3.DPR-Pandikkad - Final - 12.8.17
3.DPR-Pandikkad - Final - 12.8.17
Table of Contents
2
Detailed Project Report – GHSS Pandikkad
Buildings ............................................................................... 30
Classrooms ............................................................................ 34
Toilets ................................................................................... 35
Labs (Science Lab & Computer Lab) ....................................... 35
Kitchen ................................................................................. 35
Waste disposal ....................................................................... 36
Water Availability .................................................................. 36
Security ................................................................................. 36
PA systems ............................................................................ 36
Sports/Extra-Curricular activities ......................................... 36
Topographical survey details ....................................................... 37
3.4 Primary Surveys .......................................................................... 38
Chapter 4: FUNCTIONAL DESIGN ......................................................... 39
Background ................................................................................. 39
Location Assessment ................................................................ 39
Zoning, Circulation and Access ................................................ 40
Existing Buildings and Assets ................................................... 41
Redevelopment Plans ............................................................... 42
CoE Components of the GHSS, Pandikkad Master plans .............. 49
Chapter 5: ENGINEERING DESIGN ....................................................... 53
General ........................................................................................ 53
Soil condition and Foundation .................................................... 53
Structural analysis. ..................................................................... 53
Material Properties ................................................................ 54
Loading and Analysis ............................................................. 54
Structural Drawings .................................................................... 55
Electrical System Design ............................................................. 55
5.6 Demolition of buildings ............................................................... 57
Chapter 6: FINANCIAL ESTIMATES AND COST PROJECTIONS ............. 58
6.1 Summary of Cost Estimate .......................................................... 58
Chapter 7 REVENUE STREAMS ............................................................ 59
Chapter 8: COST BENEFIT ANALYSIS AND INVESTMENT CRITERIA ..... 60
Chapter 9: RISK ASSESSMENT AND MITIGATION MEASURES .............. 63
3
Detailed Project Report – GHSS Pandikkad
4
Detailed Project Report – GHSS Pandikkad
List of Tables
Table 1: Intake and Strength ................................................................ 23
Table 2: Details of staff strength and administration ............................. 23
Table 3: Situation assessment .............................................................. 31
Table 4: Primary survey details ............................................................. 38
Table 5: Load calculation for different buildings .................................... 55
Table 6: Revenue generating components ............................................. 59
Table 7: Social cost benefit analysis ...................................................... 62
Table 8: Risk assessment and mitigation measures ............................... 63
Table 9: Project implementation schedule ............................................ 70
Table 10: Quality analysis checklist ...................................................... 72
5
Detailed Project Report – GHSS Pandikkad
List of Figures
Figure 1: Location of Project Area ........................................................ 13
Figure 2: Methodology for preparation of Detailed Project Report ........ 16
Figure 3: Malappuram District Map ...................................................... 17
Figure 4: Pandikkad location map ........................................................ 18
Figure 5: Accessibility to Govt. HSS Pandikkad .................................... 19
Figure 6: Road Network of the Location ............................................... 20
Figure 7: Site plan of Govt. HSS Pandikkad .......................................... 28
Figure 8: View of the road in front of the school .................................. 29
Figure 9: Existing Condition of the Compound wall ............................. 30
Figure 10: View of the existing classrooms ........................................... 34
Figure 11: view of the existing toilet blocks ......................................... 35
Figure 12: view of the existing kitchen ................................................ 36
Figure 13: View of the school play ground ............................................ 37
Figure 14: GHSS, Pandikkad Location Assessment ............................... 40
Figure 15: Zoning, circulation and Access- GHSS, Pandikkad ............... 41
Figure 16: Existing Buildings and Assets- GHSS Pandikkad .................. 42
Figure 17: Phase-1 demolition plan- GHSS, Pandikkad ......................... 43
Figure 18: Phase-1 proposal- GHSS, Pandikkad .................................... 43
Figure 19: Demolition plan- GHSS, Pandikkad ..................................... 44
Figure 20: Existing and proposed new buildings- GHSS, Pandikkad ....... 45
Figure 21: Proposed zoning- GHSS, Pandikkad ..................................... 46
Figure 22: Proposed plan of building no.2 of GHSS, Pandikkad ............. 47
Figure 23: Proposed plan of toilet block in building no.9 of GHSS,
Pandikkad ............................................................................................ 48
Figure 24: Proposed plan of toilet block in building no.7 of GHSS,
Pandikkad ............................................................................................ 48
Figure 25: Proposed plan of building no.5 of GHSS, Pandikkad ............. 49
Figure 26: Project management organization ....................................... 67
Figure 27: Quality management strategy ............................................. 72
6
Detailed Project Report – GHSS Pandikkad
Preface
The Government of Kerala had taken initiatives for the Rejuvenation of
Government Schools in Kerala under the project “Upgrading one school from
each constituency as a Centre of Excellence”.
The Kerala Infrastructure Investment Fund Board (KIIFB) is the funding agency
for this infrastructure projects. KITCO Ltd. has been entrusted by Government
of Kerala for the preparation of Detailed Project Report (DPR) and Cost benefit
Analysis (CBA) for the above project.
7
Detailed Project Report – GHSS Pandikkad
EXECUTIVE SUMMARY
The public education system of Kerala has played a significant role in developing
Kerala Society and it has contributed large number of eminent and talented
people to the world. However, due to various reasons, some of the Government
schools are not effective and efficient. It is important to rejuvenate the Public
Education System to achieve quality education at affordable cost. Rejuvenation
is expected to focus on improved academic infrastructure, facilities for
promoting extracurricular activities, institutionalizing a better learning practice
etc.
This Detailed Project Report for “Creating Centre of Excellence at Govt. HSS
Pandikkad.” submitted for funding assistance through PPE Mission is an
attempt to understand and analyze the requirements of Govt. HSS Pandikkad
and propose the development plans. School is a leading education institute in
the region. The facilities and activities are proposed considering the
enhancement of the school to a Centre of Excellence in arts and academics.
8
Detailed Project Report – GHSS Pandikkad
9
Detailed Project Report – GHSS Pandikkad
Introduction
Science and technology are now established as forces of great power in the
shaping of the futures. The developing countries face the challenge of creating
for themselves pathways of learning which may lead to the mainstream of the
knowledge revolution.
India, with more than 1.4 million schools and more than 230 million
enrolments, is home to one of the largest and complex school education systems
in the world along with China.
10
Detailed Project Report – GHSS Pandikkad
system built around it must be centered on the human person. This shift to
person-centered education will mean the following core principles:
Government of Kerala has launched the Nava Kerala Mission under which 4
major initiatives are being taken up: Agriculture; Housing; Health; and
Education. The initiative for Education is titled “Protection of Public Education
Mission” (PPE Mission”) with the following major objectives:
11
Detailed Project Report – GHSS Pandikkad
Further, Government has decided that each school should prepare the master
plan incorporating existing features and proposed buildings, Bio Diversity Park,
children’s park, indoor and outdoor stadia, Autism Park etc. The funding for
the Mission will come through its own funds, funds raised through Kerala
Infrastructure Investment Fund Board (KIIFB), MLA/MP Local Area
Development Schemes; funding of local bodies and contribution from the local
community. Funding of KIIFB will be directly to SPVs under public sector.
In the above context, Govt. HSS Pandikkad has been considered for the
rejuvenation of programme and the Government of Kerala been selected the
school under the project “Upgrading one school from each constituency as a
Centre of Excellence” for the development of the basic infrastructural facilities,
autism park, Bio-diversity park, Laboratory and Library development, etc.
12
Detailed Project Report – GHSS Pandikkad
13
Detailed Project Report – GHSS Pandikkad
The detailed location analysis and the facilities in the school are briefed in detail
in the subsequent chapters.
Project Objective
14
Detailed Project Report – GHSS Pandikkad
Malappuram is a district with a great legacy in arts, which always invites the
attention of the public to this district. As GHSS Pandikkad is one of the major
schools in Malappuram and considering the unique achievements in arts it is
proposed to facelift the school as a Center of Excellence in Arts and Academics.
The major activities planned are:
With the combined effort of students, teachers and public the study center
shall be converted to a place from where the information related to the arts
can be obtained.
Methodology
The methodology adopted for the upgradation of the Detailed Project Report is
enumerated below in detail:
15
Detailed Project Report – GHSS Pandikkad
Personal interviews and discussions were conducted with the school officials,
PTA and other stake holders along with site visit and data collection were carried
out. The requirements of the school were informed by the school officials and
based on the same, the master plan was analyzed.
During the site visit, the existing situation of the school in terms of
infrastructure facilities, academic and non-academic excellence were studied
and the potential for a Centre of Excellence was identified and discussed with
the stake holders and school officials.
Malappuram District
16
Detailed Project Report – GHSS Pandikkad
Malappuram has a rich and eventful history. It was the military headquarters
of the Zamorins of Kozhikode since ancient times. This district was the venue
for many of the Mappila revolts (uprisings against the British East India
Company in Kerala) between 1792 and 1921. It was a famous centre for Hindu
- Vedic learning and Islamic philosophy and a place of cultural heritage.
The total area of the district is 3550 sq km with a population of 41,10,956 (2011
Census )
17
Detailed Project Report – GHSS Pandikkad
Pandikkad
Details on the accessibility, ecology and soil condition of the school are as
follows:
18
Detailed Project Report – GHSS Pandikkad
(a) Accessibility
The school is located around 500 m away from the National Highway 73.
The school is accessible through the internal roads emerged from the main road.
But the roads leading to the school is slightly congested. However taxi services
are available to this location.
19
Detailed Project Report – GHSS Pandikkad
The nearby railway stations are Melattur, Tuvvur and Pattikad Railway station.
20
Detailed Project Report – GHSS Pandikkad
proposed. Green campus plan has been initiated through various clubs. A new
incinerator is available for waste disposal. There are no bio-bins either.
However, there is a small biogas plant for treating biodegradable waste, which
is not in a working condition.
Hard laterite soil is present at the campus. The school is situated at different
levels. However this level difference in dominant when considering the north
side of the campus. The Topographical survey drawing is provided in the
Annexure.
21
Detailed Project Report – GHSS Pandikkad
This chapter details about the current scenario of the facilities available in the
school and the possible modifications that will facilitate to a world class
educational experience with more emphasis on education and extra-curricular
activities to the students.
The existing infrastructural facilities, buildings and facilities, utilities and other
auxiliaries, intake and strength, staff and administration and extra-curricular
activities are assessed as below
Infrastructure Facilities
22
Detailed Project Report – GHSS Pandikkad
roof, G+1 building with sheet roofing, class room building and lab
building with flat roof and RCC construction
10) Higher Secondary Block, two storied building with RCC construction
11) Classrooms for High School and Higher secondary
12) Open stage
13) Toilet blocks
14) Playground with gallery
15) Main entrance
16) Compound wall
23
Detailed Project Report – GHSS Pandikkad
Extracurricular activities:
i. The school has an excellent track record in promoting various art forms
and arranging performance
ii. The students has achieved championships in various competitions such
as youth festival, mathematics competitions, etc.
iii. Various clubs such as science club, Nature club, mathematics club, etc.
are functioning in the school
Stakeholders Consultation
New Buildings
Playground modification
Landscaping
Construction of compound wall
Dining area
Basketball and volley ball court
Modern laboratories and library
SWOT Analysis
(a) Strength:
24
Detailed Project Report – GHSS Pandikkad
Requirement/demand Analysis
25
Detailed Project Report – GHSS Pandikkad
The proposed changes are essential for the school to enhance it to the level of
Centre of Excellence. The basic mandatory infrastructure is to be provided as
per Kerala Education Rules.
The main components of the project directly impacting the education quality,
proposed to be taken up in the first phase are listed below:
26
Detailed Project Report – GHSS Pandikkad
As per the item 8(a) of schedule of EIA Notification, 2006, it is mandatory that
building and construction projects ≥20000 m2 and <1, 50,000 m2 of built-up
area are categorized as Category B and requires clearance from State Level
Environmental Impact Assessment Authority. As the total built up area for the
present project fall far below the minimum limit, the project does not attract
EIA Notification, 2006.
27
Detailed Project Report – GHSS Pandikkad
Land
Govt. HSS Pandikkad is extended in a total land area of 9.26 acres. The school
and the playground are separated by a public road. The school is not located in
a flat terrain, there are undulations in the terrain.
28
Detailed Project Report – GHSS Pandikkad
The school is having one entrance gate located at the west side of the campus.
The entrance is accessible by road. An important point to be noted regarding
the school is that, there is an open stage at the road side, which is of historical
importance. Shri. Rajeev Gandhi has addressed the people at this open stage
one week before he was assassinated.
Compound wall
There is no complete compound wall coverage for the school. The present
condition of the compound wall is shown in the figure given below:
29
Detailed Project Report – GHSS Pandikkad
Parking Space:
At present, the school lacks a proper parking space for the staff vehicles and
students cycles. The parking is done in the school premises in the available
areas.
Buildings
30
Detailed Project Report – GHSS Pandikkad
dilapidated condition. The condition of the building (G+1), with sheet roof
constructed in MP’S LAD scheme and G+1 Building situated at the center of
the plot are found satisfactory. But it was noted that all the buildings of the
school lacks proper maintenance.
The condition of the tile roofed building situated inside the campus are not up
to the mark and there require proper maintenance and modifications. An
assessment of the major buildings of the school are as follows:
Table 3: Situation assessment
31
Detailed Project Report – GHSS Pandikkad
SSA Building
Condition of the building is
satisfactory. However, require
proper maintenance.
Lab Block
The condition of the building is not
satisfactory.
32
Detailed Project Report – GHSS Pandikkad
HS Building
The condition of the building is not
satisfactory
33
Detailed Project Report – GHSS Pandikkad
Classrooms
The condition of the class rooms are not in satisfactory condition. The facilities
provided are not matching with the growing need of the students.
34
Detailed Project Report – GHSS Pandikkad
Toilets
The view of the existing toilet block are shown in the figure below:
The situation of the toilet blocks are not in acceptable condition and the same
needs proper maintenance.
The school has laboratories for the Higher Secondary and High School section
and separate lab block is also provided. Even though, the laboratories have the
facilities for conducting the experiments and test related to the curriculum, the
same requires further modification considering the upliftment to a Center of
Excellence. Better infrastructure facilities and equipment are required in the
laboratories.
Kitchen
Presently the school has a kitchen located at the campus. The noon meal is
cooked at this area. There require proper maintenance for the same.
35
Detailed Project Report – GHSS Pandikkad
Waste disposal
Presently the school does not have a scientific solid waste management system.
The incinerator available is not functioning now a days.
Water Availability
The school has an open well which caters the water demanded of the school.
Security
The school compound is secured by the compound wall, but the complete
coverage of the same is not there. Presently no CCTV cameras or other
surveillance measures are not available at the school.
PA systems
Sports/Extra-Curricular activities
The school is active in sports such as football, volleyball and badminton and
has active participation in state and national level. The playground is separated
36
Detailed Project Report – GHSS Pandikkad
from the campus by the public road, which creates certain constraints for the
students. The view of the playground is shown in figure below.
The terrain of the school campus is examined with respect to the actual site
condition and the topo graphical survey drawing. The school is located at
different levels. The lowest area is at the north side of the campus. The topo
survey drawing is enclosed as Annexure.
37
Detailed Project Report – GHSS Pandikkad
Primary Surveys
38
Detailed Project Report – GHSS Pandikkad
Background
Location Assessment
The location is a perfect setting among a very less dense predominantly housing
community. The road along the west side of the main campus is the main access
road to the school.
In figure 16 below the disconnect between the main campus and playground is
evident because of the public road that runs through it. This was one of the key
concerns highlighted by stakeholders especially considering safety and security
of students as they access the playground unsupervised. Figure 16 also
demonstrates the layout of buildings in the main campus.
39
Detailed Project Report – GHSS Pandikkad
The analysis of buildings and its current uses indicate that in this school the
zoning of UP, HS and HSS are adequate and allocation of buildings bring the
various class segments within proximity. The location of buildings however does
not provide for good access and circulation. The red arrow in Figure 17 below
illustrates the pathways that are constricted and not conducive for seamless
movement of students back and forth. In an unlikely event of an emergency the
lack of designated pathways can be disruptive.
Figure 17 also illustrates the disconnect between the main campus and
playground. To ensure safety, the school must restrict vehicular movement or
install speed controls during school hours on the road traversing the school
property. The playground is a significant asset available to the school.
40
Detailed Project Report – GHSS Pandikkad
The assets of the school are its existing buildings. In Figure 4, building
numbers 1, 2, 6, 11 and 12 are old single storied buildings with the old Kerala
style tile roof over the wooden roofing membrane. Building numbers 3, 9 and
10 are single storied buildings with sheet roofing. Owing to the dilapidated
condition of building number 9 the stakeholders are of the opinion of its
demolition and disposition to make way for open spaces. The advantage of
removing this building is that it provides an opportunity to create a large central
open space. The space can be developed into a combination of utilities like the
assembly, small play areas and dedicated pathways.
41
Detailed Project Report – GHSS Pandikkad
these buildings in a phased manner to make way for a more modern building
satisfying all spatial requirements. The standalone toilets will be demolished
and the new proposed building layouts will have attached toilet blocks.
Building number 2 and 3 are single storied structure that can be salvaged and
reconstructed with attached toilet blocks. The shed and stage next to the public
road can be demolished to create a large open area which can also be used for
parking.
Redevelopment Plans
42
Detailed Project Report – GHSS Pandikkad
be compromised to make way for new modern school buildings and related
infrastructure.
43
Detailed Project Report – GHSS Pandikkad
As part of Phase 1, two buildings (2 and 3) (473 sq.m. and 120 sq. m.) as
indicated in Figure 5 are demolished. And in its place a new L shaped building
is proposed which will be a G+2 structure with 27 modernized classrooms and
attached toilet block in each floor. It will have an area of about 1935 sq. m. The
new building (6 in figure 6) at the east end of the plot will be a G+2 structure of
which the ground floor will be completed in phase 1 which includes dining hall
and kitchen. It will have an area of about 270 sq. m. At the end of phase 2, the
building will be upgraded to G+2. Building number 12 (figure 5) is demolished
and a toilet block (G+1) (60 sq. m.) is kadded which connects building number
11 and 13 (figure 16). Two existing classrooms of building number 18 (figure
16) are converted to toilet blocks (G+1). The shed and stage near the road are
demolished to create a spacious entry space and parking area. Passages are
created which connects the various individual buildings that make the
movement of students easier.
44
Detailed Project Report – GHSS Pandikkad
At the end of Phase 3, GHSS Pandikkad will have a total of about 3425 sq. m.
built up area. With the streamlining of buildings and creation of adequate open
45
Detailed Project Report – GHSS Pandikkad
spaces the overall layout of the campus will be zoned better with enhanced
connectivity between buildings. The School will require support from the State
PWD and State Transport Department to declassify the street on the east side
to control public/commercial traffic to ensure seamless use of the two sections
within the campus.
Phase 4 will be future expansion of the school campus which will be contingent
on the anticipated surge in enrollment. Building number 3, 4 and 6(figure 19)
can be upgraded to G+2 structure according to the requirements of the school.
46
Detailed Project Report – GHSS Pandikkad
47
Detailed Project Report – GHSS Pandikkad
Figure 23: Proposed plan of toilet block in building no.9 of GHSS, Pandikkad
Figure 24: Proposed plan of toilet block in building no.7 of GHSS, Pandikkad
48
Detailed Project Report – GHSS Pandikkad
Based on the Guidelines for Creating Master plans for Schools developed by
KITCO the following are key changes proposed for the GHSS, Pandikkad:
49
Detailed Project Report – GHSS Pandikkad
50
Detailed Project Report – GHSS Pandikkad
panels.
10) Sport: The GHSS, Pandikkad master plan a utilization plan for its
playground. The proposal includes installing a mini soccer field which
can also provide for a 200-meter running track. In the newly created
central open space the design will provide creating smaller play and
recreation areas.
11) Autistic students: The master plan at this time is not proposing setting
up a designated building/rooms for the needs of a Autism Care. After
completion of the construction phase the school management will
evaluate the availability of class rooms vis-à-vis enrollment patterns and
determine if rooms or sections of the buildings can be designated for
this purpose.
51
Detailed Project Report – GHSS Pandikkad
12) Parking: The master plan provides parking within the campus for
vehicles. There are sufficient on-street parking options for visitors.
Dedicated covered parking will be created for students commuting to
school on bicycles.
14) Expansion and growth: The GHSS, Pandikkad master plan provides a
schematic on future expansion phase by identifying new areas for
construction and buildings that can be remodeled for enhanced use.
52
Detailed Project Report – GHSS Pandikkad
General
The newly proposed buildings are multistoried structures with two or more
floors. So, a framed structure with RCC column, beam and slab is the ideal
solution for such buildings. In case of RCC framed structures, the inside
planning of rooms can be altered by changing the position of partition walls.
Monolithic construction is possible with R.C.C framed structures so they can
resist vibrations, earthquakes and shocks more effectively than load bearing
walled structures.
Depending upon the nature of founding earth and type of structure, either a
shallow foundation or deep foundation shall be adopted based on the available
geotechnical data.
The different kinds of shallow footings are individual footings, strip footings and
raft foundations which are suitably selected based on structural safety, type of
structure and economy. The idea is that each footing takes the concentrated
load of the column and spreads it out over a large area, so that the actual weight
on the soil does not exceed the safe bearing capacity of the soil.
When there is a layer of weak soil at the surface. This layer cannot
support the weight of the building, so the loads of the building have to
bypass this layer and be transferred to the layer of stronger soil or rock
that is below the weak layer.
When a building has very heavy, concentrated loads, such as in a high
rise structure.
Structural analysis
53
Detailed Project Report – GHSS Pandikkad
Material Properties
Concrete
Reinforcement Steel
i. IS: 875 -1987 Part I to part V : Code of Practice for Design Loads
(other than Earthquake) for Buildings and Structures- Imposed Loads.
ii. IS:456-2000 : Code of Practice for Plain Reinforced Concrete.
iii. IS:800-2007 : Code of Practice for General Construction in Steel
iv. SP:16 : Design aids for Reinforced Concrete to IS:456
v. SP:34 :Handbook on Concrete Reinforcement & detailing
Loads considered
i. Dead load
Dead load of the modelled elements will be taken care by the analysis software
54
Detailed Project Report – GHSS Pandikkad
Suitable Live Load as per IS:875 Part-II is also applied as mentioned in the
below table.
Structural Drawings
Based on the structural analysis and design, concrete layout drawings are
prepared for foundation, column, grade beam, floor beam and slab which are
attached in annexure.
The design and engineering of the electrical installation shall satisfy all
statutory requirements of the national and State/local authorities. The
electrical system is designed in such a way that energy consumption is
minimum through the selection and utilization of efficient electrical
fixtures.
55
Detailed Project Report – GHSS Pandikkad
56
Detailed Project Report – GHSS Pandikkad
Lightning protection as per IS: 2309 / IEC 60305 is proposed for the
building depending upon the height.
Schools across the country are not only working to make their students
smarter, but also to make their campuses smarter and more energy
efficient. For schools, solar panels can easily offset monthly utility bills.
With a larger installation, it may even be possible to switch to 100%
renewable energy. As a part of the Up-Gradation and to promote a cost
effective energy option, Solar Photo Voltaic (PV) System is proposed to be
installed to meet the increasing energy demand.
57
Detailed Project Report – GHSS Pandikkad
Cost estimate prepared based on DSR 2016 and market rates (wherever items are
not reflected in DSR) and the same is placed at annexure.
KITCO has used the specifications and rates specified in the PRICE for carrying out
the detailed estimate. The same has been done with the shared license available with
KITCO (as KITCO is still not in receipt of PRICE license). KITCO request is under
finalization. However, the rates and specification of PRICE has been adhered to while
preparing the estimate.
Abstract of the estimate is tabulated below:-
TOTAL 43923978.00
TOTAL 44,174,006.00
TOTAL 45,499,226.18
58
Taxable amount as per GO(@ 15% of 40% of
estimated amount) 2,729,953.57
TOTAL 43,923,978.00
59
4.00 (SH: - 5.0 - FLOORING WORK) 71,839.20
TOTAL 250,028.00
TOTAL 1348174.00
Contingency @ 3% 40445.22
60
Detailed Project Report – GHSS Pandikkad
The project proposed includes the development of the school building with
improvement in the basic amenities to convert it into a Centre of Excellence
without compromising in other aspects like safety, hygiene, health and comfort
to students. Hence the proposal of development of the infrastructural facilities
is not intended for revenue generation.
However, some of the other facilities proposed in this project can be intended
for revenue generation, which may result in a revenue generation. This revenue
can be utilized for operation and maintenance of these facilities, provided these
facilities can be used for revenue generation on non-working days or at any time
which will not cause any difficulty to students to use these facilities.
59
Detailed Project Report – GHSS Pandikkad
61
The broad benefits of Public Education Rejuvenation programmes are:
Students in their desire to get educated from schools with modern amenities,
generally travel to far off places. In many such cases, students even spend one hour
each in the morning and evening in school bus. The same, otherwise could have
utilized for other activities like learning skills, playing games etc. Hence by proving
modern amenities, Government school will enable students to join schools near to
their homes.
On implementing the proposed facilities as enumerated in chapter 4, it is expected
the students who are availing the facilities will also increase. The students in a
locality will prefer the nearby government schools other than private schools. This
will facilitate a reduction of each students and will improve the mental mindset of
each student to a greater extent.
62
Considering a total of 20 students are relocated to the nearby schools and a
gain of Rs. 10,000/- per year from each students. On assuming all these
scenarios and extrapolating this, it is assumed that a total of Rs. 2 lakhs /
unit is expected to save in each year. This can be considered as a benefit to
the society.
Public education is one of the cheapest education facility available and with
more number of students joining to public schools will directly result into
savings to the family by virtue of lower fees and associated costs. The savings,
thus made are now available for other uses including improved healthcare,
enhanced personal investments, and more people opting for insurances. Hence,
an improved Public education system improves the health / status of the
society.
The above enumerated scenarios will facilitate a savings in the society and is
assumed to be about Rs. 1 lakh/unit. The same scenario is assumed to be continue
for all the years. The same is shown in the CBA sheet provided.
a) Additional revenue from CoE Component
63
For the development of schools into Centre of Excellence, facilities as are
provided in each schools based on the talent identified in students. The
proposal include facilities like Indoor stadium cum auditorium space,
multipurpose court, etc. These facilities can be made available to the public on
rent for gaining income from these facilities, provided the access to the public
will be made available only on non-academic hours.
64
Detailed Project Report – GHSS Pandikkad
Physical and Better games and playing facilities will improve the High
mental physical fitness. This will reduce the stress and improve
health the mental health.
improvement Lower people with obesity.
Gain on The students by saving traveling time to school can use Medium
opportunity more time for doing things they are interested in. This will
cost improve student’s overall development.
Lesser cost More students in Public schools will mean less overall Medium
for education expense for education by society. This will enhance the
savings and improve the social life.
Maximizing Public education system has a fixed cost in the form of High
the benefits cost of assets, salary and other expenses. With more
of public students in public schools, the expenses / student gets
education lowered.
62
Detailed Project Report – GHSS Pandikkad
63
Detailed Project Report – GHSS Pandikkad
64
Detailed Project Report – GHSS Pandikkad
A Special Purpose Vehicle (SPV) as Project Management and Support Unit (PPE-
SU) will be formed for the overall smooth roll out of PPE Mission.
a) Government
The Government shall facilitate the linkages between parties and different
Ministries and their departments and other stakeholders as required for the
smooth implementation of PPE Mission.
In order to implement the project an SPV will be formed. The funds received
from KIIFB will be utilized through this SPV. In order to ascertain the timely
completion of the project, SPV will appoint an agency, which is called the
implementation agency. The progress of the work will be monitored by the SPV
through the implementation agency with the assistance of the technical
committee.
c) Implementing Agencies
d) Technical consultant
65
Detailed Project Report – GHSS Pandikkad
i. Carry out the detailed review of the master plans provided to it by the
CEO who has received them from the schools selected by the MLAs in
consultation with Government.
ii. In case the master plans are not available, prepare them after discussions
with the Parent Teacher Association/School Development Committee and
the local MLA.
iii. Consult with the implementing SPV and develop the DPRs (Detailed
Project Reports) for Civil Works to be completed under PPE Mission.
iv. These DPRs (as required in DPR formats to be mutually established by
CEO and KITCO) will be submitted to KIIFB by CEO- PPE Mission with
the help of PPE-SU after appropriate discussions.
v. Assist CEO- PPE Mission to prepare agreements to ensure that the
SPV/builder is responsible for the maintenance of the newly created
school building for at least 5 years.
vi. Assist CEO PPE Mission to develop a project implementation schedule
and be responsible for ensuring that the progress is documented and
timelines adhered to by SPVs and implementing agencies
vii. Monitor and provide periodic progress and status report of the school
civil works to CEO PPE Mission
viii. Coordinate with the SPVs to get completion and occupancy certificates
e) School Development committee/ School level monitoring committee:
The development committee at each school also will be in charge of the project
monitoring. The members of the committee will include the Principal, Head
Teacher, PTA and other various stake holders.
f) Contractor:
The works will be carried out by the Contactor appointed through the tendering
process.
