Commissioning Tests For HV Underground Cables (Up To 33Kv) SWP
Commissioning Tests For HV Underground Cables (Up To 33Kv) SWP
1. PURPOSE AND SCOPE * Note: This course is part of Cable Joining Training. Staff
performing HV Cable Testing should complete this training if not
The purpose of this Standard Work Practice (SWP) is to standardise
competent.
and prescribe the method for pre commissioning and commissioning
tests on high voltage underground cables. Where new cables are 3. DOCUMENTATION
jointed to existing cables the test requirements are modified as Hazchat On-site risk assessment
described in this SWP to cater for the aged insulation of existing
SP0407R01 Commissioning Tests for New HV Cables (up to 33 kV)
cables.
Job Safety Analysis
2. STAFFING RESOURCES SP0407R02 Testing HV Cables Supplementary Information
Electrical Fitter and/or Mechanic or Cable joiner. SP0407R03. Commissioning Test for HV Underground Cable (up to
Competent Assistant. 33kV) SWP SP0407 - Field Instruction
Safety Observer where required. SP0407C01 HV Cable Commissioning Test Report Form
Required Training SP0407C04 Commissioning Tool – HV Cables (Up to 33kV)
Staff must be current in all Statutory Training relevant for the task. SP0506. Substation Primary Plant and Secondary Systems Field
Testing SWP
All workers must have Completed Field Induction or have recognition
of prior Ergon Energy Field Experience. SWMS001. Working at Heights - Poles & Ladders
Contractors must have completed Ergon Energy's Generic SWMS002. Working at Heights (Mobile Elevated Work Platform
Contractor Worker Induction. P53. Operate the Network Enterprise Process
Additional Training (as required) AS2067-2016 Substations and High Voltage Installation Exceeding 1
Training Course Description for Authorisations or Certificates. kV a.c.
Safe Entry to High Voltage Enclosures and Authorised Pole Rescue Kit.
Switchboard Rescue kit.
Access / Test Permit Recipient and Authorised
Confined Space Monitoring and Rescue equipment.
Safe Work in Confined Spaces
Roadway warning signs.
* Test HV UG Cables up to 33kV
Barricading.
Confined Space Awareness
It is noted that the insulating qualities of XLPE are very good, and • High Voltage Withstand including subsequent IR Test (additional
that except in the case of major insulation damage such as physical to major cable testing only);
• Final Checks.
Earth the screen after test for at least 5 minutes. 2. After operating the Earth Switch the switching operator must
Where the prescribed values cannot be achieved the connection visually confirm that the correct switch state is displayed by the
arrangement should be first checked. indicator. If the indicator is incorrect or in an indeterminate state
personnel must stay well clear of the RMU and associated cable(s)
Where applicable the assistance of a high voltage test specialist may and contact the Switching Co-ordinator for further instructions.
be sought and the Asset Manager must be advised where the value
remains low. 5.6 Core Insulation Test
The Asset Manager will decide if sheath resistance values lower than Prior to the high voltage withstand test (if required), the cable shall
the prescribed figures will be accepted. be tested for insulation resistance (IR).
Cables with a suspected or confirmed sheath fault are not to be The test voltage used for the core insulation test is specified in the
energised. table below.
If the cable has two insulated metallic layers (the cable screen and
brass tape termite protection) then the insulation between these
Location = geographic location eg Smith St • Inspect cable terminations to ensure they are not damaged
From = source end of cable eg Mareeba Sub • Ensure terminations are not porcelain or oil filled *
To = destination end of cable eg HVL12 • Inspect switching device (e.g. ABS/HV Links) is operational
Cable Number = unique cable ID (if allocated) • Consider the effect of ferroresonance **
Date = date of test yyyyymmdd eg 20060129 • Close switch
These results will be subsequently filed at \\ecasd01\Protection\Test The Switching Operators Assistance will ensure that the switching
Data - (Test-Commissioning-Maintenance)\Region\Cable Tests\Town device closes correctly. If the device doesn’t function correctly DO
NOT attempt to reopen. Comply with the requirements of P53 HV
5.13 Energise HV Cable Switching and Access.
It is preferred that a remote switching device is used to energise any
* Caution – If the terminations are porcelain or oil filled then the
new HV cables (including plant) for the first time. The earth fault
cable shall be energised remotely. If this is not possible then a
protection operating time of the cable’s protection system may be
voltage withstand test as per paragraph 5.8 shall be carried out.
reduced during the initial cable energisation. Ensure the auto reclose
on the feeder is blocked for the duration of the switching. **Ferroresonance
In power systems, the most common place to find ferroresonance is
The remote switching device for energising must have full fault make with a three phase distribution transformer energised through an
capabilities. It is envisaged that the remote switching device would underground cable of moderate length. Under no load, or very light
be an RMU further upstream at a safe distance from the cable to be load conditions, the capacitance of the cable is sufficient to
energised or a remotely controlled circuit breaker. precipitate ferroresonant behaviour under single phase switching
Because not all minor HV Cables have to undergo an applied high conditions (e.g. the operation of an HV fuse or asynchronous
voltage withstand test as per paragraph 5.8, and where the cable operation of single phase 11kV switches such as a drop-out fuse
doesn’t have to supply customer load within a 24 hour period the unit.)
cable should be energised and left until supply is required. This will
minimise loss of supply or damage should a fault develop The four most effective methods of controlling ferroresonance
are:
Prior to loading the cable, a phase out must be completed. In a radial
a) three-phase switching;
system, a phase rotation check must be used in lieu of a phase out.
Page 11 of 13 Standard Work Practice SP0407 Ver 16
Three-phase Switching
The use of ganged three-phase switching is one of the most effective
and commonly used methods of avoiding ferroresonance.