Accelerated Highway Construction: Workshop Series Summary
Accelerated Highway Construction: Workshop Series Summary
Accelerated
Highway
Construction
Workshop Series Summary
Sponsored by
In cooperation with
The Transportation Research Board is a division of the National Research Council, which serves as an independent adviser to the federal
government on scientific and technical questions of national importance. The National Research Council, jointly administered by the National
Academy of Sciences, the National Academy of Engineering, and the Institute of Medicine, brings the resources of the entire scientific and
technical community to bear on national problems through its volunteer advisory committees.
The Transportation Research Board is distributing this Circular to make the information contained herein available for use by individual
practitioners in state and local transportation agencies, researchers in academic institutions, and other members of the transportation research
community. The information in this Circular was taken directly from the submissions of the authors. This document is not a report of the National
Research Council or of the National Academy of Sciences.
Preface
T his report, prepared under the sponsorship of the Transportation Research Board (TRB) Task
Force on Accelerating Innovation in the Highway Industry (A5T60), summarizes three
workshops held in Washington, D.C., Indianapolis, Indiana, and Pittsburgh, Pennsylvania, in
2000–2002. The objective of this workshop series was to provide a forum for the exchange of
new ideas and developments in the field of accelerated construction. All three workshops were
sponsored by the TRB Task Force A5T60. The workshops in Indianapolis and Pittsburgh were
presented in cooperation with FHWA and AASHTO.
TRB Special Report 249: Building Momentum for Change: Creating a Strategic Forum
for Innovation in Highway Infrastructure, published in 1996, recommended conducting strategic
forums for emerging innovation in highway infrastructure (1). The TRB Task Force A5T60—
working with AASHTO, FHWA, and industry—elected to conduct these accelerated
construction workshops because of the emerging importance of accelerated construction to both
the departments of transportation and the traveling public.
The author of this report is Ted Ferragut, TDC Partners, Ltd. The views expressed in the
papers contained in this publication are those of the author and do not necessarily reflect the
views of TRB and the other sponsors of the workshop series. Each organization will use the
information included and the experience gained as a continuum in its efforts to prepare research,
policy, and training in this area. This report has not been subjected to the formal TRB peer
review process.
i
Acknowledgments
T he technical program for the first workshop in Washington, D.C., was developed by the TRB
Task Force on Accelerating Innovation in the Highway Industry. Members of the task force
at the time included the following:
The technical program for the next two workshops in Indianapolis and Pittsburgh was
developed through the joint efforts of TRB Task Force A5T60, AASHTO’s Technology
Implementation Group, and FHWA. Gary Hoffman, Pennsylvania Department of Transportation,
Chair of AASHTO’s Technology Implementation Group, and King Gee, FHWA, are
acknowledged for their leadership in this joint effort.
In addition, many transportation professionals listed in Appendix A participated in the
three workshops. Their efforts made a valuable contribution to the workshop series.
ii
Contents
References.....................................................................................................................................59
APPENDIXES
A. List of Participants..................................................................................................................60
B. Guidelines on Organizing and Managing an Accelerated
Construction Technology Team Workshop..........................................................................66
C. Flowchart on ACTT Critical Elements.................................................................................70
D. Acronyms and Abbreviations ................................................................................................71
iii
Executive Summary
O n November 16–17, 2000, the Transportation Research Board’s (TRB) Task Force on
Accelerating Innovation in the Highway Industry (A5T60) conducted a workshop in
Washington, D.C., to explore the issues associated with accelerating construction. Fifty
executives and engineers from around the country shared comments and thoughts on the subject.
Various statistics show that accelerated construction needs will grow considerably over the next
decade, especially considering traffic growth of 50% to 60% with little to no capacity increases.
Presentations and discussion took place on the following subjects:
Within each category, the attendees discussed many subinitiatives that need to be
addressed, including research, implementation, experimentation, and deployment, for the country
to properly advance accelerated construction. Many participants were particularly concerned that
many of the solutions require a multidisciplinary, multitiered systems approach that in turn
requires strong leadership.
The second workshop, cosponsored by Task Force A5T60, AASHTO, and FHWA, was
held in Indianapolis, Indiana, on March 18–19, 2002. The Indiana Department of Transportation
(INDOT) was planning major rehabilitation and expansion of the 13-mi west leg of the
Interstate-465 (I-465) corridor around Indianapolis. The project was relatively complicated in
that it included airport expansion and connection, along with major interchange construction.
INDOT normally would commit to three to four design contracts and four to five construction
contracts, allotting 5 to 6 years for construction. However, INDOT wanted to determine whether
the corridor construction could be accelerated to minimize inconvenience to the public—
reducing the “orange barrel syndrome.” INDOT wanted to explore using the multidisciplinary
approach discussed at the first workshop.
The third workshop, also cosponsored by TRB Task Force A5T60, AASHTO, and
FHWA, was held in Pittsburgh, Pennsylvania, on April 10–12, 2002. The Pennsylvania
1
2 Transportation Research Circular E-C059: Accelerated Highway Construction Workshop Series Summary
OBJECTIVES
PLENARY SESSION
The workshop was held at TRB in November 2000. More than 50 national experts shared
experiences and offered suggestions as to how the innovation process might be expedited to
address the concept of accelerated construction.
Opening Remarks
In his opening remarks, Donald Lucas, former Chief Engineer of INDOT, stated that the results
of this workshop must focus on customers and their expectations. He defined customers as
both the traveling public and the businesses that depend on the facility for the movement of
goods and services and for access to and from the highway. He presented a series of open-
ended questions relevant to accelerated construction:
3
4 Transportation Research Circular E-C059: Accelerated Highway Construction Workshop Series Summary
Mr. Lucas also reported on the recently completed National Quality Initiative (NQI)
Survey (2), which clearly shows an emerging issue with construction and mobility demands.
Although statistics showed an increased level of satisfaction with the highway members of the
public use most often (from 40% to 65% from 1995 to 2000), they also showed an increased
trend in dissatisfaction (from 17% to 24% from 1995 to 2000). The survey shows that the
combination of congestion increase plus delays associated with construction and maintenance
projects are seen as combined negatives.
The survey also showed some significant dissatisfaction with work zone issues:
Mr. Lucas noted that dissatisfaction numbers of this magnitude would normally close
private-sector companies. Mr. Lucas also pointed out that from 1980 to 1999, the United States
experienced a 76% increase in vehicle miles traveled, whereas lane miles only increased by 1%
(3). The lane mileage figures more than likely will not increase dramatically because the survey
also showed that the public generally is not amenable to tax increases or the addition of roads in
their neighborhoods to provide this additional capacity. Congestion indices currently show that
extremely or severely congested roadway mileage more than doubled from 1982 to 1997.
Uncongested mileage on the system shrunk by nearly 50%.
Mr. Lucas also remarked that the 160,000 mi of the National Highway System (NHS) and
the 300,000 mi of the arterials are moving toward middle age. Although national funding under
the Transportation Equity Act for the 21st Century (TEA-21) increased by nearly 40% to address
these issues, this has led to many more work zones throughout the country. FHWA estimates that
on the NHS alone, during the peak summer roadwork season, nearly 13% of the system is under
construction, leading to approximately 3,000 work zones at any one time.
Work zone fatalities, unfortunately, are also on the increase—to more than 1,000
fatalities in 2000, on the basis of statistics gathered by the National Highway Traffic Safety
Administration’s Fatality Analysis Reporting System. This is approximately a 20% increase over
the last 6 years. Approximately 42,000 people are injured annually as a result of motor vehicle
crashes in work zones.
He pointed out that the public appears to support short-duration, high-intensity shutdowns
of projects to conduct long-lasting repairs. Nearly 67% of the public supports a 1-week closure
of a facility if the work is done in accordance with the promise to stay out. This may offer an
important window of opportunity into the future.
These statistics all look backward, Mr. Lucas noted. “What is not known is how
construction acceleration may have affected these numbers. Did acceleration reduce the overall
exposure rates? What impact did the movement of work to nighttime do to these rates? Or to
weekend work? And to the future—how do these trends translate to future program decision
making?”
Corridor Approach
During this session, speakers addressed the question of assembling work into discreet packages
by analyzing corridors and incorporating innovative project assembly to both minimize overall
construction impacts and to accelerate work completion. Increasingly, DOTs are considering a
corridor approach to work. This session focused on how corridor needs can be addressed in such
a way as to minimize the number of construction sites and the amount of construction time
required.
Mr. Pete Rahn, Secretary of Transportation for the New Mexico State Highway and
Transportation Department (NMSH&TD), presented his department’s policy for addressing
major corridor improvements, which deviates from its traditional technique of improving 5-mi
sections of roadway. NMSH&TD’s corridor improvement technique has four key components:
Secretary Rahn was particularly concerned that the highway budget was filled with
projects—the concept that “everybody got something” minimizes the NMSH&TD’s ability to
produce measurable results. “Nothing ever appeared to be accomplished,” Mr. Rahn stated. He
believes that if planned and executed properly, corridor management can better address a more
complete restoration strategy and can reduce the overall number of work zones that may be
required to complete the activities. The corridor approach has upgraded 1,300 mi of deficient
highway in the New Mexico system. During corridor construction, accidents have dropped 12%.
Secretary Rahn noted that one critical point in corridor analysis was goal setting. “You are half
6 Transportation Research Circular E-C059: Accelerated Highway Construction Workshop Series Summary
way there by simply stating what the goal is,” Rahn said, “Leave the creativity to the engineers
and contractors to do the rest.” In setting longer project limits with higher dollar volumes and
shorter construction schedules, he believes that many projects were successfully accelerated.
John Bourne, I-15 Reconstruction Project Director, Utah Department of Transportation
(UDOT), discussed the I-15 corridor project. This 17-mi, $1.6 billion, 4½-year corridor project,
with 144 bridges replacements, 3.4 million yd2 of pavements, and major interchange construction
was completed on time and basically in accordance with the budget. Although UDOT used
innovative design–build (DB) contracting, warranties, time incentives, and other mechanisms,
Bourne supported Rahn’s statement that goal setting and focus is extremely important. “This
corridor project was also driven by a goal—complete the work in time for the 2002 Winter
Olympics. Projects of this magnitude must have a ‘hook’ or there is little incentive,” stated Bourne.
Overall, the UDOT’s goals to reduce time, maintain quality, and control costs were all
met. What lessons were learned? Bourne believes in
As a contracting mechanism, the DB concept breaks from tradition and has been
successful. A lesson that must be emphasized, however, is that over time, the constant pressure
wears on individuals and on the team, destabilizing the effort through lower morale and more
difficult decision making. Future projects must address the human factor for both the DOT and
the contractor.
Gary Taylor, Chief Engineer, Michigan Department of Transportation (MDOT),
discussed a relatively new concept for corridor management called “mix of fixes.” This concept
determines the time pavement sections are due for (a) capital preventive maintenance,
(b) rehabilitation, and (c) reconstruction. Mix of fixes includes a road quality and forecasting
system integrated with a pavement management system (PMS). Strategies for the system are
based on the PMS as well as a road quality forecasting system. “By integrating these concepts,”
Mr. Taylor noted, “the DOT hopes to reduce the number of miles that will need reconstruction
and hence reduce the number of critical long-term lane closures.” Mix of fixes is a way to
smooth the distribution of dollars required for construction while at the same time reducing the
number of work zone closures required in a corridor or in a district.
Capital preventative maintenance must be used on roads with a remaining service life
minimum of 5 to 7 years. Chip seals, diamond grinding, and crack sealing are examples of
pavement preservation strategy with varying lives to meet a set of condition goals. These
techniques limit disruption to traffic. Rehabilitation strategies target 10 to 20 years and include
overlays, patching, rubblization, and overlays. Reconstruction aims for a design life of 20 years
or more.
The PMS uses remaining service life categories—I to VI—as a function of the number of
years of remaining life. “Our objective is to constantly try to move pavements ‘up’ in the scale,”
noted Mr. Taylor. Pavement strategy analysis uses annual budget and mix of fixes to predict
what the network condition will be in the future. For example, if all resources are spent on any
one of the three areas, the system does not fare well. The resources must be distributed among
the three. If a mix of the three is used, the same investment improves the overall network—
Washington, D.C., Workshop 7
reducing the number of poor pavements. The tool allows for “what if” games to determine the
effect of different funding levels, maintenance and rehabilitation strategies, and so forth
Although a mix of fixes is used to reduce poor pavements, to increase good pavements,
and to manage fair pavements, it also may have huge potential to minimize construction delays
and to provide a consistent level of work. The process has worked in Michigan—the poor
pavements are being reduced, although the excellent pavements have not increased significantly.
MDOT will improve the modeling in the future to account for the effect on work zone reduction.
Many highway projects in the planning stages are very complex and expensive and dramatically
affect the public. INDOT, for example, reports it currently has six extremely large projects that
will require large capital and tremendous creativity. Sometimes called megaprojects, these
projects take years to plan, address many options, and require the most experienced personnel.
From an initial timeline that may show 6 to 8 years to build a project, many DOTs are attempting
to identify creative ways to accelerate the construction and to minimize the effect on the public.