66
Detailed Project Report – GHSS Pandikkad
Implementation
consultant
School Development
Contractors
67
(g) Completion and handing over
68
Project
Management Unit
(Will report to SPV)
support team -
Project Manager
Technical Records and
(Implementiing
Consultant Finance
Agency)
Management
Site supervision
team
The SPV, with the help of technical consultant will review the reports, bills,
statements from the site and will provide the feedback to the Project
Manager.
SPV will have a team to handle the records, documents of the project. The team
will also act as fiancé control team for the project to support the payments as
per the agreed schedule. Also this team will extend the administrative support
to the SPV while implementing the project.
69
Detailed Project Report – GHSS Pandikkad
2) Tendering:
All the bids received will be evaluated and the selection of contractor as per the
existing norms.
4) Award of work
5) Signing of Agreement
The contractor to whom which the work is awarded need to sign an agreement
with the implementing agency.
Time is the essence of Contract, hence clear time line with details about the
works to be completed in each phase or within stipulated time should be
mentioned in detail. The project implementation schedule will be a part of the
agreement.
7) Work execution
During execution, the compliance with the Contact conditions and adherence
to the Contractual obligations shall be ensured by multiple level reviews under
68
Detailed Project Report – GHSS Pandikkad
taken by the SPV, technical team and implementation team. The project
manager, who is in charge of the project, member of the implementation team
will strictly monitor the project in adhering to the Contract conditions. The
amendments and changes shall be properly documented and the necessary
approvals will be obtained from the approving authority. All such matters will
be routed through the project manager.
The quality analysis and quality control of the works need to assess as per the
approved QA/QC plan.
The Contractor can raise the Running Account Bill as per the payment after
conducting the joint inspection at site, as certified by the Project Manager.
After completing all the works including civil works, electrical works,
mechanical works, instrumentation works, signage works, security systems and
other auxiliary works, the implementing agency handover the facilities to the
school for inauguration.
The project is intended to execute through capable and competent
implementing agencies. The agencies with proven track record, recognized by
Government of Kerala for executing its works etc are eligible for considering as
implementing agencies. Through a fair and transparent process, the agencies
will be empanelled. Among these agencies, through suitable means (as decided
by the SPV in line with the existing practices and guidelines), selection will be
carried out for implementing the project.The work will be executed as item rate
tender PWD procedures will be adhered to.
69
Detailed Project Report – GHSS Pandikkad
Project schedule:
The work has been considered as a composite work combining the civil,
electrical and all other utility work packages combined in one contract. The
work in each phase has been scheduled to complete as per the following
schedule:
Months
Activity
M1 M2 M3 M4 M5 M6 M7 M8 M9
1. Tendering and award of
work
1.1 Issue of tender notice
1.2 Receipt of bids
1.3 Bid evaluation / Selection
of Contractor
1.4 Award of work
2. Preparatory work and
mobilisation
2.1 Signing of contract
2.2 Obtaining of preliminary
statutory approvals
2.3 Submission of drawings
2.4 Completion of mobilisation
3. Implementation of Civil
package
4. Up gradation of Electrical
works
5. Up gradation of utilities
6. Landscaping, signage,
circulation improvement
7. Procurement and placing of
school furniture
8. Obtaining approvals and
inauguration
70
Detailed Project Report – GHSS Pandikkad
71
Detailed Project Report – GHSS Pandikkad
In order to manage the quality of the work specific plan is envisaged. Even
though quality is the responsibility of each individual involved in the project, a
team will be formed with objective to assure quality. The team will be headed
by a quality manager from the implementation unit whose activities will be
reviewed by the SPV. Under the quality manger, there will be a quality team
consist of inspection and testing unit and site engineers. The quality
management organization frame work is as follows:
Implementing Agency
Quality Manger
72
Detailed Project Report – GHSS Pandikkad
Quality Management system will be as per IS 9001: 2015. All the organizations
involved in the implementation has to strictly adhere to the Quality
Management policies.
73
Detailed Project Report – GHSS Pandikkad
O&M plays a vital role in deriving maximum out of any infrastructure. Schools
generally lack mechanism/ system for operation and maintenance of its
facilities due to various reasons including inadequate fund, lack of dedicated
staff etc.
An O&M fund need to be maintained which will take care of all the revenue from
providing these facilities to the public, as mentioned in chapter 7
c) O&M staff
Additional staffs need to be engaged, other than the existing staff, if required
for keeping clean and safe campus. The remuneration for these staffs needs to
be met from the O&M fund.
74
Detailed Project Report – GHSS Pandikkad
Taluk Wandoor
Legislative Assembly constituency Manjeri
4. Implementing agency/ SPV under finalization by Govt. of
Kerala
5. DPR prepared by KITCO LTD
75
Detailed Project Report – GHSS Pandikkad
76
Detailed Project Report – GHSS Pandikkad
Annexures
77
Detailed Project Report – GHSS Pandikkad
Annexure 1
Key map of Project Region
78
Detailed Project Report – GHSS Pandikkad
Annexure 2
Architectural Drawings
79
4.2
2 5
5.1
Double Galvalume sheet
over MS steel truss (Gray color)
3.76
Aluminum Louvered window
1.20
3.60
1.50
Aluminum window Aluminum window MS RHS support(Gray color)
7
2.5
Single Galvalume sheet
over MS steel truss (Gray color)
Single Galvalume sheet
MS RHS support(Gray color) 1.00 over MS steel truss (Gray color)
3.60
1.00
5
1.1
3.60
1.4
Aluminum Louvered window MS RHS support(Gray color)
8
1.2
1
ELEVATION SCHEMATIC SECTION
PANDIKKAD GHSS
1 2 3 4 5 6 7 8 9 10 11 12
B2 2205 B2 6010 B2
B2 B1
H K H
B2 B2 B2
125 Thk.
3230
B1
J
125 Thk.
B2 B2 B2
125 Thk.
3230
G G
B2 B1
H
RCC SLAB RCC SLAB
B2 B2 B2
125 Thk.
3230
350
450
B1
RCC BEAM
RCC BEAM G
125 Thk.
250
250
F TYPICAL CROSS SECTION B2 B2 B2 F
125 Thk.
3230
B2 B2 B2
125 Thk.
3230
29330
B1
E
125 Thk.
E E
B2 B2 B2
3230
125 Thk.
B2 B1
D
B2
1740
B2 B2 B2 B2 B2 B2 B2 B2 B2 B2 B2 B2 B2 B2
B2 STAIRCASE B2
C
125 Thk.
D B2 125 Thk. B2 125 Thk. B2 125 Thk. B2 125 Thk. B2 125 Thk. B2 125 Thk. B2 125 Thk. B2 125 Thk. B2 D
2200
B2 B2 B2 B2 B2 B2 B2 B2 B2 B2 B2 B2 B2 B1
B
B1 B1
B1 125 Thk. B1 125 Thk. B1 125 Thk. B1 125 Thk. B1 125 Thk. B1 125 Thk. B1 STAIRCASE B1 125 Thk. B1 125 Thk. B1 125 Thk. B1 125 Thk. B1 125 Thk. B1 125 Thk. B1 140 Thk. B1 140 Thk. B1 140 Thk. B1
6010
B2 B2 B2 B2 B2 B2 B2 B2 B2 B2 B2 B2 B2 B1 B1 B1
A
3230 3230 3230 3230 3230 3230 3830 3230 3230 3230 3230 3230 3230 3237 613 1592 2258 3752
54042
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
CHECKED
TOILET AREA KITCO Ltd.
(Estd. in 1972 by IDBI & Govt. of Kerala)
DRAWN PUTHIYA ROAD - NH BYPASS, KOCHI - 28
2205 6010
150
H K H
250 250 GL
250 F2,C2
150
GRADE BEAM
100 100
1500 (MIN.)
J
250
400
450
100(TYP.)
F1,C1 F1,C1
D2
3230
100 (TYP.)
D1
PCC 1:4:8, F2,C2
G PCC 1:4:8, 100 THK. G
100 THK. C1 - 250 x 450 C2 - 250 x 250
100 B 100 GRADE BEAM-GB1 (250x400) H
HARD STRATA
F2,C2
G
SCHEDULE OF COLUMN FOOTING
100
3230
L
WHERE SBC IS ASSUMED AS 200 kN / SQ.M
A A
COLUMN F1,C1 F1,C1
3230
29330
F2,C2
E
E E
B F1,C1 F1,C1
3230
PLAN F2,C2
DETAILS OF COLUMN FOOTING
D
F2,C2 F2,C2 F2,C2 F2,C2 F2,C2 F2,C2 F2,C2 F2,C2 F2,C2 F2,C2 F2,C2 F2,C2 F2,C2 F2,C2
1740
D D
2200
F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1
6010
F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1
3230 3230 3230 3230 3230 3230 3830 3230 3230 3230 3230 3230 3230 3237 613 1592 2258 3752
54042
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
DESIGNED
H H
RCC SLAB RCC SLAB
350
450
RCC BEAM
RCC BEAM
250
G G
250
TYPICAL CROSS SECTION
TYPICAL CROSS SECTION OF BEAM B2 - 250 x 350
OF BEAM B1 - 250 x 450
F F
1 2 3 4 5 6 7 8 9 10 11
32110
3238 3238 3200 3200 3200 3200 3200 3196 3208 3230
B2 B2 B2 B2 B2 B2 B2 B2 B2 B2
C
E E
B1 B1 B1 B1 B1 B1 B1 B1 B1 B1 B1
125 Thk. 125 Thk. 125 Thk. 125 Thk. 125 Thk. 125 Thk. 125 Thk. 125 Thk. 125 Thk.
6010
8210
D
B2 B2 B2 B2 B2 B2 B2 B2 B2 B2
B
B2 125 Thk. B2 125 Thk. B2 125 Thk. B2 125 Thk. B2 125 Thk. B2
2200
C A
B2 B2 B2 B2 B2 B2 B2 B2 B2 B2
DESIGNED CLIENT:
DEPARTMENT OF EDUCATION
GOVT. OF KERALA
CHECKED
PROJECT:
REJUVENATION OF GOVERNMENT SCHOOLS
DRAWN
PANDIKKAD GOVT. HIGH SCHOOL
SL.No. PARTICULARS INITIAL DATE UNIT: SCALE: DRG NO: SHEET NO: REV. DATE:
mm. NTS DP 871 DRG CL 00 004 1 OF 1 17.06.2017
1 2 3 4 5 6 7 8 9 10 11 12
DETAILS OF COLUMN
GL. COLUMN TYPICAL DETAILS OF GRADE BEAM
H 250 250 H
150
GL
100
250
150
GRADE BEAM
250
100 GRADE BEAM
450
400
100(TYP.)
L
A A
COLUMN 100 100
1500 (MIN.)
PCC 1:4:8,
G C1 - 250 x 450 C2 - 250 x 250 100 THK.
G
D2
100 (TYP.) SCHEDULE OF COLUMN FOOTING
D1
PCC 1:4:8, TYPE L B D1 D2
B 100 THK.
100 B 100 F1 2000 2000 400 500
PLAN HARD STRATA
F2 1400 1400 350 350
F DETAILS OF COLUMN FOOTING F
SECTION A - A FOOTING PCC TO BE LAID ON HARD STRATA
WHERE SBC IS ASSUMED AS 200 kN / SQ.M
1 2 3 4 5 6 7 8 9 10 11
32110
3238 3238 3200 3200 3200 3200 3200 3196 3208 3230
E C E
F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1
6010
D
8210
F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1 F1,C1
2200
C
F2,C2 F2,C2 F2,C2 F2,C2 F2,C2 F2,C2 F2,C2 F2,C2 F2,C2 NOTE: F2,C2 F2,C2
1. ALL DIMENSIONS ARE IN MILLIMETERS AND LEVELS ARE IN METERS.
LAYOUT OF RCC COLUMN AND FOOTING 2. ONLY WRITTEN DIMENSIONS SHOULD BE FOLLOWED.
3. ±0.00 Lvl. CORRESPONDS TO FINISHED FLOOR LEVEL.
4. CONCRETE SHALL BE CONTROLLED QUALITY AS PER IS:456-2000, MIX. M25.
B 5. BEND,HOOK,LAP LENGTH ETC., SHOULD BE TAKEN AS PER IS:456-2000.
6. FOUNDATION IS DESIGNED FOR G+2 FLOORS
DESIGNED CLIENT:
DEPARTMENT OF EDUCATION
GOVT. OF KERALA
CHECKED
PROJECT:
REJUVENATION OF GOVERNMENT SCHOOLS
DRAWN
PANDIKKAD GOVT. HIGH SCHOOL
SL.No. PARTICULARS INITIAL DATE UNIT: SCALE: DRG NO: SHEET NO: REV. DATE:
mm. NTS DP 871 DRG CL 00 003 1 OF 1 17.06.2017
Detailed Project Report – GHSS Pandikkad
Annexure 3
Detailed Estimate
80
KITCO LTD
DEPARTMENT OF EDUCATION, GOVT. OF KERALA
GHS PANDIKKAD
SH: ELECTRICAL WORKS
ABSTRACT OF COST
TOTAL 1348174.00
Contingency @ 3% 40445.22
\\datalibrary1\2017-18 Open\School Reports- Modified\11. Pandikad\27.Pandikkad GHS EE\abs (Pa No. 1)\gm 1
KITCO LTD
DEPARTMENT OF EDUCATION, GOVT. OF KERALA
GHS PANDIKKAD
SH: ELECTRICAL WORKS
SPECIFICATION AND SCHEDULE OF QUANTITIES
PART -A
LT PANEL BOARDS AND ACCESSORIES
METERING BOARD
PART -B
CABLES AND CABLING
2.0 Supply of following size 1.1 KV grade XLPE insulated, PVC
sheathed, armoured Aluminium /copper conductor cable
conforming to IS 7098 (Part 1) amended upto date.
4.0 Laying and fixing of one number PVC insulated and PVC sheathed
/ XLPE power cable of 1.1 KV grade of following size on wall or
surface as required.
4.01 Upto 35 sq. mm (clamped with 1mm thick saddle) m 25.00 35.05 876.25
5.0 Laying of one number PVC insulated and PVC sheathed armoured
power cable of 1.1kV grade fo the following sizes in ground
including excavation ,sand cushioning , providing protective
covering and refilling the trench etc. as required
6.0 Laying of one number PVC insulated and PVC sheathed / XLPE
power cable of 1.1 KV grade of following size in the existing RCC/
HUME/ METAL pipe as required.
7.0 Laying and fixing of one number PVC insulated and PVC sheathed/
XLPE power cable of 1.1 KV grade of following size on cable tray
as required.
7.01 Upto 35 sq. mm (clamped with 1mm thick saddle) m 5.00 29.44 147.21
8.0 Providing, laying and fixing following dia G.I. pipe (medium class) in
ground complete with G.I. fittings including trenching (75 cm
deep)and re-filling etc as required
\\datalibrary1\2017-18 Open\School Reports- Modified\11. Pandikad\27.Pandikkad GHS EE\est (Pa No. 2 - 12) \gm 2
Sl.No Description of Items Unit Qty Rate (Rs) Amount (Rs)
11.0 Providing & fixing Fire Barrier mortar with minimum 2 hours fire
rating when tested in accordance with BS 476 part 20 and UL 1479
for horizontal openings in fire rated floors or slabs and vertical
openings in walls for passing service shafts. The service lines could
be of various types like electrical cables trays, metal pipes, GI
Ducts for AC, etc.The mortar shall have minimum hardened density
of 0.8 g/cm3 and It should have a compressive strength of 2.9N/Sq
mm . The product shall be Smoke & Air Seal and 30 years Age
tested as per Dafstb and DIBT standards. The product shall be
tested and approved by third party agencies such as UL and FM.
The mortar should be tested in accordance with IEC 60068-2-
57:1999-11 (Environmental Testing) as per Part 2-57: Test for
Vibration-Time-history method and VERTEQII for seismic zone 4.
The product shall bear the UL and FM approval logo on the packing
where applicable.
sqm 0.32 11500.00 3726.00
PART- C
WIRING AND ACCESSORIES
12.0 Wiring for light point/ fan point/ exhaust fan point/ call bell point with
1.5 sq.mm FRLS PVC insulated copper conductor single core cable
in surface / recessed medium class PVC conduit, with modular
switch, modular plate, suitable GI box and earthing the point with
1.5 sq.mm. FRLS PVC insulated copper conductor single core
cable etc as required. (Note:The total distance from the switch box
to the point will not exceed 5mtr, incase if length increases above 5
metres, the wiring shall be measured under item 18.1)
no 210.00 1061.31 222875.94
13.0 Wiring for twin control light point with 1.5 sq.mm FRLS PVC
insulated copper conductor single core cable in surface / recessed
medium class PVC conduit, 2 way modular switch, modular plate,
suitable GI box and earthing the point with 1.5 sq.mm. FRLS PVC
insulated copper conductor single core cable etc as required..
(Note:The total distance from the switch box to the point will not
exceed 5mtr, incase if length increases above 5 metres, the wiring
shall be measured under item 18.1) no 5.00 1008.04 5040.19
14.0 Group controlled light point with 1.5 sq. mm wire - Wiring for Group
controlled light point (from one point to another point) with 3X 1.5
sq. mm PVC insulated, (FRLS), copper conductor cable in
surface/recessed mounted rigid medium class 20mm PVC conduit
with all accessories as required. ( Note: This item does not include
the cost of MCB or 16Amp/ 6Amp one way switches. The total
distance from one point to another point will not exceed 5meters. In
case if the total length increases 5meters, the additional lengtth
shall be measured under item 18.1 The distance from DB to 1st
point will be measured under point circuit wiring.
no 25.00 829.40 20735.00
15.0 Circuit wiring -Wiring for circuit/ submain wiring along with earth
wire with the following sizes of FRLS PVC insulated copper
conductor, single core cable in surface/ recessed medium class
PVC conduit as required.
15.1 2 X 1.5 sq. mm + 1 X 1.5 sq. mm earth wire m 436.00 157.02 68462.46
15.2 2 X 2.5 sq. mm + 1 X 2.5 sq. mm earth wire m 1308.00 192.07 251232.79
16.0 Supplying and fixing following modular switch/ socket with modular
plate & cover on surface or in recess, including proving and fixing
suitable size GI box,inter connection etc as required complete.
17.0 Supplying and fixing stepped type electronic fan regulator with
modular plate & cover on surface or in recess, including proving
and fixing suitable size GI box,inter connection etc as required
complete. no 65.00 649.13 42193.19
18.0 Supplying and fixing suitable size GI box with modular plate and
cover in front on surface or in recess, including providing and fixing
6 pin 5/6 & 15/16 amps modular socket outlet and 15/16 amps
modular switch, connection etc. as required. no 1.00 569.21 569.21
19.0 Supplying and fixing suitable size GI box with modular plate and
cover in front on surface or in recess, including providing and fixing
3 pin 5/6 amps modular socket outlet and 5/6 amps modular switch,
connection etc. as required. (For light plugs to be used in non
residential buildings). no 58.00 438.83 25451.91
20.0 Supply & fixing Computer points with 3 nos 3 pin 5/6A socket with
2no.5/6A switch with modular front plate and cover on
surface/recess, including proving and fixing suitable size GI boxs,
its interconnections etc as required complete. (Note: 2 nos 5/6A
socket fixed at 60cm above FFL and 2 nos 6A switch with 1no 5/6A
socket at 1m above FFL) no 1.00 1099.31 1099.31
21.0 Supply, fixing of Network point, UTP RJ45, CAT 6 modular type
socket with modular plate & cover on surface or in recess, including
proving and fixing suitable size GI box, inter connection etc as
required complete. no 1.00 608.50 608.50
\\datalibrary1\2017-18 Open\School Reports- Modified\11. Pandikad\27.Pandikkad GHS EE\est (Pa No. 2 - 12) \gm 3
Sl.No Description of Items Unit Qty Rate (Rs) Amount (Rs)
22.0 Supplying and fixing modular blanking plate on the existing modular
plate & switch box excluding modular plate as required.
no 20.00 33.65 672.96
PART -D
MCBs AND MCB DISTRIBUTION BOARDS
25.0 Supplying and fixing following way, horizontal type three pole and
neutral, sheet steel, MCB distribution board, 415 volts, on
surface/recess, complete with tinned copper bus bar, neutral bus
bar, earth bar, din bar, interconnections, powder painted including
earthing etc. as required. (But without MCB/RCCB/Isolator).
26.0 Supplying and fixing following way, single pole and neutral, sheet
steel, MCB distribution board, 240 volts, on surface/ recess,
complete with tinned copper bus bar, neutral bus bar, earth bar, din
bar, interconnections, powder painted including earthing etc. as
required. (But without MCB/RCCB/Isolator)
27.0 Supply and fixing of following rating residual current circuit breaker
with MCB having earth leakage and overload protection
(RCCB+MCB) as per specification as required
29.0 Supplying and fixing single pole blanking plate in the existing MCB
DB complete etc. as required. no 25.00 9.81 245.35
PART- E
LIGHT FIXTURES AND FANS
30.0 Supply of indoor industrial surface mounted LED tube and batten
along with driver , surge protector,system wattage of 20+/-2
Watts,lumen output of lamp greater than 1600lumen, power factor
> 0.9,rated life of L70 @ 50,000 hours, system efficacy greater
than 70lumen/watt and including all necessary accessories as
required complete.Make:Philips TMC 501 P 1xT-LED 20W or
equivalent approved make)
no 126.00 1570.00 197820.00
31.0 Supply of indoor decorative surface mounted LED Batten with High
Efficiency Extruded aluminium housing and Polycarbonate Diffuser
with provision of End to End connection,along with driver,system
wattage of 10+/-2 Watts,lumen output of lamp greater than 800,
power factor > 0.9,rated life of L70 @ 50,000 hours, system
efficacy greater than 70lumen/watt and including all the necessary
accessories as required complete.(Make: Philips BN021C LED20S
PSU NW GR or equivalent approved make)
no 22.00 739.00 16258.00
32.0 Supply of indoor industrial surface mounted LED tube with Batten
along with driver , surge protector,,system wattage of 40+/-4
Watts(2x20 watts),lumen output of lamp greater than 3000 lumen,
power factor > 0.9,rated life of L70 @ 50,000 hours, system
efficacy greater than 70lumen/watt and including all necessary
accessories as required complete.(Make:Philips TMC 501 P 2xT-
LED 20W or equivalent approved make)
no 4.00 1382.00 5528.00
\\datalibrary1\2017-18 Open\School Reports- Modified\11. Pandikad\27.Pandikkad GHS EE\est (Pa No. 2 - 12) \gm 4
Sl.No Description of Items Unit Qty Rate (Rs) Amount (Rs)
PART - F
EARTHING AND SAFETY EQUIPMENTS
36.0 Earthing with C.I. earth pipe 4 metre long, 100 mm dia including
accessories, and providing masonry enclosure with heavy duty CI
cover plate of 300X300mm having locking arrangement and
watering pipe etc. with 64kg charcoal/ coke and 5kg salt as
required. (As per IS 3043 ammended uptodate) no 2.00 13389.01 26778.02
38.00 Supplying and laying G.I/Copper strip at 0.50 metre below ground
as strip earth electrode, including connection/ terminating with G.I.
nut, bolt, spring, washer etc. as required. (Jointing shall be done by
overlapping and with 2 sets of G.I. nut bolt & spring washer spaced
at 50mm)
\\datalibrary1\2017-18 Open\School Reports- Modified\11. Pandikad\27.Pandikkad GHS EE\est (Pa No. 2 - 12) \gm 5
KITCO LTD
DEPARTMENT OF EDUCATION, GOVT. OF KERALA
GHS PANDIKKAD
SH: ELECTRICAL WORKS
RATE ANALYSIS
A2 Lumpsum item
1 Cartage @ 1% of A1 2.04
Total A2
Total of A = A1 + A2 206.45
A2 Lumpsum item
1 Cartage @ 1% of A1 1.34
\\datalibrary1\2017-18 Open\School Reports- Modified\11. Pandikad\27.Pandikkad GHS EERate Ana (Pa No. 13 -32)27.Pandikkad GHS EE\gm 13
Sl.No Description Unit Qty Rate(Rs) Amount (Rs)
Total A2
Total of A = A1 + A2 135.79
8.0 Providing, laying and fixing following dia G.I. pipe (medium class) in
ground complete with G.I. fittings including trenching (75 cm deep)and
re-filling etc as required
\\datalibrary1\2017-18 Open\School Reports- Modified\11. Pandikad\27.Pandikkad GHS EERate Ana (Pa No. 13 -32)27.Pandikkad GHS EE\gm 14
Sl.No Description Unit Qty Rate(Rs) Amount (Rs)
14 Group controlled light point with 1.5 sq. mm wire-5 MTR LENGTH
A1 Materials
1 1.5 sqmm, PVC insulated, copper conductor single core wire, FRLS
Mtrs 15.75 15.56 245.10
2 Ceiling rose, 3 pin, 5A, ISI marked Nos 1.00 20.19 20.19
3 20mm rigid PVC junction box, one way Nos 1.00 21.66 21.66
4 20 mm dia, PVC conduit Mtrs 4.73 16.56 78.32
5 20 mm PVC bends Each 1.00 7.92 7.92
6 20 mm PVC couplers Each 2.00 4.91 9.81
7 20mm iron staples/saddles/screws Each 9.00 2.24 20.19
8 PVC fastners 40mm long Each 9.00 0.39 3.53
9 Cement, Paint, sand etc L.S. 1.00 15.42 15.42
Total A1 422.15
A2. Lump Sum Items
2 Cartage @ 1% of A1 4.22
Total A2 4.22
Total of A = A1 + A2 426.37
B. Labour
1 Wireman Days 0.22 626.69 137.87
2 Mason Days 0.04 570.61 22.82
3 Wireman Helper Days 0.26 515.94 134.14
Total B 294.84
Total A + B 721.21
C. Overhead & profit @ 15% of (A+B+C) 108.18
Total A + B + C 829.40
Rate per point 829.40
Say 829.40
21.00 RJ 45
Cost for 1 each
A1 Materials
1 RJ 45 socket Nos. 1.00 267.4 267.40
Total A1 267.40
A2 Lumpsum Items
1 Cartage @ 1% of A1 2.67
Total A2 2.67
\\datalibrary1\2017-18 Open\School Reports- Modified\11. Pandikad\27.Pandikkad GHS EERate Ana (Pa No. 13 -32)27.Pandikkad GHS EE\gm 15
Sl.No Description Unit Qty Rate(Rs) Amount (Rs)
