Key Formulas - BSCM
Key Formulas - BSCM
Available Time The product of hours of operation multiplied by number of workers or equipment in use during
those hours.
Available to The uncommitted portion of a company's inventory and planned First Period ATP = On-hand inventory less customer orders that are due and overdue. Following
Promise (ATP) production maintained in the master schedule to support periods ATP = master production schedule - orders.
customer-order promising. Al’s Note: Know the principles of ATP
Average Actual The average actual cycle time consistently achieved to fulfill Sum of actual cycle times for all orders delivered/Total number of orders delivered.
Cycle Time customer orders. For each individual order this cycle time starts
from the order receipt and ends with customer acceptance of the
order. This cycle time consists of a ‘gross’ component and a ‘net’
component defined as Order Fulfillment Process Time, according
to the following formula: Order Fulfillment Cycle Time = Order
Fulfillment Process Time + Order Fulfillment Dwell Time. Note
that dwell time will equal 0 for companies who do not utilize this
metric, so Order Fulfillment Cycle Time will equal Order
Fulfillment Process Time
Benefit/Cost A way to determine whether the revenue/profit of doing an Benefit/Cost Analysis = Total Benefits/Total Costs (calculate for a defined period of time)
Analysis activity will exceed the cost within a certain timeframe.
Capable-to- A process of committing orders against available capacity, as Capable-to-promise employs a finite-scheduling model of the manufacturing system to
Promise well as inventory, to determine when new or unscheduled determine when an item can be delivered. It includes any constraints that might restrict the
customer orders can be delivered. production, such as availability of resources, lead times for raw materials or purchased parts, and
requirements for lower-level components or subassemblies. The resulting delivery date takes into
consideration production capacity, the current manufacturing environment, and future order
1
Capacity Determines in detail the amount of labor and machinery required Step 1: Check open order file. Step 2: Check planned order releases. Step 3: Check the routing
Requirements to complete production tasks specified by MRP. Short term file. Step 4: Check the work center file. Calculate in CRP to determine if capacity exceeds load
Planning (CRP) capacity planning. Open shop orders and planned orders input to or not. If not, change load to match capacity
CRP which uses parts routings and time standards to calculate
hours of work by work center by time period.
Cash-to-Cash The time it takes for an investment made to flow back into the Cash to Cash Cycle Time = Inventory days of supply + days of sales outstanding - days of
Cycle Time company after it is spent on raw materials. payables outstanding.
Coefficient of Measures variability relative to average demand coefficient of variation = standard deviation/mean
Variation (CV)
Cost Effect of Number of warehouses for the logistics system impacts costs of: Total costs = inventory costs + warehouse costs + transportation costs + costs of lost sales
Increasing warehousing, carrying inventory, transportation and cost of lost
Number of sales. Total costs tend to decline as number of warehouses
Warehouses increase until the point where increasing inventory costs
eventually overwhelm savings in other areas.
Cost of Goods Cost associated with buying new materials and finished goods. COGS = Direct material + Direct Labor + Overhead
Sold (COGS) Includes direct costs (Labor, materials) and indirect costs
(overhead).
Al’s Note: Uses ABC Classification method. A 1000 Monthly - 20 days 1000/20 = 50
B 3500 Quarterly - 60 days 3500/60= 58
C 5500 Semiannually - 120 days 5500/120= 46
Total counts per day -> 154
2
Demand Time Used in MPS. That point in time inside of which the forecast is See appendix I
Fence (DTF) no longer included in Total Demand and Projected Available Al’s Note: Understand principle of time fences in planning.
Impact Balance calculations - only customer orders are included.
Beyond this point, Total Demand is a combination of forecast
and orders, depending on forecast consumption method chosen.
Disaggregation Process by which the Operations Plan (usually monthly time See appendix II
of Operations periods) is broken down by the Master Scheduler into smaller
Plan time periods (usually weeks, could be days or other) and specific
item (SKU) level of detail.
DRP Grid An MRP like calculation that takes planned orders from DCs and See appendix III
Calculation consolidates them on a central supply location.
