Conceptual Flow Sheets Development For Coal Conversion Plant Coal Handling-Preparation and Ash/Slag Removal Operations
Conceptual Flow Sheets Development For Coal Conversion Plant Coal Handling-Preparation and Ash/Slag Removal Operations
• .. • • ~ .. .»• ~ • .
DISCLAIMER
JULY 1979
,_;--·--- · - - - - - D I S C L A I M E R
This bOOk was prepared as an account ot work sponsored by an ogency of the United States Government.
Neither the United States Gover~ment nor any agency thereof. nor any of their employees, makes any
warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, """"
completeness. or usefulness of any information. apparatus, product, or process disclosed, or -
repre~nti .. thllt ib ·u)U wuull.l iiUt ir~hlu!Jt! ~rlvdtely uwnoo rlgnts. Reterenee nefein to any specilic
commercial product, process, or service by trade name. trademark, manufacturer. or otherWise, does
, not necessarily constilute or imply its endorsement, recommendation, or favoring by the United
States Government or any agency thereof. The views and opinioru of authors expressed herein do not
1
1 necessarily state or reflect those of the United States Government or any agency thereof.
Section
1 ABSTRACT 1-1
2 SUMMARY 2-1
3 CONCLUSIONS 3-1·
APPENDIX A A-1
REFERENCES R-1
iv
TABLES
Table
v
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
FIGURES
Figure
,·
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
LIST OF FLOW SHEETS AND EQUIPMENT LISTS
Number
ABSTRACT
This report presents 14 conceptual flow sheets and major equipment lists
for coal handling and preparation operations that could be required for
future, commercial coal conversion plants. These flow sheets are based
on converting 50,000 tons per day of clean coal represAntAtive of the
Pittsburgh and Kentucky No. 9 coal seams. Flow sheets were used by
Union Carbide Corporation, Oak Ridge National Laboratory, in a survey
of coal handling/preparation equipment requirements for future coal con-
version plants. Operations covered in this report include run-of-mine
coal breaking, coarse coal cleaning, fine coal cleaning, live storage and
blending, fine crushing (crushing to top sizes ranging from 1/4-inch to
20 mesh), drying, and grinding (70 percent minus 200 mesh).
Two conceptual flow sheets and major equipment lists are also presented
for handling ash or granulated slag and other solid wastes produced by
nine leading coal converHion processes. These flow sheets provide for
solid wastes transport to an environmentally acceptable disposal site
as either dry solids or as a water slurry.
1-1
Section 2
SUMMARY
All conc~ptual flow sheets are for coal conversion plants that consume
50,000 short tons per day of coal having a nominal total moisture
of 8.0 wt percent. Of this coal quantity, 15 percent is used in an
atmospheric pressure fluidized-bed (AFB) power/steam plant which is part of
the coal conversion plant. The other 85 percent is provided to cbnversion
2-1
reactors for the nine coal conversion processes identified in Table 2-1.
This table also summarizes reported process conversion reactor coal feed
requirements,
Table 2-1
'PrnrPss
Cuuv~L::.lo11 rroccoc and TypP Conversion Reactor Coal Feed Requirements
Number -- Size Cuu::•.i.:-;t Moi11t1.1rP --
-----=-~-~------,~·-------=~-------------+--------------------------,_------------------~
1 U-Gas - Fluidized-Bed
Gasification 100 Percent Minus 1/4 As Received
Inch
7 r.OGAS - Fluidized-Bed
Gasification 100 Pcrl!l!lll HhnJs 1/4
J;nch
3 HYGAS - Fluidized-Bed
Gasification 100 Percent Minus As Received
14 Hesh
4 Texaco Partial Oxidation -
Entrained Flow Gasification 100 Percent Minus As Received
20 Mesh
5 Exxon Donor Solvent -
Liquefaction 100 Percent Minus As Received
8 Mesh
6 Exxon Catalytic Gasifica-
tion - Fluidized-Bed Gasifi-
cation lUU .I:' ere E>n r. 1vfluus A3 Rccciv!dJ
8 1'1esh
7 SRC-l and SRC-ll - Lique-
and faction 100 Percent Minus As Rec.ei ved
8 12 MP.sh
2-2
Two major bituminous coal seams wete specified as possible conversion
plant sources·:
Coal fiom either seam was postulated to be provided from a coal mine
complex locat~d adjacent to the conversion plant ~ite or from regional
coal mines. located appreciable distances from the plant site. For both
coal suu1~~s, ·the conceptual flow'sheets start at the. conversion plant
site after coal receiv.i.n.g. The coal operations· .flow sheets terminate at
conversion reRctor coal feed systems.
