100% found this document useful (1 vote)
413 views

Generator Relay Protection Setting Calculation REV 1.0

This document provides instructions for setting calculations for various generator protection devices, including: 1) Generator differential protection 2) Overall differential protection 3) Settings are calculated based on generator nameplate ratings and transformer parameters to ensure proper protection sensitivity and security. Minimum operation and restraint currents, ratio settings, and sensitivity checks are determined.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
413 views

Generator Relay Protection Setting Calculation REV 1.0

This document provides instructions for setting calculations for various generator protection devices, including: 1) Generator differential protection 2) Overall differential protection 3) Settings are calculated based on generator nameplate ratings and transformer parameters to ensure proper protection sensitivity and security. Minimum operation and restraint currents, ratio settings, and sensitivity checks are determined.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 18

Generator Protection Setting

Calculation Instruction
Rev No. 1

XJ Electricity Co., Ltd

2010.2

Note: This setting calculation instruction is only for reference, protection device
running setting is confirmed by user.
Catalog
1. Generator Differential Protection(87G) .................................................................................3
2. Overall Differential(87ALL) ...................................................................................................4
3. Generator Inter-turn Fault(95G) ............................................................................................6
4.Generator Inadvertent Energize protection,Stator Earth Fault Protection of startup condition
(99V) ...........................................................................................................................................7
5. Generator Over-voltage(59G) ................................................................................................7
6. Reverse Power Protection(32G); Low Forward Power Protection(37G) .........................8
7. Generator Stator Overload(49G) ............................................................................................8
8. Generator Negative-Sequence Over-current(46G) ...............................................................10
9. Generator Pole Slipping(78G) .............................................................................................. 11
10. Generator loss of excitation protection(40G) .....................................................................13
11. Generator Under & Over Frequency(81G).........................................................................14
12. Generator Over Fluxing(24G) ............................................................................................15
13. Generator Under-voltage(27G) ..........................................................................................16
14. Stator Earth Fault 100%(64G1) .........................................................................................16
15. Stator Earth Fault 100%(64G2) .........................................................................................17
16. Stator Earth Fault 95%(64G3) ...........................................................................................17
17. Field Winding Earth Fault((64F) ........................................................................................18
18. Generator 95% Voltage Check(59GB) ................................................................................18
19. Back Up Impedance(21GA) ................................................................................................18
20. Back Up Impedance(21GB) ................................................................................................18
21. TV Fuse-failure(160G) ........................................................................................................18
I op.o = 0.441A
I res.o = 4.41A
1. Generator Differential Protection(87G) S = 0.3

1.1 Basic parameter

CT ratio( nTA ) 8000/5

I gn1 7060A
rated primary current( )

I gn1 7060
) I gn 2  n  1600  4.41A
I gn 2
rated secondary current(
TA

1.2 Setting calculation

1)Min operation current I op.0

Setting by the max unbalanced current under the condition of avoid the normal
generator rated load.

I op.0  K rel  2  0.03I gn 2  1.5  2  0.03I gn 2  0.09 I gn 2

Suggest to select: I op.0  0.3I gn 2  0.3  4.41  1.324 A

2)Min brake current I res.0

I res.0  0.8I gn 2  0.8  4.41  3.53 A

3)Ratio brake coefficient S


External three-phase short-circuit the maximum short-circuit current:

Sb 100000
I k( 3. max
)
   32.69
X  3  13.8  nTA 0.08  3  13.8  1600
,,
d

I res. max  I k( 3. max


)
 32.69 A

The max unbalanced current of differential protection when the generator is


outer short circuit:
I unb. max  K ap  K er  K cc  I k( 3. max
)
 2  0.1  0.5  32.69  3.27 A

Therein:K ap is the non-periodic branch coefficient, select 1.5~2.0;K cc is the

same type coefficient of transformer, select 0.5; K er is the error coefficient of

transformer ratio, select 0.1;


Put the condition of the differential protection won’t error operate under the max
outer short circuit current,the secondary current value I op .max of correspondent max

operation current:
I op.max  K rel I unb.max  1.5  3.27  4.9 A

Therein: K rel is the reliable coefficient, select 1.3~1.5.

