Review of Lecture # 1
Introduction to Quantity-Survey & Estimation
Example #1 Brick Wall with Foundation - its quantity survey and its estimation
Discussion on Assignment#1
Wall ½ 1 1½ 2 2½ 3
Brick
Wall ½ 1 1½ 2 2½ 3
Brick
Precaution:
Junctions of wall at the corners and at the meeting points of walls require
special attention.
General Specifications:
1. Foundation concrete shall be of lime concrete
3. D.P.C - 2.5 cm cement concrete [c.c] (1:1.5:3) with water proofing compound.
5. Wall Finishing – Inside wall 12 mm cement plastered (1:6) & white washed 3 coats.
Outside wall 12 mm cement plastered, 1:6 including 10 cm below ground level & finished
with 2 coats of color wash over 1 coat of white washing.
(Fig.1)
Quantity*Unit Rate=Amount
1. The method is to take the long walls & short or cross walls separately & to find out the center to
center length of long walls & short walls from the plan.
2. For long walls, add the center to center length one breadth of wall, which gives the length of the
wall out-to-out, multiply this length by the breadth & height to get the quantities (m3).
For finding the quantities of earthwork in excavation, for length of the trench out-to-out add to the
Adopt the same process for foundation concrete, and for each footing.
It should be noted that each footing is to be taken separately & the breadth of a particular footing is
Long wall length out-to-out = Center to center length + one breadth of wall
Short wall length in-to-in = center to center length – one breadth of wall
Summary:
In case of long wall, add one breadth & in case of short wall subtract one breadth from the center
By taking dimensions in this way, the long walls are gradually decreasing in length from
Walls which is taken first is to be treated as long wall, thought its length may be lesser, & the
Estimate the quantities of the following items of a 2-roomed building from the
given plan & section (Fig.2)
1. Earthwork in excavation in foundation