Design of Bridges
Design of Bridges
Answer: a
Explanation: For medium and long spans prestressed concrete is ideally suited for
the super structure of bridges and the structural forms generally used for bridges
are listed as follows solid slabs(10-15m), voided or hollow slabs(15-25m), rigid
frame bridges(15-30m), Tee beams and slabs(20-40m), two cell box girders(30-
70m), multi cell box girders(40-80), balanced cantilever type bridges(20-30m),
continuous girders of variable depth(30-40), cable stayed bridges(100-500m).
Answer: a
Explanation: Prestressed concrete has more or less replaced reinforced concrete as
the most suitable material for bridge construction due to its inherent advantages of
high strength coupled with durability, energy absorption under dynamic loads,
ability to resist repetitive loads, freedom from cracks, easy mould ability to desired
shape, economy and ease of maintenance.
Answer: b
Explanation: The floor and girders of through type structures should be placed in
one continuous unless otherwise specified in which case a special sear anchorage
should be provided to ensure monolithic action between the girders and floor and
the case of tee beam slab floors, it is preferable to deposit concrete first up to the
top of the girder ribs followed by concreting of the slab in one continuous
operation and if the slab concrete is delayed, suitable shear keys should be formed
by roughening the top of the girder before depositing the centre in the slab.
Answer: a
Explanation: Prestressed concrete members should be compacted by mechanical
vibrations expect when certain types of extrusion machines are used which
consolidate the concrete by tamping and depending on the type of structural
members, internal, external or surface type vibrators are used and normally
vibrators having frequencies in the range of at least 3200-3600 cycles per minute
are used.
Answer: b
Explanation: Vibration should be well distributed so that the concrete reaches a
state of plastic mass with uniform density and vibrators should be used for
compaction only and not for moving concrete horizontally along the forms.
6. When vibrators are used for horizontal and vertical operation, the spacing should
____________
a) Overlap
b) Attached
c) Hardened
d) Made wet
View Answer
Answer: a
Explanation: When vibrators are used for horizontal and vertical operation, the
spacing of points of vibration should be such that their zones of influence overlap
and when concrete is deposited in layers such as that in column, the vibrator should
be inserted vertically.
Answer: a
Explanation: When concrete is deposited in layer it is allowed to sink due to its
own weight to the bottom of the layer and then slowly withdrawn and during
vibration of succeeding layers, the vibrator should preferably penetrate the surface
of the preceding layer by at least 150mm and good vibration should result in a
surface without honey combing, aggregate or mortar pockets or excessive air
bubbles.
Answer: c
Explanation: Rheodynamic concrete generally referred to as self compacting
concrete (SCC) is able to flow under its own weight and completely fill the
formwork, even in the presence of dense reinforcements without the need for any
vibration whilst maintaining homogeneity and resulting in concrete of high early
strength and durability.
Answer: b
Explanation: Degussa-MBT construction chemicals (INDIA) have developed
revolutionary type of admixtures using nano polymers which can be used to bring
together functional groups aimed at targeted performances in concrete and based
on nano science.
10. A system of polymers with longer side and shorter side chains is called
____________
a) Zero energy system
b) Elastic energy system
c) Bonded energy system
d) Force energy system
View Answer
Answer: a
Explanation: A system of polymers with longer side chains and shorter main
chains to facilitate high early strengths in concrete without steam curing and with
specific applications in precast reinforced and prestressed concrete units
manufacturing industry.
1.Minimum Free Board required in a bridge is
2.Free Board is the level difference between Formation Level and …………….
a)C.L. of water course to C.L. of track
b)C.L. of water course to C.L. of pier
4.In a single span bridge, the clear span is the distance between
c)Outer faces of Abutments d) Width of Abutment
a)Abutment b)Girder/Slab
c)Piers d) Wing and Return walls
a)earth on approaches
b) ballast
c)track on approaches d) none
a)major bridge b)minor bridge
c)unimportant bridge d) important bridge