PPP BOOK 2020 (Kepmen PPN No 22 Dan 61 Tahun 2020)
PPP BOOK 2020 (Kepmen PPN No 22 Dan 61 Tahun 2020)
PUBLIC
PRIVATE
PARTNERSHIP
INFRASTRUCTURE PROJECTS
PLAN IN INDONESIA 2020
Foreword
BY MINISTER OF NATIONAL DEVELOPMENT PLANNING/ HEAD OF NATIONAL
DEVELOPMENT PLANNING AGENCY (BAPPENAS)
Suharso Monoarfa
Foreword ................................................................................................................................................... i
Table of Content ...................................................................................................................................... ii
ii
Construction of Merangin Dam........................................................................................................... 119
Pasir Kopo Dam....................................................................................................................................... 129
Sidan Dam Raw Water Channel ......................................................................................................... 133
Construction of Kamijoro Regional Water Supply System ........................................................ 136
Construction of Jatigede Regional Water Supply System ......................................................... 141
Pantura Regional Water Supply System ......................................................................................... 147
Dadimuria Regional Water Supply System ..................................................................................... 151
Bregas Regional Water Supply System ........................................................................................... 155
Wosusokas Regional Water Supply System Phase II .................................................................. 159
Construction of Waste to Energy Facility in South Tangerang ................................................. 163
Legok Nangka Regional Waste Processing Facility..................................................................... 167
Sarbagita Suwung Waste to Energy Facility .................................................................................. 171
Jatibarang Waste to Energy Facility ................................................................................................. 175
Development of Piyungan Landfill..................................................................................................... 179
Integrated Hazardous Waste Management System in Sumapapua........................................ 184
Integrated Hazardous Waste Management System in Sumatera ........................................... 189
Development of Modern Land Registry Information System.................................................... 193
Provision of Kuta Integrated Utility Panel....................................................................................... 198
Surakarta Street Lighting .................................................................................................................... 202
Madiun Street Lighting .......................................................................................................................... 206
Teluk Bintuni Industrial Zone .............................................................................................................. 210
Development of Jogja Agro Park ....................................................................................................... 214
Development of Ngawi Agrotourism ................................................................................................ 219
Construction of National Maritime Research Zone ...................................................................... 223
Construction of Class A Regional General Hospital In Central Kalimantan ........................ 228
Construction of Industrial Correctional Facility in Nusakambangan ..................................... 232
Relocation of Correctional Facility from City Downtown to Outskirt ..................................... 236
Bina Harapan Cisaranten Housing .................................................................................................... 240
Attachment
Success Story
Balikpapan - Samarinda Toll Road.................................................................................................... 244
Batang - Semarang Toll Road............................................................................................................. 245
Pandaan - Malang Toll Road ............................................................................................................... 246
Jakarta - Cikampek II Elevated Toll Road ....................................................................................... 247
Manado - Bitung Toll Road................................................................................................................... 248
Cileunyi - Sumedang - Dawuan Toll Road ...................................................................................... 249
Serang - Panimbang Toll Road .......................................................................................................... 250
Serpong - Balaraja Toll Road ............................................................................................................. 251
Jakarta - Cikampek II South Toll Road ............................................................................................ 252
Krian - Legundi - Bunder - Manyar Toll Road ............................................................................... 253
Development of Bandar Lampung Water Supply System .......................................................... 254
Development of Umbulan Water Supply System .......................................................................... 255
Development of West Semarang Water Supply System ............................................................ 256
Development of Nambo Regional Waste Management System ............................................... 257
Construction of Palapa Ring West Package ................................................................................... 258
Construction of Palapa Ring Central Package .............................................................................. 259
Construction of Palapa Ring East Package .................................................................................... 260
iii
Central Java Power Plant .................................................................................................................... 261
iv
1. INDONESIA COUNTRY PROFILE
Indonesia, with the land area of 1,916,862 square kilometres, is the 14th largest country in the
world. The ranks increased to the 7th largest country in terms of land and sea area
combined, where it consists of 34 provinces. Indonesia’s population — which at 266.7 million
makes it the world’s fourth-most-populous country, is the most populous in Southeast Asia.
According to the World Bank, Indonesia’s GDP per capita has steadily risen, from $823 in
the year 2000 to $3,932 in 2018. Indonesia is also a member of the G-20, where it is a
representative of developing countries that give economic impact towards the world.
In order to achieve the medium scenario of GDP growth target and infrastructure stock
target in RPJMN 2020-2024, infrastructure development needs are 6,445 Trillion IDR or an
average of 6.2 percent of GDP. However, the government’s ability to fund the infrastructure
development only 2,385 trillion IDR or only 37 percent of total needs (RPJMN 2020-2024). It
required an innovative effort to encourage the participation of the community and business
entities to finance the remaining 63% of infrastructure development needs.
Over the years, the investment climate for the private sector is getting better, as Indonesia
have steadily increased its Ease of Doing Business (EoDB) Ranks by World Bank. Indonesian
EoDB rank arises from 106 in 2016 to 73 in 2019. At the moment, Indonesia is the Top 3 Asian
Best Investment Destination according to The Economist and also the Top 3 Japan
Investment Destination (JBIC rating). Moreover, Indonesia’s Sovereign Credit Rating is rated
by Moody’s (Baa2/Stable Outlook), Fitch (BBB/Stable Outlook), and S&P (BBB/Stable
Outlook) in 2020.
v
2. REGULATORY FRAMEWORKS FOR PUBLIC-PRIVATE PARTNERSHIPS IN THE PROVISION
OF INFRASTRUCTURE
The Government has taken a series of major steps to refine the PPP policies and regulatory
framework to improve the attractiveness and competitiveness of the Government’s PPP
program. The regulations consist of:
vi
c) Minister of Finance Regulation Number 30/2012 regarding contingency liability
fund.
vii
3. PPP STAGE EXPLANATION
There are four stages for the PPP scheme: Planning, Preparation, Transaction and
Implementation.
3.1 Planning
In solicited PPP projects, determining whether the project is suitable for PPP or
not must be done using a preliminary study. A preliminary study is an initial study
conducted by the GCA to provide descriptions of the requirements necessary for
the infrastructure provision and its benefits if it is delivered under cooperation
with the business entity through the PPP mechanism. Furthermore, the
Preliminary Study should consist of:
a) Need analysis
b) Compliance criteria
The GCA must set up and eventually disburse the budget for planning phase, at
least for preparation of Preliminary Study and conducting Public Consultation.
4) Public consultation
Public consultation on preparation stage will discuss the planned projects with
related stakeholders. The goal of the public consultation is to gather inputs and
responses from stakeholder regarding the projects.
5) PPP screening
After completing the preliminary study including the public consultation, the GCA
then will decide whether the planned project is suitable to be continued using PPP
or other scheme. Then, the GCA must propose the project by sending a letter
attached with all the documentation to the Minister of National Development
Planning to be evaluated.
Ministry of National Development Planning after receiving the project from many
GCAs will then evaluate and compile the projects into one document called PPP
Book. This document is issued annually.
7) PPP Categorization
While evaluating the projects, the Ministry of National Development Planning must
categorize the projects into 2 (two) categories: under preparation projects and
ready to offer projects, according to its readiness and completion level.
3.2 Preparation
The PPP preparation stage comprises of Pre-Feasibility Study, which consists of:
1) Pre-Feasibility Study
Pre-Feasibility Study in the case of solicited PPP Projects can be divided into 2
(two) documents. Outline Business Case (OBC) and Final Business Case (FBC)
where the FBC is the improvement of the OBC with more detailed data and
analysis. Although on special cases, both can be combined into one document,
such as if the project is considered priority project and/or national strategic
project or if there are similar projects with proven high demand on the market.
The OBC/FBC document must include at least:
b) Technical study;
ix
d) Environmental and social study;
2) Public Consultation
The purpose of Public Consultation is to review the compliance of the social and
environmental standards by the provisions stipulated in laws and regulations of
the environmental sector, obtain inputs regarding public needs related to the PPP
project and ensure the readiness of the project.
3) Market Sounding
Market Sounding is intended to obtain inputs and response from the PPP markets
(business entities/ agencies/ institutions/ national or international organizations).
3.3 Transaction
1) Market Consultation
GCA must determine and set the location of the project as in most PPP projects,
land acquisition is one of the responsibilities of the GCA. The GCA must consult
with the preparation document and any related institution to ensure that the land
acquisition and the ensuing relocation (if any) is compliant with the regulation. GCA
must also ensure that the project have obtained any applicable environmental
permits and licenses.
x
4) Agreement Signing
After the letter of award is issued, the winner must establish a Special Purpose
Company (SPC) as a legal entity to sign the agreement regarding the PPP project.
In general, the SPC must sign the PPP agreement with the GCA. If there is some
form of government guarantee, SPC must also sign guarantee agreement with
Indonesian Infrastructure Guarantee Fund (IIGF) while the GCA sign a recourse
agreement with the IIGF.
5) Financial Close
After signing the agreement, the SPC should be able to secure the financing of the
project. This must be obtained no longer than 12 months after signing the PPP
Agreement and could be extended from time to time if the failure to obtain
financing is not contributable to the failure of the PPP project. Every extension
given for financial close should be no longer than six months. Financial close could
also be done periodically according to project cycle and the agreement between
SPC and GCA.
3.4 Implementation
To prepare for the implementation, GCA must establish the monitoring team,
prepare and issue guidelines on PPP implementation monitoring, handover all
project documentation to the monitoring team, and oversee the progress of
financial close from the SPC.
The monitoring will commence from construction phase, operational phase until
the handover of asset after the cooperation period is finished
Due to the nature of PPP which requires cross-sector and cross-agency coordination to
ensure the success of the PPP project, a coordination system between government
agencies are needed. Responding to those needs, in December 2016, PPP Joint Office was
established.
This PPP Joint Office was established to assist the GCA and investors, and also to answer
any queries about the PPP Scheme in Indonesia. The PPP stakeholders from the central
government and institution agreed to establish the PPP Joint Office in Jakarta. PPP
Joint Office now acts as a ‘one-stop service’ for PPP scheme in Indonesia. Hence, the use
xi
of a PPP scheme could be accelerated in an accountable method. It has no structural system
between the agencies but works as a coordination system.
2) Facilitate all parties related the project to accelerate PPP project implementation in
Indonesia; and
1) Coordinating Ministry of Economic Affairs - CMEA has the duty to solve any policy or
regulatory issues regarding financing schemes and utilization of infrastructure built
through the PPP scheme to support national and regional economic growth.
2) Coordinating Ministry of Maritime – CMoM has the task of solve any policy or
regulatory obstacles regarding implementation of PPP scheme in the maritime and
investment fields.
3) Ministry of Finance - MoF has the duty to provide fiscal support in accordance with
applicable regulations, in the form of:
a) feasibility support;
b) infrastructure guarantee;
e) proposals related to the funding structure and financing of the PPP project.
4) Ministry of Home Affairs - MoHA has the duty to carry out regional planning, regional
development budgeting, and give consideration regarding the implementation of the
PPP projects by regional government.
d) oversee the implementation of project investments that will use the PPP
scheme.
xii
7) National Public Procurement Agency (LKPP) has the duty to prepare business
entity procurement policies and provide assistance to the business entity
procurement process on the PPP project.
8) Indonesia Infrastructure Guarantee Fund – IIGF has the duty in evaluating the risk
analysis and its mitigation and examining the financial and economic calculation to
provide the guarantee for the PPP project.
Each of PPP Joint Office members has its role and authorization in implementing PPP
project. Each of the member’s roles, timeframes, and workflows related to PPP pipeline is
shown in figure 2.
xiii
5. PPP PROJECT PIPELINE
Based on the Presidential Regulation Number 38/2015, there are two PPP project proposal
schemes, which are Solicited and Unsolicited. Project pipeline comparison between the two
schemes is shown below. Solicited Proposal is initiated by the Government, while the
Unsolicited Project is initiated by the private sectors.
Figure 3 shows the interrelation between the four phases of the PPP Projects Pipeline. The
four phases are straightforward phases; each of them consists of another sub-process.
1) The planning phase consists of Project Identification and Preliminary Study. The first
step is used to choose a viable PPP project from a list of projects. Then, during the
second step, the project will go through a series of qualitative studies to determine
whether the project is suitable for a PPP scheme. This phase is estimated to take 3
to 8 months.
2) In the Preparation phase, the project will undergo a series of quantitative studies to
see the viability of the PPP projects, in terms of financial value, economic value, risk
analysis and mitigation, et cetera. In this phase, private sectors are invited to give
input in Public Consultation and Market Sounding. It is to be noted that on special
cases, OBC and FBC can be combined into one document, if the project is considered
priority project and/or national strategic project or if there are similar projects with
proven high demand on the market. In general, it is estimated to take 6 to 8 months
for a project to finish the preparation phase.
3) Transaction phase, which facilitates the project through a transaction to find the
suitable business entity, includes Market Consultation, Prequalification, Request for
Proposal, Bid Award, PPP Agreement Signing, and then Financial Close. It is
estimated to take 4 to 8 months to finish the transaction phase.
xiv
4) Last phase is implementation phase, which consist of construction stage, operation
stage and handover of asset after cooperation period is finished. During all of three
stages, GCA will establish a monitoring team to oversee and evaluate each aspect of
contract implementation.
As already mentioned above, the unsolicited PPP proposal is initiated by the private sector
or the project proponent. The process framework of unsolicited PPP proposal is quite the
same: Planning, Preparation and Transaction. However, the planning and preparation are
conducted by the private sector as the initiator, while the transaction is conducted by the
government (GCA).
1) The first stage is the Approval Process. It starts from the time the project proponent
presents the project in form of Letter of Intent (LoI) accompanied with Pre-Feasibility
Study or Feasibility Study. After receiving the feasibility study, the GCA then must do
all internal assessments and decide whether to approve the project or not. When the
GCA approve the project after assessing and evaluating the proposal it must issue
an Approval Letter.
xv
The Project Initiator may choose the incentives or benefit as a compensation for their
work of preparing the project. The choices of incentives or benefits to the Project
Initiator are as follows:
a) Right to Match
If another bidder with a better proposal wins the tender process after the
evaluation, Project Initiator may, at their own consideration, match their
proposal to the winning proposal and be declared as the winner.
The Project Initiator automatically gains additional score of 10% during the
proposal evaluation process.
GCA can purchase the intellectual property of the feasibility study on an agreed
price from the Project Initiator. The feasibility study document is then owned
by the GCA. Then, Project Initiator can decide whether to participate without
any added incentives or not participate in the tender process at all.
2) The second stage involves a Competitive Tender Process. the bidding process is
conducted similar to the solicited PPP project from pre-qualification until the bid
award.
3) The third stage, the PPP Agreement Signing is also done in similar way to the solicited
PPP project. This stage starts from the signing of PPP agreement until the financial
close.
1) User charge payment in the form of Tariff, in this scheme the SPC’s main income is
based on user charge payment;
2) Availability Payment, in cases where the project is not financially profitable, the
government will pay an agreed amount of annual payment as the SPC’s main income;
and
xvi
Figure 5: User Charge Scheme
The PPP Book is a list of Public-Private Partnership projects planned in Indonesia. The list
consists of two categories: (i) Under Preparation Projects; and (ii) Ready to Offer Project.
The PPP Book is prepared and published every year by the process of the Government’s
Work Plan.
To be registered in the PPP Book, the Minister, Head of Institution or Head of Local
Government must submit their project proposal to Bappenas along with a statement about
the Ministry/Institution or Local Government’s working unit that will be responsible for
planning, preparation and transaction of the proposed PPP project. The PPP project
xvii
proposal should be accompanied by supporting documentation that differs between
planning stages, shown in Figure 7.
Following is a summary of assessment criteria for projects to be integrated into the PPP
Book, along with requirements associated with environmental assessment, land acquisition
and resettlement, government support and the government guarantee for each of the
planning categories of the Book.
xviii
2) Ready to Offer Project
3) Important Notes related to the Viability Gap Fund and Government Guarantee during
the Procurement Process
4) Unsolicited Project
xix
8. PPP Project Evaluation
The following figure depicts the evolution of PPP projects throughout the successive PPP
Books since the year 2009.
During 2019, Bappenas received proposals for new infrastructure project from ministries as
well as local government. Bappenas had been reviewing and screening those proposals in
compliance with Minister of National Development Planning Regulation 4/2015 as amended
by Minister of National Development Planning Regulation 2/2020. From the review and
screening process, 51 proposals can be accepted to be included in PPP Book 2020
categorized as Ready to Offer and Under Preparation Projects. Other than two categories
as regulated the regulations, there are other categories such as Already Tendered projects
and Successful Stories.
Figure 9 summarizes the results of the evaluation process carried out since the publishing
of the previous edition of the PPP Book. Of the 20 projects in the 2019 edition, 10 projects are
carried on to this edition while others have progressed to next stage of PPP scheme or
dropped because of various conditions.
xx
4. Development of Motor Vehicle Weighing Implementation Unit (UPPKB) in Java and
Sumatera
5. Semarang City Light Rail Transit (LRT)
6. Construction of Industrial Correctional Facility in Nusakambangan
7. Relocation of Correctional Facility from City Downtown to Outskirt
8. Teluk Bintuni Industrial Zone
9. Surakarta Street Lighting
10. Legok Nangka Regional Waste Processing Facility
The PPP Book 2020 contains those projects that have progressed or remained unchanged
from the previous edition and new projects that have succeeded in the evaluation of the
process.
xxi
PPP PROJECTS
Registered in PPP Book 2020
Project Summary
The following is the list of projects registered in PPP Book 2020 based on Minister of
National Development Planning Decree No. 22/2020 and No. 61/2020.
Table 1: Ready to Offer Project Summary
Status
No Project Name Description
(per June 2020)
1
Status
No Project Name Description
(per June 2020)
toll road network system in the
Jabodetabek (Jakarta, Bogor,
Depok, Tangerang, Bekasi) area
and will support Pantura
strategic area.
2
Status
No Project Name Description
(per June 2020)
road plan will be above the
existing toll road section, which
the start point located in Cikunir
(at the junction between JORR
and the Jakarta-Cikampek toll
road) and the end point located
after the Alam Sutera
intersection. Business entity
shall responsible to perform the
toll road project with build-
operate-transfer (BOT) scheme.
10 Multi Lane Free Flow The project is to establish new Ready to Offer
(MLFF) Toll Road toll collection system, which (Approval Letter)
Transaction System replaces the existing manual toll
(Unsolicited) collection method. The project
scope is Design, Build, Finance,
Operate, and Transfer (D-B-F-
O-T). The proposed system has
the technical requirement of
MLFF GNSS toll collection.
3
Status
No Project Name Description
(per June 2020)
the retention pond will be
financed by government of
Semarang city.
4
Table 2 : Under Preparation Project Summary
Status
No Project Name Description
(per June 2020)
5
Status
No Project Name Description
(per June 2020)
the congestion problem still
occurred and delayed travelling
time from point to point. LRT is
proposed as one of the solutions
to reduce congestion and planned
to be built with elevated track.
6
Status
No Project Name Description
(per June 2020)
Mamminasata Toll Road is
planned to have 4 interchanges
with trumpet interchange type.
8 Construction of Badung The role of the ring road (11.5 km) Under Preparation
Southern Ring Road is to improve connectivity (OBC)
between regions with different
functions in South Badung, which
can then lead to an increase in the
quality of the area in accordance
with its function. The various
potentials of both developing new
tourism areas and reviving local
community commodities,
including arts and culture, are the
reasons for this southern ring
road development plan.
7
Status
No Project Name Description
(per June 2020)
Housings (“PUPR”). The program
is expected to generate economic,
social, environmental, water
management and livelihood
benefits for the people of the
Merangin Regency and Jambi
Province, as well as to enhance
food and energy security and
boost economic growth on the
Jambi Province.
13 Sidan Dam Raw Water Sidan Dam Raw Water Channel is Under Preparation
Channel part of bigger development (Preliminary Study)
project to support clean water
supply for Sarbagita (Denpasar,
Badung, Gianyar, and Tabanan)
Region in Bali. This channel will
distribute water from Sidan Dam.
8
Status
No Project Name Description
(per June 2020)
16 Pantura Regional Water Pantura Water Supply System will Under Preparation
Supply System utilize water from Bengawan Solo (Preliminary Study)
River to supply water in
Lamongan, Bojonegoro and Tuban
Regency..It is projected that in 25
years, the water demand in the
area will grow to 1,749 lps. To
fulfill this demand, the
government needs to expand the
current water supply system.
9
Status
No Project Name Description
(per June 2020)
each of these regions has the
coverage of piping services that is
still below 50%. This project aim at
increasing the coverage area and
increase the efficiency of the
system.
10
Status
No Project Name Description
(per June 2020)
11
Status
No Project Name Description
(per June 2020)
still needed. This project it to
develop Integrated Hazardous
and Specific Waste Management
Facility in Sumapapua and
Sumatera Area with PPP scheme.
The Project scheme implemented
will be build-operate-transfer.
12
Status
No Project Name Description
(per June 2020)
requires the Business Entity to
finance, design, develop, operate,
and maintain the PSL service.
29 Madiun Street Lighting Madiun Regency is one of the main Under Preparation
investment destinations for (Preliminary Study)
prospective industries in West
East Java, which borders Central
Java Province. Madiun Regency is
directly well connected to the
Trans-Java toll road network and
is the main gateway for
transportation from East Java to
Central Java Province. This traffic
needs to be supported by well-
maintained street lighting to
support economic activities and
industrial estates, increase social
mobility and improve road safety
and security. To achieve this goal,
Madiun District proposes a PPP
Project for Madiun Street Lighting.
13
Status
No Project Name Description
(per June 2020)
farming, offering consultation for
farmers, and maintain
management of Jogja Agro Park.
14
Status
No Project Name Description
(per June 2020)
15
Project Investment Summary
Estimated Project
No Project Name Cost
(USD Million)
Ready to Offer
1 Patimban Port 511.11
2 Motor Vehicle Roadworthiness Testing and Certification Agency 116.76
(BPLJSKB) Proving Ground
3 Semanan-Balaraja Toll Road 1,117.26
4 Kamal-Teluk Naga-Rajeg Toll Road 1,331.39
5 Patimban Access Toll Road 457.37
6 Gedebage-Tasikmalaya-Cilacap Toll Road 4,143.49
7 Bogor-Serpong (via Parung) Toll Road 621.73
8 Cikunir-Karawaci Inner City Elevated Toll Road 1,815.57
9 Cikunir-Ulujami Jakarta Outer Ring Road (JORR) Elevated Toll Road 1,541.00
10 Multi Lane Free Flow (MLFF) Toll Road Transaction System 300.72
11 Sarbagikung Regional Water Supply System 222.00
12 Semarang Harbour Toll Road 836.81
13 South Sentul – West Karawang Toll Road 1,067.70
14 Karian-Serpong Regional Water Supply System 169.26
Under Preparation
1 Construction of Singkawang Airport 313.04
2 Development of Baubau Port 24.00
3 Development of Anggrek Port 69.58
4 Semarang City Light Rail Transit (LRT) 1,041.48
5 Development of Motor Vehicle Weighing Implementation Unit 23.57
(UPPKB) in Java and Sumatera
6 Preservation of Eastern Sumatera National Road in Riau Province 67.85
7 Makassar-Maros-Sungguminasa-Takalar Toll Road 638.24
8 Construction of Badung Southern Ring Road (Option 1)* 315.00
Construction of Badung Southern Ring Road (Option 2)* 142.80
9 Duplication and/or Replacement of Callender Hamilton Bridge in 188.38
Java Main Road
10 Batam-Bintan Bridge 609.69
11 Construction of Merangin Dam (Option 1)* 242.85
Construction of Merangin Dam (Option 2A)* 331.32
Construction of Merangin Dam (Option 2B)* 331.32
Construction of Merangin Dam (Option 2C)* 339.87
Construction of Merangin Dam (Option 3)* 339.87
12 Pasir Kopo Dam (Option 1)* 141.73
Pasir Kopo Dam (Option 2)* 158.33
13 Sidan Dam Raw Water Channel 32.40
16
14 Construction of Kamijoro Regional Water Supply System (Option 1)* 18.89
Construction of Kamijoro Regional Water Supply System (Option 2)* 20.29
15 Construction of Jatigede Regional Water Supply System 141.64
16 Bregas Regional Water Supply System** Under Calculation
17 Dadimuria Regional Water Supply System** Under Calculation
18 Pantura Regional Water Supply System** Under Calculation
19 Wosusokas Regional Water Supply System Phase 2** Under Calculation
20 Integrated Hazardous Waste Management System in Sumapapua & 67.89
Sumatera (Sumatera Region)
43.48
(Sumapapua Region)
21 Construction of Waste to Energy Facility in South Tangerang 126.16
22 Legok Nangka Regional Waste Processing Facility 253.05
23 Sarbagita Suwung Waste to Energy Facility 163.50
24 Jatibarang Waste to Energy Facility 194.44
25 Development of Piyungan Landfill 15.18
26 Development of Modern Land Registry Information System 743.05
27 Provision of Kuta Integrated Utility Panel 80.50
28 Surakarta Street Lighting 25.57
29 Madiun Street Lighting** Under Calculation
30 Teluk Bintuni Industrial Zone 451.10
31 Development of Jogja Agro Park 34.23
32 Development of Ngawi Agrotourism 2.52
33 Construction of National Maritime Research Zone 199.21
34 Construction of Class A Regional General Hospital In Central 50.36
Kalimantan
35 Construction of Industrial Correctional Facility in Nusakambangan 36.60
36 Relocation of Correctional Facility from City Downtown to Outskirt 96.60
37 Bina Harapan Cisaranten Housing 79.85
TOTAL PROJECT COST 20,898.82
*) For Total Project Cost calculation, only the highest cost option is chosen
17
READY TO OFFER
PROJECTS
Transportation:
1. Patimban Port
2. Motor Vehicle Roadworthiness
Testing and Certification
Agency (BPLJSKB) Proving
Ground
PATIMBAN PORT
Location : Subang, West Java Province
Description:
Patimban Port in Subang (West Java)
Patimban
designated as a national strategic project
Port
located near Cikarang Industrial Zone to
support trading activities in Java, the country's
most populated island and center of its
manufacturing activities.
Financial Feasibility:
IRR : 13.40%
NPV : USD 103.12 Million
Government Contracting Agency:
Minister of Transportation delegated to Estimated Concession Period: 40 years
Director General of Sea Transportation
Type of PPP:
Solicited
Return of Investment:
User Charge
18
Project Digest
2. The Opportunity
Government of Indonesia has officially declared the Patimban Port in Subang (West Java) as a
national strategic project through Presidential Decree No. 47/2016, signed by Indonesian
President Joko Widodo. This declaration implies that the project is regarded as priority project
that benefits the economy and society as a whole. The priority status further means that all
ministers, government agencies and governors need to support the development of the
project.
The decree also mandates Indonesia's Ministry of Transportation to handle the development of
the USD $3.1 billion seaport project in collaboration with a port operator.
The new seaport in Patimban, a two-hour drive from the Cikarang industrial zone, thus
superseded an earlier plan to build a deep sea port in nearby Cilamaya. Cilamaya is 30 minutes
closer to Cikarang, but government change the plan to build a port as the construction work
may interfere with oil and gas lines in and around the area.
19
The proposed Patimban port will have a capacity of 7.5 million twenty feet equivalent units
(TEUs) by 2037, providing support for trading activities in Java, the country's most populated
island and center of its manufacturing activities.
The development will provide added value to the economy of West Java, particularly Subang,
as it would provide employment opportunities. Consequently, industrial players in West Java
will also get an alternative harbour for their logistics and this will cut transportation costs
compared to transportation from/to the Port of Tanjung Priok, Jakarta.
Business entity shall be responsible for financing, designing, construction, operation, and
maintenance of the project during concession period.
4. Technical Specification
Based on the points concerning the sea transportation sector, this project is classified to
require an Environmental Impact Assessment (AMDAL), Environmental Management Plan and
Public Consultation.
From the results of studies of the Land Acquisition Planning Document, it is known that the
land required for the development of Port Patimban consists mainly of fields, rice paddies,
ponds, roads, cemeteries, settlements, irrigation and river. Government will be responsible for
the land acquisition and resettlement.
