Inspection Test Plan: Itp No: REV:1.0 Date

This document outlines an inspection test plan for piping replacement using carbon steel. It details quality control activities, acceptance criteria, responsibilities, and inspection status for items including: 1) QA/QC document submission and approval including drawings, welding procedures, and welder qualifications. 2) Material receiving including inspection, storage, handling, and traceability. 3) Production welding and consumables including welding parameters, consumables, storage, and issuing. 4) Shop fabrication including material storage and handling.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
228 views

Inspection Test Plan: Itp No: REV:1.0 Date

This document outlines an inspection test plan for piping replacement using carbon steel. It details quality control activities, acceptance criteria, responsibilities, and inspection status for items including: 1) QA/QC document submission and approval including drawings, welding procedures, and welder qualifications. 2) Material receiving including inspection, storage, handling, and traceability. 3) Production welding and consumables including welding parameters, consumables, storage, and issuing. 4) Shop fabrication including material storage and handling.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

PIPING REPLACEMENT (CARBON STEEL)

INSPECTION TEST PLAN ITP NO: REV:1.0 DATE:

CLIENTS : ABBREVIATIONS
PROJECT : M : MONITOR W : WITNESS
BY : STS EDAC PLANT SERVICES SDN BHD R : REVIEW AP : APPROVAL
DESCRIPTIONS : GENERIC ITP FOR PIPING REPLACEMENT (CARBON STEEL) RD : RANDOM H : HOLD
NA : NOT APPLICABLE

RESPONSIBILITY INSP. STATUS


ITEM
PROCESS DESCRIPTION QC ACTIVITY SPEC / ACCEPTANCE CRITERIA VERIFYING RECORD THIRD THIRD REMARK
NO STS EDAC CLIENT STS EDAC CLIENT
PARTY PARTY

1 QA/QC Document Submission & Approval

1.1 Drawing
Receive Dwgs from CLIENT Review against Dwg Masterlist NA Transmittals QA/QC NA MECH R NA AP
Approval drawing NA Transmittals QA/QC NA MECH M NA AP
1.2 PQR & WPS
Qualification of PQR/WPS Perform Procedure Qualification Test ASME -IX, July 2015 Procedure Qualification Record (PQR) QC Inspector Inspector CLIENT INSP W/AP R/AP R
Visual Inspection ASME -IX, July 2015 Procedure Qualification Record (PQR) QC Inspector Inspector CLIENT INSP W/AP AP R
Non-destructive Testing(NDT) ASME -V / IX, July 2015 RT Report QC Inspector Inspector CLIENT INSP W/R AP R
Mechanical Testing ( if required ) ASME -IX, July 2015 Lab. Report ( if required ) QC Inspector Inspector CLIENT INSP W/AP R R
Compile WPS ASME -IX, July 2015 Welding procedure spec.record(WPS) QC Inspector Inspector CLIENT INSP W/AP R R
1.3 Welder Qualification Testing (WQT)
Qualification of Welders Perform Welder Qualification Test ASME -IX, July 2015 Welder Qualification Test Record QC Inspector Inspector CLIENT INSP W/R AP/W R
Visual Inspection ASME -IX, July 2015 Welder Qualification Test Record QC Inspector Inspector CLIENT INSP W/M AP/W R
Non-destructive Testing(NDT) ASME -V / IX, July 2015 RT Report QC Inspector Inspector CLIENT INSP W/R AP R
Issue welder certificate. ASME -IX, July 2015 Welder certificate QC Inspector Inspector CLIENT INSP R AP R

2 Material Receiving
2.1 Material receiving inspection Check material against purchasing docs API 573/API 650 Delivery Note Matl Contl NA CLIENT INSP R/AP NA H
Check material certificates (mill cert) Material Receiving Inspection Report QC inspector Inspector CLIENT INSP M/R H H
Mill Cert

2.2 Storage of Material Ensure all material adequately protected NA NA Supervisor NA CLIENT INSP M NA RD

2.3 Handling of materials Ensure all material carefully handled NA NA Supervisor NA CLIENT INSP M NA RD

2.4 Material Traceability NA NA Traceability / Mill cert Supervisor / Inspector CLIENT INSP M/R R/RD M
QC inspector

3 Production Welding & Consumable


3.1 Welding Pipe Amps, volts, weave width, heat input WPS NA QAQC Supv Inspector CLIENT INSP M RD R/RD
Check correct consumable WPS NA QAQC Supv Inspector CLIENT INSP M RD R