Although projects sometimes linger 10 to 14 years in project development, once the plans and
finances are ready, the pressure to “accelerate and deliver the project” becomes nearly
overwhelming. This session focused on high-visibility projects that were successfully completed
ahead of schedule and that received high marks from the public. The DOTs also used many
creative “stay out” techniques by improving quality elements of the design and construction.
Jim Slifer, Highway Director, Illinois Department of Transportation (IDOT), discussed
IDOT’s accelerated construction program that began more than 20 years ago with the Eden
Expressway in Chicago. This 14-mi-long reconstruction was completed in just 2 years. IDOT
elected to build a “slow” pavement with a high service life. The high-service, continuously
reinforced concrete pavement is still performing excellently after 20 years of extremely high
truck traffic. IDOT has completed the Eisenhower Expressway and the Dan Ryan Expressway as
well. The Kennedy Expressway was completed in 3 years (1992–1994) while accommodating
250,000 vehicles per day (vpd). INDOT also recently completed the Stevenson Expressway.
“Our next challenge,” stated Mr. Slifer, “is to do two ‘megaprojects’ at the same time. These will
include another portion of the Dan Ryan Expressway as well as the I-80, I-90, and I-94 merge
near the Indiana border. Both will be done in a 2-year window.” The IDOT position is that the
public will no longer tolerate 5-year construction zones. The trend for accelerated construction is
even reaching southern Illinois with the reconstruction of I-74.
To what did Mr. Slifer attribute IDOT’s success on these projects? “Without a doubt, it’s
planning and communication. Planning is more than just the details of the project. It is working
with the public, both those impacted by the construction and those using the facility.” IDOT has
used focus groups and user surveys extensively, public relations firms, mascots, and catch
phrases such as “Jack Hammer” and “Mission Impossible.” By providing the public with
information, IDOT and the press became allies. IDOT also is looking to intelligent transportation
system (ITS) solutions to keep the public informed during construction.
During construction, the key to success is a solid relationship between the contractor and
IDOT. Very little good will happen without communication and partnering. IDOT uses cost +
time (A + B) and lane rental extensively and rates these tools as very successful. In addition,
IDOT requires the contractor to do most of the QC on the project.
Technically, IDOT likes to build structural shoulders on the Interstate as temporary riding
8 Transportation Research Circular E-C059: Accelerated Highway Construction Workshop Series Summary
surfaces during reconstruction. This requires the shoulder to be raised during resurfacing
operations as well. High early strength concrete patches and prefabricated structural steel have
all played key roles in accelerated construction. IDOT is exploring alternative designs for
pavement selection. However, utility companies and utility relocation are still very difficult to
deal with on many projects. IDOT is also beginning to look at corridor improvements to dispel
the “always out there” perception.
Dale Swanburg, Vice President, Walsh Construction, discussed his firm’s experiences on
the Chicago projects. He listed important details that other DOTs should consider when looking
to accelerated construction improvements:
was to change the way it approved contractor submissions such as shop drawings and materials.
Overall, the project was completed ahead of time with nearly $7 million in bonuses added to $53
million of work effort.
John Deatrick, City of Cincinnati Transportation and Engineering Department, discussed
Cincinnati’s Fort Washington Way project. This urban project also demanded considerable
preconstruction public involvement. Nearly 200 public hearings and meetings were conducted.
Even though the project was well planned, many of the “smart” ideas surfaced after construction
started. “The key to our success,” stated Mr. Deatrick “was having a very open communication
system and a quick decision-making mechanism. I cannot minimize its importance.”
The purpose of the following discussion was to share experiences on how very high-intensity,
short-duration projects can be managed.
Randy Ashmore, Ashmore Brothers, discussed a world-class reconstruction of Runway
9R-27L at Hartsfield Atlanta International Airport. The 2-mi runway removal and replacement
project was completed in 33½ days with more than 1,000 workers typically on site. This project
had a $175,000-per-day disincentive but no incentive. Mr. Ashmore pointed out the critical
importance for expedited decision making with contracting authorities. A quick contractor
decision-making system can be minimized if the authorities do not have a similar system.
Although one of the most critical decisions was to save the original base (done through a value-
engineering proposal), much of the project related to human factors: obtaining skilled workers,
being safe, feeding the workers, and cooperating with others continuously and positively. The
work was conventional—it just took so much more of everything—from saws to trucks to
worker lunches.
Neil Hawks, TRB Special Programs Division Director, reported on the results of a “Get
In–Get Out–Stay Out” workshop in California in 1998. The focus of the workshop was on the
rehabilitation of I-710 between the Port of Long Beach and Los Angeles, which passes through
nine municipalities. Teams of 12 members each attacked the problem; each team had equal skill
sets. The participants were instructed to develop a solution that would meet the long service life
goal identified by the workshop steering committee. Two of the teams were charged with
producing asphalt solutions; the other two teams were charged with concrete solutions. The
creativity and energy in the groups were exceptional; many solutions were extremely creative.
There was some similarity in the techniques. All of the teams used ITS technologies and public
information campaigns. All of the teams used recycling techniques. The workshop effectively
pointed out the legitimate alternatives possible to build long-term pavements under accelerated
construction conditions. None of the pavement solutions was improbable or fanciful. The mix of
expertise on each team proved to be very synergistic. The teams also applied underused
technologies such as unbonded concrete overlays and stone matrix asphalt as base course. The
teams recommended the following follow-up activities:
During this session, three DOT safety specialists discussed emerging concepts in handling work
zone traffic from both flow-through and worker and public protection perspectives. They
discussed the trade-offs and what might be expected in the future for work zone management and
safety.
Tom Hicks, Traffic and Safety Engineer, Maryland DOT, discussed Maryland’s future,
which is basically striving for balance. Public and worker safety issues both need to be
considered. The Manual on Uniform Traffic Control Devices, Part 6, suggests that traffic flow be
as uninhibited as possible with safe roadsides (4). Before roadways or lanes are closed, the
Maryland DOT undertakes traffic demand and lane closure queuing analyses. During
construction, traffic flow is monitored. The Maryland DOT also requires backup plans for
incidents or unusual flow.
Mr. Hicks suggested that future project planning will undergo extensive analysis of stage
construction examining traffic flow. For example, a typical project safety plan will include
material delivery and movement into and onto the project site. The safety plan will be
coordinated with enforcement personnel to ensure that no organizational conflicts exist.
Techniques such as telecommuting, ride sharing, bus service, van pool, and 4-day workweeks
will be promoted. Operational techniques, such as reversible lanes, shoulders, and speed controls
at merges, will be considered. Maryland DOT is looking to ITS technologies for construction
control as well. The University of Maryland is developing guidelines to improve traffic
operations in work zones, especially to determine the economic balance between construction
cost and delay costs, with some advanced and innovative software.
Phil Ditzler, Work Zone Safety Team Leader, FHWA, discussed the growing number of
states using queue length policies, ramp closures, weekend closures, and otherwise intense
techniques to move traffic during construction. Individual policies vary, but most show the trend
toward more aggressive control of both construction windows and traffic flow. States also are
beginning to use public information campaigns to announce very critical, short-duration
shutdowns. Mr. Ditzler again noted that although traffic is increasing, capacity is not. Work zone
fatalities are increasing, as are accidents. It is clear that many more states will need to address
these techniques.
Dave McKee, Director of Technical Assistance, American Traffic Safety Services
Association, presented the industry’s response to FHWA’s vision of no delays or accidents in the
work zone. To do that, he believes the industry must use more ITS innovation. In an effort to
reduce delays and crashes in the work zone, one objective would be to provide road users with
“real time” information that allows better decision making by motorists regarding alternate
routes they can use to avoid work zones. The traditional ITS components for work zones have
been limited to queue detectors, portable changeable message signs (PCMS), and highway
advisory radio. However, the integration of these components into a much larger architecture is
the future. Having all these components “handshake” with the system will give transportation
agencies and motorists more information and better use of the infrastructure. Emerging portable
devices that can be used now include traffic management, traveler information, roadway weather
conditions, real-time photos, incident detection, highway advisory radio, portable traffic
cameras, and PCMSs all working within an established architecture.
Companies are now coming on line with services that provide advanced technology for
use in highway construction and maintenance work zones. The new technology is usually
combined with current off-the-shelf equipment to provide smart work zones. For example, one
company used its computerized highway information processing system to implement a fully
automated traffic management system for use during the major reconstruction of US-22 in
eastern Pennsylvania. During the preliminary design stage, the need to divert some of the traffic
from the work zone was identified; this eventually led to the installation of a real-time traffic
control and incident management (IM) system as part of the project. This step was considered
necessary to provide for the safety of the traveling public and to maintain efficient traffic flow.
These types of services are expected to become more common as the demand for them
increases.
Alternative Contracting
Ever since the 1991 European Scan Study of Asphalt Technology, FHWA and the DOTs have
experimented with many new contracting options. Although the low-bid process has been the
staple for many years, accelerated construction demands require a process that allows for more
contractor creativity, considers the transfer of risk from one organization to another, and better
compensates a high-performing contractor.
Professor Stuart Anderson, Texas Transportation Institute, discussed the effect new
techniques could have on future contract administration. Obviously, time incentives based on A
+ B and lane rental have had huge impacts. As pointed out in several research and experimental
projects (5), other techniques may prove to be just as valuable:
• A + B + quality,
12 Transportation Research Circular E-C059: Accelerated Highway Construction Workshop Series Summary
• A + B + warranty credit,
• A + B + incentive, disincentive,
• A + B + traffic control bonus,
• A + B + past performance,
• A + B + warranty with performance payments,
• Best-value selection,
• Lump sum bidding,
• Performance incentives,
• Flexible notice to proceed,
• No-excuse bonus,
• Multibid award,
• DB,
• Build–operate–transfer or build–operate–own,
• DB–finance–lease back, and
• Indefinite delivery–indefinite quantity contracting.
Although there is concern within the highway community about different elements of
alternative contracting, Professor Anderson suggested that the highway community research
nonhighway industries as well. Other industries may prove to have additional new ideas worth
exploring, several of which are included in this list.
“As strange as the terms sound today, so was A + B 10 years ago. There is merit in
exploring some of these concepts,” said Professor Anderson. “The future will demand even more
creative and innovative solutions. They may be in some of these concepts.”
Ken Leuderalbert, Manager, Quality Initiatives Office, Florida DOT (FDOT), reported on
Florida’s experience with innovative techniques. They include the conventional A + B and lane
rental, along with DB, liquidated savings, bid-averaging methods, and lump sum payments.
FDOT’s analyses of all these new techniques have shown an average time-savings of nearly
24%, with cost savings of 8.5% as well.
Tanya Mathews, Past Chair Design–Build Institute (DBI), discussed the growth and
maturation occurring in DB. DBI recommends a series of “dos” and “don’ts” developed because
of this experience. For more information, see www.dbia.org/pubs/pd_intro.pdf. Design for
accelerated construction is especially appropriate because the team can integrate constructability
into the design process very efficiently.1
The attendees then divided into smaller breakout groups to identify more detailed needs
to address accelerated construction.
No Single Solution
There is no single solution—no “silver bullet”—that will solve the problem. Accelerated
construction is a systems issue, which requires many disciplines and technologies.
Others need to be made aware of the importance of the problems and the possibilities for
solutions.
Good statistics to paint the appropriate picture for the public, legislators, and industry personnel
are in short supply.
Congestion and construction needs should be connected in the minds of both the public and
politicians. Congestion will only increase because capacity is relatively stable. Construction and
maintenance needs exacerbate the issue. Many large metropolitan areas are approaching a system
failure; there may be severe damage if we do not start accelerating the issue and the solutions.
All sectors and departments within a DOT overlap and have responsibilities in accelerated
construction; this must be emphasized. A full system approach is the only way to advance future
efforts.
Responsibilities
If the DOT engineers and the construction industry do not address accelerated construction,
politicians eventually will. Through solid public relations, the highway community needs to tell
politicians about the problem and to describe the possible solutions.
Both the contractors and the DOTs will experience labor shortages and the imminent retirements
of experienced, critical personnel. Many DOTs are currently working at an “overload” pace.
There is no easy solution, but the subject must be discussed and studied.
Legislation
The next highway bill should provide some focus to accelerated construction, possibly through a
major research initiative.
14 Transportation Research Circular E-C059: Accelerated Highway Construction Workshop Series Summary
Although many ideas have been generated, in practice, no ways exist to share the information
effectively. States need to improve the technology-sharing aspect of accelerated construction.
National Focus
Setting Goals
For the innovative ideas to bear fruit, agencies should consider setting maintenance of traffic
policy goals that would guide the overall construction program for the future. Whether it is a
fixed number of lanes during peak hour or a fixed level of service, such public and targeted goals
would help the construction community package innovations to meet these goals.
Many future projects will challenge the traditional size and value of today’s construction
contracts. Project limits will be as much set by traffic controls and public expectations as by the
ability of the small- to medium-sized construction firm to provide the services. In the future,
project-defining terms such as “5 mi and $50 million” will be inputs and not necessarily
controlling factors.
A survey of all states should be conducted to collect information on the current policy
concerning construction restrictions as they relate to lane closures, maintenance operations, and
so forth. It would be most effective if the information referenced 10 years ago, today, and
projections for the future.
