Generating Units, if necessary.

Primary. ASA IThe measured response in MW/Hz is within ±5% of the level of response specified in the
Secondary and iAnciliary Services Agreement for that Genset.
High Frequency
G)
Response
Q~~~~~-~---------+-----------------------------------------------------------~ :::0
co
o
<
Governor CC Measurements indicate that the Governor parameters are within the criteria set out o
co ~ Compliance in the appropriate governor standard. (")
::J
~ ~-------------r--------------+_--------------------------------------------------------------------~
o
High SOC 3 The measured response is within the requirements of SOC 3.
o
en Limited m
~ Frequency
ct> Response
3r-------r--------+------------------------------~
Output at CC For variations in System Frequency exceeding 0.1 Hz within a period of less than
Reduced SOC 10 Seconds, the Active Power output is within ±O.2% of the requirements of
System CC xxx when monitored at prevailing external air temperatures of up to 25°C.
Frequency

Fast Test ASA The Fast Start Capability requirements of the Ancillary Services Agreement
or that Genset are met
~'-
,
)-~p,.-L-E-L..L~C.. r---t-------r-------t----------------------------------l

~ a,
...(') Black Start OC 12.5.1 The relevant Generating Unit is Synchronised to the System within two hours
~ .~
... \'. of the Auxiliary Supplies being required to start.
m ~
>"1: ~
~m~ fm+-~L--------------L--------------~--------------------------------------------------------------------~
:x:-<o :.0
o <: ~
~ m ~
=f 0 ~
-< ~<::-
. ;} nT>..'CO}.
The Generator will Pass the Test if the following Criteria is Met

Parameter to be Grid Code Pass Criteria


Tested Reference

Export and OC 12 The Export and Import, OPN, Joint BM Unit Data and Dynamic Parameters
Import Limits, Under test are within 2i'2% of the declared value being tested
QPN, Joint
Generator data
and Dynamic
Parameters

o
'<
~

3mr--------------+--------------;---------------------------------------------------------------------~ G')
(") Synchronisation SDC Synchronisation takes place within ±5 minutes of the time it should have achieved ::u
\J time Synchronisation. o
m
...,
OJ ("')
3 o
CD
r--------------r--------------+---------------------------------------------------------------------~
o
CD
en Run-up Rates OC 12 ~chieves the instructed output and, where applicable, the first and or/second
m
intermediate breakpoints, each within ±3 minutes of the time it should have reached
such output and breakpoints from Synchronisation calculated from the run-up rates
in its Dynamic Parameters.

Run-down OC12 Achieves the instructed output within ±5 minutes of the time, calculated from the
Rates run-down rates in its Dynamic Parameters.

.I" The following conditions will apply to each of the above tests:
{ '--
--~-~l-E-Lf'~:r~The duration of the test will be consistent with and sufficient to measure the relevant expected input or output derived from the Final Physical
~~ ~ ~ Notification Data.
:t: C'
m > -0
> ~~~--------------------------------------------------------------------------------------------------------~
C ~ -
-i[D;;tJrn
:t:-<O ;.0
0<;0
~ ~ !f
~ ~~
~~}..~O~
GRID CODE

OC 12.3.7 If in the opinion of the System Operator the Generator again fails the
re-test, every effort should be made to resolve the mailer. In the event
that a dispute arises between the User and the System Operator, either
Entity may approach the Review Panel for a determination of the
dispute which shall be binding on both Entities.

OC 12.4 DISPUTE RESOLUTION PROCEDURE

OC 12.4.1 If after the procedure described in OC 12.3 it is accepted that a


Generator has failed the test or re-test, this Code Participant or the
User shall within 10 working days submit to the System Operator a
date with a proposal by which the Generator shall be able to comply
with the relevant requirements and its obligations under its Purchase
Agreement (PPA) and/or Power Station Operation & Dispatch
Agreement (PSODA) as applicable, and the Grid Code. The System
Operator should not withhold approval or unreasonably delay in the
approval of the proposal. If the System Operator does not approve the
date and time submitted by the User, the User shall amend such
proposal having regard to ::Iny comments given by the System
Operator and re-submit it for the System Operator's approval.

OC 12.4.2 If the Generator fails the test, the User shall submit revised limits and
other data as may be relevant in the case of a Generator as per
Revised GSDP Notice for the period of time until the Generator can
achieve the Parameters previously registered or demonstrated under
SOC 1 (GSDPs).

OC 12.4.3 When the User advises the System Operator that the Generator is able
to achieve the previously Generation Scheduling and Dispatch
Parameters (GSDPs): the System Operator shall either accept this
information or require the User to re-test the Generator to confirm the
stated capability. The System Operator shall give 48 hours Notice to
the User for a re-test. The test shall be conducted in accordance with
OC 12.3, and the provisions of OC 12.4 shall apply to this further test.

OC 12.5 BLACK START (BS) TESTING

OC 12.5.1 General Requirements

(a) The System Operator may request a Generator with a Black


Start Station to perform a Black Start (BS) Test with the Black
Start Station remaining connected to an alternating current
supply or whilst disconnected from all external alternating
current supplies, in order to demonstrate that the Black Start
Station has Black Start Capability.

(b) If the System Operator requires a Generator with a Black Start


Station to undertake a BS Unit Test, the System Operator shall
not require the test to be conducted on more than one
Generating Unit at the same time, and would not normally R
,\>0'<'1 E. R.€G
______________________________________________-+__nrc¥' ~~

OC-12 90 (j
~
1.>':;0
~ APPROVED ~
~ BY
~\THr=. AUTHORITY
GRID CODf;

expect any other Generating Unit at the Black Start Station to be


directly affected by the Black Start Unit Test.

(c) Normally any Generator shall not be tested more than once in
any year and a Black Start Station test shall not be requested
by the System Operator more frequently than once every two
years.

(d) When the System Operator requests a Generator to perform a


Black Start Test, a minimum notice of seven days shall be given
to the Generator.

OC 12.5.2 Procedure for a Slack Start (SS) Test

OC 12.5.2.1 SS Unit Test

(a) The relevant Generator shall be synchronised and loaded

(b) All auxiliary supply sources in the Black Start plant where the
Generator is located shall be shuidown.

(c) The Generator shall be de-Loaded and de-synchronised, and all


alternating current supplies to its auxiliaries shall be
disconnected.

(d) The auxiliary supplies in (b) shall be re-started and energise the
unit board of the relevant Generator, thereby enabling the
Generator to return to synChronous speed.

(e) The relevant Generator shall be synchronised to the system but


not loaded unless instructed to do so by the System Operator.

OC 12.5.2.2 SS Station Test

(a) All Generators at the Black Start Station other than the
Generator on which the Black Start Test is to be undertaken,
and all auxiliary supplies to the Back Start Station shall be
shutdown.

(b) The relevant Generator shall be synchronised and loaded

(c) The relevant Generator shall be de-Loaded and de-


synchronised.

(d) All external alternating current electrical supplies to the


generator board of the relevant Generator, and to the station
board of the relevant Black Start station shall be disconnected.

(e) The auxiliary supply generator at the Black Start Station shall be
started and shall re-energise either directly or via the station
board, the unit board of the relevant Generator.

OC-12 91

"
GRID CODE

(f) The relevant Generator shall be synchronised to the System but


not loaded unless instructed to do so by the System Operator.
OC 12,5,3 Failure of a Black Start Test

A failure shall be recorded if the Black Start plant fails to demonstrate it


has a Black Start Capability.

oc 12,5.4 In the event of such failure, the Generator must provide the System
Operator with a written report detailing the reasons for the failure within
ten working days of the failed Black Start Test. If a dispute arises
between the System Operator and the Generator, they shall seek to
resolve their differences. In the event that there is no resolution, the
Generator may require the System Operator to permit a further Black
Start Test on 48 hours notice, The relevant test procedures, as set out
in OC 12.5.2.1 and OC12.5.2.2 shall apply to the re-test.

OC 12,5,5 If the Black Start plant fails the re-test and a dispute arises between the
Generator and the System Operator, either Code Participant may use
the disputes resolution procedure as provided through the Review
Panel. The findings of the dispute resolution procedure shall be binding
on both Code Participants.

OC 12,5,6 If, a Black Start station fails the Black Start Test and subsequent re-
test, the Generator shall, within fourteen working days, advise the
System Operator in writing of the date and time by which the Generator
shall restore the Black Start Capability to that Black Start station. The
System Operator shall not unreasonably withhold approval to the
Generator's proposal. Should NTDC not approve the Generator's
proposal, the Generator shall re-submit the proposals by taking into
account the System Operator's comments.

OC 12,5.7 When the Generator advises the System Operator that the Black Start
station has been restored to Black Start Capability status, the System
Operator shall either accept this information or require a further Black
Start Test to demonstrate the validity of the Generator's information.
Any further test shall be in accordance with test procedures detailed in
OC 12.5.2,1 and OC 12.5.2.2

Hi Hi ~~ ~~ End of OC 12 IH H~ H~ H~ H~

OC-12 92
GRID CODE

PLANNING CODE

CONTENTS

Sr. No. Subject Page No.


PC 1 INTRODUCTION, OBJECTIVE & SCOPE PC-94
PC2 PLANNING CRITERIA PC-95
PC3 RESPONSIBILITY PC-102
PC4 FORECASTS AND GENERATION EXPANSION PLAN PC-102
PC 5 PLANNING DATA PC-104

Appendix A Part-1
General
STANDARD PLANNING DATA PC-106
Appendix A Part-2
STANDARD PLANNING DATA
GENERATING UNIT DATA PC-112
Appendix A Part-3
STANDARD PLANNING DATA
DEMAND AND ACTIVE ENERGY DATA PC-114
Appendix B
SINGLE LINE DIAGRAM PC-116

PC
GRID CODE

PLANNING CODE

PC 1 INTRODUCTION, OBJECTIVE & SCOPE

The Planning Code provides requirements for the planning process by


which the objectives of system security, adequacy, reliability, and
performance shall be satisfied. Some of the objectives are:

(a) To specify the responsibilities of NTDC and other Users in the


planning and development of the national transmission
grid/NTDC Transmission System;

(b) To specify the planning procedures and technical studies that


shall ensure the safety, security, reliability, and stability of the
national transmission grid;

(c) To specify the planning data required from Users seeking new
Connection or a modification in their existing Connection to the
NTDC Network;

(d) To specify the data requirements to be used by NTDC in


planning the development of the NTDC's Transmission System.

The Planning Code provides the basis for system reliability goals that
are to be achieved and maintained by NTDC and the System Operator.
The reliability goals need to be coordinated with policy objectives for
the electric power sector as well as with short-term and long-term
system planning objectives.

The planning process is based on a philosophy that conforms to the


regulatory process, allows for competition, and is coordinated with
operational considerations. Requisite information inputs to the planning
process from Code Participants shall be provided.

The objective of the Code is to promote NTDC/User interaction for any


proposed development of the NTDC or User Systems. It also provides
for an exchange of planning information between NTDC and Users and
specifies the Licence Standards that the NTDC shall adopt in planning
and developing its Transmission System.

PC
GRID CODE

specifies the information to be exchanged between NTDC and the


Users.
The reinforcement and/or extension of the NTDC Transmission System
may be necessary for several reasons, but not be limited to the
following:

(a) a development on a User System already connected to the


NTDC Transmission System;

(b) the construction of a new Transmission Connection Point or the


modification of an existing Transmission Connection Point;

(c) the cumulative effects of developments referred to in (a) and (b).

To accommodate User System developments, reinforcements or


extensions of the NTDC Transmission System may involve the
following activities:

(a) At one or more Transmission Connection Points;

(b) On transmission lines which join Transmission Connection


Points;

(c) On remote transmission lines, which may not be directly


connected to the affected Transmission Connection Points.

PC 1.1 The scope of this Code applies to all NTDC Transmission System
Users, i.e.

(a) NTDC;

(b) Generators;

(c) DISCOs;

(d) Transmission-connected Consumers; and

(e) Externally Connected Consumers/Parties.

PC 2 PLANNING CRITERIA

This sub-code provides system reliability/planning criteria, standards


and guidelines to be followed in the definition of reinforcemenV
up-gradation/expansion projects for the 500 kV and 220 kV NTDC
Transmission System as well as for portions of the 132 kV DISCO sub-

PC 95
GRID CODE

transmission systems. The objectives and aims of the planning


function are stated in terms of steady state, and dynamic performance
of the NTDC Transmission System.

PC 21 Contingency Conditions

Planning for steady-state, shall be based on (N-O) and (N-1)


contingency conditions. In the (N-O) state, all transmission system
components are expected to be in-service fQc the base case model.

There shall be two base case scenarios for each year; Summer-peak
(High-Water) and Winter-peak (LOW-Water). In each case, the (N-O)
condition shall be adjusted to account for planned and scheduled
generation and transmission facility maintenance Outages. As required
by maintenance scheduling requirements, NTDC shall prepare several
(N-O) base cases to account for Summer and Winter base cases in a
given year.

Single contingency cases (N-1) shall be studied for each base case
scenario; an (N-1) contingency shall be defined as the unplanned
Forced Outage of any single transmission and grid system facility,
plant, or apparatus. For planning studies, a single transmission facility
Outage shall be defined to be anyone of the following:

(a) Outage of a 500/220/132 kV transmission circuit under the


Operational Control of NTDC;

(b) Outage of a Generator's step-up transformer;

(c) Outage of a Grid station transformer;

(d) Outage of a SUb-station 500 kV or 220 kV bus; and

(e) Outage of a 500 kV shunt reactor

Planning for dynamic performance (transient instability) shall be based


on the occurrence of each of the following contingencies:

(a) Permanent three-phase fault on any 500/220 kV line, and


subsequent outage of an associated transmission line.

(b) Failure of a circuit breaker to clear a fault ("Stuck Breaker"


condition) in 5 cycles, with back up clearing in 9 cycles after fault
initiation.

PC 2.2 Steady State

Adequacy evaluation of planning studies for steady-state system


performance shall be based on equipment loading, congestion
management, fault levels and voltage regulation. Steady-state planning

--P-C-------------------------9-6--------------------~--vn~lr~~
--- ~~~
filO't-JE.~ Rfc

::J ~-<.
~/ %>.rHEAu~~ORITY t
UJ
APPROVED
GRID CODE

studies for steady state load flow studies shall be deemed acceptable if
they do not result in any voltage violations or overloads based on pre-
determined loading limits for Normal (N-O) and Emergency (N-1)
contingency conditions.

PC 2.2.1 Component Loading

Loading levels for current carrying component (everywhere on the


NTDC network) shall be determined in steady-state load flow studies.
This includes transmission circuits, transformers, substation bus, circuit
breakers, disconnect switches and auxiliary equipment that contributes
to the reliability of the system. For the purpose of evaluating load flow
studies the following loading criteria shall be observed:

(a) Under normal operating conditions (N-O condition), all


transmission lines and transformers shall be loaded below their
Normal Continuous Maximum Ratings;

(b) Under contingency conditions (N-1), all transmission lines and


transformers shall be loaded below their Emergency Ratings;
and

(c) Within 15 minutes following the change from the (N-D) state to
the (N-1) state, after Spinning Reserve (ten minute reserve) has
been deployed, the System shall have the capability to first
change generation d'lspatch and second shed load to reduce
any transmission line and transformer loading from the
Emergency Rating to below the Normal Continuous Maximum
Ratings.
In some cases, line loading limits may be adjusted for unique
geographical regions. All loading limits shall be determined in
accordance with applicable IEC Standards and updated from time to
time as new and revised standards are issued. In the event that an
IEC Standard with necessary scope does not exist, then applicable
standards such as: ANSI, IEEE, JEC, or other internationally
recognized institution may be used. In the event of a dispute as to
wh'lch planning and design Standards are to be used, Review Panel
shall have the final decision.

Transmission circuit loading limits shall be based on the following


conditions:

(a) Thermal 10ad'lng limits of the conductor;

(b) Maximum ambient temperature;

(c) Minimum clearance to ground at mid-span under maximum load;

PC
(d) Allowable over load for 15 minutes; and

97
J
GRID CODE

(e) Transient (power angle) stability and voltage stability limits.

(f) Maximum allowable conductor temperature.

(g) Wind velocity.

Transformer loading limits shall be based on following conditions:

(a) Maximum loading capacity with forced cooling;

(b) Maximum ambient temperature;

(c) Allowable over load for two hours;

(d) Summer (April - October) loading; and

(e) Winter (November - March) loading.

Substation Transformer Capacity Adequacy

The NTDC shall submit an "Annual System Reliability Assessment and


Improvement Report" (ASRAIR) to NEPRA on or before April 15 th of
each year for the next year (including Table 2-1) listing the Total
Installed Transformer Capacity in MVA, Firm Transformer Installed
Capacity, and Estimated Load Demand for the next year for each
500/220 kV, 500/132 kV, and 220/132 kV Substation. For each
substation, the ratio of Estimated Peak Substation Demand to Firm
Transformer Capacity shall be calculated and reported. If the ratio of
Estimated Peak Substation Demand to Firm Sub-station Capacity is
80% (Single Transformer sUb-station) or 100% (more than one
Transformer sub-station) then the NTDC shall include a description of
its plans, together with cost and in-service date, to either add additional
transformer capacity or to shift load from/to other substations. If load is
shifted to another substation then the amount of the shifted load will be

PC 98
GRID CODE

TABLE 2-1
Substation Transformer Capacity Adequacy
Ratio of
Sub-station Number of Transformer Firm Estimated Peak
Name Transformers Voltage Sub-station Peak Substation
and Ratio Capacity (1) Substation Demand to
Total Name (2) Demand Firm
plate (3) Transformer
Capacity
MVA KV/kV MVA MVA %

(a) Firm Sub-station Capacity MVA is the Total Installed


Transformer Capacity less the largest transformer based on its
Nameplate MVA rating;

(b) Transformer MVA loading based on Manufacturer's Nameplate


Rating, and IEC standard 60354 Ed 2.0, 1991, Loading Guide
for Oil-Immersed Power Transformers; and

(c) In the case of single transformer sub-station, the Firm Capacity


of the SUb-station is 80% of Transformer's Nameplate Rating.

Elimination of Congestion

Each year NTDC shall, based on the information regarding all


congestion conditions that existed for the past year, carry out studies to
find solutions to resolve the congestion problems. Steady-state load
flow studies shall be made to precisely llefine the congestion
conditions. The results of such studies shall be submitted to NEPRA on
an ann ual basis.

NTDC shall make load flow studies and develop improvement plans to
eliminate the congestions that existed in the past year. The description
of the plan shall include estimated cost and required commissioning
date for the improvement plan.

PC
GRID CODE

Transmission Circuit Availability

Evaluation of the reliability of transmission system components (such


as transmission lines, transformers, circuit breakers etc.) shall be
determined according to the Outage statistics. Outage statistics shall
be based on two measures (1) Frequency of Failure, and (2) Time
Duration to make repairs and return the line to service. These
measures are to be calculated on an annual basis as described in the
Operating Sub Code of the Grid Code and the relevant requirements of
the NEPRA Transmission Performance Standards Rules shall be
followed in this regard.

PC 22.2 Dynamic System Performance

NTDC shall make transient stability studies for the existing as well as
future System as planned for the following most likely fault conditions.
Transient stability studies shall be prepared for Summer (High Water)
and Winter peak (Low Water) load conditions for each of the next five
years following the Calendar Year.

System st;lbility must be maintained following the disturbances listed


below:

(a) Permanent three-phase faults on any primary transmission line


and associated components. It is assumed that a fault will be
cleared by circuit breaker action in 5 cycles 1;

(b) Failure of a circuit breaker to clear a fault ("Stuck Breaker"


condition) in 5 cycles, with back up clearing in 9 cycles after fault
initiationJ2) ; and

If the System is found to be unstable, then mitigation measures shall


be identified and incorporated into the system improvement plans for
future years.

PC 2.2.3 Voltage

For the purpose of evaluating system planning steady-state load flow


study results, the following Voltage shall be used:

(a) Under normal operating conditions (N-O condition) all bus


voltages shall be within the bandwidth of (+5%) to (-5%) of
Nominal System Voltage; and

(b) Under contingency conditions (N-1) all bus voltages shall be


within the bandwidth of.!. 10% of Nominal System Voltage.

1 Timings of 5 and 9 cycles are based on the sum of relay action, communication time, and circuit
bre3ker operating time. Timings may be re'/ised to reflect technology improvements. _ _~

PC 100
GRID CODE

PC 2.2.4 Short Circuit (Fault Levels)

Short circuit calculations shall be prepared for each study year, and
adequacy of fault interrupting capability and short circuit withstand
capacity shall be ensured.

PC 3 RESPONSIBILITY

All Code Participants are responsible for participation in the short-term


and long-term planning process. The primary responsibility for the
planning process is assigned to the Planning Department of NTDC.
Other Code Participants include; distribution companies, KESC,
GENCOs, Hydel Generators, IPPs, other Generators under Central
Dispatch, Externally-connected Parties and Consumers, and
Transmission-connected Consumers.

The annual reporting requirements regarding its System Reliability


Assessment and Improvement are included in the NERPA
Transmission Performance Standards Rules.

PC 4 FORECASTS AND GENERATION EXPANSION PLAN

Each year, the NTDC shall prepare and deliver to NEPRA a Ten-Year
"Indicative Generation Capacity Expansion Plan (IGCEP)" covering 0-
10 Year timeframe. NTDC shall provide this IGCEP or NTDC Plan.

The "Indicative Generation Capacity Plan" (NTDC Plan) shall identify


new capacity requirements by capacity, location and commissioning
date. This capacity expansion plan shall satisfy Loss of Load
Probability2 criteria, load growth forecast, operating reserve
requirements, and other related capacity planning criteria. The plan
shall be subject to review and approval by NEPRA.

NTDC shall establish and maintain a marketing group whose function


shall be to track and identify potential new industrial, commercial and
government projects that can result in the need to construct new
generation, substations and transmission facilities.

Information about potential new generating projects and new loads


shall be directed to NTDC for use in preparation of load forecasts and
transmission expansion plans.

PC 4.1 Generation Capacity Additions

The "Indicative Generation Capacity Expansion Plan" (NTDC Plan)


shall take into account capacity requirements and upgrades as
reported by generation owners. The "NTDC Plan" shall include
generation needed to meet estimated load as well as required

1 LOLP of 1% per NTDC Master Planning Document.

PC 10 1
GRID CODE

reserves. The NTDC Plan shall produce a year-by-year list of projects


and specify capacity, and location, and take into account capacity
retirements and major maintenance Outage periods.

The NTDC Plan shall be based on a twenty-year Load Demand and


Energy Forecast and shall be prepared according to a Loss of Load
Probability (LOLP) methodology established under this Grid Code, and
NEPRA Transmission Performance Standards Rules.

An initial target value of LOLP, not to exceed 1% per Year, shall be


used. NEPRA shall review and revise the LOLP value from time to
time.

The "NTDC Plan" shall be used as an input to the preparation of


NTDC's Transmission System Expansion Plan (TSEP).

The NTDC shall be submitted to NEPRA on or before April 15 for the


next financial year.

PC 4.2 Procedures for Transmission System Expansion

NTDC shall establish a planning process that leads to the


recommendation of specific transmission system reinforcements,
upgrading, and expansion projects. Specific projects shall be defined
according to established planning criteria contained in this Grid Code,
and in response to load growth, and the NTDC Plan.

The TSEP shall be presented to NEPRA each year as part of the


"Annual System Reliability Assessment and Improvement Report", and
shall be in terms of specific projects. The projects shall be identified in
terms of: new transmission lines, new transmission circuits, new grid
stations, new transformer installations, sub station bus expansions,
voltage control projects, circuit breaker upgrading projects, elimination
of congestion bottlenecks, and system stability improvement projects.

NTDC shall participate in and coordinate its system planning efforts


with the 132 kV planning efforts to be carried out by the distribution
companies. In this regard, it is to be expected that there will be some
jOint projects until the planning and development of the 220 kV and 500
kV System makes the NTDC System independent of the distribution
company 132 kV system planning process.

NTDC shall submit to NEPRA for information its proposed plan for its
planning process on or before the year of enforcement of the Grid
Code. The Plan shall as a minimum address the following points:

Load Forecasting

Three levels of load forecasts should be employed for a time horizon of


at least next twenty years for the long-term. The three levels are (1)

PC 102
GRID CODE

High Growth; (2) Medium Growth and (3) Low Growth projections.
Factors that are to be taken into account when preparing the load
forecasts are: economic activity, population trends, industrialization,
weather, distribution companies forecasts, demand side management,
load shedding etc.

Project Identification

A Detailed "Transmission Investment Plan" shall be prepared that is


based on the "NTDC Twenty-Year Load Forecast", 'Indicative
Generation Capacity Expansion Plan (IGCEP or NT DC Plan)", and the
Transmission System Expansion Plan (TSEP)" based on ASRAI. The
Plan shall be broken into several time periods. The Transmission Plan
may be prepared for next one, three, five and ten years into the future.

PC 5 PLANNING DATA

Data requirements for planning of future works, which would include


the development of new facilities, reinforcements, up-ratings,
extensions and augmentation of the existing facilities, and planning for
the new Connection Points shall be provided to NTDC each year by all
51
the Users/Code Participants on 1 of January each year.

Demand, Active and Reactive Energy Data

Each Code ParticipanUUser directly connected to the NTDC


Transmission System shall provide to NTDC its Load Demand data,
historiC, current and projected. The required data shall be provided for
each sub station in each UserfCode Participant's System as applicable.

Each UserfCode Participant shall provide forecast data for power


demand, Active and Reactive energy and demand requirements on its
System. The User/Code Participant shall separately indicate its non-
BPC Load Demand on sector-wise basis. BPC's Demand, and the
Load Demand of the Second-tier Users of their network, if any.

The Code Participants shall provide the following Load Curves:

(a) Monthly Load Curves of daily peaks; and

(b) Yearly load of monthly peaks

The User/Code Participants shall provide the expected monthly peak


Load Demand for each of their Connection Points with the NTDC
System.

General Demand Data

(a)

PC 103
GRID CODE

Users shall supply all such data individually through quickest


means of communication; and

(b) The following information shall be supplied upon request by the


NTDC;

(i) details of any individual loads which have characteristics


significantly different from the typical categories of
domestic, commercial, industrial, and agricultural loads
supplied;

(ii) The sensitivity of the Load Demand (Active and Reactive


Power) to variations in voltage and Frequency on the
NTDC Transmission System at the time of the peak Load
Demand (Active Power); and

(iii) Details of any traction loads, arc furnace, welder etc.

(c) User Technical Data

Technical parameters of User Apparatus and Plant connected to


the NTDC Transmission System, including the submission of
updated technical parameters whenever there is a change of
User Apparatus or Plant shall be submitted as and when
required.

(d) NTDC Technical and Network Operator's Data

NTDC shall have network data relevant to short circuit current


contributions.

NTDC is required to make available to Users the network


Operator's Data relevant to short circuit current contributions
listed in Part 3 of Appendix A (PCA.2.2.10) and Part 2 of
Appendix A. NTDC is required to make this technical data
available in week 45 of each year to cover for the following
NTDC's Calendar Year.

Information to be provided to NTDC by the Users and Network


Operators or Vice Versa for planning purposes is covered in Appendix
A and B of this sub-code. ~

PC 104

"()
\~/
'. ' \.
GRID CODE

Appendix A

PART·1

STANDARD PLANNING DATA

PC.A.1 GENERAL

All Users connected directly through existing Connection Points to the


NTDC Transmission System or seeking a direct Connection shall
provide NTDC data on their Systems which relates to the Connection
Site which may have an effect on the performance of NTDC
Transmission System.

PCA2 USER'S SYSTEM DATA

PCA2.1 User's System Layout

PCAA.2.1.1 Each User shall provide a Single Line Diagram, depicting both its
existing and proposed arrangement(s) of load current carrying
apparatus relating to both existing and proposed Connection Points.

PCA2.1.2 The Single Line Diagram must include all parts of the User System
operating at EHV and those parts of its sub-transmission system at any
NTDC Site. In addition, the Single Line Diagram must include all parts
of the User's sUb-transmission system operating at a voltage 66kV &
above.

At the User's discretion, the Single Line Diagram can also contain
additional details of the User's sub-transmission System not already
included above, and also details of the transformers connecting the
User's sub-transmission system to a lower voltage. With NTDC's
agreement, the Single Line Diagram can also contain information about
the User's System at a voltage below the voltage of the sub-
transmission system.

PC.A.2.1.3 The Single Line Diagram shall also include:

(a) Electrical circuitry identifying overhead lines, underground


cables, power transformers reactive compensation equipment
and similar equipment etc.

(b) Name of the sUb-station with operating voltages

(c) Circuit breakers isolators, current transformers, potential


transformers, protection data.

1
PC 105
GRID CODE

PC A2.2.4 For each circuit shown on the Single Line Diagram, the User shall
provide the following circuit parameters details relating to that part of its
system:

Circuit Parameters

(a) Rated voltage (kV)

(b) Operating voltage (kV)

(c) Line Length (km)

(d) Conductor Name

(e) Type of Tower

(f) Positive phase sequence reactance

(g) Positive phase sequence resistance

(h) Positive phase sequence susceptance

(i) Zero phase sequence reactance

U) Zero phase sequence resistance

(k) Zero phase sequence susceptance

PC.A 2.2.5 For each transformer shown on the Single Line Diagram, the User shall
provide the following details:

(a) Rated MVA

(b) Voltage Ratio

(c) Winding arrangement

(d) Positive sequence reactance for all windings

(e) Positive sequence resistance for all windings

( f) Zero sequence reactance for all windings

PCA2.2.6 In addition, for all interconnecting transformers between the User's


EHV Voltage System and the User's Sub-transmission System the
User shall supply the following information:-

(a) Earthing system details i.e. direct, resistance


impedance (if not directly earthed).

PC 106
GRID CODE

(b) Tap changer range

(c) Tap change step size

(d) Tap changer type

PC.A.2.2.7 User shall supply the following information about the User's equipment
installed at a Connection Site which is owned, operated or managed by
NTDC: -

(a) Switchgear: User shall provide the following parameters for the
circuit breakers.

(i) Rated Voltage (kV)

(ii) Operating Voltage (kV)

(iii) Rated 3-phase rms short-circuit breaking curren!, (kA)

(iv) Rated 1-phase rms short-circuit breaking curren!, (kA)

(v) Rated 3-phase peak short-circuit making current, (kA)

(vi) Rated 1-phase peak short-circuit making curren!, (kA)

(vii) Rated rms continuous current (A)

(viii) DC time constant applied at testing of asymmetrical


breaking abilities (Secs.)

(b) Substation Infrastructure: User shall provide the following


parameters for the installed electrical equipment.

(i) Rated 3-phase rms short-circuit withstand current, (kA)

(ii) Rated 1-phase rms short circuit withstand current, (kA)

(iii) Rated 3-phase short-circuit peak withstand current, (kA)

(iv) Rated 1-phase short-circuit peak withstand current, (kA)

(v) Rated duration of short circuit withstand (Sees)

(vi) Rated rms continuous current (A)

(c)
Detailed short circuit data for single-point or multi-point connection
sites.

PC 107
GRID CODE

PC.A2.2.B Lumped System Susceptance

For all parts of the User's Sub-transmission System which are not
included in the Single Line Diagram provided under PC.A.2.1.1, each
User shall provide the equivalent lumped shunt susceptance at Nom'lnal
frequency.

PC.A2.2.9 Reactive Compensation Equipment

For all independently switched reactive compensation equipment,


including that shown on the Single Line Diagram, not owned by NTDC
and connected to the User's System at 132kV and above, other than
power factor correction equipment associated directly with User's Plant
and Apparatus, the User shall supply the following information is required.

(a) Type of equipment (e.g. fixed or variable);

(b) Capacitance and/or inductive rating or its operating range in Mvar;

(c) Details of any automatic control logic to enable operating


characteristics to be determined;

(d) The Point of Connedlon to the User's system in terms of electrical


location and system voltage; and

(e) Voltage assessment stUdies of the User system.

PC.A2.2.10 Short Circuit Contribution to NTDC Transmission System

General

(a) To allow NTDC .to calculate fault currents, each User is required to
provide data and short circuit analysis of its system; calculated in
accordance with good industry practice, as set out in the following
paragraphs.
(b) The data should be provided for the User's system with all
Generating Units synchronized to the User's System. The User
must ensure that the pre-fault network conditions reflect a credible
system operating arrangement.

(c) The list of data items required, in whole or part. under the following
provisions. Each of the relevant following provisions identifies
which data items in the list are required for the situation with which
that provision deals.

The fault current in sub-paragraphs (a) and (b) of the data list
should be based on an ac load flow that takes into account any
pre-fault current flow across the Point of Connection being
considered. Measurements made under appropriate system
conditions may be used by the User to obtain the relevant data. ~__
ool/'J ER R~G
---------------------------------------------r--~~~~ ~~
PC 108 1:>
APPROVED ~
GRID CODE

(d) NTDC may at any time, in writing, specifically request for data to
be provided for any alternative system condition, for example
minimum plant, and the User will insofar as such request is
reasonable, provide the information as soon as reasonably
practicable following the request.

PC.A.2.2 .11 Generator Data

For each Generating Unit with one or more associated Station


Transformers, the Generator is required to provide values for the
contribution of the power plant auxiliaries (including auxiliary gas turbines
or auxiliary diesel engines) to the fault current flowing through the Station
Transformer(s).

