The document is an inspection and test plan (ITP) for the erection of static equipment for the F-NC-174 Elephant Field Development Project. It details 17 activities to be completed, including inspection of materials, positioning equipment, bolting, grouting, installation of internals and externals, coating, insulation, and mechanical completion. Inspections and tests will be witnessed and documented to verify acceptance criteria are met at key hold points.

Uploaded by

bhct1987
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views4 pages

ITP - Erection of Static Equipment

The document is an inspection and test plan (ITP) for the erection of static equipment for the F-NC-174 Elephant Field Development Project. It details 17 activities to be completed, including inspection of materials, positioning equipment, bolting, grouting, installation of internals and externals, coating, insulation, and mechanical completion. Inspections and tests will be witnessed and documented to verify acceptance criteria are met at key hold points.

Uploaded by

bhct1987
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

F-NC-174

(Elephant) Field Development Project - GOSP


AGIP Job No.: MFIA Job No.:
F-NC-174 INSPECTION AND TEST PLAN (ITP) 520 02 21270

DOCUMENT NO. GS-MO-Q-QC-00-011-C1

INSPECTION AND TEST PLAN

FOR

ERECTION OF STATIC EQUIPMENT

Page 1 of 4

C1 14.08.04 R. Dapula T. Curry J. Rittscher Approved for Construction


01 20.05.04 A. Cuesta R. Clemens J. Rittscher Issue for Approval
Rev. Date Prepared Checked Approved Description of Revision
Procedure No. GS-MO-Q-QC-00-011-C1 Page 2 of 4

Erection of Static Equipment

Legend: I = Visual Inspection M = Monitoring W1 = Full Witness W2 = Part Witnessing H = Hold Point
Act. Activity Ref. Procedure / Acceptance QA/QC Document Remarks
No. Documents Criteria MFIA AGIP TP

1 INSPECTION OF RECEIVED Site Material Receiving Order MRR, OS&D


CONSTRUCTION MATERIAL GS-MO-Q-PR-00-024-01 Documents, Form: LGM-C F-22-1
Quantity, visual H H Form: LGM-C F-23-1
inspection for
damage
2 MATERIAL ISSUE FOR Site Material Issue FMCO
CONSTRUCTION GS-MO-Q-PR-00-025-01 Form: LGM-C F-19-1
W2 W2

3 INSPECTION OF CIVIL AND AFC Drawings, See separate Inspection


STRUCTURAL WORKS Vendors instructions and Test Plans Civil and
Existence, Elevations, Dimensions, W1 W1 Structural
Completion of underground services
(if applicable)
4 POSITIONING OF STATIC P&I diagrams, Plot Plans Inspection of Skid and
EQUIPMENT ON PREPARED AFC Drawings, Vessel
FOUNDATION Vendors instructions Form: LGM-MF-58-1
W1 W1
Check orientation of nozzles,
flanges, instrument and electrical
connections.
5 FINAL ALIGNMENT & BOLTING UP AFC Drawings, Vertical and Inspection Skid and
Shimming & Levelling, Tightening of Vendors instructions horizontal axes, Vessel
foundation/anchor bolts Elevations H H Form: LGM-MF-58-1

6 GROUTING OF SKIDS, FRAMES AFC Drawings, Grouting Inspection


OR BASE PLATES Vendors instructions Record
As required W1 W1 Form: LGM-MF-61-1
Procedure No. GS-MO-Q-QC-00-011-C1 Page 3 of 4

Erection of Static Equipment

Legend: I = Visual Inspection M = Monitoring W1 = Full Witness W2 = Part Witnessing H = Hold Point
Act. Activity Ref. Procedure / Acceptance QA/QC Document Remarks
No. Documents Criteria MFIA AGIP TP

7 REMOVAL OF TEMPORARY AFC Drawings, Vendor Inspection of Skid and


SUPPORTS AND BRACINGS Vendors instructions Documentation Vessel
Anchorage and fixing bracing from W2 W2 Form: LGM-MF-58-1
components. Construction aids

8 INSTALLATION OF EXTERNAL AFC Drawings, Visual check of Checklist – Installation of


STRUCTURES Vendors instructions, joints, Steelwork Structural Steel
Support, ladders, stairways, E/TK/X/SP/99/004 Spec. W2 W2 Form: LGM-MF-22-1
platforms, etc.

9 RE-INSTATE SKID MOUNTED AFC Drawings, Vendor Inspection of Skid and


EQUIPMENT Vendors instructions Documentation Vessel
Re-installation of any part which W1 W1 Form: LGM-MF-58-1
have been removed due to transport
limitations / restrictions
10 INTERNAL INSPECTION OF Vendor recommendations Internal Inspection of Skid and
VESSELS / TANKS / instruction cleaning, Test of Vessel
Installation of internals and packing internal parts H H Form: LGM-MF-58-1
as required

11 CLOSURE OF EXTERNAL Vendor Instructions Inspection of Skid &


MANWAYS Vessel
H H Form: LGM-MF-58-1

12 FITTING AND INSTALLATION OF AFC Drawings, See separate Inspection


PIPEWORK Vendors instructions and Test Plan Station Pipe
W1 W1 Work
Procedure No. GS-MO-Q-QC-00-011-C1 Page 4 of 4

Erection of Static Equipment

Legend: I = Visual Inspection M = Monitoring W1 = Full Witness W2 = Part Witnessing H = Hold Point
Act. Activity Ref. Procedure / Acceptance QA/QC Document Remarks
No. Documents Criteria MFIA AGIP TP

13 INSTRUMENT AND ELECTRICAL AFC Drawings, See separate Inspection


INSTALLATIONS Vendors instructions and Test Plans Electrical
W1 W1 & Instrumentation

14 FINAL COATING Paint Procedure GS-MO- Vendor Coating Report


Holiday Detection of field wrapped Q-PR-0 0-052 -01 Instructions, Form: LGM-MF-07-1
Areas, Touch up painting and DFT Wrapping Procedure GS - E/TK/M/SP/00/6 W2 W2 Holiday Test Report
checks MO-Q-PR-00-053-01 004 Form: LGM-MF-06-1

15 INSULATION Line List 03652.VAR.GE Check List


Cold / Hot Insulation Vendor Instructions N.SPC Form:
Personnel Protection 03653.VAR.GE W2 W2
N.SPC

16 MECHANICAL COMPLETION Pre-Commissioning Proc. AFC Drawings, Check List


Completion of Systems, GS-MO-Q-PR-00-021-01 Vendor Form:
Pre-Commissioning Documentation H H

17 PUNCH LIST DRAW UP AND Procedure Punch Listing Relevant Punch List
CLOSE OUT GS-MO-Q-PR-00-039-01 documents and Form: LGM-C F-31-1
Completion of Systems, specifications H H
Pre-Commissioning

18 AS BUILT DOCUMENTS Procedure As -built CS/LC/GAPR/0 Client accepted As -built


Preparation + submission of as built documentation GS-MO-Q- 0/0009PS/LA/Q documentation
drawings and documentation PR-00-026-0 1 SP/00/001 H H