Anugraha Vasan 1812560, 5bcomp A
Anugraha Vasan 1812560, 5bcomp A
2. PROGRAM EVALUTATION AND REVIEW TECHNIQUE (PERT): PERT was developed in 1957 by
the US Navy Special Projects Office . It is a method of analyzing the tasks involved in
completing a given project, especially the time needed to complete each task, and to
identify the minimum time needed to complete the total project. It incorporates uncertainty
by making it possible to schedule a project while not knowing precisely the details
and durations of all the activities. It is more of an event-oriented technique rather than
start- and completion-oriented, and is used more in those projects where time is the major
factor rather than cost. It is applied on very large-scale, one-time, complex, non-routine
infrastructure and on Research and Development projects.
A valuation of planned work, called planned value (PV) or budgeted cost of work
scheduled (BCWS)
Pre-defined "earning rules" (also called metrics) to quantify the accomplishment of work,
called earned value (EV) or budgeted cost of work performed (BCWP)
EVM implementations for large or complex projects include many more features, such as
indicators and forecasts of cost performance (over budget or under budget) and schedule
performance (behind schedule or ahead of schedule). However, the most basic requirement of
an EVM system is that it quantifies progress using PV and EV.
4. DRAG COST : This cost is amount by which the ROI of the cost is reduced due to the critical
cost drag. . This cost is most commonly used for justifying the project resources .Drag cost is
used on an activity where the impact of that is caused by the project level which is either by
Reduction of projects expected value by late completion
Increase in cost by increase in indirect cost because of longer cost duration .
5. Gantt chart: It is a type of bar chart that illustrates a project schedule, named after its
inventor, Henry Gantt who designed such a chart around the years 1910–1915.
Gantt charts illustrate the start and finish dates of the terminal elements and summary
elements of a project. Terminal elements and summary elements constitute the work
breakdown structure of the project. Modern Gantt charts also show the dependency (i.e.,
precedence network) relationships between activities. Gantt charts can be used to show
current schedule status using percent-complete shadings and a vertical "TODAY" line as
shown here. Gantt charts are sometimes equated with bar charts.