Total of A = A1 + A2 270.07
B Labour
1 Wireman Days 0.04 626.69 25.07
3 Helper Days 0.04 515.94 20.64
Total B 45.71
Total A + B 315.78
C. Overhead & profit @ 15% of (A+B) 47.37
Total A + B + C 363.15
Rate per each 363.15
Say 363.15
27.01 Supply and fixing of following rating residual current circuit breaker with MCB having earth leakage and
A.1 Material
1 4 pole 40amps. (415 Volts), 30mA sensitivity No. 1.00 2909.45 2909.45
2 4 pole 40A MCB No. 1.00 1891.54 1891.54
Total A1 4800.99
A.2 Lump Sum Items
1 Cartage @ 1% of A1 48.01
Total A2 48.01
Total of A = (A1+A2) 4848.99
B. Labour
1 Wireman, Grade 1 day 0.08 626.69 50.14
2 Khallasi day 0.08 515.94 41.27
Total B 91.41
Total (A+B) 4940.41
C Overheads & Profit @ 15% of (A+B) 741.06
Total (A+B+C) 5681.47
Rate per Each 5681.47
Say 5681.47
27.02 Supplying and fixing single pole blanking plate in the existing MCB DB complete etc. as required.
A.1 Material
1 4 pole 63amps. (415 Volts), 30mA sensitivity No. 1.00 3481.72 3481.72
2 4 pole 63A MCB No. 1.00 1717.80 1717.80
Total A1 5199.52
A.2 Lump Sum Items
1 Cartage @ 1% of A1 52.00
Total A2 52.00
Total of A = (A1+A2) 5251.51
B. Labour
1 Wireman, Grade 1 day 0.08 626.69 50.14
2 Khallasi day 0.08 515.94 41.27
Total B 91.41
Total (A+B) 5342.92
C Overheads & Profit @ 15% of (A+B) 801.44
Total (A+B+C) 6144.36
Rate per Each 6144.36
Say 6144.36
\\datalibrary1\2017-18 Open\School Reports- Modified\11. Pandikad\27.Pandikkad GHS EERate Ana (Pa No. 13 -32)27.Pandikkad GHS EE\gm 16
Sl.No Description Unit Qty Rate(Rs) Amount (Rs)
1 Wireman No 0.08 626.69 50.14
2 Wireman Helper No 0.08 515.94 41.27
Total B 91.41
Total A+B 1595.49
C. O.H & Profit @ 15 % of (A+B) 239.32
Total = A+B+C 1834.81
Say 1,834.81
A1 Material
1x28W T5 light fixture No 1 1338.75 1338.75
Total A1 1338.75
A2 Lumpsum item
Cartage @ 2% of A1 26.78
Total A2 26.78
Total of A = A1 + A2 1365.53
A1 Material
10W LED batten No 1 630.00 630.00
Total A1 630.00
A2 Lumpsum item
Cartage @ 2% of A1 12.60
Total A2 12.60
Total of A = A1 + A2 642.60
A2 Lumpsum item
Cartage @ 2% of A1 23.56
Total A2 23.56
Total of A = A1 + A2 1201.77
\\datalibrary1\2017-18 Open\School Reports- Modified\11. Pandikad\27.Pandikkad GHS EERate Ana (Pa No. 13 -32)27.Pandikkad GHS EE\gm 17
Sl.No Description Unit Qty Rate(Rs) Amount (Rs)
Rate per each 1382.03
Say 1382.00
A2 Lumpsum item
Cartage @ 2% of A1 34.87
Total A2 34.87
Total of A = A1 + A2 1778.13
A2 Lumpsum item
Cartage @ 2% of A1 22.84
Total A2 22.84
Total of A = A1 + A2 1164.98
\\datalibrary1\2017-18 Open\School Reports- Modified\11. Pandikad\27.Pandikkad GHS EERate Ana (Pa No. 13 -32)27.Pandikkad GHS EE\gm 18
Sl.No Description Unit Qty Rate(Rs) Amount (Rs)
Total A + B + C 922.75
Rate per meter 92.28
Say 92.28
Supply ISI pipe earthing as per IS 3043 with 100mm dia B class Ci
36
pipe earth
A1 Materials
1 100mm dia CI pipe B class Mtr 4.00 1260.00 5040.00
2 100mm to 20mm CI reducer Set 1.00 54.15 54.15
3 GI funnel with weld mesh on top Each 1.00 57.22 57.22
4 GI strip 40x6mm, 200mm length kg 0.50 65.55 32.77
Charcol kg 64.00 7.01 448.64
salt kg 5.00 11.50 57.48
5 Gully trap with covering box in CI (300x300x6mm) Each 1.00 2743.65 2743.65
TOTAL A1 8433.91
1 Cartage @ 1% of A1 84.34
2 Wastage @ 5% of 1 of A1 252.00
TOTAL A2 336.34
TOTAL OF A=( A1+A2) 8770.25
(B) LABOUR
1 Skilled No 1.00 626.69 626.69
1 Helper No 1.00 515.94 515.94
Total B 1142.63
TOTAL A+B 9912.88
D (C)Excavation including refilling as required Cu.m 2.50 179.92 449.80
E (D)Brick work in cement mortar Cu.m 0.30 3691.85 1107.55
F (E)Plastering Sq.M 1.20 143.65 172.38
TOTAL = A+B+C+D+E 11642.61
(F) O.H & Profit @ 15 % of (A+B+C+D+E) 1746.39
TOTAL = A+B+C+D+E+F 13389.01
Say Rs 13389.01
\\datalibrary1\2017-18 Open\School Reports- Modified\11. Pandikad\27.Pandikkad GHS EERate Ana (Pa No. 13 -32)27.Pandikkad GHS EE\gm 19
Sl.No Description Unit Qty Rate(Rs) Amount (Rs)
38.01 Supply & providing 25x6mm GI strip
Cost for 30m
A1 Materials
1 25mm x 6mm GI tape (1.2kg/ mtr) Kg. 37.8 58.88 2225.82
2 Solder jointing each 5 16.82 84.12
TOTAL A1 2309.94
(A2)lumpsum items
1 Cartage @ 1% of A1 23.10
TOTAL A2 23.10
TOTAL OF A=( A1+A2) 2333.03
(B) LABOUR
1 Wireman Days 0.13 626.69 81.47
2 Khallasi Days 0.13 515.94 67.07
3 Cable jointer Days 1 626.69 626.69
Total B 775.24
TOTAL A+B 3108.27
(C) O.H & Profit @ 15 % of (A+B) 466.24
TOTAL = A+B+C 3574.51
rate per meter 119.15
SAY Rs 119.15
9.00 Supply & installing of 200 mm wide ladder type cable tray.
Cost for 30 mtr
A1 Materials
200mm wide cable tray m 30 444.26 13327.80
Total A1 13327.80
A2 Lumpsum Items
GI suspenders and accessories @ 2% of A1 266.56
Cartage @ 1% of A1 133.28
Accessories @ 2% of (1) of A1 266.56
Total A2 666.39
Total of A = A1 + A2 13994.19
B Installation charges @ 10% of A 1399.42
Total B 1399.42
Total A + B 15393.61
\\datalibrary1\2017-18 Open\School Reports- Modified\11. Pandikad\27.Pandikkad GHS EERate Ana (Pa No. 13 -32)27.Pandikkad GHS EE\gm 20
Sl.No Description Unit Qty Rate(Rs) Amount (Rs)
C. Overhead & profit @ 15% of (A+B) 2309.04
Total A + B + C 17702.65
Cost per m 590.09
Add for labour welfare cess @ 1% 5.90
Say 596.00
\\datalibrary1\2017-18 Open\School Reports- Modified\11. Pandikad\27.Pandikkad GHS EERate Ana (Pa No. 13 -32)27.Pandikkad GHS EE\gm 21
KITCO LTD
SH : CIVIL WORKS
TOTAL ABSTRACT OF COST - GREEN SPACE 2
TOTAL 250,028.00
Mixing the red earth and sand in equal quantities and adding
8.05 manure in required proportion etc. complete as directed by
the Engineer- in- charge cum 4.00 28.21 112.82
8.07 Supplying and Planting grass over the red earth and sand
bed closely to get a thick grass lawn suitable for ground in
rows of 5cm apart in both direction, keep the area moisture
by spraying and sprinkling water till the grass gets sufficient
deep roots cutting to level the top surface, trimming and
dressing etc. complete as directed by the Engineer- in-
charge.
1.01 Surface dressing of the ground including removing vegetation and in-equalities not
exceeding 15cm deep and disposal of rubbish, lead upto 50m and lift upto 1.5m.
All kinds of soil sqm 100.000
105.000 18.39 1930.95
1.03 Filling with contractor's own earth ( excluding rock) in trenches, plinth, sides of foundations
etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming
and watering, lead up to 50 mm and lift up to 1.5 m as per direction of site Engineer-in-
charge cum
for filling inside seating arround tree 10.400
2.01 Providing and laying cement concrete of specific grade properly mixed and consolidated
with hand rammers, including cost and conveyance of all materials, labour, curing, lead lift ,
etc. complete for all work up to plinth levels as directed by Engineer- in-Charge.
2.01.01 1:4:8 (1 Cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size) cum
Seat arround tree 5 10.000 0.200 0.100 1.000
1.000
Say 2.000 6349.32 12698.64
2.02 Extra for providing and mixing water proofing material in cement concrete work, masonry
work, plastering etc in the proportion recommended by the manufacturers including cost
and conveyance of all materials, labour, curing, lead lift , etc. complete as directed by
Engineer-in-Charge at all levels. ltr
plastering item= 2.721
slab RCC= 0.000
2.721
Say 3.000 71.08 213.24
3.01 Providing and constructing Solid block masonry M-10 grade(mix 1:3:6) (1;cement ,3:crusher
sand,6: 6mm metal)in CM1:6(1cement, 6 coarse sand) with Solid blocks of 30x20x20 cm
size and approved quality including scaffolding, raking out of joints,curing, cost and
conveyance of all materials,labour, lead, lift, etc. complete for all types of masonry works in
super structure above the highest plinth level as directed by Engineer-in-Charge at all levels
cum
All work above plinth
Seat arround tree 5 10 0.2 0.45 4.500
4.500
Say 5.000 7222.93 36114.65
6.01 12mm cement plaster of mix 1:4 (1 cement : 4 fine sand)including cost and conveyance of
all materials, labour charges, scaffolding, sundries etc complete as directed by the Engineer
in charge at all levels.
Seat arround tree 10 10 0.45 45.000
5 10.000 0.300 15.000
60.000
Say 63.000 241.14 15191.82
6.02 Applying one coat of water thinnable cement primer of approved brand and manufacture on
all surface including cost and conveyance of all materials, labour charges, scaffolding,
sundries etc complete as directed by the Engineer in charge at all levels.
sqm
12 mm plaster 60.000
60.000
Say 62.000 52.92 3281.04
6.03 Finishing walls with Premium Acrylic Smooth exterior paint with Silicone additives of
required shade for new work (Two or more coats applied @ 1.43 ltr/ 10 sqm over and
including priming coat of exterior primer applied @ 2.20 kg/ 10 sqm). including cost and
conveyance of all materials, labour charges, scaffoldings etc complete as directed by the
Engineer in Charge at all levels.
sqm
60.000
8.01 Digging holes in ordinary soil and refilling the same with the excavated earth mixed with
manure or sludge in the ratio of 2:1 by volume (2 parts of stacked volume of earth after
reduction by 20%:1 part of stacked volume of manure after reduction by 8%) flooding with
water, dressing including removal of rubbish and surplus earth, if any, with all leads and lifts
(cost of manure, sludge or extra good earth if needed to be paid for separately). The rate
shall include maintenance of all planted species of the entire work as per the terms of the
contract. cum
Trees 7.00 0.60 0.60 0.6 1.51
1.512
Say 2.000 284.31 568.62
8.02 Supplying and stacking of good earth at site including royalty and carriage complete (earth
measured in stacks will be reduced by 20% for payment). cum
Lawn 212.00 0.150 31.80
Trees 7.00 0.60 0.60 0.15 0.38
Shrubs 0.00 0.60 0.60 0.15 0.00
32.178
Say 33.000 473.72 15632.76
8.03 Supplying river sand brought from outside including transportation,loading, unloading
,taxes etc complete as directed by the Engineer- in- charge cum
Lawn 212.00 0.040 8.48
Trees 7.00 0.60 0.600 0.080 0.20
8.682
Say 9.000 3280.39 29523.49
8.04
Supplying and stacking manure brought from outside to standard heaps for measurements
including transportation, loading, unloading ,taxes etc complete as directed by the Engineer-
in- charge ( manure measured in stacks will be reduced by 8% for payment) cum
Lawn 212.00 0.05 10.60
8.05 Mixing the red earth and sand in equal quantities and adding manure in required proportion
etc. complete as directed by the Engineer- in- charge cum
Lawn 1 184 0.010 1.840
trees 7 0.900 0.900 0.200 1.134
2.974
Say 4.000 28.21 112.82
8.06 Spreading of red earth, manure and river sand in required thickness as per direction of
Engineer-in-charge.( cost of red earth, manure and river sand paid seperately) cum
2.974
Say 4.000 332.83 1331.32
8.07 Supplying and Planting grass over the red earth and sand bed closely to get a thick grass
lawn suitable for ground in rows of 5cm apart in both direction, keep the area moisture by
spraying and sprinkling water till the grass gets sufficient deep roots cutting to level the top
surface, trimming and dressing etc. complete as directed by the Engineer- in- charge.
Trees
0.05 Peltophorum pterocarpum no
4
Say 4.000 145.19 580.76
Sl.No Code Description of Items Unit Quantity Rate (Rs) Amount (Rs)
5.02 Providing and laying 60mm thick faciory made cement concrete
interlocking paver block of M -30 grade made by block making
machine with strong vibratory compaction, of approved s;ze,
design & shape, laid in required colour and pattern over and
including 50mm thick compacted bed of coarse sand, filling the
joints with line sand etc. all complete as per the direction of
Engineer-in-charge
16.7 Rate as per DSR Item no16.68 615.70
cost index 1.48
908.89
Grand Total 908.89
6.01 13.1 DSR 12mm cement plaster of mix 1:4 (1 cement : 4 fine
sand)including cost and conveyance of all materials, labour
charges, scaffolding, sundries etc complete as directed by the
Engineer in charge at all levels. sqm
13.1.1 Rate as per DSR Item no 13.1.1 163.35
cost index 1.48
241.14
Grand total 241.14
6.02 13.43 DSR Applying one coat of cement primer of approved brand and
manufacture on wall surface sqm
6.03 13.46 DSR Finishing walls with Acrylic Smooth exterior paint of required
shade: sqm
13.47.1 Rate as per DSR Item no 13.46.1
New work (Two or more coat applied @ 1.67 ltr/10 sqm
over and including base coat of water proofing cement
paint applied @ 2.20 kg/10 sqm) 90.00
cost index 1.48
132.86
Grand total 132.86
Digging holes in ordinary soil and refilling the same with the
excavated earth mixed with manure or sludge in the ratio of 2:1
by volume (2 parts of stacked volume of earth after reduction by
20%:1 part of stacked volume of manure after reduction by 8%)
flooding with water, dressing including removal of rubbish and
surplus earth, if any, with all leads and lifts (cost of manure,
sludge or extra good earth if needed to be paid for separately).
The rate shall include maintenance of all planted species of the
entire work as per the terms of the contract.
8.01 cum
Details for pit size of 60x60x60cm
Excavation(0.6*0.6*0.6) (DSR item 2.6.1) cum 0.216 229.70 49.61
Refiiling mixture and flooding L.s 4.15 2.63 10.90
TOTAL 60.52
Add 1% for water charges 0.11
TOTAL 60.63
Add 15% for contractor's profit and overheads 1.64
Cost of 0.216 cum 62.26
Cost of 1 cum 284.31
284.31
Grand Total 284.31
9.01 Providing and laying at or near ground level factory made kerb
stone of M-25 grade cement in position to the required line,
level and curvature jointed with cement mortar 1:3 (1 cement: 3
coarse sand) including making joints with or without
grooves(thickness of joints except at sharp curve shall not to
more than 5mm) including making drainage opening wherever
required complete etc. as per direction of Engineer-in-Charge
(length of finished kerb edging shall be approved by Engineer-in-
Charge). cum
16.69 Rate as per DSR Item no 16.69 5295.90
cost index 1.48
7817.76
Grand Total 7817.76
8.05 Mixing the red earth and sand in equal quantities and adding
manure in required proportion etc. complete as directed by the
Engineer- in- charge cum
Details of cost for 10 cum.
LABOUR:
114 Beldar day 0.250 485.667 121.42
115 Coolie day 0.250 485.667 121.42
TOTAL 242.83
Add 1% for water charges 2.43
TOTAL 245.26
Add 15% for contractor's profit and overheads 36.79
TOTAL 282.05
Cost of 1.00 cum 282.05
28.21
Grand Total 28.21
8.07 Supplying and Planting grass over the red earth and sand bed
closely to get a thick grass lawn suitable for ground in rows of
5cm apart in both direction, keep the area moisture by spraying
and sprinkling water till the grass gets sufficient deep roots
cutting to level the top surface, trimming and dressing etc.
complete as directed by the Engineer- in- charge.
TOTAL 43923978.00
TOTAL 44,174,006.00
TOTAL 45,499,226.18
TOTAL 43,923,978.00
KITCHEN
HIGH Toilet Septic
Sl.No Description of Items Unit AND Sump Qty Rate(Rs) Amount(Rs)
SCHOOL Block build 1
DINNING
1.03.01 Beyond 30cm girth upto and including 60cm girth no 1 1.0 1.0 3.00 307.32 921.96
1.04.01 All kinds of soil cum 640 1,421.0 81.0 2142.00 233.29 499707.18
1.05.01 All kinds of soil. cum 36 79.0 12.0 127.00 305.84 38841.68
2.03 Extra for providing and mixing water proofing material in cement
concrete work in doses by weight of cement as per
manufacturer's specification kg 64 39.0 12.0 22.0 3 140.00 67.23 9412.20
All works above plinth level upto floor V level cum 67 331.0 43.0 - 441.00 10164.57 4482575.37
3.04 Providing, hoisting and fixing above plinth level up to floor five
level precast reinforced cement concrete work in string
courses, bands, copings, bed plates, anchor blocks, plain
window sills and the like, including the cost of required
centering, shuttering but , excluding cost of reinforcement, with
1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone
aggregate 20 mm nominal size).
cum 1 5.0 1.0 7.00 9774.88 68424.16
3.06.04 Columns, Pillars, Piers, Abutments, Posts and Struts. sqm 224 858.0 18.0 1100.00 655.93 721523.00
3.06.06 Stairs, (excluding landings) except spiral staircases. sqm - 71.0 - 71.00 587.93 41743.03
4.05.07 Edges of slab and breaks in floors and walls under 20 cms
m 0.00 171.32 0.00
wide.
0.00
3.06.08 Weather shade, Chajjas, corbels etc., including edges. sqm - - 13.0 - 13.00 731.49 9509.37
4.01 Solid block masonry using pre cast solid blocks ( factory made)
M-10 grade(mix 1:3:6) of size 40x20x20cm or nearest available
size confirming to IS 2185 part 1 of 1979 for foundation and
plinth with thickness 20 cm and above in: CM 1:6 ( 1 cement : 6
coarse sand) etc complete and approved quality including
scaffolding, raking out of joints,curing, cost and conveyance of
all materials,labour, lead, lift, etc. complete as directed by
Engineer-in-Charge. cum 0.00 5203.67 0.00
0.00
4.02 Solid block masonry using pre cast solid blocks (Factory made)
M-10 grade(mix 1:3:6)of size 30x20x20cm or nearest available
size confirming to IS 2185 part I of 1979 for foundation and
plinth with thickness 20cm and above in: CM 1:6 ( 1 cement : 6
coarse sand ) etc complete and approved quality including
scaffolding, raking out of joints,curing, cost and conveyance of
all materials,labour, lead, lift, etc. complete as directed by
Engineer-in-Charge.
cum 54.0 52.0 - 106.00 4977.00 527562.00
4.03 Solid block masonry using pre cast solid blocks (Factory made)
M-10 grade(mix 1:3:6) of size 40x20x20cm or nearest available
size confirming to IS 2185 part I of 1979 for super structure up
to floor two level thickness 20cm and above in: CM 1:6 ( 1
cement: 6 coarse sand) etc complete including scaffolding,
raking out of joints,curing, cost and conveyance of all
materials,labour, lead, lift, etc. complete as directed by
Engineer-in-Charge. cum 0.00 5691.83 0.00
0.00
4.04 Solid block masonry using pre cast solid blocks ( Factory
made) M-10 grade(mix 1:3:6) of size 30x20x20cm or nearest
available size confirming to IS 2185 Part I of 1979 for super
structure up to floor two level thickness 20cm and above in: CM
1:6 ( 1 cement : 6 coarse sand) etc complete including
scaffolding, raking out of joints,curing, cost and conveyance of
all materials,labour, lead, lift, etc. complete as directed by
Engineer-in-Charge. cum 16 257.0 - 273.00 5465.15 1491985.95
4.05 Solid block masonry using pre cast solid blocks (Factory made)
M-10 grade(mix 1:3:6) of size 30x20x20cm or nearest available
size confirming to IS 2185 part I of 1979 for super structure
above floor two level upto floor five level thickness 20cm and
above in : CM 1:6 ( 1 cement : 6 coarse sand sand) etc
complete including scaffolding, raking out of joints,curing, cost
and conveyance of all materials,labour, lead, lift, etc. complete
as directed by Engineer-in-Charge.
cum 67 25.0 92.00 5375.40 494536.80
4.09 Extra for providing and placing in position 2 Nos 6mm dia. M.S.
bars at every third course of half brick masonry including cost
and conveyance of MS bars etc complete as directed by
Engineer-in-Charge sqm 52 200.0 86.0 - 338.00 79.70 26938.60
4.13 Extra for laying brick work in or under water and/or liquid mud
including cost of pumping or bailing out water and removing
slush etc. complete. NOTE :- The quantity will be calculated by
multiplying the depth measured from sub - soil water level up to
the centre of gravity of brick work under sub - soil water with the
quantity of brick work in cum. executed under the sub - soil
water. The depth of centre of gravity shall be reckoned correct
to 0.1 m, 0.05 m or more shall be taken as 0.1 m and less than cum.
0.05 m ignored. per m
depth 0.00 665.25 0.00
5.01.01 For fixed portion kg 105 575.0 51.0 - 731.00 539.07 394060.17
0.00
5.03.01 with float glass panes of 5.00mm thickness sqm 0.00 1407.54 0.00
5.03.02 with float glass panes of 4.00mm thickness sqm 23 121.0 4.0 - 148.00 1039.58 153858.28
5.05 Extra for providing vision panel not exceeding 0.1 sqm in all
type of flush doors (cost of glass excluded)(overall area of door
shutter to be measured):Rectangular or square. sqm 0.00 227.97 0.00
0.00
5.06 Providing and fixing aluminium extruded section body tubular
type universal hydraulic door closer of approved make (having
brand logo with ISI, IS : 3564, embossed on the body, door
weight upto 36 kg to 80 kg and door width from 701 mm to
1000 mm), with double speed adjustment with necessary
accessories and screws etc. complete as directed by the
Engineer-in- Charge at all levels. no 5 24.0 5.0 34.00 544.54 18514.25
5.08 Providing and fixing Aluminium tower bolts ISI marked anodised
(anodic coating not less than grade AC 10 as per IS : 1868)
transparent or dyed to required colour or shade with nuts and
screws etc. complete as directed by the Engineer-in-Charge at
all levels.
5.10 Providing and fixing aluminium hanging floor door stopper ISI
marked anodised (anodic coating not less than grade AC 10 as
per IS:1868)transparent or dyed to required colour and shade
with necessary screws etc complete as directed by the
Engineer-in -Charge at all levels.
Single rubber stopper no 4 23.0 5.0 32.00 38.63 1236.16
Second class teak wood cum 0.2 2.0 - 2.22 130025.76 288657.19
5.18 Extra for providing heavy sheet float glass panes instead of
ordinary float glass in glazed doors, windows and clerestory
window shutters. (Area of opening for glass panes excluding
portion inside rebate shall be measured)
5.5 mm thick instead of 4 mm thick. sqm 10.0 10.00 332.20 3322.00
5.19 Providing 40x5 mm flat iron hold fast 40 cm long including fixing
to frame with 10 mm diameter bolts, nuts and wooden plugs or
approved dash fastners and embeddings in cement concrete
block 30x10x15 cm 1:3:6 mix (1 cement : 3 coarse sand : 6
graded stone aggregate 20 mm nominal size.
no 33 143.0 33.0 209.00 166.28 34752.52
5.21 Providing and fixing bright finished brass tower bolts (barrel
type) with necessary screws etc. complete as directed by the
Engineer-in-charge at all levels.
150 x 10 mm no 17 3.0 20.00 271 5424.34
5.22 Extra rate for providing etching on plain glass for Aluminium
doors including providing an additional 3 mm glass on the
rough side of etched glass including cost and conveyance of all
materials, all labour charges, lead, lift, all taxes, sundries, etc.,
complete at all levels as directed by the Engineer-in-Charge.
sqm 21.0 21.00 987.28 20732.88
0.00
5.23 Providing and fixing Fiber Glass Reinforced plastic (FRP) Door
Frames of crosssection 90 mm x 45 mm having single rebate
of 32 mm x 15 mm to receive shutter of 30 mm thickness. The
laminate shall be moulded with fire resistant grade unsaturated
polyester resin and chopped mat. Door frame laminate shall be
2 mm thick and shall be filled with suitable wooden block in all
the three legs. The frame shall be covered with fiber glass from
all sides. M.S. stay shall be provided at the bottom to steady
the frame. m 63.0 13.0 76.00 582.53 44272.28
5.25 Providing and fixing windows & ventilators, fabricated from roll
formed sections made of Galvanized steel, prepainted(base
steel as per IS 513"D" quality, Galvanised as per IS 277 with
zinc of 120 grams per sq. mtr) with total coated thickness of
0.60 mm. Coated sections should be painted with primer coat
of Epoxy primer of 5-7 microns thick, finish painted with
pollyster paint of 12-16 microns thick and back coated woth
alkyd backer of 5-7 microns thick or powder coated withpure
polyester powder coated up to 50-60 microns thick.Section for
Shutter should be of 46mm x 46mm and External Frame
should be of 46mm x 52mm. Section for Glass Beading should
be of 18mm x 25mm and center mullion should be of 46mm x
70mm and 50mm x 50mm box sections for Louvered
Ventilators.
The Frame & Shutter Sections should be cut to length and
mitre joined with Corner Bracket made of CRCA electroplated.
Mullion Section should be joined with Frame/ Mullion using
Nylon Mullion Cap, box sections for Ventilators should be joined
with aluminium
Handle made of‘L’high
brackets
gradeand PVC glass
Aluminium holders
powder will be
coated andused
with
nylon receiver. Gaskets made of Ethyl Propylene Diamine
Monomer (EPDM). Corner brackets made of CRCA with zinc
phosphating.
The assembledMullion
outercaps made
frame of Glass
should filledsto
be fixed nylon.
brick/concrete
masonry using nylon self-expanding caps driving MS
elecroplated 80 mm long screws in to the caps through outer
frames. Glazed shutters are connected to outer frames using
GI powder coated friction hinges of 250mm long. The infill for
shutter can be 4mm float glass of saint gobain/mosy make
complete. sqm 12.0 12.00 4692.46 56309.52
0.00
5.26 Providing and fixing cupboard shutters 25 mm thick, with Pre-
laminated flat pressed three layer particle board or graded
wood particle board IS: 12823 marked, exterior grade (Grade l
Type ll), having one side decorative lamination and other side
balancing lamination, including IInd class teak wood lipping of
25 mm wide x12 mm thick with necessary screws and bright
finished stainless steel piano hinges, complete as per direction
of the Engineer-in-Charge
sqm 23.0 23.00 2230.30 51296.90
6.05 Providing and fixing ball bearing for rolling shutters including
cost and conveyance of all materials, labour, etc. as directed by
the Engineer-in-Charge at all levels. no - 0.00 531.78 0.00
0.00
6.06 Extra for providing grill rolling shutter manufactured out of 8 mm
dia M.S bars instead of laths as per the design approved by
the Engineer-in-Charge(area of grill to be measured)
sqm - 0.00 439.67 0.00
6.07 Providing and fixing 1mm thick M.S sheet door with frame of
40x40x6 mm MS angles,40x40x6 mm MS angles for diagonal
braces and 3mm M.S gusset plates at the junctions and
corners ,all necessary fittings complete including two coats of
approved make and colour synthetic enamel paint over two
coats of approved make anticorrossive yellow zinc chromate
primer, conveyance of all materials, labour, etc. as directed by
Engineer in Charge at all levels.
sqm 0.00 4376.67 0.00
0.00
6.08 Providing and fixing S.S fan clamp of 16mm dia in RCC slabs,
beams including cost and conveyance of all materials,labour
charges etc complete as directed by the Engineer-in-Charge at
all levels. no 5 48.0 53.00 124.72 6609.99
6.09 Providing and fixing M.S round holding down bolts with nuts
and washer plate including two coats of approved make and
colour synthetic enamel paint over two coats of approved
make yellow zinc chromate primer,including cost and
conveyance of all materials, labour charges,lead,lift etc
complete as directed by Engineer-in-Charge kg 0.00 95.34 0.00
0.00
6.10 Providing and fixing CI manhole cover with frame 560 mm
diameter C.I. cover (heavy duty) the weight of the cover to be
not less than 108 kg in concrete slab over
manholes/Inspection Chambers/Drains, including cost and
conveyance of all materials, all labour charges, all taxes,lead,
lift, sundries, etc., complete. as directed by the Engineer- in-
Charge no - 5.0 4 9.00 8259.46 74335.14
6.11 Providing and fixing stainless steel ( Grade 304) railing made of
Hollow tubes, channels, plates etc., including welding, grinding,
buffing, polishing and making curvature (wherever required)
and fitting the same with necessary stainless steel nuts and
bolts complete, i/c fixing the railing with necessary accessories
& stainless steel dash fasteners , stainless steel bolts etc., of
required size, on the top of the floor or the side of waist slab
with suitable arrangement as per approval of Engineer-in-
charge, (for payment purpose only weight of stainless steel
members shall be considered excluding fixing accessories such
as nuts, bolts, fasteners etc.).
kg - 0.00 662.30 0.00
7.04 Providing and fixing 1st quality ceramic glazed wall tiles
conforming to IS : 15622(thickness to be specified by the
manufacture of approved make in all colours , shades except
burgundy, bottle green, black of any size as approved by
Engineer-in- charge in skirting, risers of steps and dados over
12mm thick bed of cement Mortar 1:3 (1 cement: 3 coarse
sand) and jointing with grey cement slurry@ 3.3kg per sqm
including pointing in white cement mixed with pigment of
matching shade complete. sqm 35 131.0 230.0 396.00 1044.21 413507.16
7.10 Kota stone slab flooring over 20 mm (average) thick base laid
over and jointed with grey cement slurry mixed with pigment to
match the shade of the slab, including rubbing and polishing
complete with base of cement mortar 1 : 4 (1 cement : 4 coarse
sand) :
7.10.01 25 mm thick sqm 247 329.0 86.0 662.00 1623.66 1074862.92
7.13 Providing and fixing PVC tile edging to match the wall tiles and
finishing as directed by the Engineer-in-Charge at all levels.
m 9 53.0 62.00 46.62 2890.44
8.06 Finishing walls with Premium Acrylic Smooth exterior paint with
Silicone additives of required shade for new work (Two or more
coats applied @ 1.43 ltr/ 10 sqm over and including priming
coat of exterior primer applied @ 2.20 kg/ 10 sqm). including
cost and conveyance of all materials, labour charges,
scaffoldings etc complete as directed by the Engineer-in-
Charge at all levels. sqm 266 951.0 579.0 - 1796.00 135.71 243735.16
8.10
Painting with synthetic enamel paint of approved brand and
manufacture of required colour to give an even shade two or
more coats on new work over an under coat of suitable shade
with ordinary paint of approved brand and manufacture
including cost and conveyance of all materials, labour charges,
scaffolding, sundries etc complete as directed by the Engineer
in charge at all levels. sqm 83.00 264.0 18.0 365.00 157.44 57465.60
9.01 Providing and fixing white vitreous china pedestal type water
closet (European type) with seat and lid, 10 litre low level white
vitreous china flushing cistern & C.P. flush bend with fittings &
C.I. brackets, 40 mm flush bend, overflow arrangement with
specials of standard make and mosquito proof coupling of
approved municipal design complete, including painting of
fittings and brackets, cutting and making good the walls and
floors wherever required :W.C. pan with ISI marked white solid
plastic seat and lid. no - 7.0 7.00 6440.44 45083.08
9.02 Providing and fixing water closet squatting pan (Indian type
W.C. pan ) with 100 mm sand cast Iron P or S trap, 10 litre low
level white P.V.C. flushing cistern, including flush pipe, with
manually controlled device (handle lever) conforming to IS :
7231, with all fittings and fixtures complete, including cutting
and making good the walls and floors wherever required: White
Vitreous china Orissa pattern W.C. pan of size 580x440 mm
with integral type foot rests no - 1.0 15.0 16.00 4898.87 78381.92
9.03 Providing and fixing wash basin with C.I. brackets, 15 mm C.P.
brass pillar taps, 32 mm C.P. brass waste of standard pattern,
including painting of fittings and brackets, cutting and making
good the walls wherever require:White Vitreous China Wash
basin size 630x450 mm with a pair of 15 mm C.P.brass pillar
taps no 8.0 8.00 3222.57 25780.56
9.05 Providing and fixing white vitreous china flat back half stall
urinal of size 580x380x350 mm with white PVC automatic
flushing cistern, with fittings, standard size C.P. brass flush
pipe, spreaders with unions and clamps (all in C.P. brass) with
waste fitting as per IS : 2556, C.I. trap with outlet grating and
other couplings in C.P. brass, including painting of fittings and
cutting and making good the walls and floors wherever required
: Single half stall urinal with 5 litre P.V.C. automatic flushing
cistern no - 17.0 18.0 35.00 8674.73 303615.55
0.00
9.06 Supplying and fixing approved quality white vitreous china
urinal division plate 700 x 340 including cost and conveyance of
all material, labour charge, lead, lift, all taxes etc. complete as
directed by the Engineer-in-Charge.
no - 17.0 18.0 35.00 1448.45 50695.75
0.00
9.07 Providing and fixing frameless mirror, with all four edges
machine polished and back side protected with safety film and
4 mm thick Plywood backing and fixed on walls with mirror
screws. The rate includes lifting, cutting etc. as per design and
drawing. sqm 4.0 5.0 11.0 20.00 3889.300 77786.00
9.08 Providing and fixing CP brass long body bib cock of approved
quality conforming to IS standards and weighing not less than
690 gms including cost and conveyance of all materials, labour
charges, sundries etc complete as directed by the Engineer-in-
Charge at all levels
15 mm nominal bore no - 7.0 15.0 22.00 690.56 15192.32
9.10 Providing and fixing C.P. brass stop cock concealed with
adjustable wall flange of standard design and of approved
make conforming to IS: 8931 including cost and conveyance of
all materials, labour charges, sundries etc complete as directed
by the Engineer-in-Charge at all levels
0.00
15 mm nominal bore no 2.0 2.0 4.0 8.00 765.42 6123.36
0.00
9.11 Supplying and fixing CP Towel rod 60cm or nearest available
length including cost of materials and labour charges etc
complete as per the direction of site Engineer-in-charge.
no 0.00 127.59 0.00
0.00
9.12 Providing and fixing CP Toilet paper holder with flap of
approved make as directed by Engineer-in-Charge no 0.00 540.26 0.00
0.00
9.09 Providing and fixing CP brass health faucets with 8mm dia 1
meter long flexible tube and wall hook with all fittings and
fixtures including angle valve etc complete inlcuding cutting and
making good the walls and floors wherever required including
cost and conveyance of all materials, labour charges, sundries
etc complete as directed by the Engineer-in-Charge at all
levels. no - 7.0 15.0 22.00 1280.47 28170.34
9.11 Providing and fixing PVC pipes, fittings including fixing the pipe
with clamps at 1.00 m spacing. This includes jointing of pipes &
fittings with one step PVC solvent cement and testing of joints
complete as per direction of Engineer-in-Charge. Concealed
work, including cutting chases and making good the wall etc.