The industry does not have high-quality work zone safety information. Better work zone safety
accident records should be collected.
The industry needs to better inform the public and politicians on the relationships among total
traffic volume, truck traffic volume, and the need for lane closures during construction. Data that
Washington, D.C., Workshop 15
appear in the recently completed NQI survey foreshadow serious problems ahead. It is clear that
by increasing the number and severity of construction work zones, motorists’ current
dissatisfaction with congestion will be fueled even further. The ability to maintain or fix the
system will continue to meet serious challenges. A better array of statistics and a better delivery
of this information to the public and politicians can begin to condition attitudes about these
future consequences.
Portable, affordable, and integrated ITSs that specifically address construction management are
now coming on line. An integrated construction–ITS task force could identify the current state of
the art, identify the gaps in the technology, develop national experimental and demonstration
projects, develop construction specifications and pricing structures, and organize workshops and
other technology transfer programs. This effort may be worthy of a separate, targeted structure
within the ITS program. At a minimum, the ITS industry should provide more instructional
information on how to use advanced traffic information systems to communicate construction
information to motorists—by radio, Internet, wireless—along with IM systems and services.
Education
There is a significant gap in translating work zone safety and work zone flow through to the
construction workforce. Safety specialists may be able to better translate this information to the
construction personnel. Additionally, driver education about work zones as they increase in
numbers and severity must be improved. This should start with driver education at the earliest
ages.
Corridor Improvements
The mix-of-fixes and corridor management approaches take a more systematic approach to
construction management. The mix-of-fixes approach suggests that a more structured selection
of construction and pavement restoration strategies can help smooth both budget and traffic
delays. Corridor management approaches to both reconstruction and maintenance may be able to
assess traffic impacts better than the conventional project-by-project approach. Mix-of-fixes and
corridor management need to be explored as both budget and traffic management tools. Corridor
management projects under way by NMSH&TD, Virginia DOT, and the Washington, D.C.,
District Transportation Department should be tracked closely to determine their effectiveness in
managing traffic. Both techniques may be invaluable in reducing the number of work zones
required in the future and may be excellent points to communicate to the public and to
politicians.
New, improved innovative contracting techniques need to be explored; better knowledge of how
the current mechanisms are working should be organized and assembled. DB, warranties, A + B,
and lane rental have gained credibility but will need to be further refined and improved. A more
comprehensive approach to selecting and matching innovative contracting techniques to specific
16 Transportation Research Circular E-C059: Accelerated Highway Construction Workshop Series Summary
situations is needed. The approach would consider DB, draw–build, bid–build, operate, maintain,
finance, warrant, and others and would suggest the best way these might be packaged for specific
projects or corridors. Draw–build and DB are key elements for accelerated construction in the
future. The current $50 million threshold may need to be lowered.
Performance-Related Specifications
Value Engineering
Quality Incentives
There is a subtle (some would say loud) message that accelerated construction is more important
than high quality. If there is a head to head on this issue, time appears to win over quality. With
this in mind, incentive-based quality measures need to be developed that can “compete” with the
time incentives already in place. A $25,000-per-day time incentive can dwarf a $2,500 per day
incentive for a mile of smooth pavement. In addition, ways should be found to “carry over”
credit to contractors who have done high-quality work on previous low-bid projects. This
concept needs to be explored more aggressively.
Corridor Contracts
Corridor contracts that combine construction and maintenance operations may lead to better
traffic management. Contract models need to be developed and evaluated. Inherent in these
models would be that contractors would receive incentives for keeping overall traffic impacts
below certain threshold limits. Contractors also would receive quality incentives.
Accelerated, high-visibility projects should be reconstructed using more robust designs than
those used for normal construction. Higher-order (and higher initial cost) designs that extend
service life are probably better investments when examined from life-cycle and user-cost
perspectives. In addition, if more construction time is required to build the higher-order designs,
it can be justified with the “staying out” message. The public may very well support this concept.
The premise needs to be addressed more analytically. However, more focused research on
Washington, D.C., Workshop 17
Prefabrication and modular lift-in construction needs to be better understood and evaluated.
Pockets of experience exist, but information has not been coordinated. This concept will grow
with better exposure and focus. Tools that predict performance with some assurance are needed.
High-visibility work generally requires the owner or contractor to make predictions as to
performance. The tools are coming on line but will require understanding and training.
Accelerated Construction QC
There is a pressing need for better inspection and QC tools and procedures for accelerated, short-
duration projects. The ability to prevent, detect, and immediately fix quality problems without
affecting time requirements is critical. Research is urgently needed for nondestructive,
lightweight testing tools in all material control areas. Finally, more tools that can predict and
correct potential durability problems need to be developed. The need to predict performance (or
distress) is inherent to risk analysis for warranties, PRS, and operating expense determinations.
Long-range items, such as structural steel or sign structures, could be procured in advance for
accelerated construction projects. Additionally, better tools are needed to inspect below
pavements before construction.
Utilities
Utility delays significantly affect accelerated construction operations. More innovative solutions
are required for both short- and long-term time-sensitive construction projects. A strategic
national study was suggested to investigate the following:
Of all of the suggestions, the most intriguing was the possibility of using incentive- or
disincentive-based contracting techniques, including lane rental, in utility agreements.
The safety and welfare of the workforce is important. Barriers should be required to protect the
workers. These barriers need to be part of the construction equation. Workers and managers are
under significant stress in these high-visibility, accelerated projects. The longer the project takes,
the more the initial enthusiasm wanes and the more disagreements become common. All this is
18 Transportation Research Circular E-C059: Accelerated Highway Construction Workshop Series Summary
despite the fact that DOTs and contractors tend to put their best people on these projects. Most
use only two work shifts although these projects may run 24 h a day and 7 days a week. Stress is
not limited to just the contractor or DOT workforces—it also affects a worker’s family relations.
This experience should be studied further with possible remedies identified and communicated to
the broader community.
Technology Transfer
A very aggressive program needs to be developed that collects and disseminates the many
creative accelerated construction techniques currently used by DOTs and contractors. The new
program should include formal outreach through workshops, newsletters, and websites. This
recommendation reiterates the fact that no singular innovation will solve the accelerated
construction problem. There were several specific suggestions that FHWA dedicate one resource
center directly for all national accelerated construction issues.
One critical need is workforce education that can address all of these issues. It is important that
any education program focus on a multidisciplinary approach that includes DOTs, contractors,
consultants, and the labor force. It should be approached nationally, should be industrywide, and
should have broad participation. Although it is common to say that designers need to have a
better understanding of construction, this becomes very apparent in accelerated construction. In
addition, more consideration should be given to finding ways to integrate constructability
reviews into the design phase without compromising a contractor’s abilities to bid on projects.
ENDNOTE
1. Since the workshop, the FHWA has published a final rule in the December 10, 2002, Federal
Register to implement regulations for DB contracting as mandated by Section 1307(c) of
TEA-21. The regulation allows, but does not require, the use of DB contracting procedures.
The final rule was effective on January 9, 2003.
CHAPTER 2
T wo pilot workshops were conducted subsequently not only to address the comments
included in the previous chapter but also to focus on specific projects or corridors DOTs are
considering for actual construction.
KEY BARRIER
The task force recognized there are many reasons why innovative strategies take an
exceptionally long time to implement. In the case of accelerated construction, although the
movement highlights certain innovative strategies and technologies, it requires strong leadership
and organizational momentum.
PURPOSE
The purpose of the pilot workshops was to identify corridors in the preproject development phase
that could benefit from a multidisciplinary review of potential acceleration strategies. The two
pilot workshops were established to bring together a national team of recognized experts in
various technical skill areas (coined the ACTT—Accelerated Construction Technology Team) to
meet with the skill areas counterparts in the host DOTs. Over the course of several days, the
ACTT and the host DOTs would share experiences and discuss innovative ways to accelerate the
construction within the corridor.
The workshops, as envisioned, would incorporate aspects of a constructability review that
would be performed before the establishment of project limits and at approximately the same
time environmental assessments (EAs) were under way. The ACTT workshops would include
plenary sessions, breakout sessions, skill set interaction, closing remarks, and follow-up action
plans.
SPONSORSHIP
FHWA and the AASHTO Technology Implementation Group (AASHTO–TIG) both agreed to
work with the task force in the two pilot workshops.
19
20 Transportation Research Circular E-C059: Accelerated Highway Construction Workshop Series Summary
SKILL SETS
The three organizations identified the general skill areas that might need to be included in a
specific workshop:
• Innovative financing,
• Innovative contracting,
• Work zone traffic management,
• Mobility,
• Utility management,
• Corridor improvements,
• Prefabricated and modular construction,
• Long-life pavements,
• Geotechnology,
• Maintenance,
• ROW,
• Accelerated construction QC,
• Construction ITSs,
• Training and education,
• Constructability expertise,
• Communications and outreach,
• Worker health and safety, and
• Long-life bridges.
This list helped to identify the potential skill sets that might be required in any corridor
study.
INDOT hosted the first workshop on March 18–19, 2002, in Indianapolis. PENNDOT
hosted the second workshop on April 10–12, 2002, in Pittsburgh. Both DOTs had special
corridors they proposed for consideration as the first pilots.
CHAPTER 3
PROJECT DETAILS
Corridor Description
INDOT identified an improvement of I-465 on the west side of Indianapolis from IN-67 to 56th
Street. This project included the addition of travel lanes and the major modification of
interchanges for the entire west leg. At the time of the workshop, construction was planned to
start as early as 2005 but needed to be completed by 2010. More than 150,000 vpd traveled this
12-mi stretch of Interstate. Major traffic generators who would be affected by this improvement
include Indianapolis International Airport, Indianapolis Motor Speedway, Indianapolis Raceway
Park, Ameriplex Industrial Park, and Eagle Creek City Park.
Corridor Goals
INDOT wanted the ACTT to help ensure that the traveling public would receive a quality
product in a timely and safe fashion. INDOT presented the following main goals for the next
phase of the I-465 reconstruction:
Several of the goals were clearly defined and measurable; others would require new
approaches.
Project Improvements
The current mainline pavement consists of 6 lanes—three northbound and three southbound—of
concrete with asphalt overlay. There are eight interchanges within the corridor—IN-67, I-70,
Airport Expressway, US 40–Washington Street, US 36–Rockville Road, 10th Street, I-74–
Crawfordsville Road, and 38th Street. There are six main line bridges and nine overpasses. The
annual average daily traffic ranges from 94,300 vpd to 152,700 vpd.
21
22 Transportation Research Circular E-C059: Accelerated Highway Construction Workshop Series Summary
When complete, I-465 capacity will be increased with the addition of one travel lane in
each direction. The eight interchanges within the project will be modified to increase their
efficiency. Auxiliary lanes will be added along the main-line pavement between interchanges to
increase the efficiency of weaving movements and adjacent through lanes. I-465 will then
effectively prevail as a 10-lane/12-lane facility, versus the existing 6-lane facility.
Project Status
INDOT’s consultant for the project was tasked to complete the phase of work that culminates
with what INDOT calls an engineer’s report. At the same time, the consultant will be completing
an EA that fulfills National Environmental Policy Act of 1969 requirements. The engineer’s
report provides the direction and scope of work for the planned development phase, which will
lead to construction. These work activities were scheduled for completion by September 2002.
At the time of the workshop, the planned development phase was also under way.
INDOT was surveying the project corridor. Ground monumentation was being completed so that
helicopters could take the photography for low-level aerial survey. The low-level aerial process
was being used to increase the accuracy of the aerial photography compared with more
traditional high-elevation aerial surveys. Preliminary information from the engineering
assessment was to be used to advance the plan development.
Because this construction project will not start until 2005, INDOT plans to add a thin
resurface to areas of main-line pavement that are showing distress and that could have major
deterioration before reconstruction. This work will be completed as needed.
In anticipation of corridor rebuild, INDOT plans to maximize communication with the
public through extensive media and public information campaigns. A contract has been let to
construct a 58,000 ft2 traffic management center (TMC) for the area that will collate traffic
management with police personnel and others involved with the freeway service patrol. INDOT
Indiana Department of Transportation ACTT Workshop 23
will have access to system detector data via a wireless communication system and will have the
ability to change the display on variable message signs (VMSs) to keep motorists informed
throughout construction.
Indiana has historically been a “pay-as-you-go” state. However, in the 1990s, Indiana
began bonding projects and has gradually moved toward more innovative financing methods.
Additionally, the DOT has not let a project of this magnitude before, although the future program
shows several additional corridors could approach this size and complexity. INDOT has had
limited experimental experience with contracting techniques other than the conventional design–
bid–build (DBB) or “low-bid” process.
After several planning meetings, INDOT identified the following skill sets for the workshop:
• Innovative financing,
• Innovative contracting,
• Work zone traffic management,
• Worker health and safety,
• Utilities,
• Long-life pavements,
• Prefabricated and modular construction,
• ROW,
• Traveler mobility (ITS and modal), and
• Constructability.
National experts were identified in each of these categories who could provide (a) insight
on what is occurring nationally and (b) innovative strategic approaches to the corridor analysis.
