Lecture-10 Analysis and Design of Flate Plates and Flat Slabs
Lecture-10 Analysis and Design of Flate Plates and Flat Slabs
B Prof
By: P fD
Dr. Qaisar
Q i Ali
Civil Engineering Department
NWFP UET Peshawar
[email protected]
Prof. Dr. Qaisar Ali CE 5115 Advance Design of Reinforced Concrete Structures 1
1
r
Topics Addressed
y Two Way Slabs
y Behavior
y Types
20'-0"
20'-0"
20'-0"
2
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
y Behavior 25′
25′
20′
20′ 25′
Short
Direction
y Behavior: 25′
25′
20′
20′ 25′
L
Long
Direction
3
Two Way Slabs
y Behavior: More Demand (Moment) in short direction
due to size of slab
z ∆central Strip = (5/384)wl4/EI
z As these imaginary strips are part of monolithic slab, the deflection at any
point, of the two orthogonal slab strips must be same:
z ∆a = ∆b
(5/384)wala4/EI = (5/384)wblb4/EI
z Beam supported
z Flat Plate
z Flat slab
z Waffle Slab
4
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
y Design
y Once the analysis is done, the design is carried out in the
usual manner. So no problem in design, problem is only in
analysis of slabs.
5
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
Topics
y Direct Design Method
z Introduction
z Limitations
6
Direct Design Method
y Introduction
y In DDM, frames rather than panels are analyzed as is done in
analysis of two way slabs with beams using ACI moment
coefficients
25'-0" 25'-0" 25'-0" 25'-0"
Exterior Frame
20'-0"
Interior Frame
20'-0"
Interior Frame
20'-0"
Exterior Frame
Prof. Dr. Qaisar Ali 13
20'-0"
E-W Frames
N-S Frames
20'-0"
20'-0"
7
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
l1 ≥2ll1 /3
≥2 l1
Three or more spans
l2 Rectangular slab
panels (2 or less:1) Column offset
≤ l2 /10
8
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
15
15′′ If ≥10′
≥10′ 15
15′′
DDM APPLICABLE as 2/3 (15) = 10′
10′
15
15′′ If <10
<10′′ 15
15′′
DDM NOT APPLICABLE
Prof. Dr. Qaisar Ali 17
Exterior Frame
20'-0"
Interior Frame
20'-0"
Interior Frame
20'-0"
Exterior Frame
Prof. Dr. Qaisar Ali 18
9
D
20'-0"
Interior Frame l2
l1
20'-0"
20'-0"
20'-0"
10
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
20'-0"
• Middle Strip: Middle strips are design strips bounded by two column
strips.
Column strip
Middle strip
Column strip
11
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
b) Middle Strip
20'-0"
l2 M.S/2
Half Column stripp CS/2
CS
C.S
CS/2
M.S/2
20'-0"
12
Direct Design Method
(l2)B z Step No. 02 (continued): Frame and strips in 3D.