20
7. Project Cost Structure
This project has indicated that it needs government support and guarantee from Indonesia
Infrastructure Guarantee Fund (IIGF).
9. Contact Information
Phone :-
Email : [email protected]
21
MOTOR VEHICLE ROADWORTHINESS TESTING AND CERTIFICATION AGENCY (BPLJSKB)
PROVING GROUND
Location : Bekasi, West Java Province
Description:
This BPLJSKB Proving Ground is planned as a
certification and testing facilities for motor
vehicles to improve motor vehicle’s safety and
security and also to reduce level of emission. It
will adopt UNECE standards and it will
comprise high speed tracks, brake-testing,
sound testing, sideslip-testing and other
testing facilities.
Financial Feasibility:
Government Contracting Agency: IRR : 11.40 %
Minister of Transportation delegated to NPV : USD 3.65 Million
Director General of Land Transportation
Type of PPP: Estimated Concession Period: 20 years
Solicited
Return of Investment:
Availability Payment
22
Project Digest
2. The Opportunity
To have a safe and order road traffic and land transport, the vehicles that uses the road must
comply with several technical, administrative and legal criteria. One way of achieving that is
by establishing center for testing and certification of motorized vehicles, also known as
proving ground. The task for establishing such proving ground will be handed to Motor Vehicle
Roadworthiness Testing and Certification Agency or Balai Pengujian Laik Jalan dan Sertifikasi
23
Kendaraan Bermotor (BPLJSKB), a unit under Directorate General Land Transportation which
is part of the Ministry of Transportation.
As stipulated in the regulation, the testing and certification process should use ASEAN Mutual
Recognition Arrangement (MRA) regarding motorized vehicles, which basically follows the
UNECE standard. ASEAN MRA will be implemented in two phases. Phase 1 will adopt 19
standards of UNECE, while phase 2 will adopt another 32 standards. Additional benefits from
adopting ASEAN MRA in testing and certification process is Indonesia can increase its
automotive products’ competitiveness in regional or global market.
Based on preliminary discussion, DGLT has decided to add some other testing facilities into
the scope of work, as follows:
• Crash Test
• Rollover Test
• Stability Test
• Electric Power Trained Vehicle
• Co2 Emission
• Electric Vehicle of Category
• Quiet Road Transport Vehicle
There are two kinds of certificate which is published by (“DJLT”), that is Sertifikat Uji Tipe (SUT)
and Sertifikat Registrasi Uji Tipe (SRUT). SUT is the prove that the vehicles have passed the
test, while SRUT is a prove that the vehicles have the same specification of a vehicles type that
have earned an SUT. BPLJSKB scope of work is testing vehicles for SUT certification. DJLT
have planned to streamline and integrate both certification under BPLJSKB to simplify the
work needed for car manufacturer to have a certification. The proving ground is an essential
part to realize this plan.
The construction of BPLJSKB Proving Ground is planned to use PPP scheme with a return on
investment of a business entity will be done by Availability Payment, and is offered to a
business entity that has the potential to finance, design, build, maintaining all assets and
transfer the asset at the end of the term of cooperation, while BPLJSKB operates the facilities.
o Fulfillment of motor vehicle’s safety and security standards as regulated by Law and
development of Proving Ground with adopts UN Regulations
o Project financing
24
o Provide training to enhance the capability of BPLJSKB staff
o Transfer of infrastructure asset and testing facilities back to GCA at the end of project
4. Technical Specification
Construction plan will not significantly be affected by land availability as the plan will fully
owned by DGLT, so there will be no need for land acquisition. Although, surrounding inhabitant
will be affected both positively and negatively. Predicted significant impact is the negative
perception from local inhabitants towards the project which if not handled properly will
become a security risk and possibly delaying the project. Land usage plan will be modified as
a result of the proving ground construction.
25
6. Land Acquisition and Resettlement Action Plan
There is no need for land acquisition as the project will be constructed on government land.
- Administration permit
- Tax incentives by means of removing PPN for this project
- Direct access from Cilincing-Cibitung Toll Road to proving ground area
- Constructing a noise and vision barrier alongside Cilincing-Cibitung Toll Road parallel with
proving ground area
- As there is no upside risk for the private sector, no claw back should be implemented in
this project
9. Contact Information
Phone : +62-852-8006-5003
Email : [email protected]
26
READY TO OFFER
PROJECTS
Road:
1. Semanan-Balaraja Toll Road
2. Kamal-Teluk Naga-Rajeg
Toll Road
3. Patimban Access Toll Road
4. Gedebage-Tasikmalaya-
Cilacap Toll Road
5. Bogor-Serpong (via Parung)
Toll Road
6. Cikunir-Karawaci Inner City
Elevated Toll Road
7. Cikunir-Ulujami Jakarta
Outer Ring Road (JORR)
Elevated Toll Road
8. Multi Lane Free Flow (MLFF)
Toll Road Transaction
System
9. Semarang Harbour Toll Road
10. South Sentul – West
Karawang Toll Road
SEMANAN-BALARAJA TOLL ROAD
Location : Tangerang, West Java Province
Description:
Semanan-Balaraja Toll Road section is part of
the Inner Jakarta Toll Road Network. The toll
road will start at the end of Serpong-Balaraja
Toll Road section, located in East Balaraja
Interchange. It will have the length of 32.39 km
with 4 interchanges and 2 junctions.
Financial Feasibility:
IRR : 12.04%
Government Contracting Agency: NPV : USD 4.66 Million
Indonesia Toll Road Authority (BPJT)
Type of PPP: Estimated Concession Period: 40 years
Unsolicited
Return of Investment:
User Charge
27
Project Digest
Semanan-Balaraja Toll Road will become an integrated section of the Jabodetabek Toll Road
Network.
2. The Opportunity
The development of the area in the west of Jakarta, specifically the city of Tangerang and the
Regency of Tangerang needs a high level of accessibility both within the region and to/from
outside the region. At present the development of residential and industrial zones in the Pasar
Kemis and surrounding areas is the cause of economic and social growth, thus triggering an
increase in the movement of people and goods.
Currently, the movement of traffic from the Tangerang and other cities in the west of Jakarta
is facilitated by the Jakarta-Tangerang Toll Road, the Jakarta Inner City Toll Road and the
Jakarta Outer Ring Road Toll. The traffic flow conditions in these roads are already quite
congested. To overcome the congestion on these roads, it is necessary to build alternative
roads with an adequate level of accessibility and mobility. The Balaraja-Semanan toll road is
28
a continuation of the planned 6 inner city toll roads of Jakarta and can be an alternative to
overcome the problem.
The Balaraja-Semanan Toll Road Plan is part of the Jabodetabek Toll Road Network which
stretches 31.9 km. The starting point of the project is the end of the Serpong-Balaraja toll road
which is located at the Balaraja Interchange east of the Tangerang-Merak toll road. From that
point, the road heads north and turns east in the Rajeg area. The road will then end in the
Semanan area.
There will be 6 interchange and 2 junction in this toll road. The interchanges in this toll road
are Pasar Kemis 1 Interchange, Pasar Kemis 2 Interchange, Rajeg 2 Interchange, Sepatan
Interchange, Lebak Wangi Interchange, and Batu Ceper Interchange. The two junctions are
Balaraja Junction and Rajeg 1 junction. Starting from the Lebak Wangi Interchange to Semanan
on/off ramp, this toll road will be an elevated toll road running alongside Cisadane River and
Mookervart River.
The objectives of Balaraja-Semanan Toll Road is to support the development and accessibility
oleh Tangerang and the surrounding area west of Jakarta.
4. Technical Specification
No Facilities Capacity
1 Length 31.9 km
2 Design Speed 80 Km/hr
3 Number of Lane 2x2 (initial stage)
4 Lane Width 3.50 m
5 Outer Shoulder Width 3.00 m
6 Inner Shoulder Width 1.00 m
7 Median Width (including inner 4.50 m
shoulder)
The schedule of AMDAL study has been explained in the feasibility study document and
business plan. Currently, the EIA Terms of Reference (KA-ANDAL) have been issued by the
project preparation agency.
Land Acquisition plan have been made with cost approximately USD 412.84 million.
29
7. Project Cost Structure
The study has indicated that this project needs government support in terms of Land
Acquisition and government guarantee from Indonesia Infrastructure Guarantee Fund (IIGF).
9. Contact Information
30
KAMAL-TELUK NAGA-RAJEG TOLL ROAD
Location : DKI Jakarta and Banten Provinces
Description:
38.6 km Kamal-Teluknaga-Rajeg Toll Road is
located in North Jakarta (DKI Jakarta Province)
and Tangerang Regency (Banten Province).
This toll road is planned as part of the toll road
network system in the Jabodetabek (Jakarta,
Bogor, Depok, Tangerang, Bekasi) area and will
support Pantura strategic area.
Financial Feasibility:
IRR : 10.58%
Government Contracting Agency: NPV : USD 96.44 Million
Indonesia Toll Road Authority (BPJT)
Type of PPP: Estimated Concession Period: 40 years
Unsolicited
Return of Investment:
User Charge
31
Project Digest
2. The Opportunity
Pantura coast reclamation area is expected to support the provision of land for DKI Jakarta
province as a development of a new international scale commercial center and the
development of a water front city area. The toll road is one of the infrastructures prepared to
support the development of North Jakarta area and the development of Pantura strategic area,
32
in order to overcome traffic problems and encourage economic and regional growth. This toll
road is planned as part of the toll road network system in the Jabodetabek (Jakarta, Bogor,
Depok, Tangerang, Bekasi) area.
Kamal-Teluknaga-Rajeg Toll Road (38.6 km) starts from Kamal Muara, Penjaringan sub-
district (DKI Jakarta Province) and ends in Rajeg sub-district (Banten Province), meets the
Semanan-Balaraja toll road plan. This toll road is equipped with 1 junction and 8 interchanges
as follows:
• Junction Sedyatmo;
• Interchange Kosambi;
• Interchange Teluk Naga;
• Interchange Tanjung Pasir;
• Interchange Bandara/Kohod;
• Interchange Surya Bahari;
• Interchange Pakujaya;
• Interchange Mauk; and
• Interchange Rajeg.
Construction is planned to begin in 2019, which consists of 4 stages, and will be fully completed
in 2024 and will operate in 2025.
Business entity shall responsible to perform the toll road project, including financing, land
acquisition, construction, and maintenance.
4. Technical Specification
No Facilities Capacity
1 Length 38.6 km
2 Design Speed 80 Km/hr
3 Number of Lane 2x3 (initial stage)
4 Lane Width 3.50 m
5 Outer Shoulder Width 2.50 m
6 Inner Shoulder Width 1.00 m
7 Median Width (including inner 4.50 m
shoulder)
The schedule of AMDAL study has been explained in the feasibility study document and
business plan.
33
6. Land Acquisition and Resettlement Action Plan
The government shall support the project in terms of ease of permit and licences processing
and also land acquisition. The project also indicated that it needs government guarantee from
Indonesia Infrastructure Guarantee Fund (IIGF).
9. Contact Information
34
PATIMBAN ACCESS TOLL ROAD
Location : West Java Province
Description:
The New Patimban Port development plan
requires accessibility that facilitates direct
access to and from Patimban Port. The port is
planned to be connected with industrial zones,
economic zones, urban areas and the
surrounding rural areas. Patimban access toll
road will connect Patimban Port with Cikopo -
Palimanan Toll Road Section. This toll road will
have a length of 37.7 km with 2 interchange
locations and 1 interchange junction location.
35
Project Digest
2. The Opportunity
The construction of Patimban Port replaces the Cilamaya Port project in the Karawang regency
which was canceled due to its location intersects with the oil and gas pipeline. The stipulation
is contained in Presidential Regulation No. 47 of 2016 concerning the Establishment of
Patimban Port in Subang Regency, West Java, as a National Strategic Project (PSN).
To support the operation of Patimban Port, government also plans to integrate the port with
the national road network especially through the Pantura road. Therefore, a proposal for the
construction of Patimban Access Toll Road is needed for easy access to and from the Port.
36
2.2. Project Description
Patimban Access Toll Road is a toll road section initiated by a consortium of PT Jasa Marga
(Persero), PT Surya Semesta Internusa, PT Daya Mulia Turangga and PT Jasa Sarana. The toll
road section is planned to be an alternative for connecting the traffic flow from and to Patimban
Port. The planned toll road is located in Subang Regency, West Java Province which is located
in the low hills and lowlands.
Furthermore, the plan to construct Patimban Access Toll Road sections will not only provide
proper access for vehicles to and from Patimban Port to its hinterland areas, but also provide
alternatives for vehicles originating from:
The objectives of Patimban Access Toll Road is to support the operation of Patimban Port by
increasing road capacity and connectivity between the port and surrounding hinterland.
4. Technical Specification
No Facilities Capacity
1 Length 37.7 km
2 Design Speed 80 Km/hr
3 Number of Lane 2x3 (initial stage)
4 Lane Width 3.60 m
5 Outer Shoulder Width 3.00 m
6 Inner Shoulder Width 1.50 m
7 Median Width (including inner 3.8 m
shoulder)
The schedule of AMDAL study has been explained in the feasibility study document and
business plan. Currently, the EIA Terms of Reference (KA-ANDAL) have been issued by the
project preparation agency.
Land Acquisition plan have been made with cost approximately USD 52.4 million. It is proposed
to be covered by the GCA.
37
7. Project Cost Structure
Government support will be needed to support the land acquisition process. In addition,
guarantee from Indonesia Infrastructure Guarantee Fund (IIGF) will also help the project to be
more bankable.
9. Contact Information
38
GEDEBAGE – TASIKMALAYA – CILACAP TOLL ROAD
Location : West Java and Central Java Provinces
Description:
The project is to construct 206.65 km toll road
of Gedebage-Tasikmalaya-Cilacap which is
expected to overcome traffic problems and
encourage economic and regional growth.
This toll road is equipped with 1 juction and 10
interchanges.
Financial Feasibility:
IRR : 12.00%
NPV : USD 139.28 Million
Government Contracting Agency:
Indonesia Toll Road Authority (BPJT) Estimated Concession Period: 40 years
Type of PPP:
Unsolicited
Return of Investment:
User Charge
39
Project Digest
2. The Opportunity
40
2.2. Project Description
Based on analysis, in 2023 the volume of traffic is 16,060 vehicles / day. It is estimated that it
will increase to 26,480 vehicles / day in 2025 and reach 108,137 in 2060. This toll road is
equipped with 1 juction and 10 interchanges, which will be divided into two stages of
construction:
- To increase the development of areas that are passed by toll roads; and
Business entity shall responsible to perform the toll road project, including financing,
construction, operation, and maintenance during the concession period.
4. Technical Specification
No Facilities Capacity
1 Length 206.65 km
2 Design Speed 80-100 Km/hr
3 Number of Lane
4 Lane Width 3.60 m
5 Outer Shoulder Width 3.00 m
6 Inner Shoulder Width 1.50 m
7 Median Width (including inner 5.50 m
shoulder)
41
5. Environmental Impact Assessment (EIA/AMDAL) Findings
Based on the planned schedule, AMDAL study has been conducted during Q4 of 2018 until Q2
of 2019
Based on the planned schedule, Land Acquisition and Resettlement Action Plan has been
done during Q4 of 2017 until Q3 of 2018.
The feasibility study of the project indicates the need for government supports in terms of
land acquisition. Government guarantee through the Indonesia Infrastructure Guarantee Fund
(IIGF) will also be necessary.
9. Contact Information
42
BOGOR – SERPONG (VIA PARUNG) TOLL ROAD
Location : West Java and Banten Provinces
Description:
The project is to construct ±31.117 km of Bogor-
Serpong toll road which is expected to
overcome traffic problems and encourage
economic and regional growth. This toll road is
equipped with five interchanges and two
junctions.
Financial Feasibility:
FIRR : 12.38%
NPV : USD 78.90 Million
Government Contracting Agency:
Indonesia Toll Road Authority (BPJT) Estimated Concession Period: 40 years
Type of PPP:
Unsolicited
Return of Investment:
User Charge
43
Project Digest
2. The Opportunity
44
overcrowded and has insufficient road width to accommodate the existing traffic. Therefore, a
toll road between Bogor and Serpong is expected to be a solution to overcome existing traffic
congestion.
Bogor-Serpong (via Parung) Toll Road (31.1 km) will connect Selabenda Junction (Bogor) and
Serpong Junction (Serpong) through Parung. There are five interchanges and two junctions.
The distance between intersections is ± 5 km.
The objectives of Bogor-Serpong (via Parung) Toll Road is to overcome existing traffic
congestion between Bogor and Serpong.
Build-Operate-Transfer (BOT)
Business entity shall responsible to perform the toll road project, including financing,
construction, operating, and maintenance.
4. Technical Specification
Planning standards use all regulations and specifications that apply in Indonesia, such as
regulations issued by The Directorate General of Highways, SNI, and other regulation (AASHTO,
Japanese code and specification, British Standard, etc). The design speed of Bogor-Serpong
(via Parung) Toll Road is 100 km/hour and the technical specifications as follows:
No Facilities Capacity
1 Length ±31.117 km
2 Design Speed 100 Km/hr
3 Number of Lanes per Direction 3
4 Lane Width 3.60 m
5 Shoulder Width
Outside 3.00 m
Median side 1.50 m
6 Median Width 2.50 m
The feasibility study of the project indicates the need for Environmental Impact Assessment
(EIA/AMDAL) to be prepared later.
The study indicated Land Acquisition and Resettlement Action Plan needs for land acquisition
of 227.95 ha.
45
7. Project Cost Structure
The feasibility study of the project indicates the need for government supports in terms of
land acquisition. Government guarantee also needed from Indonesia Infrastructure
Guarantee Fund (IIGF).
9. Contact Information
46
CIKUNIR-KARAWACI INNER CITY ELEVATED TOLL ROAD
Location : DKI Jakarta and Banten Provinces
Description:
The project is to construct ±40 km of Cikunir-
Tomang-Karawaci Inner City Elevated toll road
with PPP scheme. The proposed toll road plan
will be above the existing toll road section,
which the start point located in Cikunir (at the
junction between JORR and the Jakarta-
Cikampek toll road) and the end point located
after the Alam Sutera intersection. Business
entity shall responsible to perform the toll road
project with BOT scheme.
47
Project Digest
2. The Opportunity
The development of Jabodetabek Area (Jakarta, Bogor, Tangerang, Bekasi) has grown rapidly,
especially in the east-west corridor, starting from Bekasi District, Bekasi City, DKI Jakarta,
Tangerang City and Tangerang District, which require a high level of accessibility. At present
the traffic flow on the Jakarta-Tangerang Toll Road, Jakarta Inner Ring Road and Jakarta Outer
Ring Road is very congested (already saturated) with V / C Ratio already greater than 0.8. In
48
addition, the construction of the Jakarta-Cikampek Elevated Toll Road is currently underway,
one of which ends in Cikunir.
Cikunir-Karawaci Inner City Elevated Toll Road Section will be an additional alternative to the
existing Toll Road section in Jakarta. This toll road will be above the existing Toll Road,
therefore it can improve the performance of the road network in Jabodetabek and it can
overcome congestion problem.
Cikunir-Karawaci Toll Road Section (± 40 km) is located in Banten Province (Tangerang City
and Tangerang District), DKI Jakarta Province, and Banten Province (Bekasi City). The
proposed toll road plan will be above the existing toll road section. The starting point of the
project, located in Cikunir (at the junction between JORR and the Jakarta-Cikampek toll road),
which is the beginning of the Jakarta - Cikampek elevated toll road. The end of the project is
located after the Alam Sutera intersection. Location of main on/off ramp points as follows:
• East Pondok Gede;
• Cawang Junction;
• Pancoran;
• Semanggi;
• Palmerah;
• Tomang;
• Meruya; and
• Kembangan.
The objectives of Cikunir-Karawaci Inner City Elevated Toll Road is to improve the performance
of the road network in Jabodetabek and to overcome traffic congestion in the western area of
Jakarta.
Build-Operate-Transfer (BOT)
Business entity shall responsible to perform the toll road project, including financing,
construction, operating, and maintenance.
4. Technical Specification
Planning standards use all regulations and specifications that apply in Indonesia, such as
regulations issued by The Directorate General of Highways, SNI, and other regulation.
No Facilities Capacity
1 Length ± 40km
2 Lane number 2+2
3 Design Speed
Main road 80 Km/hr
Ramp (toll-to-toll) 40-60 Km/hr
49
No Facilities Capacity
Ramp (toll-to-non toll) 40-60 Km/hr
4 Lane Width 3.50 m
5 Outer Shoulder Width 2.00 m
6 Inner Shoulder Width 0.50 m
7 Median Width
Median concrete barrier 0.80 m
Median width including inner 1.80 m
shoulder
The feasibility study of the project indicates the need for Environmental Impact Assessment
(EIA/AMDAL) to be prepared later.
The study indicated Land Acquisition and Resettlement Action Plan needs for land acquisition
of 82,204 m2.
The government support is identified for land acquisition. The government guarantee is
needed from Indonesia Infrastrucutre Guarantee Fund (IIGF)
9. Contact Information
50
CIKUNIR-ULUJAMI JAKARTA OUTER RING ROAD (JORR) ELEVATED TOLL ROAD
Location : DKI Jakarta and West Java Provinces
Description:
The project is to construct ± 21.5 km of The
Cikunir-Ulujami Jakarta Outer Ring Road
(JORR) Elevated Toll Road with PPP scheme.
The starting point located in after Ulujami
Junction and the end point is before Jati Asih
Junction.
Financial Feasibility:
Government Contracting Agency: FIRR : 12.49 %
Indonesia Toll Road Authority (BPJT) NPV : USD 536.27 Million
Type of PPP:
Unsolicited Estimated Concession Period: 45 years
Return of Investment:
User Charge
51
Project Digest
2. The Opportunity
The role of the toll road network is important for Indonesia's economic development and for
the mobility of Jabodetabek (Jakarta, Bogor, Tangerang, Bekasi) residents. The Jakarta Outer
Ring Road (JORR) and Jakarta Inner Ring Road (JIUT) which play a very important role to toll
road network in Jakarta, currently overcapacity and have serious traffic congestion problem.
To overcome these problems, JORR elevated toll road development is planned with PPP
scheme.
JORR elevated toll road (± 21.5 km) is located in DKI Jakarta (South Jakarta dan East Jakarta)
and West Java (Bekasi) Province. The beginning point of this elevated toll road is after Ulujami
Junction of JORR (near Veteran toll booth) and the end point is before Jati Asih Junction of
JORR.
52
3. Business Entity’s Scope of Work
Build-Operate-Transfer (BOT)
Business entity shall responsible to perform the toll road project, including financing,
construction, operating, and maintenance.
4. Technical Specification
Planning standards use all regulations and specifications that apply in Indonesia, such as
regulations issued by The Directorate General of Highways, SNI, and other regulation.
No Facilities Capacity
1 Length ± 21.5 km
2 Lane number 2 x 2 lanes
3 Design Speed
Main road 80 Km/hr
Ramp 40-60 Km/hr
Terminal Ramp 40-60 Km/hr
4 Width of the traffic lane 2 x 7 m (@3.5 m)
5 Shoulder Width with pavement 2,0 m
6 Shoulder Width without 1.0 m (0.5 m for structure)
pavement
7 Median Width 1.0 m
8 Median path without borders 0.5 m
9 Slope 2.0%
10 Vertical clearance height 5.1 m
The study of the project has identified the Framework of Environmental Impact Assessment
(EIA/KA-ANDAL) needs.
The total land requirement for this project is 43.8 ha including government-owned land that
does not require land acquisition (41.8 ha) and land that requires land acquisition (2,04 ha). The
study indicates the implementation of land acquisition will be carried out by the consortium.
53
8. Government Support and Guarantee
9. Contact Information
54
MULTI LANE FREE FLOW (MLFF) TOLL ROAD TRANSACTION SYSTEM
Location : National
Description:
The project is to establish new toll collection
system, which replaces the existing manual
toll collection method. The project scope is
Design, Build, Finance, Operate, and Transfer
(DBFOT). The proposed system has the
technical requirement of MLFF GNSS toll
collection.
55
Project Digest
2. The Opportunity
The time spent at highway toll plazas causes significant losses to the GDP of Indonesia. The
Multilane Free Flow (MLFF) Toll Transaction System is expected to overcome the time loss
caused by delays at toll plazas with PPP scheme of 10 years concessions period. The new
Multilane Free Flow (MLFF) system will be much easier to use, every customer system
function will be available online, creates a non-stopping road usage experience. The system
will have a high social utility (eg. Less traffic congestions) therefore the users can feel and
see the need of this new system.
56
2.2. Project Description
The Multilane Free Flow (MLFF) Toll Transaction System is to establish new toll collection
system, which replaces the existing manual toll collection method. The project scope is Design,
Build, Finance, Operate, and Transfer (DBFOT). Global Navigation Satellite System (GNSS)
which uses GSM technology for communication, is purposed to be used in Indonesia for tolling
purposes as the foundation to the implementation of Cooperative Intelligent Transportation
System (C-ITS) best practices. The system covers the entire toll road network through the
country with total length of network covered of 6,075 km (untuk end of 2025). It will be operated
in two phases, i.e. Single Lane Free Flow (SLFF) Radio-frequency Identification (RFID) and
MLFF GNSS.
The objectives of The Multilane Free Flow (MLFF) Toll Transaction System is to overcome the
time loss caused by delays at toll plazas.
Business entity shall responsible to perform the project, including designing, construction,
financing, and operation.
4. Technical Specification
The proposed system has the technical requirements of MLFF GNSS toll collection. The
technical specifications as follows:
57
No Service Item Important Key Expected Level
Performance
Indicators (KPIs)
4 Settlement with Delivery of settlement Daily on-line
beneficiaries of data BLU and Toll
collected toll Road Operator
The success rate of 99.90%
settlement into Toll
Road Operator
accounts is according
to the portion each
Toll Road Operator.
Delegation of 1 x 24 hours
settlement funds to
Toll Road Operator
accounts
Settlement Daily banking days
5 Monitoring Monitoring tools On-line reporting
6 Network Implementing toll Max 5 working days
Extension collection on any new
section in MLFF
system
7 Tariff Flexibility to change User-friendly
Management tariffs
Time needed for Daily on-line
change tariffs
Enforcement related KPIs
1 Vehicle Availability 99.0%
Identification of License plate number 98.0%
Road Side Data recognition efficiency
Collection Vehicle category 98.0%
System recognition efficiency
Evidential records 98.0%
availability
2 Classification of Time needed for On-line
Road Usage differential making
(legal/violator) Send transaction On-line
violation reports
(blacklist)
Number of inaccurate 0.01%
determinations
3 Sanctioning Sanctioning efficiency 99%
4 Network Implementing toll Max 5 working days
Extension enforcement on any
new section in MLFF
system
Customer Service related KPIs
1 Online Available services 7 x 24 hours
customer
service
2 Call Centre Availability 7 x 24 hours
58
No Service Item Important Key Expected Level
Performance
Indicators (KPIs)
Available services 7 x 24 hours
Managed calls 98.0%
Lost Calls 2.0%
Waiting time Answered by IVR within 5
seconds of the call being
received at the Client Centre
3 Web site Availability 7 x 24 hours
Available services 99.0%
The study did not indicate any Land Acquisition is needed for the project.
The suggested potential support for Multilane Free Flow (MLFF) Toll Transaction System as
follows:
• Amendments of TRO contracts need to be managed by ITRA or the ministry;
• The availability of the guarantee fund in case of lower than 12.5% IRR; and
• Fasten approval from the central for Initiative Business Entity to manage and handle
virtual money.
The government guarantee can be through the Indonesia Infrastructure Guarantee Fund
(IIGF).
59
9. Contact Information
60
SEMARANG HARBOUR TOLL ROAD
Location : Central Java Province
Description:
The project is to construct ± 20.86 km of
Semarang Harbour toll road which connects
the Semarang - Batang Toll Road (SBTR) and
Semarang-Demak Toll Road to complete the
Ring Road around the City of Semarang. This
toll road will be integrated with the sea wall
and retention pond in the city of Semarang. The
return of investment of the sea wall comes
from the development of the reclamation area
given to the winner of the auction while the
retention pond will be financed by government
of Semarang city.
