Prestressed Concrete Design: A. Reference: NSCP 2015 and AASHTO 2007 (SI Edition) Philosophy of Prestressed Concrete
Prestressed Concrete Design: A. Reference: NSCP 2015 and AASHTO 2007 (SI Edition) Philosophy of Prestressed Concrete
INTRODUCTION
Methods of Prestressing
Pretensioned
Post-tensioned
B. Methods of Prestressing
1. Pretension
Tensioning of the prestressing steel (called tendons) is done before concrete pouring
Usually done in a prestressing plant
Mass production
Rapid curing (usually using steam curing where 70% of f c' is attained in 24 hours)
Figure
Bulkhead Bulkhead
Anchor
T
plate
Steam
pipeline Prestressing bed
a) Tendons are put in place and through the bulkheads. One end is anchored.
b) The other end of the tendons is pulled using a hydraulic jack with a prescribed tension
force/stress.
c) The tendons are released from the jack and anchored at the jacking end with the use of
wedges.
d) The rebars and formworks are installed.
e) Concrete pouring is done next.
f) After initial curing (e.g. after 24 hours), the tendons are released from the anchor plates.
The tension force on the tendon is now TRANSFERRED as a compression force on the
concrete members.
g) The tendons are cut (at the ends of each concrete member) and the pretensioned
concrete members are then lifted and transferred elsewhere for storage.
h) The prestressing bed is now cleaned and made ready for the next batch.
2. Post-tension
Tensioning of the tendons is done after concrete has initially cured.
Fabrication of the prestressed members can be done anywhere (e.g. at the prestressing
plant, at the project site using cast-in-place or cast-on-site techniques).
Procedure:
a) The rebars and formworks are installed.
b) The tendons are placed inside a duct and installed in place.
c) The tendon profile is either straight or a smooth curve.
Anchor T
plate Jacking
end
d) Pour the concrete
e) After concrete has attained a prescribed initial strength (f ci') from initial curing (80% of f c'
can be attained in 2 weeks of normal curing), the tendons are jacked.
f) The tendons are released from the jacks (with wedges to maintain the tension force
within the tendon) and the tension force is TRANSFERRED to the concrete member as a
compression force.
g) After the jacking operation is completed, grout is usually introduced to fill up the ducts.
Jacks
-single strand jacks
-multi strand jacks
Ducts
- 3 inch diameter can contain a maximum of 12 strands
- or slightly bigger ducts can have 18 strands
The introduction of a compression stresses in the concrete member can offset the
expected tension stresses from the external loads.
Therefore, the whole concrete section will be active when there is no tension and no
cracking. This is called FULL PRESTRESSED design. PARTIAL PRESTRESSED DESIGN will
allow some amount of tension stress and cracking to occur. The former is more
common.
High strength concrete is used (minimum is f c' of 35 MPa).
Flexural members (beams) have very high moment capacities.
Used for beams with long spans and/or large moments.
D. Stages
Jacking Stage
Force in the tendon is Pj
Stress in the tendon, Pj / Aps = fpj
Transfer or Initial Stage
Force in the tendon is Pi
Stress in the tendon, Pi / Aps = fpi
Instantaneous prestress losses will occur. This means that P i < Pj and fpi<fpj
Concrete strength is fci' and the modulus of elasticity is Eci = 4.7 √ f ' ci
Service Stage
Force in the tendon is Pe
Stress in the tendon, Pe / Aps = fpe
Time-dependent prestress losses will occur over a protracted period. This means
that Pe < Pi and fpe<fpi
Concrete strength is fc'.
Note: The next 2 stages are hypothetical, meaning the prestressed concrete member may not actually
reach these stages.
Cracking Stage
This is when the maximum tension stress is equal to the modulus of rupture, f r.
Hence, at this stage, cracking is INCIPIENT.
Ultimate Stage
This is when the ultimate capacity of the section has been reached.
The behaviour is no longer elastic and the principles of limit analysis, like USD, is
now operative.
Note: The concrete member and tendons will behave elastically within the first 3 stages.
Prestress Losses
1. Instantaneous Losses
a. Anchorage Loss
b. Friction Loss
c. Elastic Shortening
2. Time Dependent Losses
a. Creep
b. Shrinkage
c. Steel Relaxation
Section Properties:
Use of Prestressed Concrete Technology is dangerous for incompetent hands. The prestress force is an
ACTIVE FORCE and must be handled properly. The assumptions made during design should reflect the
actual condition when constructed (and vice versa).
MATERIALS:
Concrete
o High strength
o Usually 35 MPa, 41 MPa, 70 MPa, 345 MPa???
Prestressing Steel (Tendons)
o Wires
o Bars
o Strands (Area of strand shall be determined from Tables)
7-wire strand
Grade 250 (fpu = 1725 MPa), 12.7mm: Aps,1 = 92.9 mm2
Grade 270 (fpu = 1860 MPa), 12.7mm: Aps,1 = 98.7 mm2
Stress-strain diagram
fpu
fpy
Ep
fpu Ultimate tensile strength (Gr. 270 or 1860 MPa and Gr. 250 or 1725 MPa)
fpy Yield strength (0.85fpu for stress relieved strands or 0.90f pu for low relaxation
strands). See table below.