(a) Root mean square of the symmetrical three-phase short circuit


current in feed at the instant of fault:

(b) Root means square of the symmetrical three-phase short circuit


after the sub-transient fault current contribution has substantially
decayed;

(c) If the associated generating unit step-up-transformer can supply


zero phase sequence current from the generating unit side to the
NT DC Transmission System;

(d) If the value is not 1.0 p.u;

(e) Root mean square of the pre-fault voltage at which the maximum
fault currents were calculated.

PC.A.2.2.12 If the Power Plant has separate Station Transformers, data should be
provided for the fault current contribution from each transformer at its high
voltage terminals, assuming a fault at that location, as follows: -

Data for the fault in feeds through both Step-up Transformers and
Stations Transformers shall be provided for the normal running
arrangement when the maximum number of Generating Units in the
Power Station are synchronized to the System.

Data Items

(a) The following is the list of data utilized in this part of the Planning
Code.

(i) Root mean square of the symmetrical three-phase short


circuit current in feed at the instant of fault;

PC 109
GRID CODE

(ii) Root mean square of the symmetrical three-phase short


circuit after the sub-transient fault current contribution has
substantially decayed;

(iii) The zero sequence source resistance and reactance values


of the User's System as seen from the node on the Single
Line Diagram provided;

(iv) Root mean square of the pre-fault voltage at which the


maximum fault currents were calculated;

(v) The positive sequence X/R ratio at the instant of fault; and

(vi) The negative sequence resistance and reactance values of


the User's System seen from the node on the Single Line
Diagram

PC 110
GRID CODE

Appendix A

PART·2

STANDARD PLANNING DATA

PCA3 GENERATING UNIT DATA

PCA3.1 Directly Connected Generators

Each Generator shall provide the following data to NTDC.

(a) Registered Capacity (MW);

(b) Output usable (MW) on a monthly basis;

(c) System constrained capacity (MW);

(d) Minimum Generation (MW);

(e) MW obtained from Generating Units in excess of Registered


Capacity;

(f) Generator Performance Chart at the Generating Unit stator


terminals; and

(g) Expected running regime(s) at each Power Plant and type of


Generating Unit, e.g. Steam Unit, Gas Turbine Unit, Combined
Cycle Gas Turbine Unit, (specify by type), etc.

(h) Capability V Curve and Saturation Curve for each Generating


Unit.

PC.A.3.2 Rated Parameters Data

NTDC needs the following information for detailed studies: -

(a) For all Generating Units;

(i) Rated MVA

(ii) Rated MW

(iii) Direct-axis and Quadrature-axis sub-transient and


transient reactance.

(iv) Rated Leading and tagging Power Factors.

(v) Synchronous reactances

PC 111

~
GRID CODE

(vi) Leakage reactance.

(vii) Negative and zero sequence reactances.

(viii) Direct-axis and quadrature-axis short circuit time


constraints.

(b) For each synchronous Generating Unit;

(i) Short circuit ratio

(ii) Inertia constant (for whole machine); MW secs/MVA

(c) For each Generating Unit Step-up Transformer;

(i) Rated MVA

(ii) Positive sequence reactance (at max, min, and nominal


tap)

(d) Details of the Exciter category, for example whether it is a


rotating Exciter or a static Exciter.

PC.A33 General Generating Unit Data

(a) Exciter and power system stabilizer data including block diagrams
and parameters such as gain, time constraints etc to be used in
Standards PSS/E format.

(b) Governor data including block diagrams and parameters such as


droop setting time constraints etc. to be used in the standard PSS/E
format.

PC.A3A Network Operator's Data

(a) Forecast Load Demand data, Network Operator's System


Constraints.

PC 112
GRID CODE

Appendix A

Part 3

STANDARD PLANNING DATA

PC.A.4 DEMAND AND ACTIVE ENERGY DATA

PC.A.4.1 Network Operator's Demand (MW) and Active Energy Requirements


(MWHs) - Historic, Current and Forecasted.

PC.A.4.2 Forecasted Daily Demand Profiles (Active Power).

(a) Time of Peak, and Maximum Load Demand (Active Power and
Active Energy Data);

(b) Time of NTDC's System Peak Demand as Notified by NTDC


(Active Power);

(c) Time of Minimum NTDC Demand (Active Power) as Notified by


NTDC; and

(d) Preceding Year's Total NTDC Demand (Active Power) With


Time of System Peak with Respect to Each User's System Peak
Demand (Active Power)

PC.A.4.3 NTDC's Load Forecast (System Peak Demand and Active Energy
Requirements)

(a) NTDC's Notification of its Forecasted Annual System Peak


Demand (Active Power) and Annual Minimum Demand (Active
Power); and

(b) The Total Active Energy of the NTDC in the preceding NTDC
Financial Year alongwith a Forecasted Active Energy
Requirements for the Current Financial Year.

PC.A.4.4 Other User's Load Information

(a) Total User's System Losses; and

(b)

PC
GRID CODE

PCA4.5 Connection Point Demand (Active and Reactive Power and Power
Factors)

PCA4.5.1 Timing of the Peak Demand

(a) Time of the Maximum Demand at the Connection Point as


Determined by the Users; and

(b) Time of NTDC's Peak Demand and Minimum Demand.

PC.A 4.5.2 Aggregate Demand of Two Connection Points Running in Parallel.

PCA4.6 NTDC System Demand and Energy Forecast Incorporating All the Data
Supplied by the Network Users and Network Operators.

PC.A.4.7 Demand Transfer Capability

(a) User's Active and Reactive Power Demand Reflecting a Group


or Groups of Demands for both Planned and Unplanned Outage
Conditions

PC.A.4.B General Demand Data

(a) Details of Individual Loads (sector-wise) along with the Load


Characteristics

PCA4.B.1 NTDC Demand Sensitivity. and Power Quality Impacts

Each User to provide load and its characteristics which can have
adverse impact on the NTDC system vis-a-vis Power Quality.

PC 114
GRID CODE

Appendix B

The Single Line Diagrams showing the Details of the User's Connection to the NTDC
Transmission System are included in the Appendix E of the Connection Code.

HI HI HI HI End of PC ~.~.~.~.~.

PC 115
GRID CODE

CONNECTION CODE

CONTENTS

Sr. No. Subject Page No.

CC1 INTRODUCTION CC-118

CC2 PURPOSE AND AIM CC-118

CC3 PRINCIPLES CC-119

CC4 ESTABLISHING OR MODIFYING CONNECTION CC-119

CC5 DISCONNECTION AND RECONNECTION CC-125

ce6 DATA REQUIREMENTS CC-136

CC7 SERVICE AND NETWORK DESIGN CONDITIONS CC-137

Appendix A
Format, Principles and Procedures to be
used in the Preparation Site Responsibility
Schedules (SRS) CC-139

Appendix A (ATTACHMENT)
Proforma for Site Responsibility
Schedule (SRS) CC-140

Appendix B (PART-I)
Principles and Procedures Relating to
Operation Diagrams CC-141

Appendix B (PART-II)
Principles and Procedures Relating To
Gas Zone Diagrams CC-142

Appendix B (PART-III)
List of all apparatus to be shown on Operation and
Gas zone diagrams CC-143

Appendix C
Minimum Frequency Response Requirements CC-144

Appendix D
Technical Requirements for Low Frequency
Relays for The Automatic Load Shedding

cc
GRID CODE

CONNECTION CODE

CONTENTS

Sr. No. Subject Page No.

Appendix E (Scheme 1)
Interconnection Configuration for Generators CC-146

Appendix E (Scheme 2)
In terconnection Configuration for Generators CC-147

Appendix E (Scheme 2A)


Interconnection Configuration for Generators CC-148

Appendix E (Scheme 3)
Interconnection Configuration for Generators CC-149

Appendix E (Scheme 3A)


Interconnection Configuration for Generators CC-150

Appendix E (Scheme 4)
Interconnection Configuration for Generators CC-151

Annexure F (Figure-1 )
Connection Procedure for New Connection or Modification
Of Existing Connection CC-152

CC ii

~
GRID CODE

CONNECTION CODE
CC 1 INTRODUCTION

NTDC shall in good faith negotiate a Connection Agreement with the


Entity requesting a Connection Agreement with the NTDC
Transmission System in accordance with the provisions of NTDC
Transmission Licence.

The Connection Code specifies the minimum technical design criteria


and connection requirements, which must be complied with by the
Users/Code Participants connected to or seeking connection with the
NTDC bulk power transmission system. It also details the application
procedure to be adopted by the applicants and prospective Code
Participants and the obligations to be fulfilled by Network
Owner/System Operator in the capacity of NTDC to arrange and
provide connections. NTDC shall approve the connection applications.
The procedures contained in this sub-code are applicable to the
following Code Participants:

(a) Generators

(b) Distribution Companies

(c) Transmission-connected Consumers

(d) Any other Person with a User System directly or indirectly


connected to the NTDC Transmission System to which Power
Plants and I or Consumers are connected.

(e) Externally-connected Parties

(f) Externally-connected Consumers

(g) Special Purpose Transmission Licensee (SPTL)

CC 2 PURPOSE AND AIMS

The Connection Code provides the framework for connection to the


NTDC Transmission System, and It has primarily the following aims:

(a) to define the uniform principles and guidelines for establishing a


connection, and use of the network;

(b) to establish a process to be followed by a prospective Code


Participant to establish or modify a connection to NTDC
Transmission System;

(c) to manage and prepare the System and the Point of Connection
for the applicant seeking connection to the NTDC's present and
future Transmission System;

(d) to identify
connection.
technical and financial requirements of the
---
CC 118
APPROVED
\~)
~r
\
BY
GRID CODE

CC 3 PRINCIPLES

The conditions and the procedures covered under this Connection


Code are based on, among others, the following principles and
conditions:

(a) All prospective Users and applicants sl1all have an opportunity


to form a new connection to the network, and have access to the
services provided by the NTDC;

(b) The terms and conditions on which connection to the NTDC's


Transmission System and provision of network services is to be
granted are to be set out in the Connection Agreement between
NTDC and applicants;

(c) A uniform treatment shall be applied by NTDC in identifying


terms and conditions for new connection for each applicant; and

(d) Same principles shall hold while modifying an existing


connection for the Code Participants along with Annual System
Reliability and Assessment Report (ASRA).

CC 4 ESTABLISHING OR MODIFYING CONNECTION

Under the requirements of the Transmission Licence, existing and


proposed Users may assess opportunities for connection to the NTDC
Transmission System in two ways:

(a) By reference to the Annual "NTDC Plan (IGCEP)",


"Transmission Plant (TESP)" and "NTDC Invest"",ent Plan" as
described in the Planning Code (PC) and "NTDC Investment
Plan" prepared by NTDC in accordance with the requirements of
its Transmission Licence.

(b) An Offer by NTDC to enter into a Transmission Service Contract


for Connection to the NTDC Transmission System for the
following:

(i) Existing Transmission Connection Points.

(ii) New Transmission Connection Points.

(iii) Modifications at an existing Transmission Connection


Point.

A Connection Agreement is required for every Transmission


Connection Point for each User at that Connection Point. Therefore,
for any of the above connection options, existing and potential Users
are required to enter into a Connection Agreement or to modify existing
Connection Agreements.

cc 119
GRID CODE

CC4.1 Process and Procedures

The existing or prospective Code Participants seeking new connection


or modifying the existing connection shall comply with the following
process and procedures [also shown in Annexure F (figure 1 )J.

(a) Generators, distribution companies, BPCs and SPTL shall


submit the connection application to NTDC if connecting directly
to the NTDC's Transmission System. Whereas, Generators and
BPC connecting indirectly shall submit their applications to the
respective distribution companies and NTDC simultaneously.
The distribution companies shall evaluate their application for
providing the connection, and shall forward to NTDC/System
Operator after review and approval for registration as a Code
Participant.

CC 4.2 Intention Application

An existing or prospective Code PartiCipant wishing to modify its


existing connection or connect to the Transmission System of NTDC
for the first time shall first prepare an intention application. The
application must indicate:

(a) The type of facilities it intends to establish (generator,


distribution company, BPC, etc.);

(b) Magnitude of Load Demand for the facility and load profile;

(c) Proposed Point of Connection;

(d) Tentative schedule for connection; and

(e) Proposed activity

NT DC shall evaluate the intention application within 30 business days


(preliminary evaluation time) based on the following considerations and
make communication with the applicant.

(a) Evaluate the application and accompanied information;

(b) Check suitability of the proposed Point of Connection;

(c) Linear Load Flow analysis and fault level studies in accordance
with the Planning Code by NTDC on behalf of applicant;

(d) List out functional design requirements, Performance Standards


requirements, and specification; and communicate to the
applicant in the next communication;

CC 120
GRID CODE

(e) Preliminary cost analysis for connection and estimated


connection and registration fee;
(f) Indicate if additional information is required from the applicant;
and,
(g) Consultation of NTDC with other Code Participants to obtain
their input regarding impact on their facilities due to this
connection application.

If the NTDC requires additional information· from the applicant, the


applicant must be advised within 30 business days (preliminary
evaluation time period) to provide such information and the application
for connection must include such information as may be required by
NTDC from time to time. If NTDC does not require such information,
the applicant must be offered within the preliminary evaluation time
period formally to apply for connection to the network.

In case the applicant has been requested to provide additional


information, it must provide such information within 10 business days
after receipt of request from NTDC.

The NTDC shall provide the information/data related to its


Transmission System to applicant, which should help the applicant
prepare its application. The required information is listed, but not
limited to, as follows:

(a) A list of the technical data as discussed in CC 5.4 and CC 6 to


be included with the application for connection which may vary
depending on the connection requirements; and the type, rating
and location of the facility to be connected. Required technical
data are listed in CC 5.4 and CC 6 of this Connection Code.

(b) The preliminary estimate for connection fee and registration fee.
Fees shall be determined and shall be payable on submission of
application for connection, and shall cover the following:

(i) Reasonable costs of all works anticipated to arise from


investigating the application to connect and preparing the
associated offer to connect. This should include
additional capital cost related to the new connection, and
to make the connecting transmission system at par with
the system before the connection.

(ii) If one or more Code Participants are already connected


to the proposed Point of Connection, the new Connection
may affect quality of supply to other Code Participants.
The cost required to mitigate such effects shall be
estimated by the NTDC and the applicant shall pay this

CC 121

W
GRID CODE

cost at time of submission of its application. The cost


shall be paid at the time of issuance of demand note.
(iii) If the applicant wishes to be connected to the NTDC
Transmission System, the connection shall be of in-out
arrangement. If the transmission line is loaded near its
operating limits and expected to affect the quality of
supply of the bulk power system, the applicant shall bear
the full cost of upgrading the connected section of
transmission line to which the applicant wishes to make
the connection to. The cost shall be paid at the time of
issuance of demand note.

NTDC shall use its reasonable endeavor to advise the applicant of all
risks and obligations in respect of the proposed connection associated
with planning and compliance with environmental laws of the
Environmental Protection Agency (EPA) of Pakistan not contained in
this Code

The costs of assets (these assets do not include the existing assets of
Transmission Connection Points) at the Point of Connection including
material, civil works, cost of land and other ancillary costs shall be
borne by the applicant. However, the NTDC shall provide a preliminary
cost estimate for the new connection.

CC 4.3 Application for Connection or Modification

On receipt of "Offer for Connection" from NTDC, the applicant must


submit the formal application within 30 business days from the date of
offer for connection. The application must accompany the following
information for evaluation of NTDC.

(a) Technical and commercial feasibility report;

(b) Detailed design of the facility that the applicant intends to install;

(c) A final committed implementation schedule showing proposed


milestones for construction and commissioning of the applicant's
facilities;

(d) Fees for registration and connection to the network;

(e) Details of the protection arrangements and relay settings;

(f) Copies of all safety rules and local safety instructions applicable
at applicant's Sites; and

(g) Power quality monitoring mechanism

If the NT DC considers that the applicant's proposed connection may


possibly adversely impact the networks of other Code Participants or

CC 122
A?PRO'JED
B'f L
." ~ORIi'f:;-t
GRID CODE

Users, the affected Code Participants and Users shall also be invited to
evaluate the impacts and negotiate an agreement with the applicant.

The applicant shall pay registration and connection fees to the NTDC;
and the remaining information and data required should be submitted
to NTDC as soon as possible.

(Note: If the applicant is seeking connection to a distribution company,


the distribution company shall carryout preliminary evaluation of the
application and if the application is in line with the policies and
technical criteria as outlined in the Grid Code and Distribution Code, it
shall send its concurrence to NTDC to allow Connection with its
System. The NTDC shall evaluate the application with reference to its
obligations under the Transmission Licence and process the
application of the applicant who is seeking connection to the
distribution company's system).

If the applicant wants to have multiple Points of Connections to the


NTDC Transmission System, it should include all the Point of
Connections in the same application; however, the term and conditions
for each Point of Connection may vary in accordance with the
conditions prevailing at each Point of Connection.

NTDC shall evaluate this application and its contents within


30 business days (final evaluation time period), and then imite the
applicant to have negotiations for a Connection Agreement.

CC4.4 CONNECTION AGREEMENTS

All the information forming basis of terms and conditions of the


Connection Agreement for "Connection and Use-of-System" must be
supplied by the applicant to NTDC prior to completion date of the
Agreement. Such information as listed below is referenced here for
guidance but not limited to: -

(a) updated Planning Data as specified in the Planning Code with


estimated values being confirmed or replaced with validated
actual values and updated Forecast Data such as Load Demand
pursuant to the Planning Code;

(b) details of the protection arrangements and settings referred to in


the relevant Sections of CC 5.4 below;

(c) copies of all safety rules and local safety instructions applicable
at the User's Sites which will be used at the NTDC/User
interface. These instructions must be to the satisfaction of
NTDC as set out in OC 9, CC 5.4 below;

(d) Information to enable NTDC to prepare Site Responsibility


Schedules on the basis set out in the relevant sections of
CC 5.4, and Appendix A of this sub-code;

CC 123
GRID CODE

(e) an Operation Diagram fcr all HV Apparatus on the User side of


the Transmission Connection Point as specified in CC 5.4, and
Appendix B of this sub-code;

(f) the proposed name of the User Site, which shall not be the
same as the name of any NTDC Site, or any other User Site;

(9) written confirmation that the Safety Coordinators acting on


behalf of the User are authorised and competent pursuant to the
requirements of OC 9, and relevant sections of CC 5.4;

(h) a list of Managers who have been duly authorised to sign Site
Responsibility Schedules on behalf of the User;

(i) information to enable NTDC to prepare Site Common Drawings;

U) a list of the telephone numbers for the User's facsimile


machines; and

(k) NTDC shall provide written confirmation to the User that the
Safety Coordinators acting on behalf of NTDC are authorised
and competent pursuant.

On receipt of an "Offer to Connect" to NTDC Transmission System, the


applicant (Other than a Consumer): -

(a) Must apply for a respective NEPRA licence to operate as a


Generator or a distribution company or Special Purpose
Transmission licence (SPTL);

(b) Must register with NTDC to operate as a Code Participant.

(c) Must agree to comply with all the provisions of the Grid Code,
and Distribution Code (if applicable).

(d) Must abide by all related rules and regulations already issued or
to be promulgated in the future by the GOP or the relevant
authorities.

(e) Must agree to abide by all bindings, which are set out by the
environmental agencies.

NTDC shall inform NEPRA that a Connection Agreement has been


entered into between them, and forward to NEPRA relevant technical
details of the proposed plant, apparatus, facilities and connection,
including the proposed metering installation and the terms upon which
a Code Participant is to supply any ancillary services under its
Connection Agreement.

cc 124
GRID CODE

CC 4.5 CONNECTION ARRANGEMENTS FOR GENERATORS

NTDC is required under its licence to process a connection application


or to make an offer to connect for the provision of transmission network
services to the Generator.

The Generator shall follow the same procedure for seeking connection
to the NTDC Transmission System as mentioned in CC 4. However,
as a basis for negotiation for the connection agreement, the
Generators:

(a) must provide to NTDC such information as is reasonably


requested relating to the expected operation of its Generating
Units; and

(b) NTDC must provide to the Generator such information as is


reasonably requested to allow the Generator to fully assess the
commercial significance of the connection arrangements sought
by the Generator.

A Generator may seek its Open Access arrangements at any level of


power transfer capability between zero and the maximum power
injection into the NTDC Transmission System of the Generator'
Registered Capacity.

NTDC shall make arrangements to provide connection to the


Generator to its Transmission System. However, the costs of
establishing the connection at the Point of Connection shall be borne
by the Generator.

The augmentation or the required extensions of the affected


transmission networks to provide appropriate transfer capabilities to
other Code PartiCipants with the new connection in place shall be
carried out by NTDC; and the costs incurred for such works shall be
reflected in the transmission tariff of NTDC.

The Generator shall post a performance bond in the name of NTDC, in


an amount equal to the estimated NTDC cost to construct new facilities
needed for the connection of the Generator. The bond shall be
returned to the Generator upon successful commercial operation of the
Generator's facilities. If the Generator fails to bring its project to
commercial operation, then NTDC shall collect the performance bond.

Other procedures and requirements for intent application, Offer to


connect to the network, preparation of connection application,
evaluation of application and the Connection Agreement shall be
according to the Connection Code of the Grid Code.

CC 125
GRID CODE

CC 5 DISCONNECTION AND RECONNECTION

The following procedures must be adopted for disconnection of any


facility from the NTDC Transmission System.

CC 5.1 Voluntary Disconnection

For the voluntary disconnection of any equipment or the facility, the


Code Participant must give advance notice, as established in the
Connection Agreement, in writing, that it intends to disconnect its
facility from NTDC Transmission System, subject to the procedures set
out in its Connection Agreement.

However, it should be ensured that disconnection and reconnection


procedures are made an integral part of the Connection Agreement.

Before taking any decision for disconnection of the equipment of the


facility, of the Code Participant, NTDC shall ensure that such
disconnection will have no impact on the quality or reliability of supply
or Systems of other Code Participants.

Prior to any disconnection, the NTDC shall inform NEPRA about the
disconnection proposal and its expected impact on the network.

All tt1e costs incurred on disconnection of equipment or facility from the


network will be borne by the Code Participant who is seeking the
discon nection.

CC 5.2 INVOLUNTARY DISCONNECTION

The System Operator/NTDC may disconnect Equipment, Apparatus, or


the Facility of a Code Participant by giving an advance notice in the
case of only as per Connection Agreement if: -

(a) The Code Participant is not operating its facility in accordance


with the Connection Agreement or in accorda nce with the law of
the land or in accordance with the NEPRA licence, and other
applicable documents.

(b) In case of operational emergencies, where transmission system


of NTDC becomes incapable of providing the reqUired services.

(c) In the event of emergencies, the Code Participant's facility must


be disconnected in an orderly manner or as indicated in the
Connection Agreement, such that the security and integrity of
the System is not jeopardized.

In the event of involuntary disconnection, the affected Code Participant


must not bring proceedings against NTDC to seek to recover anYT~_ _
amount for loss or damage incurred due to the disconnection. ,<O'l'IE~ Rccu
<<7
cc 126 1:>
APPROVED .~
GRID CODE

CC 5.3 RECONNECTION OF EQUIPMENT OR FACILITY

The NTDC shall reconnect the Code Participant's facility, equipment,


and apparatus after confirming that:

(a) The Code Participant has rectified all such circumstances, which
were the cause of disconnection; and NTDC has agreed and
reasonably satisfied with the corrected status of the Code
Participant's facility.

(b) NTDC shall charge such cost as indicated in the Connection


Agreement for reconnection of the facility which was
disconnected due to default.

(c) The facilities, which were disconnected due to emergenCies,


must be reconnected as soon as the causes of emergencies
were rectified and NTDC Transmission System has come in
steady-state operational conditions.

CC 5.4 OPERATIONAL OBLIGATIONS OF CODE PARTICIPANTS

All Code Participants must maintain and operate their facilities in


accordance with, but not limited to the following provisions;

(a) Abide by the relevant laws, rules and regulations.

(b) Abide by the obligations under Grid Code and Distribution Code
(if applicable).

(c) Adopt the prudent electric power industry practices and


applicable standards enumerated in other rules, regulations and
guidelines of NEPRA.

(d) Coordinate with NTDC in activities relating to operation,


maintenance and development of the NTDC Transmission
System.

(e) Abide to the conditions set out in the Connection Agreement so


that the Ouality of Supply (OoS), and security of the NTDC's
Transmission System, and Systems of other Code Participants
are not affected.

(f) Utmost care must be observed by the Code Participant in


preparation and submission of technical data and other
information required by the NTDC for planning and
development, and day to day operation of the NTDC System.

(g) The Code Participant must maintain the Ouality of Supply (OoS)
and technical standards set out for the Point of Connections as

CC 127
GRID CODE

detailed in the NT DC Licence, Grid Code, Distribution Code, and


other applicable documents of NEPRA.
(h) The Code Participant must register itself with NEPRA as a
licensee to operate as a Generator, Distribution Company, SPTL
or another Network Operator.
(i) The Code Participants should coordinate with NTDC and
prepare a program with committed implementation schedule to
install SCADA (on line data acquisition and monitoring facilities)
on its system and requisite metering facilities.
U) Inform NTDC of any real-time sudden changes on their own
System as soon as possible.

Technical, Design and Operational Criteria

NTDC shall ensure that NTDC Transmission System complies with the
following technical, design and operation criteria at the Connection Site
with a User.

This section contains detailed technical transmission system


requirements, which NTDC shall specify in consultation with other
Code Participants and Users (NTDC to provide detailed specifications
outlined below if not included thus for).

(a) t'JTDC Transmission System Performance Characteristics

(i) Grid Frequency Variations

The Frequency of the NTDC Transmission System shall


be nominally 50Hz and shall be maintained within the
limits of 49.8 to 50.2 unless exceptional circumstances
prevail.

(ii) Grid Voltage Variations

Under (N-O) normal operating conditions, System


Operating Voltages of the Total System shall be
maintained within the bandwidth of +8% to -5% of
Nominal System Voltage. U~der (N-1) contingency
operating conditions, the voltage variation shall be in the
range of +10% and -10% of Nominal System Voltage.

However, 132 kV System Operating Voltages at the


Points of Connection shall be governed by the limits
provided in the Performance Standards (Transmission)
and/or Performance Standards (Distribution) as
applicable ..

cc 128
GRID CODE

(iii) Power Quality

• Harmonic Content
Total Harmonic Distortions (THO) level should be
in accordance with IEEE Standard 519-1992

• Phase Unbalance
Under Planned Outage conditions, the maximum
negative phase sequence component of the phase
voltage on the NTDC Transmission System should
remain below 1% unless abnormal conditions
prevail.

• Voltage fluctuations/Dips

• Negative and zero sequence loading

(b) Plant and Apparatus relating to User/NTDC Transmission


Connection Site.

(i) General Requirements

• Design of Connections

• Earth Fault Factor

• Earthing Requirements

• Voltage Conditions

(ii) SUbstation Plant and Apparatus

./ Plant and/or Apparatus prior to 1st January, 2005

./ Plant and/or Apparatus post 1st January 2005 for


a New Connection Point

./ New Plant and/or Apparatus post 15t January


2005 for an existing Connection Point

./ Used Plant and/or Apparatus being moved,


Re-used or Modified

• Technical Specification of Substation Plant and


Apparatus


proposed Connection.

CC 129
GRID CODE

• User Compliance with NTDC's Specification.

• Design, Manufacturing and Testing.

(c) Requirements Relating to Generator/NTDC Connection


Points

(i) Generating Unit and Power Plant Protection


Arrangements.

(ii) Minimum Requirements.

(iii) Fault Clearance Times.

(iv) Equipment to be Provided.

(v) Protection of Inter-connections.

(vi) Circuit-breaker Fail Protection.

(vii) Loss of Excitation.

(viii) Pole-Slipping Protection.

(ix) Signals of Tariff Metering (CTs and PTs).

(x) Work on Protection Equipment.

(xi) Relay Settings.

(d) Requirements Relating to Network Operator/NTDC and


Non-embedded Consumers/NTDC Connection Points.

(i) Protection Arrangements for Network Operators and


Non-embedded Consumers.

• Fault Clearance Times.

• Fault Disconnection Facilities.

• Automatic Switching Equipment.

• Relay SeWngs.

• Work on Protection Equipment.

• Equipment to be provided.

• Protection of Inter-connections.

cc 130
GRID CODE

(e) General Generating Unit Requirements

(i) Technical, Design and Performance Requirements

• Reserve and Ancillary Service Obligations.

• Maintenance Outage Requirements.

• Stability and Suitability Requirements

• Insulation Level Requirements.

• Lightning Protection

(ii) Plant Performance ReqUirements

• All Generators Units must be capable of supplying


rated power output (MW) at any point between the
limits 0.80 power factor lagging and 0.90 power
factor leading at the Generating Unit terminals.
The short circuit ratio of Generating Units shall be
not less than 0.5%;

• Each Generating Unit must be capable of


Continuously maintain constant output for system \
frequency changes within the range 50.5 to 49.5
Hz; and

• The Active Power output under steady-state


conditions of any Generating Unit directly
connected to the NTDC Transmission System
should not be affected by voltage changes in the
normal operating range. The Reactive Power
output under steady-state condition should be fully
available within the voltage range of ~5% at all
voltage levels.

(iii) Control Arrangements

• Each Generator must be capable of contributing to


frequency and Voltage Control by conti nuous \.
modulation of Active Power and Reactive Power
supplied to the NTDC Transmission System;

CC
GRID CODE

frequency response under normal operation


conditions. The governor must be designed and
operated to the appropriate international standard;
and

• A continuously-acting automatic excitation control


system is required to provide constant terminal
voltage control of the Generator without instability
over the entire operating range of the Generator.

• Frequency and Voltage Control Modulation


Minimum Frequency Response Requirements
(Appendix C).

• Steady-State load Inaccuracies


The standard deviation of load error at steady
state load over a 30 minute period must not
exceed 2.5% of a Generating Unit.

• Negative Phase Sequence loadings

• Neutral Earthing
At Nominal System Voltage of 132kV and above
the higher voltage windings of a transformer of a
Generating Unit must be star-connected with the
star pOint suitable for connection to earth.

• Frequency Sensitive Relays


Generators shall be responsible for protecting all
their Generating Units against damage if frequency
excursions outside permissible range ever occur.
Should such excursions occur, it is up to the
Generator to decide whether to disconnect his
Apparatus Plant or Facility for reasons of safety of
Apparatus, Plant and/or personnel.

(f) General Network Operator and Transmission-connected


Consumer Requirements

This part of the Grid Code describes the technical and design
criteria and performance requirements for authorized electricity
operators and Transmission connected Consumers.

CC 132
GRID CODE

(i) Neutral Earthing


(ii) Frequency Sensitive Relays
Technical Requirements for Low Frequency Relays for
the Automatic Load Shedding (Appendix D)

(g) Communications System

(i) Communication Requirements

(ii) Control Telephony

(iii) Operational Metering

(iv) Instructor Facilities

(v) Electronic Data Communication Facilities

(vi) Facsimile Machines

(vii) Busbar Voltages

(h) System Monitoring

(i) Site Related Conditions

(i) Responsibilities of Construction, Commissioning, Control,


Operation and maintenance of Facilities

(ii) Responsibility for Safety

• NTDC Safety Rules and Their Area of Application

• User's Safety Rules and Their Area of Application

• NTDC's Authorization to User/Network Operator to


Carryout Works

• User's/Network Operator's Authorization to NT DC


to Carry Out Works

• Connection Sites
(iii) Site Responsibility Schedules
• Format, Principles and Procedures to be used in
the preparation Site Responsibility Schedules
(SRS) (Appendix A)

• Proforma for Site Responsibility Schedule (SRS)/~__


(Attachment to Appendix A)

CC 133
GRID CODE

(iii) Operation and Gas Zone Diagrams

• Appendix B (Part-I)
Principles and Procedures Relating to Operation
Diagrams.

• Appendix B (Part-II)
Principles and Procedures Relating to Gas Zone
Diagrams.

• Appendix B (Part-III)
List of all Apparatus to be shown on Operation and
Gas Zone Diagrams.

• Operation Diagrams

• Gas Zone Diagrams

• Preparation of Operation and Gas Zone Diagrams


for User's Sites

• Preparation of Operation and Gas Zone Diagrams


for NTDC's Sites

• Changes to Operation and Gas Zone Diagrams

(iv) Site Common Drawings

• Preparation of Site Common Drawings for a User


Site

• Preparation of Site Common Drawings for NTDC


Sites

(v) Physical Access

• Physical Access Requirements and Conditions.

(vi) Maintenance Standards

(vii) Site Operational Procedures

134
CC~
GRID CODE

U) Ancillary Services

(i) System Ancillary Services

(ii) Commercial Ancillary Services

Maintenance and Replacement of Interconnecting Facilities due to


Aging/damage

The NTDC or the distribution company, as the case may be, who owns
the assets at the Point of Connection shall carry out the maintenance
of the equipment, including the equipment used for connection. All the
costs incurred in this respect shall be borne by the owner of the assets.

The replacement of equipment due to aging shall be the responsibility


of the NTDC or the distribution company, as the case may be, who
owns the assets at the Point of Connection.

SCADA and SCADA Communications System

The SCADA and SCADA communication system shall be used by


NTDC and Code Participants to monitor and control the NTDC
Transmission System, including 500 kV and 220 kV grid stations,
portions of 132 kV substations, and to dispatch Generators connected
to the Transmission System of NTDC. The SCADA system shall also
include data from Generators, and other Code Participant facilities as
required by NTDC.

Open Access

NTDC shall operate the Transmission System in the spirit of ·Open


Access". By "Open Access· is meant that all Code Participants (extant
and potential) shall be treated fairly and equitably without any
discrimination or prejudice.