Estimated Project Cost: USD 836.81 Million
Government Contracting Agency:
Indonesia Toll Road Authority (BPJT) Financial Feasibility:
Type of PPP: IRR : 11.10%
Unsolicited NPV : USD 12.20 Million
Return of Investment: Estimated Concession Period: 50 years
User Charge
61
Project Digest
2. The Opportunity
Economic growth in the Semarang area had an impact on regional development and travel
demand growth in recent years. The road network in the Semarang region also shows a
declining performance. In addition, the existence of the Trans Java toll road is will also
increase the traffic load on the road network significantly. This condition indicates the need to
develop a new road network to respond to the high growth in travel demand in the Semarang
and surrounding areas. Therefore, the Semarang Harbour Toll Road Development Plan has
been prepared. This toll road is planned to be circular on the northern side of Semarang City,
from Kaliwungu, Ahmad Yani Airport, and Tanjung Mas Port.
Semarang Harbour Toll Road will connect the Semarang - Batang Toll Road (SBTR) to complete
the Ring Road around the City of Semarang. The Semarang Harbour Toll Road is projected to
benefit the Semarang City and the surrounding area, because this toll road network is
connected to several vital areas around Semarang, especially Kendal Industrial Area (KIK),
62
Ahmad Yani Airport, Tanjung Mas Port, and Semarang Toll Road Section A, B, C. This toll road
will also be integrated with the sea wall and retention pond in the city of Semarang.
The Semarang Harbour Toll Road Section starts from Kaliwungu Area of Kendal Regency which
connecting the Semarang Batang Toll Road and the Semarang Harbour Toll Road, then ends at
Kaligawe of Semarang which connecting Semarang Demak Toll Road and Semarang Harbour
Toll Road.
The length of the Semarang Harbour Toll Road is 20.86 km which is divided into:
This project is proposed to use a PPP scheme with user charge. The initial operating tariff
proposed is Rp. 1,700 / km (Group 1) with a closed operating system. The return of investment
of the sea wall comes from the development of the reclamation area given to the tender winner
while the retention pond will be financed by Government of Semarang City
- The objectives of Semarang Harbour Toll Road is to overcome the current traffic jams in
the road network in the Semarang region
- Integrated with sea wall as a solution of abrasion in the north coast region
- Provision of raw water for the Semarang City
The scope of work for the business entity will be Design-Build-Finance-Operate – Maintain
and Transfer (D-B-F-O-M-T).
4. Technical Specification
A business entity is required to meet the minimum toll road service standard as stipulated in
Minister of Public Works Regulation No. 16/PRT/M /2014 concerning Toll Road Minimum Service
Standards. Minimum toll service standards include the following service substances: toll road
conditions, average travel speed, accessibility, mobility, safety, rescue unit and service
assistance, environment, and rest area and rest area and service.
The technical specifications for toll roads will refer to all regulations and specifications apply
in Indonesia, such as regulations and codes issued by the Directorate General of Highways,
Indonesian National Standard (SNI), and other regulations. Some technical specifications for
the main road including:
No Facilities Capacity
1 Length 20.86 km
2 Design Speed 80 Km/hr
3 Number of Lane 2 x2 (initial stage)
3 x3 (final stage)
63
No Facilities Capacity
4 Lane Width 3.6 m
5 Outside Shoulder Width 3.0 m
6 Inner side Shoulder Width 1.5 m
7 Design Speed 80 Km/hr
8 Median Width (include inner 5.5 m
side shoulder)
9 Cross slope 2%
10 Shoulder slope 2%
This study indicates the need for Environmental Impact Assessment (EIA/AMDAL). Based on
the plan schedule, the preparation of EIA study conducted in 2019.
For the unsolicited toll road project, the land acquisition and resettlement action financed by
Business Entity which will be calculated as part of investment. Based on the plan schedule,
the preparation of Land Acquisition and Resettlement Action Plan conducted in 2018-2019.
This project does not require Government Support either in the form of fiscal contributions or
other forms. This project will be proposed to obtain Government Guarantee by Indonesia
Infrastructure Guarantee Fund (IIGF).
9. Contact Information
64
SOUTH SENTUL – WEST KARAWANG TOLL ROAD
Location : West Java Province
Description:
The project is to construct ± 61.5 km of The
South Sentul – West Karawang Toll Road which
connecting Sentul Junction and Karawang
Junction. At the South Sentul – West Karawang
Toll Road there are 3 junctions that connect to
the Bogor Ring Road Toll Road, the Jakarta –
South Cikampek Toll Road, and the existing
Jakarta - Cikampek Toll Road.
Financial Feasibility:
Government Contracting Agency:
IRR : 12.08%
Indonesia Toll Road Authority (BPJT)
NPV : USD 104.79 Million
Type of PPP:
Unsolicited Estimated Concession Period: 40 years
Return of Investment:
User Charge
65
Project Digest
2. The Opportunity
Infrastructure developments are one of the keys to increasing Indonesia's economic growth.
Currently, Government of Indonesia is accelerating the infrastructure development in various
sectors, including the toll roads. To overcome the limitations of the budget, the government
implemented various policies to attract the private sector to invest in the toll road sector.
66
The government plans to construct 5,405 km of toll roads as part of the road network system.
A total of 820 km of toll roads is operational and 1,016 km have Toll Road Concession
Agreements (Perjanjian Pengusahaan Jalan Tol/PPJT). Therefore, the initiative of Business
Entities will be very helpful to accelerate the construction of toll roads. Thus, the target of
completing 1,000 km of new toll roads planned by the Government in the next five years can
be realized.
At present, the existing Sentul - Karawang road has insufficient road width to accommodate
the existing traffic. Especially in the area around Karawang there are many industrial areas.
The Sentul-Karawang Toll Roads Construction Plan is expected to be a solution to overcome
the existing traffic demand.
The South Sentul – West Karawang Toll Road construction project crosses 3 (three) regency
areas, i.e. Bogor Regency, Bekasi Regency, and Karawang Regency. The total length of the
South Sentul - West Karawang Toll Road is 61.5 kilometers, connecting Sentul Junction and
Karawang Junction. At the South Sentul - Karawang Toll Road there are 3 (three) junctions
that connect to the Bogor Ring Road Toll Road, the Jakarta – South Cikampek Toll Road, and
the existing Jakarta - Cikampek Toll Road. Overall, there are 5 interchanges on this toll road
section. The average speed on the non-toll road is 21.10 km/hour. The design speed of the toll
road is 100 km/hour.
The objectives of South Sentul – West Karawang toll road is to overcome the current traffic
jams in South Sentul – Karawang area, especially area around Karawang.
The scope of work for the business entity will be Build-Operate-Transfer (B-O-T). The following
are private partner’s list of responsibilities:
1) Designing a Detailed Engineering Design (DED) of the South Sentul – West Karawang Toll
Road based on the basic design;
3) Operation and Maintenance of the South Sentul – West Karawang Toll Road during the
concession period, after the construction phase has been completed; and
4) Sign and commit in the Guarantee Agreement with Indonesia Infrastructure Guarantee
Fund (IIGF).
4. Technical Specification
The technical specifications for toll roads will refer to all regulations and specifications apply
in Indonesia, such as regulations and codes issued by the Directorate General of Highways,
Indonesian National Standard (SNI), and other regulations AASHTO, Japanese Code and
Specifications, British Standard, etc.). Some technical specifications for the main road
including:
67
No Facilities Capacity
1 Length 61.5 km
2 Right-of-Way (ROW) typical 30 m
3 Design Speed 100 Km/hr
4 Number of Lane 2 x (2x3.6) m
5 Lane Width 3.6 m
6 Outside Shoulder Width 2 x 3.0 m
7 Inner side Shoulder Width 2 x 1.5 m
8 Median Width 0.8 m
9 Cross slope 2%
10 Shoulder slope 2%
The study indicates the need for Environmental Impact Assessment (EIA/AMDAL).
The land requirement for the South Sentul - West Karawang Toll Road is ± 355.24 Ha. Land
acquisition is purposed to be done in Q1 2022.
The feasibility study of the project indicates no need for government supports but will need to
be guaranteed by Indonesia Infrastructure Guarantee Fund (IIGF).
9. Contact Information
68
READY TO OFFER
PROJECTS
Drinking Water:
1. Sarbagikung Regional Water
Supply System
2. Karian-Serpong Regional
Water Supply System
SARBAGIKUNG REGIONAL WATER SUPPLY SYSTEM
Location : Bali Province
Description:
The Sarbagikung Water Supply System project
built with capacity 2,300 lps for Increasing the
capacity and quality of drinking water services
in the Denpasar city, Badung regency, Gianyar
regency, and Klungkung regency.
Financial Feasibility:
IRR : 11.63 %
NPV : USD 30.20 Million
69
Project Digest
2. The Opportunity
The tourism industry and the rapid population growth in the southern area of bali province
resulted in the crisis of the clean water. That also impact many aspects such as:
• Decrease of quantity, quality and access to clean water, in particular to meet basic
needs of the community
• The disparity the provision of the water between the tourism sector and domestic
tourists, that would cause it appears that the conflict as well as social and
environmental problems in the short term and long
The Sarbagikung Water Supply System project will take place in four regency/city in Bali:
a. Denpasar city
b. Badung regency
c. Gianyar regency
d. Klungkung regency.
70
2.3. Project Objectives
Increase the capacity and quality of drinking water services in the Denpasar city, Badung
regency, Gianyar regency, and Klungkung regency.
The private partner responsibilities are Design, Build, Finance, Operate and Maintain the facility
during concession period.
4. Technical Specification
The technical specification for Sarbagikung Water Supply System should comply with SNI
6774-2008 and Permen PU No.27/PRT/M/2016
The Sarbagikung Water Supply System Project is required to provide AMDAL documents. The
documents will be prepared by the Government Contracting Agency.
Land Acquisition for the project and any consequential resettlement will be assisted by the
GCA.
This project has indicated that it needs government guarantee through Indonesia
Infrastrucutre Guarantee Fund (IIGF).
9. Contact Information
71
KARIAN-SERPONG REGIONAL WATER SUPPLY SYSTEM
Location: Lebak, Banten Province
Description:
Karian-Serpong Regional Water Supply
System project is developed to accelerate the
expansion of piped water supply for DKI
Jakarta, Tangerang City, and South Tangerang
where the bulk water will be sourced from the
Karian Dam in Banten Province.
Financial Feasibility:
Government Contracting Agency: IRR : 12.30%
Minister of Public Works and Housing NPV : USD 58.74 Million
Type of PPP:
Unsolicited Estimated Concession Period: 33 years (incl.
Return of Investment: construction)
User Charge
72
Project Digest
Karian-Serpong Water Supply System will serve piped water for DKI Jakarta, Tangerang City,
and South Tangerang from Karian Dam.
2. The Opportunity
The development of Karian-Serpong Water Supply System is planned to provide bulk water
from Karian Dam to DKI Jakarta, Tangerang City, and South Tangerang. To support the
acceleration of the expansion area of water supply as one of the target from National Medium-
Term Development Plan 2020-2024, an external investment is needed to support the financing.
Karian-Serpong Water Supply System is developed to bridge the a gap between the needs of
the piped water supply system in the community and the availability of clean water supply
provided by PDAM in West Jakarta, Tangerang, City, and South Tangerang. Since the current
condition of drinking water supply service is very low, better bulk water supply will help the
improvement of the drinking water supply service level. This project will provide the PDAM in
those three region with bulk water from Karian Dam.
73
2.3. Project Objectives
The objective of Karian-Serpong Water Supply System is to supply bulk water for PDAM in
West Jakarta, Tangerang, City, and South Tangerang service area.
The scope of work for the business entity will be build- operate-transfer.
4. Technical Specification
74
Description Criteria Notes
c. NRW (%) < 1%
d. Average demand, Qavg (Lps) (b)/(1-c)
e. Maximum Day, Qmax (Lps) Qmax = 1.15 Qavg
f. Peak Demand, Qpeak (Lps) Qpeak = 1.75 Qavg
Pressure
a. Minimum 0.50 ~ 1.00 atm On Critical Point
b. Maximum 6.00 ~ 8.00 atm PVC/ACP
10.00 atm Steel Pipe/DCIP
12.40 atm HDPE PE-100
9.00 atm HDPE PE-80
Additional Equipment
a. Valve Type Gate/Butterfly
b. Pressure release tank (air chamber) Over 70 m elevation
c. River Crossing Under/over Steel Pipe
d. Thrust block Bend, Tee, Valve, etc. Concrete K-175
Standard
a. Indonesia SNI
b. International ISO, JIS, AWWA, ASTM, ANSI,
DIN and BS
The study of AMDAL will be conducted after the Land Acquisition and Resettlement Action Plan
is finished.
Land Acquisition and Resettlement Action Plan is developed by Directorate General of Human
Settlement and will be completed on Desember 2020.
75
7. Project Cost Structure
The study has indicated that this project does not need government support but requires
government guarantee from Indonesia Infrastructure Guarantee Fund (IIGF).
9. Contact Information
Email : [email protected]
76
UNDER
PREPARATION
PROJECTS
Transportation:
1. Construction of Singkawang
Airport
2. Development of Baubau Port
3. Development of Anggrek
Port
4. Semarang City Light Rail
Transit (LRT)
5. Development of Motor
Vehicle Weighing
Implementation Unit
(UPPKB) in Java and
Sumatera
CONSTRUCTION OF SINGKAWANG AIRPORT
Location : Singkawang, West Kalimantan Province
Description:
The Singkawang Airport Development Project
was included as one of the airport projects
planned to be developed under the PPP
Scheme several years ago. With new
development, the Singkawang Airport is
Singkawang Airport planned to have 2.500 x 45 m runway with
Masterplan
12.500 m2 area of domestic passenger terminal.
77
Project Digest
2. The Opportunity
Singkawang City is a city in West Kalimantan Province. It is approximately 153 km from the
Provincial Capital, Pontianak City. Singkawang City which is well-known with Chinese culture
has several events that are very famous and attract many tourists. Singkawang City also has
Simping Island in Sedau Beach with the title of the smallest island in the world that has been
recognized by the United Nations (UN).
With the variety of attractions that are now starting to interest domestic and foreign tourists
in the city, will automatically also have an impact on aspects of the availability of transportation
78
facilities and infrastructure in the City of Singkawang. However, for now access from the City
of Singkawang to the nearest capital or airport namely Supadio International Airport ("PNK")
can only be reached by land. Road access that is traversed has many connecting bridges, which
if there is damage there will be economic paralysis in Singkawang City and surrounding areas.
Therefore alternative modes of transportation are needed, such as air transportation to
support economic and tourism activities in Singkawang City.
The development of the Singkawang Airport will consist of two sides of Airport development:
Air Side and Land Side. Air Side developments includes: Runway, Runway Strip, Runway End
Safety Area (RESA), Taxiway, Apron, Airside Service Road, Airside Perimeter Road, and Airside
Operation Road. Land side developments include: Passenger Terminal, Passenger Parking
Area, Conning Tower, Operation Office, Powerhouse, Security Office, Cargo Terminal and other
facilities.
By using the forecast results, the construction of the Project facilities will be based on the
most actual movement projection annually. From the assessing the number of passengers,
the number of passengers during peak hours, and the largest type of aircraft serving
passengers, the level of aircraft occupancy (load factor) can be estimated. Upon review of the
previous Project development plan needs, the Project development scenario recommended
that Phase I development is planned for 2021 - 2022 (overall facilities), and Phase II for 2029
(Land Side development) by following the results of the most actual forecasts of airport
movements and demand in Singkawang City.
The purpose of Singkawang Airport is to improve accessibility and mobilization of goods and
people to and from Singkawang. Therefore, economic activity and especially tourism sector
will benefit and flourish.
4. Technical Specification
No Facilities Capacity
1 Aerodrome Reference Code 4C
2 Runway Dimension 2500 x 45 m2
Runway Strip Dimension 2740 x 45 m2
Runway Strength 60 F/C/X/T
Runway End Safety Area (RESA) 90 x 90 (Threshold 16); 90x90 (Threshold 34)
Taxiway 2
Apron Dimension 220 x 85
Total Parking Stand 5
Facilities Domestic Passenger Terminal
79
No Facilities Capacity
Hanggar
Cargo Terminal
Parking Area
Administration Office
Workshop/Maintenance Area
Security Office
Clinic
Waste Management Plant
Sewerage Treatment Plant
Powerhouse
Cafetaria
Quarantine Area
Hotel and Garden
Religious Facilities
The City Government of Singkawang is working to fulfill its responsibility in preparing the
AMDAL Document for the Project's plan to accommodate the construction of Projects that have
runway specifications above 1,200 m. This will, in addition the extent of the area affected by
operational and safety area of the airport, certainly requires the handling of the potentially
crucial impacts of environmental management during the construction and operation stages
of the Project. The mandatory AMDAL activities are regulated in LH Regulation 5/2012
concerning Types of Business Plans and / or activities that are required to have an
Environmental Impact Analysis (AMDAL).
There is a land requirement of 151.45 ha with a fair value of replacement of IDR 13,754,408,056
sourced from the Singkawang City Government's Budget (APBD) for Fiscal Year 2019, therefore
all assets that have been built through APBD investments must be donated / handed over to
the Directorate General of Air Transport, the Ministry of Transportation to be managed in
accordance with the laws and regulations that are applies to the KSPI scheme through the use
of BMN/D (Government Owned Asset) in the form of land.
80
8. Government Support and Guarantee
2. Construction Support
3. Tax Incentive
In terms of project guarantee by IIGF, the indicative risk that needs to be guaranteed are:
3. Political Risk
4. Termination Risk
9. Contact Information
Email : [email protected]
Email : [email protected]
81
DEVELOPMENT OF BAUBAU PORT
Location: Baubau, Southeast Sulawesi Province
Description:
The Murhum Baubau Port needs to be developed to
meet the increasing demand and to support long-
term programs of Baubau Regional Government
which aims to make the city as the gateway of
economy and tourism in Southeast Sulawesi. This
port has the most rapid economic activities
compared to the other two ports in the city of
Baubau.
Financial Feasibility:
IRR : Under Calculation
Government Contracting Agency: NPV : Under Calculation
Minister of Transportation delegated to
Director General of Sea Transportation Estimated Concession Period: 30 years
Type of PPP:
Solicited
Return of Investment:
User Charge
82
Project Digest
2. The Opportunity
Baubau Seaport is located in Wolio District, Baubau City, Southeast Sulawesi Province. This
port is one of the strategic transportation nodes in the Eastern Indonesia region. Due to this
geographical position, Baubau Seaport is in the line of sea transportation movement from
western regions of Indonesia such as Jakarta, Surabaya and the central region like Makassar
to eastern part of Indonesia such as Maluku, North Maluku, Central Sulawesi and North
Sulawesi. Baubau Port is also a gateway for maritime transport for Southeast Sulawesi
Province where most of the passenger and goods movement transit at this port.
Stated in Baubau development roadmap, the Port of Baubau will be further developed to
fulfill the needs of better service to support long term plan of making Baubau the gateway for
economic and tourism area in Southeast Sulawesi. In order to achieve that, facilities of
Baubau Port will need to be upgraded periodically to sustain the demand. The upgrade will
include land reclamation, commercial area development, and port terminal development.
83
2.2. Project Description
4. Technical Specification
a. Container Yard
b. Container Freight Station
c. Cargo Warehouse
d. Open Storage
e. Parking Area
f. Passenger Terminal
g. Parking Area
Land acquisition is needed for the addition of gateway and access road to multipurpose
terminal in order to ease the circulation of cargo and container movements.
84
7. Project Cost Structure
Government support and government guarantee will be determined after completing of FBC
9. Contact Information
Phone :-
Email : [email protected]
85
DEVELOPMENT OF ANGGREK PORT
Location : North Gorontalo Province
Description:
Anggrek Port as a goods gateway and a region
economic driver needs to be supported by the
development of the hinterland area including its
accessibility. Trading activities and distribution of
goods especially in the North Gorontalo depend on
this port. Furthermore, this port is non-commercial
port and operated under the Directorate of Sea
Transportation of the Ministry of Transportation.
Financial Feasibility:
IRR : 13.47 %
Government Contracting Agency: NPV : USD 31.73 Million
Minister of Transportation delegated to
Director General of Sea Transportation Estimated Concession Period: 30 years
Type of PPP:
Solicited
Return of Investment:
User Charge
86
Project Digest
2. The Opportunity
Gorontalo is one of developing areas in Indonesia which still need infrastructure development
support. Main infrastructure to support the development of the Gorontalo is the development
of ports. Several ports built in Gorontalo play important role in enhancing the regional
economic, thereby need to be optimized. One of them is Anggrek Port located in North
Gorontalo Regency. Thus, trading activities and distribution of goods especially in the North
Gorontalo and its surroundings, depend on this port.
The basic and supporting facilities at this port are sufficient, but seeing the trends in
development, including the trend of market demand and the development of the hinterland
area, the infrastructure of Anggrek Port needs to be developed. The development of Anggrek
Port is based on port development planning established through the Port Master Plan. The
intended planning is determined by taking into account related various aspects both from the
technical and non-technical aspects which represent the long-term development needs of
Anggrek Port.
Considering the potential of Anggrek Port as a trade and distribution of goods gateway and
also as a region economic driver, it needs to be supported by the development of the hinterland
87
area including accessibility around it. The intended development is not only the responsibility
of the Government, but also the role of the private sector or business entity is very necessary
to accelerate the development. Especially for Anggrek Port, through involvement of the private
sector or business entities, value for money of this port can be increased to provide great
benefits to the economy of its surrounding community and especially Gorontalo Province.
The scope of work for Anggrek Port Development consist of constructing, providing,
operating and maintaining facilities:
4. Technical Specification
a. Container Yard
b. Reefer Container
c. Container Freight Station
d. Cargo Warehouse
e. Open Storage
f. Cold Storage
g. Parking Area
88
6. Land Acquisition and Resettlement Action Plan
Land acquisition and reclamation are needed for the addition of landside facilities.
9. Contact Information
Phone :-
Email : [email protected]
89
SEMARANG CITY LIGHT RAIL TRANSIT (LRT)
Location : Semarang, Central Java Province
Description:
Semarang has already had an urban public
transportation with BRT system. Since the BRT
does not have its own dedicated lane, the
congestion problem still occurred and delayed
travelling time from point to point. LRT is
proposed as one of the solutions to reduce
congestion and planned to be built with
elevated track.
90
Project Digest
2. The Opportunity
Semarang has already had an urban public transportation with BRT system. Since the BRT
does not have its own dedicated lane, the congestion problem still occurred and delayed
travelling time from point to point. LRT is proposed as one of the solutions to reduce congestion
and planned to be built with elevated track.
The LRT route will be divided to nine (9) corridors with the total length 78.4 km.
1. Corridor 1: Mangkang-Kalibanteng
2. Corridor 2: Ahmad Yani Airport-Tawang Station
3. Corridor 3: Simpang Lima-Tawang Cycle Line
4. Corridor 4: Penggaron-Simpang Lima
91
5. Corridor 5: Dr.Cipto-Citarum-Fatmawati
6. Corridor 6: Tawang-Pelabuhan-Bangetayu
7. Corridor 7: Fatmawati-Bangetayu
8. Corridor 8: Kalibanteng-Pamularsih-Milo
9. Corridor 9: Bandara-Madukoro-Kokrosono-Pasar Bulu-Cokroaminoto-Simpang Lima
To provide Semarang with alternative public transportation with TOD approach that can reduce
the congestion and travelling time to every destination.
The scope of work for the private partner will be elaborated more in further study.
4. Technical Specification
AMDAL requirements will be assesed in the Outline Business Case study. In the mean time, if
the project requires to have AMDAL, the document will be prepared by the GCA.
92
8. Government Support and Guarantee
9. Contact Information
Phone : +62813-2557-1434
Email : [email protected]
93
DEVELOPMENT OF MOTOR VEHICLE WEIGHING IMPLEMENTATION UNIT (UPPKB) IN JAVA
AND SUMATERA
Location : Java and Sumatera Region
94
Project Digest
Mess Enforcement
Room
Main Office
Security Post
Generator
Room
Security Post
95
2. The Opportunity
Vehicle weighing violation have caused road damage or lowering road design life. The
decreasing of road capacity also impact many aspect such as:
• Decreasing economic center and industries connectivity
• Interrupting trade flow and public transportation
• Decreasing road and bridge infrastructure quality rapidly
• Increasing road safety and traffic risk.
The Motor Vehicle Weighing Implementation Unit project will take place in six locations in
Sumatera and Java that are:
1. UPPKB Tanjung, Brebes Regency, Central Java
2. UPPKB Subah, Batang Regency, Central Java
3. UPPKB Guyangan, Nganjuk, East Java
4. UPPKB Way Kanan, Way Kanan Regency, Lampung
5. UPPKB Merapi, Lahat Regency, South Sumatera
6. UPPKB Muara Tembesi, Batanghari Regency, Jambi.
The regulation on vehicle weighing should be implemented to control the load carried by the
vehicle. The task will be held by Motor Vehicle Weighing Implementation Unit.
The private partner responsibilities are Design, Build, Financing, and Maintain the facility
during concession period. Private partner also provides and maintain the instrument for Motor
Vehicle Weighing Unit.
4. Technical Specification
The technical specification for Motor Vehicle Weighing Implementation Unit should comply with
The Director General of Land Transportation Decree No. SK/5765/KP.803/DRJD/2017. There are
two types based on the regualation:
1. Type I, for road section with less than 2,000 vehicles/day per direction and one weighing
platform
2. Type II, for road section with equal or more than 2,000 vehicles/day per direction and
two or more weighing platform
The Motor Vehicle Weighing Implementation Unit Project requires to provide AMDAL
documents. The documents will be prepared by the Government Contracting Agency.
96
6. Land Acquisition and Resettlement Action Plan
There is no need for land acquisition as the project will be built on government land.
Government support and government guarantee will be determined on the Final Business Case
document.
9. Contact Information
Email : [email protected]
97
UNDER
PREPARATION
PROJECTS
Road:
1. Preservation of Eastern
Sumatera National Road in
Riau Province
2. Makassar-Maros-
Sungguminasa-Takalar Toll
Road
3. Construction of Badung
Southern Ring Road
4. Duplication and/or
Replacement of Callender
Hamilton Bridge in Java Main
Road
5. Batam-Bintan Bridge
PRESERVATION OF EASTERN SUMATERA NATIONAL ROAD IN RIAU PROVINCE
Location : Riau Province
Description:
One of the Eastern Sumatra Road in the
Province starting from the Kayu Ara
Intersection (Pekanbaru City) to Lago
Intersection (Pelalawan Regency) consists of
three streets that could be categorized as a
National Road which is correlated towards the
national economic growth. The approximate
total length of this project will be 43 km.
Investment return will be paid using the
Availability Payment Method.
98
Project Digest
2. The Opportunity
National connectivity needs to be improved and maintained to sustain economic growth and
ensure the welfare of the people. The better road will improve people’s accessibility to the
goods and services needed. In its development, the allocated budget is not enough to achieve
the target of developing a non-toll national road. The budget limitation becomes constraints to
99
the provision of adequate non-toll national road infrastructure services, both for the
preservation of existing sections and for the development of new sections.
To overcome the limitations of the budget, the government needs to think about schemes of
financing to accelerate development on national non-toll road. One such scheme is PPP
through availability payment.
Eastern Sumatera National Road network stretches from Aceh to Lampung going across Riau
Province. Riau part of this national road is divided into three sections:
1. Kayu Ara Intersection –Palalawan Regency (3,6 km)
2. Palalawan Regency – Sikijang Mati (9,1 km)
3. Sikijang Mati –Lago Intersection (30,3 km)
The total length of the road is 43 km with four bridges along the way.
The objectives of this project are to construct, maintain and preserve the road condition of
Preservation of Eastern Sumatera National Road in Riau Province so that it can serve the
growing number of traffic in Sumatera throughout the concession period.
The business entity is responsible for performing the road preservation project, including
designing, financing, construction, operation, and maintenance during the concession period.
4. Technical Specification
The technical specifications for Preservation of Eastern Sumatera National Road in Riau
Province as stated by government regulation must comply with several criteria:
1. Design speed
2. Road width
3. Road capacity
4. Entryway
5. Intersection and U-Turn
6. Superstructures
7. Road equipment
8. Road use according to function; and
9. Road continuity
100
6. Land Acquisition and Resettlement Action Plan
The information related to the land acquisition and resettlement plan will be provided in
subsequent studies.