½ column
l strip idth l1/4 or (l2)B/4,
t i width: /4 whichever
hi h iis minimum
i i
(l2)A
½-Middle strip
Column strip
½-Middle
½ Middle strip
ln
13
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
Span of frame
wu l2 ln2 20'-0"
Mo = Mo
8 ln l2
20'-0"
20'-0"
20'-0"
M+
M − = 0.65Mo
M + = 0.35
0.35Mo
M− M−
20'-0"
20'-0"
14
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
20'-0"
M − = 0.65Mo 0.60M +
0.75M − 0.75M −
M + = 0.35
0.35Mo
20'-0"
20'-0"
20'-0"
Mo
20'-0"
20'-0"
15
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
20'-0"
Mint- = 0.70Mo
20'-0"
20'-0"
M ext+ = 0.5
0.52Mo
20'-0"
Mint- = 0.70Mo
20'-0"
16
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
Mext − = 0.26Mo
20'-0"
M ext+ = 0.52Mo
1.00Mext− 0.75Mint− 0.60M+
20'-0"
M - = 0.65Mo
M + = 0.35Mo
20'-0"
20'-0"
20'-0"
20'-0"
17
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
z Take hf = 10″
18
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
20'-0"
19
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
b) Middle Strip
20'-0"
l2 5′
Half Column stripp 5′
10′
5′
5′
20'-0"
Mo = wul2ln2/8
20'-0"
= 540 ft-kip
l2
Mo = Mo =
540 ft-k 540 ft-k
20'-0"
ln =23.83′
l1
20'-0"
20
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
20'-0"
20'-0"
21
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
M − = 0.65M
0 65Mo = 405 20'-0"
M + = 0.35Mo = 189
20'-0"
M − = 0.65M
0 65Mo = 405 20'-0"
M + = 0.35Mo = 189
22
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
M − = 0.65M
0 65Mo = 405 20'-0"
M + = 0.35Mo = 189
M − = 0.65M
0 65Mo = 405 20'-0"
M + = 0.35Mo = 189
75 % of Mint- goes to
column strip and 20'-0"
remaining to middle strip
23
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
M − = 0.65M
0 65Mo = 405 0 112/2 94/2 101/2 76/2 101/2
20'-0"
M + = 0.35Mo = 189
20'-0"
20'-0"
Mu (per foot width) 0 112/2
11.2 9.4
94/2 101/2
10.1 76/2
7.6 101/2
10.1 5′ half middle strip
20'-0"
24
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
20'-0"
20'-0"
25
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
l2 =25′ 20'-0"
20.6 4.6
M - = 0.65M
0 65Mo = 274
M + = 0.35Mo = 148 3.9 8.88 20'-0"
20.6 4.6
l2 =25′ 20'-0"
26
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
Mo = 220.5 ft-kip 58 0
Mext − = 0.26Mo = 58
69 45 20'-0"
Mext+ = 0.52Mo = 114
Mint − = 0.70Mo = 154 115.5 38.5
107.3 35.75
l2 =13.08′ 20'-0"
Mo = 220.5 ft-kip
10.4 0
Mext − = 0.26Mo = 58
Mext+ = 0.50Mo = 110 12.32 6
19.2 4.76
M − = 0.65M
0 65Mo = 143
M + = 0.35Mo = 77 8.27 4.12
19.2 4.76
l2 =13.08′
27
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
20'-0"
25'-0
25 0" 25'-00"
25 25'-00"
25 25'-00"
25
10.4 0 00 11.0 0
20'-0"
28
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
0 11.0 8 8 8 6.8
(0) (10.4) (9.4) (8.4) (7.6) (8.4)
20 16.0 28 28 10.5 28
(14) (16.8) (28) (30.4) (11.3) (30.4)
20 16.0 28 28 10.5 28
(14) (16.8) (28) (30.4) (11.3) (30.4)
0 12.5 9 9 8 7.7
(0) (11.2) (9.4) (10.1) (7.6) (10.1)
10 7 12 9 7
(11.9) (5.8) (12.7) (12.7) (5.6)
20 2.6 22 22 1.8
(20.69) (5.13) (22.1) (22.1) (5.13)
20 1.5 22 22 1
(19.2) (4.76) (20.6) (20.6) (4.6)
9 4.5 9 9 3.8
(8.27) (4.12) (8.88) (8.88) (4.12)
29
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
Slab
3/4″
Support
30
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
31
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
Slab
ld
Support
Prof. Dr. Qaisar Ali 63
32
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
Ln Ln
33
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
34
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
Topics
y Shear in Slabs Without Beams
y Two-way
o ay sshear
ea (pu
(punch
c out sshear)
ea )
y Example
35
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
Beam
36
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
Beam
1
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
C4 C3 C3 C3 C4
20'-0"
C2 C1 C1 C1 C2
20'-0"
C2 C1 C1 C1 C2
20'-0"
bo = 2(c1+d)+2(c2+d) C4 C3 C3 C3 C4
2
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
C4 C3 C3 C3 C4
20'-0"
C2 C1 C1 C1 C2
20'-0"
C2 C1 C1 C1 C2
20'-0"
bo = 2(c1+d/2)+ (c2+d) C4 C3 C3 C3 C4
z (2 + 4/βc) √ (fc′)bod
3
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
z When ΦVc < Vu, then either increase ΦVc = Φ4√ (fc′)bod by:
z Increasing d ,depth of slab: This can be done by increasing the slab depth
as a whole or in the vicinity of column (Drop Panel)
z Increasing
g bo, critical shear perimeter:
p This can be done by
y increasing
g
column size as a whole or by increasing size of column head (Column
capital)
z Bent Bars
z Shear heads
z Shear studs
4
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
5
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
C4 C4
Vu = wu × At = 189 kip C3 C3 C3
6
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
Therefore, C2 C1 C1 C1 C2
C4 C3 C3 C3 C4
7
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
y ACI 6.4.6 requires that the capital concrete be placed at the same time as
the slab concrete. As a result, the floor forming becomes considerably
more complicated and expensive.