Coal produced frop! the adjacent coal mine complex can be cleaned and then
conveyed to live or dead storage facilities, or not cleaned, and after
reduction to 2 inch x 0, conveyed to live or dead storage. Coal transported
from regional mines is sized to 2 inch x o,. and i.f justified, cleaned before
transport in rail cars and/or river barges.
In coal cleaning, coal is broken to 6 inch x 0 and wet scieened at 3/8 inch.
Six-inch x 3/8-inch coal is cleaned in coarse coal jigs~ screen dewatered,
and crushed to ·2-inch top size prior to conveying to live or· dead storage.
Undersize coal and crushed coarse coal jig middlings can be cleaned by
selecting any one of three flow sheet processes: jig, hydrocyclone, or
table fine coal cleaning. After cleaning, fine coal is dewatered with
vibrating centrifuges, mixed with crushed coarse coal, and conveyed to
live or dead storage. Effluents from both coarse and fine coal dewatering
are treated to separate minus 28 mesh solids and recycle water.
Two methods are identified for live storage-blending follmvihg coal cleaning
or unloading of coal from regional mines: open, multiple, wedge-shape
stockpiles and totally-enclosed V-bunkers. Specifi~d design r.r:~p;:~ri ty for
2-3
both methods is 500,000 tons. With this live storage capacity, normal
fluctuations between mining or long-distance transport operations and con-
version reactor operations can be accommodated without use of a dead storage
facility. Dead coal storage, for use in emergency situations, is pruvlded
by open, sealed coal piles built and reclaimed by mobile equipment.
2-4
One flow sheet is presented for the H-Coal Process. This flow sheet uses
single-stage, open circuit wet ball mills to produce 70 percent minus
200 mesh coal. The grinding fluid is liquefaction solvent; a grinding
approach which requires development.
Two conceptual ash/slag removal flow sheets are presented for handling
of the three identified conversion plant solid waste streams. One
is for transport-of combined solid wastes as a dry material. Methods
considered for transport of dry solid wastes are overland conveyors,
rail cars, and trucks. The second ash/slag removal flow sheet is for
water slurry transport with recycle of water from the solid wastes dis-
posal site. Nominal ash/slag transport distance from conversion plant
site to an ultimate, environmentally acceptable disposal site is 5 miles
for both ash/slag removal flow sheets.
2-5
Section 3
CONCLUSIONS
3-1
Scaleup of coal pulverizers
Solvent-coal slurry grinding
Scaleup of gravimetric feeders
Coal collection baghouse explosion prevention systems
Pulverized and ultrafine coal transport equipment
Pressurized ash and slag crushers
3-2
efficient than direct coal firing and in the case of fluidized-
bed steam/gas generators eliminates the need for flue gas de-
sulfurization following coal pulverizing or drying.
3-3
Section 4
4.1 INTRODUCTION
·Najar objectives of the Union Carbide survey are determination of: current
equipment p~rform~nce characteristics, suita~ility of spec{fic equipment
for use in commercial coal conversion plants, equipment research and develop-
ment needs, and lead time requirements for. producing and demonstrating
equipment.of advanced design of critical'importance for coal conversion
cornrnercial~zation.
4-1
• Demonstrate how individual types of equipment can be inte-
grated to form complete, matched, efficient, reliable
materials handling-preparation operations
4-2
In developing the flow sheets presented in· this report, emphasis was placed
on selected coal liquefactiori processes specified by Unibn C~rbide. How-
ever, because commercial coal liquefaction plants will require gasification
operations for hydrogen and/or fuel gas production, coal handling-prepara-
ation and ash/siag removal equipment requirements for selected gasification
processes are also included in this report.