In total, the national team consisted of 23 specialists.
The workshop began with opening remarks from three senior executives: Bryan Nichol,
Commissioner, INDOT; Mike Ryan, Assistant Secretary, PENNDOT; and Pete Rahn, Secretary,
NMSH&TD.
After welcoming remarks, the commissioner urged participants to be as creative as possible and
to remain open to any new ways of doing business. INDOT was always looking for alternatives,
for a mix-of-fixes approach to these major projects. Although at the time of the workshop
INDOT could not commit to moving out with a project of this magnitude, it could commit to
being as creative as possible and to identifying the challenges as well as possible solutions. Mr.
Nichol promised fair and open discussion of any new ideas that come out of the workshop.
Mr. Ryan presented the background and history of the task force, the November 2000 workshop,
and the concept behind the pilot workshops. He emphasized the need for new solutions to
24 Transportation Research Circular E-C059: Accelerated Highway Construction Workshop Series Summary
today’s construction impact on the traveling public. He also stressed that in today’s climate, it is
very hard to explain to the public the time it takes to bring corridors on line. Workshops like this
one may help to clarify the complexity of at least one facet of the issue—the relationship
between construction and traffic management. Finally, he urged participants not to fixate on any
barrier to implementation but to focus on a multidisciplinary approach to creating new ideas and
synergy to overcome these barriers.
Secretary Rahn discussed the work performed by the NMSH&TD over the last several years.
NMSH&TD has developed detailed definitions of major corridors and has established needs,
budgets, and strategies to address full corridor needs. One major point raised by Secretary Rahn
was setting sound goals for the project. By establishing goals that are clear, bold, and
challenging, INDOT may just be at the halfway marker already. He also stated that there will
always be challenges from different segments of the industry because change is never easy and
always requires adjustments.
Workshop Process
The eight national and state skill set teams then retreated to individual meeting rooms to discuss
the key issues. After several hours, the skill set teams met with other skill set teams to discuss
overlapping issues. Each group developed an overall summary that was coordinated with the
other skill sets.
If one skill set was the driver for meeting the INDOT goals, it was the financing of the project.
INDOT had not yet programmed the funds for this corridor. The national team introduced an
approach early in the process:
• Align the financing options with the goals of the project, especially in the time frame
of 3 years;
• Match cash flow management tools to project needs; and
• Recognize the competing project priorities for existing resources.
INDOT examined seven potential financing tools, including various federal-aid fund
management techniques, advance construction, and matching options. Matching options could
include devices such as tapered match, toll credits, the use of state bond investments as credit for
match (FHWA’s Test and Evaluation Program TE-45 experimental program), or a soft match. It
also examined various cost-sharing strategies, tolling mechanisms, contractor financing,
leveraging techniques, credit assistance, and cost management and containment concepts. The
leveraging techniques included general obligation bonds, grant anticipation revenue vehicles
(GARVEEs), and highway lease revenue bonds. Credit assistance included the State
Indiana Department of Transportation ACTT Workshop 25
Infrastructure Bank, a Section 129 Loan, and the Transportation Infrastructure Finance and
Innovation Act of 1998 Credit Program.
After a thorough review of these options, members of the national team listed the
following ideas:
• Consider the GARVEE bond mechanism as the principal financing vehicle (Table 1);
• Maximize federal matching tools;
• Implement cost containment through procurement strategy, value engineering, and
early industry reviews;
• Set a project budget and manage to the budget; and
• Involve other stakeholders in funding.
Membership of the national team then listed supporting principles that would underpin
the financing plan:
• Control development costs—do not pass the point of diminishing returns, and do not
erode private innovation and efficiency;
• Accelerate the financial plan;
• Emphasize cost containment strategies and economies of scale; and
• Scope out a plan of finance.
To implement the plan, the national team listed the following items that INDOT should
consider:
The innovative contracting team set the course for the design and construction issues for a
project of this magnitude. The team discussed in depth the delivery of the design and the
construction, both as separate issues and as a package. INDOT has experimented with DB; it is
controversial within many segments of the construction and engineering professions.
Members of the national team listed the following three options, including suboptions:
The DB process for early design work not affecting main-line traffic would include
utilities, sound walls, lighting, bridge fabrication, and so forth. Where feasible, ITS
infrastructure—both along the main line and along key regional and local alternative
routes—and local street operational improvements also could be included as part of any early
design work to provide increased roadway capacity and to facilitate the management of local
and regional traffic diversions.
The apparent low-bid combinations allow for single or total bid acceptance on the
basis of the sum of low bids. Included in the package is a bid item for cash flow converted to
present worth. Whatever technique is finally adopted by INDOT, the concept could be
marketed to the contracting community to ensure that it is involved and knowledgeable. The
technique also can allow for materials to be procured (or at least planned for) early in the
process.
This team had significant discussions on a wide range of issues, including ITS, transportation
demand management (TDM), IM, local street diversions, operations and improvements, and
public awareness. In addition, traveler mobility and ITS issues interrelate with and can be
considered when assessing requirements for the following skill sets:
• Innovative contracting,
• Constructability,
• Modular and prefabricated bridge systems,
• ROW,
• Worker health and safety, and
• Utilities.
Members of the team suggested defining maintenance of traffic policies and key
requirements early in the process and identifying what is politically attainable. The DOT
could set key policies and develop an implementation approach. For example, keeping traffic
on I-465 dictates an aggressive IM program, whereas closing multiple main-line lanes
dictates the pursuit of aggressive TDM and local street operation improvement strategies.
Some team members also suggested completing a pre-main-line closure construction
contract(s) before initiating the main-line work. This would include completing route
improvements and operational fixes on the local system, including signal system
improvements within the I-465 corridor’s area of influence. They also suggested deploying
as much future ITS as possible on the main line and along identified regional and local
alternate routes to support incident and traffic management functions during the construction
period. It also could be effective to implement ramp metering in conjunction with
acceleration lanes during construction to balance traffic flows and to increase main-line
capacity. The use of an ITS contractor–systems integrator could help to minimize
deployment costs and to maximize the construction schedule. Team members also listed
28 Transportation Research Circular E-C059: Accelerated Highway Construction Workshop Series Summary
widening the median bridges and building structures that span the main line to maximize the
potential pavement width, the number of potential travel lanes, and the shoulder widths
during the construction period for the purpose of maintaining capacity and facilitating IM
response personnel in a timely and organized fashion.
Some members suggested a public awareness and TDM initiative that would include
establishing partnerships with a public relations firm and the INDOT public affairs office.
The DOT could identify customers, proactively reach out to them early and often, and speak
directly to all customers. It might be advantageous to establish a transportation management
association (TMA)1 to work with employers and commuters to identify alternative
commuting options. Some other issues listed included marketing a suite of TDM alternatives
such as telecommuting, transit, carpooling, park and ride, flextime, and financial incentives.
The marketing of the INDYGO transit system could be improved, and incentives for
telecommuting could be provided.
A key to construction mobility will be the deployment of a construction zone IM plan.
This plan could help integrate and expand the use of the INDOT Traffic Wise program. To
facilitate IM response and clearance in a timely and organized fashion, full shoulders could
be provided on the mainline. Where shoulders are not available to provide a safe haven for
disabled vehicles and motorists, emergency pull-off areas every ½ mi could be established.
Additional items listed include (a) developing IM staging areas so the emergency response
community can stage major response efforts without blocking additional travel lanes, (b)
using the INDOT Traffic Wise program instead of the contractor to provide the IM, (c) using
photogrammetry in lieu of total station units to quicken the clearance of major incidents, and
(d) providing tabletop training for the incident and construction management community.
Constructability Team
• Use a pre-main-line contract to complete all work items that do not affect traffic,
before initiating the traffic impacting work items.
• Conduct an intensive utility survey to minimize the risk by both parties. If
possible, the parties should consider hiring an outside entity (not the DOT or the design
contractor) to conduct and manage the utility work. If possible, develop ways that the
contractor can be involved in moving the utilities.
• Develop a collaboration process—contractor, utilities, ROW, designers
(emphasize traffic control), DOT construction engineers, and local agencies. This could help
minimize any misunderstandings and expedite the change approval process.
• Establish an innovation process that provides more incentives. This could
maximize the opportunity and acceptance of innovation, maximize access to work areas, and
maintain flexibility throughout the process. The DOT should consider designer incentives as
well. For example, it is possible to pay the designer in phases on the basis of quality of
design, including appropriate incentive fees. The NMSH&TD has documentation.
Indiana Department of Transportation ACTT Workshop 29
“Staying out” is a major factor for the overall success of the project. For high-intensity
projects such as this, it is feasible to look at pavement designs that push the 60-year
envelope. Many members of the team agreed that telling the contractor what the DOT wants,
not how to build the pavement, is critical to getting a sound final product.
The team discussed design life for the pavement and focused on a 60-year design life.
30 Transportation Research Circular E-C059: Accelerated Highway Construction Workshop Series Summary
• Ensure that the pavement performance goals and objectives for the project are
clearly identified and communicated to the designer and contractor, allowing the maximum
freedom to determine methodology.
• Provide the contractor with all pavement design inputs—traffic information,
environmental information, and available and preferable materials to the contractor.
• Consider one of the following four different pavement delivery techniques that
address the pavement type selection and design options; each technique transfers more
responsibility from INDOT to the designer and contractor:
− Option 1—Traditional (INDOT selects pavement and designer; contractor
builds);
− Option 2—Design, build (state selection);
− Option 3—Design, build, maintenance warranty (contractor option for design
with a 5-year maintenance warranty); and
− Option 4—Design, build, maintenance warranty (contractor option for design
with a 10-year maintenance warranty).
• On the basis of current design procedures, use the following as guides of what
pavement type might be ultimately designed:
− Sixty-year portland cement concrete (PCC)—18 in. plus 1 in. for diamond
grinding preventive maintenance;
− Sixty-year asphalt cement concrete—mill and fill (1 to 1½ in.) (preventive
maintenance); and
− Composite 60-year PCC with 4-in. stone mastic asphalt—mill and fill (1 to 1½
in.) (preventive maintenance).
• Use a typical pavement width of 88 ft, including a 12-ft outside shoulder and a 16-
ft inside shoulder.
• For the pavement below the frost line, incorporate underdrains in all designs, and
include positive surface drainage across the pavement.
• Regardless of the pavement type or design, the work could be performed within
the following parameters as they relate to pavement construction:
− Establish a traffic plan that allows no more than a 1½ in. drop-off for safety
during construction;
− Maintain traffic flow at 45 mph (or whatever standards are set for the project);
and
− Use cost plus time plus quality (A + B + Q). Quality incentives could be
revisited to ensure balance and equity with time.
• Use lane rental to quantify any maintenance activities that would be required
during the maintenance warranty period, should it be selected (see Option 4 above). This
could mean that if any repairs to the pavement are required, under a predetermined set of
conditions, INDOT would charge the contractor $60,000 per day per lane for lane rental (on
the basis of true user costs). However, if the repairs or maintenance could be done during
Indiana Department of Transportation ACTT Workshop 31
off-peak hours, the lane rental would drop to $3,000 per lane. These numbers would need to
be determined for specific projects’ values.
• Measure pavement performance by four parameters:
– International roughness index (IRI),
– Friction,
– Cracking (longitudinal and transverse), and
– Rutting and scaling.
These four factors can be woven into (a) pavement design, (b) pavement construction
acceptance, (c) pavement maintenance requirements, and (d) pavement turn back
requirements after the warranty period.
Members of this team discussed three concepts that could help to build the project more
efficiently and could reduce quality problems.
Standardization of the design includes (a) creating standard span lengths, beam types, beam
spacings, and so forth, for use throughout the project to the greatest extent possible; (b) using
a single designer for all bridges; and (c) using segmental or other prefabricated unit
construction for flyovers. However, the effect on aesthetics could be a concern. Also,
because of standardization of the span lengths, the structure may not fit the site—it may be
longer than necessary, which may result in additional material costs.
The concept of prefabrication is based on the idea of fabricating as many of the
structural components off site as possible. These components are then brought to the bridge
site and assembled. In modular construction, repetitive structural units are used to create the
completed structures. These modular units may be prefabricated or may be fabricated on site.
Prebuilding could help reduce the traffic interruption time. This method also could include
the prepurchase of materials as part of the effort. Prebuilding eliminates the need for
prefabrication or modular construction. This technique requires early and careful
coordination with utilities. There is also the question of the cost-effectiveness of this effort
because it requires mobilization costs for two separate contracts. All prebuild issues
interrelate with traveler mobility, ROW, contracting, and finance and must be included in the
front end of project development.
Large component assembly consists of building and lifting into place complete span units,
piers, caps, and so forth or erecting beams in groups with the slab placed later. This
technique can reduce the time for lane closures. The repetitive nature could improve
contractor productivity. The current disadvantage is that the direct project costs may
32 Transportation Research Circular E-C059: Accelerated Highway Construction Workshop Series Summary
increase. User costs must be considered to determine cost-effectiveness. The overall savings
and benefits of this technique are, in part, dependent on industry experience and volume of
work required.