Open Access requires that NTDC shall develop a set of procedures for
the receipt and management of requests for new connection to its
Transmission System. NTDC shall prepare and maintain a list of the
names of all persons requesting a connection to the system along with
pertinent data including: date of request, location of connection, MW
capacity of connection, name of line or substation to which the
connection is requested and expected in-service date. NTDC shall
provide NEPRA with a revised list whenever there is a change to the
list of applicants.

CC

~
GRID CODE

makes a change in any of the following: name of applicant, location of


connection, MW capacity of connection, point of connection to grid, or
expected in-service date. NTDC shall publish the list on its Internet
Web Page and provide copies on request from interested parties.

NTDC shall prepare load flow and short-circuit studies for each
proposed new connection and the study results shall distinguish in a
clear and impartial way between impact of a new connection on the
steady state power flow, and short circuit impacts of a proposed new
connection during summer and winter peak load conditions for the year
of proposed in-service date. Such studies shall not be made for a
given proposed new connection for years after the year of the proposed
new connection. NTDC shall advise each new connection of the
transmission and substation facilities to be added to allow the output
from the proposed new connection to flow onto the NTDC
Transmission System.

NTDC shall not require new connection to pay for upgrades and
improvements of the Transmission System that are beyond the
immediate Open Access Point of Connection. In the case of an Entity
being aggrieved by any determination of the Code Administrator
(NTDC), the decision shall be referred to Review Panel for arbitration.

Frequency and Voltage Control

Each Generator, through automatic action, must be capable of auto-


monitoring and contributing to Frequency and Voltage Control and
regulation of the NTDC's Transmission System by continuous
modulation of Active Power and Reactive Power output.

Reactive Power Supply and Voltage Regulation

The Generators shall maintain a System Voltage or reactive power


output as required by the NTDC within the reactive capability of the
Generators.

Load Following and Freguency Regulation (balance supply and


demand).

Generators that have good response capability and necessary controls


may after frequency regulation as an ancillary service, and may be
assigned the function of providing the load following and frequency
regulation services or duties as the case may be.. The output of the
generating units used to provide load-following service shall be
adjusted continuously and automatically to compensate for changes in
system load.

cc 136

~/
GRID CODE

CC6 DATA REQUIREMENTS


CC 6.1 Preferred Connection Arrangement
The six schemes have been described in Table 3-1 for Interconnection
of the Generators including GENCOs, IPPs and other Generators
(private or public). The existing Generators are using these schemes,
however, the new Generators may design new configurations, which
shall be acceptable by NTDC after evaluation of the prevailing system
conditions. These schemes of connection diagrams are provided in
Appendix E of this sub-code.
Table-3-1
Connection Approximate Connection Configuration
Voltage Generation Size Schemes
1 2& 2A 3 & 3A 4

11 kV and Bellow 1-4 MW •


66kV 4-40 MW •
132kV 40-150 MW •
220kV 150-400 MW •
400 MW and
500kV
above •
The suggested connection arrangements for each plan and three
typical protection schemes are shown in diagram 3-1 through diagram
3-6 in Appendix E of this sub-code.

CC7 SERVICE AND NETWORK DESIGN CONDITIONS


CC 7.1 Service Conditions
Parameters (Based on prevailing
Standards)
Altitude 0- 1500 M
Maximum ambient temperature 50°C
Minimum ambient temperature* -4 to -7°C
Every day temperature* 30-42oC (summer)
0- 32°C (winter)
Relative humidity (Percentage) 0-100
Average rainfall 500-900 mm
Isokeraunic level- Average 32 -65
Isokeraunic level- Maximum 120 thunder storm days/year
Maximum wind velocity 160 km/hour
Atmospheric pollution Marine-desert & industrial
Maximum ESDD mg/cm 2 1.0 south of Jamshoro
0.67 south of Guddu
0.12 North of Guddu

CC
GRID CODE

CC 72 Network Conditions

Parameters
{Based on I2revailing 500kV 220kV 132kV
Standards}
Frequency 50 Hz 50 Hz 50Hz
Configuration 3 phase, tri and 3 Phase single 3 Phase single
quad and twin and twin
bundle/phase bundle/phase bundle/phase
Neutral arrangement Solidly earthed Solidly earthed Solidly earthed
Nominal vOltage 500kV r.m.s 220kV r.m.s 132kV r.m.s
Highest voltage for 550kV r.m.s 245kV r.m.s 145KV r.m.s
equipment
Three phase 40 kA r.m.s 40 kA r.m.s 31.5/40 kA r.m.s
symmetrical short
circuit curren t
Three phase 100kAl125 kA 100 KPJ 125 kA 80/100 KA r.m.s
symmetrical peak r.m.s r.m.s
withstand current
Insulation
Coordination
Lightening impulse
with stand 1.2/50 us
a- To earth and 1550 kV peak 1050 kV peak 650 kV peak
between phases
b- Between open 1550 kV peak 1200 kV peak 750 kV peak
isolator contacts (+315)kV peak
One minute power
frequency withstand
a-To earth and 620 kV r.m.s 460 kV r.m_s 275 kV r.m.s
between phases
b- Between open 800 kV r.m.s 530 kV r.m.s 315 kV r.m.s
isolator contacts

Connection diagrams (3-1 to 3-6) as referred to in Table 3.1 are provided in


Appendix E of this sUb-code.

CC 138

/
GRID CODE

APPENDIX A
OF
CONNECTION CODE

FORMAT, PRINCIPLES AND PROCEDURES TO BE USED IN THE


PREPARATION SITE RESPONSIBILITY SCHEDULES (SRS)

CC.A.1 Principles
Principles which form the basis of developing SRS

CC.A.1.1 Types of Schedules


b. Commissioning
a. Construction
d. Operation
c. Control
f. Testing
e. Maintenance

CC.A.1.2 New Connection Sites

CC.A.1.3 Sub-division of Connection Sites; if any

CC.A.1.4 Description of each Item of Plant and Apparatus at the


Connection Site.

CC.A.1.5 Additional Detail of Plant and Apparatus, if any.

CC.A.1.6 Lines and Cables Emanating from Connection Sites.

CC.A.1.7 Issuance of draft SRS

CC.A.1.8 Accuracy Confirmation by concerned Parties

CC.A.1.9 Site Responsibility Schedule (Signed by NTDC)

CC.A.1.10 Distribution of SRS

CC.A.1.11 Availability of Site Responsibility Schedules (SRS)

CC.A.1.12 Alterations/Revisions to Existing Site Responsibility


Schedules; if any

CC.A.1.13 Revised Site Responsibility Schedules

CC.A.1.14 Finalization of Site Responsibility Schedules

CC.A.1.15 Urgent Changes


CC.A.1.16 Names and Designation of Authorized Person and Safety
Coordinators

CC.A.1.17 De-commissioning of Connection Sites

CC 139
GRID CODE

APPENDIX A
OF
CONNECTION CODE
(ATTACH MENT)

PROFORMA FOR SITE RESPONSIBILITY SCHEDULE (SRS)

This Performa should at least contain the following:

1. Number of Schedule, Issue, Number and Date.

2. Name of Complex and Connection Site.

3. Identification of Apparatus.

4. Name of the Owner of the Apparatus.

5. Name of the Person Incharge of the Work Site (Authorized Person)

6. Item of Plant Apparatus.

7. Name of the Safety Co-ordinator.

8. Details of the Operations carried out on each Apparatus.

9. Safety Rules and Precautions.

10. Operational Procedures.

11. Party Responsible for Undertaking Inspections, Fault Investigation and


Maintenance.

12. Remarks

cc 140
GRID CODE

APPENDIX B
OF
CONNECTION CODE
(PART-I)

PRINCIPLES AND PROCEDURES RELATING TO OPERATION DIAGRAMS

(The Operation Diagram shall include all HV Apparatus and the Connections to all
external circuits including Numbering, Nomenclature, Labeling as set out in OC 10).

CC
GRID CODE

APPENDIX B
OF
CONNECTION CODE
(PART-II)

PRINCIPLES AND PROCEDURES RELATING TO GAS ZONE DIAGRAMS

(Areas of the Connection Sites where gas-insulated metal enclosed switchgear


and/or gas-insulated HV apparatus is installed shall be depicted by a chain detted
line which intersects the Gas Zone boundaries. A Gas Zone Diagram is to be
prepared for each Connection Site where a gas-insulated switchgear/apparatus has
been used. These Diagrams shall conform to the Operation Diagrams in terms of
Graphical symbols and Nomenclature)

cc 142
GRID CODE

APPENDIX B
OF
CONNECTION CODE
(PART-III)

List of all apparatus to be shown on the Operation and Gas Zone Diagrams that is
installed at the Connection Sites including its present status as it pertains to the
System Operation.

CC 143
GRID CODE

APPENDIX C
OF
CONNECTION CODE

Minimum Frequency Response Requirements

CC.C.1 Scope

CC.C.2 Plant Operating Range

cec.3 (a) Minimum Frequency Response Capability Profile in the


graphical form;

(b) Interpretation of Initial and Secondary Response Values by the


Connecting Party in the graphical form

CC.CA Testing of Minimum Frequency Response Capability

CC.C.5 Repeatability of Response

144
GRID CODE

APPENDIX D
OF
CONNECTION CODE

TECHNICAL REQUIREMENTS FOR LOW FREQUENCY RELAYS


FOR THE AUTOMATIC LOAD SHEDDING

CC.D.1 Low Frequency Relays

(Technical Specifications and Setting as per Connection Agreement)

CC.D.2 Low Frequency Relay Voltage Supplies

(Secured voltage supply arrangement for the low frequency relay)

CC.D.3 Scheme Requirements

a. Minimum dependability functional requirements at each


Connection Site.

b. Outage requirements with respect to load shedding specified by


NTDC.

CC 145

~
GRID CODE

Annexure E
Scheme 1
INTERCONNECTION CONFIGURATIONS FOR GENERATORS
Connections at 11 kV

The Generators may adopt any of the configurations depending on its location with
reference to the substation and existing feeders and loading and operating condition
of the feeders.

To Consumers

Licensee's
Substation

Generator Substation

To Consumers

Licensee's
Substation

Generator Substation

CC 146

\\l,;
GRID CODE

Annexure E
Scheme 2
INTERCONNECTION CONFIGURATIONS FOR GENERATORS
Connections at 66kV

For connection of Generators at 66kV, two configurations have been indicated which
may be adopted according to the system conditions. The new Generators may opt
for new configurations, which NTDC/System Operator may accept after carrying out
necessary system studies.

66kV 66kV
Licensee's Licensee's
Substation Substation

Generator Substation

CC 147
GRID CODE

Annexure E
Scheme 2A
INTERCONNECTION CONFIGURATIONS FOR GENERATORS
Connections at 66kV

66kV 66kV
Licensee's Licensee's
Substation Substation

Generator Substation

cc 148
GRID CODE

Annexure E
Scheme 3
INTERCONNECTION CONFIGURATIONS FOR GENERATORS
Connections at 132kV

For interconnection of Generators to 132kV system two configurations schemes


3&3A have been provided. Both the schemes are in use by existing Generators.
However, the new Generators may opt for new configurations, which the
NTDC/System Operator may accept according to prevailing and expected future
conditions of the Transmission System.

132kV 132kV
Licensee's Licensee's
Substation Substation

Generator Substation

cc 149
GRID CODE

Annexure E
Scheme 4
Interconnection Configurations for Generators
Connections at 220kV and 500kV

(To be provided by NTDC)

151
GIRD CODE

Annexure F
Figure-1
CONNECTION PROCEDURE
for New Connection or Modification
of Existing Connection

t t
DISCO NTDC APPLICANT
I I I I I I

Evaluate the Evaluation Prepare


Application with respect Intention
Preliminary to Grid Code Application
Evaluation

Comments Submit Intention


---. Application to NTDC
and DISCO
Simultaneous

Provide Additional
Information if Required

Offer for Connection

t Submit Fonnal
Application for
Final Evaluation of Connection
Application

Prepare Negotiation I Negotiation l Prepare Negotiation


Connection Ag,eemen~ Comments on
Metering and
l lConnection Agreement
Protection

~
Ik.u""lE..!3
t'-.Iake Connection
ReG
,,-,,c...)/ u(

CC 152
u
~
ll1
APPROVED
BY
~ ~~):t-
0

~ ~. THE AUTHORITY ~
9-<'A.. . .'-~
.:
GRID CODE

PROTECTION AND METERING CODE

CONTENTS

Sr. No. Subject Page No.

PMCl INSPECTION AND TESTING PMC-154

PMC2 METERING AND PROTECTION PMC-155

PMC3 PROTECTION OF POWER SYSTEM EQUIPMENT PMC-168

PMC

\\\J. ~
GRID CODE

PROTECTION AND METERING CODE

PMC1 INSPECTION AND TESTING

Each User/Code Participant must furnish, for NTDC review and


approval, proposed settings of the relays of their facilities. If requested,
NT DC shall provide its Transmission System data needed to determine
the relay settings.

Before commencing integrated operation with the NTDC Transmission


System, the installation must be witnessed and inspected by NTDC.
The Code Participant is responsible for providing necessary equipment
and qualified personnel, who will complete all required tests. NTDC
shall not perform any of the testing unless contracted to do so.

The Code Participant must perform submit certified test reports to


NTDC, and have NTDC witness the following tests:

a) CT and PT ratio tests

b) CT and PT secondary circuit tests to verify phasing, polarity etc.

c) Completion of relay manufacturers recommended acceptance


tests.

d) Tests of phasing between NTDC and Code Participants


System.(primary Voltage)

e) Directional test for distance (impedance) relay (s), if required.

f) Final synchronization tests, before paralleling the two systems,


to verify Code Participants/Generator (s) are in phase with the
NTDC Transmission System.

g) Earthing - Earthing test to be performed at request of NTDC

h) Insulation - Megger and hi-pot testing

i) Switching Operation - Functional Operational Testing

j) Other tests prescribed by NTDC to verify design conformance,


functioning and safety of equipment.

k) CT/PT Continuity test

I) C & OF test for CT/PT

m) CT Saturation Curve Test

n) CT VA Burden test

PMC 154
GRID CODE

Satisfactory results shall demonstrate the design performance,


functionality, and safety of individual components as well as the entire
sUbstation.

The User/Code Participant must notify NTDC at least ten business


days before performing the required tests. Updated drawings (as built)
must be provided to NTDC for verification at least seven business days
before performing testing.

Once the NTDC determines th9 installations to be suitable to operate in


parallel with NTDC Transmission System, both the Code Participant
and NTDC representatives must sign and date the "Approval for
Operation of the Facility" in, parallel with NTDC Transmission System.
After this is done, the Code Participants facility is authorized to operate
its System in parallel with the NTDC Transmission system.

PMC2 METERING AND PROTECTION

PMC 2.1 Metering Coordination

a. Purpose

This section specifies the minimum technical, design and


operational criteria for revenue metering, for the purpose of
electricity sales and flow, which must be complied with by all
Generators and other Users connected to or seeking connection
with the electric Transmission System of DISCOs and/or
National Transmission and Dispatch Company (NTDC).

For the purpose of settlement, electric energy (active and


reactive) supplied and delivered at each defined metering point
must be measured and recorded through metering equipment
installed, operated and maintained under this Metering Code
with the accuracy standards defined in this sub-code.

b. Location of Metering Points

Metering facilities would be installed at the SUbstation for Point


of Connection between the Users and the Transmission System
of NTDC. Metering between the generator and the Transm'lssion
System of NTDC would be installed at the high voltage side of
the Point of Connection. Metering between the Delivery Point to
the User and the transmission network would be installed at the
132 kV, low side of the connection. Metering cabinet shall be
installed inside the SUbstation building. Revenue class
instrument transformers as specified in IEC or IEEE Standards
shall be installed at the substation as required.

PMC 155
GRID CODE

Notwithstanding the above, the location of the Metering Point on


each transformer shall be such that the cost of transformation
losses shall always be with the Entity that owns the transformer.
c. Application

Metering shall provide accurate metering of electrical quantities


delivered to or received from the NTDC Transmission System.
Metering devices including all instrument transformers must
have revenue class accuracy in accordance with the applicable
NTDC Standards or IEC Standards as listed in PMC 2.1.f, for
reference with options for measuring apparent energy, active
and reactive energy, load demand, power factor, etc. that are
required for billing, planning and engineering purposes.
Metered quantities shall be remotely transmitted and recorded in
the metering database at the computer systems of the System
Operator/NTDC.

Metering shall be provided in a separate metering cabinet to be


located in a control building. For new metering installations
separate dedicated revenue class current (CT) and potential
(PT) transformers shall be provided for revenue metering, and
shall not be shared with protection system or check meter. For
existing installation where instrument transformers are shared
for metering and protection, a metering audit shall be performed
to ascertain that no unacceptable error due to overload or
instrument transformer saturation is introduced in the metering.
If error introduced to revenue metering is unacceptable, new
instrument transformers for metering shall be installed. CTs and
PTs shall have a locking termination compartment that can be
sealed. All wiring between the CTs and PTs shall be stranded
copper wire, with PVC/polyethylene jacket. The metering
cabinets shall be installed in rigid conduits. The metering cabinet
shall be heavy gauge steel, primed and finished with gray finish,
with locking door. A glass window shall be provided on the door
to permit visual reading of the meter.

d. Principles

Metering facility shall be provided at the Point of Connections


between Code Participants and NTDC to record energy and
maximum power (Active and Reactive both) supplied to or
delivered from the Transmission System of NTDC for the
purposes of billing, engineering studies, and planning. Metering
must provide accurate measurements of energy and power
delivered at the Points of Connection between NTDC,
Generators and other users. All metered electrical quantities,
including time and date information shall be transmitted to the
System Operator for processing. billing and settlement of
accounts. Metering data shall be made available to Code
Participants.

PMC 156

.~
GRID CODE

e. Metering Requirements

Metering will be installed by NTDC at a secured location in the


substation where connection between the Generator or other
Users and NTDC Transmission System is made. Metering and
instruments transformers shall be installed in such a manner
that they cannot be tampered with.

Each User/Code Participant shall provide and install the revenue


meter at the connection location. Meter shall be the type and
mOdel approved by the NTDC. Meters and associated CTs and
PTs shall comply with relevant IEC Standards listed in PMC
2.1.f., and/or applicable NTDC Standards.

The CTs and PTs shall be supported be required accuracy


certificate from th~ manufacturer. The energy meter test shall be
conducted or site jOintly by NTDC and the respective Code
participant.

NTDC shall be responsible for testing and maintenance of the


meters, and shall have test and calibration facility, with
necessary tools and instruments, for testing and calibration of
meters and will be responsible for periodic testing and
maintenance of the metering and anCillary equipment. All test
eqUipment shall comply with IEC 60736 or applicable
IEC Standards to be prescribed by NTDC. The User shall
replace meter or other metering component that is found to be
defective.

f. Standards

Protection/Metering Devices and instrument transformers for


revenue metering must comply with the latest applicable
international and local standards, including, but are not limited
to, the following:

• IEC 60145 Var-hour (reactive energy) meters

• IEC 60521 Class 0.5, 1 and 2 alternating-current watt-


hour meters
• IEC 60687 Alternating current static watt-hour meters
for active energy (classes 0.2 Sand 0.5 S).

• IEC 61036 Alternating current static watt-hour meters


for active energy (classes 1 & 2).

• IEC 61107

PMC 157
GRID CODE

• IEC 61354 Electricity meters - marking of auxiliary


terminals for tariff devices

• IEC 61361 Electricity metering - local and remote data


exchange.
• IEC 62053-61 Electricity metering equipment (ac) -
particular requirements - Part 61: power
consumption and voltage requirements.

• IEC 62056-31 Electricity metering - Data exchange for


meter reading, tariff and load control - Part
31: Use of local area networks on twisted
pair with carrier signalling.

• IEC 62056-41 Electricity metering - Data exchange for


meter reading, tariff and load control - Part
41 :Data exchange using wide area
networks: Public Switched Telephone
Network with lINK+ protocol.

• IEC 62056-51 Electricity metering - Data exchange for


meter reading, tariff and load control - Part
51: Application layer protocol.

• IEC 60044-1 Instrument transformer - Part 1: Current


transformer.

• IEC 60044-2 Instrument transformer - Part 2: Inductive


voltage transformer.

• IEC 60044-3 Instrument transformer - Part 3: Combined


transformers

• IEC 60186 Voltage transformers

g) Performance Requirements

Revenue metering and ancillary equipment must read energy


and power (Active and Reactive) delivered to or received from
the NTDC Transmission System, with an appropriate degree of
accuracy specified in applicable IEC Standards, but not less
than
+/- 0.2%. Revenue class metering shall have the following
ch a racteristi cs:

(i) Three elements four-wire configuration, electronic, digital,


with accuracy class of 0.2 in accordance with IEC
Standards for Grid Meters.

PMC 158
GRID CODE

(ii) Meters shall be capable of measuring and recording


active energy at 30 minutes intervals for a period of 70
days with intervals programmable from 5 minutes to 30
minutes.

(iii) The meter must have the capability of recording active


and reactive power and energy and maximum Load
Demand for the entire billing period. The meter-billing
period may be programmable and capable of being
programmed to automatically store the accumulated
value and reset the counter for the next billing period.

(iv) Multiplier corresponding to the combination of CT and PT


ratios may be programmable in the meter. Accuracy class
of CT and PT shall be in accordance with NTDC technical
specifications.

(v) Meters may be capable of time-of-use and seasonal


applications. Meters shall have internal time clock for time
and date stamping of data. Time clock must have high
accuracy and synchronize to GPS time signals.

(vi) Meters may have capability for remote meter reading by


telemetering or by SCADA. Communication ports should
be provided with optical and serial data communication
with industry standard protocol support.

(vii) Meter should have self-diagnostic capability and include


an alarm to indicate failure and/or tampering.

h) Installation

Installation of revenue meter and ancillary equipment at the


substation for the Point of connection shall be the Generator and
other Code Participant/Users' responsibility. The Generators
and other User connecting to the NTDC Transmission System
shall submit to the NTDC for approval the engineering design for
revenue metering, proposed location of metering equipment and
ancillaries complete with wiring and installation drawings and bill
of materials. The proposed metering location shall be adjacent
to any telemetering, communication and data logging
equipment.

Revenue metering and ancillary devices shall be provided in


secured metal enclosure. Enclosure shall have doors with locks
for easy access. Glass window shall be provided on the door to
allow visual reading of the meter inside the enclosure.
Instrument transformers shall be installed in secured location
and shall be dedicated and not be shared with protection or
other metering devices, to prevent tampering. All wiring b~I1m~­
'Y~----:
~CJ
CJ
pr.le 159 ::J APPROVED .-<.
LU BY }:>

~
c~
THE AUTHORITY
,S)"
.7
GRID CODE

the instrument transformer outside the metering compartment


shall be installed in rigid galvanized steel conduits. Meter shall
be located where it is accessible for reading the registers and for
testing and maintenance. Access to the metering facility shall be
accorded to NTDC personnel as per PMC 2.1.k.

i) Telemetering (Data Collection System)

Facilities are to be provided for remote transmission of metering


information to the NTDC to be recorded in the metering
database. Transmission of telemetered data information must be
secure and reliable and not prone to tampering. All metered
quantities including times and date of acquisition must be
telemetered. Quantities that are to be metered shall include:

(i) Apparent Energy

(ii) Real Energy

(i i i) Energy (KWh or MWh) delivered to Load

(iv) Energy (KWh or MWh) received from Supply

(v) Reactive Energy (KVArh or MVArh)

(vi) Peak Demand MW or KW

(vii) Peak MVAr or kVAR Demand

(viii) Power Factor

(ix) Active and Reactive Energy Import and Export (MWh and
MVARh)

Metering database is to be provided at the NTDC Headquarters


or National Power Control Centre location. Database shall have
metered quantities, meter information, metering constants,
instrument transformer ratios, etc. Information in the data base
computer will be accessible to for billing, engineering studies
and planning.

The communication protocol for transmitting metering


information shall be in accordance with IEC 61107.

j) Settlement of Accou nt

Discrepancy in meter reading arising from error introduced by


the meter or saturation or defect in instrument transformers
should be resolved by the Grid Code Review Panel. This may
require an audit of the metering system to verify the accura~~~
~O ER REG
( , 'I; u(
-------------------------------------------------+--~~~- ~~
PMC 160 0
':J APPROVED ~
UJ BY ~
i,,~
THE AUTHORITY ::.-..
::;i
GRID CODE

the meter and instrument transformers. If problem with the meter


and instrument transformer accuracy is detected, the reading
will be adjusted as per agreed procedure between the
Users/Code Participants and NTDC.

The User/Code Participant, at his option, may elect to install a


check meter to verify the reading in the revenue meter at the
Point of Connection. Instrument transformers for revenue meter
must not be shared with check metering. Any check meters
should have separate instrument transformers

All disputes regarding meter readings and settlement of


accounts shall be presided over by NTDC in accordance with
the provisions of the Commercial Code and Bulk Power Supply
Agreements (to be developed later).

k) Access

Each User/Code PartiCipant shall authorize each Code


Participant, its employee, agents and sub-contractors right to
enter upon and pass through and remain upon any part of such
User's property to the extent necessary for the purpose of
performance obligations under this sub-code.

The right of access provided for under this sub-code includes


the right to bring on to such Code Participants/User's property
such vehicles, plant, machinery, and maintenance or other
materials as shall be necessary for the purpose of performance
obligations under this sub-code.

Each User/Code participant shall ensure that all reasonable


arrangements and provisions are made and/or revised from time
to time as when necessary or desirable to facilitate the safe
exercise of his right of access.

I) Tamper and Revenue Protection

Representatives of the NTDC and any other concerned Entity


shall supervise meter installation. After completing the
installation, the representatives of concerned Entity, NTDC as
observers, shall lock and seal the meter and metering
compartment.

m) Testing and Calibration

Meter audits shall be conducted periodically, on a schedule to


be determined by the System Operator/NTDC and Code
Participants/Users but not less than every two years, to verify
meter accuracy and resolve disputes regarding meter reading.
Meter audit may be performed by NTDC. Meter found to ~-_
,?O\"lER RE:c
__________________________________________________~~~~~~L~ ~~~

PMC 161 ~ APPROVED


BY
%
~~9r
LU p
:1
.• ' \
THE AUTHORITY / .~
l
GRID CODE

inaccurate would be removed for testing and calibration at the


NTDC laboratory. NTDC laboratory shall have all the necessary
equipment and devices to test and calibrate the different types
and models of meters used. .

Test and calibration of meters shall be in accordance with


applicable IEC Standards listed in PMC 2.1.f, above. All test
equipment for testing energy meters shall conform to IEC
60736, Testing Equipment for Electrical Energy Meters.

n) Metering and Reconciliation Agreements [ to be provided as part


of Commercial Code]

0) Right to access and use of distribution company'sl BPC's


switchyard by NTDC.

NTDC. shall have the right to enter a distribution company and BPC
switchyards for the purpose of installing, checking, testing and
maintaining metering and related equipment and wires. Distribution
Companies and BPCs shall accommodate requests by the NTDC for
access on demand, and shall not prevent NTDC from making
unscheduled inspections on short notice.

PMC 2.2 Protection Coordination

a. General

The design of Inter-connection between any Generator; other


Users and the NTDC Transmission System should be consistent
with the Operation, Planning Standards and Protection Design
Standards of NTDC, and the Standards laid down in this Grid
Code. Apparatus for the protection of Generators, substation
equipment and transmission lines from faults and overloads
shall be provided at the Points of Connection. Both Primary and
Secondary (back-up) protection schemes are to be provided to
enhance system reliability. Design and settings of protection
system shall be coordinated between the Users/Code
Participants and NTDC. Settings of protective devices shall be
reviewed periodically by NTDC to maintain consistency with
operation, planning and protection design standards.

b. Standards and Practices

Protection devices shall conform to the applicable IEC


Standards and prudent utility practices adopted by NTDC.
Design of protection system at the Points of Connection shall be
submitted by Users/Code Participants for review and approval of
NTDC. ~

PMC 162
GRID CODE

c. Generator Protection

connection between a Generator and NTDC Transmission


System must be controlled by a circuit breaker capable of
interrupting the maximum short circuit current at the Point of
Connection. The maximum short circuit current shall be
specified by NTDC at the time of design based on most recent
analyses.

Protection of Generators and their connections to the NTDC


Transmission System must meet the minimum requirements
delineated below (relay settings are to be reviewed by the
System Operator/NTDC from time to time):

(i) For faults on the Generator's equipment directly


connected to the NTDC Transmission System and for
faults on the NTDC Transmission System directly
connected to the Generator's equipment, fault clearance
period from fault inception to circuit breaker arc extinction
shall be set out in either Transmission Service or
Connection Agreement, as the case may be. The time
limit shall be according to the respective IEC Standards.

(ii) In the event the fault clearance times are not met as a
result of a failure to operate the primary or main
protection system, a back-up or secondary protection
system shall be provided. Sack-up protection shall be
coordinated with the primary protection so as to provide
discrimination.

On the Generator connected to the NTDC Transmission System


where only one primary or main protection is provided to clear
fault on the high voltage Generator connections within the
required fault clearance time, the secondary or back-up
protection in the Generator shall operate within the limits
provided in the respective IEC Standards. On the Generator
connected to the NTDC Transmission System where two
primary or main protections are provided, the secondary or
back-up protection shall operate to give a total fault clearance,
which is within the time limits provided in the respective IEC
Standards.

Generator secondary or back up protection shall be required to


withstand, without tripping, the loading incurred during clearance
of a faul t by a breaker fail protection on the NTDC Transmission
System. Back-up protections in the Generator and NTDC
Transmission System shall be coordinated to provide
discrimination. 1
A

PMC 163
GRID CODE

(i) Circuit breakers provided at the Points of Connection


between the Generator and the NTDC Transmission
System shall be provided with breaker fail protection. In
the event the breaker failed to operate, the breaker fail
protection shall initiate tripping of all the electrically
adjacent circuit breakers within the time limits provided in
the respective IEC Standards.

(ii) The target performance for the system fault dependability


index shall not be less than 99%. This is a measure of the
ability of the protection system to initiate successful
tripping of circuit breakers that are associated with the
fault in the system.

(iii) The Generator shall have protection equipment, but not


limited to the following:

• Protection of primary conductors from the current


transformer at the line side of the circuit breaker to
the Point of Connection.

• Circuit breaker fail protection equipment shall be


provided at the Generator. A back-up trip signal
shall be provided in the event of a main circuit
breaker failure to trip the electrically adjacent
breakers to clear the fault.

• Protection shall be provided to initiate a Generator


trip when loss of excitation is detected.

• Pole slipping protection shall be provided with the


generating units.

(iv) Protection system shall be designed to provide adequate


protection of the Generator, substation apparatus and the
Transmission System of NTDC.

d. Substation Protection

Connections between the NTDC Transmission and other


Users/Code participants (DISCOs, BPC, etc.) substations must
meet the minimum requirements delineated below:

(i)

PMC
GRID CODE

Service or Connection Agreement as the case may be.


The period specified shall be within the time limits
specified in the respective IEC Standards.

Longer fault clearing times may be specified by


NTDC/System Operator if permitted by protection and
design criteria of NTDC.

(ii) In the event the primary or main protection system failed


to meet the fault clearance times listed above, a back up
or secondary protection system shall be provided. Back-
up protection shall be coordinated with the primary
protection so as to provide discrimination.
Code Participants/Users substations connected to the
NTDC Transmission System where only one primary or
main protection is provided to clear fault of the Points
Connection within the required fault clearance time, the
secondary or back-up shall operate to give a total fault
clearance time as specified in the respective IEC
Standards.

Substation secondary or back up pr'Jtection will be


required to withstand, without tripping, the loading
incurred during clearance of a fault by a breaker fail
protection on the NTDC Transmission System. Back-up
protections in the substation and NTDC Transmission
System shall be coordinated to provide discrimination.

(iii) Circuit breakers provided at the Points of Connection


between the Code Participants/User's substation and the
NTDC Transmission System shall be provided with
breaker fail protection. In the event the breaker-failed to
operate, the breaker-fail protection will initiate tripping of
all the electrically adjacent circuit breakers within the time
limits specified in the respective IEC Standards.

(iv) The following protection shall be provided at the


substation:

• Bus bar protection


• Transformer protection
• Transmission line protection
• lightning protection

(v) The target performance for the system fault dependability


index shall not be less than 99%. This is a measure of the
ability of the protection system to initiate successful
tripping of circuit breakers that are associated with the
fault on the System. ~--
o'v'lER RCG

--------------------------------------------------------~~--
PMC 165 i ~c... <?
APPROVED ~
~<.,;
~

~~.
'. ~~ THE AUTHORITY
BY
_y~
. r)
GRID CODE

e. Fault Recording Equipment

Equipment for recording fault condition and sequence of events


shall be provided by the Code ParticipanUUser at the Points of
Connection. The recording equipment shall record a snapshot of
the voltages and current during the fault, and sequence of
events for evaluation and analysis of the fault. The fault
recording equipment shall have facilities for the information via
SCADA to the NTDC.

f. SCADA

The Users shall provide a Remote Terminal Unit (RTU) at the


Points of Connection to monitor and control apparatus at the
substation. At the Generator, a RTU shall be provided for
monitoring and control (dispatch) of the Generators. The Users
shall provide the communication link to the nearest
communication node in the NTDC communication system for
RTU communication with the NTDC SCADA System. The RTU
shall have sufficient number of input and output points; and shall
be fully compatible with the NTDC SCADA system. In addition,
RTU provided by the Generator shall have facility of dispatching
and loading the Generator from the NPCC Control Centre. The
communication link shall be fully compatible with the NTDC
communication system.

g. Time Clock Synchronization

Time clock in protection devices, recording equipment and


SCADA shall have facilities for synchronizing time with geo-
stationary positioning satellite (GPS). The User at the Points of
Connection shall provide the required receiving and signal
distribution equipment.

h. Testing, Calibration and Maintenance

NTDC shall carry out a thorough review of the entire protection


system in their System and at the Points of Connection
periodically. Adjustments or changes in relay settings shall be
performed due to changes in the characteristics of the NTDC
Transmission System. In addition, periodic testing, calibration
and maintenance of the protection system for the NTDC
Transmission System and Points of Connection shall be
performed by NTDC. NTDC shall provide testing facility, test
vehicle and test instruments for field and laboratory for the
purpose of testing, calibration and maintenance of protection
equipment. Cost of providing this service to Code Participants!
User shall be included in the tariff.