The project indicates no need for government support. Government guarantee by Indonesia
Infrastructure Guarantee Fund (IIGF).
9. Contact Information
Position : Director of Implementation Infrastructure Financing for Road and Bridge, DGIF
101
MAKASSAR-MAROS-SUNGGUMINASA-TAKALAR TOLL ROAD
Location : South Sulawesi Province
Description:
The project is to construct approximately 48
Km of Mamminasata toll road. This Toll Road
will connect Maros Sub-district and Takalar
Sub-district without passing through Makassar
City and expected to shorten the logistics path
between the two regions. Mamminasata Toll
Road is planned to have 4 interchanges with
trumpet interchange type.
Financial Feasibility:
Government Contracting Agency: IRR : 12,21%
Minister of Public Works and Housing NPV : USD 55.44 Million
Type of PPP:
Solicited Estimated Concession Period: 40 years
Return of Investment:
Under Review
102
Project Digest
2. The Opportunity
The Mamminasata Bypass road (approximately 48 Km) has begun construction since 2015 and
is still constrained by several things, one of which is land availability. Therefore, there is a plan
to raise the status of this road to be a toll road in order to accelerate its development and the
PPP scheme is expected to be a solution.
This Toll Road which connect Maros Sub-district and Takalar Sub-district without passing
through Makassar City, will shorten the logistics path between the two regions, so that it will
have a positive impact on the economies of both regions.
103
2.2. Project Description
Mamminasata is a urban area consisting of Makassar, Maros, Sungguminasa, and Takalar. This
Toll Road will connect Maros Sub-district and Takalar Sub-district without passing through
Makassar City. It is planned to have four interchanges with trumpet interchange type.
1. To shorten the logistics path between Maros Sub-district and Takalar Sub-district;
Business entity shall responsible to perform the toll road project, including design, construct,
finance, operate, maintain during the concession period, and transfer the asset to the
government in the end of the concession period.
4. Technical Specification
The length of this toll road is 48.123 km. The technical specifications for toll roads will refer to
Minister of Public Works and Housing Regulation Number 19 Year 2011. Some technical
specifications including:
1. Design speed
2. Number of Lane
3. Lane Width
4. Outer Shoulder Width
5. Inner Shoulder Width
6. Median Width
The information related to the land acquisition and resettlement planned to be provided in
subsequent studies.
104
7. Project Cost Structure
Outline business case study indicates possible business model options, user charge with
government support or availability payment (AP). The government support identified in this
OBC study are Viability gap fund (VGF) and construction support from Ministry of Public Works
and Housing. The business model selected and the need for government support shall be
provided in subsequent studies.
9. Contact Information
105
CONSTRUCTION OF BADUNG SOUTHERN RING ROAD
Location : Badung, Bali Province
Description:
The role of the ring road (11.5 km) is to improve
connectivity between regions with different
functions in South Badung, which can then lead
to an increase in the quality of the area in
accordance with its function. The various
potentials of both developing new tourism
areas and reviving local community
commodities, including arts and culture, are
the reasons for this southern ring road
development plan.
106
Project Digest
Tunnel
Segment 1
Elevated
Segment 2
Tunnel
Segment 2
2. The Opportunity
Based on Badung Regency Regulation No. 26 of 2013 concerning Regional Spatial Planning of
Badung Regency, the purpose of of the spatial planning is to establish Badung Regency as a
Center for National Activities and high quality international tourism destinations, which are
competitive through the synergy of North Badung, Central Badung and South Badung regions
development in a sustainable manner, based on agricultural activities, services and tourism
towards community welfare as the implementation of the Tri Hita Karana philosophy. One of
the strategies to improve the quality of tourism supported by international standard regional
infrastructure systems is to provide international standard infrastructure and develop
integrated transportation network systems. This then becomes the basis of the planned south
ring road development which is located in the District of South Kuta, Badung Regency.
107
The role of the ring road is to improve connectivity between regions with different functions in
South Badung, which then can lead to an increase in the quality of the area in accordance with
its function. As stated in the Badung Regency Regulation No.26 of 2013 concerning RTRW of
Badung Regency in 2013 - 2033, the Regional Arrangement of Badung Regency aims to
establish the regency area as a National Activity Center and as a high quality, competitive and
cultural tourism destination for international tourism. The various potentials of both
developing new tourism areas and reviving local community commodities, including arts and
culture, are the reasons for this southern ring road development plan.
The total length of this ring road approximately will be 31.3 km and divided into 4 segments.
The options of Badung Southern Ring Road project scope then will be listed below:
1. Pavement in all Segment
2. Tunnel Construction at Segment 2
3. Elevated Construction at Segment 2
4. Road infrastructure facilities (public road lighting, walkways, traffic signs, road markings,
traffic signal devices, road user control and safety devices, road monitoring and security
equipment, and road parks).
Private partners shall be responsible for constructing and procuring some facilities to
accomplish the required facilities and infrastructure. The following are private partner’s list of
responsibilities:
1. Construction of
• Pavement at Segment 1,2, 3 & 4
• Tunnel Construction at Segment 2
• Elevated Construction at Segment 2
108
• Road infrastructure facilities (public road lighting, walkways, traffic signs, road
markings, traffic signal devices, road user control and safety devices, road monitoring
and security equipment, and road parks)
4. Technical Specification
Badung Southern Ring Road main scope for technical specification are:
1. Pavement with specification of AC-BC (Asphalt Concrete – Binder Coarse) and AC-WC
(Asphalt Concrete – Wear Coarse) both for ROW 24 m and 10 m
2. Tunnel Construction with TBM (Tunnel Bored Machine) Method
3. Elevated Construction either Balanced Cantilever using Box Girder, or Launch Gantry
using Box Girder, or using PCI Girder
According to the Minister of Environment and Forestry Regulation 38/2019, the Badung
Southern Ring Road area required to have Environmental Impact Assessment (EIA / “AMDAL”)
type A. This type has high complexity of project scope, high sensitivity of project location, and
high complexity of environmental baseline condition needed. This EIA development has
maximum time of 60 days.
Until now, the land that has been acquired by the Badung Regency Government as a PJPK for
the PPP project has only reached Segment 1, and in the future land acquisition will be carried
out for Segments 2, 3 and 4. Thus, the Land Acquisition and Resettlement Action Plan (LARAP)
is not required in this project due to the availability of land.
109
8. Government Support and Guarantee
The indicative Government support for Badung Southern Ring Road listed in the following
points:
1. Tax incentive from the government, Corporate income tax reduction for private sector
2. Project Development Facility (PDF) to develop Final Business Case (FBC) from the Ministry
of Finance
3. Guarantee of payment failure from Government Contracting Agency (GCA) to the private
sector by the Indonesia Infrastructure Guarantee Fund (IIGF)
9. Contact Information
Position : Head of Regional Public Works and Spatial Planning, Badung Regency
Email : [email protected]
110
DUPLICATION AND/OR REPLACEMENT OF CALLENDER HAMILTON BRIDGES IN JAVA
ISLAND MAIN ROAD
Location : Java Region
Description:
This project is to replace and/or duplicate 38
Callender Hamilton Bridges in the Java Island
Main Road. The location of the bridges is on the
national road connecting the provincial capital
and are the main logistics route to Sumatera
Island in order to increase national economic
activity. There are bridges in Banten, in West
Java, in Central Java, and East Java. The PPP
scheme used is Build – Operate – Transfer with
Availability Payment.
111
Project Digest
Legend:
Regency Boundary
Provincial Boundary
National Road
CH Bridge
112
2. The Opportunity
The development of national connectivity needs to be done in order to improve the social
welfare and Indonesia's competitiveness in the international market. The limited National
Budget (APBN) becomes an obstacle to the provision of Callender Hamilton Bridge
Replacement and Duplication, both for preservation of existing sections and for the new road
construction. To overcome these budget limitations, a PPP scheme is needed. The location of
Callender Hamilton Bridges Replacement and Duplication with PPP Scheme are on the national
road connecting the provincial capital and are the main logistics route to Sumatera Island in
order to increase national economic activity.
This project is to replace and duplicate Callender Hamilton Bridges in the Java Island Main
Cross Road. The location of Callender Hamilton Bridges Replacement and Duplication with PPP
Scheme are on the national road connecting the provincial capital and are the main logistics
route to Sumatera Island. There are as follows:
1. Bridge in Banten Province;
2. Bridge in West Java Province;
3. Bridge in Central Java Province; and
4. Bridge in East Java Province.
The Replacement and Duplication of 38 Hamilton Callender Bridges will be carried out in one
work package. The estimated project cost is 188.38 million USD which is expected to be fully
funded by the Business Entity. Project financing scheme is the Availability Payment where the
payment is payed after the fulfillment of output specification until the end of concession period.
The objectives of Callender Hamilton Bridges Replacement and Duplication are as follows:
1. To increase national economic activity;
2. To support the function of roads as the backbone of regional economic development; and
3. To facilitate a reliable regional transportation system.
113
4. Technical Specification
The number of Hamilton Callender Bridges to be replaced and/or duplicated are 38 bridges.
Replacement and/or duplication bridge will use steel box girder for span length > 40 meters
and PCI girder for span length < 40 meters.
The total land requirement for this project is 4,73 Ha. The study indicates the implementation
of land acquisition will be carried out by government.
The project is expected to get guarantees from IIGF for political and regulatory risks and the
risk of payment and adjustments to the AP value. It is expected that the preparation of the
feasibility study can be assisted by Ministry of National Development Planning and the Ministry
of Finance.
9. Contact Information
Email : [email protected]
114
BATAM-BINTAN BRIDGE
Location : Riau Islands Province
Description:
This project is to construct a bridge connecting
Batam and Bintan which located in Riau Islands
province. the project is expected to use a PPP
scheme with user charge as return of
investment scheme.
Financial Feasibility:
IRR : 10.80%
NPV : -
Government Contracting Agency:
Indonesia Toll Road Authority (BPJT) Estimated Concession Period: 40 years
Type of PPP:
Solicited
Return of Investment:
User Charge
115
Project Digest
Tanjung Sauh –
Batam Island
Length of 2.17 Km
Buau Island –
Tanjung Sauh
Length of 3.9 Km
Bintan Island –
Buau Island
Length of 0.9 Km
116
2. The Opportunity
Connectivity is one of the most important things in growing economic activities. Batam is
planned to be developed into a national industrial zone and Batam as a Free Trade Zone (FTZ)
area with major advantages in the field of trade and industry. Batam is also a strategic area
which is near Singapore and Malaysia. Bintan Island is also a strategic area and also as a Free
Trade Zone (FTZ) area. This project will be built with PPP scheme.
This project is to construct a bridge connecting Batam and Bintan which located in Riau Islands
Province. This bridge alignment is Kabil (Batam) – Tanjung Sauh – Buau Island – Kuala Lobam
(Bintan). Road length is 6,974 m and bridge length is 7,783 m. The Batam-Bintan Bridge
Construction Project is included in toll road infrastructure, and also one of the infrastructures
that can be conducted with PPP financing schemes with user charge as a return of investment
scheme. The scope of work for the business entity will be Build-Operate-Transfer (B-O-T). The
study has indicated that this project needs Government support in terms of partial construction
from the Ministry of Public Works and Housing and Government guarantee by Indonesia
Infrastructure Guarantee Fund (IIGF).
The objectives of this project to support the development and accessibility of Batam dan Bintan
in order to increase to increase trade and industries in Batam and Bintan.
The scope of work for the business entity will be Build-Operate-Transfer (B-O-T). The following
are private partner’s list of responsibilities:
3) Maintenance of the Batam-Bintan Bridge during the concession period, after the
construction phase has been completed; and
4) Sign and commit in the Guarantee Agreement with PT. Indonesia Infrastructure
Guarantee (Persero).
4. Technical Specification
The Batam-Bintan Bridge operation will be used as a toll road with dedicated motorcycle lanes
thus the technical specifications will refer to all regulations and specifications in the geometric
planning of roads (main road, ramp and access road). Some technical specifications for the
main road including:
No Facilities Capacity
1 Bridge Length 7,783 m
2 Road Length 6,974 m
117
No Facilities Capacity
3 Design Speed 80 Km/hr
4 Number of Lane 2x2
5 Lane Width 3.6 m
6 Outside Shoulder Width 3.0 m
7 Inner side Shoulder Width 1.5 m
8 Median Width (include inner 4.0 m
side shoulder)
9 Cross slope 2%
10 Outside Shoulder slope 4%
The study has indicated that this project needs Environmental Impact Assessment
(EIA/AMDAL) which is the responsibility of Ministry of Public Works and Housing. It also
indicated the needs of the Environmental Support and Capacity Study (Kajian Daya Dukung dan
Daya Tampung Lingkungan Hidup/DDDTLH) which is the responsibility of Riau Islands
Government. AMDAL and DDDTLH will be prepared in 2020.
The study has indicated that this project needs land acquisition of 701,665.31 m2. Land
acquisition is purposed to be done in 2021.
The study has indicated that this project needs Government support in terms of partial
construction from the Ministry of Public Works and Housing and Government guarantee by
Indonesia Infrastructure Guarantee Fund (IIGF).
9. Contact Information
118
UNDER
PREPARATION
PROJECTS
Sector : Water Resources and Irrigation Sub-Sector : Water Storage Infrastructure, Dam
Description:
The program has been prepared with the
support of Bappenas and the Ministry of Public
Works and Housings (“PUPR”). The program is
expected to generate economic, social,
environmental, water management and
livelihood benefits for the people of the
Merangin Regency and Jambi Province, as well
as to enhance food and energy security and
boost economic growth on the Jambi Province.
119
Project Digest
TUNNEL PLAN
SPILLWAY PLAN
120
Picture 2 – Map of Merangin Dam
2. The Opportunity
Irrigation sector is the largest water user in Indonesia but it only uses 12% of the average
annual flow. In line with the new Law on Water Resources No 17/2019, that Central Government
has policies and plans to expand irrigation areas to increase rice production, to respond to
food security needs and to address rural poverty. Irrigation system can be expected to reduce
the risk of crop damage from water shortages in the wet season and expand cropping area in
the dry season. Climate change is predicted to affect the future supply and demand for water
resources. Climate change will increase the intensity and duration of droughts as well as the
frequency of extreme floods especially in Merangin Regency since year 2000’s due to the
Merangin upper catchment area’s (a tributary of Batanghari River) unsustainable land use
which is driving land degradation, which in the form of soil erosion, nutrient depletion, water
scarcity and disruption of biological cycles is a fundamental and persistent problem,
diminishing productivity, biodiversity, other ecosystem services, and contributing to climate
change effect.
The proposed of Merangin multipurpose dam is considered to meet high demand of new
agriculture irrigation area of 12,000 ha in order to address the impacts of climate change on
the reliability of water supply as well as to mitigate flood risks, health, agriculture, energy
generation and aquatic ecosystems as well as renewable energy needs in a green and
sustainable manner.
The PPP Merangin Multipurpose program has been prepared with the support of Bappenas and
the Ministry of Public Works and Housings (“PUPR”). The program is expected to generate
121
economic, social, environmental, water management and livelihood benefits for the people of
the Merangin Regency and Jambi Province, as well as to enhance food and energy security and
boost economic growth on the Jambi Province. The program is envisaged to be developed
through the use of a public-private partnership (PPP) approach as stipulated by the
Presidential Decree No. 13/2015.
The US$ 253.07 million program involves a PPP scheme with a DBFOMT modality includes
financing, designing and building, operating and maintaining a multipurpose dam to provide
water for an irrigation scheme covering about 12,000 hectares in Merangin Regency, control
floods about 200 m3/sec in the Bangko town as the capital of Merangin Regency and other
populated areas in the lower part of the Merangin basin, impound water for a 95 - 144 MW
hydro power plant. Other components of the program include local water supply, recreation,
and social infrastructure. Land acquisition of ± 900 ha will be provided by the Government.
1. Option 1, Single GCA (Dam Only). Using Availability Payment scheme to cover the private’s
investment, risks and returns
2. Option 2, Single GCA (Dam + Hydropower Plant 95/107,45 MW). Using Availability Payment
scheme in option 2a to cover the private’s investment, risks and returns. There is also
another possibility to request VGF (Option 2b & 2c) in order to reduce Capex and to
enhance the Project Bankability, investment return scheme through electricity sales
tariffs for 30 years.
3. Option 3, Bundling GCA (Dam + Hydropower Plant 107,45 MW). Using Viability Gap Funding,
Investment return scheme through electricity sales tariffs for 30 years
The main objective of the Merangin Multipurpose Dam project is to foster the socio-economic
development in the Merangin Regency and Jambi Province as well as to contribute to the
economic growth of the country. This objective can be achieved through the development of
12.000 ha of irrigated agriculture and to reduce floods of 200 m3/sec for the benefit of local
farmers and stakeholders and by increasing food security and trade at the larger scale of the
country. The Merangin dam also improves the resilience to climate change by regulating the
flow of the Merangin River allowing a stable supply of fresh water, food and energy throughout
the year.
In addition, the proposed Merangin Multipurpose Dam could produce a hydropower scheme,
with an estimated annual production of the range 95 - 144 MW. It will provide a response to
the challenge facing the state utility company Perusahaan Listrik Negara (PLN) electricity
demand in Sumatra Island as well as consumers concerned about climate change are
increasingly demanding that their electricity come from renewable sources; as both the
national government and PLN are keen to increase the use of renewable energy, with a target
of 23% renewable energy by year 2025 of the its primary energy needs from renewable
sources, within the next six years, from 12% currently.
122
3. Business Entity’s Scope of Work
The proposed PPP Merangin Multipurpose Dam’s scope project of the following:
4. Technical Specification
123
Spillway Elevation +220 m Flood Control Q 200 m3/sec and QPMF 1,000-year return
period
Irrigation flow allocation 16,8 m3/second Average Flow allocation to turbine: Option 2a, 2b:
96.92m3/sec
Option 2c, 3: 96,85 m3/sec
According to the Regulation of Minister of Environment and Forestry No. 38/2019, the proposed
PPP Merangin Multipurpose Dam Project requires to have an Environmental Impact
Assessment (EIA / “AMDAL”) type A. Government has a plan to execute the EIA Study by year
2020 to identify anticipated environmental impacts of the proposed project. EIA scope includes
but not to limited to the following: (i) identification of potential mitigation measures and
discussion of these with BWS Sumatra VI and others, so as to analyze practicality and likely
cost; (ii) Finalization of recommended mitigation measures required during design,
construction and operation of the project; (iii) Development of cost estimates of the mitigation
measures; (iv) Preparation of a project-specific Environment Management Plan/ Mitigation
Management Action Plan.
The Government will conduct a LARAP Study on an area of ± 900 ha in year 2020 consisting of:
(i) a Social Economic Surveys; (ii) a census of population to be affected by the project and
preparation of desegregated data; (iii) identification of socio-economic impacts of the project
to the stakeholders; (iv) carrying out of an aerial survey of the project area and cadastral
survey of the land parcels to be affected and accompanying list of the registered land owners;
and (v) determination of the land to be acquired and the tentative compensation values for both
land, permanent, semi-permanent and temporary structures and both cash/subsistent crops.
124
Picture 3 – PPP Project Structure (Option 1)
Option 2b Option 2c
Option 2a
Dam + Hydropower Dam + Hydropower
Description Dam + Hydropower
Plant 95 MW (using Plant 107,45MW
Plant 95 MW (using AP)
VGF) (using VGF)
Estimated Project Cost USD 331.32 million USD 340.77 million USD 339.87 million
Capex
VGF Estimated - USD 134.03 million USD 126.67 million
Opex USD 4.07 million USD 4.07 million USD 4.17 million
AP / year USD 34.96 million - -
Revenue / year USD 48.68 million USD 52.47 million
Indicative debt to (to be confirmed in (to be confirmed in (to be confirmed in
equity FBC) FBC) FBC)
i. Debt Level 70% 70% 70%
ii. Equity Level 30% 30% 30%
FIRR 12.15% 13.43% 13.38%
NPV USD 58.37 million USD 51.38 million USD 55.17 million
Cost of Equity 16.54% 16.76% 16.76%
Cost of Debt (after tax) 7.35% 7.35% 7.35%
WACC 10.11% 10.17% 10.17%
Using Availability Payment scheme to cover the private’s investment, risks and returns as
stipulated by the Minister of Finance Regulation Number 260/2016 as an amendment of the Ministry
of Finance’s Regulation Number 190/2015 regarding Availability Payment on PPP scheme
Infrastructure Provision.
There is also using Viability Gap Fund (VGF) facility to subsidy some parts of construction costs of
the future Hydropower Plant.
125
Picture 4 – PPP Project Structure (Option 2a with AP)
126
iii. Debt Level 70%
iv. Equity Level 30%
FIRR 13.38%
NPV USD 55.17 million
Cost of Equity 16.76%
Cost of Debt (after tax) 7.35%
WACC 10.17%
Using Viability Gap Fund (VGF) facility to subsidy some parts of construction costs of the future
Hydropower Plant.
The indicative Government supports for the Merangin Multipurpose Dam are listed in the
following points:
1) Land acquisition for the access roads, dam axis and reservoir areas and supporting
facilities.
2) Tax incentive from the government:
o Corporate income tax reduction for private sector
o Import tax relief of testing devices which have yet to be produced domestically
o Value added tax relief of testing devices import which have yet to be produced
domestically.
3) Project Development Facility (PDF) will be provided by the Ministry of Finance to further
develop of Final Business Case (FBC) phase, as well as to further exercise either using the
Availability Payment (AP) scheme or using the Viability Gap Fund (VGF) facility.
4) Guarantee of payment failures from Government Contracting Agency (GCA) to the private
sector will be provided by the Indonesia Infrastructure Guarantee Fund (IIGF).
127
9. Contact Information
Email : [email protected]
128
PASIR KOPO DAM
Location: Lebak, Banten Province
Sector: Water Resources and Irrigation Sub-Sector: Water Storage Infrastructure, Dam
Description:
This project is to construct a Pasir Kopo Dam
which located on Lebak Regency of Banten
Province. Pasir Kopo Dam is will cover area in
the Cidanau – Ciujung – Cidurian River Region
(C3).
Financial Feasibility:
IRR : 11.30%
Government Contracting Agency: NPV : USD 14.19 Million (Dam only)
Minister of Public Works and Housing USD 15.97 Million (Dam + Hydropower
Type of PPP: Plant)
Solicited
Return of Investment: Estimated Concession Period: 30 years
Availability Payment
129
Project Digest
2. The Opportunity
Along with the development of the Banten area and various kinds of infrastructure facilities
such as irrigation, flood control facilities, raw water supply, and electricity sources, the
construction of Pasir Kopo Dam is needed. Pasir Kopo Dam will cover Cidanau-Ciujung-
Cidurian River Region (C3) so that the service area of the Pasir Kopo Dam is not limited to the
Lebak Regency only. This project will be conducted with a PPP scheme through Availability
Payment.
Pasir Kopo dam is included in the Draft Strategic Plan of the Ministry of Public Works and
Housing 2020-2024 so that this dam becomes one of the major projects by contributing to the
supply of raw water of 3.8 m3/s.
130
2.2. Project Description
This project is to build a Pasir Kopo Dam which located on Lebak Regency of Banten Province.
Kopo Dam is included in the Cidanau – Ciujung – Cidurian River Region (C3) with PPP scheme.
Return on Investment will use the Availability Payment system. The scope of work for the
business entity will be Design-Build-Finance-Operate – Maintain and Transfer (D-B-F-O-M-
T).
The objectives of this project are to fulfill the needs of various aspects such as irrigation of
3.2 m3/s, providing flood control of 288.77 m3/s, providing raw water of 3.8 m3/s, and fulfillment
the electricity needs in the Cidanau-Ciujung-Cidurian River Region (C3) with an estimated
annual production of 20.64 MW.
The scope of work for the business entity will be build, operate, and transfer.
4. Technical Specification
Design review will be prepared by Directorate General of Water Resources in 2020. Further
specification will be detailed in the OBC/FBC.
The documents already finished in 2016 and will be reviewed by Directorate General of Water
Resources in 2020. Further requirement will be detailed in the OBC/FBC.
The documents already finished in 2015 and will be prepared by Directorate General of Water
Resources in 2020. Further plan will be detailed in the OBC/FBC.
131
• Option 2 (Dam + Hydropower Plant)
The study has indicated that this project needs Government guarantee by Indonesia
Infrastructure Guarantee Fund (IIGF).
9. Contact Information
Email : [email protected]
132
SIDAN DAM RAW WATER CHANNEL
Location: Bali Province
Description:
Sidan Dam Raw Water Channel is part of bigger
development project to support clean water
supply for Sarbagita (Denpasar, Badung,
Gianyar, and Tabanan) Region in Bali. This
channel will distribute water from Sidan Dam.
Financial Feasibility:
IRR : 11.21%
NPV : USD 2.41 Million
133
Project Digest
Sidan Dam
WTP Luwus
WTP Carangsari
2. The Opportunity
Sidan Dam Raw Water Channel is part of bigger development project to support clean water
supply for Sarbagita (Denpasar, Badung, Gianyar, and Tabanan) Region in Bali. This channel
will distribute water from Sidan Dam.
The initial activities for Sidan Dam Raw Water Channel Project is to develop transmission
system to PDAM Denpasar, PDAM Badung, PDAM Gianyar, PDAM Tabanan; develop water
stabilization pond, and pressure relief system. The intended capacity is 1,750 lps.
134
2.3. Project Objectives
The objectives of this project is to develop raw water channel from Sidan Dam to respective
Regional Water Company (PDAM) of 1750 lps. The planned service areas are Denpasar, Badung,
Gianyar, and Tabanan.
The scope of work for the business entity will be build, operate, and transfer.
4. Technical Specification
The technical specifications for Sidan Dam Raw Water Channel will be defined further in the
Outline Business Case
The documents will be prepared by Directorate General of Water Resources in 2020. Further
requirement will be detailed in the OBC/FBC.
The documents will be prepared by Directorate General of Water Resources in 2021. Further
requirement will be detailed in the OBC/FBC.
The project needs for government support and guarantee will be defined in subsequent studies.
9. Contact Information
Email : [email protected]
135
UNDER
PREPARATION
PROJECTS
Drinking Water:
1. Construction of Kamijoro
Regional Water Supply
System
2. Construction of Jatigede
Regional Water Supply
System
3. Pantura Regional Water
Supply System
4. Dadimuria Regional Water
Supply System
5. Bregas Regional Water
Supply System
6. Wosusokas Regional Water
Supply System Phase II
CONSTRUCTION OF KAMIJORO REGIONAL WATER SUPPLY SYSTEM
Location : Kulon Progo and Bantul, Yogyakarta Province
Description:
Kamijoro Regional Water Supply system is
aimed to supply the drinking water to the
regencies of Bantul and Kulon Progo. The
project utilizes bulk water from Progo River
through Kamijoro Dam, which has been
Legend
REGIONAL WATER SUPPLY
planned to supply 475 lps (“lps”) drinking
water, consisting of 286 lps to Bantul Regency
and 189 lps to Kulon Progo Regency.
136
Project Digest
2. The Opportunity
• The needs of the project are driven by water shortage in the Regencies of Bantul and
Kulon Progo, while at the same time, the quality and continuity of current available
water have been deteriorated.
• Overexploitation of ground water by local people, which result in unsuitable drinking
water quality. The current water pipeline service is considered low, approximately 35%
of Special Region of Yogyakarta population.
• Based on FBC Preliminary Report, the current coverage area of Regional-Owned
Drinking Water Company (Perusahaan Daerah Air Minum/”PDAM”) in Kulon Progo
Regency and Bantul Regency are 21,34% and 10,47%, respectively. These percentage
are considered significantly below the government target to fulfill 100% of drinking
water supply in Indonesia, as mandated on RPJMN 2014 – 2019.
137
• The development of New Yogyakarta International Airport (“NYIA”) and Sentolo
Industrial Area establishes significant water demand for Kulon Progo Regency.
Similarly, the development of Pajangan – Sedayu Industrial Area also create water
demand for Bantul Regency.
• The project utilizes raw water from Progo River. The water intake facility is located
near Kamijoro Dam (on the west side). Currently, the intake facility is under
construction by Directorate General of Water Resources (Balai Besar Wilayah Sungai
Serayu Opak) through multi-years contract scheme from 2017-2019. The intake facility
has been designed and built with a capacity of 500 liter per second.