The ratio brake coefficient S is:


I op.max  I op.0 4.9  1.324
S   0.12
I (3)
max  I res.0 32.69  3.53
Suggest to select:S=0.3。
4)Sensitivity check
Sensitivity check principle : Generator terminal side of two-phase metallic
short-circuit occurs when generator is parallel off:
0.866  S b 0.866  100000
I k . min    28.3 A
X  3  13.8  nTA 0.08 3  13.8  1600
,,
d

I k . min
I res   14.15 A
2
I op  I op.0  S ( I res  I res.0 )  1.324  0.3  (14.15  3.53)  4.51A

I k . min 28.3
K sen    6.27  2
I op 4.51 I op.o = 0.2x0.45 =0.090A
I res.o = 0.45A
5)Output model : Trip All CBs S = 0.3
2nd Harm = 15%
2. Overall Differential(87ALL) Iop = 5x0.45 = 2.25A

2. 1 Basic parameter
Name M.T. HV Side Generator terminal A.T. HV Side
Rated Voltage(kV) 230 13.8 13.8
Rated Current(A) 452.4 7539.6 7539.6
CT ratio 1000/1 8000/5 8000/5
Second side Current(A) 0.45 4.71 4.71
2.2 Setting Calculation
I op .0
1)Min operation current

Setting by the max unbalanced current under the condition of avoid the normal main

transformer rated load.:

I op.0  K rel (f i ( n )  U  m)I b  1.5  (0.06  0.05  0.05) I b  0.24 I b

Suggest to select: I op.0  0.5 I b  0.5  0.45  0.225 A

Therein:

I b is the value of rated current of transformer norm side converted to the TA


secondary side.
K rel is the reliable coefficient, K rel  1.3 ~ 1.5 ;

f i( n )
is the transformer ratio error of the current transformer under rated current.

U is the error caused due to the regulation of transformer tapping (relative to the
percent of the rated voltage).
m is the error caused due to the incomplete matching of transformer ratios of TA and
TAA, m takes 0.05 in general.

2)Min brake current


I res.0

I res.0  0.8I b  0.8  0.45  0.36 A

3)Ratio brake coefficient S


The calculation of three-phase main transformer high-voltage busbar metallic short-circuit
occurs current when generator is parallel off:

1 Sb 1 100000
I k( 3. max
)
     1.674 A
X  XT 3  230  nTA 0.08  0.07
,,
d 3  230 1000
External three-phase short-circuit the maximum short-circuit current:

I unb . max  ( K st K aper f i   U   m ) I (3)


k . max

 (1  1 . 5  0 . 1  0 . 05  0 . 05 )  1 . 674  0 . 4185 A

式中:
K st is the same type coefficient of TA, K st  1.0

K aper K aper  1.5 ~ 2.0


is non-periodic coefficient of TA , ( 5P or 10P type TA )

K aper  1.0
or (TP type TA)
Setting of ratio braking coefficient S:

K rel I unb.max - I op.0 1.5  0.4185  0.225


S   0.31
I res.max - I res.0 1.674  0.36

Suggest to select: S  0.4

4)Sensitivity check
Sensitivity check principle : Main transformer high-voltage side of two-phase
metallic short-circuit occurs when generator is parallel off:
0.866  S b 0.866  100000
I k . min    1.45 A
( X  X T )  3  230  nTA (0.08  0.07)  3  230  1000
,,
d
I res. min  I k . min  1.45 A

I op  I op.0  S ( I res  I res.0 )  0.225  0.4  (1.45  0.36)  0.661A

I k . min 1.45
K sen    2.19  1.5
I op 0.661

5)Setting of second harmonic braking coefficient


Suggest to select: 15%
6)Difference current quick brake
Select: I op  5 I b  5  0.45  2.25 A

7)Difference current quick brake sensitivity check


Sensitivity check principle : Main transformer low-voltage side of two-phase
metallic short-circuit occurs:
0.866  S b 0.866  100000
Ik    5.08 A
X //( X S  X T )  3  230  nTA 0.08 //(0.022  0.07)  3  230  1000
,,
d

Ik 5.08
K sen    2.26  1.2
I op 2.25 Manual required to check setting.
How operation is prevented during stator E/F and System Ph-Ph
8)Output model: Trip all CBs fault (which generate NPS current) ?
Normally this type of generator is single turn, so interturn prot not
3. Generator Inter-turn Fault(95G) required. Also this type of protection can lead to mal-operation on
other type of fault.
3.1 Basic parameter

I gn1 7060
Rated secondary current( I gn 2 ) I gn 2    4.41A
nTA 1600

13.8 0.11 0.11


PT ratio( nTV )
3 3 3
3.2 Setting Calculation
1)Zero-sequence Voltage
Setting by the max unbalanced zero-sequence voltage under the condition of
avoid the normal generator rated load.