PMC 166
GRID CODE

Substation direct current check.

All Code Participants/Users shall co-operate with NTDC and the


System Operator in the scheduling and performance of testing
and periodic checks of the readiness and adequacy of direct
current systems and facilities in their substations.

j) Testinq Frequency and Calibration

Code Participants shall provide on an annual basis a schedule


for testing for substation facilities in its substations. NTDC and
the System Operator shall have the right to require additional
testing, and to request recalibration of testing equipment.

k) Testinq Equipment Ownership

Code Participants shall own and maintain, or contract with


qualified testing companies, for the testing equipment required
to perform tests.

I) NTDC Right to Inspect

NTDC shall have the right to' inspect 132 kV substations and
transmission lines that are connected to the Transmission
System of NTDC, and which are owned by DISCOs, SPCs,
SPTLs or any other Code Participant.

PMC 2.3 CONTROL AND SWITCHING COORDINATION

a. General

For the purpose of connecting and disconnecting a Generator


and User's substation from the NTDC Transmission System, it is
essential that the necessary equipment be provided. This
equipment shall include, but not limited to the following:

(i) In conjunction with the protection system, circuit breakers


shall be provided at the Point of Connection between the
Code Participants/User and the NTDC Transmission
System. The circuit breaker shall have the proper voltage
ratings, short circuit current rating and continuous current
rating. Rating shall be submitted to NTDC for approval.

(i i) Control panels for circuit breakers. disconnecting


switches and protection system shall be provided at the
Points of Connection. SCADA connections for monitoring

PMC 167
GRID CODE.

and control of circuit breakers, disconnecting switches,


metering and protection devices.

(iii) Disconnecting switches shall be provided for isolating


circuit breaker for maintenance. Disconnecting switches
shall be no-load break type and have the same voltage,
continuous current and fault closing current capability as
the circuit breaker.

(iv) Disconnecting switches shall be provided for isolating


transformer in the substation for maintenance.
Disconnecting switches shall have wiper to prevent arcing
when energizing the transformer. Disconnecting switches
shall be no-load break type and have the same voltage,
continuous current and fault closing current capability as
the circuit breaker.

(v) Grounding switches shall be furnished to ground the bus


bars and transmission line for maintenance.

(vi) Disconnecting and grounding switches shall be


motor-operated to permit remote operation and
interlocking with other switching devices. Control and
electrical interlock for disconnecting and grounding
switches shall be provided in the control panel. Control
shall have interface with SCADA for remote control and
monitoring of the disconnecting and grounding switches.

b. Switching Procedures

All switching activities performed at the Points of Connection


shall be performed under the direction of the NTDC/System
Operator. All other switching activities in the Code
ParticipanUUsers system shall be coordinated with the NTDC.
Proper communication and tagging procedure shall be observed
to prevent accidents and damage to equipment involved in the
switching operation.

c. Testing and Maintenance of Control Facilities

Control and switching shall be scheduled periodically for testing


and maintenance. Adjustments in protection system and control
shall be made at this time if necessary. Equipment found to be
defective would be repaired or replaced, accordingly. Testing
and maintenance shall be coordinated with The System
Operator/NTDC. Tests, calibration, repair and replacement of
equipment shall be recorded and distributed to all concerned
parties.

PMC 168
GRID CODE

PMC3 PROTECTION OF POWER SYSTEM EQUIPMENT

PMC 31 Introduction

Power system security shall depend greatly on the design of the


protection system, as well as, proper coordination with the protective
relay systems and settings in the User/Code Participant's Systems. As
a minimum, a primary protection scheme and a back-up protection
scheme shall be provided for each User/Code Participant's System.
Code Participants/User shall provide protection systems for the
following:

(a) 220 kV and 500 kV grid sub-station bus bars

(b) 220 kV and 500 kV transmission lines

(c) Transformers

(d) Generators

(e) Circuit breakers

(f) 132 kV distribution company substations, and BPC facilities

where applicable

(g) 132 kV transmission lines

(h) Grid station auxiliary systems

PMC 3.2 Types of Protection

The following protective relaying schemes shall be provided for the


following sub-systems:

(a) 220 kV and 500 kV sub-station bus bars


(i) Bus differential relaying

(ii) Lightning protection

(iii) Additional protection for bus bars if needed

(b) (I) 500 kV Transmission Lines

(i) Distance protection Set-I

(ii) Distance protection Set-II

(iii) Transfer trip

PMC 169
GRID CODE

(iv) Line over current and earth fault protection

(v) Line auto re-closing scheme

(c) (II) 220 kV Transmission lines

(i) Distance protection Set -I

(ii) Distance protection Set-II

(i i i) Line overcurrent, and earth fault protection

(iv) Line auto re-closing scheme

(v) Transfer trip

(d) 500/220 kV AND 220/132 kV Transformers

(i) Transformer differential relays

(i i) Ground relays

(i ii) Sudden pressure relays-Bucholtz relay

(iv) Temperature relays

(v) Under/over voltage relays

(vi) Over current relays

(vii) Over fluxing relay

(viii) Over load relay

(ix) Tertiary overcurrent relay

(x) REF relays

(e) Generators

(i) Generator differential relays

(i i) Over current relays

(ii i) Over/under voltage relays

(iv) Loss of excitation relays

(v) Ground relays

(vi) Over/under frequency relays

(f) Circuit Breakers

(i) Breaker-fail relays

(i i) Transfer trip relays

PMC

~
170

~
GRID CODE

(g) 132 kV DISCO substation

(i) Bus differential relays

(ii) Transformer differential relays

(iii) Overcurrent relays

(iv) Over and under voltage relays

(v) Breaker failure relays

(vi) Distance relays

(vii) Ground fault relays

(viii) Transfer trip relays

(ix) Over/under frequency relays


(x) Auto re-dosing

NTDC shall install cross-tripping schemes in the eventuality of loss of a


particular Generator or Power Plant or plant and/or transmission facility
utilizing over/under frequency or voltage protection to protect System
from Total or Partial Collapse.

PMC 3.3 Instrument Transformers

Current Transformers (CTs) and Potential Transformers (PTs) shall be


furnished for the protection systems. CTs and PTs shall have the
accuracy, ratio and burden ratings required to operate the protective
relays. Instrument transformer for protective relaying shall not be
shared with revenue metering equipment. Likewise, instrument
transformers for revenue metering shall not be shared by protective
relaying equipment.

PMC 14 Shunt Reactor Protection

The shunt reactors shall be protected from internal as well as external


faults. Circuit breakers may be provided for shunt reactors to allow for
disconnection of the shunt reactor if an internal fault occurs. If circuit
breakers are not provided for each reactor then protective relaying on
shunt reactors shall be used to trip associated line circuit breakers.
I solation switch shall be provided to allow isolation of shunt reactor and
circuit breakers for maintenance. The following relays shall be provided
for shunt reactor protection as a minimum:

(a) Differential relays

(b) Impedance relays


f
t'

PMC 171

~
GRID CODE

(c) Sudden Pressure Relays - Bucholtz relay

(d) Lightning protection

Protective relay settings shall be coordinated with the line and


substation relays to prevent inadvertent and unwanted operations of
protective relays.

PMC 3.5 Relay Coordination

Protective relays in the various sub-systems of the national power grid


system must be coordinated to prevent unwanted tripping. Proper
coordination of protection systems of the various sub-systems will
enhance the security and safe operation of the system.

To facilitate proper protective relay coordination, relay coordination


software shall be used by NTDC. Relay coordination should be
checked and updated each time a User/Code Participant's system
characteristics are changed, but in any case at least every five years.

Any changes in the User/Code Participant's system that affects the


operation of the power system must be communicated to the NTDC
immediately. The NTDC shall evaluate the impact of the changes to the
protection of the power system, and initiate the necessary adjustments
in the operation and/or changes in protective relay settings.

PMC 3.6 Single Pole Tripping

The line relaying system shall be arranged to allow for single pole
tripping of selected 220 kV and 500 kV transmission lines. One-shot
re-closing of the tripped line shall be allowed according to studies
designed to establish the best re-closing time. If the tripped phase fails
to re-close, all three phases will be tripped accordingly.

PMC3.7 Relay Testing and Maintenance

Periodic testing of all protective relays shall be performed by


NTDC/System Operator to ensure that all protective relays are in good
operating condition, and are set properly. Relays found defective or
with substandard design during the test must be repaired or replaced,
accordingly. Circuit breakers and control circuits shall be tested
periodically, and if parts are found to be defective or deficient, they
should be repaired or replaced.

Protective relaying in the User/Code Participant's System shall be


tested and calibrated annually to ensure that they are in good operating
condition; and that the relay settings are correct. User/Code
Participants may perform testing and maintenance of their protective
relay under supervision of System Operator/NTDC, or request NTDC to
perform testing and setting of their relays for a fee.

PMC 172
GRID CODE

All testing and maintenance performed on the protection and control


equipment, including those of the User/Code Participants, shall be
recorded and a copy submitted to the NTDC for review and archiving.
All test and maintenance records shall be kept for a period of 5 years.

PMC 173
GRID CODE

SCHEDULING AND DISPATCH CODE NO.1 (SOC 1)

GENERATION SCHEDULING

CONTENTS

SOC 1.1 INTRODUCTION SDC-175

SOC 1.2 OBJECTIVE SDC-176

SOC 1.3 SCOPE SDC-177

SOC 1.4 PROCEDURE SDC-177

APPENDIX A
SCHEDULING AND DISPATCH CODE 1
Generation Scheduling and Dispatch Parameters
(GSDPs) SDC-192

APPENDIX B
Power plant, Daily Scheduling, Availability Notices SDC-194

APPENDIX C
GSDP Revision Notice SDC-198

APPENDIX 0
Notification of Revised Availability SDC-199

APPENDIX E
Power Plant, Daily Scheduling, Notices SDC-200

APPENDIX F
Notification of Revised, Availability/Range Availability SDC-201

APPENDIX G (Part 1)
Trading Data: Participating Generators SDC-202
APPENDIX G (Part 2)
Supplemental Energy Bids SDC-203

SDC-1
GRID CODE

SCHEDULING AND DISPATCH CODE NO.1

GENERATION SCHEDULING

SOC 1.1 INTRODUCTION

As a part of functions of the National Transmission and Dispatch


Company (NTDC), Scheduling and Dispatch of generation is
performed by the Syst~m Operator. The Generation Scheduling sub-
code (SDC 1) defines the roles and responsibilities of the System
Operator/NTDC and Code Participants in the scheduling of available
generation facilities, and operation and management of a secure bulk
power transmission system of NTOC.

The purpose of this sub-code is to set out the processes. guidelines.


and procedures for: -

(a) Generation Scheduling


(b) Ancillary Services Scheduling and Dispatch
(c) Generator Outage Co-ordination

SOC 1.1.1 Scheduling and Dispatch Code ·No. 1 ("SOC 1") sets out the ..,., :

Procedure for:

(8) The daily Notification by a Generator to the System Operator of


the Availability of any of its CDGUs in an Availability Notice;

(b) The daily Notification to the System Operator of whether there are
any Parameters which differ from the Contracted Generation
Scheduling and Dispatch Parameters (GSDPs) in respect of the
following schedule day by each Generator in a GSDP Notice;

(c) Each Generator with CDGUs (Centrally Dispatched Generating


Units), the daily Notification to the System Operator in respect of
the next following Schedule Day in an Availability Notice of the
MW Availability of each Generator with CDGUs;

(d) In the case of all Generators under Central Dispatch with PPA I
and/or PSODA as applicable, the submission to the System i
Operator of any revisions to fuel rates (or energy purchase prices, :
as the case may be) by such Generators as per the provisions of,
their PPA and/or PSODA as applicable. .

(e) The issuance by the System Operator of a "Day Ahead

?
Notification" on the day before the Schedule Day as a
"Statement" of which of the Available Generators may be required
for the next Schedule Day.

SOC-1 175
GRID CODE

SCHEDULING AND DISPATCH CODE NO.1

GENERATION SCHEDULING

SOC 1.1 INTRODUCTION

As a part of functions of the National Transmission and Dispatch


Company (NTDC), Scheduling and Dispatch of generation is
performed by the System Operator. The Generation Scheduling sub-
code (SDC 1) defines the roles and responsibilities of the System
Operator/NTDC and Code Participants in the scheduling of available
generation facilities, and operation and management of a secure bulk
power transmission system of NTDC.

The purpose of this sub-code is to set out the processes, guidelines,


and procedures for: -

(a) Generation Scheduling

,I
.'.:
'::
" ,
(b)
(c)
Ancillary Services Scheduling and Dispatch
Generator Outage Co-ordination

I~.
SOC 1.1.1 Scheduling and Dispatch Code 'No. 1 ("SOC 1") sets out the
Procedure for:

(a) The daily Notification by a Generator to the System Operator of


the Availability of any of its CDGUs in an Availability Notice;

(b) The daily NoUfication to the System Operator of whether there are
,:
any Parameters which differ from the Contracted Generation
Scheduling and Dispat9h Parameters (GSDPs) in respect of the
following schedule day by each Generator in a GSDP Notice;

(c) Each Generator with CDGUs (Centrally Dispatched Generating


Units), the daily Notification to the System Operator in respect of
the next following Schedule Day in an Availability Notice of the
MW Availability of each Generator with CDGUs;

(d) In the case of all Generators under Central Dispatch with PPA
and/or PSODA as applicable, the submission to the System
Operator of any revisions to fuel rates (or energy purchase prices,
as the case may be) by such Generators as per the provisions of
.
their PPA and/or PSODA as applicable .

(e) The issuance by the System Operator of a "Day Ahead


Notification" on the day before the Schedule Day as a
"Statement" of which of the Available Generators may be required
for the next Schedule Day. ~

?
SDC-1 175
GRID CODE

Provided that the System Operator, in the process of Scheduling and


Dispatch of generation facilities shall have the following consideration:
All the information contained in Appendices A-G of SOC 1 needs to be
provided by all the COG Us, which are declaring their Availability for the
next Schedule Day.

SOC 1.1.2 The System Operator shall take into account the impacUeffects of power
transfers across any External Interconnection when preparing its
Generation Schedule (including taking into account the cost of any such
transfers when compiling the "Generation Schedule"); and any power
transfers across the NT DC's Transmission System.

SOC 1.1.3
(a) This sub-code (SOC 1) requires that each Generator under
Central Dispatch to submit an Availability Notice, the form of
which is set out in, Appendix B, which needs to be submitted in
writing or through telephone; and the required information is to be
submitted in full in such a notice.

(b) The notice, if given through telephone, must then be confirmed by


facsimile and in writing as soon as possible thereafter (and in any
event be sent to the System Operator within 2 hours). Where a
facsimile and written notice are so sent by way of confirmation,
each notice shall state clearly that it is in confirmation of a notice
already given by telephone and must state the exact time at
which the notice was given by telephone.

SDC 1.1.4 In this SOC 1, the term "Notice Submission Time" shall mean,
10.00 a.m.

SDC 1.1.5 For the purposes of this SOC 1, any reference to the fuel used for a
CDGU shall, in the case of a PPA CDGU (regardless of the entity it is
contracting with) be construed as a reference to the Des'lgnated Fuel.

SOC 1.2 OBJECTIVE

To enable the System Operator to prepare a "Generation Schedule"


(utilising, amongst other things, a Merit Order) to be used in the
Scheduling and Dispatch process, and thereby to ensuring (as far as
possible): -

(a) the integrity of the NTDC System;

(b) the security and quality of supply;

(c) compliance with emissions requirements if any; and

(d) that there is sufficient generation capacity to meet total demand


at all times together with an appropriate Reserve Margin (Sum of
Operating and Contingency Reserve). ~

SDC-1 176
GRID CODE

The purpose of this sub-code is also to enable the System Operator to


prepare and issue the "Day-ahead Notification".

SOC 1.3 SCOPE

SOC 1 applies to NTDC and to all the Generators under Central


Dispatch with regard to their Generating Plants.

soc 1.4 PROCEDURE

SOC 1.4.1 Availability Notice

SOC 1.4.1.1.a
(a) Each Generator including those at a Power Station with multiple
Generating Units shall, by no later than the notice submission
time each Schedule Day, notify the System Operator by means of
an Availability Notice, in the form set out in Appendix B to this
SOC 1 or in such other form as the System Operator/NTDC may
specify with the approval of NEPRA, notify to each Generator,
from time to time, the Availability of each of its COG Us.

(b) The Availability Notice shall state the Availability of the relevant
CDGU for each period in the following Schedule Day (subject to
revision under SOC 1.4.2.5(a)).

SOC 1.4.1.1.b In the case where a PPA CDGU (with/without PSODA) is capable of
firing on different fuels, then the Generator must submit an Availability
Notice in respect of each Designated Fuel for the CDGU, each
containing the information set out in SOC 1.4.1.1.a above for each
Designated Fuel and each marked clearly to indicate for which
Designated Fuel the Availability Notice applies to.

SOC 1.4.1.1 .c
(a) Notwithstanding that a CDGU has been declared unavailable. the
Generator shall submit all the information that it would have
submitted under this SOC 1 had the CDGU been declared
Available.

(b) The System Operator shall use its reasonable endeavours to


seek uniform treatment in terms of availability of Gas turbines for
start-up purposes with due regard to their PPA and/or PSODA
conditions as applicable.
soc 1.4.1.1.d
(a) In relation to gas turbine PPA CDGUs (the Availability of which (
varies according to ambient temperature). an Availability Notice I"~
submitted by a Generator to NT DC for the purposes of declaring :
the level of Availability of such CDGU must state the Availability i
at an ambient temperature of 15°C. ,,1
(b)

SDC-1
GRID CODE

a PPA CDGU as specified in the relevant Schedule to their Power


Purchase Agreement (PPA) and/or Power Station Operation &
Dispatch Agreement (PSODA) adjusted by the temperature
correction factor set out in the relevant schedule of the relevant
Power Purchase Agreement (PPA) and/or Power Station
Operation & Dispatch Agreement (PSODA) by applying that
absolute MW value.
(c) In relation to gas turbine PPA CDGUs, the term "Availability" shall
be construed accordingly.
SOC 1A.1.1.e In relation to any steam turbine PPA CDGU (with/without PSODA) at a
power plant which is capable of firing both on gas (which may include
a mixture of gas and oil) and on oil, the System Operator may, in
respect of any settlement period (and/or successive settlement
periods) give notice (an "0 verburn Notice") to the relevant Generator
with as much notice as possible and in any event (except in the
circumstances specified in (c) below) not less than 24 hours before the
start of such settlement period (or the first such period) with the
following effect and subject as follows:

(a) the Contracted Capacity (Gas) shall thereby be increased to


Overburn Contracted Capacity in respect of such settlement
period (or periods) following which the Generator shall re-declare
the Availability of the CDGU in an Availability Notice (and, for the
avoidance of doubt, such increase shall only apply for the
settlement periods specified in the Overburn Notice);

(b) the aggregate number of settlement periods in any period of 24


hours and in any period of 12 months for which Overburn Notices
may be given shall be no greater than the limits set out in the
respective Schedule of the relevant Power Purchase Agreement
(PPA) and/or Power Station Operation & Dispatch Agreement
(PSODA) as applicable;

(c) NTDC shall waive the rebate of Availability Payments for late
declaration of Availability under relevant schedule to the relevant
Power Purchase Agreement (PPA) and/or Power Station
Operation & Dispatch Agreement (PSODA) as applicable if the
Overburn Notice is issued by NTDC less than 24 hours in
advance of the start of the relevant settlement period.
SDC1.4.1.1.f
(i) The Availability Notice issued by the Generator at a Power Plant
where CDGUs can be operated Singly or in pairs, in accordance
with SOC 1.4.1.1 (a) Shall, in addition to the information required
by SOC 1.4.1.1 (a), state the CDGUs, that have been declared to
be Available for the next following Schedule Day, shall be
operated in pairs; and which CDGUs shall be singly operated.
For this purpose;

SOC-1 178
GRID CODE

SOC 1.4.1.2 Availability of Generating Plant

(a) Each Generator under Central Dispatch Power Station with


multiple Generating Units shall, subject to the terms and
conditions of the relevant Power Purchase Agreement (PPA)
and/or Power Station Operation & Dispatch Agreement
(PSODA) throughout the term of the Power Purchase Agreement
(PPA) and/or Power Station Operation & Dispatch Agreement
(PSODA) relating to a particular CDGU, maintain, repair, operate
and fuel its CDGU as required by Prudent Operating Practices
and any legal requirements with a view to providing the power
delivery, system support services, Contracted Capacity, and the
Contracted GSDPs.

(b) All the Generators under Central Dispatch Power Station with
multiple Generating Units shall use all reasonable endeavours to
ensure that it does not at any time declare by issuing or allowing
to remain outstanding an Availability Notice, or a GSDP Notice
which declares the Availability or GSDPs of the CDGU at levels or
values different from those that the CDGU could achieve at the
relevant time under its Purchase Agreement (PPA) and/or Power
Station Operation & Dispatch Agreement (PSODA) with NTDC
as applicable except under unavoidable circumstances with the
prior consent of the System Operator.

(c) Provided that nothing contained in this Grid Code shall require the
Generator to declare levels or values better than the Contracted
Capacity and the Contracted GSDPs in respect of a PPA CDGU.

SOC 1.4.1.3 If at any time when the Availability of a CDGU is zero, an Availability
Notice shall be given increasing the Availability of the CDGU with effect
from a specified time, such Notice shall (in the case of a steam turbine
CDGU) be construed as meaning that the CDGU is capable of being
synchronised with the NTDC's System at that specified time or, (in the
case of a gas turbine PPA CDGU), capable of being started at that
specified time. A dispatch instruction issued by the System Operator to
synchronise the CDGU to the NTDC's System or, as the case may be,
start the CDGU, at or after the specified time shall be a valid dispatch
instruction (regardless of the minimum time to synchronise specified in
the GSDPs).

SOC 1.4.1.4 If at any time when a CDGU is synchronised with the NTDC's System,
the Generator issues an Availability Notice increasing the level of
Availability of the CDGU from a specified time, such notice shall be
construed as meaning that the CDGU is capable of being dispatched to
increase generation to levels greater than the previously prevailing level
of Availability up to the level specified in the new Availability Notice but
commensurate with the maximum loading rate declared for the CDGU
as a GSDP from the specified time. ~

SOC-1 179
GRID CODE

SOC 14.1.5 If at any time when a COGU is synchronised with the NTDC's System,
the Generator issues an Availability Notice decreasing the level of
Availability of the COGU from a specified time, such Notice shall be
construed as meaning that the COGU is capable of maintaining output at
the level of the prevailing Availability until the time specified in the Notice
and thereafter, shall be capable of maintaining output to the level which
would have been achieved if a dispatch instruction had been given to
de-load, with effect from the specified time, at the maximum de-loading
rate declared for the COGU in the GSOP Notice at such time down to
the level of Availability specified in the new Availability Notice.

SOC 14.2 GENERATION DISPATCH METHODOLOGY

soc 14.2.1 GSDPs Revisions

Any revisions to the Contracted GSDPs during Real Time Operations


must be well documented and agreed to with the System Operator
including the nature and quantification of the revision, duration of such
revision, reason for the revision, and anticipated time when the
Generator shall be back to its Contracted GSOP values.

(a) (i) By no later than the notice submission time each Schedule
Day, each Generator shall in respect of each of its COGU
that has been declared Available in an Availability Notice
submit to the System Operator in a revised GSDP Notice, in
the form set out in Appendix C to this SOC 1 or in such other
form as the System Operator may notify to each Generator
from time to time.

(ii) In the case of a PPA COGU (with/without PSOOA), any


revisions to the GSDPs compared with the Contracted
GSOPs to apply for the next following schedule day in the
form set out in Appendix C to this SOC 1 or in such other
form as NTDC may specify from time to time.

(b) In the case of any revision to the GSOPs, as to which the


Generator should, acting in accordance with prudent operating
practices, have some flexibility either in the revision itself or in the
time-frame in which the revision is to take place, the System
Operator may, acting reasonably, suggest an amended revision
to the Generator (including a statement to provide that there shall /
be no further revision) and/or an amended time at which the
revision is to take effect. Insofar as the System Operator is able
to do so without breaching any obligations regarding
confidentiality contained either in the NTOC's Licence or in any
Agreement, the System Operator shall notify the Generator of the
reasons for such amended revision request in such degree of
detail as the System Operator considers reasonable under the
circumstances. If the Generator agrees to such suggestion of the
System Opera tor (such Agreement not to be unreasonably
withheld by either Entity), the Generator shall use '-t-R-R-E-c
~<.q
-0
180 ~.
SDC-1
GRID CODE

endeavours to accommodate such suggestion, and submit a


revised GSDP Notice accordingly. In any event, the System
Operator may require such further information on the revision as
is reasonable, and the Generator must give the System Operator
such information as soon as possible. None of the revisions to the
GSDPs shall be in violation of the terms of the specific PPA
Agreements with NTDC. Financial impacts of such deviations or
revisions in the Contracted GSDPs shall be assessed by the
NT DC/System Operator, and communicated with the Generator.

The methodology of calculating the financial impacts of GSDPs


revisions requested by the Generator shall be sufficiently detailed
in the approved Commercial Code.

(c) In the case where a CDGU is capable of firing on different fuels,


then the Generator must submit a GSDP Notice in respect of
each Designated Fuel for the CDGU (or fuel in the case of an
Externally-connected CDGU), each containing the information set
out in (a) above for each Designated Fuel (or each fuel) and each
marked clearly to indicate to which Designated Fuel (or fuel) it
applies to.

(d) A Generator must notify NTDC in writing in the form set out in
Appendix C of this SOC 1 as soon as it becomes aware, acting in
accordance with prudent operating practices, if (whether due to a
defect in the CDGU or in its associated Power Plant equipment)
any of its CDGUs is unable to meet the Spinning Reserve
capability set out [in the case of a PPA CDGU (with/without
PSODA)] in the Sustained Load Diagram attached to relevant
Schedule of the Power Purchase Agreement (PPA) and/or
Power Station Operation & Dispatch Agreement (PSODA) as
applicable, and submitted pursuant to the Planning Code or
Connection Code or in the relevant applicable documents.

Such notification must be made by submitting a GSDP Revision


Notice (Appendix C) in relation to item 2(c) of Appendix A to this
SOC 1. In accordance with the Generator's obligations under
SOC 1.4.1.2(b), such reserve characteristics may only be
amended (with the System Operator's consent) in the event of a
defect in or failure of a CDGU or any associated Power Plant
equipment. Such amendment shall only take place so long as it
takes place in accordance with Prudent Operating Practices, legal
requirements of the Power. Purchase Agreement (PPA) and/or
Power Station Operation & Dispatch Agreement (PSODA) as
applicable for the relevant CDGU or associated Power Plant
equipment to be repaired; and such repair must re-instate the
Spinning Reserve capability to its level stated in the GSDPs or to
such other level as the System Operator may propose acting in
accordance with prudent operating practices, and agree, taking
into account the provisions of SOC 1.4.1.2(a), and the Generator '
must then submit a GSDP Revision Notice re-declaring its re- __- _
«o'-NER REG
:--,c.. u<:
----~------------------------------------------------~_h~~~ ~~
SDC-1 181 APPROVED %
..J BY ~
'io. THE AUTHORITY ("',--2
GRID CODE

instated Spinning Reserve capability accordingly. The Generator;


must specify to the System Operator of the nature of any such.
defect or its failure; and of the Generator's best estimate, acting
as a reasonable and prudent Generator of the time it shall take to
complete the repair and restore the reserve characteristics to their
former Contracted levels.

SOC 1.4.2.2 Other Generation Relevant Data

(a) By no later than the notice submission time each Schedule Day,
each Generator shall in respect of each CDGU which has been
declared Available in an Availability Notice under SOC 1.4.1.1 in
respect of the following Schedule Day submit to the System
Operator in writing (in the form set out in Appendix B to this SDC1
or in such other form as the System Operator may notify to each
Generator from time to time) details in relation to the following
Schedule Day of any "newly arisen special factors" which in the
reasonable opinion of the Generator may have a material effect
on the likely output of its Generating Unit. The notice must be
consistent with the Generator's obligations under the provisions of
SOC 1.4.1.2(b).

(b) In the case where a CDGU is capable of firing on different fuels,


the Generator must submit details in respect of each Designated
Fuel for the CDGU, each containing the information set out in (a)
above for each Designated Fuel, and each marked clearly to
indicate to which Designated Fuel (or fuel) it applies to.

SOC 1.4.2.3 Fuel Rate

(a) The generation or energy purchase prices including any revisions


to the energy purchase prices for a PPA CDGU in respect of the
week beginning on the Schedule Day falling on the next following
Monday shall be deemed to be submitted by that Generator by
the notice submission time each Tuesday.

(b) In so far as not revised or if the fuel rate in the energy bid price
notice is higher than that deemed to have been submitted under
(a) above, the. most recently submitted generation or energy
prices shall apply for the relevant week.

Supplemental Energy Bid

(a) Each Generator may in respect of each Generator each day


prior to the notice submission time submit to the System
Operator a supplemental energy bid, if any, in accordance with
the approved commercial arrangements as per the provisions
of the approved Commercial Code.

SDC-1 182
GRID CODE

Excess Output

(a) Each Generator may in respect of each PPA CDGU (with/without


PSODA) on each day prior to the notice submission time submit
to the NTDC a set of generation or energy prices consistent with
its PPA in respect of the following Schedule Day in relation to
output over and above the Contracted Capacity for the relevant
Declared Fuel or Designated Fuel.

Unit Nominations

(b) Each Generator shall a day prior to the notice submission time
submit to the System Operator a Unit Nomination in accordance
with approved commercial arrangements as specified in the
approved Commercial Code.

(c) Before the notice submission time for each schedule day, each
Generator must give the System Operator the information
referred to in paragraph (c) below. The information must be in
the form set out in Appendix G to this SOC 1 or such other form
as the System Operator may specify from time to time. All Unit
Nominations are assumed to be expressed as "Generator Sent
Out Energy", and it is the responsibility of the Generators
concerned to take that into account when submitting Unit
Nominations.

(d) Each Generator must notify the System Operator of the number
of kWh of active electric energy each of its Generating Units
wants to deliver to the NTDC's System as power supply by the
Generator for each settlement period during the Schedule Day.
Unit Nominations must include:

(i) If requested by the System Operator, specify the number


of kWh of energy being supplied to each User;

(ii) Be in whole numbers of kWh.

(e) When converted into MW at the generator terminals, the Unit


Nomination for a particular Generator for a given settlement
period must not exceed the Availability of the Generating Unit
for that settlement period.

(f) Unit Nomination of a Generating Unit for a given settlement


period must not be less than minimum generation of that
particular Generator.

SDC-1 183
GRID CODE

SOC 1.4.2.4 Generating Unit Works Units

Once per week, on a day and time specified by the System Operator
from time to time but not less than two (2) hours before the occurrence
of maintenance outage, each Generator must, in respect of each of its
Power Plants, unless the data is supplied in some other agreed and
approved form, submit to the System Operator, in writing, details of the
Generating Unit Works Units for that Power Plant consumed by that
Power Plant since the last submission under this SOC 1.4.2.4, together
with such other information as the System Operator may require in order
to calculate the Generating Unit Works Units consumed by each COGU
at ttlat Power Plant.

SOC 1.4.2.5 Further Revisions

(a) A Generator Power Station with multiple Generating Units may


make revisions to the Availability Notice submitted to the System
Operator under SOC 1.4 .1.1 at any time after submission of the
Availability Notice in accordance with its obligations under
SOC1.4.1.2(b) by submission of a revised Availability Notice
which shall be in the form set out in Appendix 0 - F to this SOC 1
or in such other form as the System Operator may reasonably
notify to each Generator from time to time. In the event that the
Generator submits a maintenance outage notice under OC4 or
NTOC submits a post-event notice under OC 12 in relation to any
part of the period covered by the Availability Notice at any time
after submission of the Availability Notice, the Generator shall be
deemed to have submitted a revised Availability Notice consistent
with such Outage Notice or post event notice, as the case may
be. However, in the case where the Outage Notice is not issued
immediately and does not specify the reduced Availability, the
Generator must, as soon as possible, submit a revised Availability
Notice reflecting its reduced Availability.· The System Operator
shall, insofar as it is reasonably possible, take account of such
revisions in the preparation of its "Generation Schedule".