• Assuming 95% production efficiency from intake, the WTP is designed to supply 475
lps, which will serve Kulon Progo Regency (286 lps) and Bantul Regency (189 lps).
• The estimated sub-districts within Bantul Regency covered by this project are
Pajangan, Pandak, Sedayu, Bantul, Sanden, Srandakan, Pundong, Kretek,
Bambangliouro and Jetis.
• The estimated sub-districts within Kulon Progo Regency covered by this project are
Sentolo, Lendah, Galur, Panjatan, Wates, and Temon.
• The scope of distribution unit (from reservoirs onwards) will be further studied, it is
either included in PPP scope or procured through government’s or local government’s
budget.
• Furthermore, the scope of House Connection unit will be undertaken by Region-Owned
Drinking Water Company (Perusahaan Daerah Air Minum/”PDAM”).
• In line with PPP preparation stage, Provincial Government will establish the Provincial
Government Water Supply Company (Perusahaan Air Minum Daerah /”PDAB”) as
operator, which will be assigned to manage the supply of bulk water to PDAMs. PDAB
will also further be assigned as Government Contracting Agency (“GCA”). PDAB is
targeted to be established by Quarter 1 2020.
Private sector which will participate in this project will have to:
• Operate and Maintain intake facilities built by Ministry of Public Works and Housing.
• Construct, Operate and Maintain Water Treatment Plant with the capacity to produce
475 lps.
• Construct, Operate and Maintain two reservoirs (Beji and Gunting) to serve 189 lps to
Bantul Districts.
• Construct, Operate and Maintain two reservoirs (Tuksono and Jekeling) to serve the
Kulon Progo districts.
• Construct, Operate and Maintain transmission pipeline.
The SPCwill be responsible for constructing, operating and maintaining the Water Treatment
Plant, Clean Water Transmission pipe, reservoirs until the handover points to PDAM. The SPC
138
scope also include operating and maintaining the intake facilities constructed by Ministry of
Public Works and Housing.
PROJECT SCOPE OF KAMIJORO REGIONAL WATER SUPPLY
KAMIJORO REGIONAL SPAM IN BANTUL REGENCY
Distribution Pipeline
4. Technical Specification
Project technical specification will be further studied during finalization of FBC Report.
The previous Environmental Impact Assessment (AMDAL) of Kamijoro Stage I (Kulon Progo)
was undertaken by Government of Special Region of Yogyakarta. While there are changes on
the scope into integrated system of Water Supply project for Bantul and Kulon Progo, the
permit requires new AMDAL assessment, altogether with the location allocation permit
(Penetapan Lokasi).
• Land acquisition required, altogether with construction of intake facility, has been
undertaken by the Ministry of Public Works and Housing.
• Land acquisition needed for Water Treatment Plant, and reservoirs Tuksono and
Jekeling in Kulon Progo Regency has been acquired by Government of Special Region
of Yogyakarta.
• Land acquisition for reservoirs Gunting and Beji in Bantul Regency will be undertaken
by Government of Special Region of Yogyakarta, targeted in 2020.
• Land Acquisition Resettlement Action Program (“LARAP”) document is under
progress.
• Any other permit requirement during construction and operation will be undertaken
by SPC.
139
7. Project Cost Structure
There are possible government supports and guarantee for the project:
• Viability Gap Fund (“VGF”), Based on Ministry of finance Regulation No. PMN 223/2012 and
PMK 143/2013, which subsidy of construction cost given to increase project’s feasibility.
The amount and portion needed will be further studied on FBC Final Report.
• Central and Local Government Support, based on Ministry of Public Works and Housing
Regulation No. 19/2016, which is fiscal and non-fiscal support to increase project
feasibility. The needs and amount of the supports will be further studied on FBC Final
Report.
• Government Guarantee, Based on Presidential Regulation No. 38/2015, No. 78/2010, also
Ministry of Finance Regulation No. 260/2010, is the guarantee given by Central Government
for PPP Project. Further needs for government guarantee will be studied on FBC Final
Report.
9. Contact Information
Position : Head of Department of Public Works, Housing, and Energy and Mineral
Resources
Email : [email protected]
140
CONSTRUCTION OF JATIGEDE REGIONAL WATER SUPPLY SYSTEM
Location : West Java Province
Description:
1,500 L/sec of Jatigede regional water supply
will service Sumedang Regency, Majalengka
Regency, Cirebon Regency, Indramayu
Regency and Cirebon city. Jatigede water
supply consist of intake, 3x500 L/s WTP, 56.3
km main distribution network: 56.3 km, and
distribution reservoir: seven distribution
reservoirs located at each off-taker (Tomo,
Jatitujuh, Jatiwangi, Jatibarang, Krangkeng,
Babadan and Kepompongan).
141
Project Digest
2. The Opportunity
The implementation of regional Water Supply is one of the efforts for more efficient and
effective water supply in terms of technical and economic aspects. In addition, the limited
funding sources in conducting investment for the implementation of water supply, would be
carried out through Public Private Partnership scheme.
142
Jatigede Regional Water Supply is a National Strategic Project, where the governments both
central and regional will coordinate and issues series of policies to accelerate the
implementation of the project.
The service area for Jatigede regional water supply are as follows:
• Sumedang Regency;
• Majalengka Regency;
• Cirebon sub Regency;
• Indramayu Regency; and
• Cirebon city
Jatigede regional water supply will be implemented by the BOT mechanism. The scope of
activities that will be cooperated for the Jatigede Regional Water Supply include:
• Special Purpose Company sell treated water (bulk water) to PDAM through GCA using the
‘take or pay’ method;
• Target Area: Sumedang sub district, Majalengka sub district, Indramayu sub district,
Cirebon sub district, Cirebon city;
• Water treatment plant phase I: 3 x 500 L/s;
• Main distribution network: 56.3 km;
• Distribution reservoir: three locations at each off-taker (Tomo, Jatitujuh, and Jatiwangi).
WTP will be located in Kadipaten. Production capacity of 1,500 L/sec consists of 3 WTPs with a
capacity of 500 L/d. For each WTP, it consists of processing units: coagulation, flocculation,
sedimentation and filtration. The construction phase is planned to be carried out in 2020 for
three years and will start operating in 2022.
The objectives of Jatigede Water Supply is to provide clean water services to the community
in service area.
4. Technical Specification
The technical specifications for Jatigede Regional Water Supply are as follows:
143
No. Description Capacity
1. Construction Reinforced Concrete
2. Capacity 3 x 550 L/sec
III Transmission Pipe
1. Capacity 1,500 L/sec
2. Maximum Pressure 60 - 80 m water column
3. Minimum Pressure 5 - 10 m water column
IV NRW
1. Intake 2%
2. Production Facilities 5%
3. Transmission Pipeline 1-2%
V Operation time 24 hours/day
VI Water Quality Minister of Health Regulation No. 49/2010 and
WHO Guidelines for Drinking Water Quality,
2011
Until June 2018, Housing and Settlement Agency is completing an Environmental Impact
Assessment (AMDAL) for PPP Project of Jatigede Regional Water Supply. In OBC document
explained that due to a change in the location and a large capacity of 2,000 L/d of the Intake,
the Agency needs to revise AMDAL of Jatigede Regional Water Supply and at the same time
proposing for the environmental permit from the West Java Governor
In Jatigede Regional Water Supply, the initial identification of the project development intake
location, transmission pipeline, and reservoir is as follows:
144
No Land purpose Land Area (ha) Land Contract / Land
Ownership Acquisition
Method
1. Intake located in Cilutung 0.89 ha Owned by West Java
BBWS Provincial
Cimanuk- Government as
Cisanggarung GCA, get from
BBWS
Cimanuk-
Cisanggarung
2. Raw water Transmission 4.58 ha Owned by West Java
Pipeline BBWS Provincial
Cimanuk- Government as
Cisanggarung, GCA, get from
National road, BBWS
village and Cimanuk-
community Cisanggarung,
land Bina Marga,
and acquiring
village and
community
land
3. WTP Located in Kadipaten 5.03 ha Owned by West
(including reservoir) Java Provincial
Government
4. Pipeline (from WTP to each Total area 20.42 - 2.74 will be Inspeksi irigasi
reservoir) ha placed on road: permit for
Inspeksi utilization of
irigasi road roads from the
- 0.84 will be MoPWH and a
placed on lease
Rumija Toll agreement with
land the MoPWH.
Rumija Tol:
permit for
utilization of
roads from the
PT. Lintas
Marga Sedaya.
5. Tomo Reservoir 0.09 ha Owned by Built on
Sumedang Sumedang’s LG
sub-district land.
6. Jatiwangi Reservoir 0.09 ha Owned by Built on
Majalengka Majalengka’s
sub-district LG land.
7. Jatitujuh Reservoir 0.12 ha Owned by Built on
Majalengka Majalengka’s
sub-district LG land.
8. Jatibarang Reservoir 0.12 ha Owned by Built on
Indramayu Indramayu’s LG
sub-district land.
145
9. Krangkeng Reservoir 0.16 ha Owned by Built on
Indramayu Indramayu’s LG
sub-district land.
10. Babadan Reservoir 0.08 ha Owned by Built on
Cirebon sub- Cirebon’s LG
district land.
11. Kepompongan Reservoir 0.25 ha Owned by Built on
Cirebon city Cirebon city’s
LG land.
The project is indicated to require government support in the form of fiscal and non-fiscal.
Government support includes VGF, Guarantee, Technical Support of the Ministry of Public
Works and Housing.
9. Contact Information
146
PANTURA REGIONAL WATER SUPPLY SYSTEM
Location : Lamongan, Tuban and Bojonegoro Regency, East Java Province
Description:
Pantura Water Supply System will utilize water
from Bengawan Solo River to supply water in
Lamongan, Bojonegoro and Tuban Regency. It
is projected that in 25 years, the water demand
in the area will grow to 1,749 lps. To fulfill this
demand, the government needs to expand the
current water supply system.
Financial Feasibility:
IRR : Under Calculation
Government Contracting Agency: NPV : Under Calculation
Director of PT. Air Bersih Jatim (Perseroda)
Type of PPP: Estimated Concession Period: Under Review
Solicited
Return of Investment:
Under Review
147
Project Digest
RIVER
DISTRIBUTION
PUMP
PRE-SEDIMENTATION
RAW WATER FILTRATION CLEAN WATER
SEDIMENTATION
2. The Opportunity
In line with the role of the Regency and City Governments in the era of regional autonomy
and in connection with the existence of Law 17 of 2019 on Water Resources, Government
Regulation Number 122 of 2015 concerning Drinking Water Supply Systems, Minister of
Public Works Regulation Number 20 / PRT / M / 2006 concerning National Policies and
Strategies in the Development of SPAM and Minister of Public Works Regulation No. 18 /
PRT / M / 2007 concerning the Implementation of Drinking Water Supply System
Development, that the development of drinking water supply systems is the responsibility
of local governments (Provincial and Regency / City). The Indonesian government aspires
to be able to achieve universal access to safe drinking water by 2019. This means that 100%
of the people have access to safe drinking water services that year. This is stated in the
2005-2025 Long-Term National Development Plan (RPJPN).
The current service level of drinking water services in East Java is still far from sufficient.
The potential of raw water sources in East Java is not yet comprehensively identified and
also has not been used optimally, on the other hand there are still many areas that lack
and have difficulty in getting drinking water to meet their daily needs.
Example of an integrated clean water supply system that can be used together in East
Java Province is the Bengawan Solo River that will cater the population in Bojonegoro,
Tuban and Lomongan Regency, hereinafter referred to as the "Pantura Regional Water
Supply System".
148
2.2. Project Description
To fulfill the water demand until 2045, the water supply system would need to have the
capacity of 1,749 lps of water, with 643 lps supplied to Lamongan Regency, 559 lps supplied
to Tuban Regency and 547 supplied to Bojonegoro Regency.
The purpose for the development of Pantura Regional Water Supply is to:
The project will implement D-B-F-O-M-T (Design – Build – Finance – Operate– Maintenance-
Transfer) scheme for the PPP Project.
4. Technical Specification
Land needed for this project is approximately ± 3.5 hectares with details as follows:
149
7. Project Cost Structure
Government Supports identified in the preliminary study are Viability Gap Fund (VGF) and
Project Development Facility (PDF). It is also identified that this project would need
Government Guarantee from IIGF.
9. Contact Information
Name : M. Falahul A. A
Position : Head Of Planning and Development Division
Phone : 08113520538
Email : [email protected]
150
DADIMURIA REGIONAL WATER SUPPLY SYSTEM
Location : Grobogan, Kudus, Pati and Jepara Regency, Central Java Province
Description:
Dadimuria Regional Water Supply System will
provide clean water for population in Grobogan
Regency, Kudus Regency, Pati Regency and
Jepara Regency. The needs for clean water will
be increase due to the growing population in
this area. The first phase of the project will be
constructed using PPP scheme.
Financial Feasibility:
IRR : Under Calculation
Government Contracting Agency: NPV : Under Calculation
Director of PDAB Tirta Utama
Type of PPP: Estimated Concession Period: Under Review
Solicited
Return of Investment:
Under Review
151
Project Digest
2. The Opportunity
Central Java as one of the most populated provinces in Indonesia needs to have proper
water supply system to fulfill the needs water supply for the community. Dadimuria
Regional Water Supply System will cover areas in Grobogan Regency, Kudus Regency,
Pati Regency and Jepara Regency. Currently, the water demand for the region is
approximately 10,422 lps of water and in 20 years will grow to around 14,192 lps. Currently,
the water production capacity is only 1,138 lps. Dadimuria Water Supply System is intended
to fulfill this demand gap.
152
The Dadimuria Regional Water Supply System will consist of construction of new water
intake from Klambu Dam, construction of new Water Treatment Plant (WTP) with capacity
of 500 lps along with reservoirs, pumping system and transmission pipe network to cater
population in the area.
The phase I of the project will supply water to 40,000 customer connections, with details
as follows:
• Grobogan Regency with water supply of 100 lps will supply 8,000 connections
• Kudus Regency with water supply of 110 lps will supply 8,800 connections
• Jepara Regency with water supply of 190 lps will supply 15,200 connections
• Pati Regency with water supply of 100 lps will supply 8,000 connections
The purpose for the development of Dadimuria Regional Water Supply is to:
The Business Entity will work with Build-Operate-Transfer (B-O-T) scheme for facilities as
follows:
It is noted that in 2022, MPWH plans to build water intake facility in Klambu Dam. If the plan
goes through, then water intake facility will be taken out from project scope of work.
4. Technical Specification
Facility Specification
Water Intake Unit 500 lps
Reservoir
- Taruman Reservoir 2,000 m3
- Jati Reservoir 6,000 m3
- Pati Reservoir 2,000 m3
- Rajagwesi Reservoir 4,000 m3
Transmission Pipe Network
- From WTP to Grobogan Reservoir 15,000 m HDPE Pipe dia. 500 mm
153
Facility Specification
Land acquisition and resettlement action plan will be detailed in subsequent OBC/FBC
Documents.
9. Contact Information
154
BREGAS REGIONAL WATER SUPPLY SYSTEM
Location : Brebes and Tegal, Central Java Province
Description:
Bregas Regional Water Supply System
development plan is implemented to fulfill and
accelerate the development target of 100-0-100
by expanding coverage water supply piping
services in Brebes Regency, Tegal Regency and
Tegal City. Currently each of these regions has
the coverage of piping services that is still
below 50%. This project aim at increasing the
coverage area and increase the efficiency of
the system.
155
Project Digest
2. The Opportunity
Bregas Regional Water Supply will provide water supply for population in Brebes Regency,
Tegal Regency and Tegal City. It is projected that in 20 years, the water demand in the
coverage area will increase substantially to nearly 8,800 lps. While the currently installed
capacity of Bregas Regional Water Supply System is only 872 lps, leaving the supply gap
of over 90% in the coverage area. This situation is worsened by the high rate of water loss,
up to 30.27% in 2019. This will make the operation of Bregas Regional Water Supply System
very costly and will make it less profitable.
To address this situation a project is needed to rehabilitate the water supply system and
expand the piping network. This will increase the coverage, minimize the water loss, and
ensure the efficiency of the system that will lower the operation and maintenance cost of
the system.
156
The project will rehabilitate the Bregas Regional Water Supply System by rehabilitating
the main distribution piping system from Babakan Chamber to Brigif Chamber,
constructing new Babakan Reservoir, rehabilitating Gombong Spring broncaptering, and
rehabilitating transmission pipeline from Kaligiri Spring to Babakan Chamber.
The scope of work for business entity in this project will be B-O-T with activities as follows:
• Rehabilitation of the main distribution piping system from the Babakan Chamber to the
Brigif Chamber with the HDPE PN 12.5 Dn 500 pipe along 2.5 km.
• Rehabilitation of the main distribution pipeline from Lebaksiu Reservoir to the Brebes
Regency, Tegal City, Tegal Regency
• Construction of Babakan Reservoir with capacity of 5,000 m3.
• Rehabilitation of Gombong Spring Broncaptering.
• Rehabilitation of the transmission pipeline from the Kaligiri Spring to the Babakan
Chamber with Dn 400 steel pipe along 35 km.
4. Technical Specification
Project technical specification will be further studied during finalization of FBC Report.
Land acquisition will be part of GCA’s responsibility. In preliminary study, the construction of
reservoir would need around 10,000 m2 of land to be acquired. The detailed land acquisition
and resettlement action plan will be prepared in OBC/FBC.
157
8. Government Support and Guarantee
9. Contact Information
158
WOSUSOKAS REGIONAL WATER SUPPLY SYSTEM PHASE II
Location : Surakarta and Sukoharjo, Central Java Province
Description:
Wosusokas Regional Water Supply System
provide clean water for population in Wonogiri
Regency, Karanganyar Regency, Sukoharjo
Regency and Surakarta City. The needs for
clean water will be increase due to the growing
population in this area. The project will be done
in two phases with phase II to be constructed
using PPP scheme.
Financial Feasibility:
Government Contracting Agency: IRR : Under Calculation
Director of PDAB Tirta Utama NPV : Under Calculation
Type of PPP:
Solicited Estimated Concession Period: Under Review
Return of Investment:
Under Review
159
Project Digest
Surakarta City
Sukoharjo Regency
Nguter Reservoir Gentan Reservoir Plesungan Reservoir 500 lps
200 lps
1.000 m3 (+142 masl) 1.000 m3 (+107 masl) 10.000 m3 (+135 masl)
2. The Opportunity
Central Java as one of the most populated provinces in Indonesia needs to have proper
water supply system to fulfill the needs of water supply for the community. Wosusokas
Regional Water Supply System is one the system that will cover areas in Wonogiri
Regency, Sukoharjo Regency, Karanganyar Regency and Surakarta City. It is estimated
that in 20 years, the region would need approximately 9,300 lps of water supplied through
its system. Currently, the water production capacity is only 1,757. To fulfill this gap,
Wosusokas Water Supply System needs to be upgraded and expanded.
160
2.2. Project Description
The Wosusokas Regional Water Supply System will consist of construction of new water
intake from Wonogiri Multipurpose Dam, Main Transmission Pipe, Water Treatment Plant,
Distribution Units and Customer Connection for nearly 116,000 connections.
It will be separated into two phases. Phase I of the project will construct WTP with capacity
of 750 lps to supply water to 60,000 customer connections, with details as follows:
While the Phase II will construct WTP with capacity of 700 lps to supply 56,000 customer
connections in Sukoharjo (16,000 connections) and Surakarta (40,000 connections) only.
The purpose for the development of Wosusokas Regional Water Supply is to:
The project will implement Build-Operate-Transfer scheme with scope of work is as follows:
• Construction of Water Treatment Plant (WTP) with capacity of 700 lps and Clear Well
2,500 m3.
• Construction of Main Distribution Pipe and corresponding Piping Bridge.
• Construction of Nguter Reservoir System with capacity of 1,000 m3.
• Construction of Gentan Reservoir System with capacity of 1,000 m3.
• Construction of Plesungan Reservoir System with capacity of 10,000 m3.
• Construction of Nguter Booster System with capacity of 500 m3.
• Construction of Plesungan Booster System with capacity of 2,000 m3.
The Business Entity will then operate the facility and transfer it back to the GCA after
concession period.
4. Technical Specification
Project technical specification will be further studied during finalization of FBC Report.
EIA document has been prepared by Government of Central Java Province in 2013. It will be
updated to accommodate new project scope during the preparation stage.
161
6. Land Acquisition and Resettlement Action Plan
Land acquisition will be part of GCA’s responsibility. It is indicated in preliminary study that
the project will need 352,700 m2 of land, with 304,500 m2 is located in government land. Of the
remaining 48,200 m2 of land, 36,000 m2 have been acquired. More than 12,000 m2 of land could
not be acquired due to technical issue. However, it has been confirmed that the project can
be done using the currently acquired land. The detailed land acquisition and resettlement
action plan will be prepared in OBC/FBC.
9. Contact Information
162
UNDER
PREPARATION
PROJECTS
Waste Management:
1. Construction of Waste to
Energy Facility in South
Tangerang
2. Legok Nangka Regional
Waste Processing Facility
3. Sarbagita Suwung Waste to
Energy Facility
4. Jatibarang Waste to Energy
Facility
5. Development of Piyungan
Landfill
6. Integrated Hazardous Waste
Management System in
Sumatera and Sumapapua
CONSTRUCTION OF WASTE TO ENERGY FACILITY IN SOUTH TANGERANG
Location : South Tangerang, Banten Province
Description:
Waste management of 800 tonnes per day is
located in Cipeucang Landfill, South Tangerang,
Banten. Conversion of waste to electricity with
output capacity to be determined and Purchase
Agreement with PLN. Scope of this project are
design, build, finance, operate, maintain the
WTE plant and supporting infrastructure.
Financial Feasibility:
IRR : 10%
Government Contracting Agency: NPV : USD 140.14 Million
Mayor of South Tangerang City
Type of PPP: Estimated Concession Period: 3 years
Solicited construction and 20 years operation.
Return of Investment:
User Charge
163
Project Digest
COMPOSTING
LANDFILL
GUARD HOUSE
DEVELOPMENT LAND
VEHICLE WASHES
ENTRANCE ACCESS 1
GUARD HOUSE
LANDFILL EXISTING PORTAL
RECLAMATION ZONE
ENTRANCE ACCESS 2
2. The Opportunity
Population growth and continuous industrialization in South Tangerang will increase the
amount of waste generated. In 2017, Municipal Solid Waste (MSW) in South Tangerang was 970
tonnes/day, most are buried in unhealthy ways. South Tangerang City needs a stable and
efficient solid waste management plan to use solid waste to produce renewable energy. This
is the reason South Tangerang City has planned to build and operate Waste to Energy facilities.
164
2.2. Project Description
The objectives of South Tangerang Waste to Energy is to operate a solid waste treatment
facility with the Build – Operate – Transfer (BOT) scheme. This project will build a solid waste
treatment facility for South Tangerang and will contribute to the environmentally friendly solid
waste management and economically efficient.
4. Technical Specification
The technical specifications for South Tangerang Waste to Energy are as follows:
No Facilities Capacity
1 Area 4 hectare
2 Incineration capacity 800 tonnes/day (400 tonnes/days x 2 units)
3 Electricity generated 11.7 MW
4 Electricity sold 10.0 MW
165
6. Land Acquisition and Resettlement Action Plan
According to OBC document, currently 13.6 hectares (including existing landfill) is owned by
the South Tangerang Government and it requires the provision of additional land of 1.4 hectares
to supporting facilities. Further mapping of the existing land status and the land area that need
to be expanded will be assessed in the subsequent studies.
Outline business case study indicates the government support options for this project, namely
Viability gap fund (VGF) and tax incentives.
9. Contact Information
Phone : 08121338136
Email : [email protected]
166
LEGOK NANGKA REGIONAL WASTE PROCESSING FACILITY
Location : West Java Province
Description :
Waste management of 1,853 – 2,131 tonnes per
day of waste sourced from 6 municipalities
(Bandung Regency, Bandung City, Sumedang
Regency, Cimahi City, West Bandung Regency,
and Garut Regency) located in Legok Nangka,
West Java. Scope: Design, Build, Finance,
Operate, maintain the WTE plant and
supporting infrastructure.
Financial Feasibility:
Government Contracting Agency: IRR : 13.30%
Governor of West Java NPV : USD 49.65 Million
Type of PPP:
Solicited Estimated Concession Period: 2 years
Return of Investment: construction and 20 years operation
User Charge
167
Project Digest
2. The Opportunity
West Java Province has rapidly growing population and urbanization rate, reaching 46 mil-
lion people in 2017. The number is estimated to increase to more than 57 million in 2035 and
approximately more than 67.5 million in 2050. Population growth combined with increasing in-
come per capita and change in consumption will generate larger demand for Municipal Solid
Waste Management. Regarding this issue, West Java Government need to handle because the
current Waste Management facility will be over capacity and out of order after 2020.
168
2.2. Project Description
A total of 1,853 – 2,131 tonnes per day (tpd) of municipal solid waste (MSW) is intended to be
processed at Legok Nangka WtE plant which will be supplied from six municipalities including
Bandung City, Bandung Regency, Cimahi City, West Bandung Regency, Garut Regency, and
Sumedang Regency.
• To build Regional Waste Treatment facility for Bandung City, Bandung Regency, Cimahi
City, West Bandung Regency, Garut Regency, and Sumedang Regency.
• To support the national target of renewable energy usage 25% from total national energy
consumption in 2025 – as in Minister of Energy and Mineral Resources Decree No. 70/2014.
• To increase municipalities’ health and sanitation quality.
• To reach 85% efficiency of waste treatment.
• To apply international emission standard waste management technology with minimal
hazardous secondary product.
• To optimize the value of waste by transforming it into commercial product.
• To support circular economy concept where the sustainable waste management system
could produce electricity for the municipalities.
1. Design, Build, Finance, Operate, and Maintain the Waste Treatment Plant and Supporting
Infrastructures. In the end, the facility must be transferred back to the GCA.
2. Operate and Maintain existing landfill in Legok Nangka Site.
3. Design and Build transmission networks and hand over to PT PLN upon completion.
4. Technical Specification
Based on data sampling at Sarimukti landfill, the three dominant waste products Bandung City
and Regency are organic waste (>55%), plastics (>20%) and hygiene products (≈6%). The Legok
Nangka Regional Waste Treatment Installation output specification should provide:
Performance
Item
Minimum Requirement Additional Requirement
Waste Reception Digitalized Online
Service/Truck Weighing
Information System
Waste Reception Service – 1,853 tonnes per 9 hours > 1,853 tonnes per 9 hours
Waste Disposal Platform
Capacity Emission
169
Performance
Item
Minimum Requirement Additional Requirement
Free Temporary Shelter 9,225 tonnes > 9,225 tonnes
Leachate and Wastewater All leachate and waste water
Management
Waste Management 673,425 tonnes/year Max 774,439 tonnes/year or
Capacity 15% of requirement above
Installation Avalability 7,800 hours/year > 7,800 hours/year
Water Consumption Max 20 liters/second < 10 liters/second
Emission Standard Equal to Chinese Standard Equal to USA/Japanese
(GB18482-2001) Standard
Residue Disposal 276.7 tonnes/day < 276.7 tonnes/day
Waste Management in Minister of Public Works and Not Applicable
Landfill Housing Regulation No. 3/2013
Legok Nangka Regional Waste Treatment Project requires to provide AMDAL documents. The
documents will be prepared by the Government Contracting Agency.
The Land Acquisition will be done by the GCA, in progress for minor additional land. Further
plan will be available after finalization of FBC document.
GCA will propose government guarantee and support. The feed-in tariff will obey Presidential
regulation, Government of West Java committed to pay the required tipping fee.
9. Contact Information
Email : [email protected]
170
SARBAGITA SUWUNG WASTE TO ENERGY FACILITY
Location : Bali Province
Description:
Bali is planning to construct WtE plant to
improve waste management services in Bali
Province, especially in the areas of Denpasar,
Badung, Gianyar and Tabanan. The plant will
have a waste input capacity of 1,350 tonnes /
day and electricity production capacity of 19.5
MW. This development will make waste
management in Bali environmentally friendly
and cost efficient.