3.2 Consumables received. Check manufacturer's certificate Retain all manufacturer's certificates M/Controller Inspector CLIENT INSP M/W R R
Storage Ensure stored dry and sealed NA QAQC Supv NA CLIENT INSP M/W NA R
Baking / Holding Bake and hold electrodes activity Baking/Holding record QAQC Supv Inspector CLIENT INSP M/W RD R
Issuing Record weight and type of electrodes Consumable Issue record QAQC Supv Inspector CLIENT INSP M R RD
issued/return

4 Shop Fabrication
4.1 Storage of Material/Handling of Materials Ensure all material adequately protected NA NA Supervisor NA CLIENT INSP M NA RD

4.2 Site Verification & Measurement Confirm with verified the defect area Inspection report QC inspector Inspector CLIENT INSP M/W H W/AP
Client Acceptance
Ensure the located area Inspection report QC inspector Inspector CLIENT INSP M/W H W/AP

4.3 Marking / cutting / edge prep Visual Inspection Approved Drawing , Inspection Report NA Supervisor Inspector CLIENT INSP M W RD

4.4 Fit-up Fit-up Inspection ASME VIII DIV.1, July 2015 - Division1 / UW-33 Fit-up inspection report QC Supervisor Inspector CLIENT INSP W/M H H
i)Dimensional check Approved Drawing
WPS/PQR

4.5 Fit-up Inspection ASME B31.3, 2014 ASME B31.3, 2014 - para 328.4 Fit-up Inspection Report QC Supervisor Inspector CLIENT INSP W/M H H

4.6 Welding (GTAW/SMAW Process) Amps, volts, weave width , heat imput Refer WPS/PQR IPC Static Sumamry QC Supervisor Inspector CLIENT INSP W/M H M/W
Check correct consumable Refer WPS/PQR Welder Pass

4.7 Visual Inspection To verify that all completed joints ASME V, July 2015 - Article 9 - Visual Examination Visual Inspection Report QC Supervisor Inspector CLIENT INSP M R H
Comply with the acceptance standard ASME V, July 2015 - Article. 2
PIPING REPLACEMENT (CARBON STEEL)
INSPECTION TEST PLAN ITP NO: REV:1.0 DATE:

CLIENTS : ABBREVIATIONS
PROJECT : M : MONITOR W : WITNESS
BY : STS EDAC PLANT SERVICES SDN BHD R : REVIEW AP : APPROVAL
DESCRIPTIONS : GENERIC ITP FOR PIPING REPLACEMENT (CARBON STEEL) RD : RANDOM H : HOLD
NA : NOT APPLICABLE

RESPONSIBILITY INSP. STATUS


ITEM
PROCESS DESCRIPTION QC ACTIVITY SPEC / ACCEPTANCE CRITERIA VERIFYING RECORD THIRD THIRD REMARK
NO STS EDAC CLIENT STS EDAC CLIENT
PARTY PARTY

4.8 Non-Destructive Test (NDT) Evaluate Welding Quality Non-Destructive Examination NDT Report QC Inspector NDT Tech CLIENT INSP M R R/AP
4.8.1 Dye Penetrant Test (DPT) ASME V, July 2015-Article 6 - Liquid Penetrant examination

4.8.2 100% Radiographic Test (Butt Joint) before PWHT Evaluate Welding Quality ASME V, July 2015 - Article II - Radiographic examination / UW-51 RT Report QC Inspector NDT Tech CLIENT INSP M R R/AP
ASME B31.3 Ed 2014 - Table 341.3.2

4.8.3 Post Heat Treatment (PWHT), If required To ensure temperature within range of WPS & PQR ASME B31.3 Ed 2014 - Table 330.1.1 PWHT Report QC Inspector Inspector CLIENT INSP M R R/AP *PWHT temperature shall be
follow WPS/PQR & Code and
ASME VIII DIV.1, 2015 - Table UCS-56 standard

4.8.4 100% Radiographic Test (Butt Joint) after PWHT Evaluate Welding Quality ASME V, July 2015 - Article II - Radiographic examination / UW-51 RT Report QC Inspector NDT Tech CLIENT INSP M R R/AP *After 24 hours
ASME B31.3 Ed 2014 - Table 341.3.2

4.8.5 Hardness test (after PWHT) To ensure the test using correct tools ASME B31.3, 2014 - Table 331.1.1 (Brinell Hardness) Hardness Test Report QC Inspector Inspector CLIENT INSP M R R/AP
PTS 15.12.01 – Welding of Chemical, Oil, and Gas Industries