Efficiency Efficiency measures how well something is performing relative Efficiency is a measure of actual output as a percentage of standard expected output (standard
to existing standards. A work center that produces 110 standard hours of work / hours worked x 100).
hours of work while operating for only 100 hours has an
efficiency rate of 110 percent. (The term “standard hours,” or
“standard time”, refers to the amount of time an average worker
or piece of equipment is expected to need, following prescribed
methods, to produce one unit of output.
EOQ Economic Order Quantity. The EOQ is the order size that gives General quantity – cost relationships: (1) The total cost tends to drop until they reach a
you the least total cost for holding, ordering, and setup. The minimum, and then they start rising again, (2) The minimum total cost occurs where holding
EOQ is the point on the total cost curve that lies directly above and setup cost are equal – which is the point where the cost lines intersect.
the intersection of the holding cost and setup / order cost curves. Understand the variables in the EOQ equation, as well as the assumptions that
make it valid.
Exponential A type of weighted moving average forecasting technique in New Forecast = Previous Periods Forecast + α (Last Periods Demand – Last Periods Forecast)
Smoothing which past observations are geometrically discounted according Three basic terms: the last period’s forecast, the last period’s actual demand), and a smoothing
to their age. constant, a number between 0 and 1 represented by the Greek letter α (between 0.05 and 0.5).
The higher the constant, the more weight your forecast gives to the actual demand data from the
preceding period. Understand the principles of exponential smoothing and what the
alpha factor is.
Forecast Error The deviation of actual from the forecasted quantity. Forecast Error = Actual Demand - Forecast
Hidden Cost See Landed cost Landed Cost – Purchase Prices, Import Duty, International Freight, Special Packing, Travel and
other Communication Cost, Fees and Commissions, Currency Exchange, Interest Cost, Hiring,
Training Personnel.
Import Duty Import duties are generally assessed as a percentage of either the
CIF (Cost, Insurance, Freight) or on the Fob (Free On Board)
amounts. The FOB amounts paid by the exporter to transport the
freight from its dock and load it on the ship.
Inventory days This is related to an IMS (Inventory Management System) Inventory days on Hand = inventory on hand / average daily usage
on Hand (average daily usage takes into account historical usage and forecast damand)
3
Inventory Turns Inventory Turns are also a measurement of IMS inventory turns = (annual usage X value of component) / current Value of inventory or
The number of times that an inventory cycles, or “turns over,” = annual cost of sales / average inventory value
during the year. A frequently used method to compute inventory This turn analysis can be done for a single component, a product line and the total system
turnover is to divide the average inventory level into the annual
cost of sales. For example, an average inventory of $3 million
divided into an annual cost of sales of $21 million means that
inventory turned over seven times. Syn: inventory turns,
inventory velocity, turnover
Landed Cost Landed cost needs to take into account hidden costs associated to Landed Cost = purchase price + import duties+ Freight +Packaging + Travel and
the procurement transaction Communication fees used during purchase + exchange rate and interest costs + Hiring and
training of employees to deal with the purchase
Lead Time lead-time offsetting is a process to determine the latest start time
offsetting for an release based on the lead-time to complete the activity.
The BOM structure is an intregal part of the calculation
MRP Material Requirements Planning (MRP) : A set of techniques that Time-phased MRP begins with the items listed on the MPS and determines (1) the quantity of all
uses bill of material data, inventory data, and the master components and materials required to fabricate those items and (2) the date that the components
production schedule to calculate requirements for materials. It and material are required. Time-phased MRP is accomplished by exploding the bill of material,
makes recommendations to release replenishment orders for adjusting for inventory quantities on hand or on order, and offsetting the net requirements by the
material. Further, because it is time-phased, it makes appropriate lead times.
recommendations to reschedule open orders when due dates and
need dates are not in phase.