Several states are aggressively evaluating precast deck panels. Texas DOT has a
significant amount of information on this topic. Precast technology has proven to be much
faster construction with less disruption to traffic on the roadway below. The only
disadvantage is that a number of states tried this technique many years ago, and it carries a
“we tried that before and it did not work” stigma with it.
In addition, an entire temporary bridge may be brought in for project needs and
removed after the operation is complete. Essentially, the contractor leases the bridge to the
DOT. It does not cause much interruption to the traveling public. However, additional ROW
may be required, and tight urban conditions may make this solution impractical.
Members of the team did not discuss a specific design life. However, they did discuss
making use of improved products and emerging technologies that could provide longer life
structures, such as high-performance concrete, self-compacting concrete, steel with improved
corrosion resistance, and other high-performance steels. There is a learning curve, and,
although there are high hopes for these emerging technologies, these technologies are not
proven as yet, and the costs are still uncertain.
Although not directly a bridge issue, members of the team noted that Texas DOT is
experimenting with precast–posttensioned concrete pavement slabs. It may be possible to tie
to specific bridges for short sections of pavements. Obviously, this technique is not currently
cost-competitive with traditional construction. It does not circumvent the weather and may
be better suited for rehabilitation strategies.
Timing and coordination of the structural work are also important. Members of the
team offered the following ideas for enhancing operational needs:
Members of the team also listed the following ways to integrate bridge operations
with ITS and mobility, utilities, and financing:
ROW Team
Historically, the ROW discipline is on the outside of the planning process and is called in
“when needed.” The workshop allowed the ROW discipline to interact with other skill sets
early and to provide them with a real estate perspective for this project. Under normal
situations, the following timeline would apply:
• INDOT would finalize the EA/finding of no significant impact (FONSI) for the
corridor in 2002.
• ROW would then begin preparing abstracts, descriptions, and appraisals, which
are estimated to take approximately 16 months. In reality, it is more likely to take 24 months
for the corridor and may take upward of 36 months.
• Offers would be made around the middle of 2004.
ROW team members believed that the following ideas, if implemented, could reduce
overall project delivery time by 1 year. The focus is on allowing ROW work to proceed
sooner with fewer revisions and rework. Title and abstract work would start before the
EA/FONSI is finalized. The first major time-saver is to set a generous ROW limit now. A
second major time-saver involves developing the utility easement needs at the same time.
34 Transportation Research Circular E-C059: Accelerated Highway Construction Workshop Series Summary
• Use an integrated project development approach with a project manager and set
the project schedule as soon as possible. This is necessary for both the ROW and utility
sections to do resource planning. They also may benefit from the formation of a team
concept—ROW, utilities, and the design team that will coordinate issues and needs as early
as possible.
• Set the ROW limits now using a generous approach and assuming an open
drainage system. Detailed design can continue within these “generous” ROW limits. That
way, the utility and ROW sections can coordinate and begin working on abstracts,
descriptions, appraisals, and acquisition even though a final design is not complete. This
could speed up ROW clearance by as much as a year. This is not to say that ROW will never
go back to an owner to increase the acquisition later. That is one of the risks with this
process.
• Coordinate with legal to get the necessary statutory authority to purchase
whatever land is needed in conjunction with a highway project. This includes land needed for
environmental mitigation and utility relocation. Although this legal authority may not be
available in time for use on this corridor, it is needed for timely delivery of future projects.
• Coordinate closely with utilities to determine whether the ROW section can assist
in acquiring the necessary utility easements. If the DOT or contractor can make the contact
for both ROW and utility needs, it means dealing with the property owner once. FDOT has
language available to use.
• Focus first on the parcels that will require more time for difficult relocations.
Work on these acquisitions can begin before final design is complete when the ROW limit is
set early. Parcels near the airport can be left for last to avoid conflicts with the scheduled
airport expansion.
Additional notes from members of the ROW team included the following:
• If 100% state funds are used to acquire some parcels, these funds can be used as a
credit toward the required project match.
• The DOT may be interested in developing a pilot project and may request FHWA
approval to use an acquisition incentive payment. These funds are above the offer and do not
count against the relocation payment. They are a bonus for signing before the parcel is filed
for condemnation. FDOT is using an FHWA-approved schedule on a pilot project in three
Florida districts.
• The DOT also could develop a pilot project and request FHWA approval to use a
relocation incentive payment. These funds are over and above the relocation payment offer
and are tied to specific time frames. The Virginia DOT also can provide an example.
• If INDOT decides to go with DB contracting, it could include ROW acquisition in
that contract.
• For the long term, work on getting legislation to approve “quick take.”
• Outsourcing condemnation could expedite work by the Indiana attorney general.
This would consist of letting a contract to have condemnation documents prepared for the
attorney general, making payments for the attorney general to hire outside counsel, and
making payments to help expand the court system to alleviate delays.
Indiana Department of Transportation ACTT Workshop 35
Members of the ROW team know there needs to be a mindset to not “minimize” ROW
acquisition around the country. INDOT stated as much for this project. History shows it was a
cost-containment idea that started in the Interstate era. Many members of the ROW team do not
believe that the ROW costs are that great compared with overall project costs or the cost of a
year of delay. In addition, residences are often left that should be acquired. The profession gets
caught up in an effort to acquire the perfect amount of land and sometimes loses sight of the need
to deliver the project to reduce congestion and to build a safer roadway now. Under normal
circumstances, the design team, with ROW input, could set a generous ROW limit early.
Changing how and when ROW limits are set could help ROW sections around the country. This
has the potential to speed up project delivery on all projects, not just special projects. Although
this concept appears simple, it is not. It requires major rethinking by every person involved in
developing a project, including those working on the EAs. When all is said and done, however,
there are times when the ROW needs must be examined carefully, particularly with regard to
very high-cost areas and sensitive areas that have environmental or historical significance. In
these cases, ROW acquisition will have to wait for final design.
Worker health and safety is a growing concern on all projects, especially those with major
accelerator clauses included.
The worker health and safety team members identified the following considerations:
• All safety issues should be addressed and integrated with the constructability reviews
discussed earlier.
• Safety should be fully integrated with the traffic management plan. Of particular
concern are night work illumination and pavement issues. To this end, there could be a site-
specific safety and health plan with singular responsibility of one person on the contractor staff.
• For the traveling public, safety should be linked to the public awareness program
mentioned in the traveler mobility sections.
• Although there are few specific highway data on the relationship of worker fatigue to
safety, the long arduous hours under accelerated construction conditions may dull the
effectiveness of workers, for both the contractor and the inspection forces. The contract
documents require forced and scheduled time off the project. This time off can be integrated with
speedway and raceway traffic generator events. In addition, worker access to the site can be
controlled through satellite parking and busing to the specific work area.
Utilities Team
The overall goal is to have minimum impact on the construction contract and on the traveling
public. The most common problems are as follows:
INDOT thoroughly evaluated all the ideas and has adopted many of them in its long-range
planning. Several of the key concepts that are still evolving are as follows:
• The DOT believes that the most critical item related to meeting the project schedule is
the ROW. INDOT has had significant concerns in accelerating ROW. Additionally, the work
start may slip until 2007 because of other needs around the state.
• The concept of requiring a performance-based traffic goal of 45 mph through the
work area is worth exploring, but the DOT has no (a) contract language, (b) quality measurement
tools, or (c) experience with managing such a concept. INDOT believes it is more practical to
require a minimum of three lanes in each direction. Currently during peak hour, the traffic does
not attain the 45 mph goal without construction under way.
• The DOT was impressed with the financial plan and believes the national team did a
fine job in defining the options. Because legislative approvals are required, it is not a simple
path.
• The DOT believes that multibid award would probably work better for this project.
Most of the design is fairly straightforward and can be accomplished before bidding of work,
even with a 2005 start date. The DB concept has been tried before and has not been welcomed by
the industry.
• The DOT also expected that perhaps four engineering contracts would be required to
handle the design work. The DOT plans to award all four, even though the national team
recommended one major contract with some control of subcontract design work. The lead
designer in essence would work as the coordinator, filling roles classically filled by DOT staff.
The DOT believes this may happen, but a number of issues need to be resolved.
Overall, INDOT was very pleased with the ideas provided by the national team. It
believes that the project could be built in 3 years, which is, after all, the major thrust of the
review. The ACTT concept is something INDOT may replicate on other projects.
Indiana Department of Transportation ACTT Workshop 37
ENDNOTE
1. In Delaware, this is a pseudo public–private agency funded by companies that sign up for
services from the TMA. These services include setting up ride share partners, educating
the public about alternative travel programs, and establishing congestion management
update centers within a business site and between various sites located within a similar
region. Additional services of the TMA include the HomeFree Guarantee Ride Home
program, the School Pool program, Wage Works Programs, tax incentive plans for
individuals and employers using alternative travel programs, and so forth. Its budget is
partially funded by the state’s transit organizations, that is, Dart First State also pays for
maintaining the TMA program in Delaware.
CHAPTER 4
PROJECT DETAILS
PENNDOT was contemplating an improvement of PA-28 from Chestnut Street in the city of
Pittsburgh to the Millvale interchange in Millvale Borough. PA-28 is a limited-access principal
arterial serving as a major interregional transportation facility connecting the communities in
Armstrong, Butler, Clarion, and Jefferson Counties with I-76 (Pennsylvania Turnpike), I-279, I-
579, the city of Pittsburgh, and Pittsburgh International Airport. PA-28 is a limited access facility
for its entire length except for the subject section to be improved, which is an approximate 2.8-km
(1.8-mi) segment from 500 m (1,659 ft) west of I-579 near Chestnut Street to the Millvale
Interchange. Proposed improvements include elevating and bifurcating PA-28 to accommodate
widening to four 12-ft lanes with shoulders and median barrier, providing grade-separated
interchanges at the 31st and 40th Street Bridges, and realigning Rialto Street to a “plus”
intersection with the 31st Street Bridge. On average, more than 60,000 vpd travel this section of
PA-28.
Allowing for a construction start in 2007, the following deadlines would have to be met:
38
Pennsylvania Department of Transportation ACTT Workshop 39
PA-28 Budget
Amount Year
Phase (000) Programmed
Design $4,120 2003
ROW $1,500 2003
ROW $15,500 2004
Utilities $200 2005
Utilities $1,400 2006
Construction $140,000 2007–2010
PENNDOT Goals
In an attempt to accelerate the corridor and to alleviate the congestion in the area, PENNDOT
wanted to explore with the national team the possibility of meeting the following corridor goals:
The project-needs statement identified several factors that require improvements to this
segment of PA-28, including capacity, safety, system linkage and continuity, design issues, and
compliance with comprehensive transportation planning. The improvements to PA-28 will save
approximately $11 million per year in users’ delay cost.
The project segment of PA-28 is a four-lane, undivided, free access highway with at-
grade intersections and drive accesses. Traffic analyses show the average daily traffic ranges
from 56,000 vpd at the southern end of the project to 70,000 vpd at the northern end. The truck
percentage ranges from 7% to 9%. This section includes four signalized intersections, narrow
lanes, and a tightly confined corridor. The roadway is supported by a retaining wall adjacent to
active railroad tracks along the northbound lanes as well as development, including numerous
historic resources, residences and businesses, and a church adjacent to the southbound lanes.
The project is currently in Step 6, preliminary engineering, of PENNDOT’s 10-step
project development process. PENNDOT has a consultant under contract to complete
preliminary engineering studies. A predraft EIS was prepared on the basis of the most current
information, and the draft EIS is being submitted for review in March 2002. An ROD is
anticipated for June 2003. A consulting firm will be retained to complete final design of the
project following the ROD.
Shortened time frames for completion of engineering and environmental studies, ROW
acquisition, utility clearance, permits, and final plan development are the rule when accelerating
construction projects. Project management and scheduling will be critical elements in achieving
the scheduled letting dates for the project.
As stated earlier, PA-28 carries a high volume of traffic. Traffic typically has a
southbound peak during the morning peak hour and a northbound peak during the afternoon peak
hour. The corridor also experiences increased traffic volumes as the public commutes to and
from professional hockey, football, and baseball events; the Three Rivers Regatta; the Three
Rivers Arts Festival; and other sports and cultural events in the Pittsburgh area. Few alternative
routes can be used to reach the destinations for the travelers along this corridor. The alternate
routes all involve two-lane facilities in residential or commercial areas, and most are congested
already. Maintaining traffic flow along PA-28 during construction will be necessary to minimize
traffic impacts during construction. Alternative means of reducing or improving traffic flow
during construction are needed.
As for ROW issues, the project will affect more than 200 properties and include
relocation of some residences and businesses. A park, a cemetery, an industrial park, and
historically eligible properties, including St. Nicholas Church, will be affected as well. The
church is currently eligible for inclusion in the National Register. Alternatives would either
relocate the church or perform recordation and demolition of the church. Acquisition of
approximately 239 properties will be required for this project. Most of the parcels will be total
takes, not requiring the relocation of a business or residence. PENNDOT is proceeding with
appraisals and making offers to properties that qualify for hardship acquisition. Nine hardship
properties have been acquired. PENNDOT also is planning to begin ROW incidentals (e.g.,
appraisals) in October 2002 before the ROD in an effort to expedite ROW acquisition.