U op  2V

2) Fault branch negative-sequence direction elements

 i  3% I gn 2  3%  4.41  0.13 A

 u  1%U gn 2  1%  100  1.1V


0.1% Pgn
p   0.1%  3  I gn 2  U gn 2  0.1%  3  4.41  110  0.84VA
nTV  nTA
3) Time delay: t  0.2 s
4)Output model: Trip All CBs

4.Generator Inadvertent Energize protection,Stator Earth Fault Protection of


startup condition(99V) Manual required to
check setting
4.1 Basic parameter

Rated secondary current( I gn 2 ) 4.41A

Rated secondary voltage( U gn 2 ) 110V


4.2 Setting calculation
1)Low impedance element setting
0.8U gn 2 0.8  110
Z set    38.4 
3  0.3I gn 2 3  0.3  4.41

Rset  0.85Z set  0.85  38.4  32.64 

2)Over current element setting

I op  1.2 I gn 2  1.2  4.41  5.29 A

3)Stator Earth Fault Protection of startup condition operation voltage

U op  10V

Time delay: t  2 s
4)Output model
Generator Inadvertent Energize protection: Trip 220kV CB & excitation CB

Stator Earth Fault Protection of startup condition: Trip excitation CBs。

5. Generator Over-voltage(59G) Setting OK

5.1 Basic parameter

Rated secondary voltage( U gn 2 ) 110V


5.2 Setting Calculation
1)Operation voltage

U op  1.3U gn 2  1.3  110  130V

2)Time delay
Select: t  0.5s
3)Output model: Trip all CBs
6. Reverse Power Protection(32G); Low Forward Power Protection(37G)
6.1 Basic parameter
32G
Pop = 0.5% of rated power = 3W
Generator rated power( Pn ) 135WM Delay with Turb trip = 3s
Delay without Turb trip = 10s
Generator rated secondary power( Pn 2 ) 611.4W
6.2 Setting Calculation
1)Min operation power

Pop  K rel( P1  P2 )  0.5  (3%  1  98 .6%)  611 .4  13 .45W

Suggest to select: Pop  10W

Therein: K rel is the reliable coefficient,select 0.5~0.8;

P1 is the min loss when steam turbine is in reverse power operation,generally

select 2%~4% of the rated power;


P2 is the min loss when steam turbine is in reverse power operation,generally select

(1 -  )P gn , Pgn is the rated capacity of generator.

2)Time delay

Reverse Power Protection(32G): t1  5s (32G )

t 2  100s(32G )
Low Forward Power Protection(37G):
t  1s (37G ) 37G
Pop=0.5% = 3W
Delay with turb trip = 1 sec
3)Output model
Reverse Power Protection(32G):

Time delay t1 : Alarm

Time delay t 2 : Trip All CBs


Low Forward Power Protection(37G): Trip All CBs

7. Generator Stator Overload(49G) Iop = 1.1x4.41 = 4.85A, t=10s


I op min = 1.05x4.85=5.09A, t min=120s
7.1 Basic parameter I op max = 32.68A, t max = 0.7s

Rated secondary current( I gn 2 ) 4.41A

allowed heat time constant of stator winding( K ) 37.5


7.2 Setting calculation
1)Time specified overload
Stator winding time specified over-load can be set by the condition of the long
term allowed loading current can reliable return.
K rel 1.05
I op   I gn 2   4.41  5.14 A 4.41x1.1=4.85A
Kr 0.9

Therein:
K rel is the reliable coefficient, select 1.05;

Kr is the return coefficient, select 0.9;


Time specified overload time delay: t  9 s
2)Reverse time specified overload
Reverse time specified over-current can be set by the over-load ability allowed by
stator winding,it should be determined by the over-load ability allowed by the stator
winding of the motor manufacturer. The relation of allowed duration time is ::
K
t
I (1 )
*
2

Therein:K is the allowed heat time constant of stator winding,it should be based
on the parameter provided by the motor manufacturer;
I * is the per-unit value based on stator rated current;
 is the heat radiation constant and related to the stator winding temperature
rising and temperature margin,generally select 0.01~0.02.
3)Reverse time specified startup current

Reverse time specified startup current I op . min should be set by the condition of

matched with time specified over-load protection:


I op . min  K C 0I op  1.05  5.14  5.4 A 1.05x4.85=5.09A

I op
Therein: is the set value of time specified startup current; K C 0 is the matching
coefficient,select 1.05。
Reverse time specified delay lower limit: t min  120 s OK

