Calculations in The Main Direction: Lazareto Extension Stack Foundation Raft Slab
Calculations in The Main Direction: Lazareto Extension Stack Foundation Raft Slab
Materials
Concrete = C20/25 Design situation = Persistent & Transient
fck = 20 N/mm² уc = 1.5
fcd = αcc*fck/yc = 13.33 N/mm² αcc = 1.00
fctm = 2.210 N/mm² λ= 0.8
Ecm = 29962 N/mm² η= 1.0
εcu = 3.5 ‰
Steel = S400
fyk = 400 N/mm² уs = 1.15
fyd = fyk/ys = 347.8 N/mm²
Es = 200000 N/mm²
Slab geometry
b= 1000 mm h= 600 mm
cbottom = 75 mm ctop = 35 mm
Effective heigths
cbtm.main = 75 mm ctop.main = 35 mm
dbtm,main = 517 mm dtop,main = 557 mm
d'btm,main = 83 mm d'top,main = 43 mm
Page : 3(6)
TOP reinforcement in MAIN direction
d= 557 mm As = 1,005 mm² c= 35 mm
d' = 83 mm Asc = 1,005 mm²
Materials
Concrete = C20/25 Design situation = Persistent & Transient
fck = 20 N/mm² уc = 1.50
fcd = αcc*fck/yc = 13.33 N/mm² αcc = 1.00
fctm = 2.21 N/mm² λ= 0.80
Ecm = 29962 N/mm² η= 1.00
εcu = 3.5 ‰
Steel = S400
fyk = 400 N/mm² уs = 1.15
fyd = fyk/ys = 347.8 N/mm²
Es = 200000 N/mm²
Slab geometry
b= 1000 mm h= 600 mm
cbottom = 75 mm ctop = 35 mm
Effective heigths
cbtm.trans = 91 mm ctop.trans = 51 mm
dbtm,trans = 501 mm dtop,trans = 541 mm
d'btm,trans = 99 mm d'top,trans = 59 mm
Page : 6(6)
TOP reinforcement in TRANSVERSAL direction
d= 541 mm As = 1,005 mm² c= 51 mm
d' = 99 mm Asc = 1,005 mm²
Materials
Concrete = C20/25 Design situation = Persistent & Transient
fck = 20 N/mm² уc = 1.5
fcd = αcc*fck/yc = 13.3 N/mm² αcc = 1
Steel = S400
fyk = 400 N/mm²
fyd = fyk/ys = 347.8 N/mm²
Slab geometry
b= 1000 mm h= 600 mm
cbottom = 75 mm ctop = 35 mm
Slab reinforcement
As.btm.m = 1005.3 mm² As.btm.trans= 1,005 mm²
As.top.main = 1,005 mm² As.top.trans= 1005.3 mm²
Check for flexural shear resistance without shear reinforcement EC2 6.2.2
fck = 20 N/mm2 ρ = As/(b*dw) < 0.02
k1 = 0.15 σcp = NEd/Ac < 0.2fcd
CRd.c = 0.12 CRd.c= 0.18/yc
bw = 1000 mm k =1+(200/d)0.5 < 2.0
Point load VEd acting on top of the slab -> Bottom reinforcement used
As.btm.main = 1,005 mm² As.btm.trans= 1,005 mm²
dbtm.m = 517 mm dbtm.trans= 501 mm
ρbtm.m = 0.0019 ρbtm.t = 0.0020 ρbtm = As/(b*d) < 0.02
d= 509 mm d = (dX+dY)/2
k = 1.626839 k =1+(200/d)0.5 < 2.0
k1 = 0.1
ρl = 0.00198 ρl = (ρlX*ρlY)0.5
CRd.c = 0.12 CRd.c= 0.18/yc
VEd.down = 50 kN
a = 1018 mm a = 2*d
Rectangular loaded area Circular loaded area
c1 = 200 mm r= 100 mm
c2 = 200 mm
Point load at the center of slab (A)
uA = 7196 mm ua = 2*(C1+C2)+2*a*π uA = 7025 mm ua = 2*(r+a)*π
vEd = 0.014 N/mm² vEd = VEd/uid vEd = 0.014 N/mm² vEd = VEd/uid
vEd/vRd.c = 0.04 OK! vEd/vRd.c= 0.05 OK!
