Charles Hanskat, P.E., FACI, FASCE Managing Principal Concrete Engineering Group, LLC

The document discusses the differences between ACI 301, which is intended for structural concrete in buildings, and ACI 350.5, which is intended for structural concrete in liquid-containing structures and has additional requirements due to the aggressive environments. ACI 350.5 provides specifications for contractors building liquid-containing structures, covering areas like material requirements, shotcrete, and prestressed reinforcement protection. The presentation reviews the development of ACI 350.5 and its differences from ACI 301 to help specifiers understand how to apply its requirements for liquid-containing concrete projects.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
59 views33 pages

Charles Hanskat, P.E., FACI, FASCE Managing Principal Concrete Engineering Group, LLC

The document discusses the differences between ACI 301, which is intended for structural concrete in buildings, and ACI 350.5, which is intended for structural concrete in liquid-containing structures and has additional requirements due to the aggressive environments. ACI 350.5 provides specifications for contractors building liquid-containing structures, covering areas like material requirements, shotcrete, and prestressed reinforcement protection. The presentation reviews the development of ACI 350.5 and its differences from ACI 301 to help specifiers understand how to apply its requirements for liquid-containing concrete projects.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 33

Charles Hanskat, P.E.

, FACI, FASCE
Managing Principal
Concrete Engineering Group, LLC
ACI 350-06 Code Requirements for
Environmental Engineering Concrete
Structures
Intended for who?
Designers
Not appropriate for Contractors
ACI 350.5 Specification for
Environmental Engineering Concrete
Structures
Is specifically and entirely intended
for the Contractor
ACI 301 is intended for
Structural concrete for buildings
Parallels ACI 318
ACI 350.5 is intended for
Structural concrete for liquid-
containing structures
Parallels ACI 350
Liquid-Containing Structures (LCS) are not
the same as building
Higher loads
Dynamic loads
Constant exposures to aggressive
environments
Liquids
Chemicals
Extremely sensitive to cracking that
affects serviceability
Through section cracks 5 mils wide will
leak
High fluid pressure
Special Structures or Processes not
Covered by ACI 301
Membrane floors
Thin, highly reinforced concrete slabs
on soil.
Circular wrapped prestressed tanks
Shotcrete
Similar Layout and Organization
Greater Cover Requirements
Enhanced Material Requirements for Exposures
Shotcrete
Higher Prestressed Reinforcement Protection
Additional Section on Wrapped Prestressed
Reinforcement
Includes “Membrane Floors”, Doesn’t Include
“Industrial Floors”
“ACI Specification 350.5 cannot and
does not address responsibilities for
any project participant other than
Contractor.”
Guidance to the specifier
Mandatory
Optional
Are not part of the ACI 350.5 Specification
Serve as Flags
Items Specifier evaluates in developing the
specific Project Specification
Mandatory Checklist Items
“indicates work requirements regarding
specific qualities, procedures, materials,
and performance criteria that are not
defined in ACI Specification 350.5.”
Mandatory Checklist Items
“The Specifier must include these
requirements in the Project Specification.”
Optional Checklist Items
“identifies Specifier choices and
alternatives. The checklist identifies the
Sections, Parts, and Articles of the ACI
Reference Specification 350.5 and the
action required or available to the Specifier.

Optional Checklist Items
“Specifier should review each of the items in
the Checklist and make adjustments to the
needs of a particular project by including
those selected alternatives as mandatory
requirements in the Project Specification.”
ACI 350.5 Completed
Committee Balloting
TAC Review
Public Review
Response to Public Comments Complete
Next is Approval of Standards Board
Publication Formatting
Committee Review of Proofs
Publication – Maybe End of 2012, Early 2013
Font, size, and color for text have been formatted
for you in the Slide Master
Use the color palette shown below
See next slide for additional guidelines
Hyperlink color: www.microsoft.com

Sample Fill Sample Fill Sample Fill

Sample Fill Sample Fill Sample Fill


Subtitle color

Example of a slide with a subhead


Set the slide title in “title case”
Set subheads in “sentence case”
Generally set subhead to 36pt or smaller so it will fit on
a single line
The subhead color is defined for this template but must
be selected. In PowerPoint 2007, it is the fourth font
color from the left
5

3 Series 1
Series 2
2 Series 3

0
Category 1 Category 2 Category 3 Category 4
Chart Title
9%
10% 1st Qtr
2nd Qtr
23% 58% 3rd Qtr
4th Qtr
6

4 Series 1
3 Series 2
Series 3
2
Series 4
1

0
Category 1 Category 2 Category 3 Category 4
14

12

10

8 Series 3
6 Series 2
Series 1
4

0
Category 1 Category 2 Category 3 Category 4
Name
Title
Group
Name
Title
Company
Name
Title
Company

You might also like