VSL
CCL
Freyssinet
BBRV
Advantages of Prestressed vs RC
Disadvantages of Prestressed vs RC
A. Analysis Methods
Method of Stresses
Used only for determinate systems.
Equivalent Load Method
Applicable to both determinate and indeterminate systems.
B. Method of Stresses
Note: The first column of stresses are from the prestress force P. This is expressed by the formula:
fc = -(P/A) + (P*e)y/I
f = -(P/A) E Pe/S
In Figure (d) and (e) above, at midspan, the concrete stresses due to P are
The concrete stresses due to the external loads are determined using the usual procedures and formulas
(f = My/I). These are then combined with the stresses due to P, (f = -P/A).
The tendon stresses are evaluated at the JACKING STAGE and at the TRANSFER/INITIAL STAGE.
> fpj
> fpi
Concrete stresses are evaluated at the TRANSFER/INITIAL STAGE and at the SERVICE STAGE.
o At TRANSFER or INITIAL STAGE, the active forces are P i and beam weight.
o Permissible Concrete Stresses at TRANSFER or INITIAL STAGE
Concrete Tensile
Stress Limit
o At SERVICE STAGE, the active forces are Pe, beam weight, other dead loads and live loads.
o Permissible Concrete Stresses at SERVICE STAGE
A rectangular concrete beam with a width b = 275mm and a total depth h = 700mm is post-
tensioned using a single parabolic tendon with an eccentricity of 200mm at midspan and 0mm
at the simple supports. The initial prestress force P i = 1500 kN, and an effectiveness ratio R =
Pe/Pi = 0.84. The member is to carry superimposed dead and live loads of 4.4 kN/m and 14.6
kN/m, respectively, uniformly distributed over the 12m span. Specified concrete strength f c’ = 35
MPa, and at time of transfer f’ci = 28 MPa. Determine the flexural stress distributions in the
concrete at midspan (a) for initial conditions before application of superimposed load and (b) at
full service load. Compare with NSCP limit stresses for Class U members.
Solution:
At INITIAL stage, the active forces are Pi = 1500 kN and the beam weight wo = 0.1925*24 = 4.62 kN/m.
The maximum moment at midspan due to the beam weight is M o = 4.62*122/12 = 55.44 kN-m. Stresses
at the top and bottom of the section at midspan are as follows:
Therefore, tension reinforcements are required. The amount of reinforcements will depend on the
tension force T.
3.097
y
y = 3.097/21.778*700
= 99.545mm
1 18.681
T = ∗3.097∗99.545∗275 /1000
2
= 42.39 kN
Assuming that Gr. 40, 16mm bars are used, the amount of reinforcements can be determined using an
allowable tensile stress of 0.5fy for the rebars.
42.39∗103
Req’d As = =¿ 307.17 mm2
0.5∗276
307.17
=¿
The required number of bars, n = π∗162 1.52 bars, say 2 bars.
4
The permissible stress for compression at the INITIAL stage is as follows:
Allowable fcomp = 0.6*28 = 16.8 MPa < 18.681 (Fail)
At SERVICE stage, the active forces are Pe = 0.84*1500 = 1260 kN and the total load w T = 4.62 + 4.4 + 14.6
= 23.62 kN/m.
The maximum moment at midspan due to the total load is M T = 23.62*122/12 = 283.44 kN-m. Stresses at
the top and bottom of the section at midspan are as follows:
The permissible stress for tension at the SERVICE stage for Class U is as follows:
There is no tensile stress in the section at midspan since the stress at the bottom is still in compression.
Therefore, the tensile permissible stress is complied with.
The permissible stress for compression at the SERVICE stage based on the total load is as follows:
For sustained loads: wS = 4.62 + 4.4 = 9.02 kN/m. The maximum moment is M S = 9.02*122/12 = 108.24
kN-m. The maximum compressive stress at the top is solved below.
Top: ftop = -P/A + Pe/St – MS/St = -6.545 + 11.221– 108.24/22.458 = -0.144 MPa
The permissible stress for compression at the SERVICE stage based on the sustained loads only is as
follows:
Determine the required number of strands using Gr. 270, ½” diam. strands for a prestressing for P i =
1500 kN.
Solution:
1500∗1000
A ps= =1152.1 mm2
1302
The area of one strand is Aps1 = 98.7 mm2 and the required number of strands is
1152.1
n= =¿ 11.67 strands, say 12 strands.
98.7
Example: Determine the maximum eccentricity that will comply with the concrete stresses at INITIAL
stage based on the loads and the other given data from the previous problems and without using
tension reinforcing bars.
Solution:
Top: ftop = -P/A + Pe/St - Mo/St = -1500/192.5 + 1500*e/22.458 – 55.44/22.458 = 1.323 MPa
22.458
Therefore, e = (1.323 + 7.792 + 2.469)* = 0.173 m
1500