The project scope requires the improvement of a 2-mi section of East Ohio Street
between Millvale and the H. J. Heinz Plant in Pittsburgh. The project scope includes the
preliminary design of two new interchanges at the ends of the 31st Street and 40th Street
Bridges, which cross the Allegheny River, and new limited-access northbound and southbound
lanes. The narrow corridor is between the Norfolk Southern Railroad property and a steep
hillside, including rock cliffs, that supports the Troy Hill neighborhood of Pittsburgh. Additional
constraints include two churches designated as historical landmarks, old service station sites, a
cemetery, and an industrial park. The PENNDOT consultant expects the project to involve 5
bridges with 21 substructures, 18 retaining walls totaling 5 mi in length, 8 rockfall fences, and 3
landslide-prone slopes. Construction phasing and temporary support required to maintain traffic
lanes during construction require detailed evaluation. The wall design, which is complex because
of the weak bedrock of the Pittsburgh redbeds, will be additionally complicated by the
construction sequencing. Because of the urban setting, the subsurface investigation will be
complicated by traffic, environmental hazards, utilities, railroad property, and ROW. A critical
consideration of the project is the relocation of existing utilities. Utilities located within the
project corridor include an existing 60-in. waterline with numerous supply lines; extensive
sanitary sewers, including an interceptor line; natural gas supply lines, including a 20-in.
transmission line; and electric and telecommunication lines. The existing sanitary sewers are a
combination sanitary–storm water system that will have to be separated. The existing
combination system could be maintained to carry the existing sewerage, and the new highway
storm water system will require new outlets running under the railroad and trail to the Allegheny
River.
A Norfolk Southern Corporation railway line is immediately adjacent to the project
between the highway and the Allegheny River. Close railroad coordination will be required of
the project for construction access and for new storm water or sanitary sewer lines that will have
to run under the railroad.
Contractors will have significant challenges with the construction of this project.
Contractors will be pressed to deliver a quality product in confined quarters, including working
on steep and unstable slopes, while maintaining traffic flow. Completion dates and maintenance
of traffic will be very visible to the traveling public. Pittsburgh does not have a local roadway
network serving the Allegheny Valley that provides good north–south parallel access adjacent to
42 Transportation Research Circular E-C059: Accelerated Highway Construction Workshop Series Summary
the project. The local roads are one lane in each direction and have parking on one or both sides
of the road with many intersections and driveway access. Motorists seeking alternate routes
around the construction will affect the local network. One of the project challenges is to
implement methods to reduce the amount of traffic diverted to local streets.
ITS technologies are in place for much of the Interstate system in the Pittsburgh area.
This system is controlled from the TMC adjacent to the PENNDOT District 11–0 office in
Bridgeville. ITS applications could be considered for maintaining traffic during construction or
for possible inclusion in the project.
Local coordination will be extremely important. The metropolitan planning organization
for this project is the Southwestern Pennsylvania Commission (SPC). SPC will be involved in
the planning, funding, and scheduling of the project. Coordination with the city of Pittsburgh and
the borough of Millvale will be ongoing throughout the life of the project.
I-279 southbound is an important highway for PA-28 traffic to downtown and to
Pittsburgh International Airport. Currently there is no direct connection from PA-28 southbound
to I-279. PENNDOT is studying the feasibility of constructing this missing link between these
two important corridors.
In planning sessions before the workshop, the DOT selected the following skill set areas for the
ACTT workshop:
• Geotechnology,
• Innovative contracting,
• Utilities,
• Constructability,
• Prefabricated and modular construction,
• Long-life pavements,
• Traveler mobility (ITS and modal) and work zone traffic management,
• ROW, and
• Worker health and safety.
The workshop began with opening remarks from four senior executives: Mike Ryan, Assistant
Secretary, PENNDOT; Gary Hoffman, Chief Engineer, PENNDOT, and Chair of AASHTO’s
Technology Implementation Group; Ray Hack, District Engineer, PENNDOT; Don Lucas, Task
Force on Accelerating Innovation in the Highway Industry, Chair, and former Chief Engineer,
INDOT.
Mr. Ryan welcomed the participants to the workshop. He noted that this effort, with so many
experts from both inside and outside of Pennsylvania, is unprecedented in its scope. This corridor
is probably one of the most difficult and at the same time one of the most challenging in the
entire state. He urged all participants to be as creative as possible and stated that PENNDOT was
very serious in looking for ways to bring corridors such as this one to full service in less time.
Pennsylvania Department of Transportation ACTT Workshop 43
Mr. Hoffman also welcomed the experts to the workshop. He expressed his belief that many new
ideas would be generated in this effort and that PENNDOT was ready to follow up on them. He
also told the audience that accelerated construction was one of the three topics chosen for
national technology transfer to all the states. The two pilot workshops—here and in Indiana—
would be the foundation for promotion around the country.
Mr. Hack presented the background on this particular project and its long history. He stated that
he is hoping to generate as many new and innovative ideas that the participants can present. Mr.
Hack stated that all suggestions would be pursued and fully evaluated.
Mr. Lucas presented the background and history of the A5T60 Task Force, the November 2000
workshop, and the concept behind the pilot workshops. He emphasized the need for new
solutions to today’s construction effect on the traveling public. He also stressed that in today’s
climate, it is very hard to explain to the public the time it takes to bring corridors on line.
Workshops like this one may help to clarify the complexity of at least one facet of the issue—the
relationship between construction and traffic management. Finally, he urged the participants not
to fixate on any barrier to implementation but to focus on a multidisciplinary approach to
creating new ideas and generating the synergy to overcome these barriers.
Workshop Process
The nine national and state skill set teams then retreated to individual meeting rooms to discuss
the key issues. After several hours, the skill set teams then met with other skill set teams to
discuss overlapping issues.
Geotechnical Team
The geotechnical team addressed several of the most difficult technical issues associated with
this project. It identified six major issues that need to be addressed, several of which affect the
other skill set decisions:
The development of the construction sequencing, with all other work predicated on the
wall construction, is key to the project. Members of the geotechnical team identified the
following sequence of operations:
• Consider using soil nail walls to replace a conventional wall in cut sections. Soil nail
walls could save time, are more economical, have a built-in redundancy, allow for smaller
equipment to be used in the constrained corridor, and do not require excessively deep
foundations. PENNDOT has no experience with soil nails in the district and could conduct some
experimental work before the PA-28 work.
• Consider using mechanically stabilized earth (MSE) walls. MSE walls are
economical and can save time. However, PENNDOT has experienced some high costs on
previous projects—this may be a barrier to using them. PENNDOT may need to conduct a
thorough examination of the specifications to try to isolate the high costs. MSE design may be
modified by reducing reinforcement lengths, which minimizes excavation requirements and
costs. Modified MSE will require project-specific testing. This is not common practice in
PENNDOT, and it will require some advance experimentation to show benefit to PA-28.
• Consider using MSE walls and reinforced soil slopes as temporary structures
necessary for maintenance of public traffic and for construction access. The industry-accepted
practice is to have the contractor design the temporary structure.
• Consider wasting the excavated material because it does not appear suitable for fill
material. Its removal may affect the schedule and the public traffic.
• Consider using flowable fill as a means to backfill trenches at an accelerated pace
without loss of lateral support. It may be worth the extra cost.
• Investigate the use of high-capacity driven piles. They may reduce the risk of
removing contaminated soil, are economical, and are easy to inspect. They also pose less risk to
potential aquifer contamination.
• Explore the use of lightweight fill that can reduce foundation settlement, provide a
quality subgrade, and support accelerated construction. It is important that high-quality material
be specified for use as subgrade material to ensure pavement longevity; special placement and
compaction will be critical to quality. Price needs to be considered because lightweight fill has
been quite expensive historically.
• Consider using performance-based specifications for the geotechnical work. These
allow for greater contractor flexibility; however, they require a higher level of coordination with
other project activities.
• Consider using DB contracting for faster construction start-up, early involvement by
the contractor in proposal development, performance requirements, and QA/QC review. In
addition, explore warranty and performance requirements of the wall system after completion of
Pennsylvania Department of Transportation ACTT Workshop 45
The innovative contracting team examined several design and construction issues for a project of
this magnitude. The team discussed the delivery of the design and the construction, both as
separate issues and as a package. It should be noted that PENNDOT has experimented with DB;
it is still controversial within many segments of the construction and engineering professions.
The team examined four options:
• DB,
• A + B + other factors,
• Construction management at risk, and
• Traditional multiple construction contracts.
In the DB option, PENNDOT would be responsible for overseeing quality, assigning fair
risk to either party, and setting the overall standards. The contractor would provide the creativity
needed for a project of this complexity. The scope of the work would include ROW, utilities, and
site investigation. It was suggested that the award use best-value criteria and that only one
contract be let for this corridor.
The team identified a series of potential advantages to the corridor if DB is elected:
Potential advantages will not come easily because there are many cultural hurdles to
overcome. The limitation of competition (or apparent limitation) may need to be addressed with
the contracting community. PENNDOT may need to clearly evaluate the risk assignment to
better determine costs. The determination of performance criteria will be an important factor in
this risk determination. Finally, PENNDOT still has legislative issues that need to be addressed
because it cannot use a short list for DB contracts.
The A + B + other factors options is well understood by all parties, is proven, and would
result in less complex bidding and award procedures, as well as less complex specification
language. This option still allows for warranties to be added and is a good vehicle for adding
incentives for quality, safety, and traffic management. For this corridor, however, it may lead to
a longer project delivery time (design followed sequentially by construction). It also may require
46 Transportation Research Circular E-C059: Accelerated Highway Construction Workshop Series Summary
multiple contracts and more management and project testing by PENNDOT staff. This option is
not nearly as good a vehicle for constructability and innovation input from the contractor. It also
requires PENNDOT to coordinate traffic impacts with one or more contractors. For this option to
work, PENNDOT needs to have the ROW clear, to take full responsibility for the utility
adjustments, and to have a completed geotechnical investigation prepared.
Many team members believed that the DB option is better suited to this project.
Construction could be completed within 2 years, quality could be managed better,
comprehensive public information and involvement could be managed more efficiently, and the
design and construction decisions could be much better integrated.
Even before beginning construction, this corridor already has a constrained traffic flow; there is
very little area to work between the river and the embankment. In addition, there are few
alternative routes.
Many members of the travel and mobility ITS team suggested that a thorough analysis
and evaluation of existing traffic patterns before construction would be invaluable to better
predict movements and requirements during construction. This could be accomplished through
an origin–destination study, quick zone traffic simulation, and use of NETSIM/CORSIM to
evaluate queue lengths.
Although the first impression is that four through lanes should be required during
construction, members of the team suggested that PENNDOT consider three lanes. Three lanes
would allow PENNDOT to
• Incorporate 12-ft lane widths to increase driver comfort and maintain 35 mph design
speed, subject to a detailed evaluation so they can be effective as reversible lanes with overhead
lane control;
• Incorporate raised/reflective pavement makings; and
• Incorporate a positive separation (barrier) on the west side between travel lanes and
the work/staging area to maintain safety, thereby protecting both travelers and workers and
providing construction access while improving traffic flow.
Eliminating bottlenecks is critical to traffic flow. This includes the 31st Street Bridge.
Traffic flow could be maintained by closing the 31st Street Bridge and Rialto Street to PA-28
and eliminating an existing signal during construction. Access to the island could be maintained
through River Road and the 31st Street Bridge (from city side). Additionally, on the 40th Street
Bridge, PENNDOT should consider eliminating the signal at the intersection, making the
northbound a right turn on bridge continuously, a left turn off bridge prohibitive, and a right turn
only off bridge.
ITS technology includes many possibilities that can be included on this project. They
include a project-based TMC, a project website, a highway advisory radio, wizard CB radio,
vehicle detection for speed and presence, queue detection, camera surveillance, a 511
demonstration project, an IM system, technology-assisted police enforcement, kiosks and video
monitors, and changeable or variable message signs. All of these concepts should be explored
further.
For a project-based TMC, PENNDOT could use wireless technology to communicate
Pennsylvania Department of Transportation ACTT Workshop 47
with the permanent TMC based in Bridgeville via a link to existing PENNDOT fiber optic. The
wireless technology eliminates the barrier of the lack of a permanent infrastructure for this
corridor. A permanent ITS infrastructure could be installed as the project progresses. It could be
placed in the utility corridor. The advantage to this strategy is linkage between the corridor-
specific traffic management and the regional TMC. The technology could include a project-
based TMC, a project website, highway advisory radio, camera surveillance, kiosks and video
monitors, and VMSs.
For an IM system, it is possible to use wireless technology and solar power to provide
camera surveillance of traffic flow during construction. The team also suggested that tow trucks
and service patrols be dedicated to the project. Finally, surveillance cameras could be linked to
the project website, thereby providing real-time information to the traveling public.
