This document provides instructions for installing and configuring Cyberoam Central Console (CCC) as a virtual machine on VMware ESX server. The key steps include: 1. Downloading the CCC OVA file and deploying the OVF template in vSphere Client. 2. Configuring resource allocation, network mapping, and disk format settings. 3. Activating the CCC virtual machine by providing an appliance activation key. 4. Configuring basic network and security settings in the CCC web admin console.

Uploaded by

raddouane
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
113 views

CCC Vmware Server Installation Guide: Document Version 1.0-02.00.1 Build 016

This document provides instructions for installing and configuring Cyberoam Central Console (CCC) as a virtual machine on VMware ESX server. The key steps include: 1. Downloading the CCC OVA file and deploying the OVF template in vSphere Client. 2. Configuring resource allocation, network mapping, and disk format settings. 3. Activating the CCC virtual machine by providing an appliance activation key. 4. Configuring basic network and security settings in the CCC web admin console.

Uploaded by

raddouane
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 16

CCC VMware Server

Installation Guide
Document Version 1.0- 02.00.1 build 016
CCC VMware Server Installation Guide

Table of Content

Typographic Convention ........................................................................................................... 3 


Preface ...................................................................................................................................... 4 
System Requirements .................................................................................................................... 4 
Installation Procedure ..................................................................................................................... 4 
Resource Allocation ................................................................................................................... 10 
CCC Virtual Machine Activation ................................................................................................. 11 
Virtual CCC Basic Configuration ................................................................................................ 12 
Other Configurations .................................................................................................................. 14 
CCC VMware Server Installation Guide

Typographic Convention
All contents in this guide including text or screenshots follow the given list of conventions.

Item Convention Example


Topic titles Shaded font
typefaces
Preface
Subtitles Bold & Black
typefaces Notation conventions
Navigation link Normal File → Deploy OVF Template it means, to open the
typeface required page click on File then on Deploy OVF Template.

Notes & Bold typeface


Recommendati between the Note
ons black borders
CCC VMware Server Installation Guide

Preface
Welcome to CCC VMware Server Installation and Deployment Guide. This guide describes how to
download, deploy and run Cyberoam Central Console as a virtual machine on VMware platform.

System Requirements
The hardware requirement for installing CCC VMware Server is dependent on number of
appliance(s) to be managed by CCC VMware Server. Following table outlines the important
hardware components and their recommended availability.

Appliances
Model RAM Hard Disk Drive Browser
Supported
CCC VMS 15 15 2 GB free space SATA or SCSI hard Microsoft
(Minimum) disk with minimum 80 Internet Explorer
GB free disk space 7.0+
CCC VMS 50 50 4 GB free space SATA or SCSI hard Mozilla Firefox
(Minimum) disk with minimum 3.0+
160 GB free disk Google Chrome
space
Best view -
CCC VMS 100 100 4 GB free space SATA or SCSI hard
Mozilla Firefox
(Minimum) disk with minimum
3.0+
250 GB free disk
space
CCC VMS 200 200 4 GB free space SATA or SCSI hard
(Minimum) disk with minimum
320 GB free disk
space

Installation Procedure
Pre-requisite
Make sure that VMware ESX server and VMware vSphere client to access ESX server is already installed
in your network.
Please refer to http://www.vmware.com/ for details.

Installation procedure covers:

• CCC Virtual Machine Installation


• CCC Virtual Machine Management

CCC Virtual Machine Installation

1. Download OVA file


Download .ova file of Cyberoam Central Console OVF image from following link and store it in your
machine.
http://download.cyberoam.com/virtualccc

2. Login to VMware vSphere Client

Start VMware vSphere client and login using credentials provided by your service provider to
manage CCC Virtual machine.
CCC VMware Server Installation Guide

Screen – Login to VMware vSphere Client

3. Deploy OVF Template


Once you login to VMware vSphere client go to File → Deploy OVF Template.

Screen – Deploy OVF Template


Click Browse to locate .ova file (step 1) in your machine and click Next to proceed.
CCC VMware Server Installation Guide

Screen – Specify OVF Template Location


4. OVF Template Details
This screen displays details of deployed OVF template. OVF template details include:
• Product name
• Download size
• Size on disk

Click Next to proceed.


CCC VMware Server Installation Guide

Screen – OVF Template Details


5. Name and Location for Deployed OVF Template
Specify the name and location of deployed OVF template and click Next to proceed.

Screen – Name and Location


CCC VMware Server Installation Guide

6. Disk Format
Specify the disk format to store CCC virtual machine. Choose one of the following disc allocation
formats as per your requirement:
• Thin Provisioned Format: Thin provisioning allows allocation of storage space to virtual
machine(s) on on-demand basis i.e. initially it commits only that much space which is
required for initial operations.
• Thick Provisioned Format: Thick provisioning allows allocation of all the available space to
the virtual machine(s) immediately.

Click Next to proceed.