9.11.03 50mm OD(6 kg/cm2) m 24.0 72.0 96.0 192.00 265.67 51008.64
9.12 Providing and fixing PVC pipes includings jointing of pipes with
one step pvc solvent cement, trenching , refilling & testing of
joints complete as per direction of Engineer in Charge - external
works
9.12.01 150mm OD(6 kg/cm2) m - 78.0 228.0 8.0 314.00 817.53 256704.42
9.12.02 110mm OD(6 kg/cm2) m 45.0 30.0 48.0 265 388.00 440.68 170983.84
9.12.03 75mm OD(6 kg/cm2) m 12.0 12.0 24.0 48.00 256.10 12292.80
9.13 Providing and fixing PVC vent cowl to pipe already fixed as
directed by Engineer-in-Charge at all levels.
9.14 Providing and fixing Cleanout with Spigot, with SS 304 Square
Frame & Round Frame with Flat Round Cover with Rubber
Seal & SS Screw including cost and conveyance of all
materials, labour charges, sundries etc complete as directed by
the Engineer in charge at all levels
10.01.01 Pipes, cables etc. not exceeding 80mm dia m 20.0 20.0 20.0 60.00 193.55 11613.00
10.01.02 In all kinds of soil for pipes, cables etc exceeding 80mm dia but
notexceeding 300mm dia. m 20.0 100.0 100.0 220.00 316.08 69537.60
10.01.03 Pipes, cables etc. exceeding 300mm dia but not exceeding
600mm m 20.0 20.0 20.0 60.00 493.50 29610.00
10.02.02 50 mm nominal outer dia Pipes m - 18.0 24.0 42.00 769.07 32300.94
10.02.03 40 mm nominal outer dia Pipes m - 12.0 24.0 36.00 540.47 19456.92
10.02.04 32 mm nominal outer dia Pipes m 6.0 6.0 12.0 24.00 405.25 9726.00
10.02.05 25 mm nominal outer dia Pipes m 6.0 6.0 12.0 24.00 303.11 7274.64
10.03 Providing and fixing gun metal gate valve with C.I. Wheel of
approved quality (screwed end) including cost and conveyance
of all materials, labour charges, sundries etc complete as
directed by the Engineer- in-Charge at all levels
10.03.01 65 mm dia nominal bore no 2.0 2.0 4.0 2 10.00 1804.10 18041.00
10.03.02 50 mm dia nominal bore no 2.0 2.0 4.0 2 10.00 1051.36 10513.60
10.03.03 40 mm dia nominal bore no 2.0 2.0 4.0 4 12.00 819.75 9837.00
10.03.04 32 mm dia nominal bore no 2.0 2.0 4.0 4 12.00 702.06 8424.72
10.03.05 25 mm dia nominal bore no 3.0 2.0 4.0 9.00 600.34 5403.06
10.05.01 62.50 mm nominal inner dia pipes m 6.0 42.0 24.0 24 96.00 1516.61 145594.56
10.05.02 50 mm nominal outer dia pipes m 6.0 42.0 186.0 114 348.00 678.92 236264.16
10.05.03 40 mm nominal outer dia pipes m 6.0 12.0 42.0 34 94.00 450.25 42323.50
10.06 Supplying approved make PVC gully trap of size 160 x 110mm
and CI grating 150mmx150mm size and light duty C.I cover
with frames 300mmx300mm size(inside) the weight of cover to
be not less than4.5kg and frame to be not less than2.7kg (CI
MH cover and frame as per IS:1726) single sealed of size
conveying to size the above mentioned items and constructing
30cmx30cm internal size gully trap chamber and depth upto
60cm,115 thk brick wall in CM 1:6 on a foundation of PCC
1:4:8.100mm thick plastering inside with CM 1:3,12mm thk with
a neat cement flushing coat and conveying to site,cleaning
,installing and testing approved make PVC gully trap with
160mm outlet(Fabricated),surrounding with CC 1:1.5:3,
150x150mmm,top with CI grating above the PVC gulley trap
and light duty CI cover and frame over the chamber including
cost of all materials, etc complete as per approved drawing and
as directed by Engineer-in- Charge.
no 2.0 2.0 2.0 6.00 2846.87 17081.22
10.08.01 Inside size 90x80 cm and 45 cm deep including C.I. cover with
frame (light duty) 455x610 mm internal dimensions total weight
of cover and frame to be not less than 38 kg (weight of cover
23 kg and weight of frame 15 kg) :
0.00
With bricks.Class designation 75 no - - 8.0 8.00 12105.01 96840.08
10.09.01 Size 90 x 80 cm. With bricks.Class designation 75 m 3.0 3.0 6.00 8017.48 48104.88
10.10 Supplying and fixing of CI double flanged wall casting pipe with
puddle, 0.6m length including cost and conveyance of all
materials,labour charges,making good the walls etc complete
as directed by the Engineer-in-Charge.
10.11 Supplying and fixing of CI single flanged wall casting pipe with
puddle, 0.6m length including cost and conveyance of all
materials,labour charges,making good the walls etc complete
as directed by the Engineer-in-Charge.
10.13 Supplying and fixing gun metal Non return valve with all
accessories including cost and conveyance of all
materials,labour charges etc complete as directed by the
Engineer- in-Charge at all levels
10.15 Providing and fixing enclosed type water meter (bulk type)
50mm dia conforming to IS : 2373 and tested by Municipal
Board complete with bolts, nuts, rubber insertions etc. (The tail
pieces if required will be paid separately) including cost and
conveyance of all materials, labour etc. complete and as
directed by Engineer-in-Charge no - 1.0 1.0 2.00 8288.48 16576.96
10.17 Providing and constructing soak pit 1.5 m x 1.5 m x 1.5 m size
with honey comb brick work on the sides upto a height of 0.9m
and brick masonry in CM 1:6 for the balance height,providing
and filling brick bats graded, upto a height of 1.2 m,providing
and laying precast slab over the pit supporting on the brick
work, including cost and conveyance of all materials,labour
charges, lead, lift, etc. complete as directed by the Engineer-in-
no - 1.0 1.0 2.00 24669.36 49338.72
charge.
TOTAL OF SUB HEAD-10.0 1476365.69
11.04 Providing and laying non-pressure NP2 class (light duty) RCC
pipes with collars jointed with stiff mixture of cement mortar in
the proportion of 1:2 (1 cement : 2 fine sand) including testing
of joints etc. complete.
11.06 Providing and laying at or near ground level factory made kerb
stone of M-25 grade cement concrete in position to the required
line, level and curvature, jointed with cement mortar 1:3 (1
cement: 3 coarse sand), including making joints with or without
grooves (thickness of joints except at sharp curve shall not to
more than 5mm), including making drainage opening wherever
required complete etc. as per direction of Engineer-in-charge
(length of finished kerb edging shall be measured for payment).
(Precast C.C. kerb stone shall be approved by Engineer-in-
charge). cum 16.0 16.00 7027.74 112443.84
11.07 Providing and fixing stainless steel coat & hat hook of approved
make and pattern on door including cost and conveyance of all
materials, labour charges,fixing charges,etc complete as
directed by the Engineer-in-Charge.
no 16.0 16.00 65.80 1052.78
0.00
11.08 Providing and fixing to the inlet mouth of rain water pipe cast
iron grating 15cm diameter and weighing not less than 440
grams. no 10.0 10.00 57.34 573.40
Sl.No Description of Items Unit No Length Breadth Height Quantity Rate(Rs) Amount(Rs)
(SH : 1.0 EARTHWORK)
3.02 Providing and laying in position machine batched and machine mixed design
mix M-30 grade cement concrete for reinforced cement concrete work, using
cement content as per approved design mix, including pumping of concrete
to site of laying but excluding the cost of centering, shuttering, finishing and
reinforcement, including admixtures in recommended proportions as per IS:
9103 to accelerate, retard setting of concrete, improve workability without
impairing strength and durability as per direction of Engineer-in-
charge.“(Note :- Cement content considered in this item is @ 340
kg/cum.“Excess/ less cement used as per design mix is payable/recoverable
separately).
All work upto plinth level. cum
Sump base slab 1.00 6.35 6.35 0.30 12.10
wall 2.00 5.75 0.28 2.40 7.59
5.00 5.15 0.28 2.40 17.00
1.00 2.00 0.20 2.40 0.96
sump cover slab 1.00 5.75 5.75 0.15 4.96
42.60
say 45.00 9135.36 411091.20
3.06 Centering and shuttering including strutting, propping etc. and removal of
form for :
3.06.01 Foundations, footings, bases of columns etc. for mass concrete. sqm
PCC
Sump 1.00 26.20 0.10 2.62
RCC
Sump base slab 1.00 25.40 0.30 7.62
10.24
say 11.00 271.92 2991.12
3.06.02 Suspended floors, roofs, landings, balconies and access platform. sqm
sump cover slab 1.00 5.75 5.75 33.06
33.06
say 35.00 592.06 20722.10
6.10 Providing and fixing CI manhole cover with frame 560 mm diameter C.I.
cover (heavy duty) the weight of the cover to be not less than 108 kg in
concrete slab over manholes/Inspection Chambers/Drains, including cost no 4.00 8259.46 33037.84
and conveyance of all materials, all labour charges, all taxes,lead, lift,
sundries, etc., complete. as directed by the Engineer- in-Charge
8.04 15mm cement plaster of mix, 1:3 (1 cement : 3 fine sand) finished with a
floating coat of neat cement 2 kg/sqm including mixing water proofing
material in separately).proportion recommended by manufacturer over roof
at all heights including cost and conveyance of all materials, labour charges, sqm
scaffolding, sundries etc complete as directed by the Engineer-in-Charge at
all levels. (water proofing liquid will be paid separately)
9.12 Providing and fixing PVC pipes includings jointing of pipes with one step
pvc solvent cement, trenching , refilling & testing of joints complete as per
direction of Engineer in Charge - external works
10.03 Providing and fixing gun metal gate valve with C.I. Wheel of approved
quality (screwed end) including cost and conveyance of all materials, labour
charges, sundries etc complete as directed by the Engineer- in-Charge at all
levels
10.05 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having
thermal stability for hot & cold water supply including all CPVC plain & brass
threaded fittings This includes jointing of pipes & fittings with one step CPVC
solvent cement, trenching, refilling & testing of joints complete as per
direction of Engineer in Charge.
10.10 Supplying and fixing of CI double flanged wall casting pipe with puddle,
0.6m length including cost and conveyance of all materials,labour
charges,making good the walls etc complete as directed by the Engineer-in-
Charge.
10.11 Supplying and fixing of CI single flanged wall casting pipe with puddle, 0.6m
length including cost and conveyance of all materials,labour charges,making
good the walls etc complete as directed by the Engineer-in-Charge.
10.12 Supplying and fixing CI foot valve with all accessories including cost and
conveyance of all materials,labour charges etc complete as directed by the
Engineer -in - charge at all levels.
11.03 Providing and placing in position suitable PVC water stops conforming to IS
:12200 for construction / expansion joints between two RCC members and
fixed to the reinforcement with binding wire before pouring concrete etc.,
complete including all cost and conveyance of all materials, labour charges m
etc. complete as directed by Engineer - in - Charge at all levels : Serrated
with central bulb(225mm wide, 8-11 mm thick).
Sl No.
9.02
9.03
9.05
9.06
9.07
9.08
9.09
9.10
9.09
9.10
9.10.01
9.10.02
9.11
9.11.01
9.11.02
9.11.03
9.12
9.12.01
9.12.02
9.12.03
9.13
9.13.01
9.13.02
9.14
9.14.1
9.14.2
10.01
10.01.01
10.01.02
10.01.03
10.02
10.02.01
10.02.02
10.02.03
10.02.04
10.02.05
10.03
10.03.01
10.03.02
10.03.03
10.03.04
10.03.05
10.04
10.04.01
10.04.02
10.04.03
10.04.04
10.05
10.05.01
10.05.02
10.05.03
10.06
10.07
10.08
10.08.01
10.12
10.13
10.13.02
10.13.03
10.15
10.17
KITCO LTD
DEPARTMENT OF EDUCATION GOVT. OF KERALA
GOVT HIGH SCHOOL PANDIKKAD
DETAILED ESTIMATE - SANITARY AND WATER SUPPLY- SCHOOL BUILDING 1
Providing and fixing water closet squatting pan (Indian type W.C. pan ) with 100 mm
sand cast Iron P or S trap, 10 litre low level white P.V.C. flushing cistern, including flush
pipe, with manually controlled device (handle lever) conforming to IS : 7231, with all
no 15.00 15.00 4898.87 73483.05
fittings and fixtures complete, including cutting and making good the walls and floors
wherever required: White Vitreous china Orissa pattern W.C. pan of size 580x440 mm
with integral type foot rests
Providing and fixing coloured vitreous china under counter round wash basin 440 mm
dia or nearest size of approved make including one CP brass pillar cock 15 mm NB
including connecting pipes with all fittings 32 mm dia rubber plugs 32 mm dia CP brass no 20 20.00 5867.05 117341.00
waste coupling, 32 mm dia CP brass bottle trap, 15mm angle valve, etc. complete as
directed by the Engineer-in-charge.
Providing and fixing white vitreous china flat back half stall urinal of size 580x380x350
mm with white PVC automatic flushing cistern, with fittings, standard size C.P. brass
flush pipe, spreaders with unions and clamps (all in C.P. brass) with waste fitting as per
IS : 2556, C.I. trap with outlet grating and other couplings in C.P. brass, including no 18.00 18.00 8674.73 156145.14
painting of fittings and cutting and making good the walls and floors wherever required
: Single half stall urinal with 5 litre P.V.C. automatic flushing cistern
Supplying and fixing approved quality white vitreous china urinal division plate 700 x
340 including cost and conveyance of all material, labour charge, lead, lift, all taxes etc. no 18.00 18.00 1448.45 26072.10
complete as directed by the Engineer-in-Charge.
Providing and fixing frameless mirror, with all four edges machine polished and back
side protected with safety film and 4 mm thick Plywood backing and fixed on walls with
sqm 11 11.00 3889.300 42782.30
mirror screws. The rate includes lifting, cutting etc. as per design and drawing.
Providing and fixing CP brass long body bib cock of approved quality conforming to IS
standards and weighing not less than 690 gms including cost and conveyance of all
materials, labour charges, sundries etc complete as directed by the Engineer-in-
Charge at all levels
15 mm nominal bore no 15.00 15.00 690.56 10358.40
Providing and fixing floor trap of PVC,110 mm outer dia(multi trap) including CP
cockroach free floor grating with cup etc including cost and conveyance of all
no 23.00 23.00 367.90 8461.70
materials, labour charges, sundries etc complete as directed by the Engineer-in-
Charge at all levels
Providing and fixing C.P. brass stop cock concealed with adjustable wall flange of
standard design and of approved make conforming to IS: 8931 including cost and
conveyance of all materials, labour charges, sundries etc complete as directed by the
Engineer-in-Charge at all levels
15 mm nominal bore no 4.00 4.00 765.42 3061.68
Providing and fixing CP brass health faucets with 8mm dia 1 meter long flexible tube
and wall hook with all fittings and fixtures including angle valve etc complete inlcuding
cutting and making good the walls and floors wherever required including cost and no 15.00 15.00 1280.47 19207.05
conveyance of all materials, labour charges, sundries etc complete as directed by the
Engineer-in-Charge at all levels.
Providing and fixing PVC pipes, fittings including fixing the pipe with clamps at 1.00 m
spacing . This includes jointing of pipes & fittings with one step PVC solvent cement
and testing of joints complete as per direction of Engineer-in-Charge - Internal work-
Exposed on wall
Providing and fixing PVC pipes, fittings including fixing the pipe with clamps at 1.00 m
spacing. This includes jointing of pipes & fittings with one step PVC solvent cement and
testing of joints complete as per direction of Engineer-in-Charge. Concealed work,
including cutting chases and making good the wall etc.
Providing and fixing PVC pipes includings jointing of pipes with one step pvc solvent
cement, trenching , refilling & testing of joints complete as per direction of Engineer in
Charge - external works
Providing and fixing PVC vent cowl to pipe already fixed as directed by Engineer-in-
Charge at all levels.
Providing and fixing Cleanout with Spigot, with SS 304 Square Frame & Round Frame
with Flat Round Cover with Rubber Seal & SS Screw including cost and conveyance of
all materials, labour charges, sundries etc complete as directed by the Engineer in
charge at all levels
Excavating trenches of required width for pipes, cables, etc. including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m including
getting out the excavated soil, and then returning the soil as required, in layers not
exceeding 20 cm in depth including consolidating each deposited layer by ramming,
watering, etc. and disposing of surplus excavated soil and unserviceable material as
directed, within a lead of 50 m
All kinds of soil
Pipes, cables etc. not exceeding 80mm dia m 20.00 193.55 3871.00
In all kinds of soil for pipes, cables etc exceeding 80mm dia but notexceeding 300mm dia. m 100.00 316.08 31608.00
Pipes, cables etc. exceeding 300mm dia but not exceeding 600mm m 20.00 493.50 9870.00
Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal
stability for hot & cold water supply, including all CPVC plain & brass threaded fittings,
including fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes &
fittings with one step CPVC solvent cement and testing of joints complete as per
direction of Engineer-in-Charge. Internal work - Exposed on wall
Providing and fixing gun metal gate valve with C.I. Wheel of approved quality (screwed
end) including cost and conveyance of all materials, labour charges, sundries etc
complete as directed by the Engineer- in-Charge at all levels
Supplying approved make PVC gully trap of size 160 x 110mm and CI grating
150mmx150mm size and light duty C.I cover with frames 300mmx300mm size(inside)
the weight of cover to be not less than4.5kg and frame to be not less than2.7kg (CI MH
cover and frame as per IS:1726) single sealed of size conveying to size the above
mentioned items and constructing 30cmx30cm internal size gully trap chamber and
depth upto 60cm,115 thk brick wall in CM 1:6 on a foundation of PCC 1:4:8.100mm
thick plastering inside with CM 1:3,12mm thk with a neat cement flushing coat and no 2.00 2.00 2846.87 5693.74
conveying to site,cleaning ,installing and testing approved make PVC gully trap with
160mm outlet(Fabricated),surrounding with CC 1:1.5:3, 150x150mmm,top with CI
grating above the PVC gulley trap and light duty CI cover and frame over the chamber
including cost of all materials, etc complete as per approved drawing and as directed
by Engineer-in- Charge.
Providing and placing on terrace (at all floor levels) polyethylene water storage tank, IS
: 12701 marked, with cover and suitable locking arrangement and making necessary
ltr 5000.00 5000.00 10.17 50850.00
holes for inlet, outlet and overflow pipes but without fittings and the base support for
tank.
Constructing brick masonry manhole with 75 class designation bricks in cement mortar
1:4 (1 Cement : 4 coarse sand) R.C.C. top slab with 1:2:4 (1 Cement : 2 coarse sand :
4 graded stone aggregate 20 mm nominal size) foundation concrete with 1:4:8 mix (1
Cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size) inside
plastering 12 mm thick with cement mortar 1:3 (1 Cement : 3 coarse sand) finished with
floating coat of neat cement and making channels in cement concrete 1:2:4 (1 Cement
: 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) finished with a
floating coat of neat cement complete as per standard design including cost and
conveyance of all materials, labour charges, sundries etc complete as directed by the
Engineer-in-Charge
Inside size 90x80 cm and 45 cm deep including C.I. cover with frame (light duty)
455x610 mm internal dimensions total weight of cover and frame to be not less than 38
kg (weight of cover 23 kg and weight of frame 15 kg) :
Supplying and fixing CI foot valve with all accessories including cost and conveyance
of all materials,labour charges etc complete as directed by the Engineer -in - charge at
all levels.
50mm no 4.00 4.00 3277.92 13111.69
Supplying and fixing gun metal Non return valve with all accessories including cost
and conveyance of all materials,labour charges etc complete as directed by the
Engineer- in-Charge at all levels
Providing and fixing enclosed type water meter (bulk type) 50mm dia conforming to IS
: 2373 and tested by Municipal Board complete with bolts, nuts, rubber insertions etc.
(The tail pieces if required will be paid separately) including cost and conveyance of all no 1.00 1.00 8288.48 8288.48
materials, labour etc. complete and as directed by Engineer-in-Charge
Providing and constructing soak pit 1.5 m x 1.5 m x 1.5 m size with honey comb brick
work on the sides upto a height of 0.9m and brick masonry in CM 1:6 for the balance
height,providing and filling brick bats graded, upto a height of 1.2 m,providing and
no 1.00 24669.36 24669.36
laying precast slab over the pit supporting on the brick work, including cost and
conveyance of all materials,labour charges, lead, lift, etc. complete as directed by the
Engineer-in-charge.
1.03.01 Beyond 30cm girth upto and including 60cm girth no 1.00 1.00 307.32 307.32
1.05 Filling with contractor's own earth ( excluding rock) in trenches, plinth, sides
of foundations etc. in layers not exceeding 20 cm in depth, consolidating
cum
each deposited layer by ramming and watering, lead up to 50 mm and lift up
to 1.5 m as per direction of site Engineer-in-charge
Plinth filling (area from Cadd) 1.00 646.22 0.60 387.732
0
387.732
-271.01
116.73
Say 123.00 436.40 53677.20
2.01 Providing and laying in position cement concrete of specified grade excluding
the cost of centering and shuttering - All work up to plinth level :
3.01 Providing and laying in position machine batched and machine mixed design
mix M-25 grade cement concrete for reinforced cement concrete work, using
cement content as per approved design mix, including pumping of concrete
to site of laying but excluding the cost of centering, shuttering, finishing and
reinforcement, including admixtures in recommended proportions as per IS:
9103 to accelerate, retard setting of concrete, improve workability without
impairing strength and durability as per direction of Engineer-in-charge.“(Note
:- Cement content considered in this item is @ 330 kg/cum.“Excess/ less
cement used as per design mix is payable/recoverable separately).
3.03 Providing and laying in position machine batched and machine mixed design
mix M-25 grade cement concrete for reinforced cement concrete work, using
cement content as per approved design mix, including pumping of concrete
to site of laying but excluding the cost of centering, shuttering, finishing and
reinforcement, including admixtures in recommended proportions as per IS:
9103 to accelerate, retard setting of concrete, improve workability without
impairing strength and durability as per direction of Engineer-in-charge.“(Note
:- Cement content considered in this item is @ 330 kg/cum.“Excess/ less
0.00 cement
All worksused as plinth
above per design
level mix
uptoisfloor
payable/recoverable
V level separately). cum
Columns
Ground floor
Column,C1 48.00 0.25 0.45 3.60 19.44
Column,C2 21.00 0.25 0.25 3.60 4.73
First floor 0.00
Column,C1 48 0.25 0.45 3.6 19.44
Column,C2 21.00 0.25 0.25 3.6 4.73
Head Room
Column,C1 8 0.25 0.45 3.6 3.24
51.57 columns
Beam
Ground floor
all arround bldg 1 168 0.25 0.325 13.65
on grid 2 to 18 15 8.4 0.25 0.325 10.24
on grid 17 1 23 0.25 0.325 1.87
on grid B 1 54 0.25 0.325 4.39
on grid D to J 6 8.4 0.25 0.325 4.10
First floor
all arround bldg 1 168 0.25 0.325 13.65
on grid 2 to 18 15 8.4 0.25 0.325 10.24
on grid 17 1 23 0.25 0.325 1.87
on grid B 1 54 0.25 0.325 4.39
on grid D to J 6 8.4 0.25 0.325 4.10
on grid 16 0 4.73 0.25 0.325 0.00
315.03
Say 331.00 10164.57 3364472.67
3.05 Steel reinforcement for R.C.C. work including straightening, cutting, bending,
placing in position and binding with 16 gauge GI binding wire etc complete
including cost, conveyance, lead, lift of all materials for all types of RCC
works as per drawing/specification and as directed by Engineer-in-Charge at
all levels.
Thermo-Mechanically Treated bars of grade Fe-500D or more. kg 498.96
Foundation @80kg/m3 1.00 141.12 80.00 11289.76
Plinth beam @ 180 kg/m3 1.00 32.06 180.00 5770.96
Lintels and sunshade @ 100 kg/m3 1.00 20.34 100.00 2034.09
columns @ 230 kg/m3 1.00 62.31 230.00 14331.30
Roof beam @ 170 kg/m3 1.00 71.75 170.00 12196.99
Slab and stair @ 120 kg/m3 1.00 171.38 120.00 20565.18
3.06 Centering and shuttering including strutting, propping etc. and removal of
form for :
3.06.03 Lintels, beams, plinth beams, girders, bressumers and cantilevers. sqm
Grade beam
all arround bldg 1 168 0.8 134.40
on grid 2 to 18 7 8.4 0.8 47.04
on grid 17 1 23 0.8 18.40
on grid B 1 54 0.8 43.20
on grid D to J 3 8.4 0.8 20.16
RCC Stair footing 1 3.83 0.7 2.68
RCC Stair footing 1 3.83 0.7 2.68
Beam
Ground floor
all arround bldg 1 168 0.9 151.20
on grid 2 to 18 15 8.4 0.9 113.40
on grid 17 1 23 0.9 20.70
on grid B 1 54 0.9 48.60
on grid D to J 6 8.4 0.9 45.36
First floor
all arround bldg 1 168 0.9 151.20
on grid 2 to 18 15 8.4 0.9 113.40
on grid 17 1 23 0.9 20.70
on grid B 1 54 0.9 48.60
on grid D to J 6 8.4 0.9 45.36
Head Room
Head Room top 2 20.12 0.9 36.22
Lintel
816.48
Say 858.00 655.93 562787.94
3.08 Add for using extra cement in the items of design mix over and above the
qtl
specified cement content there in.