5 Site Execution/Installation
5.1 Marking / cutting / edge prep Visual Inspection Approved Drawing , Inspection Report NA Supervisor Inspector CLIENT INSP M W RD

5.2 *Surface Preparation Visual Inspection Client Acceptance N/A QC Supervisor Inspector CLIENT INSP W/M H RD/AP
-Cleaning area

5.3 Perform DPT on surface preparation (existing bevel) Request NDT ASME V, July 2015 - Article 6 NDT Request QC Inspector NDT Tech CLIENT INSP M R R/AP
/ASME VIII Design Code & Standard
5.4 Fit-up Fit-up Inspection ASME VIII DIV.1, July 2015 - Division1 / UW-33 Fit-up inspection report QC Supervisor Inspector CLIENT INSP W/M H H
i)Dimensional check Approved Drawing
WPS/PQR

5.5 Dehydrogenation on existing pipe (if required) Ensure the works follow procedure approved N/A QC Supervisor Inspector CLIENT INSP W/M R R/AP

5.6 Fit-up Inspection ASME B31.3, 2014 ASME B31.3, 2014 - para 328.4 Fit-up Inspection Report QC Supervisor Inspector CLIENT INSP W/M H H

5.7 Welding (GTAW/SMAW Process) Amps, volts, weave width , heat imput Refer WPS/PQR IPC Static Sumamry QC Supervisor Inspector CLIENT INSP W/M H M/W
Check correct consumable Refer WPS/PQR Welder Pass

5.8 Visual Inspection To verify that all completed joints ASME V, July 2015 - Article 9 - Visual Examination Visual Inspection Report QC Supervisor Inspector CLIENT INSP M R H
Comply with the acceptance standard ASME V, July 2015 - Article. 2

5.9 Non-Destructive Test (NDT) Evaluate Welding Quality Non-Destructive Examination NDT Report QC Inspector NDT Tech CLIENT INSP M R R/AP
5.9.1 Dye Penetrant Test (DPT) ASME V, July 2015-Article 6 - Liquid Penetrant examination

5.9.2 100% Radiographic Test (Butt Joint) before PWHT Evaluate Welding Quality ASME V, July 2015 - Article II - Radiographic examination / UW-51 RT Report QC Inspector NDT Tech CLIENT INSP M R R/AP
ASME B31.3 Ed 2014 - Table 341.3.2

5.9.3 Post Heat Treatment (PWHT), if required To ensure temp within range of WPS & PQR ASME B31.3 Ed 2014 - Table 330.1.1 PWHT Report QC Inspector Inspector CLIENT INSP M R R/AP *PWHT temperature shall be
follow WPS/PQR & Code and
ASME VIII DIV.1, 2015 - Table UCS-56 standard

5.9.4 100% Radiographic Test (Butt Joint) after PWHT Evaluate Welding Quality ASME V, July 2015 - Article II - Radiographic examination / UW-51 RT Report QC Inspector NDT Tech CLIENT INSP M R R/AP *After 24 hours
ASME B31.3 Ed 2014 - Table 341.3.2

5.9.5 Hardness test (after PWHT) To ensure the test using correct tools ASME B31.3, 2014 - Table 331.1.1 (Brinell Hardness) Hardness Test Report QC Inspector Inspector CLIENT INSP M R R/AP
PTS 15.12.01 – Welding of Chemical, Oil, and Gas Industries
PIPING REPLACEMENT (CARBON STEEL)
INSPECTION TEST PLAN ITP NO: REV:1.0 DATE:

CLIENTS : ABBREVIATIONS
PROJECT : M : MONITOR W : WITNESS
BY : STS EDAC PLANT SERVICES SDN BHD R : REVIEW AP : APPROVAL
DESCRIPTIONS : GENERIC ITP FOR PIPING REPLACEMENT (CARBON STEEL) RD : RANDOM H : HOLD
NA : NOT APPLICABLE

RESPONSIBILITY INSP. STATUS


ITEM
PROCESS DESCRIPTION QC ACTIVITY SPEC / ACCEPTANCE CRITERIA VERIFYING RECORD THIRD THIRD REMARK
NO STS EDAC CLIENT STS EDAC CLIENT
PARTY PARTY

6 Welding Repairs (If Applicable)


6.1 Remove Defect Ensure defect has fully removed ASME VIII DIV.1, July 2015 - Division1 / UW-33 NA QC Inspector Inspector CLIENT INSP M R R
Perform weld repair WPS/PQR

