JX Nippon Oil & Gas Exploration Inspection Test Record (Itr) - B

This document is an inspection test record for low voltage cable E25-B. It lists 10 steps to inspect and test the cable including: 1) verifying required documentation, 2) inspecting joints and terminations, 3) checking grounding and supports, 4) performing insulation resistance tests, 5) testing phase identification, 6) reconnecting conductors, 7) refitting covers, 8) recording defects, 9) verifying clean interior, and 10) verifying clean exterior electrical equipment. Upon completion, the record must be signed by representatives from the design, inspection, and commissioning teams.

Uploaded by

Amy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
279 views2 pages

JX Nippon Oil & Gas Exploration Inspection Test Record (Itr) - B

This document is an inspection test record for low voltage cable E25-B. It lists 10 steps to inspect and test the cable including: 1) verifying required documentation, 2) inspecting joints and terminations, 3) checking grounding and supports, 4) performing insulation resistance tests, 5) testing phase identification, 6) reconnecting conductors, 7) refitting covers, 8) recording defects, 9) verifying clean interior, and 10) verifying clean exterior electrical equipment. Upon completion, the record must be signed by representatives from the design, inspection, and commissioning teams.

Uploaded by

Amy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

JX NIPPON OIL & GAS EXPLORATION

INSPECTION TEST RECORD (ITR) - B

LOW VOLTAGE CABLE E25-B


Project No
Project Title
Facilities
INFORMATION
Tag No. System/ Sub System No.
Cable Size Voltage Level
INSPECTION / TEST OK N/A P/L NO
1 Documents required for verification:
a) Cable datasheet
b) Approved FAT report
c) Completed and signed off construction check sheet with punch list
status.
2 Confirm proper installation of joints and terminations.
3 Confirm proper shield/armor grounding, cable support and termination
of conductors.
4 Insulation Resistance Test. Measure and record insulation resistance
(IR) of each conductor with all other conductors and shields grounded.
Refer PTS 63.10.08.11 for suitable test voltage and acceptable
insulation reading

Test Point Insulation Resistance Remarks


R-YBNE
Y-RBNE
B-RYNE

Discharge all conductors to ground for a minimum period of 1 minute.


5 Confirm the both ends of the each phase "R" conductor are correctly
marked by ringing out. Do the same for phase "Y" and phase "B".
6 Reconnect all conductors such that both ends of the phase "R"
conductor connect to the phase "R" termination points. Do the same
for phase "Y" and phase "B". Torque all bolts to recommended
manufacturer's standards. Record torque setting and mark the bolts.

End ‘A’ …………………. Nm


End ‘B’ …………………….. Nm
7 Ensure all termination box covers and guards are correctly refitted.
8 Record any defects/shortcomings in the system punch-list.
9 Verify no dust inside Enclosure /Cabinet / Panel and insulation
surfaces are clean.
10 Verify Instruments & its Accessories /Electrical equipment/Panel
externally clean.
JX NIPPON OIL & GAS EXPLORATION

INSPECTION TEST RECORD (ITR) - B

LOW VOLTAGE CABLE E25-B


COMMENT(S) AND ADDITIONAL INFORMATION

COMPLETED BY VERIFIED BY ACCEPTED BY


DESIGNATION DESB Representative NIPPON Inspector Commissioning
Engineer
COMPANY JX NIPPON JX NIPPON
NAME
SIGNATURE
DATE