(b) If any of the data submitted to the System Operator under SOC
1.4.2.1 and SOC 1.4.2.2 changes, a Generator must (in the case
of data submitted under SOC 1.4.2.1 by means of a GSOP
Notice) make revisions to such data and must notify the System
Operator of any revisions to any previously revised data by
submitting another Revised GSOP Notice (in the form set out in
Appendix C to this SOC 1 or in such other form as the System
Operator may reasonably notify to each Generator from time to
time) and must notify the System Opera tor of any Other
Generation Relevant Oata of which it becomes aware at any time
after any original submission in writing. The System Operator
shall, insofar as it is reasonably possible, take account of such
revisions or notifications. The provisions of SOC 1.4.2.1 (b) shall

SDC-1 184

,\9,/
GRID CODE

apply to revisions under this paragraph to data submitted under


SOC 1.4.2.1 and SOC 1.4.2.2.

SOC 1.4.2.6 (a) (i) Insofar as any data submitted or deemed to have been
submitted on any particular day in any Availability Notice,
GSOP Notice, or Notice of Other Generation Relevant Data
or any revision thereto is inconsistent with any other data in
any other such notice, then the most recently submitted
data which, if substituted for the inconsistent data, would
make the data in such notices consistent, shall apply for the
next following Schedule Day.

(ii) Insofar as an Availability Notice is not submitted, the


Generator shall be deemed to have submitted an
Availability Notice by the notice submission time stating that
the Availability of the relevant CDGU for the whole of the
following Schedule Day shall be the level of Availability
declared in respect of the final settlement period of the
current Schedule Day.

(iii) Insofar as not revised, the most recent GSDP Notice to


have been submitted shall apply for the next following
Schedule Day.
(iv) Insofar as not revised, the most recent GSOP Notice
relating to Other Generation Relevant Data to have been
submitted shall apply for the next following schedule day.

(b) As a general requirement, the Generator must ensure that the


data in any Availability Notice, GSDP Notice, or Notice of any
Other Generation Relevant Data or any revision thereto is
consistent with its obligations under SOC 1.4.1.2(b) and the
Power Purchase Agreement (PPA) and/or Power Station
Operation & Dispatch Agreement (PSOOA) with NTOC.

SOC 1.4.2.7 Additional Supply Data

The following procedures shall be followed to allow the System


Operator to develop a daily "Schedule" for dispatching:

(a) Sixty days prior to 1 April of each year, all bilateral contracts
shall be submitted to NEPRA, NTDC, CRPEA and the System
Operator for review and approval.

(b) On or before 1 April of each year, all Generators, including'


Hydel and Nuclear shall submit a declaration of Availability to
the System Operator covering a period of next one year.

(c) Demand-side Users (distribution companies and SPCs) shall


submit a daily energy purchase requirement on an hourly basis.
The NTOC shall calculate, and issue NTDC tran

SDC-1 185
GRID CODE

losses for billing after-the-fact as per the provisions of the


approved Commercial Code.

SDC 1.4.3 Compilation of the Generation Schedule

SDC 1.4.3.1 A Generation Schedule shall be compiled daily by the System Operator
as an "Internal Statement" of which CDGUs and/or power transfer
across any External Interconnection may be required for the next
following Schedule Day.

SDC 1.4.3.2 Merit Order

Subject as provided below, a Merit Order shall be developed/compiled


for each schedule day from the Incremental Price and the No-Load Price
(which together, in relation to a particular Designated Fuel or Declared
Fuel, as the case may be, shall be known as the "Merit Order Price
Set"), which is applicable on the basis of ascending prices so that the
CDGU at the head of the Merit Order shall be that CDGU which has the
lowest Incremental Price per MWh or KwH; and that at the foot of the
Merit Order shall be that CDGU which has the highest Incremental Price
per MWh or KwH while taking account of average CDGU output and
Generating Unit Works Units based on the information supplied by each
Generator in SOC 1.4.1 through SDC1.4.2.6.
Once compiled, the Merit Order shall be used, subject as provided in this
SOC 1, to determine which CDGU is to be scheduled and dispatched.

If there is more than one Merit Order Price Set offered, then the CDGU
shall appear in the Merit Order for each Merit Order Price Set submitted.

SDC 14.3.3 In compiling the "Final Generation Schedule", the System Operator shall
take account of, and give due regard and weightage to the following
factors:

(a) NTDC's Transmission system constraints from time to time, as


determined by the System Operator;

(b) The level of generation output covered by Unit Nominations;

(c) In respect of COG Us, the values of their Contracted GSDPs


registered under this SOC 1 and other information submitted
under SOC 1.4.2.1 and SDC 1.4.2.2.

(d) The Start-up Price of each CDGU;

(e) The requirements, as determined by the System Operator for


voltage control and MVAr reactive reserves:

(i) CDGU stability, as determined by NTDC;

(ii) In respect of CDGUs, with lower emission level;

SDC-1 186
,\r!",) "
GRID CODE

(iii) Other matters to enable NTDC to meet its Licence


standards and obligations;

(f) The need to provide the required Operating Margin by using the
various categories of Reserve as specified in OC4 and OC5), as
determined by the System Operator;

(g) The requirements, as determined by the System Operator for


maintaining Frequency Control;

(h) Monitoring, testing and/or investigations to be carried out, or


being carried out, under OC12; testing to be carried out, or being
carried out, at the request of a User under OC11.2 and/or
commissioning/acceptance testing prior to connection or
re-connection or commissioning under the Connection Code of
Grid Code;

(i) System tests being carried out or to be carried out under OC11;

U) Any "Take or Pay" contract for the purchase of fuel to which a


Generator is a party, and the terms of which have been agreed to
by the NTDC and which impacts the NTOC's System, and/or the
terms of any other contract to which NTOC is a party of, and
which may, in its opinion be relevant;

(k) Operation of Generating Plant over periods of low demand to


provide, in the System Operator's view-point, a sufficient
Minimum Demand Regulation (MOR);

(I) The need for a Generator to comply willl requirements in respect


of emissions in relation to a Generator's Power Plant which
contains PPA COGUs;

(m) The inability of any COGU to meet its full Spinning Reserve
capability; and

(n) The availability and cost of power transfers across any External
Interconnection.

SOC 1.4.3.4 Taking into account of and applying the factors referred to in SOC
1.4.3.3 above, the "Final Generation Schedule" shall be compiled by the
System Operator to Schedule such COGUs which have been declared
Available in an Availability Notice, and are the subject of a Unit
Nomination, and power transfers across any External Interconnection:

(a) The System Operator shall ensure that all COGUs are Scheduled
in accordance with their Unit Nominations;

(b) In accordance with the Merit Order, starting with the least-cost
COGU at the head of the Merit Order; and taking into account the~_ _
cost of power transfers across any External Interconnection; '(O\"JER RtG
~iV GI(:
......~ ~/'
----------------------------------------------------~~~~- 0
SDC-1 187 ~
GRID CODE

(c) As shall in aggregate (after taking into account power delivered


other than from COG Us) be sufficient to match at all times (to the
extent possible having due regard to the Availability of CDGUs
and to the availability of power transfers across any External
interconnection) the forecasted NTOC's total system demand
(derived as specified in OC 2.4) together with such Operating
Margin as specified in OC 5.; and

(d) As shall in aggregate be sufficient to match minimum system


demand levels together with sufficient Minimum Demand
Regulation.

Due to taking into account of and application of the factors stated in


SOC 1.4.3.3 shall mean that, in general, the strict Merit Order as stated
in SOC 1.4.3.2 may not necessarily be the final outcome in the shape of
"Final Generation Schedule".

SOC 1.4.3.5 After the completion of the scheduling process, but before the issuance
of Day-ahead Notification, the System Operator may consider it
necessary to make adjustments to the output of the scheduling process.
Such adjustments may be required to be necessary due to any of the
following factors:

(a) Changes in Availability and/or GSDPs of COGUs notified to the


System Operator after the commencement of the scheduling
process;

(b) Changes to NTOC load demand forecast(s);

(c) Changes to NTOC's system constraints emerging from the


iterative process of scheduling and network security assessment;

(d) Changes to COGU requirements following Notification to NTDC of


the changes in the capacity of a Generator to provide a special
action as described in SOC 2;

(e) Changes to COGU requirements within constrained groups,


following re-appraisal of NTOC load demand forecasts within that
constrained group;

(f) Changes to any conditions, which in the reasonable opinion of the


System Operator, which would impose increased risk to the
NTOC's System, and would therefore require the System
Operator to increase Operating Margin;

(9) Unpredicted NTOC's Transmission System (Transmission and


Grid) Outages, and Outages on 132 kV transmission lines
connecting power stations, which places more than the equivale:::;.:_~
of one large COGU at risk to a secured fault; ~()\"lE.R REGu
~ ~~
ff 0
---------------------------------------------------1~~~~~ ~
SOC-1 188
GRID CODE

(i) Unpredicted Outage of a Generating Plant eqUipment


which imposes increased risk to the plant output;

(ii) Volatile weather conditions giving rise to low confidence in


the System Operator's load demand forecasts;

(iii) Severe weather conditions imposing high risk to the total


NTDC's system demand; and

(h) Any known or anticipated limitations and/or deficiencies of the


System Operator's process of scheduling of generating and
transmission facilities.

(i) Unexpected Outages on major 132/66 kV transmission facilities


of distribution companies.

U) Unexpected Outages of large Embedded Generators connected


to the distribution company's Systems after the commencement
of scheduling process.

SOC 1.4.3.6 When:

(a) Adverse weather is anticipated;

(b) There is a high risk to the whole or part of the NTDC's System;
(c) Load demand management and control has been instructed by
the System Operator;

(d) A Total or Partial Shutdown exists;

These factors can result in a COGU being chosen "other than in


accordance with the Merit Order" to a greater degree than would be the
case when merely taking into account and giving due regard &
weightage to the factors listed in SOC 1.4.3.3 in order to seek to
maintain the integrity, security. and adequacy of the NTDC's System.

SOC 1.4.3.7 (a) The synchronising and de-synchronising times shown in the Day Ahead
Notification are Indicative only; and it should be borne in mind by all the
Generators that the actual dispatch instructions may reflect more or
different COGU requirements than in the Day Ahead Notification.
although they should (subject to SOC 2) reflect Unit Nominations. The
System Operator may issue dispatch instructions in respect of a COGU
which may not have been declared "Wholly Unavailable" in an
Availability Notice. The Generators with CDGUs must ensure that their
Generating Units are available, able and ready to be synchronised at the
times scheduled but only if so dispatched by the NT DC by issue of a
dispatch instruction. The Generators shall, as part of a revision to the
GSDPs. indicate to the System Operator the earliest time at which a
dispatch instruction is required to meet the scheduled synchronising
time. o\~ER Rt:-
<? C"G
<i!v ~<.;
--------------------------------------------------~~~~~~.
SDC-1 189 PPROVE 0
~~ -.J
lU .
~ BY ~
\~~t7A ~o THE AUTHORITY J
V,
f;. "
k'
GRID CODE

SOC 1.4.3.8 Content of Day Ahead Notification

The information contained in the Day Ahead Notification shall indicate,


on an individual CDGU basis, the period, MW loading and Declared Fuel
for which it is scheduled during the following Schedule Day. In the case
of a CDGU which is capable of firing on two different Designated Fuels,
it shall also indicate the Designated Fuel for which it is scheduled during
the following Schedule Day. If no declared fuel andlor, where relevant,
designated fuel is contained in the Day Ahead Notification, then the
most recently specified declared fuel andlor, where relevant, designated
fuel shall be treated as having been indicated.

SOC 1.4.3.9 Issue of Day Ahead Notification

(a) The Day Ahead Notification shall be issued in writing to the


Generators by 1700 hours each day, provided that all the
necessary information from the Generators has been made
available by no later than the notice submission time. However, if
on any occasion, the System Operator is unable to meet this
time, NTDC reserves the right to extend this time scale for the
issuance of Day Ahead Notification to the extent necessary.

SOC 14.3.10 The Day Ahead Notification received by each Generator shall contain
information relating to its CDGUs only.

SOC 14.3.11 Minimum Demand Regulation (MDR)

It is a requirement for running the NTDC's System that all synchronised


COGUs must, at all times, be capable of reducing output necessary to
allow a sufficient regulating Operating Margin for adequate Frequency
Control. The System Operator shall monitor the output data of the "Final
Generation Schedule" against forecasted total system load demand to
see whether the level of MDR for any particular period is insufficient, and
may take any shortfall into account in the scheduling and dispatch
process.

SOC 1.4.3.12 Data Requirements

Appendix A sets out the GSDPs for whiCh values are to be supplied by a )
Generator in respect of each of its CDGUs by no later than the notice,
submission time on the day prior to the Schedule Day. :,
\

SOC 1.4.3.13 Verification of Contract Fulfilment

The NTOC shall be responsible for the enforcement of the PSODA


with the Generators. The NT DC shall also be responsible for the
verification of contract fulfillment for the purpose of account settlement.
The System Operator shall prepare a report of all dispatch transactions
with the exact time and amount of power delivered to the network; and
amount of power delivered to the Code Participants and other Users. ~__
~O""lER R£c
u
A~CJ ~/-
-----------------------------------------------------,-,7v~--
SOC-1 190 l<.J-,o
0
-.J --<.
UJ BY 1>
l .J C
f' .~ THe AUTHORITY . I
GRID CODE

separate report shall be prepared by the System Operator for the


ancillary services provided to the NTDC Transmission System.

For the purpose of Verification, the NTDC shall provide accurate active
and reactive power measuring instruments at the Points of Connection
between NTDC and Code Participants. For billing purposes and
account settlement, the NTDC shall provide revenue metering at the
Points of Connection, as specified in the Protection and Metering
Code. The information shall be collected by the NTDC SCADA System
and communicated to the NTDCI System Operatorl as appropriate.

The System Operator has the sole authority to Schedule and Dispatch
generation, manage and discipline a secure and safe operation of the
NTDC's Transmission System. The Code Participants who are
contracted to supply generation power supplies must comply with the
dispatch instructions of the System Operator, in totality, regardless of
their circumstances or prevailing conditions. Any Failure of Code
Participant to comply with dispatch instructions of the System Operator
shall be subject to penalties, in accordance with the provisions of the
Grid Code under Code Management sub-code.

NTDC shall oversee compliance and impose penalties, if necessary.


NEPRA shall consider failure to comply with the System Operator's
dispatch instruction as an infraction to the Power Purchase Agreement
(PPA) and/or Power Station Operation & Dispatch Agreement
(PSODA), and shall use the available information to evaluate
continued eligibility of respective NEPRA licence of the Code
Participant/User of NTDC's Transmission System.

NTDC/System Operator shall notify the Code Participant, Review


Panel, and NEPRA of each infraction not agreed to by the offending
Code ParticipanUUser in writing, immediately. If there is a justified
cause for the infraction, the Code Participant must reply in writing to
SO Review Panel, and NEPRA within seven (7) days after receiving
the infraction notice. Review PanelJNEPRA shall review justification
submitted by the offending Code PartiCipant within seven (7) days from
the receipt of the letter of justification. Review Panel/NEPRA shall
accept or reject the justification and issue their final adjudication
including imposition of penalties, if any.

SDC-1 191
GRID CODE

APPENDIX A

(SCHEDULING AND DISPATCH CODE 1)

Generation Scheduling and Dispatch Parameters (GSDPs}

A. For each CDGU:-

1. (a) in the case of steam turbine CDGUs, synchronising times


for the various levels of warmth;

(b) in the case of gas turbine CDGUs, the time from initiation
of a start to achieving dispatched load.

2. Basic data:

(a) Minimum Generation in MW;

(b) Governor Droop (%);

(c) Sustained Response Capability.

3. Two shifting limitation (limitation on the number of Start-ups per


schedule day);

4. Minimum on time;

5. Block load following synchronisation in MW;

6. Maximum loading rates for the various levels of warmth and for
up to two output ranges.

7. Maximum de-loading rates for up to two output ranges;

8. The MW and MVAr capability limits within which the CDGU is


able to operate as shown in the relevant Generator Performance
Chart;

9. Maximum number of changes to the dispatched fuel per 24 hour


period;

10. Maximum quantity of oil in "ready-use tank(s)" and associated


pipe work;

11. Maximum number of changes to the designated fuel per 24 hour


period;

12. Minimum notice to change the designated fuel;

13. Maximum number of on load cycles per 24 hour period, together


with the maximum load increases involved; and

SDC-1 192
GRID CODE

14. Settings of the Unit Load Controller for each CDGU for which a
Unit Load Controller is required under CC7.5.5.

15. in the case of gas turbine CDGUs only, ttle declared peak
capacity.

In the case of a Gas Turbine Unit, only the data applicable to Gas
Turbine Units should be supplied.

B. For the Power Plant of which the CDGU forms part:-

1. Time between synchronising different CDGUs in a power plant


taking account of actual off-load periods for the various levels of
warmth; and

2. Time between de-synchronising different CDGUs in a Power


Plant.

SDC-1 193
GRID CODE

APPENDIX B

(SCHEDULING AND DISPATCH CODE 1)

FACSlf.IILE
TO Page 1 of 4
FAX
FROM

J POWER PLANT· DAIL Y SCHEDULING NOTICES

AVAILABILITY NOTICE
Tne ayailabllity of each CDGU at [ ] Power plant for the schedule day to which this notice refers is shown on page
2 attached.

2. ENERGY BID PRICE NOTICE (Rs/MWHr· enter bid price where appropriate)
[ Power Limited] offers NTDC the following energy prices (which are lower than the contracted prices) for the
Schedule Day to which this notice refers.

[Fuel) (Fuel)

[Fuel\ (Fuel)

[Fuel]

3 GSDP NOTICE

Tne Generation Scheduling and Dispatch Parameters for each CDGU at [ ) Power Plant for the Schedule Day to
which this notice refers are as given in Schedule 1 of the relevant Power Purchase Agreement (PPA) or
Power Station Operation & Dispatch Agreement (PSODA)

YES / NO (Delete as appropriate)

(11110, each GSDP which varies from Schedule 1 must be shown on page 3 at1ached
If 'rES. page 3 shall be omitted)

4 OTHER GENERATION RELEVANT DATA

5 DECLARATION

Tnese notices are issued by ( Power Limited) in respect of the Centrally Dispatched Generating Units (C DGUs)
al [ ] Power Plant in accordance with the requirements of SOC 1.

We declare that the figures and other information given in the notices fully renect the actual capability of the CDGUs.

The notices are applicable to Schedule Day:

Signalure: _ _ _ _ _ _ _ _ _ _ Name: _ _ _::--:-_ _.,.-_ _ _ _ _ _ _ _ _ _ _ _ _ __


(in block capitals)
POllllon: Commercial Engineer/Control Engineer (delete as applicable)

Dale!Time of Issue:

SDC-1 194

,\(]
GRID CODE

AVAILABILITY NOTICE
Paqe 2 of 4
Settlement [UNITS ON OIL] [UNITS ON GAS] GAS TURBINES
Period REDUCTION
2 2 2
Contracted
Capacity

0000· 0030
0030· 0100
0100·0130
0130·0200
0200·0230
0230·0300
0300·0330
0330·0400
0400·0430
0430 ·0500
0500 ·0530
0530·0600
0600· 0630
0630·0700
0700·0730
0730 ·OBOO
0800·0B30
0830· 0900
0900·0930
0930 ·1000
1000 ·1030
1030 ·1100
1100 ·1130
1130 ·1200
1200 ·1230
1230 ·1300
1300·1330
1330 ·1400
1400·1430
1430·1500
1500·1530
1530·1600
1600·1630
1630 ·1700
1700 ·1730
1730·1BOO
1800 ·1830
1830 ·1900
1900 ·1930
1930·2000
2000 ·2030
2030 ·2100
2100·2130
2130·2200
2200 ·2230
2230·2300
2300·2330
2330·2400

/
I
~
SDC·1 195
GRID CODE

GSDPNOTICE Page 3 of 4

Power Limitedl declares that the undermenlioned CDGUs are presently unable to perform to the
characteristics stated in [Schedule 1 of the relevant Power Purchase Agreement (PPA) or Power Station
Operation & Dispatch Agreement (PSODA)I and that the affected characteristics are mentioned below with
revised values that shOuld be used for the purposes of Scheduling and Dispatch.

GENERATION SCHEDULING AND CONTRACTED REVISED TIME


!!!:!!! DISPATCH PARAMETER AFFECTED VALUE ~ FROM

Governor Droop 4.0% 4.5% 0000 2~00

2 Loading Rate after Hot Start 30~ MW 6.0 25 1800 2200

Th,\ nOlice is applicable to schedule day: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __

S,gnalure: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __

SDC-1 196
GRID CODE

Page 4 of 4
Noles
1. All Availabilities shall be expressed in MW. Alongside the MW figure shall be placed
the unit operating status (in brackets) as defined by the Final Generation Outage
Programme: 1 = Normal Availability, 2 = Innexible Outage, 3 = Flexible Planned
Outage, 4 = Advanced Flexible Planned Outage, 5 = Deferred Flexible Planned
=
Outage, 6 = Short Term Planned Maintenance Outage, 7 Return to Service, 8 =
Notified Unplanned Outage, 9 = Forced Outage.

2. For each CDGU, an Availability figure must be entered for the first settlement period.
Where the CDGU is completely unavailable, a zero shall be entered. Thereafter, an
Availability figure shall only be entered where the Availability for the CDGU is changed
from the previously expressed value.

3. This Availability Notice shall include all planned Outages agreed with NTDC and all
Unplanned/Forced Outages already notified to NTDC. It shall not include
Unplanned/Forced Outages not yet notified to NTDC unless the appropriate Outage
Notice is attached.

This notice is applicable to schedule day:

Signature: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __

SDC-1 197

\\()
GRID CODE

APPENDIXC

(SCHEDULING AND DISPATCH CODE 1)

FACSlf.lIlE Page 1 of 1
TO/FRCI.I NTDC Control Centre. X)o()(XJOO<. XXXXXXXXXXXXXXXXJ<XX:O.X
FAX { ]
FROf.110 { Power Limited]

GSDP REVISION NOTICE

] POWER PLANT REQUEST


Power Limited] advises System Operator that the GSDPs mentioned below for the following CDGUs are not in
accordance wilh Schedule 1 of the relevant Power Purchase Agreement (PPA) or Power Station Opera lion &
Dispatch Agreement (PSODA) and. as a result. the CDGUs shall be unable to meet their Spinning Reserve
capability.
ESTIMATED
CONTRACTED REVISED START DURATIOf.J
GSDP AFFECTED VALUE VALUE TIME HRS

Reason for Change

Signalure _ _ _ _ _ _ _ _ _ _ _ _ Name: _ _ _ _ _ _ _ _ _ _ _ _ _ _ __
(in block capitals)
pC\llion: Commercial Engineer/Control Engineer (delete as 'lpplicable)

OalelTime of Issue· _ _ _ _ _ _ _ _ _ _ _ _ _ __

SYSTEM OPERATOR RESPONSE TO REQUEST (Delele as applicable)

Request accepted and con finned as above


Amendment proposed as shown below:
REVISED VALUE: REVISED ESTI""ATED DURATION HRS _ _ _ _ _ __
REVISED START D·-:A~T-::-E-:- - - - - - REVISED START TIME:
SI~nalure Name· -c-----:-,-..,--------------
(In block capitalS)
po\ilion: Commercial Engineer/Control Engineer (delele as applicable)
OaieiTlme of Issue: _ _ _ _ _ _ _ _ _ _ _ _ __

SDC-1 198
GRID CODE

APPENDIX D
(SCHEDULING AND DISPATCH CODE 1)
Page 1 of 1
NOTIFICATION OF REVISED AVAILABILITY
Settlement UNITS ON OIL UNITS ON GAS GAS TURBINES
Period 1 2 2 2
Conlracted

Capacrty

0000 ·0030
0030 ·0100
0100 ·Ot30
0130 ·0200
0200·0230
0230 ·0300
0300·0330
0330·0400
0400·0430
0430 ·0500
0500 ·0530
0530 ·0600
0600 ·0630
0630 ·0700
0700·0730
0730 ·0800
0800 ·0830
0830 ·0900
0900 ·0930
0930 ·1000
1000 ·1030
1030· I 100
1100 ·1130
1130· t200
1200 ·1230
1230 ·1300
1300 ·1330
1330·1400
1400· 1n0
1430 ·1500
1500 ·1530
1530·1600
1600 ·1630
1630 ·1700
1700 ·1730
1730 ·1800
1800 ·1830
1830 ·1900
1900 ·1930
1930·2000
2000·2030
2030·2100
2100·2130
2130·2200
2200·2230
2230 ·2300
2300·2330
2330 - 2400

Notes
I. An Availabilities shall be expressed in MW. Alongside the MW figure shall be placed the unit operating status (in
brackets) as defined by the Final Generation Outage Programme: 1 = Normal Ayailability. 2 = Inflexible Planned
Outage. 3 = Flexible Planned Outage. 4 = Advanced Flexible Planned Outage. 5 = Deferred Flexible Planned Outage.
6: Short Term Planned Maintenance Outage. 7 = Relurn to Service.
2 For each CDGU. an Availability figure shall be entered in respect 01 the releyant settlement period(s) where the
Availability of the CDGU is changed Irom a value notified preYiousty in an Availability Notice. Where the Change in
Availability occurs otherwise than at the commencement 01 an Availabitity period. an appropriate annotation must be
made. stating the exact time 01 the change. II the CDGU is unavailable. a zero shall be entered.

ThiS notice is applicable to schedule day:


Signature: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __

SDC-1 199
GRID CODE

APPENDIX E
Page 1 of 1
(SCHEDULING AND DISPATCH CODE 1)

FACSIMILE

TO NTDC Control Cenlre,~, ~

FAX: [

FROM : [

I POWER PLANT· DAlLY SCHEDULING NOTICES

1 AVAJLABILITY NOTICE

The A,a1labllity of each CDGU for the schedule day 10 which this nolice refers is shown on page 2 attached.

2 ENERGY BID PRICE NOTICE [£.x.xlUxlGJ • enter bid price where appropriate)

[ I oHers NTDC the following energy prices (whiCh are lower Ihan Ihe
contracted prices) tor the week commencing the Monday following this notice.

(Fuel)

3 GSDP NOTICE

Ttle G.neration Scheduling and Dispatch Parameters for each COGU at [ I Power plant for the SChedule day to which this
notice relers are as given under Contracted Operating Characteristics In the respective Schedule at the relevant Power Purchase
Agreement (PPA) or POwer Station Operation & Dispalch Agreement (PSODA)

YES I NO (Delete as appropriate)

(If NO. each GSDP which varie strom Schedule 1 contracted operating characleristics must be
on page 3 attached If YES page 3 Shall be omitted)

4 OTHER GENERATION RELEVANT DATA

5 DECLARATION

These notices are issued by [ I in respect of the Cenlrally Dispatched


Generallng Untts (CDGUs) and Ranges at [ I Power Plant in accordance with the requirements
ot SOC 1

We declare thai the figures and other infonmalion given in Ihe notices fully renect the actual
capab~ty of the CDGUs and Ranges.

The nclices are applicable to Schedule day: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __

Slgnalure· _ _ _ _ _ _ _ _ _ _ _ __
Name __~-----------------
(in block capitals)

Posil:cn Commercial Engineer/Control Engineer (delete as applicable)

OatelT:me of Issue' _ _ _ _ _ _ _ _ _ _ _ _ __

SDC-1 200
GRID CODE

APPENDIX F

(SCHEDULING AND DISPATCH CODE 1)

FACSIMILE
TO : NTDC Control Centre, XJ()()(lO(X)OU(, ~ Page 1 of 1

FAX: [

FROM : [

NOTtFtCATlON OF REVISED AVAlLABtllTY

1. [ 1POWER PLANT NOTIFICATION


1hereby notifies NTDC that the Availability of Ihe undermenlioned CDGU(s) is/are not in accordance wilh
that declared in the current Availability/Range Availability Notice and is/are being redeclared as shown
below:

UNIT! DECLARED REVISED VALID


RANGE 10 MW/MW(e) MW/MW(e) FROM TO

Nole: where Availability is being increased, the time to be slated for the
increase to take effect shall be staled in accordance with the Grid Code.

Reason lor Change

This notice confirms the telephone notice issued at (insert time of telephone notice, if
applicable). If this notice contradicts the information given in the telephone notice it shall be
disregarded and NTDC shall so inform the Generator.

Signature: _ _ _ _ _ _ _ _ _ _ _ __ Name:
(in block capitals)

Posilion: Commerciat Engineer/Control Engineer (dele Ie as applicable)


DatelTime of Issue· _ _ _ _ _ _ _ _ _ _ _ __

SDC-1 201

\\C)y
GRID CODE

APPENDIX G
Page 1 of 2
(SCHEDULING AND DISPATCH CODE 1)

SCHEDULING DATA: PARTICIPATING GENERATORS

PART 1

UNIT NOMINATIONS

Name of Participating Generator

Name of Generating Unit

Date on which Scheduling Day Commences

Local Unit Nomination (SOC 1.4.2.3C (c))

Unit
Settlement
Nomination
Period
(Totals)

(kWh)
Start End

06.00 06.30
06.30 07.00
07.00 07.30
07.30 08.00
08.00 08.30
08.30 09.00
09.00 09.30
09.30 10.00
10.00 10.30
10.30 11.00
11.00 11.30
11.30 12.00
12.00 12.30
12.30 13.00
13.00 13.30
13.30 14.00
14.00 14.30
14.30 15.00
05.00 05.30
05.30 06.00

SDC-1 202
GRID CODE

APPENDIX G
Page 1 of 2
(SCHEDULING AND DISPATCH CODE 1)

PART 2

SUPPLEMENTAL ENERGY BIDS

1. Name of participating Generator

2. Name of Generating Unit

3. Date on which Scheduling Day commences

4. Supplemental Energy Bid for Scheduling Day

Start Up Price (Rs.)

Fixed Price (Rs.lhour)

Incremental Price (Rs'/MWh or Rs.lKwH)

SOC-1 203

\\1/
GRID CODE

SCHEDULING AND DISPATCH CODE NO.2 (SOC 2)

CONTROL SCHEDULING AND DISPATCH

CONTENTS

SDC-205
SOC 2.1 INTRODUCTION
SDC-205
SOC 2.2 OBJECTIVE
SDC-205
SOC 2.3 SCOPE
SDC-206
SOC 2.4 PROCEDURE

APPENDIX A SDC-214
DISPATCH INSTRUCTIONS FOR CDGUS
GRID CODE

CONTROL SCHEDULING AND DISPATCH CODE NO.2

CONTROL SCHEDULING AND DISPATCH

SDC 2.1 INTRODUCTION

In the daily functioning of the National Transmission and Dispatch


Company's business, scheduling, dispatch and control of generation
facilities shall be performed by the System Operator. The Control
Scheduling and Dispatch Code (SOC 2) defines the roles and
responsibilities of the System Operator and Code Participants in the
dispatch and control scheduling of Available generation facilities, and
operation and management of a secure bulk Transmission System of
NTOC.

SOC 2.1.1 Scheduling and Dispatch Code No.2 ("SOC 2") sets out the procedure s
for the System Operator to issue dispatch instructions to Generators in
respect of their COGUs (in relation to their Unit Nominations) as per
"Final Generation Schedule" concluded in SOC 1. This sub-code is
supplemental to SOC 1 and SOC 3.

SOC 2.2 OBJECTIVE

The Objectives of the Control Scheduling and Dispatch Code (SOC 2)


are to establish the process, guidelines and procedures for:

(a) Principles and criteria for dispatch


(b) Minimizing overall cost of supply
(c) Steps to be taken to prepare a dispatch algorithm
(d) Accounting for bilateral contracts
(e) Establishment of a Merit Order Ranking

The procedures for the issuance of dispatch instructions to Generators


by the System Operator is intended to enable (as far as possible) the
System Operator to match continuously, utilising the Merit Order and
"Final Generation Schedule" derived pursuant to SOC 1, and the factors
to be taken into account listed in SOC 1 (SOC 1.4.3.3), COGU output to
NT DC total system demand, taking into account any power transfers
over any External Interconnections and non-CGOU output together with
an appropriate Operating Margin whilst maintaining the integrity and
security of the NTOC's System coupled with the requirements of
adequacy and quality of power supply as provided in this Grid Code.

SOC 2.3 SCOPE

SOC·2
GRID CODE

SOC 2.4 PROCEDURE

SOC 2.4.1 Information Used

SOC 24.1.1 The information which the System Operator shall use in assessing as to
which CDGU to dispatch, shall be the 1) Availability Notice; 2) Unit
Nominations; 3) Merit Order as derived under SOC 1; 4) Other factors to
be taken into account as listed in SOC 1 (SOC 1.4.3.3); 5) Generation
Scheduling and Dispatch Parameters (GSOPs); 6) Operating Reserve
Characteristics, and; 7) Other Generation Relevant Data in respect of
that COGU, supplied to it under SOC 1 (and any revisions under SOC 1
and this SOC 2 to the date).

SOC 2.4.1.2 Subject as provided below, the factors used in the dispatch phase in
assessing which COGUs to dispatch in conjunction with the Merit Order
as derived under SOC 1, and the other matters identified in SOC 1.4.3,
SOC 1.4.3.3 and SOC 1.4.3.5 and SOC 1.4.3.6 shall be those used by
the System Operator to compile the Generation Schedule under SOC 1.

SOC 2.4.1.3 Additional factors which the System Operator shall, however, also take
into account are those Generators who have not complied with dispatch
instructions or; "special actions requests" which the System Operator
has (in its absolute discretion) granted for the early synchronisation of a
COGU to the NTDC System; requests which System Operator has made
and to which the Generator has agreed to for an early or late
synchronisation of a CDGU to the NTOC's System; and variation
between forecasted and actual NTDC system demand, as these can
have an impact on the overall dispatch. The System Operator shall also
take into account the need to dispatch CDGUs for monitoring, testing or
investigation purposes under OC11, or for testing at the request of a
User, under OC11.2.

