0% found this document useful (0 votes)
38 views

Precast Fins

This document provides a cost study for adjusting precast fins at the balcony of Phase 2 Block 1 of the MANDANI BAY QUAY project in Mandaue City, Cebu. It compares the costs of Option 1, which retains the exterior wall, and Option 2, which removes the exterior wall. Option 1 has a total direct cost of PHP 59,567 while Option 2 has a significantly higher total direct cost of PHP 396,471 due to the additional work required to remove and replace the exterior wall. The cost study was prepared on March 11, 2021 for HTLAND, Inc., the owner of the project.

Uploaded by

Immortal Justice
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
38 views

Precast Fins

This document provides a cost study for adjusting precast fins at the balcony of Phase 2 Block 1 of the MANDANI BAY QUAY project in Mandaue City, Cebu. It compares the costs of Option 1, which retains the exterior wall, and Option 2, which removes the exterior wall. Option 1 has a total direct cost of PHP 59,567 while Option 2 has a significantly higher total direct cost of PHP 396,471 due to the additional work required to remove and replace the exterior wall. The cost study was prepared on March 11, 2021 for HTLAND, Inc., the owner of the project.

Uploaded by

Immortal Justice
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Project Name : MANDANI BAY QUAY - PHASE 2 BLOCK 1

Location : F.E. ZUELLIG AVE.,MANDAUE CITY, CEBU


Owner : HTLAND, INC.
Subject : Cost Study for Precast Fins Adjustment at Balcony 6 & 7
Date: : March 11, 2021

OPTION 1 OPTION 2
(exterior wall to be retained) (exterior wall to be removed)
UNIT RATE UNIT RATE
ITEM DESCRIPTION UNIT QUANTITY AMOUNT UNIT QUANTITY AMOUNT Assumptions / Remarks
TOTAL TOTAL

A. DIRECT WORKS lot 1.00 59,567.00 lot 1.00 (396,471.00)

1.00 CSA Works 59,566.95 (396,470.67)

Structural / Concrete
Balcony (Precast) m2 7.44 5,192.38 38,631.28 m2 15.58 5,192.38 80,884.25
Zocallo - - - m2 0.78 3,115.43 2,414.46
Waterproofing m2 7.44 673.33 5,009.61 m2 17.13 673.33 11,532.53

Architectural / Finishes
Floor Finish (FF-5o) m2 7.44 1,004.98 7,477.02 m2 15.58 1,004.98 15,655.02
Zocallo Paint - - - m2 1.55 401.99 623.09
Balcony Railings - - - lm 7.75 12,102.73 93,796.16
Moisture Resistant Gypsum (Ceiling) m2 7.44 854.23 6,355.47 m2 15.58 854.23 13,306.76
Ceiling Paint (to gypsum) m2 7.44 281.39 2,093.57 m2 15.58 281.39 4,383.40
Exterior Wall Paint m2 24.03 401.99 9,657.82

Removal of Exterior Wall at Balcony n/a m2 (201.81) 3,115.43 (628,724.16)

2.00 MPF Works - - n/a

3.00 Electrical Works - - n/a

B. CONTINGENCY, 5% lot 1.00 - lot 1.00 - n/a

TOTAL 59,567.00 (396,471.00)

You might also like