I op . max
Reverse time specified delay upper limit current can be set by the condition of
three phase metal short circuit at generator side:
Ign 2 4.41
I op. max    55.1A 32.68A
X d" 0.08
0.135

K 37.5
t max    0.24 s 0.7s
I 2
 (1   )  55.1  2

  1  0.01
op . max*

 4.41 
4)Output model
Time specified overload: Alarm
Reverse time specified overload: Programming Trip Settings are OK. Can be set as
Iop = 0.37A
8. Generator Negative-Sequence Over-current(46G) Iop min = 0.44A
Iop max = 8.82A
t min = 2.5 sec
8.1 Basic parameter

Rated secondary current( I gn 2 ) 4.41A

The per-unit value of generator long term allowed


0.08 P.U .
negative-sequence current( I 2 )

time constant of withstanding negative-sequence current


10
ability of rotor surface(A)
8.2 Setting calculation
1)Time specified overload
The negative-sequence time specified over-load should be set on the condition of

under the generator long term allowed negative-sequence current I 2  can reliable
return
I 2  Ign 2 0.08  4.41
I op  K rel  1.05   0.39 A
Kr 0.95

Therein:
K rel is the reliable coefficient, select 1.05; K r is the return coefficient,

select 0.85~0.95;
I 2  is the per-unit value of generator long term allowed negative-sequence current;

Time specified overload time delay: t  5s


2)Reverse time specified overload
The reverse time specified negative-sequence over-load was confirmed by the
allowed negative-sequence over-current ability of the generator rotor surface. The
relation mode between the generator short time withstanding negative-sequence
over-current multiple and allowed duration time is :
A
t
I 2
2*  I 22
Therein:is the per-unit value of generator negative-sequence current;
I 2
is the per-unit value of generator long term allowed negative-sequence
current;
A is the time constant of withstanding negative-sequence current ability of rotor
surface。
Reverse time specified startup current
The reverse time specified startup current I op . min , generally be set by the

operation current in correspondent with delay1000s ( set value of reverse time


specified delay lower limit:
A 10
I op . min  I gn 2  I 22  4.41   0.08 2  0.56 A
1000 1000
Reverse time specified delay upper limit current I op . max should be set by the

condition of main transformer HV side two phase metal short circuit:


Ign 2 4.41
I op. max    8.38 A
X  X G 2  2 X t 0.135  0.141  2  0.125
"
d

A 10
t min    2.76s
I  I 2  8.38  2
2
2*
2

  0.08
2

 4.41 
3)Output model
Time specified overload: Alarm
Reverse time specified overload: Programming Trip

9. Generator Pole Slipping(78G) Relay manual required to


check setting
9.1 Basic parameter
Generator neutral CT ratio 8000/5=1600
Generator terminal CT ratio 13.8/0.11=125.45
9.2 Setting calculation
1)Reduced generator、transformer、system reactance etc. to the named unit (ohm)value with
the generator side voltage is 13.8kV.

13800
 0.267 
'
Generator: X d  0.237 
3  7060
2
U gn 13.8 2
Main transformer: X t  X k   0.125   0.132 
Sn 180

7.8
System: X s   0.031 
220  13.82
X st setting of system relation impedance:

X st  X t  X s  0.132  0.031  0.163 

'
2)Reduce X d 、 X t & X st to the secondary side value of generator side TV、TA.:
' ' nTA 1600
Xd 2  Xd   0.267   3.40()
nTV 125.45

nTA 1600
Xt2  Xt   0.132   1.68()
nTV 125.45

nTA 1600
X st 2  X st   0.163   2.08()
nTV 125.45
3)Setting lens principal axis obliquity

Select system impedance angle : z  85


0

4)Setting of operation power angle δset

0.9U n 0.9  13800


R1. min  COS   0.8  0.71()
3  1.15I n 3  1.15  7060

1.54 RL. min 1.54  0.71


δset  180  2arctg  180 0  2arctg  180 0  2  68.50  430
│X st││X d│  0.163  0.267

Suggest to select  set  120 0


5)Tripping blocking current setting
This protection use generator neutral CT, CT ratio is 8000/5,Main transformer high side
circuit breaker rated breaking current is 40kA:
40000 230
I set  0.5    208A
1600 13.8
Suggest to select I set  180 A