SOC 2.4.1.4 In the event of two or more COGUs having the same "Merit Order Price
Set" and the System Operator not being able to differentiate on the basis
of the factors identified in SOC 1.4.3.2, SOC 1.4.3.3 and SOC 1.4.3.4,
the System Operator shall select for dispatch first the Generator which in
System Operator's best reasonable judgement is most appropriate
under the circumstances and prevailing conditions of the Scheduling
Day.

SOC 2.4.2 DISPATCH INSTRUCTIONS

SOC 2.4.2.1 Introduction

Dispatch instructions relating to the Schedule Day shall normally be


issued at any time during the period beginning immediately after the
issuance of the Day Ahead Notification preferably with effect from 00.01
hrs (midnight). In respect of that SChedule Day. The System Operator
may, however, at its discretion, issue dispatch instructions in relation to a
COGU prior to the issuance of the Day Ahead Notification which
includes that COGU. .---..

206
GRID CODE

SOC 2.4.2.2 (a) The System Operator shall issue dispatch instructions direct to
the Generator for the dispatch of each of its CDGU. Subject to
the provisions of this SOC 2, the System Operator shall issue
dispatch instructions with respect to information submitted by
each Generator. The System Operator may issue dispatch
instructions for any CDGU which has been declared Available in
an Availability Notice even if that COGU was not included in the
Day Ahead Notification subject to Its availability later on.

SOC 2.4.2.3 Scope of Dispatch Instructions for CDGUs

In addition to instructions relating to the dispatch of Active Power,


dispatch instructions (unless otherwise specified by the System Operator
at the time of giving the dispatch instructions) shall be deemed to have
included an automatic instruction of Spinning ReseNe, and
voltage/reactive support.

SOC 2.4.2.4 In addition to instructions relating to the dispatch of Active Power,


dispatch instructions in relation to CDGUs may include:

(a) Target (at instructed MW level) voltage levels at the Points of


Connection or the individual reactive power output from CDGUs
at the Generator terminals which shall be maintained by the
CDGU. The issue of dispatch instructions for Active Power at the
Generator terminals shall be made with due regard to any
resulting change in reactive power capability, and may include
instruction for reduction in Active Power generation to increase
reactive power capability. In the event of a sudden change in the
System Operator's system voltage, a Generator must not take
any action in respect of any of its COGUs to override automatic
MVAr response unless instructed otherwise by the System
Operator or unless immediate action is necessary to comply with
voltage/stability limits. A Generator may take such action, as is in
its reasonable opinion necessary, to avoid an imminent risk of
injury to persons or material damage to property (including the
CDGU);

(b) (i) The declared fuel to be used by the Generator in operating


the CDGU must be declared by the Generator ahead of
scheduling. In the case of a CDGU capable of firing on
different fuels, the dispatch instruction may also specify
the designated fuel to be used by the Generator. If no
declared fuel and/or, where relevant, Designated Fuel is
contained in the dispatch instruction, then the most
recently instructed Dispatched Fuel and/or, where relevant,
designated fuel shall apply. The part of a dispatch
instruction which specifies a change in the dispatched fuel
and/or, where relevant, designated fuel to be burned by
the Generator shall be known as a "Dispatched Fuel

i
Notice". The System Operator may, however, use a
separate dispatched fuel notice and which may be issued
separately from any dispatch instruction, containing the
above information.

,?O\fJER REo
____________________________________________________~~~~G---- CL~~
1JJ 0
SOC-2 207 ~ ~
llJ -<
BY

~
-l l>
~ THE AUTHORITY $
9 ~
"''1- * . .... ,,-.,;~
-~~------------------------~
GRID CODE

(ii) In the case of an existing CDGU only, the Generator may


(subject to the following provisions of this paragraph, in
complying with a dispatch instruction burn a fuel other
than the Declared Fuel and/or, where relevant, the
Designated Fuel specified in the dispatch instruction.

(c) A reference to any implications for future dispatch requirements


and the security of the NTDC's Transmission System, including
arrangements for change in output to meet post-fault security
requirements;

(d) An instruction to switch into or out of service a "System to CDGU"


Intertripping scheme;

(e) Notice and changes in notice to synchronise or de-synchronise


CDGUs in a specific time scale;

(f) Instructions relating to abnormal conditions, such as adverse


weather conditions, or high or low NTDC System voltage;

(g) An instruction for a change in Generator step-up tran sformer tap


positions;

(h) An instruction for a CDGU to operate in synchronous


compensation mode;

(i) An instruction in relation to the carrying out of testing, monitoring


or investigations as required under OC11, or testing at the
request of a User under OC11.2.

U) In the case of a Gas Turbine PPA CDGU, an instruction requiring


it to generate at a level in excess of its Availability but not
exceeding its temperature adjusted peak capability which may
only be given if, at the time of issue of the instruction, the CDGU
is dispatched to an output equal to its Availability, and provided
that the limit on the number of hours for which such instructions
may be given during the year (as agreed with the relevant
Generator) is not thereby exceeded. Such an instruction shall be
identified as a "peak instruction". When the System Operator
gives a dispatch instruction which is in excess of the Availability of
the gas turbine, the CDGU which is not designated a "peak
instruction", the Generator must inform the system Operator
immediately that the dispatch instruction is so in excess in order
that the System Operator can so designate the dispatch
instruction as a "peak instruction" or withdraw the instruction
completely. The Generator shall not then be obliged to comply
with the dispatch instruction unless and until the system Operator
notifies it that the instruction is designated as a "peak instruction".

208
SDC·2

\\n
..J-., .. F
GRID CODE

SOC 2.4.2.5 Reactive Support for Voltage Control

Reactive support for necessary voltage control shall be provided by each


Generator with due regards to manufacturer's specifications of design
characteristics of the individual Generator.

SOC 2.4.2.6 Form of Instruction

(a) Instructions may be given by telephone, by facsimile


transmission, by instructor or by radio/telephone. These may be
given electronically where a relevant communication system
has been established between the System Operator and the
Generator. In the case of a low-frequency relay initiated
response from a Gas Turbine CDGU, the instruction shall be
deemed to be given at the moment that the low frequency relay
operates.

(b) In addition, the System Operator may notify a Generator that in


certain circumstances it requires the Generator to operate in
accordance with a Standing Instruction, which shall be deemed
to be given when the circumstances arise. These Standing
Instructions may include instructions on how to operate if the
System Operator loses the ability to direct the operation and
management of the NTDC's Transmission System temporarily, in
the circumstances envisaged under OC 8 where the System
Operator or the Control Centre (NPCC) is incapacitated for any
reason pending the transfer of system operations to a temporary
Control Centre. The System Operator shall not, by means of a
Standing Instruction, require any of the CDGUs to be dispatched
in a manner in which the System Operator would not have
access or be able to exercise option to require such units to be
dispatched by means of a dispatch instruction issued in
accordance with this SOC 2.

(c) The reduction by a Generator of the output of one of its CDGUs


under SOC 3.6.1 shall be deemed to have followed a dispatch
instruction issued by the System Operator.

( d) The de-synchronisation of a CDGU following the operation of an


intertrip scheme selected by the System Operator shall be
deemed to have happened as a result of a dispatch instruction
issued by the System Operator.

SOC 2.4.2.7 (a) Dispatch instructions given by telephone, by facsimile


transmission or electronically shall generally indicate the target
MW (at Target System Frequency) to be provided at the
Generator terminals (or where provided in the relevant
Connection Agreement, on the energy sent out basis).

(b) Dispatch
MW (at

SDC·2 209

\\G
GRID CODE

Generator terminals of the CDGU to which the operator relates


(or where provided in the relevant Connection Agreement, on
energy sent out basis), in the case of a Power Plant which has
an Operator for each CDGU.

(c) Dispatch instructions deemed to be given upon the Operation of


a low frequency relay shall be deemed to indicate the target MW
(at System Target Frequency), which may either be at full load or
at some lower output (as previously specified by the System
Operator), to be provided at the Generator terminals which
reflects; and is in accordance with the GSDPs of Gas Turbine
CDGUs GSDPs given as under or revised in accordance with
SOC 1 or SOC 2.

(d) Dispatch instructions deemed to be given upon the activation of


a Standing Instruction shall be deemed to indicate the target MW
(at Target System Frequency), which may either be at full load or
at some lower output {to be provided at the Generator terminals
(or where provided in the relevant Connection Agreement, on
the energy sent out basis) as set out in the Standing Instruction
notified by the System Operator from time to time; to be achieved
in accordance with the respective GSDPs given under (or as
revised in accordance with) SOC 1 or this SOC 2, or such rate
within those parameters as is specified in the Standing
Instruction.

SOC 2.4.2.8 The form, manner, and the terms to be used by System Operator in
issuing dispatch instructions together with their meanings are set out in
the attached appendices ..

SOC2.4.2.9 Subject only to SOC 2.4.2.8, and as provided below in the SOC 1 and
SOC 2, dispatch instructions shall not be inconsistent with the
Availability, Unit Nominations, Contracted GSDPs, and Other Generation
Relevant Data notified to the System Operator under SOC 1 (and any
revisions under SOC 1 or this SOC 2 to that data). A dispatch instruction
may be subsequently cancelled or varied (including an instruction for a
cancelled start) at any time. The dispatch instructions may, however, be
inconsistent with the Availability and/or Unit Nominations and/or GSDPs
and/or Other Generation Relevant Data so notified to the System
Operator for the purposes of carrying out a test at the request of the
relevant Generator under OC12.3 or a system test at the request of the
relevant Generator under OC11.2, to the extent that such dispatch
instructions are consistent with the procedures agreed (or otherwise
determined) for conducting the test or system test (as the case may be).
For the avoidance of doubt, any dispatch instructions issued by the
System Operator for the purposes of carrying out a test at the request of
the relevant Generator under OC 12.3 or a system test at the reques t of

O.i
the relevant Generator under OC11.2 shall not be deemed to be
d ispal ch ins Iruelions given pur suanl 10 S DC 2 4 .2.1

SDC-2 210

\\Ct
GRID CODE

SOC 2.4.2.10 To preserve the NTDC's Transmission System integrity under


emergency circumstances where licence standards and obligations
cannot be met, the System Operator may, however, issue dispatch
instructions to change CDGU output even when this is an outside
parameter so registered or so amended. This may, for example, be an
instruction to trip a COGU or to part-load a COGU. The instruction shall
be stated by the System Operator to be one in relation to emergency
circumstances under SOC 2.4.2.10.

SOC 2.4.2.11 Communication with Generators

(a) A Generator must, at the beginning of each shift at its Power


Station, contact the System Operator by telephone; and the
Operator at the Power Station and the System Operator must
exchange names in order to identify each other. If during the shift
at the Power Station, the Operator changes, the Person whose
Operator has changed must notify the other accordingly.

(b) Dispatch instructions whether given by telephone, by facsimile


transmission or by Operator must be formally acknowledged
immediately by the Generator at the Power Station by telephone,
by return facsimile transmission or by acceptance of the
dispatched signal, given in the manner agreed between the
Generator and the System Operator or a reason must be given as
soon as possible for non-acceptance, which may (subject to
SOC 2.4.2.10) only be to avoid, in the Generator's reasonable
opinion, an imminent risk of injury to persons or material damage
to property (including the COGU) or because they are not in
accordance with the applicable Availability Notice, or GSDPs or
do not reflect "Other Generation Relevant Data" submitted by the
Generator pursuant to SOC 1.

(c) In the event that in carrying out the dispatch instructions, an


unforeseen problem arises, leading to a possibility of, in the
Generator's reasonable opinion, to an imminent risk of injury to
persons or material damage to property (including the COGU),
the System Operator must be notified as soon as possible by
telephone.

SOC 2.4.2.12 Action Required from Generators

Each Generator shall comply in accordance with SOC 2.4.2.13 and their
Power Purchase Agreement (PPA) or Power Station Operation &
Dispatch Agreement (PSOOA) as applicable with all dispatch
instructions properly given by the System Operator unless the Generator
has given a notice to System Operator under the provisions of SOC
2.4.2.10 regarding non-agreement of dispatch instructions. A Generator
shall not, however, be in default in complying with the dispatch
instructions, if. subsequent to the issuance of the dispatch instruction,
the Generator and the System Operator agree on an early
'\l()=--:-<-'~
~G
"
SOC·2 211
GRID CODE

synchronisation, and the Generator synchronises the relevant CDGUin


accordance with that agre~ment.

SOC 24.2.13 Implementation of Instructibns by Generators

The Generators shall immediately respond to dispatch instructions


properly given by the System Operator without any delay in accor~ance
with the instructions, including those' dispatch instructions issued
pursuant to SOC 2.4.2.10 .. Instructions indicating' a target MW and
Voltage/fvWARS at that MW level and an Output at the System Target
Frequency shall be complied with by Generators notwithstanding. any
tolerance bands set out in their PPAs/PSODA.

SOC 2.4.2.14 Subject to the exception set out below in th'ls SOC 2:4.2."4. the
Generators shall only synchronise or de-synchronise COGUs tD 1he
dispatch instructions of the System Operator or unless it occurs
automatically as a result of fntertrip schemes or low-frequency relay
operations. De-synchronisation may otherwise only take place lM#lout
the System Operator's prior agreement if it is done to avoid. iA-1t'1e
Generator's reasonable opinion, an imminent risk of injury to persons or
material damage to property (including the COGU) exists_ If 1hat
happens, the System Operator must be informed that it has done so
within ten (10) minutes of the de-synchronization of the Unit.

SDC 24.2.15 The System Operator may suspend the issuance of the Dispatch
instructions to a particular Generating Unit in a plant in accordance with
the Merit Order (having taken account of and applied the factors referred
to in SOC 1.4.3.3 to the extent that the conditions in SOC 1.43_5 ~se.
When necessary, the System Operator shall issue dispatch instruclions
for a Black Start.

SOC 24.2.16 Generating Plant Changes

(a) Each Generator Power Station with multiple Generating Units


shall, without delay, notify the System Operator by te!ephune or
by facsimile transmission of any change or loss (temporary or
otherwise) to the operational capability of the Power -Plant
including any changes to the Generation Scheduting ~nd
Dispatch Parameters (GSDPs) of each CDGU (in the case of
Generation Scheduling and Dispatch Parameters, by the
submission of a GSDP Revision Notice) indicating (where
possible), the magnitude and the duration of the change. tn the
case of CDGUs already synchronised to the NTOC's
Transmission System, the Generator at its Power Plant must also
state whether or not the loss was instantaneous.

SOC 2.4.2.17 Each Generator at its Power Plant shall operate its syndlronised
COGUs with AVRs and VAR limiters in service at all times (where
required pursuant to generator control arrangements contained in
PPNPSODA or Connection Code) unless released from this obligation
in respect of a particular CDGU by the System Operator.

SOC-2 212
GRID CODE

SOC 2.4.2.18 Minimum Demand Regulation ("MORIt)

Synchro.nised cent~ally~dispatched Generating Units must at all times be


capable of. reduCing .Output sufficient to allow a sufficient Operating
Margin for' adequate. frequency control. The System Operator shall
monitor the outputqata of the Generation Schedule against forecasted
NTOC's total system demand to see whether the level of MOR for any
period is insufficient; and may take any shortfall into account in altering
the dispatch. .

SOC 2.4.3 Special Actions

The System Operator, may as part of the issuance of dispatch


instructions, issue instructions for special actions (either pre· or post-
fault) to a Generator in respect of any of its COGUs in the event that
System Operator, in its reasonable opinion, believes that such
instructions are necessary in order to ensure that the licence standards '.'
and obligations are met. Special actions shall generally involve a Load
change or a change in required Notice to synchronise within a specific
timescale on individual or groups of COGUs. They may also include
selection of "System to COGU" intertrip schemes for stability or thermal
reasons. Instructions for special actions shall always be within
Generation Scheduling and Dispatch Parameters (GSDPs).

SOC·2 213
GRID CODE

SOC 2 • APPENDIX A

Dispatch Instructions for CDGUs

SOC 2.A.1 Form of Dispatch Instruction

SOC 2.A.1.1 All loading/de-loading rates shall be assumed to be in accordance with


Generation Scheduling and Dispatch Parameters (GSDPs). Each
dispatch instruction shall, wherever possible, be kept simple, drawing
as necessary from the following forms and SOC 2.4.2.

SOC 2.A.1.2 (a) The dispatch instruction given by telephone, electronically or


facsimile transmission shall normally follow the form:

(i) The specific CDGU to which the instruction applies;

(ii) The Output to which it is instructed;

(iii) If the start time is different from the time the instruction is
issued, the start time shall be included;

(iv) Where specific loading/de-loading rates are concerned, a


specific target time;

(v) The issue time of the instruction;

(vi) The Designated Fuel and/or declared fuel (or fuel), as the
case may be;

(vii) In the case of a gas turbine CDGU, if the instruction is


designated as a "Peak Instruction", this shall be stated.

(b) The dispatch instruction given by Instructor shall normally follow


the form:

(i) The specific CDGU to which the instruction applies, if the


Instructor is on a unit basis or the group of COGUs to
which the instruction applies;

(ii) The Output to which it is instructed.

Any dispatch instruction relating to the Designated Fuel and/or


Declared Fuel, (or fuel) as the case may be, shall be given by
telephone, electronically or by facsimile transmission.

soc 2A2 Dispatching a Synchronised CDGU to Increase or Decrease Output

soc 2A21 If the time of the dispatch instruction is 1400 hours, the unit is unit 1 and
the Output to be achieved is 205 MW, the relevant part of the instruction
would be, for example:
"Time 1400 hours. Unit 1 to 205 MW"
GRID CODE'

SOC 2.A.2.2 If the start time is 1415 hours, it would be, for example:
"Time 1400 hours. Unit 1'to 205 MW, start at 1415 hours"

SOC 2.A.2.3 Loading and de-loading rates are assull!ed to be in accordance with
Generation Scheduling and Dispatch Parameters (GSOPs) unless
otherwise stated. If differE;1nt loading or de-loading rates are required,
the time to be achieved shail be' stated, for example:
"Time 1400 hours. Unit 1 to 205 MW by 1420 hours"

SOC 2.A.3 Dispatching a CDGU to 'Synchronise/de-Synchronise

SOC 2.A.3.1 CDGU Synchronising

SOC 2.A.3.1.1 In this instance, for COGUs, the dispatch instruction issue time shall
always have due regard for the synchronising time declared to System
Operator by the Generator as a GSOP.

The instruction shall follow the form, for example:


"Time 1300 hours. Unit 1, Synchronise at 1600 hours"

In relation to an instruction to synchronise, the start time referred to in


SOC 2.A.1.2(a) shall be deemed to be the time at which synchronisation
is to take place.

SOC 2.A.3.1.2 Unless a loading programme is also given at the same time it shall be
assumed that the COGU(s) are to be brought to minimum generation
level and on the Generator reporting that the Generating Unit has been
synchronised, a further dispatch instruction shall be issued.

soc 2.A.3.1.3 When a dispatch instruction for a CDGU to synchronise is cancelled


(i.e. a cancelled start) before the unit is synchronised, the instruction
shall follow the form, for example:
"Time 1400 hours. Unit 1, cancel synchronising instruction"

soc 2.A.3.2 CDGUs De-Synchronising

soc 2.A.3.2.1 The dispatch instruction shall normally follow the form, for example:
"Time 1300 hours. Unit 1, Shutdown".

If the instruction start time is for 1400 hours the form shall be. for
example:
"Time 1300 hours. Unit 1, Shutdown, start at 1400 hours"

Both the above assume de-loading rate at declared Generation


Scheduling and Dispatch Parameters (GSOPs). Otherwise the message
shall conclude with, for example:
..... and se-synchronise at t 500 hOUrs" '~
1

SOC·2 215
GRID CODE

SOC 2A4 Frequency Control

SOC 2A4.1 All the above dispatch instructions shall be deemed to be at "Target
System Frequency" (50 Hz), i.e. where a COGU is in the Frequency
Sensitive Mode, instructions refer to target Output at Target System
Frequency. Target System Frequency changes shall always be given to
the Generator by telephone and shall normally only be 49.95, 50.00,
50.05Hz (at an interval of 0.05 Hz).

SOC 2A4.2 CDGUs required to be frequency insensitive shall be specifically


instructed as such. The dispatch instruction shall be of the form for
example:

"Time 2100 hours. Unit 1, to Frequency Insensitive mode"

SOC 2A4.3 Frequency control instructions may be issued in conjunction with, or


separate from, a dispatch instruction relating to Output.

SOC 2A5 Emergency Load Drop

The dispatch instruction shall be in a pre-arranged format and normally


follow the form, for example:

"Time 2000 hours. Emergency load drop of "X"MW in "Y" minutes"

SDC 2A6 Voltage Control Instruction

In order that adequate NTDC Transmission System voltage limits as


specified in OC 4 are maintained under Normal and (N-1) conditions, a
range of voltage control instructions shall be utilised from time to time,
for example:

(a) Operate to Nominal System Voltage as specified in OC 4.9;

(b) Maximum generation of reactive power (at current instructed MW


output);

(c) Increase reactive output by 10MVAr (at current instructed MW


output).

soc 2A7 Instruction to change dispatched fuel

When the System Operator wishes to instruct a Generator to change the


fuel being burned in the Operation of one of its CDGUs from one
Dispatched Fuel (or fuel) to another (for example from 1 % sulphur oit to
3% sulphur oil), the dispatch instruction shall follow the form, for
example:

"Time 1500 hours. Unit 2 change to 3% Fuel at 1700 hours".

SOC·2 216

Wr
GRID CODE

SOC2.A.8 Instruction to change Designated Fuel for a Dual Firing CDGU

When the System Operator wishes to instruct a Generator to change the


fuel being burned in the operation of one of its CDGUs which is capable
of firing on two different fuels (for example, coal or oil), from one
Designated Fuel (or fuel) to another (for example, from coal to OM), the
instruction shall follow the form, for example:

"Time 1GOO hours. Unit 1 generate using oil at 1800 hours".

SOC 2.A.9 Peak Instruction to Gas Turbine CDGUs

'0
When the System Operator wishes to instruct a Generator operate its
Gas Turbine PPA COGU at a level in excess of its Availabl'rty in
accordance with SOC 2.4.2.4U>, the instruction shall follow the form, for
example:

"Peak Instruction. Time 1800 hours. Unit GT2 to 58MW.-

SDC·2 217
GRID CODE

SDC-2 218
GRID CODE

SCHEDULING AND DISPATCH CODE NO.3 (SOC 3)

FREQUENCY CONTROL

CONTENTS

INTRODUCTION SDC-217
SOC 3.1

OBJECTIVE SDC-219
SOC 3.2

SCOPE SDC-219
SOC 3.3

PROCEDURE SDC-220
SOC 3.4

SOC 3.5 ACTION REQUIRED BY GENERATORS


IN RESPONSE TO LOW FREQUENCY SDC-221

SOC 3.6 ACTION REQUIRED BY GENERATORS


IN RESPONSE TO HIGH FREQUENCY SDC-221

ELECTRIC TIME SDC-222


SOC 3.7
GRID CODE

SCHEDULING AND DISPATCH CODE NO.3

FREQUENCY CONTROL

SOC 3.1 INTRODUCTION

All Generators (with/without Bilateral Contracts) shall have an obligation


to meet their due share of ancillary services including voltage and
frequency control, operating reserve both (spinning and non-spinning
reserve), reactive support, load imbalance services, black-start, system
restoration, and load following requirements.

soc 3.1.1 SOC 3 sets out the procedure by which the System Operator shall use to
direct frequency control. The NTOC System Frequency shall be
controlled by:-

(a) Automatic response from COGUs operating in "Frequency


Sensitive Mode", including "Unit Load Controller Operation-;

(b) The dispatch of CDGUs; and

(c) Load demand controL

soc 31.2 The requirements for frequency control are determined by the
consequences and effectiveness of generation scheduling and dispatch;
and by the effects of power transfers across any External
Interconnection; and therefore, SOC 3 is supplemental to SOC 1 and
SOC 2.

soc 3.2 OBJECTIVE

The procedure for the System Operator to direct frequency control is


intended to enable (as far as possible) the System Operator to meet the
requirements of frequency control as contained in this Grid Code and
NEPRA Transmission Performance Standards.

soc 3.3 SCOPE

SOC 3 applies to the System Operator, NTOC, Distributors, Generators


with regard to their Generating Units, Transmission-connected
Consumers, and Externally-connected Parties and conS1ers

SOC·3 219
GRID CODE

SOC 3.4 PROCEDURE

SOC3.4.1 Automatic Response from Generating Plant

SOC 3.4.1.1 (a) All CDGUs must be capable of operating at all times in Frequency
Sensitive Mode (including, wh~He applicable, with the Unit Load
Controller in Operation) which means an automatic incremental or
decremental generation response (Primary Response) to contain
the initial system frequency change together with a sustained
generation and load response (Secondary Response) which can
contribute to correcting and containing the system frequency within
the requirements for frequency control contained in this Grid Code
and NEPRA Transmission Performance Standards Rules.

(b) All synchronised CDGUs must, unless relieved of the requirement


by the System Operator, operate at all times in the Frequency
Sensitive Mode (including, where applicable, with the Unit Load
Controller in Operation) except where, in the Generator's
reasonable opinion, it is necessary to cease operation in Frequency
Sensitive Mode in order to avoid an imminent risk of injury to
persons or material damage to property (including the CDGU) with
the consent of the System Operator. The detailed instructions for
droop settings and participation factor would be given by the
System Operator sBparately to the CDGUs for contribution to\'w'ards
frequency corrections.

SOC 3.4.1.2 A System Frequency induced change in the Active Power Output of
COGUs which assists the recovery to Target System Frequency must
not be manually overridden by a Generator except where it is necessary,
in the Generator's reasonable opinion, to avoid an imminent risk of injury
to persons or material damage to property (including the CDGU) with the
consent of the System Operator.

SOC 3.4.2 SYSTEM OPERATOR'S DISPATCH INSTRUCTIONS

SOC 3.4.2.1 When' the System Operator determines it is necessary, by having


monitored the NTOC System Frequency, it shall, as a part of the
procedure set out in SOC 2, issue dispatch instructions including the
instructions for Spinning Reserve, in order to regulate the NTOC System
Frequency to meet the requirements for frequency control as contained
in the Grid Code, and NEPRA Transmission Performance Standards
Rules. The CDGUs to be selected by the System Operator for Unit Load
Controller Operation shall be instructed by the System Operator to
operate at the NTOC Target System Frequency, which shall be 50.00
Hz.

SOC 3.4.2.2

SOC·3
GRID CODE

SOC 3.4.3 Low frequency relay initiated response from Gas Turbine PPA CDGUs.

SOC 3.4.3,1 The System Operator may allocate a part of the requirements for
Operating Reserve to Gas Turbine PPA CDGUs with the capability of
low frequency relay initiated response for start-up to a pre-determined
output level which have not been sCheduled for dispatch in accordance
with SOC 1, altt)ou'gh the System Operator may, in the event, decide to
issue a dispatch- instruction in respect of any of such CDGU in
accordance with SOC 2. Alternatively, Gas Turbine PPA COGUs of this
type may be scheduled for dispatch by the System Operator in
accordance with SOC 1. .

SOC 3.4.3,2 The System Operator shall periodically specify, within the range
established pursuant to the Connection Agreement, low frequency relay
settings to be applied to the CDGUs pursuant to SOC 3.4.3.1 and shall
instruct the low frequency relay initiated response to be placed in and
out of service.

SOC 3.43.3 All Generators and Users/Code Participants shall comply with System
Operators instructions issued under SOC 3.4.3.2 for low frequency relay
settings. The Generators shall not alter such low frequency relay settings
or take low frequency initiated response out-of-service without the
System Operator authorization, except where necessary, in the
Generator's reasonable opinion, to avoid an imminent risk of injury to
persons or material damage to property (inc!~ding the CDGU) with the
authorization of the System Operator.

SOC 3.5 ACTION REQUIRED BY GENERATORS IN RESPONSE TO LOW


FREQUENCY

SOC 3.5,1 (a) If the NTOC System Frequency falls to or below 49.8 Hz, each
Generator at its Power Plant shall be required to check that each
of its COGUs is achieving the required levels of response
including that required from the Unit Load Controller, where
applicable, in order to contribute to containing and correcting the
low System Frequency.

SOC 3,5.2 In order that the System Operator can deal with emergency conditions
effectively, it needs as much up-to-date information as possible and
accordingly, the System Operator shall be informed of the action taken
as soon as possible after the fall in the System Frequency directly by
telephone from the Power Plant.

SOC 3.6 ACTION REQUIRED BY GENERATORS IN RESPONSE TO HIGH


FREQUENCY

SOC 3.6,1 If the NTOC System Frequency rises to or above 50.2 Hz, each
Generator at its Power Plant shall be required to ensure that each of its
COGUs has responded in order to contribute to correcting and
containing the high System Frequency by automatically or manually

SDC-3 221

\\~/
. ,
,
GRID CODE

reducing output by a minimum amount of 2% and by a maximum


amount of 5% of Power Plant output per 0.1 Hz deviation of the NTOC's
System Frequency from declared or Target System Frequency.

SOC 3.6.2 This reduction shall have to be made without reference to the System
Operator: and must be maintained until the NTOC System Frequency
has returned to Target System Frequency or receipt of revised dispatch
instructions from the System Operator under SOC 2. In order that the
System Operator can deal with the emergency conditions effectively, it
needs as much up-to-date information as possible and accordingly, the
System Operator must be informed of the action taken as soon as
possible after the rise in System Frequency directly by telephone from
the generating plant.

SOC 3.7 ELECTRIC TIME

SOC 3.7.1 The System Operator shall endeavour (in so far as it is able to) control
electric clock time to within plus or minus 10 seconds of Standard Time
by specifying changes to target the NTOC's System Frequency, and by
dispatch taking into account Merit Order and forecast Power PlanULoad
Demand margins. Errors greater than plus or minus 10 seconds may be
temporarily accepted at the System Operator's reasonable disaetion.
The System Operator shall give 15 minutes notice to each generator of
variation in Target System Frequency.

SDC·3 222

~/.
GRID CODE

The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached). -

GLOSSARY AND DEFINITIONS

ITEM Sub-Code DEFINITION


24 Hour Recall SOC An Agreement [Power Purchase Agreement (PPA)!
Power Station Operation & Dispatch Agreement
(PSODA)] between NTDC and a Generator whereby a
CDGU subject to a Notified Unplanned Outage may be
recalled by NTDC upon giving a 24 hours Notice to the
Generator.
Active Energy PMC 2.1 The electrical energy produced, flowing or supplied by
an electrical circuit during a time interval, being the
integral with respect to time of the instantaneous power,
measured in units of watt- hours or standard multiples
thereof, Le.:
1000Wh = 1 kWh ,
1000 kWh = 1 MWh
=
1000 MWh 1 GWh
1000 GWh = 1lWh
Active Load Limiter SOC 3 Device that does not allow a Generator to increase its
active power higher than establistled.
Active Power SOC 3.4.1.2 The product of voltage and the m-phase component of
alternating current measured in units of watts and
standard multiples thereof, i.e.: -.
=
1000 Watts 1 kW ,
.
1000 kW = 1 MW ..
1000 MW = 1 GW .j-
1000 GW = 1lW ~

ASRAR OC Annual System Reliability & Assessment R~rt


Apparatus CC5.4 All electrical equipment, conductor installed on the
Code electrical power system.
Management
Apparent Power OC4 The product of voltage and of alternating current
Appendix 7 measured in units of Volt·amperes and standard
multiples thereof, Le.:
=
1000 VA- 1kVA
=
1000 kVA 1 MVA
Automatic Generation OC4 The mechanism, and equipment instaled on a
Control (AGC) SOC 1 & 2 Generator to process and monitor the sys1em frequency,
and contribute in stabilizing and maintaining 'the system
frequency within permissible Uml1s included. in the Grid
Code and NEPRA Performance :; Standards
(Transmission) Rules. ..
Automatic Load CC 5.4 A load shedding scheme, utilized by NTDC. to prevent
Shedding OC4 frequency collapse or other problems, and to restore the
balance between generation output and toad demand on
the NTDC system,
Automatic Voltage SOC 2 A continuously acting automatic eXcitation control
Regulator (AVR) system to control the voltage of a Geperatoi'measured
at the Generator terminals. .~
Auxiliaries OC12 Any item of Plant and/or Apparatus "cjt diredlya part of
the boiler plant or Generator's, but required f :0. r

plant's or Generator's functional o~&~~~

G&D 223
1"fir"~
t,
~
UJ
~.~
'"

BY
..
APPROVE 0
I~
0

\ \(\ ' ~ ,THE AUTHORITY -~,


GRID CODE

The Terms Not Contained here have been Defined in Various Applicable
Documents.of NEPRA and li.sted as Annexure-A (attached).