8
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
Vu = ΦVc C4 C3 C3 C3 C4
Now, 20'-0"
bo = 4 (c + d)
111.26 = 4(c + 9) C2 C1 C1 C1 C2
Simplification gives,
20'-0"
c = 18.8 ≈ 19″
C4 C3 C3 C3 C4
c = 19″
y = 2.5/ tanθ θ y
column
9
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
bo = 4R + 4c
Prof. Dr. Qaisar Ali 91
10
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
y R = √ (x2 + x2)
y bo = 4√ (2) x + 4c1
y Therefore lv ≈ 20″
11
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
lv = 20″ ≈ 24″ or 2′
Where,
12
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
α = EcbIb / EcsIs
13
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
14
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
z ACI tables 13.6.4.1, 13.6.4.2 and 13.6.4.4 of the ACI are used to
assign moments to column strip.
15
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
z ACI tables 13.6.4.1, 13.6.4.2 and 13.6.4.4 of the ACI are used to
assign moments to column strip.
z ACI tables 13.6.4.1, 13.6.4.2 and 13.6.4.4 of the ACI are used to
assign moments to column strip.
1
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
2
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
z l2/l1 = 1.3
z αl2/l1 > 1.
1
3
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
z l2/l1 = 1.3
z αl2/l1 > 1
65 % of interior
positive
negative
longitudinal
longitudinal
moment
moment
will go towill
column
go to
column
strip strip
Prof. Dr. Qaisar Ali 107
4
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
20'-0"
5
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
z Where walls are used as supports along column lines, they can be
regarded as very stiff beams with an α1l2/l1 value greater than one.
111
6
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
z Where,
y2 y2
x2 x2
x1
x1
y1
y1
7
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
20'-0"
20'-0"
βt = EcbC/(2EcsIs) = C/ (2Is)
hw ≤ 4hf = 17″
z Calculation of C:
7″
24″
12″
8
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
βt = EcbC/(2EcsIs) = C/ (2Is)
z Calculation of C:
y2 = 17″
2 x2 = 7″
y1= 24″ 1
x1 =12″
βt = EcbC/(2EcsIs) = C/ (2Is)
z Calculation of C:
y1= 17″ 1
x1 =12″
9
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
βt = EcbC/(2EcsIs) = C/ (2Is)
z Calculation of C:
z Calculation of Is:
20'-0"
20'-0"
20'-0"
10
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
z βt = C/ (2Is)
z Lateral Distribution of
Longitudinal Moments
z Once βt is known,
exterior negative
moment in column strip
can be found. For,
z l2/l1 = 1.3
11
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
12
Department of Civil Engineering, N-W.F.P. University of Engineering and Technology Peshawar
z The positive and negative reinforcement in any case, should be of a size and
spacing equivalent to that required for the maximum positive moment (per foot
of width) in the panel.
The End
13