For the public involvement and education campaign, the following options were
suggested:
• Conduct an intensive public involvement campaign, similar to that undertaken for the
Ft. Pitt Bridge closure;
• Communicate the changes in traffic patterns before construction (bridge closures,
movement restrictions, and so forth);
• Use kiosks and media;
• Use ITS equipment to communicate changes in real time through the construction zone;
• Promote travel demand management (e.g., car pooling, telecommuting, ride sharing,
flexible work hours);
• Investigate Park and Ride—possibly undertake a joint venture with the Port Authority
of Allegheny County (innovative contracting) and the Heinz plant and its employees; and
• Inform the public through an extensive involvement and education campaign,
including pre-trip information, real-time information, and the promotion of travel demand
management such as carpooling, telecommuting, ride sharing, and park and ride.1
Utilities will have a major effect on traffic management. The travel and mobility team
listed an advanced utility relocation contract as an option. If technically feasible, the team
suggested relocating utilities to a dedicated corridor. It also suggested the geotechnical option of
constructing as much of the southbound roadway and retaining walls as possible in the first
construction season. This step could be a triple boon to the project—improved geotechnical
quality, higher construction speed, and less impact on traffic.
Although much time is spent on the traffic services required, the “who provides traffic
services” issue is equally important to the eventual success of the project. The travel and
mobility team listed the following options:
The team also suggested that a DB option be considered and explored in more detail. This
option would allow for the development of project-specific selection criteria. The selection
criteria could be related to the DB team’s projected time of completion, its traffic management
plan and demonstrated history of traffic management, and its demonstrated history of successful
public relations campaigns and incident response plans. From this information, PENNDOT could
develop performance and selection requirements that could be turned into incentives for traffic
management during construction. For this to be effective, the DB team would need to evaluate
the existing traffic patterns suggested previously. It also would need to determine current and
potential travel times through the corridor and make allowances for closing signals at the 31st
and 40th Street Bridges.
Constructability Team
One of the biggest challenges to the constructability of the project is getting equipment in and
out of the site while minimizing the impact on the traveling public.
The constructability team offered the following suggestions:
property, the Millvale Industrial Park, the Heinz property, or even barges. Additionally, it is
important to identify waste and reuse options. To maximize waste excavation and to minimize
haul costs and traffic disruption, reuse of excavated embankment material should receive a top
priority for this project. Part of the design effort should include the evaluation innovative
removal techniques. Limited blasting or mechanical removal methods are suitable for this
project. Also, particularly for the wall excavation, a conveyor system could be used to transport
material across the roadway to temporary storage areas or hauling operations adjacent to the
river.
• The walls are critical to both construction and long-term success of the project. The
designer should (a) consider long-term service of the retaining walls as part of the project design,
(b) create an aesthetically pleasing wall, and (c) support top-down wall construction.
• Consider use of nighttime construction to expedite the schedule and to enhance
material handling operations. Night operations may need to be included in negotiations with the
local authorities. If there will be restrictions on the type of operations allowed, they need to be
clearly included in the plans and incorporated into the overall project schedule.
• Given the complexity and accelerated delivery schedule, use DB. The traditional
process using a single contract for design and a single contract for construction of the project
would probably not meet the desired schedule. Incentive and disincentive strategies could be
used. Finally, A + B bidding would be an appropriate choice for this project.
The constructability team recognized the importance of the geotechnology to the success
of the project. Team members suggested that the geotechnical team identify possible issues with
slope stability, noise, air and water quality, traffic disruption, protection of adjacent structures,
erosion, and sediment control.
Many members of the long-life pavement team believed that a 60-year design life was feasible
for this project and that major intrusion on this corridor in later years would have a dramatic
impact on the movement of traffic. Many also noted that either an asphalt or concrete option
could meet the design life requirements. Overall, members of the team believed that the utility
issue and the future need to gain access to service them through the pavement must be evaluated
as the prime impediments to ensuring a long-term pavement.
If PENNDOT elects an asphalt pavement option, the members suggested
• Plain-jointed PCC,
• 15-ft joint spacing,
• Noncorrosive dowels,
50 Transportation Research Circular E-C059: Accelerated Highway Construction Workshop Series Summary
Many members of the long-life pavement team also suggested that PENNDOT build a
composite pavement option that integrates the best of the asphalt and concrete options. The top
course could consist of a curable, rut-resistant asphalt surface, with saw and seal asphalt concrete
joints to provide a smooth and quiet ride. The PCC could be the same as the PCC option
previously mentioned.
Regardless of the type of pavement section, many members of the team suggested
inclusion of the following construction requirements:
• Specify a strong select borrow material for the top 12 in. of subgrade,
• Apply a prime coat sealer on the subgrade, and
• Place the drainage system at the edge of the cut slope.
The bridge team recognized that the area available for construction and staging is constrained. It
also recognized that PENNDOT and the contracting industry are largely unfamiliar with the use
of prefabricated systems.
Members of the bridge team noted several areas in which prefabrication could be used
and made the following suggestions:
• Allow the use of prefabricated structural units to expedite construction at the 31st and
40th Street Bridges. If the bridge is on the critical path, the contractor would have the option to
use the technology.
• Build drilled shaft (bent) structures to limit the scope of retaining walls.
• Relocate and elevate single-lane ramps at 31st Street to reduce the need for retaining
walls, assuming this technique is cost-effective.
• Consider new material technologies to build longer-lasting structures (e.g., steel with
improved corrosion resistance and high-performance concrete).
Pennsylvania Department of Transportation ACTT Workshop 51
Members of the bridge team also recognized that utilities are a significant issue and,
many team members believed that, to the maximum extent possible, utilities should not be placed
under the roadway. If there is no alternative to placing utilities under the roadway, construction
of a three-sided precast concrete culvert, 20-ft wide × 12-ft high (as dictated by the utilities
team), should be considered. The culvert could serve three roles: utility tunnel, retaining wall,
and elevated roadway.
ROW Team
The ROW team noted the significance of the railroad ownership of property parallel to existing
roadway. The team also noted the challenges in relocating residential, business, and nonprofit
structures that exist near the current roadway. A not-so-minor problem is the presence of
billboard and other advertising signs along the route.
Many members of the ROW team suggested the development of a flexible (pre-ROD)
hardship acquisition program using federal-aid funds with the concurrence of the FHWA
division. Also, as necessary, PENNDOT should pursue early (pre-ROD) acquisitions that are
100% state funded with credit to state matching share, assuming that there are available state
funds. Many members of the ROW team also suggested the development of a strategy to address
the acquisition and removal of approximately 50 outdoor advertising devices within the project.
Potential litigation by the sign owners may delay the project development and clearance of
necessary ROW.
Although not applicable to this project, PENNDOT may wish to seek FHWA approval of
a pilot project to use incentives to settle before filing condemnation, similar to the pilot being
conducted in Florida. Team members also suggested flexible use of hardship acquisitions—
PENNDOT may wish to request that FHWA delegate some approval authority, with the criteria
set out in advance.
The ROW team, like most other teams, suggested close coordination with utilities and
design. Many team members believed that the three disciplines should coordinate activities to
inventory the existing utilities in the project area and to identify and evaluate potential relocation
52 Transportation Research Circular E-C059: Accelerated Highway Construction Workshop Series Summary
corridor(s). This should be done as soon as possible. They also suggested that the design and
utilities teams work with the ROW team to determine whether more than 30 partial acquisitions
should be considered for full ROW acquisitions. A joint field inspection by a joint team from
ROW, design, and utilities within 90 days would be appropriate.
Two important issues to consider as the corridor is designed and constructed are limiting worker
exposure to public traffic and construction vehicles and equipment and addressing potential
worker fatigue during an accelerated construction process.
Members of the safety team offered the following suggestions for consideration:
• A site-specific safety plan should be required as a bid item, and worker safety should
be integrated with public safety planning. At each juncture of project scheduling, safety practices
should be woven into the project. The contractor could assign a single entity that could have the
overall responsibility and accountability for safety on the project. The safety issue should be a
key element of the pre-bid meetings with the contractor community.
• Construction vehicle traffic on the site should be controlled by requiring the
contractor to provide off-site worker parking and busing and by establishing alternative systems
for the delivery of materials. The contractor should include this in the safety plan.
• The safety plan should address the incorporation of safety practices into the project
scheduling. PENNDOT should take the lead on this issue during the design and require the
contractor to do it as part of the overall safety plan.
• Although there are no scientific standards concerning worker fatigue, the contractor
should closely monitor and manage worker stress, assuming many long hours and days
throughout the project life. The contractor should be required to establish and administer a
substance abuse screening and control program. Both could be considered in the safety plan.
However, to equalize the bidding process, the DOT may want to establish some time restrictions
in the contract specifically for workforce rest periods. Also, PENNDOT should examine the
legal issues related to mandatory substance abuse screening and control.
• A contracting clause could be added that provides safety performance incentives.
Although there is no experience with this concept, team members recommend that it be studied
nationally. As of now, the contractor has some incentive through the insurance carrier to
maintain a high safety record.
Utilities Team
Members of the utilities team clearly understood the utility challenges associated with this
project and the potential for delays and cost overruns. They also noted the limited availability of
space to relocate the utilities. Of utmost importance is the identification and location of existing
utilities.
With this in mind, they suggested the following options:
• Include all utility work in the project scope, assuming that agreement can be reached
with the utility companies;
• Relocate utilities before road construction;
• Eliminate the need for certain utilities with loop modifications, if possible; and
• Vacate the existing building and eliminate the need for local services.
The first choice for relocation of the utilities is to move them outside the roadway. Utility
relocation can be performed under a separate Phase 1 contract. The possibility of financing the
utilities relocation should be explored. The second choice for relocation is to build a utility
access tunnel near or under the side of the road.
Senior PENNDOT representatives accepted many of the suggestions and ideas for consideration
as the project evolves. PENNDOT will probably not use DB because certain restrictions in
Pennsylvania allow only a modified approach. However, PENNDOT will include as many
innovative contracting methods as possible, primarily incentives.
ENDNOTES
1. This is a regional issue. PENNDOT will work with the SPC and the Pittsburgh Downtown
Partnership, at a minimum.
2. If PENNDOT includes a long-term warranty, it should consider whether it is proper to
require a specific design procedure as well.
CHAPTER 5
T his process of examining accelerated construction has been an extremely illuminating and
challenging process. Representatives involved in all three workshops were assembled to
summarize what was learned. Following are their significant observations:
MANAGEMENT
Over the next decade, the need to apply accelerated construction strategies will grow both in
numbers and in complexity of projects. An interpretation of the available statistics supports this
conclusion, as do customer expectations. There is no single solution to the multidisciplinary,
multitiered issue of accelerated construction. The existing roles and responsibilities of many of
the key organizations are changing, but probably not as fast as will be required over the next
decade. These organizations should consider a central source of information and coordination.
TECHNOLOGY TRANSFER
Excellent strategies and tactics are being used on many projects; however, sharing of this
information within the state and across the country needs major attention. A methodology that
allows the identification and sharing of innovative strategies among the various DOTs and
industry should be developed. This should include interactive list-serve functions. Again, a
central point of information and coordination would be extremely beneficial.
CORRIDOR ANALYSIS
Accelerated construction assessments that start before the final establishment of project and
budget limits provide more flexibility to managers. Corridor studies can be effective tools for
identifying the key issues and for ensuring interdisciplinary cooperation. Setting goals for a
corridor or project appears to be a positive way to focus on the key issues. The establishment of
clear and realistic goals helps the engineers to craft solutions or to report on options. Corridor
approaches and the subset “mix of fixes” are emerging strategies that can integrate work needs
with traffic impacts. They are not widely understood or applied at this stage. To support this
concept, continued development of the “corridor” and “mix of fixes” concepts should be
considered. The ACTT workshop concept, if applied, could help to further define the corridor
approach.
54
Summary of Workshop Output and Closure 55
SECONDARY DISCIPLINES
CONSTRUCTABILITY
There is a growing need for one or more constructability reviews during the corridor or project
development phase. Constructability reviews can be accomplished without prejudicing the
bidding process, as many DOTs can attribute. A constructability review done before the
establishment of project limits or project budgets for all major projects could be very beneficial.
Many new financing tools have come on line in the last several years. These can help to bring
corridors and projects to reality earlier. However, the financing plan must be linked to the
innovative contracting and warranty strategies and to the construction schedule. If innovative
financing is being contemplated, it should be analyzed in conjunction with innovative
contracting, bridge and pavement warranties, and maintenance personnel, which are all
interconnected.
Current and future reduction in both the numbers and experience of employees within the DOTs
may require major transfer of responsibilities to the construction and design industries. However,
there is little effort under way nationally to identify (a) the specific services that could be
transferred, (b) the work that is uniquely governmental and must be retained, (c) the risks
associated with the transfer, and (d) the ability of the receiving organization to provide the
services.
Utilities are thought of as being the leading cause of construction claims. The issue is
exacerbated in an incentive-based project. It is a difficult and challenging issue. Likewise,
railroad relocation is difficult to coordinate, especially with the major consolidation that has been
under way over the last decade. The regional nature of both utilities and railroads makes the
56 Transportation Research Circular E-C059: Accelerated Highway Construction Workshop Series Summary
DOT’s coordination effort much more difficult. A national strategic forum with AASHTO,
FHWA, the construction industry, national railroads, and key utility companies convened to
understand the issues faced by all the organizations and to develop a common agenda of what
might need to happen to resolve and improve relations might be very beneficial.