ITEM Sub-Code DEFINITION


Auxiliary Diesel SOC A diesel engine driven electric generator used to provide
Engine Generator emergency:electric power for auxiliary power supply.
Plants with sufficiently large auxiliary diesel-generator
could have Black Start capability.
Availability Notice SOC The Notice for each COGU, must state the Availability in
a whole number of MW and, for each CDGU, state the
Availability in MW to one decimal place.
Available Power SOC 1.4.1 Effective power from the Generator available in the bulk
power transmission system for load dispatch.
Back-up Protection PMC Protection equipment or system which is intended to
operate when a system fault is not cleared in due time
because of failure or inability of the primary or main
protection scheme to operate or in case of failure to
operate a circuit-breaker other than the associated
circuit-breaker. Also known as secondary protection.
Balancing Code (Be) OC & SOC That part of the Grid Code which details the Balancing
Mechanism.
Balancing OC & SOC A balancing arrangement for the purpose of bilateral
Mechanism contracts for dispatching Generators, access to
additional generation for system needs, and establish a
price for each operating time period at which differences
between contractual and real time operations are settled.
Bilateral CcntrClcts SOC 1.4.2.7 A diract cont~act, (without ~noc having to purchase
power on behalf of the Buyer), between the Power
Producer (Seller) and Purchaser (Buyer) for the
purchase of electric power and energy.
Black Start OC 1.2 The procedure necessary for a recovery from a Total
SOC 2 Shutdown or Partial Shutdown.
Black Start Capability OC For a designated Black Start Station, the ability for at
least one of the generating units of a Generator to Start-
Up from Shutdown; and to energize a part of the System
and/or be synchronized to the System on the instructions
of NTOC, without any external electrical power supply.
Black Start Station OC Black start stations are Generators with Black Start
capability .. An emergency auxiliary (station service)
supply, such as auxiliary diesel-electric generator
capable of supplying auxiliary power to the station is
provided.
Black Start Test OC 11 A test carried out by a Generator to the instructions of
NTOC to demonstrate that the designated Black Start
Station has a Black Start Capability.
BM Participant OC & SOC A Person who is respon~ble for and controls one or
more Generators. For the avoidance of doubt, it does not
imply that they must be active in the Balancing
Mechanism.
Bulk Power Supply PMC The commercial agreement (PPA) between a Generator
Agreement and a purchaser of electric power for the delivery and/or
use of the electric power.
Bulk Power PMC The commercial agreement between the NTOC and a
Transmission Cpq~ Participant for the provision of transmission
Agreement services. f
~~Q"C !'cGU
j) <i?~ (..;.".
~ fJ APPROSED(
~
G&D 224
W BY _ ~)
~ THEAUTHbRITY,.~
GRID CODE

The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached).

ITEM Sub-Code DEFINITION


Schedule as stated in SOC 1.4.3.4) for simultaneous
transmission pur~oses of electric power.
Congestion Condition OC 1 A constraint resulting from overloading of transmission
line and/or transformer which could jeopardize the
system security and integrity.
Connection CC 4 An Agreement between NTDC and or User setting out
Agreement CC 4 the terms and conditions relating to a Connection to
and/or use of its bulk power transmission system.
Connection Charges SOC NTDC's charges to Users for Connection to the NTDC
System.
Connection Point SOC 1 A point at which a User's or Code Participant's Plant and
lor Apparatus connects to the bulk power transmission
system of NTDC.
Connection Site CC 5.4 A site containing a Connection Point.
CC Appendix A
CC Appendix B
Consumer DRC A power generating plant installed at the consumer's
Generating Plant premises by the Consumer.
Consumption PMC Is the use of electrical energy by a licensee or Bulk
Power Consumer, in a period of time that has been
previousli established
Contingency Reserve soc The margin of generation over forecast load demand,
which is required in the periuu frorTI 24 hours ahead, to
be available within 30 minutes of the contingency event;
down to real time to cover against uncertainties in
generation availability and mismatch between load and
generation, and against both weather forecast and
demand forecast errors.
Contracted Capacity soc 1 In relation to a CDGU with a PPA, the Normal Full Load
(NFL) Capacity of the CDGU which is set out in the
Power Purchase Agreement (PPA)/Power Station
Operation & Dispatch Agreement (PSODA) for that
CDGU, as that Normal Full Load (NFL) Capacity which
may be amended from time to time in accordance with
the Power Purchase Agreement (PPA)/Power Station
Operation & Dispatch Agreement (PSODA).
Contracted Capacity SOc In relation to a gas turbine PPA CDGU, the figure
(Peak) (expressed in MW) specified as such in the relevant
Power Purchase Agreement (PPA)lPower Station
OQeration & Disp_atch Agreement (PSODA).
Contracted SOC 1 In relation to a CDGU with a PPA, the values of GSDPs
Generation which are identical to those parameters set out in a
Scheduling and Schedule to the Power Purchase Agreement
Dispatch Parameters (PPA)/Power Station Operation & Dispatch Agreement
(GSDPs) (PSODA) for that CDGU, which are those referred to as
'Contracted Operating Characteristics", as those values,
which can be amended from time to time in accordance
with the Power Purchase Agreement (PPA)/Power
Station Operation & Dispatch Agreement (PSODA). In
the case of an EC CDGU (External~IY C ...tor.jf_"'~."~_k~
values of GSDPs which are identical ara I :Q:
set out in the relevant Inter-conr{ecti ~ reeme~lt~r\
) 2 APPROVED \%\
G&D 226 • -II . BY I~I
\ - .., ~. THEAUTHOHITYI ~
\"U I"), .. ?
GRID CODE

The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached).

ITEM Sub-Code DEFINITION


Frequency Control SOC The control of the frequency on the NTOC System by the
System Operator.
Frequency Deviation SOC A measure of frequency error, from the declaredfTarget
System Frequency, accumulated over a~eriod of time.
Frequency SOC The, mechanism through which the system's frequency
Regulation is maintained within the allowable limits as specified in
the Grid Code (OC 4.8) and NEPRA Performance
Standards (Transmission)-Rules.
Frequency Sensitive OC4.8 The operation of a Generator whereby its generation
Mode level is varied automatically to compensate for variations
in the frequency of the NTOC System in the Frequency
Sensitive Mode (49.8-50.2 Hz).
Frequency Transient SOC For the purposes of Operating Code and Metering &
Protection Code, a period when the NTDC System
Frequency is below 49.5 Hz (Tolerance Frequency
Band).
Fuel Rate SOC 1 Has the meaning ascribed to that term in the relevant
Generator's Power Purchase Agreement (PPA)/Power
Station Operation & Dispatch Agreement (PSOOA) as
applicable. -
Full Load SOC Highest value of load specified for rated conditions of
operation.
Fully Availabl~ CC 5.4 In relation to a COGU or a Range, means Available to
the COGU's Contracted Capacity (or full output in the
case of an EC CDGU).
Generating Plant SOC 1 A Power Plant subject to Central Dispatch.
Generating Unit SOC 1 One of the Units of a Generator in a Generating
CC PlanVStation producing electric power and energy.
Generating Unit Work SOC 1 Auxiliary consumption of an individual Generating Unit of
Unit a Generator.
Generation Offer SOC A set of prices submitted by a Generator in respect of
Prices each of its dispatch units specifying.
1. A Start-up Price (expressed in Rupees)
2. A No-Load Price (expressed in Rupees per Hour)
3.A Maximum Generation Price (a positive value
expressed in Rupees per MWh).
Generation Prices SOC A set of prices for each COGU with PPA calculated by
relevant division of NTDC from the relevant Power
I Purchase Agreement (PPA) and the Fuel Rate
calculated in accordance with the Power Purchase
Agreement (PPA).
Generator CC An Entity who is involved in generation business under a
SOC 1, 3 Generation License granted by NEPRA.
Generator SOC 1 A diagram which shows the MW and MVAr capability
Performance Chart Appendix A limits within which a Generator is expected to operate
under steady-state conditions in the format set out in the
Grid Code.
Generator SOC The main transformer for a COGU through which power
Transformer passes from the Generating Unit to the NTDC System.
Governor CC5.4 A mechanical device used to automatically regulate..Jhe
speed of a turbine of electric generator ~ ~\'J ER R G
; £~
J " ~~-'
C() if APPROVED .%.
~
G &0 231
~ ~I BY ~
\~ THE AUTHORITY .....
~
~
GRID CODE

The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached).

ITEM Sub-Code DEFINITION


Governor Droop SOC 1 In relation to the operation of the governor of a
Appendix A & B Generating Unit, the percentage droop in system
frequency which would cause the Generating Unit under
free governor action to change its output from zero to full
load.

Grid Entry Point SOC A point at which a Generator connects to the NTDC
System.
Grid Exit Point SOC A point at which electricity may be delivered from the
NTDC System to a Bulk Power Consumer. Distribution
Company or to a Tie-line or to Externally-connected
Parties/Consumers.
GSDP Notice SOC 1 A Notification given by a Generator to NTDC stating the
Appendix B GSDPs of a CDGU to apply for the next following
Schedule Day which, if given by not later than the Notice
Submission Time. shall be in the form set out in
Appendix B to SDC1 or in such other form as
NTDC/System Operator may reasonably notify to each
Generator from time to time. and which, if given after the
Notice Submission Time, shall be in the form set out in
Appendix C to SDC1 (which is headed "GSDP Revision
Notice") or in such other form as NTDC may reasonably
notify each Generator from time to time. I

Half Hour OC 4 Means any 30-Minute period ending on the Hour or Half
Hour
Hot Standby SOC A condition of readiness to be able to synchronize and
attain an instructed output in a specified time period that
must be maintained b~ Generator.
IGeEP OC Indicative Generation Capacitl'" Ex~ansion Plan
Incidents OCB An event of external or internal origin. affecting
equipment or the supply system, and which disturbs the
normal operation of the System.
Incremental Price SOC 1 The marginal price (i.e. incremental price for each MWh
AppendixG produced) between zero and Normal Full Load (NFL)
Capacity of a Generator.
Independent SOC A Generator not owned by any public sector entity which
Generating Plant mayor may not be sut&ect to Central Dispatch.
Independent Power PC 3 A private power generating company not owned/
Producer (IPP) controlled by any public sector organization but subject
to Central Dispatch.
Initial Response SOC The device by which NTDC can issue a signal by way of
Instructor dispatch relating to the loading of CDGUs from the
National Power Control Centre (NPCC) to the
Generators.
Instrument SOC A transformer intended to transmit an information signal
Transformer to measuring instruments, meters and protective or
control devices. The term "instrument transfonner"
encompasses both current transformer and voltage
transformers.
Inter tripping Scheme PMC The tripping of circuit-breaker(s) by signals initiated from
protection at a remote location indepen en~\'$rat~

G&D
\\~/
of the local ~rotection.

232 It 'y
rC."V
V.J
c;j
F---I_I
<,
....
APPROVED
BY
GL(
~.0"5.
:t>
fHE: A!lTI!,"""TV C
GRID CODE
The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached).

ITEM Sub-Code DEFINITION


Isolation Device PMC A device for achievin..a electrical I solation.
Load SOC 1 The Active, Reactive or Apparent Power as the context
CC 4.2,5.4 requires to be generated, transmitted or distributed.
Load Curve SOC The curve that represents the behavior of the MW load
during a particular stu~eriod.
Load Curves of Daily SOC The graphical representation of daily peak MWs of an
Peaks electric power entity over a given study period.
Load Factor SOC Is the relation between the average Load Demand of an
established period with regard to the maximum Load
Demand for the same period.
Loss of load PC 4 Loss of Load Probability, the percentage of time that the
probability (LOLP) system c~acitl' is inade~uate to meet load demand.
Low Frequency SOC The process, a part of load reduction or management, of
Disconnection load disconnection (manually or automatic) under low
freguen9' system conditions.
Low Frequency SOC A capability of a Generator to respond to low system
Initiated Response Frequency Transient to initiate its Primary and
Secondary responses to help correct and maintain
permissible system frequency limits as contained in the
Grid Code (OC 4.8 of Operating Code) and approved by
the Authority.
Major Event SOC An Event which either:
(a) was notified by a User To NTDC which NTDC I
considers that has had a or may have had a significant
effect on the NTDC Transmission System, and NTDC
requires the User to report that Event in writing and
notifies the User accordingly; or
(b) was notified by NTDC to a User, and which that User
considers that has had or may have had a significant
effect on that User's system, and that User requires
NTDC to report that Event in writing and notifies NTDC
accordingly.
Maximum Continuous CC, PC, SOC The normal Full Load MW Capacity of a Generator,
Rating (MCR) which can be sustained on a continuous basis under
specified conditions.
Maximum Demand PC Appendix A Maximum electrical power (MW and MVAR) used and
registered in a specified time period.
Merit Order Price Set SOC 1 A price set consisting of an Incremental Price and
No-load Price in relation to a particular designated
declared fuel.
Merit Order Ranking SOC The order at which all the Generators participating in the
Central Dispatch are ranked by the System Operator
based on their Merit Order Price Set for the purpose of
Scheduling and Dispatch. The ranking order is from
lowest to the highest cost, the lowest cost being the first
ones to be di~f>atched.
Metering Data SOC Information on measured electrical quantities recorded in
the meter register, such as energy, demand and power
factor, including time and date.
Metering Equipment SOC Ens-emble of instruments for the purpose of measuring
electricalJluantities which includes Me!€.'.[. CTs CJA¢tr~~.o
) 'If)'?v -
,
u
~
~G Gu.<.....
,~
0

~
G&D 233 ~ '::i APPROVED .~

l~ TUC ~t~~nnITv s)
GRID CODE

The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached).

ITEM Sub-Code DEFINITION


Minimum Generation SOC 1 The minimum MW output, which a Generator can
Appendix A generate continuously, registered with NTOC under
SDC1 as a Generating Station Dispatch Parameter
(GSDP).
Minimum Demand SOC 1 Means minimum level of Active Power of a Generator,
Regulation or MDR which is sufficient to provide an adequate regulating
margin for necessary Frequency Control.
Monitoring Notice SOC A Notice issued by NTDC to a Generator informing the
Generator that NTDC is monitoring one of its COGUs.
Multiple Connection CC More than Single Connection Point, interconnected to
Point each other through the User's System.
Network Operator CC 5.4 An Entity, which operates and manages an electrical
{lower jtransmission or distribution) network.
NFL Capacity SOC The Normal Full Load (NFL) Capacity of a CDGU
(expressed in MW and stated, where relevant, in relation
to a Designated Fuel) to generate electricity (using,
where relevant, the Designated Fuel), determined at the
Generator terminals.
No-Load Price SOC 1 That component of the generation prices of a CDGU
(expressed in Rupees/hour of operation of the CDGU)
which relates to the operation of the CDGU at "No Load:
but vlhich is applicable to all levels of output of that
CDGU.
Nominal or SOC The rated power output specified by the manufacturer of
Nameplate Power agiven electrical equipment.
Nominal System OC4 As defined in NEPRA Rules on Performance Standards
Voltage (Rated (Distribution) or other NEPRA applicable documents.
Voltage)
Notice to SOC The amount of time (expressed in minutes) that is
Synchronize declared by a Generator in relation to a dispatch unit to
enable it to be synchronized following the receipt of an
Instruction to synchronize with the NTDC system.
Notification SOC The daily submission Notice of Availability by Generators
to the System Operator for dispatch purposes.
NTDC Calendar Year Grid Code 1SI January-31 51 December of agivenyear.
NTDC Site CC 4.5 & 5.4 Means a site of inter-connection owned by NTDC or by a
User but occupied and managed by NTDC.
NTDC System PC i. The amount of electricity to be supplied from the Grid
Demand Appendix A Supply Points (Entry or Exit) plus to be supplied by
Embedded Generating Plant plus NTDC
Transmission System Losses less the output of
directly-connected Independent Generating Plants.
ii. Demand on the Total System less the output of
Independent Generating Plants.
Open Access CC 5.4 Provision of connection and non-discriminatory ·Use" of
the transmission, sub-transmission and distribution
network of a licensee.
Operat'mg Margin SOC 1 & OC 5 Sum of Contingency Reserve and Operating Reserve as
defined in OC 5.2.
Operating Reserve SOC The additional output frorn Generators which must be
realizable in real-time operations to respond i~~tr,~-
/' ftG 'r G~~o
t,1 \,-.J4.; AP PROVED~.
-n

\\~/
G&D 234
~ UJ BY :t>
_J c:
.:i I!~ r. ~ ! I T ~ () Q f TV" ,
GRID CODE

The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached). "

ITEM Sub-Code DEFINITION


contribute to correcting and containing any system
frequency fall to an acceptable level after the loss of
generation or loss of import from an External
Interconnection or mismatch between generation and
Load Demand,
Optimum Dispatch SOC The dispatch with due regard to both economic and
(Final Dispatch) technical conditions r~~resents the optimum dispatch,
Out of Band VAR SOC Reactive power supplied by a Generator operating
outside of its rated power factor.

Outage SDC1 a, In relation to a CDGU/Generator. a total or partial


Appendix B reduction in Availability in connection .un the repair
or maintenance of the CDGU or any associated
power plant equipment, or resutting from a
breakdown or failure of the CDGU or any associated
power plant equipment.
b, In relation to NTDC. the removal for repair or
maintenance, or as a result of failure or,breakdown,
of any part of the NTDC System.
c, Means the state of a component when it is not
available to perform its intended funaion due to
some event directly associated with that.component.
An outage mayor may not cause an interruption of
service to customers, depending -nn system
configuration.
Outage Notice SOC A Notice submitted by a Generator under OC4 notifying
NTDC of an Outage, "

Output CC 5.4 The actual output at the main generator terminals of a


SOC 1 CDGU (in MW) derived from data measwed pursuant to
Appendix A this Grid Code,
Overburn Contracted SOC In relation to a CDGU, which is capable of firing one or
Capacity two different Designated Fuels, the flQUre expressed in
MW, measured at the Generator terminals iientified in a
Schedule to the relevant Power Purchase Agreement
(PPA)/Power Station Operation & Oispatdl Agreement
jPSODAl as ·Overburn Contracted C~
Part load SOC A Generator which is loaded but is not .running at its
declared Availability,
Partial Collapse SOC Breakdown of the electrical system due to a failure or
contingency that affects a particular area or region of the
country and is limited to that area or reJi.ion only.
Partial Shutdown SOC 1 The situation existing when all generation has ceased in
a particular part of the Total System: and 'there is no
electricity supply from External Interconnections or other
parts of the Total System to that particular:',part of the
Total System and, therefore, that particular',part of the

Total System is shutdown; with the result !Rat it is not
possible for that particular part of the Total System to
pegif1
.
;, , ~
to function again without NTDC directOns
, ... relating
to a Black Start. .'i :,

'1 !J:7:,
J..
Peak Capability SOC In relation to a -.9,as turbine COGU.j1fe ca ~';I~~ I

~ ,',
3 ," APPROVED -~
,(..~ ()

~
G&0 235 .
, 1~~1
'.J" BY- 1:> I
~\ THE AUTHORITY I~
GRID CODE

The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached).

ITEM Sub-Code DEFINITION


CDGU (expressed in MW) to generate electricity in
excess of its Contracted Capacity determined in
accordance with the relevant Power Purchase
Agreement (PPA)/Power Station Operation & Dispatch
Agreement (PSODA).
Plant CC 4.4 & 5.4 Fixed and movable equipment used in the generation,
SDC 1 transmission and distribution of electricity.
Appendix A
PI ant Factor DRC The relation of the total actual generation to the
generation that may have been produced if the unit had
operated in a continuous manner to its Normal Full Load
(NFL) Capacity.

Po'mt of Con nection CC 5.4 An electrical Connection Point between the NTDC bulk
power transmission system and a User's/Code
Participant System as defined in OC 4.2 of the Grid
Code.
Power Line Carrier OC6 Communications system of radio frequency generally
(PLC) under 600 kHz, which transmits infonnation using high
voltage transmission lines.
Power Plant SDC 1 An installation comprising one or more Generating Units
Appendix A & B owned and controlled by the same Generator.
CC 1
Power Purchase SDC 1 Power Purchase Agreement is between the Seller
Agreement (PPA) ("Generator" in this case) and the Buyer [licensed
distribution companies, Bulk Power Consumers whether
directly or indirectly connected to the NTDC's bulk
transmission system and other Persons as stated in
DRC 1.2 (d)], other externally-connected Parties and
Consumers, for the purpose of purchase of electric
power and energy.
The Power Purchase Agreement mayl contain
operational, control, dispatch, outage and maintenance
procedures and requirements of the power station,
technical limits, GSDPs, Generation Performance
Charts, and other Generator data requirements stated in
various sub-codes of this Grid Code or it may refer to the
Grid Code for such requirements.
Power Station SDC 1 Not withstanding anything contained in the PPA between
Operation & Dispatch a Generator and Purchaser of electric power and
Agreement (PSODA) energy, each Generator having a bilateral contract shall
have in place, at all times, a Power Station Operation &
Dispatch Agreement (PSODA) with NTDC for the
purposes as follows:
The PSODA shall contain operational, control, dispatch,
outage and maintenance procedures and requirements
of the power station, technical limits, GSDPs, Generation
Performance Charts, and other Generator data
requirements stated in various sub-codes of this Grid
Code.

G&D 236
GRID CODE

The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached).

ITEM SUb-Code DEFINITION


Power Station SOC 1 Power Station means Power Plant in this Grid Code.
Power System CC Equipment controlling the exciter output via the voltage
Stabilizer (PSS) regulator in such a way that power oscillations of the
synchronous machines are dampened. Input variables
may be speed, frequency or power (or a combination of
these).
Preventive OC 4, SOC 1 Is the periodic maintenance performed on the equipment
Maintenance to avoid the occurrence of possible unplannned failure or
outCJaes.
Primary Response SOC The automatic response to NTDC system frequency
changes released increasingly with time over the period
o - 3 seconds and 3-10 seconds from the time of
frequency change, and fully available within these time
scales and achieving its maximum value within 10
seconds following a frequency fall and subject to the
agreed Unit Load Controller adjustment where
applicable and must be sustainable for upto 30 seconds.
Protection and PMC The provisions for detecting faults or other abnormal or
Control emergency conditions in a power system. For enabling
fault clearance, for terminating abnormal or emergency
conditions, and for initiatif'!.9. slanals or indications.
Reactive Power CC 5.4 The product of voltage and current and the sine of the
SOC i phase angle belween them measured in units or volt-
amperes reactive and standard multiples thereof i.e.
1000Var = 1kVAr
1000kVAr = 1MVAr
=
1000MVAr 1GVAr
Reactive Reserve SOC The MVAR reserve on the on-line Generators (difference
between MVAR capability at the output MW level at a
Jliven time and actual MVARRr'oducedl
Real Time Operation OC4 Operation performed by NTDC through the SCADA
monitoring system.
Registered PC The Normal Full Load (NFL) Capacity of a Generator in
Capacity Appendix A MW measured at the Generator terminals.
Regulating Margin SOC The margin of generating capacity over Demand which
is required in order to maintain fre~uency control.
Remote Terminal Unit OC6 A part of the SCADA system. It is a set of electronic
(RTU) devices that collects and transmits data to, and receives
and execuies the commands from the master unit.
Reserve SOC The MW level of reserve required at any given MW
Characteristics output of a CDGU as set out in the Sustained Load
Diagram which is a part of the Grid Code or Power
Purchase Agreement (PPA)/Power Station Operation
and Dispatch Agreement (PSODA).
Revenue Metering SOC 1 Metering used to measure the demand and energy at a
specific point in the system upon which an invoice will be
prepared and payments shall be made between power
supplier and User.
Safety Coordinator CC A Person or Persons nominated by NTDC and each
User to be responsible for the co-ordinati~~1~
Precautions at each connecti0lr PO~~ .~~
Jwhich includes testinJIl is to be c rried CJ n a System k;o
I 1&( APPROVED ~.
~ ~I ~
~
G&D 237 BY
i iHE AUTHORITY _~
~;.. ~
GRID CODE

The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached).

ITEM Sub-Code DEFINITION


which necessitates the provision of Safety Precautions
on HV Apparatus
Schedule Day SOC 1 The period from 0000 hours until 2400 hours on the
Appendix A same day.
Scheduling SOC The process of compiling a Generating Schedule as set
out in SOC 1, and the term "Scheduled" and like terms
shall be construed accordingly.
Second-tier Users CC The Users having bilateral contracts with another
licensee through the NTDC transmission system for
acq uiring power.
Secondary Response CC 3 It is the increase in active power output of the online
generators or reduction in active load demand that can
be increasingly applied in the short-term following the fall
in frequency available within the time scale of
10-30 seconds after achieving its maximum value within
30 seconds following the fall in frequency, subject to
agreed Unit Load Controller Adjustments where
applicable, and must be sustainable for 30 minutes
following the fall in frequency.
Short Term Planned SOC An Outage designated as an STPM Outage, the duration
Maintenance Outage of which shall not, unless NTDC in its absolute discretion
or STPM Outage agrees, exceed 72 hours but not including any overrun
of such Outage.
Single Line Diagram PC Appendix A Schematic representations of a three-phase network in
which the three phases are represented by single lines.
The diagram shall include (but not necessarily be limited
to) bus bars, overhead lines, underground. Cables,
power transformers, and reactive compensation
equipment. It shall also show where Generating Plant is
connected, and the points at which Demand is supplied.
Single Point of CC A single Point of Connection, with no interconnection
Connection through the User's System to another Point of
Connection.
Site Common CC4.4 Drawings prepared for each Connection Site which
Drawings incorporate Connection Site layout drawings, electrical
layout drawings, common protection! control drawings
and common service drawings.
Spinning Reserve SOC 1 As defined in OC 5.2 of this Code which is available
within 10 minutes of the initial fre_quency fall.
Standing Instruction SOC An Instruction for a specified action notified to a
Generator in advance by NTDC whereby. when the
specified circumstances arise, the Generator will take
the specified action as though a valid Instruction had
been issued by NTDC. This shall include:
a) The date on which an Outage is to begin.
b) The time at which an Outage is to begin.
Start·Up SOC 1 The action of bringing a Generator from shutdown to
~pendixA synchronous speed.
Start-up Price SOC That element of the generation prices for a CDGU which
relates to the start-up of the CDGU. ....-:~rn ....--.

Station Transformer PC 2.1 A transformer supplying electrical ~~~~(~


auxiliaries of a Generator, whJ:;h i s ' direc'ti7~G1/,
u/ 0
I.I.J APPROVED -~
I I~I BY ~C
G&D 238
\\Q-./- t.
,
.J
,~ T' lE.A I.lTHORITY .;!
GRID CODE

The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached).

ITEM Sub-Code DEFINITION


connected to the Generator terminals.
Subsequent Schedule SOC 1 A Schedule prepared subsequent to the Generation
Schedule following a re-optimization of that Generation
Schedule or another Subsequent Schedule. within the
ap2licable Control Phase time scale.
Sustained Load SOC 1 A Schedule setting out the Sustained Response
Diagram Capability of a CDGU annexed to the Power Purchase
Agreement (PPA)/Power Station Operation & Dispatch
Agreement (PSODA) for that CDGU and submitted to
NTDC pursuant to the Planning Code.
System Grid Code Bulk power transmission system of NTDC.
System Constrained PC Appendix A That portion of transmission capacity which is not
Capacity available due to a system or transmission constraint.
System Energy OC2 Total MWhr requirements of the entire NTDC system
Requirements which is based on summation of all the measured
energy on all the Connection Points of the NTDC system
with its Users consuming electric power.
System Fault PMC A measure of the ability of Protection to initiate
Dependability Index successful tripping of circuit breakers, which are
(DP) associated with a faulty item of Apparatus. It is
calculated using the formula:
DP = 1 - F1IA Where:
A = Total number of systt!m faults
F 1 = Number of system faults where there was a failure
to triR a circuit breaker.
System Operating OC4.9 Bus Voltage as a percentage of the Nominal System
Voltage Voltage of the Total System during normal system
operation (including both normal and contingency
operating conditions but excluding transient and
abnormal system conditions).
System Margin OC5 The Margin in any period between (i) Offered Availability
and (ii) The sum of Forecast Demand and the Operating
Margin. for that period.
System or OC. PC. SOC 1 A limitation on the Use of Transmission System due to
Transmission lack of transmission capacity or other system conditions.
Constraint
Target System OC4 FreqeucnyLevels of the NTDC bulk transmission system
Frequency as stated in this Grid Code for the normal steady-state
operation of the NTDC bulk supply tranmission system
as contained in the Opeating Code(OC 4.8)
Target Voltage Levels OC4.9 Voltage limits for the normal and contingency operation
of the NTDC bulk supply transmission system as
contained in the Operating Code
(OC 4.9).
Technical Parameters Code Such parameters which define the design and operation
Management of the electrical system and its facililes that are
owned/operated by NTDC.
Telemetering OP6. OP 7. CC A process in which measurements are made at some
remote location and the results are transmitted through
telecommunication facilities. The transmission of the
values of measured variables using teleC~t~~~
~c "9:
G &D
~/
techniques is also called telemeterir]Q.

239 ~I (09'
j..-
4[
ILl
..§..C

APPROVED
BY
t;
.~9~
~
;: TUt: 'ItTUnOITV 5
GRID CODE

The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached).

ITEM Sub-Code DEFINITION


Temperature SOC In relation to a gas turbine CDGU, the Peak Capability
Adjusted Peak adjusted by the temperature correction factor in
Capability accordance with Schedule to the relevant Power
Purchase Agreement (PPA)/Power Station Operation &
Dispatch Agreement (PSOOA).
Thermal Efficiency SOC 1 Is the quantity of BTU's required for the fuel to generate
a kWh of electrical energy.
Thermal Loadings OC 4 Electrical loadings (MW/MVAR) of the electrical
transmission facilites of NTOC bulk supply system.
Tolerance Frequency SOC & OC 4 Protected periods of operation of the system at the
Band frequency in the range of 49.5 Hz - 50.5 Hz as defined
in OC 4.8.
Total Collapse OC 8 Breakdown of the national intercomected electrical
system due to a failure or severe contingency that
causes the interruption of the electrical services of the
entire system.
Total Harmonic CC The departure of a waveform from sinusoidal shape, that
Distortion is caused by the addition of one or more harmonics to
the fundamental, and is the square root of the sum of the
squares of all harmonics expressed as a percentage of
the magnitude of the fundamental.
Total Shutdown OC 8 The situation existing when ali generation of the system
has caased resulting in the shutdown of the power
system, that it is not possible for the power system to
begin to function again without NTOC directions relating
to a Black Start.
Total System Grid Code Bulk power transmission system of NTDC.
Transmission CC 1 & CC 5.4 A consumer receiving electricity directly from the NTOC
Connected Transmission system irrespective of the supplier of
Consumers electrical power and energy.
Transmission SOC A point at which a User's or Code Participant's Plant and
Connection Point lor Apparatus connects to the bulk power transmission
system of NTOC.
TSEP OC Transmission System Expansion Plan
Unit Control Board SOC A switchboard through which electrical power is supplied
to the auxiliaries of a Generator and which is supplied by
the station transformer. It may be interconnected with
the station main control board.
U nit Load Controller SOC A device which regulates the generation level when the
Generator is operating in Frequency Sensitive Mode to
ensure (as far as possible) that it does not exceed or fall
short of acceptable limits as set in the Grid Code (OC
4.8) and NEPRA Performance Standards
(Transmission)-Rules.
U nit Load Controlier SOC The time constant expressed in units of seconds, of the
Response Time power output increase that occurs in response to a step
Constant change in system frequency.
Unit Nomination SOC 1 In relation to a Generator means the Unit Nomination
Appendix G and covered in SOC 1.4.2.3.C submitted day ahead by
each Generator.
User CC1 A term used to refer to the Code Participant o~~ w.:--
I Iftc.,>( Gu
I {;-~ ~-'"'
~ 0
G &0 240 ~
(-JAPPROVED /J
\\G., ~ lU
•.-1
~i T 'C
BY
-'liT.,
-<
.~
GRID CODE

The Terms Not Contained here have been Defined in Various Applicable
Documents of NEPRA and listed as Annexure-A (attached).

ITEM Sub-Code DEFINITION


whom the Grid Code applies; who is directly or indirectly
connected and using the bulk transmission network of
NTDC for the purposes of acquisition, transmission,
distribution, and/or consumption of electrical power and
energy.
User Site CC 4.4 A site owned (or occupied pursuant to a lease, licence or
other agreement) by a User in which there is a
Connection Point. For the avoidance of doubt, a site
owned by NTDC but occupied by a User as aforesaid, is
a User Site.
User System CC 1 Any system owned or operated by a User comprising: (i)
Generator; or (ii) Electrical systems consisting (wholly or
mainly) of electric facilities used for the transmission or
distribution of electricity from Connection Points
onwards.
The User system includes any sub-transmission assets
operated by such User or other Person, and any plant
and/or apparatus and meters owned or operated by the
User or other Person in connection with the
transmission, distribution and delivery of electric power
but does not include any part of the NTDC bulk power
transmission system.
Voltage Regulation OC 4.9 Is the process that is used to contiOl the System
Operating Voltage, and maintain it within the tolerable
limits as specified in OC 4.9 of the Grid Code.
Warning Notice SDC A Notice issued by NTDC to a Generator pursuant to the
Operating Code informing the Generator that it has failed
to compJi with a Dispatch Instruction.

G&D 241
(Annexure-A)
DEFINITION
Sr. Item Definition Reference
No.
1. Act Means the Regulation of Generation, Transmission and Application and
Distribution Electric Power Act, 1997 (XL of 1997). Modification Procedure
Rules-1999
2. Affiliate In relation to any person, means any person who owns licensing Rules
or controls, or is owned or controlled by, or is under (Distribution) 1999
common ownership or control with, the person, and for licensing Rules
that purpose of this definition. (Generation) 1999

(a) Control Means the right, power or ability to influence or Transmission Licence to
NTDC
determine any decision in respect of the conduct of
affairs of the person under control.