Point load VEd acting on bottom of the slab -> Top reinforcement used
As.top.main = 1,005 mm² As.top.trans= 1,005 mm²
dtop.m = 557 mm dtop.trans= 541 mm
ρtop.m = 0.0018 ρtop.t = 0.0019 ρtop = As/(b*d) < 0.02
d= 549 mm d = (dX+dY)/2
k = 1.603572 k =1+(200/d)0.5 < 2.0
k1 = 0.1
ρl = 0.00183 ρl = (ρlX*ρlY)0.5
CRd.c = 0.12 CRd.c= 0.18/yc
VEd.up = 40 kN
a = 1098 mm a = 2*d
Rectangular loaded area Circular loaded area
c1 = 200 mm r= 100 mm
c2 = 200 mm
Point load at the center of slab (A)
uA = 7699 mm ua = 2*(C1+C2)+2*a*π uA = 7527 mm ua = 2*(r+a)*π
vEd = 0.009 N/mm² vEd = VEd/uid vEd = 0.010 N/mm² vEd = VEd/uid
vEd/vRd.c = 0.03 OK! vEd/vRd.c= 0.03 OK!
Materials
Concrete = C20/25 Design situation = Persistent & Transient fck = 20.0 N/mm²
αcc = 1.00 fcd = 13.3 N/mm²
fyk = 400.0 N/mm²
Steel = S400 fyd = 347.8 N/mm²
Slab geometry Ecm = 29962 N/mm²
b= 1000 mm cbottom = 75 mm Es = 200000 N/mm²
h= 600 mm ctop = 35 mm
Results ULS
εs MRd MEd/MRd VRd.c VEd/VRd.c
>0.2% kNm kN
Btm.main 1.23% 176.2 1.47 158.2 0.65 MRd OK! εs>fyk/Es OK!
Top.main 1.35% 190.2 0.37 164.0 0.58 MRd OK! εs>fyk/Es OK!
Btm.trans 1.18% 170.6 0.56 155.9 0.49 MRd OK! εs>fyk/Es OK!
Top.trans 1.30% 184.6 0.32 161.7 0.42 MRd OK! εs>fyk/Es OK!
Results SLS
Iu Ic Mcr MEk/Mcr σc/fck σs/fyk wk
mm4 x106 mm4 x106 kNm mm
Btm.main 18645.4 1457.5 137.2 0.62 0.07 0.01 0.00 OK! Mcr>MEk no cracking!
Top.main 18645.4 1697.6 137.6 0.33 0.04 0.01 0.00 OK! Mcr>MEk no cracking!
Btm.trans 18561.8 1359.9 136.6 0.47 0.05 0.01 0.00 OK! Mcr>MEk no cracking!
Top.trans 18561.8 1598.9 136.9 0.28 0.03 0.01 0.00 OK! Mcr>MEk no cracking!
Material lists
Following calculations and checks are performed for Main & Transversal direction for both Bottom
and Top layer reiforcements (Main.btm ; Main.Top ; Trans.Btm ; Trans.Top)
ULS
- Calculation and check bending moment resistance
- Calculation and check for flexural shearing resistance
- Calculation and check for punching shear resistance (Note: Not referred to the Output sheet)
- Check for minimum area of reinforcement
- Check for maximum spacing of reinforcement
SLS
- Calculation for Un-cracked and Cracked cross section properties: xu, Iu, Mcr, xc, Ic
- Calculation and check for stress in concrete
- Calculation and check for stress in tensile reinforcement
- Check for minimum area of reinforcement
- Calculation and check for crack width
Instructions:
- Fill in the necessary input to the yellow cells
- Make sure that there are no "Not OK" and/or "NOTE!" messages - otherwise the design is not
valid and/or on the unsafer side.
- Calculations_M is the main input sheet. Slab geometry and reinforcement is given here.
- Required input for the Shear calculations are referred from Calculations_M sheet to the
Calculations_S sheet.
- Most important inputs and results are referred to the Output sheet that you can print
- Separate calculation for creep according to EC2 Annex B can be found from the Data sheet
Sources:
[1] Designers Guide to EN-1992-2, Chapter 7
[2] Rak-43.2100 Rakenteiden suunnittelu ja mitoitus, luento #3
[3] Betoni.com,Betonirakenteiden suunnittelu eurokoodien mukaan, taipuma