Although long-duration accelerated projects may start well with partnering, the longer they last,
the more difficult it is to maintain teamwork and cooperation. Additionally, many mid- to small-
sized construction companies do not have the trained personnel to staff accelerated construction
projects. The toughest work goes to the best employees. These projects often demand long hours
and nights, pose higher job risks, and involve overall high stress. A toolbox of techniques should
be developed for (a) helping to detect early signs of breakdown in cooperation, (b)
recommending ways to improve cooperation and alleviate stress, and (c) suggesting ways to
rotate employees or require time off from the project.
INCENTIVES
Incentives have produced exceptional results in meeting both time and quality requirements.
However, most agree that time demand pressures challenge quality requirements. A project with
a $25,000 per day time incentive, for example, may include only a $2,500 per day incentive for
quality pavement smoothness, for example. Several new initiatives should be considered. The
first initiative is to complete work on defining an overall “Q” factor to go with A + B time
factors that will elevate attention to final product quality. The second initiative would be to
examine softer project goals such as safety, traffic management and traffic flow, utility location
and relocation, engineering quality, partnering, for example, and developing an overall project
management quality index and incentive.
VALUE ENGINEERING
Value engineering before construction should be restructured to become a more effective tool
that creates additional innovation as it relates to accelerating construction. As part of this
consideration, the conventional 50–50 split between the contractor and the agency for approved
submittals might be increased as an incentive to propose other time-savings initiatives.
PROJECT CONSOLIDATION
There is a trend toward consolidating the number of construction contracts both to handle traffic
and to accommodate the DOT workforce. This trend also leads to an increased dollar value of the
projects and puts exceptional pressure on the small- to mid-sized construction firms. It is
important to recognize that the contract consolidation, along with innovative contracting
strategies, are in response to the need to (a) accelerate projects, (b) improve quality, and
(c) alleviate DOT personnel shortfalls. None of these pressures will decrease in the future, which
in turn requires a fuller understanding of risk transfer from one organization to another.
No single source of key statistics can help identify the extent of the change needed in the future
or track the extent of acceleration under way. Statistics that could be packaged include lane
closure policies, incentive-based project usage, safety in work zones, construction workforce
accidents, innovative contracting mechanisms, and so forth. Construction activity and congestion
are linked in the minds of the public. Better statistics could be used as an advantage in promoting
additional patience as part of the planning process. The public appears to be willing to accept
high-intensity, short-duration closures for construction work. This could lead to more high-
intensity, short-duration shutdowns of roadways to do as much work as possible in a shorter
period of time. This also may help to build longer-lasting, higher-quality facilities.
Prefabrication and modular technologies can considerably speed construction, and they need to
be advanced. In the future, these technologies could be included as allowable alternatives to cast-
in-place technology not only to meet time constraints but also to meet warranty or quality
considerations. Pavement technology should be included in this technology group as well.
Work zones improvement technologies are both merging and emerging. However, both the
construction industry and the inspection workforce need to better understand the use and
application of work zone improvement on construction projects. Initiatives aimed directly at the
construction industry that examine ITS technology and describe its applicability would be
58 Transportation Research Circular E-C059: Accelerated Highway Construction Workshop Series Summary
extremely beneficial. It is important that ITS be presented as an integrated system, not just a
collection of individual products. The initiatives also should include guideline procurement
language, bid strategies, QC checks, and so forth.
NATIONAL RESEARCH
Rapid renewal is a relatively new concept being defined under the Future Strategic Highway
Research Program Study. Many of the items mentioned in this report should feed directly into
identifying the long-range research needs of that program.
The two workshops in Indiana and Pennsylvania showed great results and, if applied elsewhere,
could prove to be a solid way to communicate the many details associated with accelerated
construction. Appendixes B and C provide the details. The ACTT workshop process will, as a
spin-off, identify a pool of national experts who could be available to DOTs for future assistance.
TECHNOLOGY TRANSFER
One of the most difficult technology transfer efforts is identifying and sharing the many good
work efforts that happen on individual projects. It is difficult to (a) identify them, (b) document
them, and (c) share them. A creative new approach to technology transfer in this area could be
extremely beneficial.
References
1. Special Report 249: Building Momentum for Change: Creating a Strategic Forum for
Innovation in Highway Infrastructure. TRB, National Research Council, Washington, D.C.,
1996.
2. Keever, D. B., K. E. Weiss, and R. C. Quarles. Moving Ahead: The American Public Speaks
on Roadways and Transportation in Communities. Federal Highway Administration.
February 2001. www.fhwa.dot.gov/reports/movingahead.pdf.
3. Status of the Nation’s Highways, Bridges, and Transit: Conditions and Performance Report
(C&P Report to Congress). Federal Highway Administration. 1999.
www.fhwa.dot.gov/policy/1999cpr/.
4. Manual on Uniform Traffic Control Devices: Millenium Edition. FHWA, U.S. Department of
Transportation, 2001.
5. Anderson, S. D., and J. S. Russell. NCHRP Report 451: Guidelines for Warranty, Multi-
Parameter, and Best Value Contracting. 2001. http://gulliver.trb.org/publications/
nchrp/nchrp_rpt_451-a.pdf.
59
APPENDIX A
List of Participants
60
List of Participants 61
Additional Support
Jay Dumontelle
FHWA
National Team
Dina N. Kukreja
Virginia Department of Transportation
Central Office
District Office
Consultant Support
Justin Smith
Michael Baker Jr., Inc.
APPENDIX B
A fter the Indiana and Pennsylvania workshops, FHWA and the AASHTO Technology
Implementation Group (www.aashtotig.org/) agreed to organize an implementation
program to promote the concept of accelerated construction technology transfer. At their request,
the following guidelines were developed on how to select the right corridor and how to conduct
an ACTT workshop.
If the corridor (project) substantially meets the these requirements, it is probably a good
candidate.
1. The host DOT should establish a management team and a single point of contact as
the ACTT project manager.
2. The team should have representatives from the key organizations within the DOT.
66
Guidelines on Organizing and Managing an Accelerated Construction Technology Team Workshop 67
1. Identify the overall corridor goals, objectives, urgency, needs, and so forth. One of
the most critical elements of workshop success is the establishment of the goals (performance
goals) for the corridor. These should be clear, bold, and attainable.
2. Determine the specific customers—public, abutters, and so forth—and their
expectations.
3. Describe how this corridor (project) would be built under “normal” circumstances.
4. Determine the potential impact on the traveling public, business development, work,
and so forth under normal circumstances. This means the normal lane shutdowns, delays, and so
forth for the years the project would be under construction.
5. Develop preliminary corridor goals for the workshop. These goals will be revisited
later. The goals will be very broad at this stage—challenges to the teams. Goals should address
the following:
6. Determine the critical skill sets needed to design and build the project. Consider
ROW, utilities, pavements, bridges, safety, mobility, financing, contracting, health and safety,
geotechnology, work zones, and so forth The project scope will help define the specific critical
skills needed.
7. Conduct the first meeting with senior DOT management. For the project to be
successful, it is imperative that top managers be fully engaged. They ultimately are the project
champions. Without them, it will be difficult to get buy in from the DOT technical staff. Top
managers need to commit the department and approve the funding for the initiative.
5. Review the total number of team members and determine whether the number is
manageable. With eight to ten skill sets and two to three experts per set, the national and state
teams could range from 32 to 60 members. Including speakers, facilitators, managers, and so
forth, the number could increase by 10 to 15 people. Check the venue details at this stage.
Remember that the goal is to strike a balance between the needs and the ability to have
interaction with the DOT team. Numbers count.
6. Determine the final role that local industry will play in the workshop. More than
likely, this corridor is important to the private sector (e.g., consultants, contractors, suppliers).
Most DOTs have “hot button” items that may be fundamental to the acceleration of the corridor.
Prudence should be exercised in the invitation process. It may be worth scheduling a separate
meeting with DOT management and the industry to explain the process.
1. Ensure that the ACTT management team visits the DOT, meets with key personnel,
establishes the steering committee, and meets with senior management.
2. Present the overall purpose and mission of ACTT. The ACTT management team
must make this as nonthreatening as possible.
3. Ensure that key DOT staff members are involved, including both management and
technical staff. At this stage, one DOT staff member must have the lead responsibility to work
with the ACTT management team.
4. Identify the workshop logistics, venue, facilitator services, and so forth. Some
important concepts are as follows:
• Schedule only one room per skill set. The rooms should be nearby to facilitate
working together.
• Establish a help desk that provides general information to all teams.
• Schedule a corridor site visit. During this meeting, a corridor site visit is
extremely important. A major concern during the workshop will be the need for and the time
to conduct a site visit.
• Develop the agenda, including opening speakers.
• Identify the facilitator(s) and the report writer.
• Keep the workshop short. It is generally suggested that the workshop be no longer
than 1½ days.
5. Prepare workshop documents.
3. Day 1 Program
• Plenary session:
− General presentations,
− Self introductions,
− DOT senior manager charge,
− ACTT national charge,
− Project explanation,
− Question and answer period, and
− Breakout rules (e.g., scribes).
• Skill team breakouts: Each team moves to separate rooms to discuss specific
details associated with its technical area. National team members should present
innovative or emerging methodologies. DOT members should present general practice
and experience with the technology.
• Skill team interaction: Teams must be encouraged to work together. The
workshop points out the need to integrate different skills.
• Team dinner: This is a good time to discuss “loose ends,” the results of the day,
and so forth.
4. Day 2 Program
• Skill team breakouts and final presentation development.
• Team assembly with skill team reports: The key to the presentations is a blend of
(a) skill details and (b) key interactions with other skills.
• Open discussion.
• Workshop closeout.
• Steering committee closeout meeting.
1. The first draft should be prepared within 30 days. This must be coordinated with skill
set team members.
2. The ACTT team (facilitator and report writer) should return to the DOT to present the
overall findings within 30 to 60 days.
3. At this point, the DOT needs to present its overall conclusions as well.
4. Prepare final report within 60 days, including a PowerPoint presentation.
5. Prepare 6-month and 1-year “quick reports” on the status of the recommendations.
APPENDIX C
Request for
candidate ACTT
DOT input
• Project objectives
• Project characteristics NO
• Policy issues
Good Use current
ACTT practice
candidate?
Selection criteria project
Complexity impact on
community timing of project
development
YES
Report to ACTT
Conduct workshop, Prepare reports, leadership process
speakers, facilitators, document results, refinements, publish
participants, prepare lessons results, lessons learned
scribes/note takers learned database
70
APPENDIX D
71
The National Academy of Sciences is a private, nonprofit, self-perpetuating society of distinguished scholars engaged
in scientific and engineering research, dedicated to the furtherance of science and technology and to their use for the
general welfare. On the authority of the charter granted to it by the Congress in 1863, the Academy has a mandate that
requires it to advise the federal government on scientific and technical matters. Dr. Bruce M. Alberts is president of the
National Academy of Sciences.
The National Academy of Engineering was established in 1964, under the charter of the National Academy of
Sciences, as a parallel organization of outstanding engineers. It is autonomous in its administration and in the selection
of its members, sharing with the National Academy of Sciences the responsibility for advising the federal government.
The National Academy of Engineering also sponsors engineering programs aimed at meeting national needs,
encourages education and research, and recognizes the superior achievements of engineers. Dr. William A. Wulf is
president of the National Academy of Engineering.
The Institute of Medicine was established in 1970 by the National Academy of Sciences to secure the services of
eminent members of appropriate professions in the examination of policy matters pertaining to the health of the public.
The Institute acts under the responsibility given to the National Academy of Sciences by its congressional charter to be
an adviser to the federal government and, on its own initiative, to identify issues of medical care, research, and
education. Dr. Harvey V. Fineberg is president of the Institute of Medicine.
The National Research Council was organized by the National Academy of Sciences in 1916 to associate the broad
community of science and technology with the Academy’s purposes of furthering knowledge and advising the federal
government. Functioning in accordance with general policies determined by the Academy, the Council has become the
principal operating agency of both the National Academy of Sciences and the National Academy of Engineering in
providing services to the government, the public, and the scientific and engineering communities. The Council is
administered jointly by both the Academies and the Institute of Medicine. Dr. Bruce M. Alberts and Dr. William A.
Wulf are chair and vice chair, respectively, of the National Research Council.
The Transportation Research Board is a division of the National Research Council, which serves the National
Academy of Sciences and the National Academy of Engineering. The Board’s mission is to promote innovation and
progress in transportation through research. In an objective and interdisciplinary setting, the Board facilitates the
sharing of information on transportation practice and policy by researchers and practitioners; stimulates research and
offers research management services that promote technical excellence; provides expert advice on transportation
policy and programs; and disseminates research results broadly and encourages their implementation. The Board’s
varied activities annually engage more than 4,000 engineers, scientists, and other transportation researchers and
practitioners from the public and private sectors and academia, all of whom contribute their expertise in the public
interest. The program is supported by state transportation departments, federal agencies including the component
administrations of the U.S. Department of Transportation, and other organizations and individuals interested in the
development of transportation. www.TRB.org
www.national-academies.org
TRANSPORTATION RESEARCH BOARD
500 Fifth Street, NW
Washington, DC 20001