MPS Master Production Schedule (MPS) The master production The master production schedule must take into account the forecast, the production plan, and
schedule is a line on the master schedule grid that reflects the other important considerations such as backlog, availability of material, availability of capacity,
anticipated build schedule for those items assigned to the master and management policies and goals. Syn: master schedule
scheduler. The master scheduler maintains this schedule, and in
turn, it becomes a set of planning numbers that drives material
requirements planning. It represents what the company plans to
produce expressed in specific configurations, quantities, and
dates. The master production schedule is not a sales item forecast
that represents a statement of demand.
Mean The mean (or average) is the sum of demand for given set of Mean=(Sum of demand for all Periods)
periods divided by the number of periods # of Periods
Mean Absolute The average of the absolute values of the deviations of observed MAD=(Sum of Absolute Errors for each Period)
Deviation values from some expected value. # of Periods
(MAD)
Mean Square Process of squaring provides much wider range of numbers. The MSE=(Sum of Absolute Errors for each Period)2
Error (MSE) wider range gives a more sensitive measure of the error rate. # of Periods
MSE is especially useful if the absolute error numbers are close
together and reduction of errors is important.
4
Min/Max A type of order point replenishment system where the "min" An order is recommended when the sum of the available and on-order inventory is at or below
System (minimum) is the order point, and the "max" (maximum) is the the min.
Calculation "order up to" inventory level. The order quantity is variable and
is the result of the max minus available and on-order inventory.
3-Month Moving Uses average demand per month for the three preceding months MA=(P1 + P2 …+ Pn)
Average to determine forecast for next month. n
P= Period
n= # of periods
Moving Average The theory behind a weighted moving average (WMA) is that the WMA=[(W1)P1 + (W2) P2 …+ (W3) Pn]
– Weighted recent data is more relevant than past data. Therefore, it puts n
more "weight" on the recent data and less weight on the older
data. A weighted average is any average that has multiplying W=Weight Factor Al’s Note: Understand the principles of weighted average
factors to give different weights to different data points P= Period
n= # of periods
MRP Grid An inventory balance projected into the future. The running sum of on-hand inventory - requirements + scheduled receipts and planned orders =
Calcuations Inventory balance projected into the future. Al’s Note: Basics of the MRP grid.
Net Requirement In MRP, the net requirements for a part or an assembly are Gross Delivery minus on-hand items and scheduled receipts
Calculation derived as a result of applying gross requirements and allocations
against inventory on hand, scheduled receipts, and safety stock.
Net requirements, lot-sized and offset for lead time, become
planned orders.
On-Time A measure (percentage) of meeting the customer's originally On Time Orders/Total Number of Orders x 100%
Delivery negotiated delivery request date.
Order The minimum amount of time to fulfill a customer order in the Calculation: Total average lead time from [Customer signature/authorization to order receipt] +
Fulfillment Lead absence of inventory. [Order receipt to completion of order entry] + [Completion of order entry to start manufacture] +
Time [Start manufacture to complete manufacture] + [Complete manufacture to customer receipt of
order] + [Customer receipt of order to installation complete]
Order The Level 1 measure of Supply Chain responsiveness. It starts Order Fulfillment Cycle Time = Order Fulfillment Process Time + Order Fulfillment Dwell
Fulfillment with the order receipt and ends with customer acceptance of the Time
Cycle Time order.
Perfect Order The only Level 1 measure of supply chain reliability. The The only Level 1 measure of supply chain reliability. The percentage of orders meeting
Fulfillment percentage of orders meeting delivery performance with delivery performance with complete and accurate documentation and no delivery damage.
complete and accurate documentation and no delivery damage.
5
Planned Order Due date of order - lead time of part
Release
Calculation A row on an MRP table that is derived from planned order
receipts by taking the planned receipt quantity and offsetting
to the left by the appropriate lead time.