171
Project Digest
2. The Opportunity
Bali is one of the provinces in Indonesia known as the Paradise Island. Bali is located between
Java and Lombok. The capital of the Province of Bali is the City Denpasar, located in the
southern part of the island. The Province of Bali needs improvement and expansion waste
treatment facilities and associated urban infrastructure, along with the increase the amount
of waste generated due to population growth, industrialization, and tourism continuously.
Based on data from the Preliminary Study of the Provincial Government of Bali (2019), total
SARBAGITA landfill waste in Suwung reaches 1,400 tonnes / day, with the percentage of
contributors the biggest waste is Denpasar City, which is 50% or equivalent to 740 tonnes /
day.
172
The Province of Bali needs to use waste to produce new and renewable energy building a
stable and efficient waste disposal plan. Waste Processing Technology Being Electrical Energy
(PSEL) provides an opportunity to significantly reduce the amount of waste disposed of in
landfills and also to recover energy and output other benefits of urban waste flow in Indonesia.
This is the reason why the Province of Bali has planned to build and operate a PSEL facility.
The project will consist of Building a Waste to Energy plant in Suwung landfill capable of
processing 1,350 ton of municipal waste per day and producing 19.5 MW of electricity.
Incinerator will be used to process the waste and produce energy. A WtE power plant consists
of 3 processes - pre-treatment and incineration, energy recovery, and pollution control.
1. Pre-processing and incineration - Trash is shipped by truck and stored in a bunker before
being moved to the incinerator. Waste will then be burned and reduced in both weight and
volume in the incinerator.
2. Energy recovery - The flue gas (hot garbage) from the incinerator is then channeled to the
boiler for steam produce steam which is used to drive a steam turbine generator for
electricity generation and finally condensed.
3. Pollution control - Residue from incineration (bottom ash and fly ash) and flue gas that
comes out from the boiler will then be processed before being discharged to the landfill
and the respective atmosphere
The purpose of this project is to operate a waste to energy facility under the BOT scheme. This
project will build a waste to energy facility for Bali and will contributes to the management of
environmentally friendly and economically efficient waste management system.
4. Technical Specification
No Facilities Capacity
1 Area 14.1 hectare
2 Incineration capacity 1,150 tonnes/day
3 Electricity sold 19.5 MW
173
5. Environmental Impact Assessment (EIA/AMDAL) Findings
According to OBC document, the whole project would need about 14.1 hectares of land to be
built. 4.1 hectares is located in the mangrove area.
Outline business case study indicates the government support options for this project, namely
Project Development Facility (PDF) for FBC and transaction preparation Viability gap fund
(VGF), construction support especially for land preparation, guarantee from IIGF and Tipping
Fee Support / BBLPS (Bantuan Biaya Langsung Pengolahan Sampah).
The guarantee will be needed to ensure quantity and quality of waste input, sovereign
guarantee and other applicable guarantee from IIGF.
9. Contact Information
Email : [email protected]
174
JATIBARANG WASTE TO ENERGY FACILITY
Location : Semarang, Central Java Province
Description:
Jatibarang WtE Project is one of the National
Strategic Projects under Presidential
Regulation No. 3/2016. The existing landfill site
at Jatibarang will reach its maximum capacity
within the next few years. The potential private
sector partner will be responsible for
designing, building, financing, operating,
maintaining, and transferring (DBFOMT) the
WtE plant, which has a proposed capacity of
1,000 tonnes/day of municipal solid waste.
175
Project Digest
2. The Opportunity
A new and improved scheme for solid waste management and operations is required for
Semarang City. The volume of incoming MSW to TPA Jatibarang, which is estimated to be 1,126
tonnes/day in 2020, will nearly double to 1,938 tonnes/day by 2040. Furthermore, existing
activities at TPA Jatibarang have been deemed inadequate to reduce waste disposal.
As stated in Perpres No. 3/2016, Appendix point L, in conjunction with Perpres No. 58/2017, the
proposed Semarang WtE facility is classified as a PSN. It is also part of the Committee for the
Acceleration of Priority Infrastructure Delivery (KPPIP) Priority Project list, based on the
Coordinating Ministry for Maritime Affairs (CMMA) Regulation No. 5/2017. Moreover, Semarang
is on the list of cities under Perpres No. 35/2018 that will be supported by the Central
Government in developing a WtE facility which is based on environmentally friendly technology.
176
2.2. Project Description
The proposed site’s distance from the waste catchment area (Semarang City) supports
effective waste transportation since Jatibarang is only located 11 km west from the Semarang
City Centre (Simpang Lima) and is accessable via sealed roads. Total land available for the
proposed project is approximately 4.2 hectare. TPA Jatibarang will continue to accommodate
MSW at predicted rates until the Project is operational, as well as during the Project’s
operational phase, to accommodate rejected materials. The potential private sector partner
will be responsible for designing, building, financing, operating, maintaining, and transferring
(DBFOMT) the WtE plant, which has a proposed capacity of 1,000 tonnes/day of municipal solid
waste (MSW).
At this stage, PLN suggests that the IBE will be responsible for designing, building, operating,
and maintaining the transmission line until the end of the concession period. This is to be
further discussed with PLN and GCA.
4. Technical Specification
1. Provide reception facilities that can quantify and monitor the quantity and quality of waste
delivered to the facility;
2. Process ± 1,000 tonnes/day of MSW through the facility;
3. Divert a minimum of 80% on a mass basis of Accepted MSW from landfill per year through
the facility; and
177
4. Operate for 20 years and meet, at a minimum, the equivalent of the higher of international
or Indonesian environmental standards for air emissions.
The GCA has completed AMDAL and obtained an Environmental License. The technical planning
for the Project (including the design criteria) must comply with this Environmental License.
Within the permitted scope of the Environmental License is construction of a 16MW WtE power
plant in TPA Jatibarang. In addition, among the permitted technology for a WtE power plant is
an incinerator that operates on 4 ha land with a capacity of 38 tonnes/hour and a waste volume
of 1,020 tonnes/day. The applicable environmental standards (e.g. emission standards, residual
waste treatment, leachate water treatment, etc.) must also be noted. Upon the execution of the
PPP Agreement, the IBE will be responsible to carry out any necessary updates or
amendments to the Project’s AMDAL documentation and Environmental License according to
the IBE’s committed technical and financial solutions.
The nominated site for the WtE plant will be located within TPA Jatibarang, which is currently
owned by the GCA. Accordingly, no land acquisition is anticipated to be required, except for
certain rights of way for land access, or the placement of pipes and cables (including but not
limited to the transmission line).
The project is indicated to require government support in the form of Tipping Fee and
potentially be guaranteed by the Indonesia Infrastructure Guarantee Fund (IIGF).
9. Contact Information
178
DEVELOPMENT OF PIYUNGAN LANDFILL
Location : Bantul, Yogyakarta Province
Description:
The project aims to develop current landfill
(TPA) waste management system in Piyungan
Landfill. Private partner shall be responsible to
finance, design, construct, operate, and
maintain Piyungan Landfill.
Financial Feasibility:
IRR : Under Calculation
NPV : Under Calculation
179
Project Digest
180
2. The Opportunity
• The capacity of waste landfill (TPA) has been exceeded while there is an increase in the
volume of waste that enters Piyungan Landfill, therefore appropriate technology and
professional operation management are necessary.
• Insufficient land capacity in Piyungan Landfill to treat domestic waste and the absence of
waste treatment to reduce the amount of domestic waste.
• Inadequate infrastructure in Piyungan Landfill.
• Average amount of waste that managed by Piyungan Regional Waste Landfill from
Yogyakarta City, Sleman Regency, Bantul Regency is 650-700 ton/day
• The area of Piyungan Landfill is 12.5 ha, which 10 ha used for landfill land area that consist
of 3 cells and another 2.5 ha used for supporting facilities (offices, workshops,
weighbridges, and buffer zone).
• There was an expansion of new land of approximately 1,9 ha. This expansion land is
planned to be used for new waste treatment technology. On 2020, Local Government will
add new land approximately 3,1 ha.
• The landfill area that can be filled with waste is ± 72.620.83 m2 (in 2017). However, this
landfill area is estimated to be full in 2019.
• The project scope includes:
a. New waste treatment technology (Anaerobic Digester / Refuse Derived Fuel / etc.).
b. Methane gas production from waste processing that can be used as Incinerator or
RDF energy
c. Waste sorting and processing facility
d. Landscape arrangement from its area & maintenance
e. Closed existing landfill
f. Operate and maintain Piyungan Landfill
The potential scope of partnership that can be carried out by investors, but not limited to the
following, are:
181
4. Technical Specification
This project aims to manage domestic waste based on the following regulations:
The area of Piyungan Landfill is 12.5 ha, which 10 ha used for landfill land area that consist of
3 cells and another 2.5 ha used for supporting facilities (offices, workshops, weighbridges, and
buffer zone). There was an expansion of new land of approximately 5 ha ( 1,9 ha of land has
been acquired and 3,1 ha will be acquired in 2020).
• Land provision, DIY Government provides land for construction of the project in Sitimulyo
village, Piyungan.
• Permittance, the government is committed to provide necessary permits for the investors
in the implementation of this project.
• Support for central government (Ministry of Public Works and Housing) in optimalization
of Piyungan landfill and improving supporting facilities
• Support in the policy on building an integrated waste management infrastructure.
To mitigate the project’s risks from changes in demand risk and shifts in political scenario,
government guarantee may be required. In this regard, the level of risk perceived from
investors will be determined at market sounding.
182
9. Contact Information
Position : Assistant for Economic Affairs and Development of the Regional Secretariat
Email : [email protected]
Email : [email protected]
183
INTEGRATED HAZARDOUS AND SPECIFIC WASTE MANAGEMENT FACILITY IN SUMAPAPUA
Location : South Sulawesi Province
Description:
The amount of hazardous waste that can be
managed is still inadequate compared to the
production of hazardous waste for each year,
so that hazardous waste management services
are still needed. This project it to develop
Integrated Hazardous and Specific Waste
Management Facility in Sumapapua Area with
PPP scheme. The Project scheme implemented
will be build-operate-transfer.
184
Project Digest
1. The Opportunity
The types of industrial waste that often cause environmental problems and are difficult to treat
are those that fall into the category of hazardous and toxic materials (Bahan Berbahaya dan
Beracun / “B3”). To process this type of waste, in addition to requiring high technology, it also
requires rather expensive investment and operational costs. B3 waste, when it is discharged
directly into the environment, has the potential to cause adverse impacts and is accumulative
in nature.
The amount of B3 waste that can be managed is still inadequate compared to the production
of B3 waste for each year, so that hazardous waste management services are still needed.
Integrated B3 waste management facilities currently exist only in Java with a capacity of
250,000 - 300,000 tonnes per year. Another large utilization facility is in West Java and has a
utilization capacity of 300,000 tonnes per year. Some types of B3 waste that cannot be
managed by third parties in specific regional locations outside Java must be sent to Java which
causes the cost of B3 waste management to be expensive.
B3 waste management that is adequate and efficient may be done collectively, namely by
building a B3 Waste Management Center. B3 waste generated from industry is first separated
from other non-B3 waste, then sent to the Hazardous Waste Management Center. At this
facility, the waste is treated, recyclable materials are reused and those that cannot be recycled
are processed through various treatment methods. B3 Waste Management Center needs to be
built on a location that meets specific technical requirements so that the risk of pollution
impacts that may be caused by this activity can be minimized. Considering the substantial risks
posed by B3 Waste, the government is trying to manage B3 Waste in a comprehensive,
integrated, and sustainable manner. Therefore, the Integrated Hazardous and Specific Waste
Management Facility in Sumapapua Area is developed.
185
form of user charge, that is a payment from the users during the 15 years of cooperation period.
The Project scheme implemented will be build-operate-transfer.
1. To prevent and cope with the environmental pollution/damage caused by the hazardous
waste and the recovery of the environmental quality that has been polluted, so it is suitable
with its origin function;
3. Accelerating the procurement of the Hazardous Waste Management and Specific Waste
on a large scale.
Business entity shall be responsible for the management of hazardous and specific waste,
including storage, collecting, transporting, processing, utilization, and stockpiling, as
elaborated on the Project Technical Specification during concession period. The Project
scheme implemented will be build-operate-transfer.
However, considering the land availability, potential location of users, and existing
transportation business, it is necessary to reassert the following in carrying out the finalization
of the scope of services:
2. The possibility of carrying out the transportation activities in accordance with the licenses
issued by the Regional Government.
3. The possibility of land being provided by the Regional Government for the use of Transfer
Station in each service area, so the services provided by Business Entity in the Project did
not include the provision of the Transfer Station.
4. The possibility of the inclusion of a specific waste (e-waste) into one of hazardous waste
to be managed.
3. Technical Specification
No Item Specification
1 Storage The activity of temporarily storing the
hazardous waste carried out by the
hazardous waste producers
2 Collecting Collecting hazardous waste from the
hazardous waste producers before it is
submitted to the hazardous waste users,
processors, and/or hoarders
186
No Item Specification
3 Transporting Transporting hazardous waste from the
waste collector or producer to the
processing facility
4 Processing Process to reduce and/or eliminate the
hazardous and/or toxic nature of the waste
5 Utilization Reuse, recycling and/or recovery activities
aimed to turn the hazardous waste into a
substitute product to a safe material for
human health and the environment
6 Stockpiling Placing the hazardous waste on the landfill
facility so it doesn’t endanger human health
and the environment.
The Project falls under the ‘Hazardous Waste management service industry which conducts a
combination of 2 (two) or more activities including utilization, processing and/or landfilling of
the Hazardous Waste’ category, which required an AMDAL. The AMDAL needed is a Category
A AMDAL (if the stockpiling is included).
No land acquisition is needed. The Project will be conducted on a Local Government Owned
Property.
• Government Support: The Project does not apply for any Government Support.
• Preparation and Transaction Facility: The Project is applying for a Project Development
Fund (PDF) to the Ministry of Finance.
187
8. Contact Information
Name : Rohimah
Email : [email protected]
188
INTEGRATED HAZARDOUS AND SPECIFIC WASTE MANAGEMENT FACILITY IN SUMATERA
Location : North Sumatera Province
Description:
This project Is to develop the Integrated
Hazardous and Specific Waste Management
Facility in Sumatera Area with PPP scheme.
The Project scheme implemented will be build-
operate-transfer.
Financial Feasibility:
IRR : 14.27 %
NPV : USD 24.12 Million
189
Project Digest
1. The Opportunity
The types of industrial waste that often cause environmental problems and are difficult to treat
are those that fall into the category of hazardous and toxic materials (Bahan Berbahaya dan
Beracun / “B3”). To process this type of waste, in addition to requiring high technology, it also
requires rather expensive investment and operational costs. Many industries have not been
able to do their waste treatment because of these constraints, and it is feared that some
industries dispose of their waste carelessly. B3 waste, when it is discharged directly into the
environment, has the potential to cause adverse impacts and is accumulative in nature so that
the levels become increasingly significant.
B3 waste management that is adequate and efficient may be done collectively, namely by
building a B3 Waste Management Center. B3 waste generated from industry is first separated
from other non-B3 waste, then sent to the Hazardous Waste Management Center. At this
facility, the waste is treated, recyclable materials are reused and those that cannot be recycled
are processed through various treatment methods. B3 Waste Management Center needs to be
built on a location that meets specific technical requirements so that the risk of pollution
impacts that may be caused by this activity can be minimized. Considering the substantial risks
posed by B3 Waste, the government is trying to manage B3 Waste in a comprehensive,
integrated, and sustainable manner. Therefore, the Integrated Hazardous and Specific Waste
Management Facility in Sumatera Area is developed.
The development of the Integrated Hazardous and Specific Waste Management Facility in
Sumatera Area with PPP scheme is to manage of hazardous and specific waste, including
storage, collecting, transporting, processing, utilization, and stockpiling, as elaborated on the
Project Technical Specification. The Business Entity will receive a return of investment in the
form of user charge, that is a payment from the users during the 15 years of cooperation period.
The Project scheme implemented will be build-operate-transfer.
190
1. To prevent and cope with the environmental pollution/damage caused by the hazardous
waste and the recovery of the environmental quality that has been polluted, so it is suitable
with its origin function;
3. Accelerating the procurement of the Hazardous Waste Management and Specific Waste
on a large scale
Business entity shall be responsible for the management of hazardous and specific waste,
including storage, collecting, transporting, processing, utilization, and stockpiling, as
elaborated on the Project Technical Specification during concession period. The Project
scheme implemented will be build-operate-transfer.
However, considering the land availability, potential location of users, and existing
transportation business, it is necessary to reassert the following in carrying out the finalization
of the scope of services:
2. The possibility of carrying out the transportation activities in accordance with the licenses
issued by the Regional Government.
3. The possibility of land being provided by the Regional Government for the use of Transfer
Station in each service area, so the services provided by Business Entity in the Project did
not include the provision of the Transfer Station.
4. The possibility of the inclusion of a specific waste (e-waste) into one of hazardous waste
to be managed.
3. Technical Specification
No Item Specification
1 Storage The activity of temporarily storing the
hazardous waste carried out by the
hazardous waste producers
2 Collecting Collecting hazardous waste from the
hazardous waste producers before it is
submitted to the hazardous waste users,
processors, and/or hoarders
3 Transporting Transporting hazardous waste from the
waste collector or producer to the
processing facility
4 Processing Process to reduce and/or eliminate the
hazardous and/or toxic nature of the waste
5 Utilization Reuse, recycling and/or recovery activities
aimed to turn the hazardous waste into a
191
No Item Specification
substitute product to a safe material for
human health and the environment
6 Stockpiling Placing the hazardous waste on the landfill
facility so it doesn’t endanger human health
and the environment.
The Project falls under the ‘Hazardous Waste management service industry which conducts a
combination of 2 (two) or more activities including utilization, processing and/or landfilling of
the Hazardous Waste’ category, which required an AMDAL. The AMDAL needed is a Category
A AMDAL (if the stockpiling is included).
No land acquisition is needed. The Project will be conducted on a Local Government Property.
• Government Support: The Project does not apply for any Government Support.
• Preparation and Transaction Facility: The Project is applying for a Project Development
Fund (PDF) to the Ministry of Finance.
8. Contact Information
Name : Rohimah
Email : [email protected]
192
UNDER
PREPARATION
PROJECTS
Telecommunication and
Informatics:
1. Development of Modern Land
Registry Information System
DEVELOPMENT OF MODERN LAND REGISTRY INFORMATION SYSTEM
Location : National
Description:
The objective of the project is to improve public
service in land affairs through development of
Modern Land Information System. Modern
Land Information System development in land
affairs focus on transformation from
conventional to electronic service (website and
mobile apps), through implementing advance
technologies to support Accelerated Systemic
Land Registration (PTSL) project target and 100
percent land certificates in Indonesia by 2025.
193
Project Digest
194
2. The Opportunity
The Ministry of Agrarian Affairs and Spatial Planning / National Land Agency (ATR/BPN) plans
to develop Modern Land Information System (LIS) to improve public service in land affairs. The
land service transformation from conventional to electronic service through smart device of
both website and mobile applications as well as current technological infrastructure support
its expected to be assist the national priority program in accelerate land services to the public,
improve the EODB rating and increasing state revenue. The development of modern land
information system will be carried out under the public private partnership scheme.
Information system for land management services that integrates Ministries and Institutions
related to land management and can be accessed by ATR / BPN partners and the community
through smart devices both websites and mobile apps. There are 118 land service activities
that are divided into 15 categories of land service management. Integration of Modern Land
Information Systems with ministry systems and other institutions. Easy access to land
information for the community and ATR / BPN partners through mobile devices. Integrated
Internal Application System at the Ministry of ATR / BPN with Command Center monitoring
media. And with the Latest Information Technology and Computer Infrastructure (ICT) support.
The project aims to transformation of land services through the development of modern land
information systems.
Private partners shall be responsible to develop land information system, DC and DRC
infrastructure improvement and maintenance, hardware procurement, helpdesk and support,
digitalization and validation land document. Within this scope of responsibility, private
investment will be returned in the form of an Availability Payment (AP) scheme for 15 years
with 14 percent of Return on Investment (ROI).
195
4. Technical Specification
4. Command Center
• Developing and Building Command Center
• Command Center Operation
196
10. Hardware Procurement
• Hardware Procurement Helpdesk
• Command Center Equipment Procurement
• Strengthening of DC / DRC ICT Infrastructure
• Procurement of Document Digitizing Devices
Not Needed.
Not Needed.
The indicative government support for modern LIS Development Project are written below:
• Licence and Permit support: need for adjustment of Government Regulations regarding
types and tariffs for types of Non-Tax Revenues applicable to the Ministry of ATR / BPN
• The need to prepare a Memorandum of Understanding (MoU) with other ministries and
state institutions related to the cooperation in data and information sharing.
To mitigate the project’s risks from changes in demand risk and shifts in political scenario,
government guarantee required. In this regard, the level of risk perceived from investors will
be determined at market sounding.
9. Contact Information
Phone : +62 21-7222951 / +62 858 1478 8839 / Fax. +62 21-7222951
Email : [email protected]
197
UNDER
PREPARATION
PROJECTS
Urban Facility:
1. Provision of Kuta Integrated
Utility Panel
PROVISION OF KUTA INTEGRATED UTILITY PANEL
Location : Badung, Bali Province
Description:
Badung Regency have decided to construct
underground utility ducting that integrates
several utility line in Kuta District and its
surrounding. The ducting will be in form of Pre-
Cast Concrete Box Culvert and Pipe Conduit.
The total length of the ducting will be 19,471 m
of Box Culvert and 36,656 m of Pipe Conduit.
Financial Feasibility:
IRR : 11.32%
Government Contracting Agency: NPV : USD 2.26 Million
Regent of Badung
Type of PPP: Estimated Concession Period: 25 years
Solicited
Return of Investment:
Avaliability Payment
198
Project Digest
2. The Opportunity
The need for improved utility facilities in Badung Regency is not accompanied by investment in
long term solutions. At present the installation of the urban utility network is not well
coordinated and often conflicting between one utility line and another. Thing these reduce the
comfort of the community, tourists and overall beauty of the city. Thus, Badung Regency must
be able to provide integrated utility network which is serviceable, efficient and reachable by
the public. This also becomes one indicator of a modern city on international standard.
Therefore, Kuta Integrated Utility Panel Development is the solution in dealing with the problem
of utility networks in Badung regency.
The construction of Kuta Integrated Utility Panel is the development of underground utility
network intended especially for high density urban areas and tourism hotspot. As the utilitiy
network is in underground, it needs to use a ducting system. Underground ducting is a way to
place any number of public utility lines such as electricity, water, telecommunications, gas,
199
etc. Before constructing the underground ducting, it is necessary to review the following
aspects:
1. Aesthetics
2. Maintenance
3. Development
4. Convenience
5. Lifespan / lifetime
The ducting model for underground utility line can take several forms such as:
1. Sleeve (conduit),
2. Round shape and box shape.
It must be adapted according to several aspects such as: space requirements, construction
method, maintenance and ease of obtaining material. For Kuta Integrated Utility Panel, it is
decided that there will be several sections, primarily in Kuta District, that use Pre-Cast
Concrete Box and other section in North Kuta and South Kuta District that use Sleeves or
conduit.
4. Technical Specification
The technical specifications for Kuta Integrated Utility Panel are as follow:
No Location Total
Length of Ducting
1 Kuta District (Pre-Cast 19,471 m
Concrete)
2 North Kuta District (Conduit) 18,897 m
3 South Kuta District (Conduit) 20,354 m
Number of Pole
1 Kuta District 50,352 unit
2 North Kuta District 85,187 unit
3 South Kuta District 102,573 unit
200
5. Environmental Impact Assessment (EIA/AMDAL) Findings
Kuta Integrated Utility Panel will dig underground tunnel that is then used to place the utility
network in the form cables and pipes such as electrical cables, telecommunications cables,
information, water, oil, gas or other fuels, sanitation, etc. It is planned to be built as long as
19,471 m which means that the project would need to have AMDAL to proceed as stated in
Environment Ministry Regulation No. 38/2019. The AMDAL would be completed later in
Preparation Stage.
There will be no land acquisition as all works will be done in public land.
Government support and guarantee will be determined during finalization of Final Business
Case.
9. Contact Information
Position : Head of Regional Public Works and Spatial Planning, Badung Regency
Email : [email protected]
201
UNDER
PREPARATION
PROJECTS
Energy Conservation:
1. Surakarta Street Lighting
2. Madiun Street Lighting
SURAKARTA STREET LIGHTING
Location : Surakarta, Central Java Province
Description:
The Municipal Government of Surakarta is
proposing to revitalize the PSL public services
within the city, covering 976 km city road
network. The project will be implemented in
PPP Scheme. The scheme will include PPP
agreement between the Municipal and the
Business Entity along the specified concession
period that requires the Business Entity to
finance, design, develop, operate, and maintain
the PSL service.
202
Project Digest
2. The Opportunity
One main focus of the Municipal Government of Surakarta in the local development plan
(RPJMD 2016-2021) is public services transformation, including Public Street Lighting (PSL).
The municipal is transforming the perspective of PSL from merely the provision of local owned
asset to public services. The improved PSL services within the City of Surakarta will provide
illumination on the streets of Surakarta City to enhance night-time visibility and to enhance
road traffic safety as well as security.
The recent feasibility study prepared by the municipal describes that the PSL as a public
service is not functioning optimally. The PSL services is performing inefficient electricity usage
and unstandardized poles and luminaires. In addition, the illumination has not been distributed
evenly along the existing public streets.
The Government of Surakarta is proposing to revitalise the PSL public services within the city,
covering 976 km city road network. The project will be implemented in PPP scheme in
accordance to Presidential Decree Number 38 Year 2015. The scheme will include PPP
203
agreement between the Municipal and the Business Entity along the specified concession
period that requires the Business Entity to finance, design, develop, operate, and maintain the
PSL service. The service has to comply with the national PSL standard, determined in the
Ministry of Transportation Regulation Number 27 Year 2018.
The revenue of the PPP Project Company (a company set up by the Winning Bidder) will be in
the form of Availability Payment (AP). The AP will be given to the PPP Project Company by the
Municipal Government based on the services conducted by the company and the compliance
to the service level standard specified on the PPP Agreement.
• Improved night-time visibility, resulting in enhanced road traffic safety and decreased
criminal activity for citizen;
• Reduction in cost (local budget) due to reduced electricity consumption resulting from
energy-efficient street lighting system;
The interested business entities should bring their knowledge and expertise on the street
lighting services to provide the most competitive offers. The Municipal Government has
conducted studies related to the total street length, estimated capital expenditure, operating
and maintenance expenses, regulation compliances, value for money and the attractiveness
of availability payment mechanism. According to the survey result performed in early 2019, the
total light points identified were more than 20,000 units. Whereas, the current feasibility study
shows that ideally the city needs around 64,000 units. However, for the scope of the project,
the Municipal Government plans to provide 22,000 units of street lighting points.
4. Technical Specification
In accordance with the national environmental safe-guards regulation, The PPP Surakarta
Public Street Project requires to prepare UKL-UPL as a safeguard document. The
implementing unit has completed the development process of the project’s document,
204
including a public consultation (community representatives and relevant local agencies) and
series of technical meeting. On June 2019, the environmental permit for the project has been
issued.
The project scope includes the development of PSL system on the government-owned roads
which has available space for PSL infrastructure. Therefore, there is no land acquisition for
this project.
9. Contact Information
Phone : +62-271-662-266
205
MADIUN STREET LIGHTING
Location : Madiun, East Java Province
Description:
Madiun Regency is one of the main investment
destinations for prospective industries in West
East Java, which borders Central Java
Province. Madiun Regency is directly well
connected to the Trans-Java toll road network
and is the main gateway for transportation
from East Java to Central Java Province. This
traffic needs to be supported by well-
maintained street lighting to support economic
activities and industrial estates, increase social
mobility and improve road safety and security.
To achieve this goal, Madiun District proposes
a PPP Project for Madiun Street Lighting.
206
Project Digest
2. The Opportunity
Madiun Regency, located in the western region of East Java Province, is a strategic area with
a traffic lane connecting Central Java. Madiun Regency has 2 interchanges on the Trans Java
Toll Road, namely Madiun Toll Gate located in Dumpil District, Sawahan Regency, and Caruban
Toll Gate located in Pilangkenceng District. Because of this, Madiun Regency economy is well
supported in terms of transportation facilities and infrastructure.
