5.CSP-J05 Rev.2
5.CSP-J05 Rev.2
CARiGAul CARlGALISTANDARDPROCEDURE
REVISION. : 2
JACKET
FOR
KUALA LUMPUR
In the event of any ambiguity, inconsistency or conflict between this procedure and the
Contract Document and I or the Petronas Technical Standards (PTS), the Contract
Document and I or PTS shall take precedence over this procedure. PETRONAS
Carigali's interpretation shall be final.
CAJliGAuI REVISION.: 2
OFFSHORE CONSTRUCTION
•
WEIGHT CONTROL PROCEDURE NO: CSP-105
coiGAUl PROCEDURES
OFFSHORECONSTRUCTION
REVISION.: 2
PAGE 1 OF 9
TABLE OF CONTENTS
1.0 PURPOSE 2
2.0 SCOPE 2
3.0 REFERENCE 2
4.0 DEFINITIONS 2
5.0 PROCEDURES 2
5. I Introduction 2
5.2 Reference Co-ordinate System 3
5.3 Calculation and Monitoring 6
5.4 Reporting 7
7.0 RECORDS 8
APPENDICES
REVISION.: 2
1.0 PURPOSE
The Weight Control Procedure is used to monitor the weight during fabrication.
The information is essential for determining the centre of gravity (COG) for plan-
ning of Jacket loadout as well as the installation.
2.0 SCOPE
The scope of this procedure constitutes the content of the Weight Control Report
(WCR) for the Jacket structure and its components such as piles, conductors, boat
landing(s), boat fender, etc. throughout the fabrication phases.
3.0 REFERENCES
4.0 DEFINITIONS
5.0 PROCEDURES
5.1 Introduction
5.2.2 The origin starts from the centre of Jacket at MSL (EL. 0.000)
5.2.3 Figure I and 2 show the position of the overall origin and
co-ordinate system.
cuiGAiJll----- WEIGHT CONTROL
PROCEDURES
OFFSHORE CONSTRUCTION
PROCEDURE NO: eSP-lOS
-I REVISION.: 2
PAGE 4 OF 9
N At EL (+) N
Work Point
x
""..~.......
/
.""'----1--- •...
W.P. W,P.
z ---I----t_ v z
(0,0,0)
AtMSL
--'
w
.... W.P. ;:;:
.•...•.
.' .....
,../
At EL (-)N at Mudline
NOTE:
KEY PLAN
Figure 1
PnROllAIN
CARIGALI(I)
WEIGHT CONTROL
PROCEDURES
PROCEDURE NO: CSP-JOS
REVISION.: 2
.. 0)
z
NOTE:
1. Diagonal bracings are not shown for clarity.
2. N - Refers to the actual elevation(s) of the Jacket framings to be detailed by
the CONTRACTOR
KEY PLAN
Figur61 2
WEIGHT CONTROL PROCEDURE NO: CSP-J05
PROCEDURES
REVISION.: 2
5.3.1 Responsibilities
b. All COG locations for each item shall use the same
reference point / origin as per the section 5.2 -
Co-ordinate System.
5.4 Reporting
5.4.5 The WCR shall be consistent in the format and content for ease
of preparation, review and comparison.
5.4.6 Summary of total weight and final COG shall be included in the
narrative portion of the WCR.
Detailed information on individual weight and COG for every item in the
particular drawing / panel shall be developed based on piece mark num-
ber.
7.0 RECORDS
The Engineering Department shall be responsible for this procedure and shall
keep all the records ofWCR for verification and reference.
WEIGHT CONTROL PROCEDURE NO: CSP-IOS
CAJiGAUI PROCEDURES
REVISION.: 2
•
CSP-J05
APPENDIX I
PAGE 1 OF 1
CONTRACT NO. :
CONTRACTOR : MONTH:
(MTl (MTl
1. STRUCTURAL
2. MECHANICAUEQUJPMENTNESSEL
3. PIPING
4. SHIPLOOSE ITEMS
5.
. MISCELLANEOUS
Note:
( .)
Total ModulefTopsides Lift Weight = Item A + B + Total Weight of slings/shackles. lifting frame, tie-down, etc ..
Source {-I Refer to Table I: Appendix XI Supplementary to PTS 20.073
!Q DESCRIPTION
DE - DESIGN ESTIMATE
VD - VENDOR DATA
FE - FINAUFABRICATED WEIGHT
CSP-I05
APPENDIX II
PAGE 1 OF 1
PROJECT NO.
PROJECT TITLE
CLIENT
CONTRACTOR
SUMMARY OF
CENTER OF GRAVITY & WEIGHT MONITORING
Actual Weighing
Weight
CSP-J05
APPENDIX III
Page 1 of 1
SUMMARY OF SHIPLOOSE ITEM
CONTRACTOR
CLIENT : PETRONAS CARIGALI SDN SHD
PROJECT
REVISION NO.
DATE
TOTAL
WEIGHT (MT)
NOTE:
The weight and COG of eachshiploose item are to be computed separately and shall be covered in their respective lifting procedure
during loadout.
DETAILED WEIGHT CONTROL REPORT CSP-J05
APPENDIX IV
PAGE 1 OF 1
CLIENT PETRONAS CARl GAll SDN BHD
PROJECT
REVISION
DATE
SIN DRAWING NO. DRAWING TITLE WEIGHT(W) LOCATION OF C.O.G. (mm) CALCULATION
(MT)
X Y Z W"X W"Y W"Z
SIN DRAWING NO. DRAWING TITLE WEIGHT(W) LOCATION OF G.O.G. (mm) CALCULATION
(MT)
X Y Z W"X W"Y W"Z
TOTAL
CONTIGENCIES - _ %
GRAND TOTAL
Note.
1. The Loadout weight is exclusive of the rigging LOADOUT WEIGHT _ _ _ _ _ _ _ _ _---'MT
platform which will be provided by PETRONAS Carigali
LOCATION OF CENTRE OF GRAVITY (COG) x _ _ _ _ _ _ _ _ _ _ mm
y _ _ _ _ _ _ _ _ _ _ mm
z _ _ _ _ _ _ _ _ _ _ mm