6.2 Welding Amps, volts, weave width , heat imput Refer WPS/PQR IPC Static Sumamry QC Supervisor Inspector CLIENT INSP W/M H H
Check correct consumable Refer WPS/PQR Welder Pass

6.3 Visual Inspection To verify that all completed joints ASME V, July 2015 - Article 9 - Visual Examination Visual Inspection Report QC Supervisor Inspector CLIENT INSP W/M H H
Comply with the acceptance standard ASME V, July 2015 - Article. 2

6.4 Non-Destructive Test (NDT) Evaluate Welding Quality Non-Destructive Examination NDT Report QC Inspector NDT Tech CLIENT INSP M R R/AP
6.4.1 Dye Penetrant Test (DPT) ASME V, July 2015-Article 6 - Liquid Penetrant examination

6.4.2 100% Radiographic Test (Butt Joint) before PWHT Evaluate Welding Quality ASME V, July 2015 - Article II - Radiographic examination / UW-51 RT Report QC Inspector NDT Tech CLIENT INSP M R R/AP
ASME B31.3 Ed 2014 - Table 341.3.2

6.4.3 Post Heat Treatment (PWHT), if required To ensure temp within range of WPS & PQR ASME B31.3 Ed 2014 - Table 330.1.1 PWHT Report QC Inspector Inspector CLIENT INSP M R R/AP *PWHT temperature shall be
follow WPS/PQR & Code and
ASME VIII DIV.1, 2015 - Table UCS-56 standard

6.4.4 100% Radiographic Test (Butt Joint) after PWHT Evaluate Welding Quality ASME V, July 2015 - Article II - Radiographic examination / UW-51 RT Report QC Inspector NDT Tech CLIENT INSP M R R/AP *After 24 hours
ASME B31.3 Ed 2014 - Table 341.3.2

6.4.5 Hardness test (after PWHT) To ensure the test using correct tools ASME B31.3, 2014 - Table 331.1.1 (Brinell Hardness) Hardness Test Report QC Inspector Inspector CLIENT INSP M R R/AP
PTS 15.12.01 – Welding of Chemical, Oil, and Gas Industries

7 Hydrostatic Test Check calibration of pressure gauges ASME VIII DIV.1 1 Ed 2015 -UG 102 (Test Gages) Calibration Certificates QAQC Supv Inspector CLIENT INSP H R H
7.1 Piping /chart recorder Valid Calibration Certificate
7.2 Valve Check test pressure & Test Duration PSM-MI-20408 - Para 5.1 (Determine Test Pressure IRP Record & Approved Drawing QAQC Supv Inspector CLIENT INSP H W/R H
and Method) Hydrotest Certificate Form QAQC Supv Inspector CLIENT INSP H
Visual Inspection of leaks ASME PCC-2 -Part 5 (Examination and Testing) NA QAQC Supv Inspector CLIENT INSP M H H
General Arrangement (GA) Drawing

8 Blasting and Painting


8.1 Surface Preparation Grade of surface preparation Blasting & Painting Report QAQC Supv Inspector CLIENT INSP H W H
i- Salt Test (if required) PTS 30.48.00.31 SEPT 2012

8.2 Painting works - Correct paint material Blasting & Painting Report QAQC Supv Inspector CLIENT INSP M W W/M
- Correct application method PTS 30.48.00.31 SEPT 2012

8.3 Painting Inspection Ensure that the dry film thickness meet the Blasting & Painting Report QAQC Supv Inspector CLIENT INSP M H H
requirement
PTS 30.48.00.31 SEPT 2012

8.4 Holiday Test (If required) Ensure the painting is no defect ASTM D5162-01, Edition Jan 1, 2016 Holiday Test Report QAQC Supv Painting Inspector CLIENT INSP M H R/AP

9 Insulation
9.1 Insulation works - Correct insulation material as per spec. Insulation Record QAQC Supv Inspector CLIENT MECH R W W/M
- Correct material thickness
CLIENT INSP &
9.2 Insulation Inspection Visually inspect completed of work Insulation Record QAQC Supv Inspector R W RD
MECH

10 Documentation Review all Quality report and compile N/A Final Documentation ( Quality ) QC Inspector Inspector CLIENT INSP M/R R AP
all Quality document

PREPARED BY : REVIEWED BY : REVIEWED BY : APPROVED BY : APPROVED BY :

NAME NAME : NAME : NAME :


DATE DATE : DATE : DATE :