Total RCC 498.96
additional 50 kg/m3 considered 24947.86
249.48
Say 262.00 943.20 247118.40
4.04 Solid block masonry using pre cast solid blocks ( Factory made) M-10
grade(mix 1:3:6) of size 30x20x20cm or nearest available size confirming to
IS 2185 Part I of 1979 for super structure up to floor two level thickness 20cm
and above in: CM 1:6 ( 1 cement : 6 coarse sand) etc complete including cum
scaffolding, raking out of joints,curing, cost and conveyance of all
materials,labour, lead, lift, etc. complete as directed by Engineer-in-Charge.
Ground floor
Along Grid A and B 2.00 51.17 0.20 3.15 64.47
Along Grid 19 1.00 30.00 0.20 3.15 18.90
Along grid 17 1.00 19.17 0.20 3.15 12.08
on grid 2 to 18 7.00 6.20 0.20 3.15 27.34
on grid D to J 3.00 6.20 0.20 3.15 11.72
Deduction
D -11.00 1.00 0.20 2.10 -4.62
D1 -5.00 0.90 0.20 2.10 -1.89
W -32.00 1.20 0.20 1.50 -11.52
Ventilator -6.00 0.90 0.20 0.60 -0.65
First floor
4.05 Solid block masonry using pre cast solid blocks (Factory made) M-10
grade(mix 1:3:6) of size 30x20x20cm or nearest available size confirming to
IS 2185 part I of 1979 for super structure above floor two level upto floor five
level thickness 20cm and above in : CM 1:6 ( 1 cement : 6 coarse sand sand) cum
etc complete including scaffolding, raking out of joints,curing, cost and
conveyance of all materials,labour, lead, lift, etc. complete as directed by
Engineer-in-Charge.
Head Room
stair room 1.00 20.12 0.20 3.00 12.07
stair room 1.00 20.12 0.20 3.00 12.07
D -1.00 1.00 0.20 2.10 -0.42
23.72
Say 25.00 5375.40 134385.00
4.08 Providing and constructing 115mm thick brick masonry in CM 1:4 (1 cement,
4 coarse sand) in partition walls, parapets, etc. with bricks of standard sizes
and of approved quality (average compressive strength not less than 50
Kg/cm2) including scaffolding, raking out of joints, curing, cost and
sqm
conveyance of all materials, lead,lift, etc.complete including providing 2 Nos.
of 6mm dia bars as reinforcement at every third layer wherever specified
(Reinforcement shall be measured and paid for under relevent item ) and as
directed by Engineer-in-Charge
Half brick & duct
1/2 brick wall
toilets 1.00 15.03 3.60 54.11
189.94
Say 200.00 959.25 191850.00
4.09 Extra for providing and placing in position 2 Nos 6mm dia. M.S. bars at every
third course of half brick masonry including cost and conveyance of MS bars sqm
etc complete as directed by Engineer-in-Charge
Quantity same as half brick wall 189.94
Say 200.00 79.70 15940.00
5.01 Providing and fixing powder coated aluminium work for doors ,windows&
partitions with extruded built up standard tubular sections/appropriate Z
sections & other sections of approved make confirming to IS:733 & IS:1285
fixed with rawl plugs & screws or with fixing clips including necessary filling
up of gaps at junctions,at top,bottom & sides with required PVC/neoprene felt
etc.Aluminium sections shall be smooth,rust free,straight,mitred & jointed
mechanically where ever required including cleat angle,aluminium snap
beading for glazing/panelling,cp brass/stainless steel screws,removing the
stickers clearly all complete as per architectutral drawings & directions of
Engineer-in-Charge at all levels.(glazing & panelling to be paid
seperately).Minimum thickness of powder coating for powder coated
Aluminium shall be 50 micron.
5.01.01 For fixed portion kg kg/m2
Ground floor
W 32.00 1.20 4.50 1.50 259.20
First floor
W 32.00 1.20 1.50 57.60
115.20
Say 121.00 1039.58 125789.54
6.48
Say 7.00 984.48 6891.39
5.06 Providing and fixing aluminium extruded section body tubular type universal
hydraulic door closer of approved make (having brand logo with ISI, IS :
3564, embossed on the body, door weight upto 36 kg to 80 kg and door width
no
from 701 mm to 1000 mm), with double speed adjustment with necessary
accessories and screws etc. complete as directed by the Engineer-in-
Charge at all levels.
Ground floor
D 11.00 1.00 11.00
First floor
D 11.00 1.00 11.00
Head Room
D 1.00 1.00 1.00
23.00
Say 24.00 544.54 13068.88
5.07 Providing and fixing 125 mm aluminium handles ISI marked anodised (anodic
coating not less than grade AC 10 as per IS : 1868) transparent or dyed to
no
required colour or shade with necessary screws etc. complete as directed by
Engineer -in-Charge at all levels.
GF
D1 6.00 1.00 6.00
FF
D1 6.00 1.00 6.00
12.00
Say 13.00 71.64 931.35
5.08 Providing and fixing Aluminium tower bolts ISI marked anodised (anodic
coating not less than grade AC 10 as per IS : 1868) transparent or dyed to
no
required colour or shade with nuts and screws etc. complete as directed by
the Engineer-in-Charge at all levels.
6.07.03 200mm x 10 mm
26.00 26.00
26.00
Say 28.00 106.76 2989.28
5.10 Providing and fixing aluminium hanging floor door stopper ISI marked
anodised (anodic coating not less than grade AC 10 as per
IS:1868)transparent or dyed to required colour and shade with necessary
screws etc complete as directed by the Engineer-in -Charge at all levels.
5.11 Providing and fixing bright finished brass handles with screws etc.complete:
no
125mm
Nominal quantity 10.00
10.00
Say 11.00 240.02 2640.22
5.12 Supplying and fixing 200 mm Aluminium aldrop including cost and
conveyance of all materials,labour charges ,lead,lift etc. complete as
directed by the Engineer-in-Charge at all levels.
Toilet door 12.00 12.00
Say 12.00 170.43 2045.16
5.13 Providing and fixing aluminium casement stays, ISI marked, anodised
(anodiccoating not less than grade AC 10 as per IS : 1868) transparent or
dyed to required colour and shade, with necessary screws etc. complete. as no
directed by Engineer -in-Charge at all levels.
Ground floor
W 32.00 3.00 96.00
First floor
W 32.00 3.00 96.00
192.00
Say 202.00 69.40 14018.80
5.14 Providing wood work in frames of doors, windows , clerestory windows and
other frames, wrought frames and fixed in position with hold fast lugs or with
dash fastners of required dia & length(hold fast lugs or dash fastener shall be
paid separately).
Second class teak wood cum
Ground floor
D 11.00 8.20 0.10 0.07 0.63
First floor
D 11.00 6.60 0.10 0.07 0.51
Head Room
D 1.00 6.60 0.10 0.07 0.05
1.19
Say 2.00 130025.76 260051.52
5.15 Providing and fixing panelled or panelled and glazed shutters for doors,
windows and clerestory windows including ISI marked stainless steel butt
hinges(100 x 60 x 6.5mm IS : 12817 marked ) with necessary screws
excludings panelling which be paid for separately.
Second class teak wood
35 mm thick shutters sqm
Ground floor
D 11.00 2.00 2.10 46.20
First floor
D 11.00 2.00 2.10 46.20
Head Room
D 1.00 2.00 2.10 4.20
100% considered 96.60
96.60
Say 102.00 3712.43 378667.86
5.16 Providing and fixing panelling or panelling and glazing in panelled or panelled
and glazed shutters for doors, windows and clerestory windows(area of
opening for panel inserts excluding portion inside grooves or rebates to be sqm
measured). Panelling for panelled or panelled and glazed shutters 25mm to
40mm thick:
50% considered 96.60
\\datalibrary1\2017-18 Open\School Reports- Modified\11. Pandikad\Pandikkad-GHS-11-8-2017\High School Block 20
Length Breadth Height
Sl.No Description Unit No Quantity Rate(Rs) Amount(Rs)
(mtr) (mtr) (mtr)
96.60
Say 102.00 2855.94 291305.88
5.18 Extra for providing heavy sheet float glass panes instead of ordinary float
glass in glazed doors, windows and clerestory window shutters. (Area of
opening for glass panes excluding portion inside rebate shall be measured) sqm
5.5 mm thick instead of 4 mm thick.
5.19 Providing 40x5 mm flat iron hold fast 40 cm long including fixing to frame with
10 mm diameter bolts, nuts and wooden plugs or approved dash fastners
and embeddings in cement concrete block 30x10x15 cm 1:3:6 mix (1 cement no
: 3 coarse sand : 6 graded stone aggregate 20 mm nominal size.
Ground floor
D 11.00 8.00 88.00
First floor
D 11.00 4.00 44.00
Head Room
D 1.00 4.00 4.00
136.00
Say 143.00 166.28 23778.04
5.20 Providing and fixing bright finished brass100mm mortice latch and lock ISI
marked with 6 levers and a pair of anodised(anodic coating not less than
no
grade AC 10 as per IS:1868)aluminium lever handles with necessary screws
etc. complete at all levels.(best make of approved quality).
Ground floor
D 11.00 1.00 11.00
First floor
D 11.00 1.00 11.00
Head Room
D 1.00 1.00 1.00
23.00
Say 25.00 872.25 21806.36
5.23 Providing and fixing Fiber Glass Reinforced plastic (FRP) Door Frames of
crosssection 90 mm x 45 mm having single rebate of 32 mm x 15 mm to
receive shutter of 30 mm thickness. The laminate shall be moulded with fire
resistant grade unsaturated polyester resin and chopped mat. Door frame
m
laminate shall be 2 mm thick and shall be filled with suitable wooden block in
all the three legs. The frame shall be covered with fiber glass from all sides.
M.S. stay shall be provided at the bottom to steady the frame.
GF
D1 6.00 5.00 30.00
FF
D1 6.00 5.00 30.00
60.00
Say 63.00 582.53 36699.39
21.60
Say 23.00 2230.30 51296.90
5.27 Providing and fixing special quality chromium plated brass cupboard locks of
75mm with six levers of approved quality including necessary screws etc. no
complete.as per direction of the Engineer-in-Charge
10.00
10.00
Say 10.00 332.34 3323.40
6.01 Structural steel work welded in built up sections,trussess and framed work
including cutting, hoisting, fixing in position and applying two coats of
Synthetic enamel paint over two coats of anticorrossive Yellow zinc chromate
kg kg/m
primer including cost and conveyance of all materials,labour charges
,lead,lift etc complete as directed by Engineer- in-Charge at all levels.
Nominal quantity
Sun Shade
GF
Purlin 1.0 1091.00 1091.00
Truss 1.0 3395.00 3395.00
FF
Purlin 1 1091 1091.00
Truss 1 3395 3395.00
8972.00
6.02 Steel work welded in built up sections/framed work including cutting hoisting,
fixing in position and applying two coats of approved make and colour
synthetic enamel paint over two coats of approved make anticorrossive
yellow zinc chromate primer, etc. including cost and conveyance of all
materials, labour, lead,lift etc. complete as directed by Engineer- in-Charge at
all levels.
6.02.02 In gratings, frames, guard bar, ladders, railings, brackets, gates & similar
kg
works.
kg/m2
Ground floor
W 32.00 1.20 15.00 1.50 864.00
Ventilator 6.00 0.90 15.00 0.60 48.60
First floor
W 32.00 1.20 15.00 1.50 864.00
Ventilator 6.00 0.90 15.00 0.60 48.60
1825.20
Say 1917.00 123.95 237612.15
6.08 Providing and fixing S.S fan clamp of 16mm dia in RCC slabs, beams
including cost and conveyance of all materials,labour charges etc complete no 8.00 Say 48.00 124.72 5986.41
as directed by the Engineer-in-Charge at all levels.
6.12 Providing and fixing in position collapsible steel shutters with vertical
channels 20x10x2mm and braced with flat iron diagonals 20x5mm size, with
top and bottom rail of T-iron 40x40x6mm, with 40mm dia steel pulleys,
complete with bolts, nuts, locking arrangement, stoppers, handles, including
painting with two coats of approved make and colour synthetic enamel paint sqm
over two coats of approved make anticorrossive yellow zinc chromate primer,
including cost and conveyance of all materials, labour charges,lead,lift etc
complete as directed by Engineer-in-Charge
7.03 Providing and laying Antiskid Ceramic floor tiles 300x300x7 mm of Ist
quality conforming to IS : 15622 of approved make,shade,and pattern laid on
20mm thick cement mortar 1:4 (1 cement : 4 coarse sand) and jointed with
grey cement slurry @ 3.3 kg/sqm including pointing the joints with white sqm
cement and matching pigment etc.including cost and conveyance of all
materials,labour charges,lead,lift etc, complete as directed by the Engineer-in-
Charge at all levels.
Toilet- GF 1.00 11.20 6.20 69.44
Toilet- FF 1.00 11.20 6.20 69.44
138.88
Say 146.00 965.07 140900.22
7.04 Providing and fixing 1st quality ceramic glazed wall tiles conforming to IS :
15622(thickness to be specified by the manufacture of approved make in all
colours , shades except burgundy, bottle green, black of any size as
approved by Engineer-in- charge in skirting, risers of steps and dados over
sqm
12mm thick bed of cement Mortar 1:3 (1 cement: 3 coarse sand) and jointing
with grey cement slurry@ 3.3kg per sqm including pointing in white cement
mixed with pigment of matching shade complete.
7.09 Extra for providing opening of required size & shape for wash basins/ kitchen
sink in kitchen platform, vanity counters and similar location in marble/granite
work including providing necessary holes for pillar taps etc. including rubbing no
and polishing of cut edges etc. complete as directed by the Engineer-in-
Charge at all levels.
For wash basin opening 24.00
24.00
Say 26.00 599.99 15599.74
7.10 Kota stone slab flooring over 20 mm (average) thick base laid over and
jointed with grey cement slurry mixed with pigment to match the shade of the
slab, including rubbing and polishing complete with base of cement mortar 1 :
4 (1 cement : 4 coarse sand) :
7.10.01 25 mm thick sqm
Ground Floor
Verandah 1.00 71.00 2.20 156.20
First floor
312.40
Say 329.00 1623.66 534184.14
7.11 Kota stone slabs 20 mm thick in risers of steps, skirting, dado and pillars laid
on 12 mm (average) thick cement mortar 1:3 (1 cement: 3 coarse sand) and
jointed with grey cement slurry mixed with pigment to match the shade of the sqm
slabs, including rubbing and polishing complete.
(A) Skirting
Ground Floor
Verandah 1.00 146.40 0.20 29.28
First floor
verandah 1.00 146.40 0.20 29.28
stair case
Ground floor
Staircase landing 1.00 3.80 2.10 7.98
steps 25.00 1.50 0.45 16.88
Staircase landing 1.00 3.80 2.10 7.98
steps 25.00 1.20 0.45 13.50
First floor
Staircase landing 1.00 3.80 2.10 7.98
steps 25.00 1.50 0.45 16.88
Staircase landing 1.00 3.80 2.10 7.98
steps 25.00 1.20 0.15 4.50
142.23
Say 150.00 1735.96 260394.00
7.13 Providing and fixing PVC tile edging to match the wall tiles and finishing as
m 24.00 2.10 50.40
directed by the Engineer-in-Charge at all levels.
50.40
8.01 6 mm cement plaster to ceiling of mix 1:3 (1 Cement : 3 fine sand) including
cost and conveyance of all materials, labour charges, scaffolding, sundries
etc complete as directed by the Engineer-in-Charge at all levels. sqm
Stair Landing
Ground floor
Staircase landing 1 3.8 2.1 7.98
Staircase landing 1 3.8 2.1 7.98
First floor
Staircase landing 1 3.8 2.1 7.98
Staircase landing 1 3.8 2.1 7.98
1282.10
8.02 12mm cement plaster of mix 1:4 (1 cement : 4 fine sand)including cost and
conveyance of all materials, labour charges, scaffolding, sundries etc
sqm
complete as directed by the Engineer-in-Charge at all levels.
Ground floor
Along Grid A and B 2.00 51.17 4.20 429.83
Along Grid 19 1.00 30.00 4.20 126.00
Along grid 17 1.00 19.17 4.20 80.51
on grid 2 to 18 7.00 6.20 4.20 182.28
on grid D to J 3.00 6.20 4.20 78.12
Deduction
D -5.50 1.00 2.10 -11.55
D1 -2.50 0.90 2.10 -4.73
D2 0.00 1.20 2.10 0.00
W -16.00 1.20 1.50 -28.80
Ventilator -3.00 0.90 0.60 -1.62
First floor
Along Grid A and B 2.00 51.17 3.60 368.42
Along Grid 19 1.00 30.00 3.60 108.00
Along grid 17 1.00 19.17 3.60 69.01
on grid 2 to 18 7.00 6.20 3.60 156.24
on grid D to J 3.00 6.20 3.60 66.96
parapet wall 1.00 67.00 1.20 80.40
Deduction
D -5.50 1.00 2.10 -11.55
D1 -2.50 0.90 2.10 -4.73
D2 0.00 1.20 2.10 0.00
W -16.00 1.20 1.50 -28.80
Head Room
stair room 1.00 20.12 3.00 60.36
stair room 1.00 20.12 3.00 60.36
D -1.00 1.00 2.10 -2.10
Half brick & duct
1/2 brick wall
toilets 1.00 15.03 3.60 54.11
1.00 14.50 3.60 52.20
1973.90
Say 2073.00 242.48 502661.04
8.03 15mm cement plaster of mix 1:4 (1 cement : 4 fine sand)including cost and
conveyance of all materials, labour charges, scaffolding, sundries etc
complete as directed by the Engineer-in-Charge at all levels.
1973.90
deduction for cladding -123.84
1850.06
Say 1943.00 280.75 545497.25
8.04 15mm cement plaster of mix, 1:3 (1 cement : 3 fine sand) finished with a
floating coat of neat cement 2 kg/sqm including mixing water proofing
material in separately).proportion recommended by manufacturer over roof
at all heights including cost and conveyance of all materials, labour charges, sqm
scaffolding, sundries etc complete as directed by the Engineer-in-Charge at
all levels. (water proofing liquid will be paid separately)
694.48
Say 730.00 372.86 272187.80
8.06 Finishing walls with Premium Acrylic Smooth exterior paint with Silicone
additives of required shade for new work (Two or more coats applied @ 1.43
ltr/ 10 sqm over and including priming coat of exterior primer applied @ 2.20
kg/ 10 sqm). including cost and conveyance of all materials, labour charges, sqm
scaffoldings etc complete as directed by the Engineer-in-Charge at all levels.
Ground floor
Along Grid A and B 2.00 51.17 4.20 429.83
Deduction
D -5.50 1.00 2.10 -11.55
D1 -2.50 0.90 2.10 -4.73
W -16.00 1.20 1.50 -28.80
Ventilator -3.00 0.90 0.60 -1.62
First floor
Along Grid A and B 2.00 51.17 3.60 368.42
D -5.50 1.00 2.10 -11.55
D1 -2.50 0.90 2.10 -4.73
W -16.00 1.20 1.50 -28.80
parapet wall 1.00 67.00 1.20 80.40
Head Room
stair room 1.00 20.12 3.00 60.36
stair room 1.00 20.12 3.00 60.36
Deduction
D -1.00 1.00 2.10 -2.10
905.50
Say 951.00 135.71 129060.21
8.07 Painting the inside walls with acrylic emulsion paint of approved brand and
manufacture to give an even shade two or more coats on new work to
smooth even finish on ceiling and walls including cost and conveyance of all sqm
materials to site, labour charges, hire charges for scaffolding, etc as directed
by Engineer-in-Charge
Total painting at all levels 5106.07
deduction for exterior painting -905.50
4200.57
Say 4411.00 118.40 522262.40
8.08 Providing and laying water proofing treatment on roofs of slabs by applying
cement slurry mixed with water proofing cement compound consisting of
applying:(a) after surface preparation, first layer of slurry of cement @ 0.488
kg/sqm mixed with water proofing cement compound @ 0.253 kg/sqm. (b)
laying second layer of Fibre glass cloth when the first layer is still
green.Overlaps of joints of fibre cloth should not be less than 10 cm. (c) third
layer of 1.5 mm thickness consisting of slurry of cement @ 1.289 kg/sqm
sqm
mixed with water proofing cement compound @ 0.670 kg/sqm and coarse
sand @ 1.289 kg/sqm. This will be allowed to air cure for 4 hours followed by
water curing for 48 hours. The entire treatment will be taken upto 30 cm on
parapet wall and tucked into groove in parapet all around.
(d) fourth and final layer of brick tiling with cement mortar (which will be paid
for separately. For the purpose of measurement the entire treated surface will
be measured."). including cost and conveyance of all materials,
694.48
Say 730.00 553.79 404266.70
8.10 Painting with synthetic enamel paint of approved brand and manufacture of
required colour to give an even shade two or more coats on new work over
an under coat of suitable shade with ordinary paint of approved brand and
sqm
manufacture including cost and conveyance of all materials, labour charges,
scaffolding, sundries etc complete as directed by the Engineer in charge at all
levels.
Ground floor coeffi
D 11.00 2.00 2.10 2.60 120.12
First floor
D 11.00 2.00 2.10 2.60 120.12
Head Room
D 1.00 2.00 2.10 2.60 10.92
251.16
Say 264.00 157.44 41564.16
11.02 Diluting and injecting chemical emulsion for POST- CONSTRUCTIONAL anti-
termite treatment (excluding the cost of chemical emulsion) :Treatment of soil
under existing floors using chemical emulsion @ one litre per hole, 300 mm
apart including drilling 12 mm diameter holes and plugging with cement sqm
mortar 1 :2 (1 cement : 2 Coarse sand) to match the existing floor: : With
Chlorpyriphos/Lindane E.C. 20% with 1% concentration
11.05 Supplying and fixing of following sizes of Medium duty PVC conduits
conforming to IS 9537/1983 Part III along with accessories in surface/ recess
including cutting the wall and making good the same in case of recessed
conduit as required.
11.06 Providing and laying at or near ground level factory made kerb stone of M-25
grade cement concrete in position to the required line, level and curvature,
jointed with cement mortar 1:3 (1 cement: 3 coarse sand), including making
joints with or without grooves (thickness of joints except at sharp curve shall
not to more than 5mm), including making drainage opening wherever cum 1.00 200.00 0.20 0.40 16.00
required complete etc. as per direction of Engineer-in-charge (length of
finished kerb edging shall be measured for payment). (Precast C.C. kerb
stone shall be approved by Engineer-in-charge).
16.00 7027.74 112443.84
11.08 Providing and fixing to the inlet mouth of rain water pipe cast iron grating
15cm diameter and weighing not less than 440 grams.
800.000
840.000 5.120 4300.800
608.760
100% may considered 608.760
Say 640.000 233.290 149305.600
1.08 Filling with contractor's own earth ( excluding rock) in trenches, plinth, sides
of foundations etc. in layers not exceeding 20 cm in depth, consolidating
cum
each deposited layer by ramming and watering, lead up to 50 mm and lift up
to 1.5 m as per direction of site Engineer-in-charge
Required for plinth filling
Plinth area from CAD 277.000 277.000
277.000
Say 291.000 436.400 126992.400
balance earth including ordinary rock and hard rock qnty considered 92.784
48.409
Say 51.000 6278.370 320196.870
2.02 Providing and laying cement concrete of specific grade properly mixed and
consolidated with hand rammers, including cost and conveyance of all
0.0
materials, labour, curing, lead lift , etc. complete as directed by Engineer-in-
Charge at all levels.
2.02.01 For screed concrete 1:2:4 (1 Cement : 2coarse sand : 4 graded stone
cum
aggregate 6mm nominal size)
roof slab 1.000 277.000 0.050 13.850
13.850
Say 15.000 7712.260 115683.900
2.04 Providing and laying damp-proof course 50mm thick with cement concrete
1:2:4 (1 cement : 2 coarse sand(zone-III) : 4 graded stone aggregate 20mm sqm
nominal size)
plastering item= 12.155
slab RCC= 45.705
DPC= 2.480
60.340
Say 64.000 67.230 4302.720
2.04 Providing and laying damp-proof course 50mm thick with cement
concrete1:2:4 (1 cement: 2coarse sand : 4 graded stone aggregate of 20mm
nominal size) including cost and conveyance of all materials,labour sqm
charges,lead,lift etc complete at all levels as directed by the Engineer- in-
Charge.
wall all round 1 82.000 0.250 20.500
long wall 1 32.000 0.250 8.000
Short walls 5 8.200 0.250 10.250
38.750
38.750
Say 41.000 448.990 18408.590
2.05 Providing & applying a coat of residual petroleum bitumen of grade of VG-10
of approved quality using 1.7kg per square metre on damp proof course after
sqm
cleaning the surface with brushes and finally with apiece of cloth lightly
soaked in kerosene oil
Nominal quantity 38.750
38.750
Say 41.000 128.840 5282.440
3.01 Providing and laying in position machine batched and machine mixed design
mix M-25 grade cement concrete for reinforced cement concrete work, using
cement content as per approved design mix, including pumping of concrete
to site of laying but excluding the cost of centering, shuttering, finishing and
reinforcement, including admixtures in recommended proportions as per IS:
9103 to accelerate, retard setting of concrete, improve workability without
impairing strength and durability as per direction of Engineer-in-
charge.“(Note :- Cement content considered in this item is @ 330
kg/cum.“Excess/ less cement used as per design mix is payable/recoverable
separately).
All works upto plinth level cum
Fountation
F1 22 2.000 2.000 0.4 35.200
F1 22 0.358 7.88
F2 11 1.400 1.400 0.35 7.546
F2 11 0.351 3.862 54.49 Foundation
Grade Beam
wall all round 1 82 0.250 0.350 7.175
long wall 1 32 0.250 0.350 2.800
Short walls 5 8.2 0.250 0.350 3.588
Deduction
Column,C1 -22.00 0.25 0.25 0.35 -0.481
Column,C2 -11.00 0.25 0.25 0.35 -0.241 12.84 Grade beam
Column up to Plinth Level
Column,C1 22.000 0.250 0.450 1.500 3.713
Column,C2 11.000 0.250 0.250 1.500 1.031 4.74 col,plinth lvl
72.075
Say 76.000 9037.920 686881.920
Head Room
Column,C1 4.000 0.250 0.450 3.900
Beam
Ground floor
wall all round 1 82 0.25 0.325 6.663
long wall 1 32 0.25 0.325 2.600
Short walls 6m 4.000 6.220 0.250 0.325 2.022
Short walls 8m 6.000 8.200 0.250 0.325 3.998
Deduction
Column,C1 -22.000 0.250 0.250 0.325 -0.447
Column,C2 -11.000 0.250 0.250 0.325 -0.223 14.611 beam
Head Room
Head Room top 1.000 19.000 0.250 0.325
Deduction
Column,C1 -4.000 0.250 0.200 0.325
Lintel
Ground floor
wall allround 1.000 71.300 0.200 0.200 2.852
Short wall 3 6.5 0.200 0.200 0.780
Head Room
Head Room top 1 19 0.200 0.200 0.760
Roof slab
3.04 Providing, hoisting and fixing above plinth level up to floor five level precast
reinforced cement concrete work in string courses, bands, copings, bed
plates, anchor blocks, plain window sills and the like, including the cost of
required centering, shuttering but , excluding cost of reinforcement, with cum
1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20
mm nominal size).
Nominal quantity 1.000
1.000
Say 1.000 9774.880 9774.880
3.05 Steel reinforcement for R.C.C. work including straightening, cutting, bending,
placing in position and binding with 16 gauge GI binding wire etc complete
including cost, conveyance, lead, lift of all materials for all types of RCC 0.0
works as per drawing/specification and as directed by Engineer-in-Charge at
all levels.