(b) Ownership Means the ownership or the right to own the shares or
voting securities of the persons owned.
3. Agreement and Means the fuel Supply Agreement, the Implementation Generation Licence to
Agreements Agreement, the Power Purchase Agreement and any IPP
or all them"
• Securit y Package
• Project Co-ordination Agreement
4. Ancillary Services Means the services ancillary 0 incident to the safe, Licensing Rules
reliable, stable and efficient availability and utilisation of (Generation) 1999
electrical energy and net capacity and include without Transmission Licence to
limitation, the following, namely:- NTDC
(a) energy imbalance service;
(b) spinning reserve service;
(c) supplemental reserve service;
(d) reactive supply voltage control service; and
(e) regulation and frequency response service.
5. Applicable Documents Means the distribution licence, the second-tier supply Licensing Rules
authorisation, NERPA rules and regulations, the grid (Distribution) 1999
code, the distribution code and any documents issued Licensing Rules
under any of the foregoing or pursuant to the exercise (Generation) 1999
of the Authority's powers under the act, in each case of
a binding nature applicable to the Licensee or where Transmission Licence to
NTDC
applicable, to its affiliates and to which the Licensee or
any of its affiliates may be subject.
r-..- .. - .. - .. - .. - •. - .. - .. - .. - .. - .• - .. - .. - .. - .. - .. - .. - .. - •. -
Means the rules and regulations issued in pursuance of Feel Rules 2002
the Act by the Authority, from time to time, relating to
the generation, distribution and transmission licenses,
the grid and distribution codes and any documents,
instruments, approvals or authorizations issued or
granted by the Authority in exercise of its power under
the Act
6. Applicant Means any person who applies for a distribution Eligibility Criteria for
licensee for provision of electric power service or Consumers of
Distribution Companies
modification thereof.. 2003
7. Application Means an application made by a person in accordance Application and
with the provisions of these regulations and shall, Modification Procedure
Rules-1999
where the context so admits, include the documents-in-
support, and Happlication" shall be construed
accordingly.
8. Auditors Means the licensee's auditors for the

t-~
& AP?ROVED ~'O\
-~.\
d B't' ~I
\;1.,TH£ f.1.JTHORIT't'j!,
Sr. Item Definition Reference
No.
holding office in accordance with the requirements of
the Companies Ordinance, 1984 (XLVII of 1984), or licensing Rules
(Generation) 1999
such other auditors as may be appointed in respect of
the licensee by the Authority from time to time in
accordance with these or the distribution/generation
licence.
9. Authorised/Authorized Means in relation to any maller, authorised in writing by licensing Rules
the Authority. (Distribution) 1999
10. Authorised Etectricity Means any person other than the Licensee, who is Transmission Licence to
Operator authorised by the Authority through a licence or NTDC
otherwise for the purpose of using the Licensee's
transmission system.
11. Authority Means the National Electric Power Regulatory Transmission licence to
Authority constituted under section 3 of the Act. NTDC

12. Authority Proposed Means a modification to a licence proposed by the Application and
Modification Authority. Modification Procedure
Rules-1999
13. Authorized Officer Means the authorized by the Authority to perform NEPRA Service
functions under these Regulations. Regulations 2003
14. Availabte Means a generating unit or tie-line transfer that is both Transmission licence to
(a) available in accordance with the Grid Code and (b) NTDC
declared as available for the generation of electricity.
15. Average Energy For the purpose of Article 23 means energy charges Transmission licence to
Charge calculated on the basis of the average of the month NTDC
uniformly for the 24 hour period of each day of the
month.
16. Balancing Services For the purpose of Article 8 means services to be Transmission licence to
rendered under a ba!ancing arrangement frv.... the NTDC
purpose of bilateral contracts for dispatching plants,
access to additional generation for system needs and
establish a price for each operating time period at
which differences between contractual and real time
positions are settled.
17. Bulk Power Consumer Means in respect of and within the Service Territory, licensing Rules
(BPC) such consumer who receives or purchases, electric (Distribution) 1999
power in the amount, voltage level and frequency equal
to or grater than the characteristics of supply set out in
the distribution licence, provided that, the Authority may
change he characteristics 0 supply for bulk-power
consumers located within the Service Territory at the
time and in the manner set out in the distribution
licence. ._._._. ___ 0_0_'_ ..
Means a-eonS-urn 'who purchases or
er -recelve-s' et"eciiTc
NEPRA Act 1997
power, at one premises, in an amount of one megawatt
or more or in such other amount and voltage level and
with such other characteristics as the Authority may
determine and the Authority may determine different
amounts and voltage levels and with such other
characteristics for different areas.
18. Capacity Charge For the purpose of Article 23 means monthly capacity Transmission licence to
charge for the distribution companies, proportional to NTDC
the maximum demand recorded at each metering
points on the basis of a per kW demand charge
determined by dividing the total capacity transfer
charge by the summation of the peak demand of each
distribution compa'ny recorded at feed points.
19. Common Distribution
System
Means the distribution system as defined in the
~ttH~~
distribution licence other than the dedicated distriputio~ t-~UIlIt:I~0

i
f,.<.J'I Z\~~
(tl APPROVED %
.-J BY I~
\\Ch/ ~\THEAUTHOR'rY IS
Sr. Item Definition Reference
No.
system. Distribution Companies
2003
20. Communication Means any information, comment, representation, TariH Standards and
pleadings, correspondence, or evidence filed with the Procedures Rutes 1998
Registrar, the presiding officer or the Authority in
connection with any proceedinqs.
21. Competent Authority Means the Authority, the appointing authority or any NEPRA Service
officer/senior employee of NEPRA who is designated Regulations 2003
by the Authority to exercise the powers of the
Competent Authority.
22. Competitive Market Means a date on which the first competitive trading Transmission Licence to
Operation Date period of a bilateral contracts market shall commence. NT DC
f--_I~MOD)
23. Concession Territory Means the territory outside Ihe Service Territory of the Distribution licence
licensee defined by the administrative/geographical
boundaries as delineated in Schedule-I to this Licence.

Means the territory outside the Service Territory of the Eligibility Criteria for
Consumers of
distribution licensee defined by the
Distribution Companies
administrative/geographical boundaries as delineated 2003
in a distribution licence.
24. Connecting Point For the purposes of this Consumer Eligibility Criteria Eligibility Criteria for
Consumers of
means the pOint where the dedicated distribution
Distribution Companies
system of the applicant is connected with the existing 2003
common distribution system.
25. Connection Means the provision of electric power supply services. Perlormance standards
(Distribution) Rules 2003
26. Connection Charges Means the charges made or levied or to be made or Licensing Rutes
(Distribution) 1~~~
levied for the carrying out of works and provisions and
installation of electrical plant, electric lines and circuits
and ancillary distribution system together with charges
in respect of maintenance and repair of such items in
so far as not otherwise recoverable as use of system
charges and in respect of disconnection and the
removal of electrical plant, electric lines and circuits,
and ancillary meters following disconnection, or such,
other charges as may be specified in or pursuant to the
distribution licence.

Means the charges made or levied or to be made or Licensing Rutes


(Generation) 1999
levied for carrying out works for the installation and
maintenance of licensee interconnection facilities.
27. Consents Means all permissions or approvals required from any Licensing Rules
(Distribution) 1999
public sector entity.
Transmission licence to
NT DC
Means all permissions, approvals or consents required Licensing Rules
by the licensee from any public sector entity for the (Generation) 1999
purposes of the distribution business.
28. Consumer Means a person or his successor-in-interest who NERPA Act 1997
purchases or receives electric power for consumption
and not for delivery or re-sale to others, including a
person who owns or occupies a premises where
electric power is supplied.
29. Consumer Eligibility Means the criteria for the eligibility of consumers to Licensing Rules
Criteria obtain supply of electric power developed by the (Distribution) 1999
Authority.
30. Consumer Service Means the manual of instructions developed jb Y the./~Rl~
/r '\.LJfSlrib~

~~ ff: APPRO'lED)~~~.
w
I
pv

~
c:
Sr. Item Definition Reference
No.
Manual licensee and approved by the Authority detailing
instructions and guidance to the consumers other than
bulk-power consumers occupying domestic,
agricultural, industrial or commercial premises for
obtaining electric power distribution services, as more
fully described in rule 9.
31. Core Business Means each of the transmission business and tie-line Transmission Licence to
NTOC
business.
32. Cost per Unit of For the purpose of Article 20 means the cost per kilo Transmission Licence to
NTOC
Energy watt-hour (kWh) of electricity as determined and
verified by an independent assessor.
33. Dedicated Distribution Means that part of the distribution system, required to Eligibility Criteria for
Consumers of
System supply power for the sole consumption of an applicant
Distribution Companies
and not for supplying power to any other consumer and 2003
shall comprise of the distribution system from the
connecting point upto the interconnection point of the
applicant including the metering and service wire and
such other connection arranQements.
34. Dispatch Means the issuance of instructions to the licensee by licensing Rules
(Generation) 2000
the national grid company, the relevant national power
control center or any other entity established under the
pooling and settlement arrangement, as may be
decided from time to time in this regard by the
Authority, to schedule and control the operation of the
generation facilities in order to make available or
commence, increase, decrease or cease the delivery of
electric power or the ancillary services, in accordance
with the applicable documents.
35. Distribution Means the ownership, operation, management or NEPRA Act 1997
control of distribution facilities for the movement or
deliver or sale to consumers of electric power but shall
not include he ownership, operation, management and
control of distribution facilities located on private
property and used solely to move or deliver electric
power to the person owning, operating, managing and
controlling those facilities or to tenants thereof.
36. Distribution Business Means the business of distribution of electric power Licensing Rules
(Distribution) 1999
carried on or to be carried on by the licensee pursuant
to and in accordance with the terms of the distribution
licence Qranted to the licensee.
37. Distribution Code Means the distribution code referred to in rule 15. Licensing Rules
(Distribution) 1999
38. Distribution Company Means a person engaged in the distribution of electric NEPRA Act 1997
power.
39. Distribution Facilities Means electrical facilities operating at the distribution NEPRA Act 1997
voltage and used for the movement or delivery of
electric power.
40. Distribution System Means the distribution facilities situated within the Licensing Rules
(Distribution) 1999
Service Territory owned or operated by the licensee for
distribution of electric lines or circuits, electric plant,
meters, interconnections facilities or other facilities
operating at the distribution voltage, and shall also
include any other electric lines, circuits, transformers,
sub-stations, electric plant, interconnection facilities or
other facilities determined by the Authority as forming
part of the distribution system, whether or not operating
at the distribution voltage.
41. Distribution Voltage Means any voltage below the minimum transmisslon N~~~

~
I
~ rr~
f "PP~~VED_ •. \
Sr. Item Definition Reference
No.
voltage.
42. Document-in-Support Means the documents to be provided with the Application and
application for the licence of subsequently, in Modification Procedure
Rules·1999
accordance with regulation 3.
43 Economic· Dispatch Means system of establishing economic precedence of Transmission Licence to
electric power from available generating units or tie-line NTDC
transfers directed by the Licensee or any other entity
established under competitive trading arrangements.
licensing Rules
Means the allocation of demand to individual (Generation) 1999
generation plants or units to effect the most economical
production of electricity for optimum system economy,
security and reliability with due consideration of
incremental generation costs, incremental power
purchase costs, incremental transmission and
distribution losses, load flow considerations and other
operational considerations as determined solely by the
national grid company, the relevant national power
control center or any other entity established under the
pooling and settlement arrangement, as the Authority
may, from time to time in this regard, decide.
44. Electric Power Means electrical energy or the capacity for the NEPRA Act 1997
production of electrical power. .
45. Electric Power Means the generation, transmission or distribution of NEPRA Act 1997
Services electric power and all other services incidental thereto.
46. Emergency Means cases where the patient requires immediate NEPRA Service
medical attention and any delay may be detrimental to Regulalions 2003
his/her health.
4 (. Encumbrance Means any mortgage, charge, right of possession, Transmission licence to
assignment by way of security, right of possession or NTDC
other form of security interest.
48. Energy Imbalance Means the provision of electrical energy for any hourly licensing Rules
Service or half-hourly mismatch between the supply and (Generation) 1999
demand at any given point of delivery.
49. Financial Year Means a consecutive period of twelve calendar months Fee Rules 2002
commencing on the first day of July 0 any year and
1n
ending on the 30 day of June of the following year.
50. Fuel Supply Means the Fuel Supply Agreement dated as Generation licence to
Agreement mentioned, modified, updated, revised or restated IPP
between the Licensee and the Fuel Supplier thereofY)
51. Generation Means the ownership, operation, management or NERPA Act 1997
control of generation facilities for delivery or sale of
electric power and not solely for consumption by the
person owning, operating, managing, and controlling
those facilities.
52. Generation business Means the business of availability and provision of licensing Rules
electric power or ancillary services or other related (Generation) 2000
business through the construction, ownership,
management, control or operation of the generation
facilities or the licensee interconnection facilities carried
out, or to be carried out, by the licensee, whether itself
or through an agent or sub-contractor approved in this
behalf by the Authority, pursuant to and in accordance
with the terms of the generation licence granted to the
licensee and, where applicable, includes the second-
tier supply business carried out by the licensee.
53. Generation company Means a person engaged in the generation of electrjc NEX\Nt:R"d'~
power. / /I(~~ ~'.E..!!..u/"
Sr. Item Definition Reference
No.
54. Generation facility Means the electrical facility used for the production of NEPRA Act 1997
electric power.
55. Glossary of Standards Means as provided in Schedule-I of Performance Perfonnance Standards
Standards (Distribution) Rules 2003 (Distribution) Rules 2003
56. Grid Code Means the grid code prepared by the national grid licensing Rules
company or in the absence of the national grid (Distribution) 1999
company by the transmission licensees pursuant to the
transmission licenses and approved by the Authority,
as from time to time revised with the approval of the
Authority.
Means the grid code prepared by the national grid licensing Rules
company with the approval of the Authoritv. (Generation) 1999
57. Hydro licensee Means a generation licensee constructing, owning, licensing Rutes
operatinQ or manaQinQ hydel generation facilities. (Generation) 1999
58. Implementation Means the Implementation Agreement dated as Generation licence to
amended, modified, updated, revised or restated IPPs
Agreement
between the Licensee and the President of Pakistan.(;')
59. Incremental generation Means the additional cost that would be incurred by licensing Rules
cost producinQ the next available unit of electrical enerQY. (Generation) 1999
60. Information Includes documents, accounts, reports, records, data, Application and
returns or estimates of any description. Modification Procedure
Rules-1999
61. Information direction Means a direction issued by the authority or the Tariff, Standards and
presiding officer to any person to provide information to Procedures 1998
the Authority
62. InterConnection Point Means the point where the metering installation and Eligibility Criteria for
protection apparatus of the consumer is connected to Consumers of
Distribution Companies
the dedicated distribution system. 2003
63. Interconnection Means the equipment, including, without limitation, licensing Rules
Facility/Facilities electrical lines or circuits, transformers, switch-gear, (Distribution) 1999
safety and projective devices, meters or electrical plant,
used for interconnection services.

Means plant and equipment, including the electrical


licensing Rutes
lines or circuits, transformers, switchgears, safety and (Generation) 1999
protective devices or meters used for interconnection
services. DRC
64. Inter~onnection Means the connection of one company's electrical NEPRA Act 1997
service facilities to another company's electrical facilities.
65. Intervention request Means an intervention request filed under rule 6. Tariff, Standards and
Procedures 2002
66. KESC Means the Karachi Electric Supply Corporation, a NEPRA Act
public limited company, incorporated under the
Companies Act, 1913.
67. kV Means kilo-volts or 1,000 volts. Performance Standards
(Distribulion) Rutes 2003
68. Laws Include all statutes, rules and regulations made licensing Rules
pursuant thereto, judicial decisions, administrative (Distribution) 1999
practices or direction having the force of law in licensing Rutes
Pakistan, in each case as may be applicable to the (Generation) 1999
Licensee or its affiliates.
Transmission licence to
NTDC
69. Licence Means a licence issued for generation, transmission or NEPRA Act 1997
distribution under this Act.
70. Licensee Means a holder of a licence. NERPA Act 1997
71. Licensee
interconnection

~ ~~PPROVE~~~~
I~( ~) BY
\~;., THE AUTHORITY;;
Sr. Item Definition Reference
No.
facilities
72. Licensee proposed Means a modification to the licence proposed by the Application and
modifications licensee. Modification Procedure
Rules-1999
73. Licensee's investment Means the licensee's investment programme referred Licensing Rules
programme to in rule 17. (Distnbution) 1999
74. Licensee's power Means the licensee's power acquisition programme Licensing Rules
acquisition referred to in rule 12. (Distribution) 1999
programme
75. Load Shedding Means the process of deliberately removing either Performance Standards
(Distribution) Rules 2003
manually or automatically pre-selected consumer's
load demand from the power system as per scheduled
programme on a rotating and proportionate basis for
each class of consumers notified earlier by the DISCOs
76 Long Duration Power Means loss of electric supply to one or more Performance Standard s
Supply Interruption (Distribution) Rules 2003
consumers for a duration of more than three minutes.
77. Metering Installation Means the metering and associated equipment Eligibility Criteria tor
installed for recording Consumers of
required to be
Distribulion Companies
consumption/usage of electric power of an applicant. 2003
78. Minimum transmission Means sixty-six kilovolts or such other voltage that the NEPRA Act 1997
voltage Authority may determine to be the minimum voltage at
which electrical facilities are operated when used to
deliver electric power in bulk.
79. Motion Means any oral or, if so directed by the Authority, Tariff, Standards and
Procedures 1998
wrHten application in relation to any matter of
procedure undt:r tht::;8 rui!!:;.
80. National grid company Means the person engaged in the transmission of NEPRA Act 1997
electric power and granted a licence under section 17.
81. NEPRA (Fees and Means the rules developed by the Authority in respect Application and
Penalties) rul es Modification Procedure
of the payment of fees by the licensees and the
Rules·1999
procedure for impOSition and payment of fines and
penalties levied by the Authority.
82. NEPRA rules and Means the relevant rules and regulations made by the Licensing Rules
regulations (Distribution) 1999
Authority under the Act.
licensing Rules
(Generation) 1999
83. Net capacity Means the aggregate of the maximum rating of the licensing Rules
(Generation) 1999
generation facilities constructed, owned, managed,
controlled or operated by the licensee under its
generation licence, modified for ambient limitations,
which is established in the manner specified in the grid
code, the generation licence or a power acquisition
contract entered into by the licensee, less the capacity
used to supply the auxiliary needs.
84. NTDe Means National Transmission and Dispatch Company Performance Standards
(Distribution) Rules 2003
85. Operator Means a person authorized by the distribution company Performance Standards
to operate its electrical facilities. (Distribution) Rules 2003
86. Ordinance Means the Companies Ordinance, 1984. Application and
Modification Procedure
Rules-1999
87. Penalty Means a penalty, which may be imposed under these NEPRA Fee and Fine
Regulations. Rules 2002
88. Person Shall include an association of persons, conc rn,
~1~

\\Q,/
company, firm or undertaking

1)~t ~[
~
GY~ ~(.

lLJ
,:1. THE
AP?RO'lEb
BY
J\
.~UTHOR.ITY, .~
.~
l>
Sr. Item Definition Reference
No.
89. Petition Means a petition made to the Authority for the Tariff, Standards and
determination, modification or revision of tariff Procedures 1998
90. Planned Power Supply Means planned or scheduled outage of electrical Perfonnance Standards
supply to one or more consumers. In the event of (Distribution) Rules 2003
Interruption
Planned Power SupplY Interruption, notice shall be
served to all affected consumers at least forty-eight
hours in advance of any such planned outage
excluding defense establishments where Planned
Power Supply Interruptions will only be taken through
mutual aqreement.
91. Pleadings Means the petition, the replies to the petition and Tariff, Standards and
rejoinders to replies. Procedures 1998
92. Point of Outag e Means the point in the distribution system of a Perfonnance Standards
distribution company beyond which electric service is (Distribution) Rules 2003
interrupted including without limitation: Grid station, 11
kV feeders, 400/230 volts line, and transformer.
93. Pooling and settlement Means any arrangements implemented by or under the Licensing Rules
arrangements directions of the Authority for the spot or market based (Distribution) 1999
sales and purchases of electric power through an
electric power exchange or other means .
. _.-.-._.-.-._.-.-.-._._._._._._._._.-.-._.- . . _._.-.-.-._.-.- ..

Means the arrangements for establishing or Licensing Rules


implementing a wholesale market for the sale and (Generation) 1999
purchase of electrical energy, net capacity or ancillary
services under the relevant NEPRA rules and
regulations.
94. Power acquisition Means a contract or other arrangement for the Licensing Rutes
cor.tiact acquisition by the licensee, whether through saie and (Dis!rib'Jti"n) 1999
purchase for consideration or otherwise, of electric Licensing Rules
power including, where applicable a contract for (Generalion) 1999
purchase of electric power .on the basis of difference in
prices of electric power between the rates pursuant to
the pooling and settlement arrangements and the rates
determined according to the method stated in such
contract.
95. Power Purchase Means the Power Purchase Agreement Generation Licence to
as amended, modified, updated, IPPs
Agreement dated
revised or restated between the Licensee and the
power purchaser thereofYii)
96. Power Supply Means loss of electric supply to one or more Perfonnance Standards
Interruption consumers. (Distribution) Rules 2003
97. Prescribed Means prescribed by rules made under this Act. NERPA Act 1997
98. Presiding Officer Means the presiding officer appOinted by the Authority Tariff. Standards and
under sub-rule (5) of rule 9 and, for the purpose of Procedures 1998
these rules, where the context so admits, shall also
mean the Authority.
99. Proceedings Means the entire process commencing from the date of Tariff, Standards and
filing of petition with the Registrar or, where the Procedures 1998
authority initiates the process of determination of tariff,
the date of such initiation by the Authority, and ending
on the date the Authority makes its final determination
on a petition, and shall include any stage during the
proceedinqs.
100. Prospectus Means a report prepared by the applicant setting out: Application and
i) a brief introduction of the applicant Modification Procedure
Rules-19.9.9..
ii) the salient features of t
/ ~O\NERR..~
1

tJ /;j~APPROVE~~~
(} .....
"r
\~ ~ .-IBY
~ TH2 AUTHORITY S
l'>
Sr. Item Definition Reference
No.
iii) the facility or the system in respect of which the
licence is sought;
iv) the proposed investment; and
v) the social and environmental impact of the
proposed facility or system in a non-technical and
commonly understood language.
101. Prudent utility Means the practices of an operator of an electric power Licensing Rules
practices undertaking seeking in good faith to perform its (Distribution) 1999
obligations and in the conduct of its undertaking
exercising that degree of skill, diligence, prudence and
foresight which would reasonably be expected from a
skilled and experienced operator and complying with
the relevant Laws and codes.

Means the practices of an operator of an electric power


undertaking seeking in good faith to perform its Licensing Rules
(Generation) 1999
obligations and in the conduct of its undertaking
exercising that degree of skill, diligence, prudence and
foresight which would reasonably be expected from a
skilled and experienced operator complying with the
Laws and applicable documents.
102. Public conveyance Means a plane, train, or other mode of conveyance NEPRA Service
used for travel and is not owned by the employee. Regulations 2003
103. Public sector entity Means any authority, agency, division or instrumentality Licensing Rules
of the Federal or Provincial Government or a local (Distribution) 1999
authority but does not include the Authority. Licensing Rules
(Generation) 1999

Licence
Transll1is~iUI1 10
NTDC
104. Public sector project Means generation, transmission or distribution facilities NEPRA Acl1997
constructed, owned, managed or controlled by the
Federal Government, a local authority or any body
owned or controlled by any such Government or
Authority.
105. Reactive supply and Means the provision of reactive power through changes licensing Rules
voltage control service to the generator reactive output to maintain (Generation) 1999
transmission line or distribution line voltage.
106. Regulation and Means the provision for moment-to-moment variations Licensing Rules
frequency response in the demand or supply for maintaining scheduled (Generation) 1999
ser'Jice interconnection frequency.
107. Regulations Means regulations made under this Act NEPRA Act 1997
108. Rules Means the National Electric Power Regulatory Transmission Licence to
Authority rules made under section 46 of the Act. NTDC

Means the National Electric Power Regulatory Licensing Rules


Authority Licensing (Generation) Rules, 2000, as (Generation) 1999
amended from time to time.
109. Rural Area Means the area falling within the jurisdiction of all rural Performance Standards
local bodies, including without limitation union councils, (Distribution) Rules 2003
tehsil councils and zila councils.
110. Sale period For the purpose of Article 23 means the period of a Transmission Licence to
month, day, 4 hour, hour or half an hour during which NTDC
the generation charges for all the power stations are
averaged out on a weighted average basis to I 4NER R~
determine. the sale rate and transfer price for salEJ to I~c.. ~ ~uA
Sr. Item Definition Reference
No.
..
distribution companies or other entities receiving
electric power through central power purchasing
agency.

111. Schedul e Means the Schedule to these rules. Fee Rules 2002

112. Second-tier Supplier Means any licensee authorized to carry out the second- Licensing Rules
(Distribution) 1999
tier supply business.
113. Second-tier supply Means an authorization to engage in the second-tier Licensing Rules
(Distribution) 1999
authorization supply business.
114. Second-tier supply Means the authorised business, if any, of the licensee Licensing Rules
(Distribution) 1999
business or any of its affiliates as a supplier, whether or not
carried out pursuant to a power acquisition contract, of
electric power to one or more bulk-power consumers
_._._._._.-._.-
~it~.!n.9f ~itl1q,~,-,~~ .~~ry!~~ J.e!~iLo.ry. _ . _ . _ . _ . _ . _ . _ . . ..
Means the authorized business, if any, of the licensee
Licensing Rules
or any of its affiliates as a supplier of electric power or (Generation) 1999
ancillary services to a bulk power consumer.
115. Separate business Means each of the transmission business of the Transmission Licence to
NTDC
Licensee, tie-line business of the Licensee, the
provision of settlement services and any other business
of the Licensee, undertaken separately. ._._.-._.-.-._._ ..
Means- each' of the 'disiributTon h-u'slriess,' fh'e- secona: Licensing Rules
tier supply business or any other business taken (Distribulion) 1999
separately from one another and from any other
business of the licensee or any affiliate of the licensee .
. _._._._._._._._._._._._._.-._._._._._._.-.- . . _._._._.-.-._._ ..
Maans each of th~ gtln~ration business, the second- licensing Rules
tier supply business, the provision of ancillary services (Generation) 1999
or any other business taken separately from one
another and from any other business of the licensee or
any affiliate of the licensee.

116. Service territory Means the area specified in the distribution licence Licensing Rules
(Distribution) 1999
within which the licensee is authorised to conduct the
distribution business and, subject to the provisions of
rule 7, the second-tier supply business.
117. Short Duration Power Means loss of electric supply to one or more Performance Standards
consumers for a duralion of three minutes or less (Distribution) Rules 2003
Supply Interruption
excluding momentary interruptions of duration less than
one second.
118. SHYDO Means the Sarhad Hydel Development Organization, NEPRA Act 1997
established under the Sarhad Hydel Development
Orqanization Act, 1993 (NWFP Act No.1 of 1993).
119. Small Power Means owner of a generation facility of below 100 MW Transmission licence to
Producers gross capacity, who was engaged in generation and NTDC
nd
sale of electric power as on 22 April, 2000 and who Distribution Licence
has not signed any power purchase agreement with
WAPDA or KESC or an implementation agreement with
the Government of Pakistan.
120. Spinning reserve Means the provision of additional capacity from licensing Rules
(Generation) 1999
service generating units thai are on-line, loaded to less than
their maximum output, and available to serve system
demand immediately should be contingency occur.
121. Step Potential Means difference of voltage between the steps of an Performance....Standards
operator, human being or animal coming in contract or
operalinq electrical facilities of the distribution

~
I~~~
rn~/
lui
~
~(
~~
AP?ROVED10 ~.
~
J\
W B'f
~_ THe AUTHORITY ;...i!,
Sr. Item Definition Reference
No.
company.
. .
122. Supplemental reserve Means the provIsion of additional capacity from Licensing Rules
service generating units that can be used to respond to a (Generation) 1999
contingency within the period defined in this behalf in
the grid code.
123. System Average Means the average duration of consumer Power Performance Standards
Interruption Duration Supply Interruptions per consumer occurring in a given (Distribution) Rutes 2003
Index (SAlOl) year. SAlOl is the average time the consumers of a
distribution company who remained without power. It is
determined by dividing the aggregated sum of all
consumers power supply interruption durations in
minutes by the total number of consumers served by a
distribution company in a given year.
124. System Average Means the average frequency of consumer Power Performance Standards
Interruption Frequency Supply Interruptions per consumer occurring in a given (Distribution) Rules 2003
Index (SAIFI) year. SAIFI is calculated by dividing the total annual
number of consumer Power Supply Interruptions by the
total number of consumers served by a distribution
company in a given year.

125. Tariff Means the rates, charges, terms and conditions for Tariff, Standards and
Procedures 1998
generation of electric power, transmission, inter-
connection, distribution services and sales of electric
power to consumers by a licensee

126. Technical limits Means the limits and constraints relating to the licensing Rules
operation, maintenance and dispatch of a generation (Generation) 1999
faciiity, as agreed to between an applicant for a licence
and the Authority at the time of grant of the generation
licence or subsequently as determined by the Authority,
or between the licensee and any purchaser, procurer or
recipient of electric power or ancillary services from the
licensee, consistent with the technical functional
specifications set out in the schedule to the generation
licence pursuant to sub-rule (2) of the rule 3, the grid
code and any applicable distribution code and not
inconsistent with the applicable documents.
127. Tie·line Means interconnection facility for the transfer of electric Transmission lice,)ce to
power between the Licensee and other utilities not N70C
governed by the Act.
128 Total system Means the Licensee's transmission system and the Transmission licence to
transmission and distribution systems of all authorised NTOC
electricity operators located in Pakistan.
129. Transmission Means the ownership, operation, management of NEPRA Act 1997
control of transmission facilities.
130. Transmission Means the business of transmission of electric power Transmission licence to
Business carried on or to be carried on by the Licensee pursuant NTOC
to and in accordance with the terms or this Licence in
planning, development, construction and maintenance
of the Licensee's transmission system and operation of
such system for the transmission and dispatch of
electric power including the balancing services and
inter-connection services.
131. Transmission facilities Means electrical transmission facilities including NEPRA Act 1997
electrical circuits, transformers and sUb-stations
operating at or above the minimum transmission
voltage but shall not include: l@\~~~
-
~<.-;

J\
a. electrical circuits forming the immediate conne~tion (<po/

\\Q-/ ~ rr ~
LU
, TW
APPROVED

'.UTHO~1TY. _~~)
BY \I
~.
>
Sr. Item Definition Reference
No.
between generation facilities and the transmission
grid to the extent that those circuits are owned by a
generation company and are directly associated
with that company's generation facilities; and
b. specified facilities operating at or above the
minimum transmission voltage which the Authority,
upon an application by a licensee under section 20
determines, shall be owned and operated by a
distribution licensee.
132. Transmission System Means one or more systems comprising electrical Licensing Rules
(Distribution) 1999
facilities including. without limitation, electrical wires or
circuits. electrical plant. transformers, sub-stations. Licensing Rules
switches, meters, interconnection facilities or other (Generation) 1999
facilities operating at or above minimum transmission
Transmission Licence 10
voltage constructed, owned, managed, controlled or
NTOC
operated by the licensee or by one or more special
purpose transmission licensees and used for
transmission of electric power from the generation
facility to SUb-stations or to or from other generation
facilities or between sub-stations or to or from any
interconnection facilities or from the distribution
facilities of one licensee to the distribution facilities of
another licensee or from a generation facility to a
distribution facilityor a bulk-power consumer.
133. Unit commitment Means turning-on and bringing up to speed anyone or licensing Rules
(Generation) 1999
more of the generation units comprised in the
generation facilities of the licensee and synchronizing
and connecting st;ch units' to the transmission sl"stem
for the deliver of electric power or ancillary services
and, where the context so admits, includes the process
by which the determination as to which units are to be
committed is made.
134. Urban area Means the area falling within the jurisdiction of all urban Performance Standards
(Distribution) Rules 2003
local bodies or development authorities, including
without limitation, town committees, municipal
committees, municipal corporations, metropolitan
corporations and cantonment boards.
135. Use of system Means the use of the distribution system for the Licensing Rules
(Distribution) 1999
transport of electric power by and for and on behalf of
the licensee and, in relation to a second-tier supplier
other than the licensee, for and on behalf of such
second-tier supplier.

Means the use of the transmission system or one or Licensing Rules


more distribution systems for the transport or deliver of (Generation) 1999
electric power or ancillary services.
136. Use of system charges The charges made or levied or to by made or levied by Licensing Rules
(Distribution) 1999
the licensee for the use of the system for the purpose
of the distribution business or the second-tier supply
business or in respect of the use of the distribution
system by a second-tier supplier but shall not include
connection charges.

The charges made or levied by the national grid Licensing Rules


company, a special purpose transmission licensee or a (Generation) 1999
distribution ~icensee, as the case may be, for the use
by the licensee of their respective systems for thle
purposes of its generation business.
I
~
~---- # --

Sr.
No.
.
Item . Definition Reference

137. WAPDA Means the Pakistan vVater and Power Development NEPRA Act 1997
Authority established under the Pakistan Water and
Power Development Authority Act, 1958 (W.P .Act XXXI
I of 1958)
138... ~APDA rele~~f1~ ________ t-Ji1e- instructions, manuals or __ guidelines used by Licensing Rules
- ---
(Distnbuticn) 1999
--~

manuals WAPDA in relation to the matters to which such

139. Year
. instructions, manuals or guidelines relate.
Means a financial year.

Licensing Rules
(Generation) 1999
NEPRA SerJice
ReQulations 2003
140. Year or Annual For the purpose of these Rules means the period of Performance Standards
st
twelve months beginning on 1 July and ending on 30
th (Distribution) Rules 2003
June.

13

You might also like