Since 2014, the central government of Madiun Regency moved from its original place in Madiun
City to the Capital of Caruban, one of the new economic centers in Madiun Regency. Madiun
Regency is one of the regions commonly referred to as the Mataraman region and included in
the Wilis Selingkar Region as regulated in Presidential Regulation Number 90 Of 2019, which
207
in this case Madiun Regency has huge potential to be developed in investment. But this
condition is caused by street lighting facilities because it is still very minimal and many are
still using old technology which consequently has an impact on increasing the costs incurred
for maintenance. Therefore, a new modern street lighting system is needed to support
economic activities in Madiun. This project is very potential and received appreciation from the
community and support from the National Electricity Company (PLN).
The Madiun Regency Government is proposing to revitalize the street lights within the regency,
covering 809.32 km of road consisting of national roads, regency roads, and rural streets. The
project will be implemented in the PPP scheme under Presidential Decree Number 38 the Year
2015. The scheme will include PPP agreement between the regency government and the
Business Entity that is responsible for designing, building, financing, maintaining, and transfer
back the asset to the government after the concession period ends.
The revenue of the special purpose company (SPC) will be in the form of Availability Payment
(AP). The AP will be given to the SPC by the Regency Government based on the services
conducted by the company and the compliance to the service level standard specified on the
PPP Agreement.
• Supporting and growing economic, social activities in the region especially from the
tourism and manufacturing industries
4. Technical Specification
7,859 streetlights will be installed in both national roads and regency roads, while 4,641
streetlights will be installed in rural streets across 206 villages. Detailed specification will be
determined in OBC/FBC.
208
6. Land Acquisition and Resettlement Action Plan
The Madiun Regency Government will provide the land needed for the project which is spread
over 15 sub-districts and 206 villages. The project will cover national roads, district roads and
rural roads in Madiun Regency.
Local government will support this project on land acquisition and permit processing. While
the central government will support by means of project facilitation and capacity building
during the preparation stage. Other government support and guarantee will be identified in the
OBC/FBC.
9. Contact Information
Phone : 0351-451145
Email : [email protected]
209
UNDER
PREPARATION
PROJECTS
Zoning:
1. Teluk Bintuni Industrial Zone
2. Development of Jogja Agro
Park
TELUK BINTUNI INDUSTRIAL ZONE
Location : Teluk Bintuni, West Papua Province
Description:
210
Project Digest
2. The Opportunity
Teluk Bintuni Regency has an abundance of natural resources especially oil and gas resources.
Oil and Gas resources there have been exploited by various companies both national and inter-
national and generate a large amount of revenue to the government of Indonesia.
Most of the resources here are exported in the form of natural gas or oil without further
processing. This practice while still economically viable and profitable, can be improved if
there is a processing plant nearby, creating an added-value product that can increase revenue
for Indonesia. So, there is a need to have an industrial zone dedicated to processing the natural
resources in Teluk Bintuni Regency, so the economic aspect of processing natural gas is still
efficient and creates a new economic growth node in the eastern side of Indonesia.
The first phase of industrial zone development will be focused on the methanol plant that is
designated to be an anchor tenant in the industrial zone. Methanol plant will process natural
gas supplied from BP Tangguh refinery nearby and then be exported or used by other tenants
in the industrial zone.
211
BP Tangguh has indicated to supply up to 90 mmscfd of natural gas in the first phase. This plan
is added with potential to supply another 90 mmscfd of natural gas in 2026 when another tenant
has arrived, and methanol demand increases. In addition, there are 200 MMSCFD potential
supply from Getting Oil Kasuri Ltd. Which as of now focuses on on-shore development and no
LNG plan.
Methanol plant is expected to churn out about 900 mtpa of methanol in its first phase of
development. In the future, the industrial zone will be designated as a center for the
petrochemical industry in Indonesia.
The construction of Teluk Bintuni Industrial Zone is planned to use PPP scheme with a return
on in- vestment of a business entity will be done by Availability Payment, and is offered to a
business entity that has the potential to build and operate all facilities, and transfer the asset
at the end of the term of cooperation.
4. Technical Specification
In the year 2021 when the industrial zone comes to operational, it is predicted that there will
be only the methanol plant which needs a supply of 90 mmscfd natural gas with the land
requirement of 20 ha. In the second phase, possibly in 2026, it is expected the industrial zone
will add another methanol plant in conjunction with other petrochemical plants (DME, PE, or
Ammonia & Urea) which will require 90 mmscfd natural gas and 50 ha of land.
In the final phase of development, another petrochemical plant will be added that required
another 200 mmscfd of natural gas and approximately and there would be about 2112 ha of land
available for future development.
Teluk Bintuni regency is also famous for its palm oil and its potential coal reserves which could
be utilized as raw material for various industries. Hence the development for future
petrochemical complex is widely open and sustainable.
Environmental Impact Assessment report is being prepared up to the day this book is
published.
212
6. Land Acquisition and Resettlement Action Plan
Land acquisition for 50 ha of Teluk Bintuni Industrial Zone is being carried out by the Teluk
Bintuni Regency Government.
GCA has acquired Project Development Fund (PDF) as of 24 January 2020 for the preparation
of Final Business Case (FBC) and transaction assistance. Government guarantee will be
determined in the Final Business Case.
9. Contact Information
Name : Triyani
Email : [email protected]
213
DEVELOPMENT OF JOGJA AGRO PARK
Location : Kulon Progo, Yogyakarta Province
Description :
Jogja Agro Park (JAP) is expected to be model
that can serve as a beneficial agribusiness
learning unit (incubator). Private partners
shall be responsible for constructing some
facilities to accomplish the site plan, as well
as conducting agribusiness researches and
development, and at the same time
establishing a partnership through contract
farming, offering consultation for farmers, and
maintain management of Jogja Agro Park.
214
Project Digest
215
2. The Opportunity
The conversion of agricultural land in DIY into settlement continued to occur, which resulted
in smaller ownership of private agricultural land. There still farmers who faced difficulties in
developing quality agricultural products and agribusiness activities, which results in low
farmer income. The impact is that the interest of young generation to become farmers is
decreasing. However, this will threaten national food security.
To solve the problems above, a pilot model, education, production, marketing as well as
superior and sustainable agriculture-based tourism is needed. Therefore, the Government of
DIY plans to develop Jogja Agro Park as an incubator for farmers towards better income, while
educating integrated farming to reduce land use change.
The JAP Project located in Wijimulyo, Nanggulan, Kulon Progo Regency covering an area of
18.8 Ha. The project combines an ecotourism concept and a specific interest (agriculture-based
education) that functions as a unit of agribusiness entrepreneurship learning installation to
carry out the idea of agribusiness incubation. Agribusiness entrepreneurship learning is
designated to provide incubator service users (tenants) with facilities in accessing and utilizing
information on mobile application, agro-inputs, markets, finance, and other resources
according to the tenants need respectively, in real situation and for a certain period.
1. Paddy rice field of 6.93 hectares on the north side of the street and another 4.57
hectares on the south side (situated behind the JAP building area)
2. Existing facilities and buildings built by DIY Government budget such as Office Area,
Training Hall, Dormitories, Production Shed, Greenhouse, etc.
The project aims to increase farmers' revenue hence it may reduce agricultural land
conversion.
Private partners shall be responsible for constructing some facilities to accomplish the site
plan, as well as conducting agribusiness researches and development, such as:
a. Develop business agriculture facilities
• agribusiness incubator
• integrated and healthy farming
• contract farming (partnership with local farmers)
• agriculture training centre
b. b. Develop ecotourism facilities
• ecotourism
• mass tourism
• MICE (Meeting, Incentive, Convention, and Exhibition)
216
4. Technical Specification
Jogja Agro Park (JAP) is expected to be one agro-based industry that has function:
1) Design, build and finance the construction of the Jogja Agro Park area with a total land
area of 18.8 hectares (ha).
• zone A land area of 7.32 Ha: can be designed, built, operated, for the commercial of
agriculture and tourism; and repaired existing buildings façade;
• zone B land area of 6.93 Ha: land function as a sustainable food agriculture area is
maintained;
• zone C land area of 4.57 Ha: land function as a sustainable food agriculture area is
maintained, but can be commercialization such as building boardwalks, viewing decks
and restaurants.
2) Horticultural plants, flowers, and other plants that already exist in Zone A, can be replaced
with other plants, if the time the plants can no longer produce.
3) maintain ruminants, poultry, rabbits and fish that already exist in Zone A and are developed
as components in integrated farming.
4) establishing of contract farming by develop partnership with local farmers to improve
agricultural production in land area of 22,287 ha.
5) building facilities for incubator agribusiness.
6) building facilities for integrated and healthy farming: application for environmentally
friendly technology, zero waste and LEISA (low external input sustainability agriculture)
7) building facilities for development of upstream-downstream farming activities in the food
crops, horticulture and animal husbandry.
8) build an agro market and marketing agricultural commodities from local farmers
9) building facilities for agricultural training, compiling agricultural training modules and
conducting agricultural training.
Environmental Impact Assessment (EIA) has been completed and approved by the AMDAL
Committee in 2018. Environmental management must be carried out during the construction
and operation of the JAP.
Land owned by Local Government of DIY, situated in Wijimulyo Village, Nanggulan District,
Kulon Progo Regency is available, of 18.8 Ha. Up to the present moment, the land has been
used for food crop seed planting area (especially paddy seed) conducted by the the Seed
Development and Production Technical Unit (UPT BPPTPH) under the Agriculture Office of
DIY. An area of 7.32 ha is planned to be allocated for PPP of JAP Development.
217
8. Government Support and Guarantee
The indicative Government support for JAP Development Project are written below:
• Building Permit: Kulon Progo Regency Government provides permits needed by private
investors in the implementation of the JAP Development Project
• Support for the provision of land: land is available.
• Support from the Agriculture Agency/Ministry of Agriculture: facilitate the farmers to
follow the training in JAP with the DIY’s budget, technology support, and various
agricultural materials needed in JAP operations.
To mitigate the project’s risks from changes in demand risk and shifts in political scenario,
government guarantee required. In this regard, the level of risk perceived from investors will
be determined at market sounding.
9. Contact Information
Position : Assistant for Economic Affairs and Development of the Regional Secretariat
Email : [email protected]
Email : [email protected]
218
UNDER
PREPARATION
PROJECTS
Tourism:
1. Development of Ngawi
Agrotourism
DEVELOPMENT OF NGAWI AGRITOURISM
Location : Ngawi, East Java Province
Description:
Ngawi Agritourism is the manifestation of
creative economy in the agricultural sector
that can provide added value to agribusiness
ventures in improving the welfare of farmers.
Some positive impacts of the agritourism
development are, increasing the sale value of
agricultural commodities and providing
additional source of income for the farmers,
e.g: homestay rentals and others.
219
Project Digest
The Suitability of the Purposed PPP Project Location with Regional Spatial Plans of Ngawi Regency
2. The Opportunity
The purpose of the Ngawi Agritourism development is to support the agricultural sector of
Ngawi Regency. Tourism activities is becoming the added value of product diversification in
agribusiness. Thus, Agritourism can be the source of new growth, to boost agricultural
productivity in the economic sector.
Hence, Ngawi Agritourism can be envisioned as the new development area that will support
the improvement of the farmers’ welfare through promoting agricultural products (increasing
the sale value of agriculture commodities) , cultural attraction as well as hospitality services
(homestay rentals). In addition, Ngawi agritourism is can be used to promote agricultural and
cultural products of Ngawi.
The vision of Ngawi Agritourism in principle is to improve the welfare of farmers and
community through the concept of agricultural development in accordance with its potential
and needs. The priority of the agritourism is to add value in agricultural supply chain to
220
strengthen and enhance local economic resources. This can be achieved through government
involvement with possible cooperation support with private parties / investors.
The examples of economic opportunities that can be developed in Agritourism are multiple
systems cropping between daily harvests such as poultry, dairy cows, seasonal harvests such
as corn, rice, monthly harvests such as fish, annual harvests such as fruit, cattle, etc. This
pattern is suitable to be developed in the Ngawi’s local community with the result of helping
farmers to have multiple income stream as an addition to annual income from regular
harvests.
1. To become a recreation spot for tourist whilst expanding their knowledge on agriculture.
2. To increase farmers' incomes while maintaining local culture and technology (indigenous
knowledge) which generally have attuned to the conditions of the natural environment.
4. Technical Specification
No Facilities Capacity
1 Area 12 hectares
2 Facilities 1. Agribusiness Incubation Facilities
2. Green House
3. Aquaponic Facilities
4. Pond/Reservoir
5. Plaza
6. Agricultural & Fisheries Facilities
7. Viewing Post/Station
8. Lodging Facilities (Hotel)
9. Meeting Room
221
5. Environmental Impact Assessment (EIA/AMDAL) Findings
According to preliminary study, the area of land needed is 12 hectares with access to basic
infrastructure. Some of the land is owned by Ngawi Regency, while others owned by the local
community which are ready to be included in land acquisition process. The land use for
development of agritourism is inline with the Regional Spatial Planning (RTRW).
GCA will be responsible for land acquisition for the project and will support the SPC during the
permit and licenses process. It is also indicated during preliminary study that this project will
need government guarantee from IIGF.
Further government support and guarantee requirement will be determined in the preparation
stage.
9. Contact Information
Phone : 082132327494
Email : [email protected]
222
UNDER
PREPARATION
PROJECTS
Description:
The Project is on providing marine research
support services, including: invest on two
research vessels; construction and operation
management of a new hangar, a warehouse,
laboratories and an office building for SPC at
an area of about 20,000 sqm on LIPI Science
Park in Cibinong, West Java, as well as
operation of fleet management unit (FMU) of
both the Indonesian Institute of Sciences' (LIPI)
research vessels and SPC’s own vessels.
223
Project Digest
2. The Opportunity
LIPI is eager to upgrade the level of marine research support services into international
standard, by providing services of research vessels in particular. At present, there are several
circumtances that prevent LIPI to do this effort so far. These include state budgeting
procedures and inappropriate unit cost applied to meet the international standard. There are
many cases of unexpected failure of instrument or equipment that could not be repaired
because the any budgeting should be proposed a year before. This led to delays in repair and
maintenance procedure. As a result, the quality of the vessel become worse and scheduling
become difficult. On the other hand, unit cost applied in state budget is to maintain the vessel
224
is far below the the international standards. Therefore, Third party participation from private
sector is needed.
In addition to that, available research vessels have been in operation for more than 30 years
and need improvement. Moreover, the coverage of Indonesian ocean is too large to be explore
with existing research vessels. Hence, the number of research vessels needs to be increased.
Those situations alone would justify LIPI to engage private sector to share risk by offering
benefits to the private sectors. Therefore, LIPI not only can manage both of operation and
maintanace of the research vessels, but also expand its marine research coverage alongside
partnership with the international research society. Moreover, the operation of the research
vessels will become the new business that comply with international standard through private
sector handling.
In placing the activities of fleet management of research vessels that well equipped with
supports of laboratories related to related marine research, LIPI will invite the partner of
private sector to manage National Maritime Research Zone (Kawasan Riset Kelautan Nasional
– KRKN) within LIPI Science Park in Cibinong through PPP scheme.
The project aims to provide marine research services that comply with international standard
with sophisticated research vessels, laboratories, data/sample processing and analysis for
sustainable use of Indonesian marine resources in Indonesian Exclusive Economic Zone and
its surroundings.
SPC will handle the operation and maintenance of the research vessels, equipments,
laboratories, and human resources. allowing LIPI to focus on expanding marine research and
technology through joint research with regional/international partners in Indonesia as well as
abroad.
Private sectors shall be selected to become partner in establishing Special Purpose Company
(SPC) and contract will be prepared for constructing the facilities and an office building
according to the site plan. Some business entities will have an opportunity in the field, such
as:
• fleet management;
225
• marine research and survey;
• building constructions;
4. Technical Specification
The scope of the National Maritime Research Zone operations are as follows:
• To support the research in the field of marine geoscience, atmosphere- ocean relation,
fishery, and hydrography.
• To provide customer services that would cover: marine data acquisitions and processing.
Land side of the National Maritime Research Zone is about 20.000 sqm, less than 50.000 sqm
for the minimum limit imposed to have Environmental Impact Assessment (EIA). It is located
within a science park area. However, laboratory activities and the transportation of the
laboratory chemicals as well as samples might have to be conducted according to the proper
conduct of handling hazardous and toxic substances. Document of Environmental Management
Efforts and Environmental Monitoring Efforts (RKL/UPL) should be carried out during the
construction and operation of the KRKN.
Land, an area of about 20.000 sqm, owned by LIPI (Indonesian Sciences Institute), situated in
Cibinong at LIPI Science Park (total of 108 ha), at km 46 on the Main Road of Jakarta – Bogor,
Bogor Regency, Province of West Java.
226
Up to the present moment, the land is vacant and no resettlement will be required. The location
is nearby buildings for fishery cultivation of Ministry of Marine and Fishery. LIPI will deliver
"clean and clear" status of the area required by SPC to obtain related permission and construct
the buildings on the designated land, accordingly to the PPP agreement.
LIPI will provide two research vessels that consist of retrofitted KR Baruna Jaya VIII and a new
research vessel for the SPC to initiate and manage the services.
LIPI will act as GCA will guarantee of 360 voyage days a year for SPC on first and second year
of operation
9. Contact Information
Email : [email protected];
227
UNDER
PREPARATION
PROJECTS
Health:
1. Construction Of Class A
Regional General Hospital In
Central Kalimantan
CONSTRUCTION OF CLASS A REGIONAL GENERAL HOSPITAL IN CENTRAL KALIMANTAN
Location : Central Kalimantan Province
Description :
The ratio of beds to 1,000 inhabitants in Central
Kalimantan Province is still below the ideal
ratio. This project is to increase the bed
capacity of dr. Doris Sylvanus Regional
Hospital, a provincial-owned hospital to 400
beds and improve the hospital class from Class
B Hospital to Class A Hospital.
228
Project Digest
1. The Opportunity
One indicator of the healthcare service of a country is the availability of public health facilities.
This availability can be observed from the ratio of hospital beds to the population, that is, one
bed for every 1,000 people. The number of beds available in Central Kalimantan Province is
2,425 beds distributed in 26 hospitals in the Regency / City. Since the total population of Central
Kalimantan Province in 2018 was 2,660,209 people, then the ratio of hospital beds to the
population was 0.91.
The ratio of beds to 1,000 inhabitants in Central Kalimantan Province is still below the ideal
ratio, and this shows that there is still a shortage of 236 beds to reach the ideal ratio. As a
solution to overcome the shortage of beds in Central Kalimantan Province, dr. Doris Sylvanus
Regional Hospital will increase the bed capacity to 400 beds and improve the hospital class
from Class B Hospital to Class A Hospital.
This project is to increase the bed capacity of dr. Doris Sylvanus Regional Hospital, a
provincial-owned hospital to 400 beds and improve the hospital class from Class B Hospital
to Class A Hospital with PPP scheme. The Business Entity will receive the return of investment
in the form of Availability Payment (AP) during the 20 years cooperation period paid by the
Central Kalimantan Province Government via Regional Budget (APBD). The Project will be
conducted with a build-finance-maintenance-transfer scheme.
The objectives of Class A Public Hospital of Central Kalimantan Province are as follows:
1. Improving the access to the Tertiary Referral Health Services (specialist and sub-
specialist services)
2. Fulfilling the needs of beds for the Central Kalimantan Province
229
2. Business Entity’s Scope of Work
1. Providing the design, planning, financing, procurement, supply and construction of the
class A hospital buildings and all of the infrastructure, equipment and health service
support facilities related to the building.
2. Planned preventive maintenance activities related to testing, inspection, or other relevant
activities carried out in accordance with good operational practices to maintain the
reliability of an asset, tangible/intangible objects, or an equipment as well as their
infrastructure and facilities as part of it so that the assets, tangible/intangible objects, or
the equipment may always on their finest condition.
3. Planned or unplanned curative maintenance activities, carried out in accordance with the
operational best practices to repair and/or replace parts of assets, tangible/intangible
objects, or an equipment as well as their infrastructure and facilities as part of them so
that assets, tangible/intangible objects, or the equipment may always be on their finest
condition.
Meanwhile, the hospital’s daily operational activities will be carried out by the Regional Public
Service Agency (BLUD).
3. Technical Specification
The technical specifications for Class A Regional General Hospital are as follows:
No Item Specification
1 Finance Financing by the Business Entity for the construction,
operational, and maintenance work.
2 Construction Providing the design, planning, financing, procurement,
suppl and construction of the class A hospital buildings
and all the infrastructure, equipment and supporting
facilities for the health services related to the building.
3 Preventive Maintenance activities of the class A hospital buildings, i.e.
Maintenance planned activities related to a testing, checking, or other
relevant activities carried out in accordance with
operational best practice to maintain the reliability of an
asset, tangible/intangible objects, or an equipment as well
as their infrastructure and facilities as part of it so that the
assets, tangible/intangible object, or the equipment can
always be reliable to function in accordance with their
intended purpose.
4 Curative Maintenance Maintenance activities of the class A hospital buildings,
planned or unplanned, carried out in accordance with the
operational best practice to repair and/or replace parts of
the assets, tangible/intangible objects, or an equipment as
well as their infrastructure and facilities as part of it so
that the assets, tangible/intangible objects, or the
equipment can always be reliable to function in accordance
with their intended purpose.
230
4. Environmental Impact Assessment (EIA/AMDAL) Findings
The Project falls under the ‘Building Construction’ category, which required an AMDAL. The
AMDAL needed is a Category C AMDAL.
• Government Support: The Project does not apply for any Government Support.
• Government Guarantee: The Project is guaranteed by IIGF.
8. Contact Information
Email : [email protected]
231
UNDER
PREPARATION
PROJECTS
Penitentiary:
1. Construction of Industrial
Correctional Facility in
Nusakambangan
2. Relocation of Correctional
Facility from City Downtown to
Outskirt
CONSTRUCTION OF INDUSTRIAL CORRECTIONAL FACILITY IN NUSAKAMBANGAN
Location : Nusakambangan, Central Java Province
Description:
The Project will combine correctional facility
with productive activities such as livestock
breeding. The project aims to increase the
value of prison by adding economic production
which is expected to promote regional
economic growth.
Financial Feasibility:
IRR : 13.57 %
NPV : USD 83 Million
Government Contracting Agency:
Minister of Law and Human Right Estimated Concession Period: 25 years
Type of PPP:
Solicited
Return of Investment:
Under Review
232
Project Digest
2. The Opportunity
Correctional facilities not only aim as a prison but also to serve and train inmates prior to their
release and socialize to the people afterwards. Nusakambangan Correctional Facility is
located in Tambakreja Village, Cilacap Regency in Central Java Province with the area of about
216 km2. Indonesian government initiates a partnership of this facility by optimizing
correctional institution assets with an open prison concept. The facility will be a minimum-
security prison where inmates get training and skills of farming and/or breeding livestock.
The project will combine a correctional facility with productive activities such as livestock
breeding. The geographic potential of Nusakambangan support this project as 210,000 Ha of
the island will be used for this project. Moreover, Regency of Cilacap as the related area from
233
Nusakambangan is still facing a deficit of livestock such as cattle. Thus, the project aims to in-
crease the value of prison by adding economic production which expected to promote regional
economic growth.
The project will use Built Operate Transfer (BOT) scheme. The business entity will build the
project from construction to the operation.
Revenue generated from the warden, Ministry of Law and Human Right Management, training,
live- stock and farming sales as well as other potential activity such as biogas.
4. Technical Specification
1) Correctional Facility
a. Building : 11,453 m2
b. Others : 13,000 m2
2) Livestock Facility
a. Building : 36,000 m2
b. Cattle Yard : 3,000 m2
c. Others : 14,000 m2
3) Industry : 600 m2
4) Cattle Cycle : 15,000 cattles
Currently, the project is in progress for pre-feasibility study. AMDAL activity will be decided
afterwards and provided in subsequent studies.
234
7. Project Cost Structure
Government support and government guarantee will be determined in the Final Business Case.
9. Contact Information
Position : Director of information technology and Cooperation, Ministry of Law and Human
Rights
Phone : +62-21-3857615
Email : [email protected]
Position : Head of Planning and Budgeting Departement, Ministry of Law and Human Rights
Phone : +62-21-3452155
Email : [email protected]
235
RELOCATION OF CORRECTIONAL FACILITY FROM CITY DOWNTOWN TO OUTSKIRT
Location : Under Review
Description:
PPP project to relocate Salemba Correctional
Facility that is located in Central Jakarta has
the following objectives: (i) to solve the
overcapacity in Salemba’s prison; (ii) DKI
Jakarta Spatial Plan did not accommodate
current prison location; (iii) to accommodate
the Government’s budget constraint for
building prisons.
Financial Feasibility:
Government Contracting Agency: IRR : 11.03%
Minister of Law and Human Right NPV : USD 3.50 Million
Type of PPP:
Solicited Estimated Concession Period: 15 years
Return of Investment:
Other Type of Payment
236
Project Digest
2. The Opportunity
The project “The transfer of prison technical prison units from the center of the city to the out-
skirts aims to reduce overcrowding. In the January-January period of 2017, the average
number of assisted people around 1,300 people has exceeded the capacity of the prison for
just 572 people (an average over 130% capacity level). As can be seen in the following table.
Also, along with the development of urban areas in Jakarta, there is a mismatch of placement
of buildings with the General Spatial Plan (RUTR) in each area located in the middle of urban
areas will indirectly affect the security and order in prison Salemba.
237
2.2. Project Description
The relocation of the correctional facility in Salemba that is located in Central Jakarta : (i) to
solve the overcapacity problem in Salemba’s prison; (ii) current prison condition is no longer
appropriate with the DKI Jakarta Spatial Plan; (iii) to accommodate the Government’s budget
constraint for building prisons.
At first, the plan was to relocate the facility to Ciangir on an area of 30,000 m2 which could
accommodate 5,000 prisoners, with medium security and the open camp system is needed.
But, due to prolonged asset transfer issue, the Ministry of Law and Human Rights as the GCA
has decided to relocated to other alternative location that is already owned by tha GCA. The
location that is considered are:
3. 100 ha land in Kendal owned by Kendal Open Correctional Facility (Class IIB)
4. 6 ha land in Pasir Jambu, Bogor Regency owned by Bogor Correctional Facility (Class
IIA)
Final decision regarding the location will be decided after Final Business Case Study.
The relocation of the correctional facility in Salemba that is located in Central Jakarta will be
bundled with the development of ex-correctional facility in Salemba by commercial area,
based on Presidential Regulation, 38/2015, clause 5, point 4, for increasing the feasibility of a
PPP and/ or providing additional benefits to society, a PPP may involve activities for the
provision of commercial facilities.
Forms of cooperation between the Ministry of Law and Human Right with Business Entities
has entered the preparation of OBC phase. Cooperation opportunity available for this project
is advisory transactions, bidders, and investors.
238
4. Technical Specification
Government support and government guarantee will be determined in the Final Business Case.
9. Contact Information
Position : Director of information technology and Cooperation Ministry of Law and Human
Rights
Phone : +62-21-3857615
Email : [email protected]
239
UNDER
PREPARATION
PROJECTS
Public Housing:
1. Bina Harapan Cisaranten
Housing
BINA HARAPAN CISARANTEN HOUSING
Location : Bandung, West Java Province
Description:
Development of affordable housing plus
commercial exploitation on a land parcel of 3.7
Hectares (under calculation) comprising of
four apartment towers of 20 floors each, with
an approximate potential of 2,000 housing
units.
240
Project Digest
NORTH
Development Area
Testing Area Management Building
Road Engineering Test Area
Bridge Assembly Test Area
Landslide Handling Test Area
Soil Handling Test Area
Bridge Structure Capacity Test Area
Storage Area of the Test Results and Equipment
Test Vehicles and Heavy Equipment Workshop
Koperasi Office
Archive Building and Library
Employee Mess
Employee Mess
Employee Mess
Koperasi Store
Material Storage
EMPTY LAND
EMPLOYEE HOUSING
OFFICE AREA
MANAGEMENT BUILDING
LABORATORY BUILDING
STORAGE BUILDING
Pond or Swamp SPORTS FACILITIES
River STATE HOUSE
Land Boundary of Pusjatan GENERAL EDUCATION FACILITY
Public Road EDUCATION FACILITY
2. The Opportunity
241
percent in China, 3.1 percent in India and 2.8 percent in Thailand). In 2012, the urban population
was 52% of the total population and by 2025, nearly 68% of the Indonesians will be living in
cities. Approximately 18 million of the 21 million jobs created between 2001 and 2011 were in
urban areas, marking a major shift of the employment base toward cities.