Th~s subsection presents design .bases established by Union Carbide and Union
Carbide-Bechtel for conceptual flow sheets development. ThR hAsPs ipclud9
conversion plants feed coal characteristics, nine coal conversion processes,
flow sheets inlet and outlet boundaries, and provision of coal for conver-
sion plant electricity. and process steam generation.
Conceptual flow sheets presented in this report are for coal conversion
plants that consu.me 50,000 short tons/day of coal having a nominal total
moisture of 8.0 wt percent. To establish annual conversion plant coal
consumption, an annual plant operation of 330 days/year was specified.
Annual conversion plant coal consumption is, therefore, 16.5 million tons.
Conversion plant daily op~ration was specified as 24 hours.
Two major bituminous coal seams were specified as possible conversion plant
coal s.ources :
4-3.
• A number of separate mines and/or mine complexes
spread over the representative and neighboring counties
and located an appreciable distance from the conversion
plant sHP
ln the first mining alternativP, the term integrated coal. mine complex is
used to indicate rhar such a ml1ting operation would be extrQmely lnrgP and
wnulrl probably consist of several mines tied together by a common coal trans-
port system. ·For the Pittsburgh Seam, such a mine complex would consist exclu-
sively of underground mines. For the Kentucky No. 9 Seam, a significant
portion, if not all coal, could probably be produced from surface mines.
In the seconcl mining alternative, rh~ distance~ ueLweeu tiiin.~a and the con-
vcroion plant site w~rP pnstJJlated to be such that coal would be transported
to the conversion plant by rail and/or barges. Remote mines would:
4-4
Coal produced from an integrated mine complex was specified to have an as-
received size consist of 12 inch x 0 and a nominal total moisture of 7:0 wt
percent. A coal top size of 12 inches was specified because this is con-.
sistent with design requirements for the types of mine transport systems
thaL would be used in an integrated coal mine complex. It is also the
nomina~.t~p size of coal typically produced by longwRll shPArers and con-
tinuous miners.
Coal transported to the .conversion plant site in rail cars and/or barges
was specified to have an as-delivered size consist of 2 inch x 0 and a
uuutlual t.:ucal moisrure of 8. 0 wt percent. The L inch x 0 size is that
typically used for rail and barge transport in both West Virginia and
Kentucky_.
Two :conversion pl'ant site inlet boundaries were established for initiation
"6f coal ~andling·and preparatio~ flow sheets; ohe for coal from an adjacent
integrated coal mine' complex and one -for coal transported from remote min'es
to 'the conversion .plant site. The boundary for coal mined from an inte-
grated mine complex is the discharge point(s) of a surface coal receiving
facility. The receiving facility provides surge storage between the mine·
transport· system and the ·conversion plant conv~ying system. It would include
a silo or large bunker. The discharge ·point(s) of the conveyor(s) used to
convey coal from this silo or bunker constitutes the coal conversion plant
inlet boundary. From this boundary, coal (12 inches x 0) is fed to a
breaking facility.
The conversion plant inlet boundary for coal transported by rail and/or
barges to the plant site is the discharge point(s) of rail car and/or
barge unloading facilities. (Development of flow sheets for any rail and
barge unloading facilities was excluded from the project covered by this
report.) From this. boundary .coarse .coal. (2 inch x 0) would normally
4-5
be conveyed to live or dead storage. In the event, however, that oversize
or frozen coal is received, it would be conveyed to a crushing facility and
then to storag~.
r.onc.eptual flow sheets have been developed which meet the coal handling,
prepa~ation, and conversion reactor feeding requirements of nine coal con-
version processes. These processes, specified by Union Carbide, and their
reported coal feed requirements are presented in Table 4-1. lnformaciuu
presented in this table is consisl~11L with each proccoc develup~r's
latest coal feed specifications. However, it should be recog-
nized that all nine conversion processes are developmental. Future process
development-demonstration could result in specification of different coal
feed requirements and conversion reactor coal feed systems.