6)Slipper times setting


Outer zone,Slipper times setting:N =4;
Inner zone, Slipper times setting:N =1(#1Generator)、2(#2 Generator)、3(#3
Generator)、4(#4 Generator)。

7)Reactance line position Z C

Z C  0.9 X t 2  0.9  1.53  1.377()

8)Startup current

I st  1.2 I n 2  1.2  4.41  5.3( A)

9)Time delay
Outer zone :0.5s
Inner zone :0.1s
10)Output model
Outer zone :Alarm
Inner zone :Trip all CBs

10. Generator loss of excitation protection(40G) Settings are OK


Trip should be
10.1 Basic parameter Loss of Exc plus
Generator neutral CT ratio 8000/5=1600 U/V
Generator terminal CT ratio 13.8/0.11=125.45
10.2 Setting calculation
Reduced generator、transformer、system reactance etc. to the named unit (ohm)value with the
generator side voltage is 13.8kV.

13800
Generator: X d  2.065   2.33 
3  7060

13800
 0.267 
'
X d  0.237 
3  7060
2
U gn 13.8 2
Main transformer: X t  X k   0.125   0.132 
Sn 180

7.8
System: X s   0.031 
220  13.82
X st setting of system relation impedance:

X st  X t  X s  0.132  0.031  0.163 

As X d  X q ,Salient pole power equal 0W。

1)Set of static and stable boundary impedance

nTA 1600
Z 1B  X d   2.33   29.7()
nTV 125.45

nTA 1600
Z 1 A  X st   0.163   2.08()
nTV 125.45
2)Set of stable asynchronous impedance

nTA 1600
Z 2B  X d   2.33   29.7()
nTV 125.45

nTA 1600
Z 2 A  0 .5 X ' d   0.5  0.267   1.70()
nTV 125.45
3)Set of generator terminal low voltage

U st  0.8U n 2  0.8  110  88(V )


4)Time delay
Select t1=3S 、t2=0.8S 、t3=6S
5)Output model
loss of excitation zone 1: Alarm;
loss of excitation zone 2: Trip all CBs;
loss of excitation zone 3: exit;

11. Generator Under & Over Frequency(81G) Settings are OK

11.1 Basic parameter


Generator under & over frequency capability tables provided by the equipment
manufacturing factor:
Allow run-time Allow run-time

Frequency(Hz) accumulated Each Frequency(Hz) accumulated Each

time (min) time(s) time (min) time(s)

51.0  F  51.5 30 30 47.5  F  48 60 60

50.5  F  51 180 180 47  F  47.5 10 20

48.5  F  50.5 Run Continuously 46.5  F  47 2 5

48  F  48.5 300 300


11.2 Setting calculation
1)Under frequency zone I

under-frequency zone I frequency setting: f1.set  48.5 Hz

under-frequency zone I accumulated time:  t1.set  18000s

under-frequency zone I time delay: t1.set  300 s

2)Under frequency zone II

under-frequency zone II frequency setting: f 2.set  48 Hz

under-frequency zone II accumulated time:  t 2.set  3600s

under-frequency zone II time delay: t 2.set  60 s

3)Under frequency zone III

under-frequency zone III frequency setting: f 3.set  47.5 Hz

under-frequency zone III accumulated time:  t 3.set  600 s

under-frequency zone III time delay: t 3.set  20 s

4)Under frequency zone IV


under-frequency zone IV frequency setting: f 4.set  47 Hz

under-frequency zone IV time delay: t 4.set  20 s

5)Over-frequency

over-frequency setting: f set  51Hz

over-frequency time delay: t set  30 s

6)Generator terminal low voltage setting, U set  0.8U n  80V

7)Output model: Programming Trip

12. Generator Over Fluxing(24G) Settings are OK

12.1 Basic parameter


Generator over excitation capability tables provided by the equipment
manufacturing factor:
Stator 1.25 1.19 1.15 1.12 1.10 1.09 1.08 1.07 1.05
voltage/Frequency
Time(sec) 5 7.5 10 15 20 30 45 60 ∞
12.2 Setting calculation
1)Time specified over fluxing