As more people transition to urban areas, well-planned urbanization and increase of the
supply of affordable housing in well serviced and well-connected neighborhoods will be
critical to enhance living standards. Also, as income rises and existing large metropolitan
cities such as Jakarta and Surabaya become saturated, there is a need to provide affordable
housing facilities to next big cities. Bandung, which is the third largest city in Indonesia which
is growing fast and needs urgent interventions in the development of infrastructure and
provision of affordable housing stock for its citizens. This project is proposed by the GCA to
meet residential needs of persons in the low-income segment in Bandung.
Ministry of Public Works and Housing preliminary concept for the project has proposed four
apartment towers of 20 floors each and an approximate potential for 2,000 housing units.
To complement its public housing program and provide a fillip to private participation in
affordable housing program, the Ministry of Public Works and Housing (PUPR) has identified
one parcel of land namely, Komplek Pusjatan Jl. AH. Nasution in Bandung City, for development
of affordable housing units and through a PPP route. Affordable housing project with public
housing rental rates would require substantial support from the GCA in the form of availability
payments for financial viability through PPP. The project would explore partial commercial
exploitation of the site so as to cross subsidize the low rentals and reduce the burden of
availability payments for the GCA.
4. Technical Specification
This housing project falls in the form of a Flat building under the classification of High Rise.
Regulations to set minimum service standards for flats are contained in the provisions of
Article 80 letter f of Law 20 of 2011. The regulation include specification for Residential
Services, Managing Office, Utilities, Cleaning and Waste Management, Information, Security,
Safety, Accessibility for Disabled People, Parking, and Maintenance Code.
242
6. Land Acquisition and Resettlement Action Plan
The land for the project admeasuring 3.7 hectares is owned by PUPR as State-Owned Asset
(Barang Milik Negara/BMN). Therefore, no resettlement plan needed.
There are three options. The following is project cost structure for option 2, which estimated
to get government support (construction and VGF).
Indicative government support will be in the form of Environmental permit, Location permit,
design certifications, Availability payment (if any), Land, Rent agreement etc.
9. Contact Information
Phone : 021-7264348
243
ATTACHMENTS
SUCCESS
STORY
BALIKPAPAN – SAMARINDA TOLL ROAD
Location : East Kalimantan Province
Description :
MAPS OF BALIKPAPAN-SAMARINDA
TOLL ROAD Balikpapan-Samarinda toll road (99 km) will
Package 1 connect the two largest cities in East
Package 3
Kalimantan, Balikpapan and Samarinda. This
project is divided into two sections, Section 1
Package 4 Package 2 consists of Package 1 (25.07 km) and Package
5 (11.09 km) and Section 2 consists of Package
2 (23.26 km), Package 3 (21.90 km) and Package
Package 5
4 (17.70 km).
Financier:
Financial close through Contractor Pre-
Financing (CPF)
Implementation Schedule:
1. Preparation : 2015
2. Land Acquisition : 2016
3. Construction : 2016 - 2019
4. Operation : 2019
244
BATANG - SEMARANG TOLL ROAD
Location : Central Java Province
Description :
Batang-Semarang Toll Road (75 km) is a
section of the Trans-Java Toll Road Network
that will connect Jakarta and Surabaya. Batang
is a regency on the north coast of Central Java
Province while Semarang is the largest and the
capital city of Central Java Province.
Financial Feasibility:
IRR : 13.70%
NPV : USD 230.0 Million
Investor:
Project Structure
PT. Jasamarga Semarang-Batang
1. PT Jasa Marga (Persero) Tbk;
2. PT Waskita Toll Road.
Financier:
Financial close through Contractor Pre-
Financing (CPF)
Implementation Schedule:
1. Preparation : 2016
2. Land Acquisition : 2016
3. Construction : 2016 - 2018
4. Operation : 2019
245
PANDAAN-MALANG TOLL ROAD
Location : East Java Province
Description:
Pandaan - Malang toll road is designed to
improve connectivity in the region. In addition,
the toll road is expected to facilitate industrial
transportations from Pandaan to Malang which
are connected directly to Surabaya, and vice
versa.
Financial Feasibility:
IRR : 13.81%
NPV : USD 99.0 Million
Project Status:
Project is currently operational Concession Period: 35 years
Investor:
PT. Jasamarga Pandaan Malang
1. PT Jasa Marga (Persero) Tbk; Project Structure
2. PT PP (Persero) Tbk;
3. PT Sarana Multi Infrastruktur (Persero).
Financier:
Refinancing with syndication of BNI, BCA, and
Bank Mandiri
Implementation Schedule:
1. Preparation : 2015
2. Land Acquisition : 2016 - 2017
3. Construction : 2017 - 2019
4. Operation : 2019
246
JAKARTA – CIKAMPEK II ELEVATED TOLL ROAD
Location : Jakarta and West Java Province
Description :
The project is an elevated 36.4 km toll road to
be built over the existing Jakarta - Cikampek
toll road, which is being operated by PT Jasa
Marga. The Jakarta-Cikampek road is part of
Jakarta – Cikampek II Elevated
Toll Road Project
the Trans-Java toll road network connect- ing
High Speed Train (HST) Project
Jakarta and Surabaya. The existing road’s
capacity has already been reached, but there
are limitations to widening it thus the proposed
Light Rail Transit (LRT) Project
solution is to expand the road’s capacity by
builing over it.
Financial Feasibility:
Project Status : IRR : 12.66%
Project is currently operational NPV : USD 104.0 Million
Investor:
Project Structure
PT. Jasamarga Jalan Layang Cikampek
1. PT Jasa Marga (Persero) Tbk;
2. PT Ranggi Sugiron Perkasa.
Financier:
Syndication of bank on investment credit
Implementation Schedule:
1. Preparation : 2015
2. Land Acquisition : 2016
3. Construction : 2017 - 2019
4. Operation : 2019
247
MANADO-BITUNG TOLL ROAD
Location : North Sulawesi Province
Description:
Manado-Bitung toll road is one of the longest
in Northern Sulawesi connecting from Manado
City to Bitung City, approximately 39.9 km in
length.
Financial Feasibility:
IRR : 12.23%
NPV : USD 13.7 Million
Project Status:
Project is currently under construction
Investor:
Project Structure
PT. Jasamarga Manado Bitung
1. PT Jasa Marga (Persero) Tbk;
2. PT Wijaya Karya (Persero) Tbk;
3. PT Pembangunan Perumahan (Persero) Tbk.
Financier:
Refinance BNI, BCA, Bank Mandiri and PT SMI
Implementation Schedule:
1. Preparation : 2015
2. Land Acquisition : 2016 - 2017
3. Construction : 2017 - 2019
4. Operation : 2019
248
CILEUNYI – SUMEDANG – DAWUAN TOLL ROAD
Location : West Java Province
Description:
The Cileunyi – Sumedang – Dawuan Toll Road
project will provide direct access for
transporting agricultural and manufacturing
goods as well as services produced from
these areas to the port city of Cirebon. This
toll road is urgently required to shift some of
the development to the east side of Bandung.
Financial Feasibility:
IRR : 13.11%
NPV : USD 17.9 Million
Investor:
Project Structure
PT Citra Karya Jabar Tol
1. PT. Citra Marga Nusaphala Persada Tbk.;
2. PT. Waskita Toll Road;
3. PT. Pembanguan Perumahan (Persero);
4. PT. Brantas Abipraya (Persero);
4. PT. Jasa Sarana.
Implementation Schedule:
1. Preparation : 2017
2. Land Acquisition : 2017 - 2019
3. Construction : 2017 - 2019
4. Operation : 2019
249
SERANG – PANIMBANG TOLL ROAD
Location : Banten Province
Description:
Serang – Panimbang Toll Road is located in
Banten Province where the toll reach from
Jakarta to Tanjung Lesung Special Economic
Zone. Furthermore, one of the attractive points
for the development of this toll road is that it
will have tremendous facilities, such as the
development of residential areas and
commercial areas along the corridor.
Financial Feasibility:
Project Status: IRR : 13.96%
Project is currently under construction NPV : USD 39.1 Million
Investor:
PT Wijaya Karya Serang Panimbang
1. PT Wijaya Karya (Persero); Project Structure
2. PT PP (Persero) Tbk;
3. PT Jababeka Infrastruktur.
Financier:
Contractor Pre-Financing (PT WIKA & PT PP)
Implementation Schedule:
1. Preparation : 2016
2. Land Acquisition : 2017
3. Construction : 2019
4. Operation : 2020
250
SERPONG-BALARAJA TOLL ROAD
Location : Banten Province
Description:
Serpong-Balaraja Toll (30 km) is part of the
Jabodetabek toll road network. This toll road is
located in Banten Province and will support
rapid development in that area.
Financial Feasibility:
IRR : 15.89%
NPV : USD 231.0 Million
Investor:
PT. Trans Bumi Serbaraja
1. PT Bumi Serpong Damai; Project Structure
2. PT Astratel Nusantara;
3. PT Transindo Karya Investama;
4. PT Sinar Usaha Mahitala.
Financier:
Syndication between PT Bank Mandiri, PT Bank
BNI and PT SMI
Implementation Schedule:
1. Preparation : 2015
2. Land Acquisition : 2016
3. Construction : 2016 - 2020
4. Operation : 2020
251
JAKARTA – CIKAMPEK II SOUTH TOLL ROAD
Location : Jakarta and West Java Province
Description:
Jakarta – Cikampek II South is a toll extending
36.4 km. Traffic volume through the Jakarta-
Cikampek toll road capacity has exceeded with
the V/C ratio high of 1.51. The Corridor plan of
this toll road section is located in the
administrative area of the West Java Province,
namely: the city of Bekasi, Bogor Regency,
Bekasi Regency, Karawang Regency, and
Purwakarta Regency.
Financial Feasibility:
IRR : 11.17%
Project Status: NPV : USD 45.9 Million
Project is currently under construction
Concession Period: 35 years
Government Contracting Agency:
BPJT (Indonesia Toll Road Authority)
Investor:
Project Structure
PT Jasamarga Japek Selatan
1. PT Jasa Marga (Persero) Tbk;
2. PT. Wiranusantara Bumi
Financier:
Refinancing with syndication of BNI, BCA, and
Bank Mandiri
Implementation Schedule:
1. Preparation : 2017
2. Land Acquisition : 2018 - 2019
3. Construction : 2018 - 2019
4. Operation : 2020
252
KRIAN-LEGUNDI-BUNDER-MANYAR TOLL ROAD
Location : East Java Province
Description:
Part of the Trans-Java Toll Road located in East
Java with length at approximately 38.29 km
from Krian to Manyar. One of the attractive
points for development of this toll road is that
it will have tremendous facilities, such as
development of residential areas and
commercial areas along the corridor.
Financial Feasibility:
IRR : 14.59%
NPV : USD 287.0 Million
Investor:
Project Structure
PT. Waskita Bumi Wira
1. PT Waskita Toll Road;
2. PT Energi Bumi Mining;
3. PT Panca Wira Usaha Jawa Timur
Financier:
Financial close through Contractor Pre-
Financing (CPF)
Implementation Schedule:
1. Preparation : 2015
2. Land Acquisition : 2016
3. Construction : 2016 - 2019
4. Operation : 2020
253
DEVELOPMENT OF BANDAR LAMPUNG WATER SUPPLY SYSTEM
Location : Bandar Lampung, Lampung Province
Description:
The Project scope includes the financing,
construction, operation and maintenance of
water supply systems, covering raw water
intake with capacity of 825 lps; water treatment
plant with production capacity of 750 lps; ±22
km of Ø 1,000 mm water transmission pipeline;
reservoir with capacity of ±10,000 m3; and the
development of parts of distribution network
with pumping system (primary and secondary
distribution network).
Financial Feasibility:
Project Status: IRR : 16%
Project is currently under construction NPV : USD 20.7 Million
Implementation Schedule:
1. Preparation : 2017
2. Land Acquisition : 2018
3. Construction : 2019
4. Operation : 2020
Contact Person : Supardji (Technical Director of Way Rilau Regional Water Company)
+62-721-483855
[email protected]
254
DEVELOPMENT OF UMBULAN WATER SUPPLY SYSTEM
Location : East Java Province
Description:
GRESIK CITY
The Umbulan Water Supply Project aims to
increase the water supply capacity to meet the
demand in the East Java Province. The capacity
SURABAYA CITY
PRODUCTION
UNIT
Estimated Project Cost: 140.7 Million
Financial Feasibility:
Project Status: IRR : 12.09%
Project is currently under construction NPV : USD 34.2 Million
Investor:
PT. Meta Adhya Tirta Umbulan
Project Structure
Financier:
PT IIF and PT SMI (Persero)
Implementation Schedule:
1. Preparation : 2011 - 2016
2. Land Acquisition : 2016 - 2019
3. Construction : 2017 - 2020
4. Operation : 2020
255
DEVELOPMENT OF WEST SEMARANG WATER SUPPLY SYSTEM
Location : Central Java Province
Description:
West Semarang Water Supply project is built
with a capacity of 1,000 litres per second. The
service area is planned to serve three (3)
subdistricts divided into five (5) service zone
zones.
Financial Feasibility:
IRR : 9.07%
NPV : USD 16.08 Million
Financier:
Bank Central Asia (BCA)
Implementation Schedule:
1. Preparation : 2017
2. Land Acquisition : 2019
3. Construction : 2019 - 2021
4. Operation : 2021
Contact Person : E. Yudi Indardo, ST, MPPM, M. Ak (Director of Tirta Moedal Water Supply
Company)
+62-24-8315514
[email protected]
256
NAMBO REGIONAL WASTE MANAGEMENT SYSTEM
Location : West Java Province
Description:
The capacity of Nambo waste processing
technology is 1,650-1,800 tonnes/day. Targeted
facility is to produce some recycled products
such as compost, refused derived fuel (RDF)
and other recyclable materials.
Financial Feasibility:
IRR : 13.60%
NPV : USD 4.8 Million
Investor:
PT Jabar Bersih Lestari
1. Consortium of Emsus, Enbiocon, Forcebell, Project Structure
Kun Hwa (Korea)
2. Consortium of PT. Panghegar Energy
Indonesia and PT. Jasa Sarana
Implementation Schedule:
1. Preparation : 2014
2. Land Acquisition : 2015
3. Construction : 2017 - 2020
4. Operation : 2021
Contact Person : Ir. Edi Bahtiar H, M.S (Head of Regional Waste Management)
+62-22-7319782; +62-22-7319735
[email protected]
257
CONSTRUCTION OF PALAPA RING WEST PACKAGE
Location : Sumatera and West Kalimantan Region
Description:
Development of fiber optic-based broadband
WEST PACKAGE telecommunication network which will connect
Riau Province, Riau Islands and the Natuna
Island with a total length 2,123 km.
Financial Feasibility:
IRR : 15.08%
NPV : USD 8.6 Million
Investor:
1. PT. Mora Telematika Indonesia Project Structure
2. PT Ketrosden Trasmitra
Financier:
PT. Bank Mandiri
Implementation Schedule:
1. Operation : 2018
258
CONSTRUCTION OF PALAPA RING CENTRAL PACKAGE
Location : Kalimantan, Sulawesi, and Maluku Region
Description:
Development of fiber optic-based broadband
CENTRAL PACKAGE telecommunication network covering 17
regencies across Kalimantan, Sulawesi, and
Maluku. with a total length 3,103 km.
Financial Feasibility:
IRR : 12.63%
NPV : USD 11.5 Million
Investor:
Consortium of Pandawa Lima Project Structure
1. PT Len Industri (Persero)
2. PT Teknologi Riset Global Investama
3. PT Multi Kontrol Nusantara
4. PT Bina Nusantara Perkasa
Financier:
Syndication of PT. Indonesia Infrastructure
Finance (Persero), PT. Bank BNI (Persero), and
PT. Sarana Multi Infrastruktur (Persero)
Implementation Schedule:
1. Operation : 2018
259
CONSTRUCTION OF PALAPA RING EAST PACKAGE
Location : East Nusa Tenggara, Maluku and Papua Region
Description:
Development of fiber optic-based broadband
EAST PACKAGE telecommunication network covering 35
regencies across East Nusa Tenggara, Maluku,
West Papua and remote area in Papua with a
total length 7,002 km.
Financial Feasibility:
IRR : 14.30%
NPV : USD 22.8 Million
Investor:
1. PT. Mora Telematika Indonesia Project Structure
2. PT Infrastruktur Bisnis Sejahtera
3. PT Inti Bangun Sejahtera
4. PT Smart Telecom
Financier:
Syndication of PT. Bank BNI ICBC Indonesia,
Bank Papua, Bank Maluku Malut and Bank
Sulsebar.
Implementation Schedule:
1. Operation : 2019
260
CENTRAL JAVA POWER PLANT
Location : Batang, Central Java Province
Description:
This project is the development of coal-fired
power plant in Batang Regency, Central Java
with capacity of 2x1,000 MW. It is considered as
the largest PPP electricity project by capacity
in Asia.
Financial Feasibility:
IRR : 11.12%
NPV : USD 938.7 Million
Investor:
1. PT. J-Power Project Structure
2. Adaro Power
3. Itochu Corporation
Financier:
Bank Mandiri
Implementation Schedule:
1. Preparation : done
2. Land Acquisition : 2011
3. Construction : 2016 - 2020
4. Operation : 2020
261
ALREADY
TENDERED PROJECTS
Project Summary
The following list consists of projects that have already been tendered as of June 2020.
262
No Project Name Description Status
6 South Sumatera The location of this project is on the East side Already
Province Non-Toll of South Sumatra Road in Palembang City, Tendered
Road Preservation namely Srijaya Raya Road, Mayjen Yusuf (RfP)
Singadekane Road, Letjen H. Alamsyah Ratu
Perwiranegara Road, Soekarno Hatta Road,
Terminal of Alang-alang Lebar Road and
Sultan Mahmud Badarudin II Road. The
approximate total length of this project will be
29.37 km. Investment return will be paid using
the availability payment method.
263
No Project Name Description Status
264
No Project Name Description Status
offices all over Indonesia. Satellite technology
has become a solution to address the gap in
broadband internet access in Indonesia.
13 dr. Zainoel Abidin The Zainoel Abidin General Hospital is a public Already
General Hospital hospital operated by the Government of Tendered (PQ)
Nangroe Aceh Darussalam. Its purpose is to
provide healthcare for its citizens. To cope
with increasing demand of a better-quality
healthcare, developing and upgrading hospital
becomes a necessity. With the next
development, the hospital will provide
excellent health services for people of
Nangroe Aceh Darussalam.
265
DEVELOPMENT OF KOMODO AIRPORT
Location : Labuan Bajo, East Nusa Tenggara Province
Description:
The purpose of Labuan Bajo Airport is:
• Empowering tourism in Komodo Island in
East Nusa Tenggara Province.
• Improving airport performance and
services to the passengers and related
stakeholders.
• Increasing the number of passengers and
cargo up to 4 mppa and 3.500 tonnes
respectively in 2044.
• Expanding national air connectivity.
• Supporting local economy.
Project Schedule
Project Structure
Contact Person : Cecep Kurniawan (Head of Airport Business and Partnership Division)
+62 811-1109-188
[email protected]
266
EXPANSION OF HANG NADIM INTERNATIONAL AIRPORT PASSENGER TERMINAL
Location : Batam, Riau Islands Province
Description:
The project is to expand the passenger
terminal of Hang Nadim International Airport
and designated to handle up to 8 million
passengers in 2019.
Scope of work:
• Expansion of Passenger Terminal;
• Operation and Maintenance Passenger
Terminal; and
• Operation and Maintenance Cargo
Terminal.
Project Schedule
Project Structure
267
DEVELOPMENT OF MAKASSAR – PAREPARE RAILWAY
Location : South Sulawesi Province
Segment F
Bosowa construction of F Segment (Bosowa and Tonasa
Segment E (Government)
Project Schedule
Project Structure
268
PROBOLINGGO – BANYUWANGI TOLL ROAD
Location : East Java Province
Description:
This project is expected to play an integral part
of East Java Road System. It is 172.91 km in
length which connected Probolinggo and
Banyuwangi, crossing three districts in East
Java including Situbondo district. Each district
has different potential resources which can be
developed further.
Financial Feasibility:
IRR : 11.17%
Government Contracting Agency: NPV : USD 45.9 Million
Indonesia Toll Road Authority (BPJT)
Type of PPP: Estimated Concession Period: 35 years
Solicited
Return of Investment:
User Charge
269
SEMARANG – DEMAK TOLL ROAD
Location : Central Java Province
Description:
The proposed project will connect Semarang
(Capital of Central Java Province) and city of
Demak. This Project has high traffic volume
with ±27 km in length. Semarang as a capital
town of Central Java Province is well-
developed with industrial goods and trading. On
the other side, Demak is a region that is rich
with natural resources. This project is also
integrated with the development of Semarang
Sea Wall.
Project Schedule
Project Structure
270
SOUTH SUMATERA PROVINCE NON-TOLL ROAD PRESERVATION
Location : South Sumatra Province
Description:
The location of this project is on the East side
of South Sumatra Road in Palembang City,
namely Srijaya Raya Road, Mayjen Yusuf
Singadekane Road, Letjen H. Alamsyah Ratu
Perwiranegara Road, Soekarno Hatta Road,
Terminal of Alang-alang Lebar Road and
Sultan Mahmud Badarudin II Road. The
approximate total length of this project will be
29.37 km. Investment return will be paid using
the availability payment method.
Project Schedule
Project Structure
Contact Person : Ir. Riel Mantik, M.Eng,Sc (Head of Integrated Planning and Road Network
Subdirectorate); + 62-8129069604
[email protected] / [email protected]
271
NORTH PENAJAM PASER – BALIKPAPAN TOLL ROAD BRIDGE
Location : East Kalimantan Province
Description:
The construction of the bridge (which functions
as a toll road) will connect the North Penajam
Paser Regency with Balikpapan City across the
Bay of Balikpapan. The North Penajam Paser -
Balikpapan Toll Road Bridge will not only
eliminate the geographical obstacle between
the North Penajam Paser Regency and the
Balikpapan City, but also between East
Kalimantan and South Kalimantan Provinces.
Project Schedule
Project Structure
272
SOLO – YOGYAKARTA – KULONPROGO (NYIA) TOLL ROAD
Location : Yogyakarta & Central Java Provinces
Description:
The development of Solo–Yogyakarta–Kulon
Progo (New Yogyakarta International
Airport/NYIA) Toll Road is part of the Southern
Java Road Network, stretching from Gede Bage
in West Java province to Solo in Central Java.
The toll road will run for 93.14 km, divided into
three sections: Kartasura–Purwomartani,
Purwomartani–Gamping, and Gamping–Kulon
Progo (NYIA).
Project Schedule
Project Structure
273
YOGYAKARTA – BAWEN TOLL ROAD
Location : Yogyakarta & Central Java Provinces
Description:
Yogya–Bawen toll road will connect
Semarang-Solo toll road to Yogyakarta. It is
planned to reduce heavy traffic on the arterial
road. It will also support industrial area in
Ungaran–Bawen corridor and Joglosemar
(Yoyakarta–Solo–Semarang) tourism area.
Furthermore, this project is included in the
Indonesia National Strategic Project (PSN).
Financial Feasibility:
Government Contracting Agency: IRR : 11.61%
Indonesia Toll Road Authority (BPJT) NPV : USD 90.56 Million
Type of PPP:
Solicited Estimated Concession Period: 40 years
Return of Investment:
User Charge
Project Schedule
Project Structure
274
DEVELOPMENT OF PEKANBARU WATER SUPPLY SYSTEM
Location : Pekanbaru, Riau Province
Description:
The purpose of Pekanbaru Water Supply is to
provide reliable drinking water infrastructure
and to support economic activities in
Pekanbaru City. The project includes
rehabilitation and uprating of existing WTP and
reservoir to reach 500 lps and construction of
a new intake facility, WTP, and reservoir with
capacity of 250 lps. With total coverage of
61,000 connections for 6 districts in Pekanbaru.
Project Schedule
Project Structure
Contact Person : Kemas Yuzferi (Director of Tirta Siak Water Supply Company)
+62-761-23825 / +62-813-6440-1776
[email protected]
275
DEVELOPMENT OF JATILUHUR I REGIONAL WATER SUPPLY SYSTEM
Location : West Java and DKI Jakarta Provinces
Description:
Jatiluhur I Regional Water Supply system has
an outflow of 5,000 lps that will supply
Karawang Regency, Bekasi Regency, Bekasi
City and DKI Jakarta. The project covers the
construction of intake, transmission pipeline,
water treatment plant (WTP), and the
development of main network.
Financial Feasibility:
IRR : 13.62%
Government Contracting Agency: NPV : USD 26.98 Million
Minister of Public Works and Housing
Type of PPP: Estimated Concession Period: 30 years
Unsolicited
Return of Investment:
User Charge
Project Schedule
Pre-
Financial Close Construction Operation
Qualification
Q2 2020 2020 - 2023 2023
Q1 2020
Project Status : Pre-Qualification
Project Structure
Contact Person : Muryata (Head of PPP Regional Water Supply Team, Directorate General
of Infrastructure Financing for Public Works and Housing)
+6221 - 7264230
276
DEVELOPMENT OF MULTIFUNCTION SATELLITE
Location : National
Description:
The Multifunction Satellite Project, called the
Satelit Republik Indonesia (SATRIA), designed
to have a throughput capacity of 150 Gigabits
per second (Gbps), is expected to provide
internet services to 150,000 public facilities,
including schools and health centers, as well
as defense establishments, security
administrations and all regional government
offices all over Indonesia. Satellite technology
has become a solution to address the gap in
broadband internet access in Indonesia.
277
DR. ZAINOEL ABIDIN GENERAL HOSPITAL
Location : Banda Aceh, Nangroe Aceh Darussalam Province
Description:
The Zainoel Abidin General Hospital is a public
hospital operated by the Government of
Nangroe Aceh Darussalam. Its purpose is to
provide healthcare for its citizens. To cope with
increasing demand of a better-quality
healthcare, developing and upgrading hospital
becomes a necessity. With the next
development, the hospital will provide
excellent health services for people of Nangroe
Aceh Darussalam.
Project Schedule
Project Structure
278
DEVELOPMENT OF GORONTALO GENERAL HOSPITAL
Location : Gorontalo Province
Financial Feasibility:
IRR : 9%
Government Contracting Agency: NPV : USD 17.85 Million
Governor of Gorontalo
Type of PPP: Concession Period: 20 years
Solicited
Return of Investment:
Availability Payment
Project Schedule
Project Structure
Contact Person : Olis Bakari (Head of the Human Settlements and Housing Subdivision,
Regional Development Planning Agency)
+62-853-42353710
[email protected]
279
DEVELOPMENT OF SIDOARJO GENERAL HOSPITAL
Location : Sidoarjo, East Java Province
Description:
Sidoarjo General Hospital is the second
hospital owned by the Government of Sidoarjo
Regency which aims to provide health service
facilities that will cover the community in the
west of Sidoarjo Regency. Sidoarjo General
Hospital is planned as a class C hospital. This
project scheme is DBFOMT with Availability
Payment as the investment return to the SPC.
Financial Feasibility:
Government Contracting Agency: IRR : 15%
Regent of Sidoarjo NPV : USD 14 Million
Type of PPP:
Solicited Concession Period: 10 years
Return of Investment:
Availability Payment
Project Schedule
Project Structure
Contact Person : Agoes Boedi Tjahjono (Head of Regional Development Planning Agency)
+62-31-8947383
[email protected]
280
Glossary
Abbreviation Definition
Availability Payment
AP
Pembayaran Ketersediaan Layanan
Build-Operate-Transfer
BOT
Bangun-Guna-Serah
Feasibility Study
FS
Studi Kelayakan
281
Abbreviation Definition
Ministry of Finance
MoF
Kementerian Keuangan
282