Screen – Disk Format


7. Network Mapping
Specify the network(s) available in your inventory to be used by OVF template and click Next to
proceed.
CCC VMware Server Installation Guide

Screen – Network Mapping

Click Finish to complete installation process.

Screen – Ready to Complete


CCC VMware Server Installation Guide

Screen – CCC Virtual Machine Installation

Screen – Successful Installation of CCC VMware Server

CCC Virtual Machine Management

Management of CCC Virtual machine includes

• Resource Allocation
• CCC Virtual Machine Activation
• Virtual CCC Basic Configuration
• Other Configurations

Resource Allocation
Once the CCC Virtual machine is installed, you can start managing it using VMware vSphere
client.

Screen – Manage CCC VMware Server


To change the resource allocation of CCC Virtual machine, go to Resource Allocation tab and click
Edit to change the allocation of CPU and memory to the CCC Virtual machine.
CCC VMware Server Installation Guide

Screen – Resource Allocation

CCC Virtual Machine Activation

Pre-requisite
Please make sure that http://cyberoamupdate.elitecore.com/ is accessible from deployed CCC virtual
machine

1. You need to activate the Virtual CCC in order to start managing it.
Given below is the default network schema for your CCC Virtual machine.
• Port A: 172.16.16.16/255.255.255.0
• Port B: 192.168.2.1/255.255.240.0
• Default Gateway: 192.168.1.254

If your organization’s network schema differs from default network configuration, please update it
using ‘1. Network Configuration’ option available in CCC Virtual machine CLI Console to get
Internet connectivity.

Screen – Network Configuration

Network Configuration option allows you to view and change network settings. Use this option to
change IP address of available ports.

For further details, please refer to CCC Console guide.

2. To activate the CCC Virtual machine, select ‘AA. Appliance Activation’ option and provide
appliance activation key.
CCC VMware Server Installation Guide

Screen – CCC Virtual Machine Activation

Screen – Successful Activation of CCC Virtual Machine

3. After successful activation of CCC Virtual machine, browse to default (http://172.16.16.16) or the
configured IP address to access Web Admin Console of Virtual CCC. Use following default
credentials to access and manage Virtual CCC from Web.
• Username: admin
• Password: admin

Virtual CCC Basic Configuration


1. Once you login to CCC Web admin console you can change interface(s) IP address from
Management Console → CCC Management → Network →Interface.

Screen – Change Interface IP Address


CCC VMware Server Installation Guide

Change default gateway IP address from Management Console → CCC Management →


Network → Gateway.

Screen – Change Gateway IP Address

2. Configure DNS from Management Console → CCC Management → Network →DNS.

Screen – Configure DNS

3. Set time zone and current date from Management Console → CCC Management →
System →Time.
CCC VMware Server Installation Guide

Screen – Time Settings

Congratulations!!!
This finishes the basic configuration of Virtual CCC and you are now ready to use the Virtual machine.

Other Configurations

1. Create Customer Account and register Virtual CCC

Browse to http://customer.cyberoam.com and click Register and follow the on-screen steps. It will
create your customer account as well as register your Virtual CCC.

2. Configure Cyberoam to communicate with Virtual CCC

• Enable management of the Cyberoam appliance by Virtual CCC from System →


Administration → Central Console and enter IP address of CCC appliance.
• Select heartbeat protocol to communicate with Virtual CCC.

Make sure, Virtual CCC can receive heartbeat information on port 514 for Syslog and port 80 for
HTTP.
CCC VMware Server Installation Guide

Screen – Configure CCC in Cyberoam

3. Access Virtual CCC Web Admin Console

Browse to https://<IP address of Virtual CCC> and log on using the default username (admin) and
password (admin).

Note: Internet Explorer 7+ or Mozilla Firefox 3.0+ is required to access the CCC Web Admin
Console.

4. Configure Virtual CCC to add and manage Cyberoam

Add Cyberoam appliance to CCC from Management Console → Appliance


Management → Appliance(s).

Screen – Add Appliance(s)


CCC VMware Server Installation Guide

• Specify Appliance Name to identify added Cyberoam appliance .


• Specify Appliance Key.
• Specify routable IP Address of the Cyberoam appliance.
• Specify Administrator Username and Password of the Cyberoam appliance.
• Select Access Protocol and Port to communicate with Cyberoam appliance. Make sure to
allow HTTP/HTTPS traffic on Cyberoam for Virtual CCC.
• Select CCC administrator user who can access and manage the appliance. Only the selected
administrator will be allowed.
• Specify additional details for the administrator user e.g. name, email id and contact address.

5. Access Help

For accessing online help, click the Help button or F1 key on any of the screens to access the
corresponding topic's help. Use the Contents and Index options to navigate through the entire
online help

Additional Resources

Visit following links for more information on Cyberoam Central Console

Technical Documentation – http://docs.cyberoam.com


Cyberoam Knowledge Base – http://kb.cyberoam.com
Cyberoam Security Center – http://csc.cyberoam.com
Cyberoam Upgrades – http://download.cyberoam.com

You might also like