0.00 Thermo-Mechanically Treated bars of grade Fe-500D or more. kg 136.023
Foundation 80kg/m3 1.000 54.491 80.000 4359.241
Plinth beam @ 180 kg/m3 1.000 12.841 180.000 2311.313
Lintels and sunshade @ 80 kg/m3 1.000 4.392 80.000 351.360
columns @ 230 kg/m3 1.000 16.129 230.000 3709.613
Roof beam @ 180 kg/m3 1.000 14.611 180.000 2630.014
Slab and stair @ 100 kg/m3 1.000 33.560 100.000 3355.950
vertical wall @ 140 kg/m3 1.000 0.000 140.000 0.000
136.023 16717.490
0.000 Say 17554.000 79.350 1392909.900
3.06 Centering and shuttering including strutting, propping etc. and removal of
form for :
3.06.01 Foundations, footings, bases of columns etc. for mass concrete. sqm
PCC
Foundation
F1 22 8.800 0.100 19.360
F2 11 6.400 0.100 7.040
Grade Beam
wall all round 1.000 82.000 0.200 16.400
long wall 1.000 32.000 0.200 6.400
Short walls 5.000 8.200 0.200 8.200
Stair 1.000 4.800 0.100 0.480
RCC
F1 22.000 8.000 0.400 70.400
F2 11.000 5.600 0.350 21.560
149.840
Say 158.000 271.920 42963.360
3.06.02 Suspended floors, roofs, landings, balconies and access platform. sqm
Roof slab
Ground floor roof slab @ +3.00 lvl
Total area 1.000 277.000 277.000
Deduction
Stair area -1 6.5 3 0.125 -2.438
274.563
289.000 592.060 171105.340
3.06.03 Lintels, beams, plinth beams, girders, bressumers and cantilevers. sqm
Grade Beam
wall all round 2.000 82.000 0.700 114.800
long wall 2.000 32.000 0.700 44.800
Short walls 10.000 8.200 0.700 57.400
Deduction
Column,C1 -22.000 0.250 0.350 -1.925
Column,C2 -11.000 0.250 0.350 -0.963
Beam
Ground floor
wall all round 1.000 82.000 0.900 73.800
long wall 1.000 32.000 0.900 28.800
3.06.10 Small surfaces such as cantilever ends, brackets and ends of steps, caps
sqm
and bases to pilasters and columns and the like
Say 5.000 723.220 3616.100
4.04 Solid block masonry using pre cast solid blocks ( Factory made) M-10
grade(mix 1:3:6) of size 30x20x20cm or nearest available size confirming to
IS 2185 Part I of 1979 for super structure up to floor two level thickness
20cm and above in: CM 1:6 ( 1 cement : 6 coarse sand) etc complete cum
including scaffolding, raking out of joints,curing, cost and conveyance of all
materials,labour, lead, lift, etc. complete as directed by Engineer-in-Charge.
14.520
Say 16.000 5465.150 87442.400
4.05 Solid block masonry using pre cast solid blocks (Factory made) M-10
grade(mix 1:3:6) of size 30x20x20cm or nearest available size confirming to
IS 2185 part I of 1979 for super structure above floor two level upto floor five
level thickness 20cm and above in : CM 1:6 ( 1 cement : 6 coarse sand cum
sand) etc complete including scaffolding, raking out of joints,curing, cost
and conveyance of all materials,labour, lead, lift, etc. complete as directed
by Engineer-in-Charge.
Ground floor
wall allround 1.000 71.300 0.200 3.150 44.919
Short wall 3.000 6.500 0.200 3.150 12.285
Head Room top 1.000 19.000 0.200 3.150 11.970
Deduction
D -4.000 1.000 0.200 2.100 -1.680
W -12.000 1.200 0.200 1.500 -4.320
V -1.000 0.900 0.200 0.600 -0.108
63.066
Say 67.000 5375.400 360151.800
5.01 Providing and fixing powder coated aluminium work for doors ,windows&
partitions with extruded built up standard tubular sections/appropriate Z
sections & other sections of approved make confirming to IS:733 & IS:1285
fixed with rawl plugs & screws or with fixing clips including necessary filling
up of gaps at junctions,at top,bottom & sides with required PVC/neoprene
felt etc.Aluminium sections shall be smooth,rust free,straight,mitred & jointed
mechanically where ever required including cleat angle,aluminium snap
beading for glazing/panelling,cp brass/stainless steel screws,removing the
stickers clearly all complete as per architectutral drawings & directions of
Engineer-in-Charge at all levels.(glazing & panelling to be paid
seperately).Minimum thickness of powder coating for powder coated
Aluminium shall be 50 micron.
kg/m2
5.01.01 For fixed portion kg
W 12.00 1.20 4.500 1.500 97.200
V 1.00 0.90 4.500 0.600 2.430
5.06 Providing and fixing aluminium extruded section body tubular type universal
hydraulic door closer of approved make (having brand logo with ISI, IS :
3564, embossed on the body, door weight upto 36 kg to 80 kg and door
no
width from 701 mm to 1000 mm), with double speed adjustment with
necessary accessories and screws etc. complete as directed by the
Engineer-in- Charge at all levels.
Ground floor
D 4.000 1.000 4.000
4.000
Say 5.000 544.537 2722.684
5.10 Providing and fixing aluminium hanging floor door stopper ISI marked
anodised (anodic coating not less than grade AC 10 as per
IS:1868)transparent or dyed to required colour and shade with necessary
screws etc complete as directed by the Engineer-in -Charge at all levels.
5.13 Providing and fixing aluminium casement stays, ISI marked, anodised
(anodiccoating not less than grade AC 10 as per IS : 1868) transparent or
dyed to required colour and shade, with necessary screws etc. complete. as no
directed by Engineer -in-Charge at all levels.
W 12.000 3.000 36.000
36.000
Say 38.000 69.400 2637.200
5.14 Providing wood work in frames of doors, windows , clerestory windows and
other frames, wrought frames and fixed in position with hold fast lugs or with
dash fastners of required dia & length(hold fast lugs or dash fastener shall
be paid separately).
Second class teak wood cum
D 4.000 7.800 0.100 0.070 0.218
0.218
5.17 Providing and fixing IS : 12817 marked stainless steel butt hinges with
stainless steel screws etc. complete of size:125x64x1.90 mm.including cost
and conveyance of all materials,labour charges, etc. complete as directed no
by Engineer-in-Charge.
Extra only
D 4.00 1.000 4.000
4.000
Say 5.000 90.920 454.600
5.19 Providing 40x5 mm flat iron hold fast 40 cm long including fixing to frame
with 10 mm diameter bolts, nuts and wooden plugs or approved dash
fastners and embeddings in cement concrete block 30x10x15 cm 1:3:6 mix no
(1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size.
5.21 Providing and fixing bright finished brass tower bolts (barrel type) with
necessary screws etc. complete as directed by the Engineer-in-charge at all
no
levels.
150 x 10 mm
D 4.000 4.000 16.000
16.000
16.000
Say 17.000 271.217 4610.687
1349.000
Say 1417.000 103.560 146744.520
6.08 Providing and fixing S.S fan clamp of 16mm dia in RCC slabs, beams
including cost and conveyance of all materials,labour charges etc complete no Say 5.000 124.717 623.584
as directed by the Engineer-in-Charge at all levels.
7.03 Providing and laying Antiskid Ceramic floor tiles 300x300x7 mm of Ist
quality conforming to IS : 15622 of approved make,shade,and pattern laid on
20mm thick cement mortar 1:4 (1 cement : 4 coarse sand) and jointed with
grey cement slurry @ 3.3 kg/sqm including pointing the joints with white sqm
cement and matching pigment etc.including cost and conveyance of all
materials,labour charges,lead,lift etc, complete as directed by the Engineer-
in-Charge at all levels.
GF
Wash area 1.000 19.500 19.500
19.500
Say 21.000 965.070 20266.470
7.09 Extra for providing opening of required size & shape for wash basins/ kitchen
sink in kitchen platform, vanity counters and similar location in
marble/granite work including providing necessary holes for pillar taps etc. no
including rubbing and polishing of cut edges etc. complete as directed by
the Engineer-in-Charge at all levels.
For wash basin 5.000
5.000
Say 5.000 599.990 2999.950
7.10 Kota stone slab flooring over 20 mm (average) thick base laid over and
jointed with grey cement slurry mixed with pigment to match the shade of the
slab, including rubbing and polishing complete with base of cement mortar 1
: 4 (1 cement : 4 coarse sand) :
25 mm thick sqm
Kitchen and Dining hall 1 25 6.5 162.500
varandah 1 2.2 33 72.600
235.100
Say 247.000 1623.660 401044.020
7.11 Kota stone slabs 20 mm thick in risers of steps, skirting, dado and pillars laid
on 12 mm (average) thick cement mortar 1:3 (1 cement: 3 coarse sand) and
jointed with grey cement slurry mixed with pigment to match the shade of the sqm
slabs, including rubbing and polishing complete.
7.12 Providing and laying 60 mm thick factory made cement concrete interlocking
paver block of M -30 grade made by block making machine with strong
vibratory compaction, of approved size, design & shape, laid in required
colour and pattern over and including 50 mm thick compacted bed of coarse
sand, filling the joints with fine sand etc. all complete as per the direction of
Engineer-in-charge.
Front area 2.00 100.00 5.00 1000.00
1000.00
Say 1050.00 863.21 906370.50
7.13 Providing and fixing PVC tile edging to match the wall tiles and finishing as
m
directed by the Engineer-in-Charge at all levels.
4.000 2.100 8.400
8.400
Say 9.000 46.620 419.580
9.01 6 mm cement plaster to ceiling of mix 1:3 (1 Cement : 3 fine sand) including
cost and conveyance of all materials, labour charges, scaffolding, sundries sqm
etc complete as directed by the Engineer-in-Charge at all levels.
Roof slab
Ground floor roof slab @ +3.00 lvl
Total area 1.000 277.000 277.000
277.000
Say 291.000 201.610 58668.510
9.02 12mm cement plaster of mix 1:4 (1 cement : 4 fine sand)including cost and
conveyance of all materials, labour charges, scaffolding, sundries etc
sqm
complete as directed by the Engineer-in-Charge at all levels.
429.210
Say 451.000 242.480 109358.480
9.03 15mm cement plaster of mix 1:4 (1 cement : 4 fine sand)including cost and
conveyance of all materials, labour charges, scaffolding, sundries etc
sqm 429.210
complete as directed by the Engineer-in-Charge at all levels.
9.04 15mm cement plaster of mix, 1:3 (1 cement : 3 fine sand) finished with a
floating coat of neat cement 2 kg/sqm including mixing water proofing
material in separately).proportion recommended by manufacturer over roof
at all heights including cost and conveyance of all materials, labour charges, sqm
scaffolding, sundries etc complete as directed by the Engineer in charge at
all levels. (water proofing liquid will be paid separately)
9.06 Applying one coat of water thinnable cement primer of approved brand and
manufacture on all surface including cost and conveyance of all materials,
sqm
labour charges, scaffolding, sundries etc complete as directed by the
Engineer-in-Charge at all levels.
9.07 Finishing walls with Premium Acrylic Smooth exterior paint with Silicone
additives of required shade for new work (Two or more coats applied @
1.43 ltr/ 10 sqm over and including priming coat of exterior primer applied
@ 2.20 kg/ 10 sqm). including cost and conveyance of all materials, labour sqm
charges, scaffoldings etc complete as directed by the Engineer-in-Charge at
all levels.
Ground floor
wall allround 1.000 71.300 3.600 256.680
Deduction
D -2.000 1.000 2.100 -4.200
W -6.000 1.200 1.500 -10.800
V -0.500 0.900 0.600 -0.270
241.410
Say 266.000 135.710 36098.860
9.08 Painting the inside walls with acrylic emulsion paint of approved brand and
manufacture to give an even shade two or more coats on new work to
smooth even finish on ceiling and walls including cost and conveyance of all sqm
materials to site, labour charges, hire charges for scaffolding, etc as directed
by Engineer-in-Charge at all levels
Total painting 1101.220
deduction for exterior painting -241.410
859.810
Say 903.000 118.400 106915.200
277.000
Say 291.000 184.930 53814.630
11.05 Supplying and fixing of following sizes of Medium duty PVC conduits
conforming to IS 9537/1983 Part III along with accessories in surface/ recess
including cutting the wall and making good the same in case of recessed
conduit as required.
11.05.01 32mm dia m 25.000 124.780 3119.500
100.000
105.000 10.09 1059.45
2.02.01 Beyond 30cm girth upto and including 60cm girth no 1.000 307.32 307.32
2.07 Filling with contractor's own earth ( excluding rock) in trenches, plinth, sides
of foundations etc. in layers not exceeding 20 cm in depth, consolidating
cum
each deposited layer by ramming and watering, lead up to 50 mm and lift up
to 1.5 m as per direction of site Engineer-in-charge
Plinth area 1.0 9.650 8.600 82.990
82.990
Say 88.000 436.40 38403.20
3.01 Providing and laying in position cement concrete of specified grade excluding
the cost of centering and shuttering - All work up to plinth level :
3.02 Providing and laying cement concrete of specific grade properly mixed and
consolidated with hand rammers, including cost and conveyance of all
materials, labour, curing, lead lift , etc. complete as directed by Engineer-in-
Charge at all levels.
For screed concrete 1:2:4 (1 Cement : 2coarse sand : 4 graded stone
cum
aggregate 6mm nominal size)
For Roof slab 1.0 9.650 8.600 0.050 4.150
Say 5.000 7712.26 38561.30
3.03 Extra for providing and mixing water proofing material in cement concrete
work in doses by weight of cement as per manufacturer's specification kg
4.02 Providing and laying in position machine batched and machine mixed design
mix M-25 grade cement concrete for reinforced cement concrete work, using
cement content as per approved design mix, including pumping of concrete
to site of laying but excluding the cost of centering, shuttering, finishing and
reinforcement, including admixtures in recommended proportions as per IS:
9103 to accelerate, retard setting of concrete, improve workability without
impairing strength and durability as per direction of Engineer-in-
charge.“(Note :- Cement content considered in this item is @ 330
kg/cum.“Excess/ less cement used as per design mix is payable/recoverable
separately).
All works above plinth level upto floor V level cum
Column
Ground floor
C2 2.0 0.250 0.250 3.475 0.434
First floor
C2 2.0 0.250 0.250 3.475 0.434 0.87 columns
Building 2 - Beam
Ground Floor
Varandah 1.0 9.650 0.250 0.450 1.086
First Floor
SLAB
Ground Floor
Area 1.0 9.650 6.000 0.140 8.106
Toilet slab 1.0 4.500 0.600 0.100 0.270
First Floor
Area 1 9.65 6 0.14 8.106
Toilet slab 1 4.5 0.6 0.1 0.27
Additional for sloping slab 15.000
Kitchen platforms, Toilet wash ,seating slab etc - Building 2 1.0 19.500 0.600 0.100 1.170 32.92 roof slab
42.044
Say 43.000 10164.57 437076.51
4.05 Steel reinforcement for R.C.C. work including straightening, cutting, bending,
placing in position and binding with 16 gauge GI binding wire etc complete
including cost, conveyance, lead, lift of all materials for all types of RCC
works as per drawing/specification and as directed by Engineer-in-Charge at
all levels.
Thermo-Mechanically Treated bars of grade Fe-500D or more. kg
Foundation 100kg/m3 1.0 44.984 100.000 4498.353
Plinth beam @ 180 kg/m3 1.0 2.053 180.000 369.563
Lintels and sunshade @ 100 kg/m3 1.0 6.082 100.000 608.240
columns @ 240 kg/m3 1.0 1.069 240.000 256.500
Roof beam @ 180 kg/m3 1.0 2.171 180.000 390.825
Slab and stair @ 120 kg/m3 1.0 32.922 120.000 3950.640
vertical wall @ 140 kg/m3 1.0 0.000 140.000 0.000
44.298 10074.120
Say 10075.000 79.35 799451.25
4.06 Centering and shuttering including strutting, propping etc. and removal of
form for :
4.06.01 Foundations, footings, bases of columns etc. for mass concrete. sqm
PCC
Plinth beam
Long walls 3 9.65 0.2 5.790
Short walls 3 8.6 0.2 5.160
F2 2.0 5.600 0.100 1.120
RCC
F2 2.0 5.600 0.350 3.920
15.990
Say 31.980 271.92 8696.00
4.06.02 Suspended floors, roofs, landings, balconies and access platform. sqm
GF
Roof Slab 1.0 82.990 82.990
FF
4.06.03 Lintels, beams, plinth beams, girders, bressumers and cantilevers. sqm
Plinth beam
Long walls 3 9.65 0.3 8.685
Short walls 3 8.6 0.3 7.740
Roof Beams
Varandah
Ground Floor
Varandah 1 9.65 0.350 3.378
First Floor
Varandah 1 9.65 0.350 3.378
Lintel
Ground floor
Long walls 2.00 9.65 0.40 7.720
Short walls 3.00 6.00 0.40 7.200
First Floor
Long walls 2.00 9.65 0.40 7.720
Short walls 3.00 6.00 0.40 7.200
half brick Walls
Ground floor
Toilet walls 2 4 0.3 2.400
6 1.5 0.3 2.700
First floor
Toilet walls 2 4 0.3 2.400
6 1.5 0.3 2.700
63.220
Say 64.000 480.75 30768.00
4.06.04 Columns, Pillars, Piers, Abutments, Posts and Struts. sqm
Building2
Column up to Plinth Level
C2 2 1.000 1.600 3.200
Ground floor
C2 2 1.000 3.600 7.200
First floor
C2 2 1.000 3.600 7.200
17.600
Say 18.000 655.93 11806.74
0.00 Vertical and horizontal fins individually or forming box louvers band,facias,
sqm
and eaves board.
0.000
4.10 Random rubble masonry with hard stone in foundation and plinth including
levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12
graded stone aggregate 20mm nominal size) at plinth level with cement
mortar 1:6 (1 cement : 6 coarse sand)including raking out of joints,filling the
joints /hollows with suitable sizes of split stones,filling the joints clearly,
curing,cost and conveyance of all materials, cost of bond stone (should be
provided at every 0.5 sqm of face area) , lead, lift etc. complete as directed
by Engineer-in-Charge at all levels.
6.01 Providing and fixing powder coated aluminium work for doors ,windows&
partitions with extruded built up standard tubular sections/appropriate Z
sections & other sections of approved make confirming to IS:733 & IS:1285
fixed with rawl plugs & screws or with fixing clips including necessary filling
up of gaps at junctions,at top,bottom & sides with required PVC/neoprene
felt etc.Aluminium sections shall be smooth,rust free,straight,mitred & jointed
mechanically where ever required including cleat angle,aluminium snap
beading for glazing/panelling,cp brass/stainless steel screws,removing the
stickers clearly all complete as per architectutral drawings & directions of
Engineer-in-Charge at all levels.(glazing & panelling to be paid
seperately).Minimum thickness of powder coating for powder coated
Aluminium shall be 50 micron.
6.01.01 For fixed portion kg kg/m2
GF
Windows 1.00 1.20 4.500 1.500 8.100
Ventelators 7.00 0.90 4.500 0.600 17.010
FF
Windows 1.00 1.20 4.50 1.50 8.100
Ventelators 7.00 0.90 4.50 0.60 17.010
50.220
Say 51.000 539.07 27492.57
6.01.02 For shutter of doors ,windows & ventilators including providing and fixing
hinges/pivots and making provision for fixing of fittings,exhaust fan of
kg
required size,etc wherever required including the cost of PVC neoprene
gasket required(fittings shall be paid for separately)
Nominal quantity 50.220
50.220
Say 51.000 623.75 31811.25
0.00 Providing and fixing aluminium extruded section body tubular type universal
hydraulic door closer of approved make (having brand logo with ISI, IS :
3564, embossed on the body, door weight upto 36 kg to 80 kg and door
no
width from 701 mm to 1000 mm), with double speed adjustment with
necessary accessories and screws etc. complete as directed by the
Engineer-in- Charge at all levels.
D 4.0 4.000
4.000
Say 5.000 544.54 2722.68
0.00 Providing and fixing 125 mm aluminium handles ISI marked anodised
(anodic coating not less than grade AC 10 as per IS : 1868) transparent or
no
dyed to required colour or shade with necessary screws etc. complete as
directed by Engineer -in-Charge at all levels.
4.000 71.64 286.57
6.04 Providing and fixing Aluminium tower bolts ISI marked anodised (anodic
coating not less than grade AC 10 as per IS : 1868) transparent or dyed to
no
required colour or shade with nuts and screws etc. complete as directed by
the Engineer-in-Charge at all levels.
0 200mm x 10 mm
50% considered 10.000
10.000
Say 10.000 106.76 1067.60
6.05 Filling the gap in between aluminium frame & adjacent RCC/block work by
providing weather silicon sealent over backer rod of approved quality as per
m
drawings and direction of Engineer-in-Charge at all levels.Up to 5 mm depth
and 5 mm width.
6.06 Providing and fixing aluminium hanging floor door stopper ISI marked
anodised (anodic coating not less than grade AC 10 as per
IS:1868)transparent or dyed to required colour and shade with necessary
screws etc complete as directed by the Engineer-in -Charge at all levels.
6.07 Providing and fixing bright finished brass handles with screws etc.complete:
no
125mm
10.000
10.000
Say 11.000 240.02 2640.22
6.08 Supplying and fixing 200 mm Aluminium aldrop including cost and
conveyance of all materials,labour charges ,lead,lift etc. complete as
directed by the Engineer-in-Charge at all levels.
Toilet doors 10.000
Say 10.000 170.43 1704.30
6.10 Providing and fixing panelled or panelled and glazed shutters for doors,
windows and clerestory windows including ISI marked stainless steel butt
sqm
hinges(100 x 60 x 6.5mm IS : 12817 marked ) with necessary screws
excludings panelling which be paid for separately.
Second class teak wood
35 mm thick shutters
6.11 Providing and fixing panelling or panelling and glazing in panelled or panelled
and glazed shutters for doors, windows and clerestory windows(area of
opening for panel inserts excluding portion inside grooves or rebates to be sqm
measured). Panelling for panelled or panelled and glazed shutters 25mm to
40mm thick:
6.12 Providing and fixing IS : 12817 marked stainless steel butt hinges with
stainless steel screws etc. complete of size:125x64x1.90 mm.including cost
and conveyance of all materials,labour charges, etc. complete as directed no
by Engineer-in-Charge.
Building 2
D 4.0 8.000 32.000
32.000
Say 33.000 166.28 5487.24
6.14 Providing and fixing bright finished brass100mm mortice latch and lock ISI
marked with 6 levers and a pair of anodised(anodic coating not less than
grade AC 10 as per IS:1868)aluminium lever handles with necessary screws no
etc. complete at all levels.(best make of approved quality).
Building 2
D 4.0 1.000 4.000
4.000
Say 5.000 872.25 4361.27
6.15 Providing and fixing bright finished brass tower bolts (barrel type) with
necessary screws etc. complete as directed by the Engineer-in-charge at all
no
levels.150 x 10 mm
Building 2
D 4.0 4.000
4.000
50% considered 2.000
Say 3.000 271.22 813.65
6.16 Extra rate for providing etching on plain glass for Aluminium doors including
providing an additional 3 mm glass on the rough side of etched glass
including cost and conveyance of all materials, all labour charges, lead, lift, sqm
all taxes, sundries, etc., complete at all levels as directed by the Engineer-in-
Charge.
Nominal quantity 20.000
6.17 Providing and fixing Fiber Glass Reinforced plastic (FRP) Door Frames of
crosssection 90 mm x 45 mm having single rebate of 32 mm x 15 mm to
receive shutter of 30 mm thickness. The laminate shall be moulded with fire
resistant grade unsaturated polyester resin and chopped mat. Door frame
m
laminate shall be 2 mm thick and shall be filled with suitable wooden block in
all the three legs. The frame shall be covered with fiber glass from all sides.
M.S. stay shall be provided at the bottom to steady the frame.
Building 2
Ground floor
D1 6.00 6.000
First floor
D1 6.00 6.000
12.000
Say 13.000 582.53 7572.89
10.080
Say 11.000 3555.19 39107.11
6.19 Providing and fixing windows & ventilators, fabricated from roll formed
sections made of Galvanized steel, prepainted(base steel as per IS 513"D"
quality, Galvanised as per IS 277 with zinc of 120 grams per sq. mtr) with sqm
total coated thickness of 0.60 mm. Coated sections should be painted with
primer coat of Epoxy primer of 5-7 microns thick, finish painted with pollyster
Ground Floor
7.01 Structural steel work welded in built up sections,trussess and framed work
including cutting, hoisting, fixing in position and applying two coats of
Synthetic enamel paint over two coats of anticorrossive Yellow zinc
kg kg/m
chromate primer including cost and conveyance of all materials,labour
charges ,lead,lift etc complete as directed by Engineer- in-Charge at all
levels.
Nominal Quantity 100.000
100.000
Say 105.000 96.58 10140.90
7.02 Steel work welded in built up sections/framed work including cutting hoisting,
fixing in position and applying two coats of approved make and colour
synthetic enamel paint over two coats of approved make anticorrossive
yellow zinc chromate primer, etc. including cost and conveyance of all
materials, labour, lead,lift etc. complete as directed by Engineer- in-Charge
at all levels.
8.03 Providing and laying Antiskid Ceramic floor tiles 300x300x7 mm of Ist
quality conforming to IS : 15622 of approved make,shade,and pattern laid on
20mm thick cement mortar 1:4 (1 cement : 4 coarse sand) and jointed with
grey cement slurry @ 3.3 kg/sqm including pointing the joints with white sqm
cement and matching pigment etc.including cost and conveyance of all
materials,labour charges,lead,lift etc, complete as directed by the Engineer-
in-Charge at all levels.
Building 2
Ground Floor
Toilet 2.0 6.000 9.650 115.800
First Floor
Toilet 2.0 6.000 9.650 115.800
8.04 Providing and fixing 1st quality ceramic glazed wall tiles conforming to IS :
15622(thickness to be specified by the manufacture of approved make in all
colours , shades except burgundy, bottle green, black of any size as
approved by Engineer-in- charge in skirting, risers of steps and dados over sqm
12mm thick bed of cement Mortar 1:3 (1 cement: 3 coarse sand) and jointing
with grey cement slurry@ 3.3kg per sqm including pointing in white cement
mixed with pigment of matching shade complete.
Building 2
Ground Floor
Toilet 2 31.3 1.8 112.680
8.06 Providing and applying water proofing treatment in sunken portion of WCs,
bathroom etc., by applying cement slurry mixed with water proofing cement
compound consisting of applying : a) First layer of slurry of cement @ 0.488
kg /sqm mixed with water proofing cement compound @ 0.253 kg/sqm. This
layer will be allowed to air cure for 4 hours. b) Second layer of slurry of
cement @ 0.242 kg/ sqm mixed with water proofing cement compound @
0.126 kg/ sqm. This layer will be allowed to air cure for 4 hours followed with
water curing for 48 hours. The rate includes preparation of surface, treatment sqm
and sealing of all joints, corners, junctions of pipes and masonry with
polymer mixed slurry,cost and conveyance of all materials,labour
charges,lead,lift etc complete as directed by the Engineer-in-Charge.(The
above work shall be carriedout by an agency having sufficient experience
in membrane water proofing and should ensure a guarantee of 5 years. Only
skilled and experienced persons shall be employed for this purp
231.600
231.600
Say 244.000 418.22 102045.68
7.10 Kota stone slab flooring over 20 mm (average) thick base laid over and
jointed with grey cement slurry mixed with pigment to match the shade of the
slab, including rubbing and polishing complete with base of cement mortar 1
: 4 (1 cement : 4 coarse sand) :
Varandah GF 2.0 9.650 2.100 40.530
Varandah FF 2.0 9.7 2.1 40.5
81.060
86.000 1623.66 139634.76
7.11 Kota stone slabs 20 mm thick in risers of steps, skirting, dado and pillars laid
on 12 mm (average) thick cement mortar 1:3 (1 cement: 3 coarse sand) and
jointed with grey cement slurry mixed with pigment to match the shade of the
slabs, including rubbing and polishing complete.
SKIRTING
Varandah GF 2 9.65 0.2 3.86
Varandah FF 2 9.65 0.2 3.86
7.720
TOTAL OF SUB HEAD-8.0 726193.97
10.01 6 mm cement plaster to ceiling of mix 1:3 (1 Cement : 3 fine sand) including
cost and conveyance of all materials, labour charges, scaffolding, sundries
etc complete as directed by the Engineer-in-Charge at all levels. sqm
10.02 12mm cement plaster of mix 1:4 (1 cement : 4 fine sand)including cost and
conveyance of all materials, labour charges, scaffolding, sundries etc sqm
complete as directed by the Engineer-in-Charge at all levels.
GF
Long walls 2.00 9.65 4.20 81.060
Short walls 4.00 6.00 4.20 100.800
Deduction
Door D -2.00 1.00 2.10
Windows -1.00 1.20 1.50 -1.800
Ventelators -7.00 0.90 0.60 -3.780
FF
Long walls 2.00 9.65 4.20
Short walls 4.00 6.00 4.20 100.800
Deduction
Door D -2.00 1.00 2.10 -4.200
Windows -1.00 1.20 1.50
Ventelators -7.00 0.90 0.60 -3.780
269.100
269.100
Say 283.000 242.48 68621.84
10.03 15mm cement plaster of mix 1:4 (1 cement : 4 fine sand)including cost and
conveyance of all materials, labour charges, scaffolding, sundries etc sqm
complete as directed by the Engineer-in-Charge at all levels.
269.100
Cladding deduction -225.360
43.740
Say 46.000 280.75 12914.50
10.06 Applying one coat of water thinnable cement primer of approved brand and
manufacture on all surface including cost and conveyance of all materials,
sqm
labour charges, scaffolding, sundries etc complete as directed by the
Engineer-in-Charge at all levels.
6 mm plastering 82.990
12 mm platering 269.100
15 mm plastering 43.740
395.830
Say 404.000 51.80 20927.20
10.07 Finishing walls with Premium Acrylic Smooth exterior paint with Silicone
additives of required shade for new work (Two or more coats applied @ 1.43
ltr/ 10 sqm over and including priming coat of exterior primer applied @
2.20 kg/ 10 sqm). including cost and conveyance of all materials, labour sqm
charges, scaffoldings etc complete as directed by the Engineer-in-Charge at
all levels.