Planning Time NA
Fence (PTF)
Impact
Return on
Investment
(ROI)
(Percentage) A financial measure of the relative return from
an investment, usually expressed as a
percentage of earnings produced by an asset to
the amount invested in the asset. (Total Benefits-Total Costs/Total Costs) X100
Return on ROI (Time)=((Installation,Integration,Stabilization time)+Years to Recoup onetime cost)/Yearly
Investment return
(ROI) (Time) Years to Recoup onetime cost=onetime cost/yearly return
Return on Measures return an organization receives on its invested capital RSCFA=(Supply Chain Revenue-COGS-Supply Chain Management Costs)/Supply Chain Fixed
Supply Chain in supply chain fixed assets Assets
Fixed Assets
Rough Cut Capacity Planning technique used at the Master Planning level. Use bill of labor to extend master schedule quantity x labor requirements per unit at critical work
Capacity Focus is on critical or bottleneck work centers. centers. Offset by lead-time. Al’s Note: Understand the Planning Hierarchy, and the
Planning relationships, inputs and outputs, of each of the main boxes.
(RCCP)
6
Safety Stock Extra stock to build as a hedge against demand forecast Safety Stock=Z*(standard deviation forecast error)
variability In Excel: Z=NORMIN(Desired Service Level, Average Forecast Error, Standard Deviation of
Forecast) Al’s Note: Safety Stock assumes 100% supply reliability.
Seasonality Seasonal effect for a product Seasonality=(Seasonal monthly average)/Deseasonalized Average Monthly Sales
Smoothing A number between 0 and 1 represented by the Greek letter alpha α=(New forecast – Previous Period’s Forecast)/(Last Period’s Demand – Last Period’s Forecast)
Factor α. Used in exponential smoothing forecasting technique. The or can be chosen arbitrarily
higher the number, the more responsive is the forecast to changes Al’s Note: Understand the concept (as in exponential smoothing).
in demand.
Standard Measures absolute variability of demand for an item Standard Deviation=Square root(((Actual1- Mean)2 +…+(Actualn-Mean))2/n-1)
Deviation
Takt Time When Production of finished product is exactly synchronized Takt time =
with customer demand. Available production time /customer demand
Total Supply Key performance indicator Total annualized supply chain cost of sales/average total supply chain inventories
Chain Turns
Utilization Percentage of available time that a work center is using Utilization =
Hours worked/available hours X 100
Value Added Resembles sales tax in the United States and are assessed by the VAT = %VAT(currency value CIF or FOB x duty)
Tax (Cost, Insurance, Freight) or Freight on Board plus the import
duty
Volume Growth Key performance indicator Percentage of increase in volume. Volume P2 – Volume P1 / Volume P1 x 100%
Wait time by Group performance measure for determining customer service Wait time by SKU = date finished – date shipped
SKU/Group level. The time when a SKU remains at a locations until it is
shipped
Supply Chain All direct and indirect costs associated with operating process TSCMC = Cost to plan + Cost to source + Cost to make + Cost to deliver + Cost to return
Management across the SC
Cost
7
Appendix I:
Item Number A
Master Schedule
Lead Time 1
Safety Stock <--------------------------------------------Planning Horizon-------------------------------------------------------->
Lot Size 30 Period
Demand Time Fence 3 1 2 3 4 5 6 7 8
Forecast 2 32 2 32 2 32 2 32
Customer Orders 0 25 15 5
Scheduled Receipts 30
Projected Available Balance (PAB) 20 20 25 25 23 21 19 17 15
Master Production Schedule
(MPS) 30 30 30
8
Appendix II:
Operations Plan
Appendix III:
Distribution Center A Distribution Center B
Part 1234 Lead Time = 1 week Part 1234 Lead Time = 1 week
Week 1 2 3 Week 1 2 3
Forecast aa aa aa Forecast bb bb bb
Scheduled Receipts aa aa aa Scheduled Receipts bb bb bb
Projected Available aa aa aa aa Projected Available bb bb bb bb
Central Supply
Part 1234 Lead Time = 2 weeks
Week 1 2 3
Gross Requirements 200 100 200
Scheduled Receipts 500
Projected Available 400 200 100 400
Planned Order Release 500
Central Supply Order would be P.O. to outside supplier or an order on the factory
9
Appendix IV:
D B
1
1 wk wk
D A
4
wk
C
2 wk
E
E needs to start 7 wk prior to A being completed
10