Over fluxing times: N 0  1.06 , time delay: t 0  5s


For Alarm

Select rated voltage as reference voltage 110V。


2)Reverse time specified over fluxing For trip as per curve

Over fluxing times: N1  1.07 ,time delay: t1  60 s

Over fluxing times: N 2  1.08 ,time delay: t 2  45s

Over fluxing times: N 3  1.09 ,time delay: t 3  30s

Over fluxing times: N 4  1.10 ,time delay: t 4  20 s

Over fluxing times: N 5  1.12 ,time delay: t 5  15s

Over fluxing times: N 6  1.15 ,time delay: t 6  10 s

Over fluxing times: N 7  1.19 ,time delay: t 7  7.5s

Over fluxing times: N 8  1.25 ,time delay: t8  5s

3)Output model: Trip all CBs


Settings appears to
13. Generator Under-voltage(27G) be ok but why it is
required?
13.1 Basic parameter

13.8 0.11 0.11


Generator terminal PT ratio:
3 3 3
13.2 Setting calculation

U set  0.6U n  66V

Time delay: 0.5s


13.3 Output model: Alarm

14. Stator Earth Fault 100%(64G1) Relay manual


required to check
settings
14.1 Basic parameter
Neutral earthing transformer ratio 13.8 / 0.3kV

Neutral earthing transformer secondary resistance ( Rn ) 1.3

Neutral earthing transformer primary resistance ( RN ) 2750.8

Neutral earthing transformer secondary CT ratio( nTA 0 ) 200 / 5

Generator 3 relative capacitance ( 3C0 ) 1.392F

Generator capacitive reactance ( X C 0 ) 6860


14.2 Setting calculation
1) earthing resistance
The setting of earthing resistance low set value should be set by the principle of
one point earthing in the distance within 20% of generator neutral, the earthing fault
point current 3I0 ≤ safe earthing current Is(1A). Means:
0.2  3U gn 3
3I 0   IS
3Rg  3RN //( jX C 0 )

0.2  3U gn 3
 IS
3Rg .set  3RN //( jX C 0 )

0.2  3  13800 3
1
3Rg .set  3  2750.8 //(  j 6860)

R g .set  5.2k

Suggest to select:

Earthing resistance high value: Rhg .set  10k


Earthing resistance low value: Rlg .set  5k

Time delay:
high value time delay:3s
low value time delay:0.5s

  U 2n 0.2  300
I 50.set    1.05 A
Rn  K I  nTA0 1.3  1.1  40

Therein α can generally be selected as 20%; K I is the reliable coefficient,

generally select 1.1.


2) Output model
high value : Alarm
low value : Trip all CBs

15. Stator Earth Fault 100%(64G2) Based on 3rd Harmonics?

15.1Basic parameter

13.8 0.11 0.11


Generator terminal PT ratio:
3 3 3

13.8
Generator neutral PT ratio: 0.1
3
15.2 Setting calculation
Setting value by the protection device according to measured data
Time delay : 5s
15.3 Output model: Alarm

16. Stator Earth Fault 95%(64G3) Setting seems OK

16.1 Setting calculation


The fundamental wave zero-sequence voltage has two sections protection
including high value and low set value.
Principle ,the low setting value zero-sequence voltage should be set by the max
unbalance fundamental wave zero-sequence voltage of neutral single phase voltage
transformer when normal operation or three phase voltage transformer open triangle
winding at generator side. The setting value applied in the project should avoid the
max zero-sequence unbalance voltage that transmitted to the generator side when
system HV side and plant transformer LV side earthing short circuit.
The setting of high set value zero-sequence voltage is 20~30V.
Suggest to select: U op. H  20V (high value),U op.l  10V (low value)
,According to the

measured maximum value of zero sequence voltage imbalance adjustment 。


Time delay:
High value: 0.5s
Low value: 10s
16.2 Output model
High value: Trip all CBs
Low value: Trip all CBs

17. Field Winding Earth Fault((64F) OK

Non-electrical,time delay is setting by the owner

18. Generator 95% Voltage Check(59GB) OK

18.1 Basic parameter

rated secondary voltage( U gn 2 ) 110V


18.2 Setting Calculation
1)Operation voltage

U op  0.95U gn 2  0.95  110  104V

2)output model: Alarm Statement not correct.


At least 21G - Post Synchronisation to be
19. Back Up Impedance(21GA) set at 70% of Zb of Generator.

Based on actual engineering experience, this protection is valueless ,we suggest don’t use it.

20. Back Up Impedance(21GB)


Based on actual engineering experience, this protection is valueless ,we suggest don’t use it.

21. TV Fuse-failure(160G) Is it Voltage transformer fuse


Fail?
21.1 Basic Parameter

rated secondary current( I gn 2 ) 4.41A


21.2 Setting Calculation

Blocking current: I set  1.2 I gn 2  1.2  4.41  5.3( A)

You might also like