GF
Outside walls 2.0 31.300 4.200 262.920
FF
Outside walls 2 31.3 0 4.2 262.920
525.840
Say 579.000 135.71 78576.09
10.08 Painting the inside walls with acrylic emulsion paint of approved brand and
manufacture to give an even shade two or more coats on new work to
smooth even finish on ceiling and walls including cost and conveyance of all sqm
materials to site, labour charges, hire charges for scaffolding, etc as directed
by Engineer-in-Charge at all levels
Total painting 791.660
Deduction for exterior painting -525.840
265.820
Say 280.000 118.40 33152.00
82.990
Say 85.000 553.79 47072.15
10.11 Painting with synthetic enamel paint of approved brand and manufacture
ofrequired colour to give an even shade : Two or more coats on new work
over an under coat of suitable shade withordinary paint of approved brand
and manufactureThe rate shall include cost and conveyance of all materials, sqm
lead lift, all labour charges, scaffolding, sundries etc complete as directed by
the Engineer in charge at all levels.
13.02 Diluting and injecting chemical emulsion for POST- CONSTRUCTIONAL anti-
termite treatment (excluding the cost of chemical emulsion) :Treatment of
soil under existing floors using chemical emulsion @ one litre per hole, 300
mm apart including drilling 12 mm diameter holes and plugging with cement sqm
mortar 1 :2 (1 cement : 2 Coarse sand) to match the existing floor: : With
Chlorpyriphos/Lindane E.C. 20% with 1% concentration
13.04 Providing and fixing stainless steel coat & hat hook of approved make and
pattern on door including cost and conveyance of all materials, labour
no
charges,fixing charges,etc complete as directed by the Engineer-in-Charge.
9.01 Providing and fixing white vitreous china pedestal type water closet (European type)
with seat and lid, 10 litre low level white vitreous china flushing cistern & C.P. flush bend
with fittings & C.I. brackets, 40 mm flush bend, overflow arrangement with specials of
standard make and mosquito proof coupling of approved municipal design complete, no 7.00 7.00 6440.44 45083.08
including painting of fittings and brackets, cutting and making good the walls and floors
wherever required :W.C. pan with ISI marked white solid plastic seat and lid.
9.02 Providing and fixing water closet squatting pan (Indian type W.C. pan ) with 100 mm
sand cast Iron P or S trap, 10 litre low level white P.V.C. flushing cistern, including flush
pipe, with manually controlled device (handle lever) conforming to IS : 7231, with all
no 1.00 1.00 4898.87 4898.87
fittings and fixtures complete, including cutting and making good the walls and floors
wherever required: White Vitreous china Orissa pattern W.C. pan of size 580x440 mm
with integral type foot rests
9.03 Providing and fixing coloured vitreous china under counter round wash basin 440 mm
dia or nearest size of approved make including one CP brass pillar cock 15 mm NB
including connecting pipes with all fittings 32 mm dia rubber plugs 32 mm dia CP brass no 12 12.00 5867.05 70404.60
waste coupling, 32 mm dia CP brass bottle trap, 15mm angle valve, etc. complete as
directed by the Engineer-in-charge.
9.04 Providing and fixing 600x450x200 mm white vitreous china laboratory sink with sink
cock with swinging spout, C.I. brackets, C.P. brass chain with rubber plug ,40mm C.P.
Brass waste and 40mm C.P. Brass trap with necessary C.P. Brass unions complete no 0.00 0.00 4502.45 0.00
including painting of fitting and brackets, cutting and making good the wall wherever
required:
9.05 Providing and fixing white vitreous china flat back half stall urinal of size 580x380x350
mm with white PVC automatic flushing cistern, with fittings, standard size C.P. brass
flush pipe, spreaders with unions and clamps (all in C.P. brass) with waste fitting as per
IS : 2556, C.I. trap with outlet grating and other couplings in C.P. brass, including no 17.00 17.00 8674.73 147470.41
painting of fittings and cutting and making good the walls and floors wherever required :
Single half stall urinal with 5 litre P.V.C. automatic flushing cistern
9.07 Providing and fixing frameless mirror, with all four edges machine polished and back
side protected with safety film and 4 mm thick Plywood backing and fixed on walls with
sqm 5 5.00 3889.300 19446.50
mirror screws. The rate includes lifting, cutting etc. as per design and drawing.
9.08 Providing and fixing CP brass long body bib cock of approved quality conforming to IS
standards and weighing not less than 690 gms including cost and conveyance of all
materials, labour charges, sundries etc complete as directed by the Engineer-in-Charge
at all levels
15 mm nominal bore no 7.00 7.00 690.56 4833.92
9.09 Providing and fixing floor trap of PVC,110 mm outer dia(multi trap) including CP
cockroach free floor grating with cup etc including cost and conveyance of all
no 11.00 11.00 367.90 4046.90
materials, labour charges, sundries etc complete as directed by the Engineer-in-Charge
at all levels
9.10 Providing and fixing C.P. brass stop cock concealed with adjustable wall flange of
standard design and of approved make conforming to IS: 8931 including cost and
conveyance of all materials, labour charges, sundries etc complete as directed by the
Engineer-in-Charge at all levels
15 mm nominal bore no 2.00 2.00 765.42 1530.84
9.09 Providing and fixing CP brass health faucets with 8mm dia 1 meter long flexible tube
and wall hook with all fittings and fixtures including angle valve etc complete inlcuding
cutting and making good the walls and floors wherever required including cost and no 7.00 7.00 1280.47 8963.29
conveyance of all materials, labour charges, sundries etc complete as directed by the
Engineer-in-Charge at all levels.
9.10 Providing and fixing PVC pipes, fittings including fixing the pipe with clamps at 1.00 m
spacing . This includes jointing of pipes & fittings with one step PVC solvent cement and
testing of joints complete as per direction of Engineer-in-Charge - Internal work-
Exposed on wall
9.11 Providing and fixing PVC pipes, fittings including fixing the pipe with clamps at 1.00 m
spacing. This includes jointing of pipes & fittings with one step PVC solvent cement and
testing of joints complete as per direction of Engineer-in-Charge. Concealed work,
including cutting chases and making good the wall etc.
9.12 Providing and fixing PVC pipes includings jointing of pipes with one step pvc solvent
cement, trenching , refilling & testing of joints complete as per direction of Engineer in
Charge - external works
9.13 Providing and fixing PVC vent cowl to pipe already fixed as directed by Engineer-in-
Charge at all levels.
10.01 Excavating trenches of required width for pipes, cables, etc. including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m including getting
out the excavated soil, and then returning the soil as required, in layers not exceeding
20 cm in depth including consolidating each deposited layer by ramming, watering, etc.
and disposing of surplus excavated soil and unserviceable material as directed, within a
lead of 50 m
All kinds of soil
10.01.01 Pipes, cables etc. not exceeding 80mm dia m 20.00 193.55 3871.00
10.01.02 In all kinds of soil for pipes, cables etc exceeding 80mm dia but notexceeding 300mm dia. m 100.00 316.08 31608.00
10.01.03 Pipes, cables etc. exceeding 300mm dia but not exceeding 600mm m 20.00 493.50 9870.00
10.02 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal
stability for hot & cold water supply, including all CPVC plain & brass threaded fittings,
including fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes &
fittings with one step CPVC solvent cement and testing of joints complete as per
direction of Engineer-in-Charge. Internal work - Exposed on wall
10.03 Providing and fixing gun metal gate valve with C.I. Wheel of approved quality (screwed
end) including cost and conveyance of all materials, labour charges, sundries etc
complete as directed by the Engineer- in-Charge at all levels
10.04 Providing and fixing Chlorinated Polyvinyl chloride(CPVC) SDR 11 pipes, having
thermal stability for hot and cold water supply including all CPVC plain and brass
threaded fittingsi/c fixing the pipes with clamps at 1.00 m spacing.This includes jointing
of pipes and fittings with one step CPVC solvent cement and the cost of cutting chases
and making good the same including testing of joints complete as per the direction of
Engineer-in-Charge.(Concealed work including cutting chases and making good the
walls etc)
10.05 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal
stability for hot & cold water supply including all CPVC plain & brass threaded fittings
This includes jointing of pipes & fittings with one step CPVC solvent cement, trenching,
refilling & testing of joints complete as per direction of Engineer in Charge.
10.05.01 62.50 mm nominal inner dia pipes m 42.00 42.00 1516.61 63697.62
10.07 Providing and placing on terrace (at all floor levels) polyethylene water storage tank, IS :
12701 marked, with cover and suitable locking arrangement and making necessary
ltr 5000.00 5000.00 10.17 50850.00
holes for inlet, outlet and overflow pipes but without fittings and the base support for
tank.
10.08 Constructing brick masonry manhole with 75 class designation bricks in cement mortar
1:4 (1 Cement : 4 coarse sand) R.C.C. top slab with 1:2:4 (1 Cement : 2 coarse sand : 4
graded stone aggregate 20 mm nominal size) foundation concrete with 1:4:8 mix (1
Cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size) inside
plastering 12 mm thick with cement mortar 1:3 (1 Cement : 3 coarse sand) finished with
floating coat of neat cement and making channels in cement concrete 1:2:4 (1 Cement :
2 coarse sand : 4 graded stone aggregate 20 mm nominal size) finished with a floating
coat of neat cement complete as per standard design including cost and conveyance of
all materials, labour charges, sundries etc complete as directed by the Engineer-in-
Charge
10.08.01 Inside size 90x80 cm and 45 cm deep including C.I. cover with frame (light duty)
455x610 mm internal dimensions total weight of cover and frame to be not less than 38
kg (weight of cover 23 kg and weight of frame 15 kg) :
10.09.01 Size 90 x 80 cm. With bricks.Class designation 75 m 3.00 3.00 8017.48 24052.44
10.11 Supplying and fixing of CI single flanged wall casting pipe with puddle, 0.6m length
including cost and conveyance of all materials,labour charges,making good the walls
0.00
etc complete as directed by the Engineer-in-Charge.
10.12 Supplying and fixing CI foot valve with all accessories including cost and conveyance of
all materials,labour charges etc complete as directed by the Engineer -in - charge at all
levels.
50mm no 4.00 4.00 3277.92 13111.69
10.13 Supplying and fixing gun metal Non return valve with all accessories including cost and
conveyance of all materials,labour charges etc complete as directed by the Engineer- in-
Charge at all levels
10.14 Supplying and fixing of centrifugal pump, with CI construction, CI impeller complete
with motor, base plate, foundation bolts, nuts, pressure guage and all accessories. and
working with 415V, 3ph and 50 Hz frequency
Capacity : 17m3/hr no 0.00 0.00 10814.00 0.00
10.15 Providing and fixing enclosed type water meter (bulk type) 50mm dia conforming to IS :
2373 and tested by Municipal Board complete with bolts, nuts, rubber insertions etc.
(The tail pieces if required will be paid separately) including cost and conveyance of all no 1.00 1.00 8288.48 8288.48
materials, labour etc. complete and as directed by Engineer-in-Charge
10.16 Providing and fixing C.I. basket type dirt box strainer 50mm dia for bulk type water
meter with nuts, bolts, rubber insertions etc. complete conforming to IS : 2373 :
no 1.00 1.00 6704.54 6704.54
including cost and conveyance of all materials, labour etc. complete and as directed by
Engineer-in-Charge
10.17 Providing and constructing soak pit 1.5 m x 1.5 m x 1.5 m size with honey comb brick
work on the sides upto a height of 0.9m and brick masonry in CM 1:6 for the balance
height,providing and filling brick bats graded, upto a height of 1.2 m,providing and laying
no 1.00 24669.36 24669.36
precast slab over the pit supporting on the brick work, including cost and conveyance
of all materials,labour charges, lead, lift, etc. complete as directed by the Engineer-in-
charge.
9.03 Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps, 32 mm
C.P. brass waste of standard pattern, including painting of fittings and brackets, cutting
and making good the walls wherever require:White Vitreous China Wash basin size no 8.00 8.00 3222.57 25780.56
630x450 mm with a pair of 15 mm C.P.brass pillar taps
9.03 Providing and fixing coloured vitreous china under counter round wash basin 440 mm
dia or nearest size of approved make including one CP brass pillar cock 15 mm NB
including connecting pipes with all fittings 32 mm dia rubber plugs 32 mm dia CP brass no 8 8.00 5867.05 46936.40
waste coupling, 32 mm dia CP brass bottle trap, 15mm angle valve, etc. complete as
directed by the Engineer-in-charge.
9.04 Providing and fixing 600x450x200 mm white vitreous china laboratory sink with sink
cock with swinging spout, C.I. brackets, C.P. brass chain with rubber plug ,40mm C.P.
Brass waste and 40mm C.P. Brass trap with necessary C.P. Brass unions complete no 2.00 2.00 4502.45 9004.90
including painting of fitting and brackets, cutting and making good the wall wherever
required:
9.07 Providing and fixing frameless mirror, with all four edges machine polished and back
side protected with safety film and 4 mm thick Plywood backing and fixed on walls with
sqm 4 4.00 3889.300 15557.20
mirror screws. The rate includes lifting, cutting etc. as per design and drawing.
9.10 Providing and fixing C.P. brass stop cock concealed with adjustable wall flange of
standard design and of approved make conforming to IS: 8931 including cost and
conveyance of all materials, labour charges, sundries etc complete as directed by the
Engineer-in-Charge at all levels
15 mm nominal bore no 2.00 2.00 765.42 1530.84
9.09 Providing and fixing floor trap of PVC,110 mm outer dia(multi trap) including CP
cockroach free floor grating with cup etc including cost and conveyance of all
no 2.00 2.00 367.90 735.80
materials, labour charges, sundries etc complete as directed by the Engineer-in-Charge
at all levels
9.10 Providing and fixing PVC pipes, fittings including fixing the pipe with clamps at 1.00 m
spacing . This includes jointing of pipes & fittings with one step PVC solvent cement and
testing of joints complete as per direction of Engineer-in-Charge - Internal work-
Exposed on wall
9.11 Providing and fixing PVC pipes, fittings including fixing the pipe with clamps at 1.00 m
spacing. This includes jointing of pipes & fittings with one step PVC solvent cement and
testing of joints complete as per direction of Engineer-in-Charge. Concealed work,
including cutting chases and making good the wall etc.
9.12 Providing and fixing PVC pipes includings jointing of pipes with one step pvc solvent
cement, trenching , refilling & testing of joints complete as per direction of Engineer in
Charge - external works
9.13 Providing and fixing PVC vent cowl to pipe already fixed as directed by Engineer-in-
Charge at all levels.
9.14 Providing and fixing Cleanout with Spigot, with SS 304 Square Frame & Round Frame
with Flat Round Cover with Rubber Seal & SS Screw including cost and conveyance of
all materials, labour charges, sundries etc complete as directed by the Engineer in
charge at all levels
10.01 Excavating trenches of required width for pipes, cables, etc. including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m including getting
out the excavated soil, and then returning the soil as required, in layers not exceeding
20 cm in depth including consolidating each deposited layer by ramming, watering, etc.
and disposing of surplus excavated soil and unserviceable material as directed, within a
lead of 50 m
All kinds of soil
10.01.01 Pipes, cables etc. not exceeding 80mm dia m 20.00 193.55 3871.00
10.01.02 In all kinds of soil for pipes, cables etc exceeding 80mm dia but notexceeding 300mm dia. m 20.00 316.08 6321.60
10.01.03 Pipes, cables etc. exceeding 300mm dia but not exceeding 600mm m 20.00 493.50 9870.00
10.02 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal
stability for hot & cold water supply, including all CPVC plain & brass threaded fittings,
including fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes &
fittings with one step CPVC solvent cement and testing of joints complete as per
direction of Engineer-in-Charge. Internal work - Exposed on wall
10.03 Providing and fixing gun metal gate valve with C.I. Wheel of approved quality (screwed
end) including cost and conveyance of all materials, labour charges, sundries etc
complete as directed by the Engineer- in-Charge at all levels
10.04 Providing and fixing Chlorinated Polyvinyl chloride(CPVC) SDR 11 pipes, having
thermal stability for hot and cold water supply including all CPVC plain and brass
threaded fittingsi/c fixing the pipes with clamps at 1.00 m spacing.This includes jointing
of pipes and fittings with one step CPVC solvent cement and the cost of cutting chases
and making good the same including testing of joints complete as per the direction of
Engineer-in-Charge.(Concealed work including cutting chases and making good the
walls etc)
10.05 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal
stability for hot & cold water supply including all CPVC plain & brass threaded fittings
This includes jointing of pipes & fittings with one step CPVC solvent cement, trenching,
refilling & testing of joints complete as per direction of Engineer in Charge.
10.05.01 62.50 mm nominal inner dia pipes m 6.00 6.00 1516.61 9099.66
10.07 Providing and placing on terrace (at all floor levels) polyethylene water storage tank, IS :
12701 marked, with cover and suitable locking arrangement and making necessary
ltr 1000.00 1000.00 10.17 10170.00
holes for inlet, outlet and overflow pipes but without fittings and the base support for
tank.
10.09.01 Size 90 x 80 cm. With bricks.Class designation 75 m 3.00 3.00 8017.48 24052.44
49.27
say 50.00 176.58 8829.00
Earth work in excavation by means (Hydraulic excavator)/manual means
over areas (exceeding 30cm in depth.1.5m in width as well as 10 sqm on
plan) including disposal of excavated earth, lead upto 50 m disposed earth
to be levelled and neatly dressed, as directed by the Engineer- in-Charge
but for every additional lift of 1.5m to 3.00m or part there of :
1.07
1.07.01 All kinds of soil cum 1.00 7.82 4.20 0.85 27.92
27.92
Say 28.00 249.13 6975.64
Providing and laying cement concrete of specific grade properly mixed and
consolidated with hand rammers, including cost and conveyance of all
materials, labour, curing, lead lift , etc. complete as directed by Engineer-in-
2.02 Charge at all levels.
For screed concrete 1:2:4 (1 Cement : 2coarse sand : 4 graded stone
cum 1.00 3.50 2.00 0.18 1.23
aggregate 6mm nominal size)
say 2.00 7712.26 15424.52
Extra for providing and mixing water proofing material in cement concrete
work in doses by weight of cement as per manufacturer's specification kg
2.03
plastering item= 2.81
Cast in situ RCC cover slab 1.00 6.02 2.40 0.15 2.17 2.06 Cover slab
Manhole -2.00 0.60 0.60 0.15 -0.11
14.638
say 15.00 9135.36 137030.4
Providing, hoisting and fixing above plinth level up to floor five level precast
reinforced cement concrete work in string courses, bands, copings, bed
plates, anchor blocks, plain window sills and the like, including the cost of
required centering, shuttering but , excluding cost of reinforcement, with
1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20
3.04 mm nominal size).
cum
3.06.02 Suspended floors, roofs, landings, balconies and access platform. sqm
Cast in situ RCC cover slab 1.00 6.02 2.40 14.45
Manhole -2.00 0.60 0.60 -0.72
13.73
say 14.00 592.06 8288.84
Add for using extra cement in the items of design mix over and above the
qtl 14.84
3.08 specified cement content there in.
742.02
7.42
say 8.00 943.20 7545.6
Providing and fixing CI manhole cover with frame 560 mm diameter C.I.
cover (heavy duty) the weight of the cover to be not less than 108 kg in
concrete slab over manholes/Inspection Chambers/Drains, including cost no 5.00 8259.46 41297.3
and conveyance of all materials, all labour charges, all taxes,lead, lift,
sundries, etc., complete. as directed by the Engineer- in-Charge
6.10
15mm cement plaster of mix, 1:3 (1 cement : 3 fine sand) finished with a
floating coat of neat cement 2 kg/sqm including mixing water proofing
material in separately).proportion recommended by manufacturer over roof
at all heights including cost and conveyance of all materials, labour sqm
charges, scaffolding, sundries etc complete as directed by the Engineer-in-
Charge at all levels. (water proofing liquid will be paid separately)
8.04
Septic tank
Long Wall 2.00 5.92 2.05 24.27
Short wall 2.00 2.30 2.05 9.43
Inner wall 2.00 2.30 2.05 9.43
Inlet & outlet 4.00 2.10 1.10 9.24
Providing and fixing PVC pipes includings jointing of pipes with one step
pvc solvent cement, trenching , refilling & testing of joints complete as per
9.12 direction of Engineer in Charge - external works
Sl.No Code Description of Items Unit Quantity Rate (Rs) Amount (Rs)
176.58
Grand total 176.58
1.06.02 2.7.1 Ordinary rock
2.7.1 Rate as per DSR Item no 2.7.1 221.05
cost index 1.40
309.91
Grand total 309.91
5.33.1 Rate as per item Number5.33.1 of SH: (A) cum 5.65 9037.92 51064.25
5.34.1 Providing M-35 grade concrete instead of M-25 grade BMC/
RMC. (Note : Cement content considered in M-35 is @ 350 cum 5.65 97.44 550.53
kg/ cum)
Reinforced Cement Concrete
7183 Bentonite tonne 0.33 4346.2 1434.25
9999 Sundries - MACHINERY: L.S 317.43 2.42546 769.91
24 Hire and running charges of hydraulic piling with power unit
Day 0.75 47668 35751.00
etc. including complete accessories and shifting at site
25 Hire and running charges of light crane Day 0.06 3505 210.30
26 Hire and running charges of bentonite pump Day 0.38 5888.4 2237.59
17 Hire and running charges of tipper Day 0.3 2523.6 757.08
18 Hire and running charges of loader Day 0.3 8412 2523.60
LABOUR:
Work supervisor
kg
4.12 Rate as per DSR Item no 4.12 47.95
cost index 1.40
67.23
Grand total 67.23
128.84
Grand total 128.84
3.08 Add for using extra cement in the items of design mix over
and above the specified cement content there in. cum
5.35 Rate as per DSR Item no 5.35 672.75
cost index 1.40
943.20
Grand total 943.20
(SH: - 4.0 - MASONRY WORK)
4.02 Solid block masonry using pre cast solid blocks (Factory
made) M-10 grade(mix 1:3:6)of size 30x20x20cm or nearest
available size confirming to IS 2185 part I of 1979 for
foundation and plinth with thickness 20cm and above in: CM
1:6 ( 1 cement : 6 coarse sand ) etc complete and approved
quality including scaffolding, raking out of joints,curing, cost
and conveyance of all materials,labour, lead, lift, etc.
complete as directed by Engineer-in-Charge.
4.04 Solid block masonry using pre cast solid blocks ( Factory
made) M-10 grade(mix 1:3:6) of size 30x20x20cm or nearest
available size confirming to IS 2185 Part I of 1979 for super
structure up to floor two level thickness 20cm and above in:
CM 1:6 ( 1 cement : 6 coarse sand) etc complete including
scaffolding, raking out of joints,curing, cost and conveyance
of all materials,labour, lead, lift, etc. complete as directed by
Engineer-in-Charge.
4.05 Solid block masonry using pre cast solid blocks (Factory cum
made) M-10 grade(mix 1:3:6) of size 30x20x20cm or nearest
available size confirming to IS 2185 part I of 1979 for super
structure above floor two level upto floor five level thickness
20cm and above in : CM 1:6 ( 1 cement : 6 coarse sand
sand) etc complete including scaffolding, raking out of
joints,curing, cost and conveyance of all materials,labour,
lead, lift, etc. complete as directed by Engineer-in-Charge.
4.09 Extra for providing and placing in position 2 Nos 6mm dia.
M.S. bars at every third course of half brick masonry including
cost and conveyance of MS bars etc complete as directed by
Engineer-in-Charge sqm
6.15 Rate as per DSR Item no 6.15 56.85
cost index 1.40
79.70
Grand total 79.70
4.12 50.7.1.1 Providing and constructing Dry rubble work with hardstone
uncoursed for foundations,retaining walls etc including filling
the joints /hollows with suitable sizes of split stones,filling the
joints clearly, cost and conveyance of all materials, cost of
bond stone (should be provided at every 0.5 sqm of face
area) , lead, lift etc.complete as directed by Engineer-in-
Charge. cum
Details of cost for one cum.
1157 Stone for masonry work cum 1.05 1,212.73 1,273.37
1154 Through and bond stone size 24 x 24 x 39cm 100 nos 7 1,766.52 123.66
2215 Carriage of Soling stone & masonry stone cum 1.21 171.16 207.10
125 Mason (for plain stone work) 2nd class Day 1.07 628.096 672.06
114 Beldar Day 1.07 515.936 552.05
115 Coolie Day 0.71 515.936 366.31
101 Bhisti Day 0.09 570.614 51.36
9999 Sundries- L.S 45.76 2.42546 110.99
9999 Sundries- L.S 4.42 2.42546 10.72
TOTAL 3,367.62
Add Water Charges @ 1% 33.68
TOTAL 3,401.29
Add CPOH @ 15% 510.19
Cost of 1.0 cum 3,911.49
Cost per cum 3,911.49
Say 3,911.49
5.01 Providing and fixing powder coated aluminium work for doors
,windows& partitions with extruded built up standard tubular
sections/appropriate Z sections & other sections of approved
make confirming to IS:733 & IS:1285 fixed with rawl plugs &
screws or with fixing clips including necessary filling up of
gaps at junctions,at top,bottom & sides with required
PVC/neoprene felt etc.Aluminium sections shall be
smooth,rust free,straight,mitred & jointed mechanically where
ever required including cleat angle,aluminium snap beading
for glazing/panelling,cp brass/stainless steel screws,removing
the stickers clearly all complete as per architectutral drawings
& directions of Engineer-in-Charge at all levels.(glazing &
panelling to be paid seperately).Minimum thickness of
powder coating for powder coated Aluminium shall be 50
micron. kg
5.01.01 For fixed portion
Powder coated aluminium (minimum thickness of powder
coating 50 micron)
21.1.1.2 Rate as per DSR Item no 21.1.1.2 384.50
cost index 1.40
539.07
Grand total 539.07
5.01.02 For shutter of doors ,windows & ventilators including
providing and fixing hinges/pivots and making provision for
fixing of fittings,exhaust fan of required size,etc wherever
required including the cost of PVC neoprene gasket
required(fittings shall be paid for separately)
Power coated aluminium (minimum thickness of powder
coating 50 micron)
21.1.2.2 Rate as per DSR Item no 21.1.2.2 444.90
cost index 1.40
623.75
Grand total 623.75
5.10 Providing and fixing aluminium hanging floor door stopper ISI
marked anodised (anodic coating not less than grade AC 10
as per IS:1868)transparent or dyed to required colour and
shade with necessary screws etc complete as directed by the
Engineer-in -Charge at all levels. no
Single rubber stopper
5.11 Providing and fixing bright finished brass handles with screws no
etc.complete: 125mm
9.81.1 Rate as per DSR Item no 9.81.1 171.20
Cost Index 1.40
240.02
Grand total 240.02
5.12 50.9.15.1 Supplying and fixing 200 mm Aluminium aldrop including cost
and conveyance of all materials,labour charges ,lead,lift etc.
complete as directed by the Engineer-in-Charge at all levels.
no
Details of cost for 10 no.
MATERIALS:
MR18 200 mm Aluminium aldrop each 10 145 1450.00
9999 Sundries-Carriage of material and fixing charges L.S 10 1.73 17.30
TOTAL 1467.30
Add Water Charges @ 1% 14.67
TOTAL 1481.97
Add CPOH @ 15% 222.30
Cost of 10.0 no 1704.27
Cost of each 170.43
Say 170.43
5.15 9.5 Providing and fixing panelled or panelled and glazed shutters
for doors, windows and clerestory windows including ISI
marked stainless steel butt hinges(100 x 60 x 6.5mm IS :
12817 marked ) with necessary screws excludings panelling
which be paid for separately.
sqm
9.5.1 Second class teak wood
35 mm thick shutters
9.5.1.1 Rate as per DSR Item no 9.5.1.1 2548.15
5.18 DSR 9.11.1 Extra for providing heavy sheet float glass panes instead of sqm
ordinary float glass in glazed doors, windows and clerestory
window shutters. (Area of opening for glass panes excluding
portion inside rebate shall be measured)
5.5 mm thick instead of 4 mm thick.
Rate as per DSR Item no 9.11.1 236.95
cost index 1.40
332.20
Grand Total 332.20
5.21 Providing and fixing bright finished brass tower bolts (barrel
type) with necessary screws etc. complete as directed by the
no
Engineer-in-charge at all levels.
150 x 10 mm
9.74.3 Rate as per DSR Item no 9.74.3 193.45
cost index 1.40
271.22
Grand total 271.22
5.26 Providing and fixing cupboard shutters 25 mm thick, with Pre- sqm
laminated flat pressed three layer particle board or graded
wood particle board IS: 12823 marked, exterior grade (Grade
l Type ll), having one side decorative lamination and other
side balancing lamination, including IInd class teak wood
lipping of 25 mm wide x12 mm thick with necessary screws
and bright finished stainless steel piano hinges, complete as
per direction of the Engineer-in-Charge
9.13 Rate as per DSR Item no 9.129 1590.80
cost index 1.40
2230.30
Grand total 2230.30
6.03 Steel work in built up tubular sections YST 310 grade as per kg
IS: 4923 including cutting, bending, hoisting, fixing in position,
welded and bolted including special shaped washers etc.
complete with electric resistance or induction butt welded
tubes including painting with two coats of approved make and
colour synthetic enamel paint over two coats of approved
make anticorrossive yellow zinc chromate primer, closing all
the open ends properly with same material cost and
conveyance of all materials, labour, etc., complete as
directed by the Engineer-in-Charge at all levels.
6.08 Providing and fixing S.S fan clamp of 16mm dia in RCC
slabs, beams including cost and conveyance of all
materials,labour charges etc complete as directed by the
Engineer-in-Charge at all levels.
6.10 19.18 DSR Providing and fixing CI manhole cover with frame 560 mm
diameter C.I. cover (heavy duty) the weight of the cover to be
not less than 108 kg in concrete slab over
manholes/Inspection Chambers/Drains, including cost and
conveyance of all materials, all labour charges, all taxes,lead,
lift, sundries, etc., complete. as directed by the Engineer- in-
Charge
19.18.3 Rate as per DSR Item no 19.18.3 5891.20
cost index 1.40
8259.46
Grand total 8259.46
6.11 Providing and fixing stainless steel ( Grade 304) railing made
of Hollow tubes, channels, plates etc., including welding,
grinding, buffing, polishing and making curvature (wherever
required) and fitting the same with necessary stainless steel
nuts and bolts complete, i/c fixing the railing with necessary
accessories & stainless steel dash fasteners , stainless steel
bolts etc., of required size, on the top of the floor or the side
of waist slab with suitable arrangement as per approval of
Engineer-in-charge, (for payment purpose only weight of
stainless steel members shall be considered excluding fixing
accessories such as nuts, bolts, fasteners etc.).
10.28 Rate as per DSR Item no 10.28 472.40
cost index 1.40
662.30
Grand total 662.30
7.04 Providing and fixing 1st quality ceramic glazed wall tiles
conforming to IS : 15622(thickness to be specified by the
manufacture of approved make in all colours , shades except
burgundy, bottle green, black of any size as approved by
Engineer-in- charge in skirting, risers of steps and dados over
12mm thick bed of cement Mortar 1:3 (1 cement: 3 coarse
sand) and jointing with grey cement slurry@ 3.3kg per sqm
including pointing in white cement mixed with pigment of
matching shade complete.
11.36 Rate as per DSR Item no 11.36 744.80
cost index 1.40
1044.21
Grand total 1044.21
7.07 Providing and fixing 18 mm thick gang saw cut, mirror sqm
polished, premoulded and prepolished, machine cut for
kitchen platforms, vanity counters, window sills, facias and
similar locations of required size, approved shade, colour and
texture laid over 20 mm thick base cement mortar 1:4 (1
cement : 4 coarse sand), joints treated with white cement,
mixed with matching pigment, epoxy touch ups, including
rubbing, curing, moulding and polishing to edges to give high
gloss finish etc. complete at all levels: Granite of any colour
and shade
8.2.2.2 Rate as per DSR Item no 8.2.2.2 3113.30
7.09 Extra for providing opening of required size & shape for wash
basins/ kitchen sink in kitchen platform, vanity counters and
similar location in marble/granite work including providing
necessary holes for pillar taps etc. including rubbing and
polishing of cut edges etc. complete as directed by the
Engineer-in-Charge at all levels.
8.5 Rate as per DSR Item no 8.5 427.95
cost index 1.40
599.99
Grand Total 599.99
7.10 11.26 Kota stone slab flooring over 20 mm (average) thick base laid
over and jointed with grey cement slurry mixed with pigment
to match the shade of the slab, including rubbing and
polishing complete with base of cement mortar 1 : 4 (1
cement : 4 coarse sand) :
25mm thick.
11.26.1 Rate as per DSR Item no 11.26.1 1158.10
cost index 1.40
1623.66
Grand Total 1623.66
7.11 11.27 Kota stone slabs 20 mm thick in risers of steps, skirting, dado
and pillars laid on 12 mm (average) thick cement mortar 1:3
(1 cement: 3 coarse sand) and jointed with grey cement
slurry mixed with pigment to match the shade of the slabs,
including rubbing and polishing complete.
7.13 Providing and fixing PVC tile edging to match the wall tiles m
and finishing as directed by the Engineer-in-Charge at all
levels.
Rate as per quotation m 32.00
labour charge m 10.00
Total 42.00
Add 1% for water charges 0.42
42.42
add 15% CP 4.20
46.62
\\datalibrary1\2017-18 Open\School Reports- Modified\11. Pandikad\Pandikkad-GHS-11-8-2017\Rate (Pa No. 1- 48) 20
Sl.No Code Description of Items Unit Quantity Rate (Rs) Amount (Rs)
8.01 13.16 DSR 6 mm cement plaster to ceiling of mix 1:3 (1 Cement : 3 fine
sand) including cost and conveyance of all materials, labour
charges, scaffolding, sundries etc complete as directed by
the Engineer-in-Charge at all levels.
sqm
1:3 (1 Cement : 3 fine sand)
13.16.1 Rate as per DSR Item no 13.16.1 143.80
cost index 1.40
201.61
Grand total 201.61
8.02 13.1 DSR 12mm cement plaster of mix 1:4 (1 cement : 4 fine
sand)including cost and conveyance of all materials, labour
charges, scaffolding, sundries etc complete as directed by
the Engineer-in-Charge at all levels. sqm
13.1.1 Rate as per DSR Item no 13.1.1 172.95
cost index 1.40
242.48
Grand total 242.48
8.03 13.2 DSR 15mm cement plaster of mix 1:4 (1 cement : 4 fine
sand)including cost and conveyance of all materials, labour
charges, scaffolding, sundries etc complete as directed by
the Engineer-in-Charge at all levels. sqm
1:4 (1 cement : 4 fine sand)
13.2.1 Rate as per DSR Item no 13.2.1 200.25
cost index 1.40
280.75
Grand total 280.75
8.04 13.10 DSR 15mm cement plaster of mix, 1:3 (1 cement : 3 fine sand)
finished with a floating coat of neat cement 2 kg/sqm
including mixing water proofing material in
separately).proportion recommended by manufacturer over
roof at all heights including cost and conveyance of all
materials, labour charges, scaffolding, sundries etc complete
as directed by the Engineer-in-Charge at all levels. (water
proofing liquid will be paid separately) sqm
13.10 Rate as per DSR Item no 13.10 265.95
cost index 1.40
372.86
Grand total 372.86
8.05 13.22 DSR Extra for plastering exterior walls of height more than 10m
from GL for every additional height of 3m or part thereof
including cost and conveyance of all materials, labour
charges, scaffolding, sundries etc complete as directed by
the Engineer-in-Charge at all levels.
13.22 Rate as per DSR Item no 13.22 40.65
cost index 1.40
56.99
Grand total 56.99
8.05 13.43 DSR Applying one coat of cement primer of approved brand and
manufacture on wall surface sqm
13.43.1 Rate as per DSR Item no 13.43.1 36.95
cost index 1.40
8.06 13.47.1 DSRFinishing walls with Premium Acrylic Smooth exterior paint
with Silicone additives of required shade for new work (Two
or more coats applied @ 1.43 ltr/ 10 sqm over and including
priming coat of exterior primer applied @ 2.20 kg/ 10 sqm).
including cost and conveyance of all materials, labour
charges, scaffoldings etc complete as directed by the
Engineer-in-Charge at all levels.
sqm
13.47.1 Rate as per DSR Item no 13.47.1 96.80
cost index 1.40
135.71
Grand total 135.71
8.07 13.44 Providing and applying water proof cement paint of approved
brand and colour for new work (Two or more coats applied @
3.84 kg/10 sqm)on walls after scraping and cleaning the
surface including cost and coveyance of all materials,labour
charges,hire charges for scaffolding etc.complete at all
levels sqm
New work(Two or more coats applied @ 3.84 kg/10 sqm).
8.07 13.60DSR Painting the inside walls with acrylic emulsion paint of
approved brand and manufacture to give an even shade two
or more coats on new work to smooth even finish on ceiling
and walls including cost and conveyance of all materials to
site, labour charges, hire charges for scaffolding, etc as
directed by Engineer-in-Charge at all levels
8.10 Painting with synthetic enamel paint of approved brand and sqm
manufacture of required colour to give an even shade two or
more coats on new work over an under coat of suitable shade
with ordinary paint of approved brand and manufacture
including cost and conveyance of all materials, labour
charges, scaffolding, sundries etc complete as directed by
the Engineer in charge at all levels.
9.01 Providing and fixing white vitreous china pedestal type water
closet (European type) with seat and lid, 10 litre low level
white vitreous china flushing cistern & C.P. flush bend with
fittings & C.I. brackets, 40 mm flush bend, overflow
arrangement with specials of standard make and mosquito
proof coupling of approved municipal design complete,
including painting of fittings and brackets, cutting and making
good the walls and floors wherever required :W.C. pan with
ISI marked white solid plastic seat and lid.
no
17.3.1 Rate as per DSR Item no 17.3.1 4593.75
\\datalibrary1\2017-18 Open\School Reports- Modified\11. Pandikad\Pandikkad-GHS-11-8-2017\Rate (Pa No. 1- 48) 23
Sl.No Code Description of Items Unit Quantity Rate (Rs) Amount (Rs)
9.02 Providing and fixing water closet squatting pan (Indian type
W.C. pan ) with 100 mm sand cast Iron P or S trap, 10 litre
low level white P.V.C. flushing cistern, including flush pipe,
with manually controlled device (handle lever) conforming to
IS : 7231, with all fittings and fixtures complete, including
cutting and making good the walls and floors wherever
required: White Vitreous china Orissa pattern W.C. pan of
size 580x440 mm with integral type foot rests
no
17.1.1 Rate as per DSR Item no 17.1.1 3494.20
cost index 1.40
4898.87
Grand total 4898.87
9.03 17.7 DSR Providing and fixing coloured vitreous china under counter
round wash basin 440 mm dia or nearest size of approved
make including one CP brass pillar cock 15 mm NB including
connecting pipes with all fittings 32 mm dia rubber plugs 32
mm dia CP brass waste coupling, 32 mm dia CP brass bottle
trap, 15mm angle valve, etc. complete as directed by the
Engineer-in-charge. each
17.7.2 Details of cost for one no.
MATERIALS
MR vitreous china countertop wash basin each 1.00 1254.000 1254.000
MR 15 mm C P brass pillar taps no 1.00 1357.000 1357.00
MR 32mm diaCP brass bottle trap no 1.00 996.150 996.15
MR 15mm diaCP brass angle valve no 1.00 316.000 316.00
1951 32 mm diameter CP brass waste of standard pattern each 1.00 112.160 112.160
1309 C I/M S brackets pair 1.00 91.130 91.130
9999 Red lead, white lead and gasket Ls 16.12 2.425 39.098
9999 Cement, sand and grit etc. Ls 13.39 2.425 32.477
9999 Painting of brackets, fittings etc. Ls 26.91 2.425 65.269
9999 Carriage of materials Ls 13.52 2.425 32.792
LABOUR
0116 Fitter 1st class day 0.30 682.774 204.832
0123 Mason 1st class day 0.33 682.774 225.315
0114 Beldar day 0.63 515.936 325.040
TOTAL 5051.264
Add 1% for water charges 50.513
TOTAL 5101.777
Add 15% for contractor's profit and overheads 765.266
Cost for one no. 5867.043
Say 5867.050
Grand total 5867.050
9.04 17.10 DSR Providing and fixing Stainless Steel A ISI 304 (18/8) kitchen
sink as per IS: 13983 with C.I. brackets and stainless steel
plug 40 mm, including painting of fittings and brackets,
cutting and making good the walls wherever required :Kitchen
sink with drain board :510x1040 mm bowl depth 250 mm
no
17.10.1.1 Rate as per DSR Item no 17.10.1.1 4120.80
cost index 1.40
5777.36
Grand total 5777.36
9.07 Providing and fixing frameless mirror, with all four edges
machine polished and back side protected with safety film
and 4 mm thick Plywood backing and fixed on walls with
mirror screws. The rate includes lifting, cutting etc. as per
design and drawing.
MR Mirror sqm 1.000 3200.000 3200.00
Fixing charge 150.00
Add for water charges @ 1% 32.00
3382.00
9.08 18.51 DSR Providing and fixing CP brass long body bib cock of
approved quality conforming to IS standards and weighing
not less than 690 gms including cost and conveyance of all
materials, labour charges, sundries etc complete as directed
by the Engineer-in-Charge at all levels
no
9.09 50.17.1.5 Providing and fixing CP brass health faucets with 8mm dia 1
meter long flexible tube and wall hook with all fittings and
fixtures including angle valve etc complete inlcuding cutting
and making good the walls and floors wherever required
including cost and conveyance of all materials, labour
charges, sundries etc complete as directed by the Engineer-
in-Charge at all levels. no
Details of cost for 10.00 Nos.
MATERIALS:
MR37 Health faucet superior quality each 10 1100 11000.00
9999 Sundries- L.S 10 2.42546 24.25
TOTAL 11024.25
Add Water Charges @ 1% 110.24
TOTAL 11134.50
Add CPOH @ 15% 1670.17
Cost of 10.0 no 12804.67
Cost of each 1280.47
Say 1280.47
9.10 Providing and fixing PVC pipes, fittings including fixing the
pipe with clamps at 1.00 m spacing . This includes jointing of
pipes & fittings with one step PVC solvent cement and testing
of joints complete as per direction of Engineer-in-Charge -
Internal work- Exposed on wall
Say 328.64
9.11 Providing and fixing PVC pipes, fittings including fixing the
pipe with clamps at 1.00 m spacing. This includes jointing of
pipes & fittings with one step PVC solvent cement and testing
of joints complete as per direction of Engineer-in-Charge.
50.18.8.9. Concealed work, including cutting chases and making good
1 the wall etc.
MR54 PVC pipe 110 mm outer dia 6kgf/cm2 metre 10.5 211 2215.5
(Adding 5% for wastage, etc)
Making chases upto 12.5x12.5 cm in walls and making good
the same
50.18.78 Rate as per item Number50.18.78 of SH: (A) metre 10 160.65 1606.5
Approved Observed data
116 Fitter(grade1) Day 0.33 682.774 225.31542
117 Assistant Fitter or 2nd class fitter Day 0.66 628.096 414.54336
114 Beldar Day 0.66 515.936 340.51776
4802.37654
Add Water Charges @ 1% except on A ie 31.9587654
on ( 4521.27-1606.5=2914.77 )
TOTAL 4834.335305
Add CPOH @ 15% except on A ie 484.1752958
on ( 4550.42-1606.5=2943.92 )
Cost of 10.0 metre 5318.510601
Cost of 1 metre 531.8510601
Say 531.85
MR52 PVC pipe 75 mm outer dia 6kgf/cm2 metre 10.5 129 1354.5
(Adding 5% for wastage, etc)
Making chases upto 12.5x12.5cm in walls and making good
the same
50.18.78 Rate as per item Number50.18.78 of SH: (A) metre 10 160.65 1606.5
Approved Observed data
116 Fitter(grade1) Day 0.33 682.774 225.31542
117 Assistant Fitter or 2nd class fitter Day 0.66 628.096 414.54336
114 Beldar Day 0.66 515.936 340.51776
3941.37654
Add Water Charges @ 1% except on A ie 23.3487654
on ( 3660.27-1606.5=2053.77 )
TOTAL 3964.725305
Add CPOH @ 15% except on A ie 353.7337958
on ( 3680.81-1606.5=2074.31 )
Cost of 10.0 metre 4318.459101
Cost of 1 metre 431.8459101
Say 431.85
9.13 50.18.9.21 Providing and fixing PVC vent cowl to pipe already fixed as
.7 directed by Engineer-in-Charge at all levels.
MATERIALS
MR 15 mm C P brass pillar taps no 1.00 1357.000 1357.00
MR 32mm diaCP brass bottle trap no 1.00 996.150 996.15
MR 15mm diaCP brass angle valve no 1.00 316.000 316.00
1951 32 mm diameter CP brass waste of standard pattern each 1.00 112.160 112.16
9999 Red lead, white lead and gasket Ls 16.12 2.425 39.10
9999 Cement, sand and grit etc. Ls 13.39 2.425 32.48
9999 Painting of brackets, fittings etc. Ls 26.91 2.425 65.27
9999 Carriage of materials Ls 13.52 2.425 32.79
LABOUR
0116 Fitter 1st class day 0.30 682.774 204.83
0123 Mason 1st class day 0.33 682.774 225.32
0114 Beldar day 0.63 515.936 325.04
TOTAL 3706.13
Add 1% for water charges 37.06
TOTAL 3743.20
Add 15% for contractor's profit and overheads 561.48
Cost for one no. 4304.67
Say 4304.68
Hinged rail
9999 Carriage of material and fixing changes LS 20.28 2.425 49.19
TOTAL 49.19
Add 1% for water charges 0.49
TOTAL 49.68
Add 15% for contractor's profit and overheads 7.45
Cost for 1 No. 57.13
Say 57.14
Grab bars,
9999 Carriage of material and fixing changes LS 20.28 2.425 49.19
TOTAL 49.19
Add 1% for water charges 0.49
TOTAL 49.68
Add 15% for contractor's profit and overheads 7.45
Cost for 1 No. 57.13
Say 57.14
Cost for 5 nos of Grab bars 285.70
10.01.02 In all kinds of soil for pipes, cables etc exceeding 80mm dia
but notexceeding 300mm dia.
2.10.1.2 Rate as per DSR Item no 2.10.1.2 225.45
cost index 1.40
316.08
Grand total 316.08
10.01.03 Pipes, cables etc. exceeding 300mm dia but not exceeding
600mm
405.25
Grand total 405.25
10.06 19.4 DSR Supplying approved make PVC gully trap of size 160 x
110mm and CI grating 150mmx150mm size and light duty C.I
cover with frames 300mmx300mm size(inside) the weight of
cover to be not less than4.5kg and frame to be not less
than2.7kg (CI MH cover and frame as per IS:1726) single
sealed of size conveying to size the above mentioned items
and constructing 30cmx30cm internal size gully trap chamber
and depth upto 60cm,115 thk brick wall in CM 1:6 on a
foundation of PCC 1:4:8.100mm thick plastering inside with
CM 1:3,12mm thk with a neat cement flushing coat and
conveying to site,cleaning ,installing and testing approved
make PVC gully trap with 160mm
outlet(Fabricated),surrounding with CC 1:1.5:3,
150x150mmm,top with CI grating above the PVC gulley trap
and light duty CI cover and frame over the chamber including
cost of all materials, etc complete as per approved drawing
and as directed by Engineer-in- Charge. each
19.4.3 180x150 mm size P type
19.4.3.1 With FPS bricks of class designation 75
Rate as per DSR item no.19.4.3.1
Details of cost of one gully trap
MR 1904 160x110 mm gully trap 1.000 462.300
each 462.30
1367 C I grating 150x150 mm each 1.000 35.050 35.05
1352 C I cover with frame 300x300 mm inside each 1.000 420.600 420.60
9999 Carriage of materials LS 4.500 2.425 10.91
Cement concrete 1:5:10 (1cement: 5 fine sand: 10 graded
stone agreegate 40 mm nominal size)
0.68x0.68x0.10 m = 0.046 cum
Concrete around trap
0.30x0.30x0.675 m = 0.061 cum = 0.107 cum
Deduct: 0.55/3x(0.09+0.032+(0.09x0.032)1/2)=0.008 cum
10.10.01 65mm
10.10.02 80mm
10.10.03 100mm
cost of wall casting pipe no 1.00 2932.65 2932.65
labour
Beldar no 1.00 515.936 515.94
Total 3448.59
Add 1% for water charges 34.49
TOTAL 3483.07
add 15% cp 522.46
Grand total 4005.53
10.10.04 150mm
cost of wall casting pipe no 1.00 4713.45 4713.45
labour
Beldar no 1.00 515.936 515.94
Total 5229.39
Add 1% for water charges 52.29
TOTAL 5281.68
add 15% cp 792.25
Grand total 6073.93
Total 3133.59
Add 1% for water charges 31.34
TOTAL 3164.92
add 15% cp 474.74
Grand total 3639.66
10.15 Providing and fixing enclosed type water meter (bulk type) no
50mm dia conforming to IS : 2373 and tested by Municipal
Board complete with bolts, nuts, rubber insertions etc. (The
tail pieces if required will be paid separately) including cost
and conveyance of all materials, labour etc. complete and as
directed by Engineer-in-Charge
Material:
MR 50 mm Water meter each 1 6087.965 6087.97
9999 Testing charges l.s. 130 2.43 315.31
Total 7136.02
Add water charges @ 1% except on A 71.36
Total 7207.38
Add CPOH @ 15% except on A 1081.11
Cost of each 8288.48
Say 8288.48
10.16 Providing and fixing C.I. basket type dirt box strainer 50mm no
dia for bulk type water meter with nuts, bolts, rubber
insertions etc. complete conforming to IS : 2373 : including
cost and conveyance of all materials, labour etc. complete
and as directed by Engineer-in-Charge
50 mm Water meter and dirt box strainer (including testing
MR charges) each 1 5301.348 5301.35
9999 Carriage of water meter l.s. 25 2.43 60.64
9999 Labour for laying water meter l.s. 30 2.43 72.76
Providing flanged joints to double acting air valves with bolts,
nuts and rubber insertions etc
18.30.1 Rate as per item number 18.30.1 of SH: Water supply each 2 168.78 337.56
Total 5772.31
Add water charges @ 1% 57.72
Total 5830.03
Add CPOH @ 15% 874.50
Cost of each 6704.54
Say 6704.54
Say 24669.36
Grand total 24669.36
11.03 22.4 DSR Providing and placing in position suitable PVC water stops
conforming to IS :12200 for construction / expansion joints
between two RCC members and fixed to the reinforcement
with binding wire before pouring concrete etc., complete
including all cost and conveyance of all materials, labour
charges etc. complete as directed by Engineer - in - Charge
at all levels : Serrated with central bulb(225mm wide, 8-11
mm thick).
m
Serrated with central bulb (225mm wide, 8-11 mm thick).
11.04 19.6 DSR Providing and laying non-pressure NP2 class (light duty) RCC
pipes with collars jointed with stiff mixture of cement mortar in
the proportion of 1:2 (1 cement : 2 fine sand) including testing
of joints etc. complete. m
150 mm dia. RCC Pipe
11.04.01 19.6.2 Rate as per DSR Item no 19.6.2 356.70
cost index 1.40
500.09
Grand total 500.10
11.06 Providing and laying at or near ground level factory made cum
kerb stone of M-25 grade cement concrete in position to the
required line, level and curvature, jointed with cement mortar
1:3 (1 cement: 3 coarse sand), including making joints with or
without grooves (thickness of joints except at sharp curve
shall not to more than 5mm), including making drainage
opening wherever required complete etc. as per direction of
Engineer-in-charge (length of finished kerb edging shall be
measured for payment). (Precast C.C. kerb stone shall be
approved by Engineer-in-charge).
11.08 Providing and fixing to the inlet mouth of rain water pipe cast
iron grating 15cm diameter and weighing not less than 440
grams. no
12.44 Rate as per DSR Item no 12.44 40.90
cost index 1.40
57.34
Grand total 57.34
12.02 Demolishing R.C.C work, including stacking of steel bars and cum
disposal of unserviceable material within 50 metres lead as
per direction of Engineer-in-Charge
15.3 Rate as per DSR Item no 15.3 1454.55
cost index 1.40
2039.28
Grand Total 2039.28
In cement mortar
15.9.2 Rate as per DSR Item no 15.9.2 1005.70
cost index 1.40
1409.99
Grand Total 1410.00
12.09 Dismantling tile work in floors and roofs laid in cement mortar sqm
including stacking material within 50 metre lead:For thickenss
of tiles above 10mm and upto 25mm
15.23.1 Rate as per DSR Item no 15.23.1 31.55
cost index 1.40
44.23
Grand Total 44.24
12.10 Dismantling roofing including ridges, hips valleys and gutters sqm
etc., and stacking the material within 50 metres lead of:G.S.
Sheet
15.28.1 Rate as per DSR Item no 15.28.1 70.10
cost index 1.40
98.28
Grand Total 98.29
12.12 Laying old cement cocrete interlocking paver blocks of any sqm
design/ shape laid in required line, level, curvature, colour
and pattern over and including 50 mm thick compacted bed
of coarse sand, filling the joints with fine sand etc. all
complete as per the direction of Engineer in-charge. (Old CC
paver blocks shall be supplied by the department free of
cost).
16.84 Rate as per DSR Item no 16.84 209.20
cost index 1.40
293.30
Grand total 293.30
Annexure 4
Geo-technical survey
81
Detailed Project Report – GHSS Pandikkad
Annexure 5
Topographical survey
82
Detailed Project Report – GHSS Pandikkad
Annexure 6
Minutes of Meeting
83
COST - BENEFIT SHEET (QUICK SHEET)
NET PRESENT VALUE (NPV) of COSTS 455
NET PRESENT VALUE (NPV) of BENEFITS 533
COST BENEFIT RATIO (B/C) 1.172
NAME OF PROJECT PROJECT
DEPARTMENT: Dept. of General Education Dept. of General Education Protection of Public Education Mission
SPV: NAME: ID:
COST ANALYSIS
Period for which costs will be incurred: (in years from commencement of incurring costs) 6
Remarks: 1. If costs will be incurred beyond five years OR for an infinite or longer time horizon, enter an approximate figure for the other years as percentage of cost for the first year for each item.
2. Include Recurring costs like Annual Maintenance Costs if known.
3. If Units and Rates are not known with reasonable degree of accuracy, please enter the Units as '1' and then the total Amount in the Rate column
4. Group activities into not more than 10 sets of COSTS for simplicity of computation.
5. Enter value of year from the picklist given by the side of the cell.
Year 1 = 2017 Year 2 = 2018 Year 3 = 2019 Year 4 = 2020 Year 5 = 2021 Year 6 and beyond
(Enter as
approximate
Rate (Rs. Rate (Rs. Rate (Rs. Rate (Rs. percentage of cost
Item Units Description/Remarks Rate (Rs. Lakh/Unit) Amount Units Description/Remarks Lakh/Un Amount Units Description/Remarks Lakh/Un Amount Units Description/Remarks Lakh/Un Amount Units Description/Remarks Lakh/Un Amount for that item to
it) it) it) it) the average cost
incurred in the
FIRST five years)
BENEFIT ANALYSIS
Period for which BENEFITS will be derived: (in years from first year of start of getting benefits of the project) 10
Remarks: 1. If benefits will be derived beyond five years OR for an infinite or longer time horizon, enter an approximate figure for the other years as percentage of benefits for the first year for each item
2. If Units and Rates are not known with reasonable degree of accuracy, please enter the Units as '1' and then the total Amount in the Rate column
3. Group activities into not more than 10 sets of BENEFITS for simplicity of computation
4. Enter value of year from the picklist given by the side of the cell.
Year 1 = 2019 Year 2 = 2020 Year 3 = 2021 Year 4 = 2022 Year 5 = 2023 Year 6 and beyond
(Enter as
approximate
percentage of
benefit for that
Rate (Rs. Rate (Rs. Rate (Rs. Rate (Rs. item to the benefit
Lakh/Un Lakh/Un Lakh/Un Lakh/Un derived in the
Item Units Description/Remarks Rate (Rs. Lakh/Unit) Amount Units Description/Remarks it) Amount Units Description/Remarks it) Amount Units Description/Remarks it) Amount Units Description/Remarks it) Amount FIRST five years)
Value of increased revenue generation by improved human 50 50 Value of increased revenue generation by improved 60 60 Value of increased revenue generation by improved 100 100 Value of increased revenue generation by improved 150 150 Value of increased revenue generation by improved 200 200 100
1 1 capital 1 human capital 1 human capital 1 human capital 1 human capital
2 1 Gain on opportunity cost 2 2 1 Gain on opportunity cost 2 2 1 Gain on opportunity cost 2 2 1 Gain on opportunity cost 2 2 1 Gain on opportunity cost 2 2 100
3 1 Savings in health cost and development of child 2 2 1 Savings in health cost and development of child 2 2 1 Savings in health cost and development of child 2 2 1 Savings in health cost and development of child 2 2 1 Savings in health cost and development of child 2 2 100
4 1 Increased Savings in Society 1 1 1 Increased Savings in Society 1 1 1 Increased Savings in Society 1 1 1 Increased Savings in Society 1 1 1 Increased Savings in Society 1 1 100
5 1 Additional revenue from Infrastructure by Public Use 10 10 1 Additional revenue from Infrastructure by Public Use 10 10 1 Additional revenue from Infrastructure by Public Use 10 10 1 Additional revenue from Infrastructure by Public Use 10 10 1 Additional revenue from Infrastructure by Public Use 10 10 100
6 0 0 0 0 0
7 0 0 0 0 0
8 0 0 0 0 0
9 0 0 0 0 0
10 0 0 0 0 0
TOTAL FOR YEAR 1 = 65 TOTAL FOR YEAR 2 = 75 TOTAL FOR YEAR 3 = 115 TOTAL FOR YEAR 4 = 165 TOTAL FOR YEAR 5 = 215
0$
%*(0'4/
,
10'(2" ,"$
2-"// %++")"
,#'( 3
%.")"+$("
(8(.+,
"5'
!!1)58$3("(&+01.1*: &6/64,0(44$3-
-+.$ 0'6453,$.45$5(
(8(.+, ; 0',$+10(
+(00$,
"5'
45 $,0 1$'#!#
!" 1$' "$/%$3$/ !$0$513,6/+(00$, ;
0',$
+10(
"+,367$0$05+$263$/
"5'
164(1 "
(.+$7(0$3'(0 18',$3
"+,367$0$05+$263$/
(3$.$0',$
+10($9