Coal feed requirementR presented in Table 4._1 are based on design studies
using one of the two coals specified in Subsection 4.2.1 or similar bitumi-
nous coals. With the exception of H-Coal, the processes do riot require
coal drying or coal drying is an integral part of the conversion process.
To indicate this condition, the term "as received" has been used to identify
conversion reactor coal feed moisture requirement. Processes, such as
Exxon Donor Solvent (EDS), in which coal drying is part of the conversion
re6ctor 3yotcm arc identifiQd in thP t~hlP nntRR. Ac.t11al coal total mois-
ture concentrations considered to be "as received" total moisture range
from 7 co 10 wl !Jt:!iCen t.
The reactor coal feed size consist presented in Table 4-1 for SRC-1 and ~rr
4-6
Table 4-1
i
•
COAL CONVERSION PROCESSES COAL
FEED REQUIREMENTS
1 U-Gas 100 percent minus 1/4 As received Lock Hopper 50-350 (1) Cleaned and uncleaned 1,2
Fluidized-Bed inch Kentucky No. 9 Seam coal
Gasification May contain up to has been succes'sfully
I
10 percent minus 200 gasified in a p~ilot gasi-
mesh coal fier (3 ft diameter) without
pretreatment to control
1
agglomeration during
gasification. /1
2 COGAS 100 percent minus 1/8 As received Hot Flue Gas 50 (1) The COGAS ~rocess uses mul-
Fluidized-Bed inch. Injection tiple-stage fluidized-bed
Gasification pyrolysis. CoalI
is dried in
the first-stag~
. I
fluidized-bed
reactor(s). I
3 HYGAS
Fluidized-Bed
100 percent minus 14
mesh with minimum
As received Low-Pressure Lock
Hopper (Feeds Coal
1,155-1,165 '
(1) Both Pittsburgh Seam and
Kentucky No. 9 lseam coal were
1,4,5
li
4 Texaco 100 percent minus 20 As received Water Slurry 500-1,500 (1) Operating temperature and 1,6
11
Partial mesh with minimum Injection from a pressure for tlie Texaco Par-
Oxidation ultrafines Slurrying and tial Oxidation~gasifier depends
Surge Storage . I .
Entrained on syn th es~s gas requ~rements
Flow Vessel and feed coal 1omposition.
Gasification
5 Exxon Donor 100 percent minus 8 As received Donor Solvent 1,485 (1) Coal is dr±ed to less than 7
Solvent mesh Slurry Injection 4 wt percent t~tal moisture
Liquefaction from Slurrying and after fine cruS,hing during
Drying Vessel slurryj_ne :i.n hqt (27 .50F)
recycle donor solvent.
6 Exxon 100 percent minus 8 As received Lock Hopper 500 (1) Coal is dr~ed after fine 8
Catalytic mesh crushing and c~talyst addition.
GasHication Catalyst is added as an aqueous
Fluidized-Bed solution. I
Gasification !
'!
( 1 ) Presented in Report References. section
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK .
Table 4-1 (Continued)
I
I
Conversion Reactor Coal Conversion Reactor
Conversion Conversion Reactor I
Process Conversion Reactor Coal Feed Total Moisture Design Operating References(!)
Process ~Notes
No. Feed Size Requirements Requirements Coal Feed System Pressure
and Type
Wt Percent psig
I
7 and 8 SRC- I and 100 percent minus 12 As received Solvent Slurry 2,400 (1) Gulf MinJral Resource Co. 9,10
I
SRC-II mesh Injection from a is currentlylevaluating a
Liquefaction Slurrying and range of conversion reactor
Drying Vessel coal feed siie consists for
SRC-I and IIidemonstration
I
plants. These range from
100 percent ~inus 6 mesh to
100 percent ~inus 50 mesh.
(2) In some dommercial-scale
I
conceptual conversion plant
designs, pulverized coal
(nominally 70I percent minus
200 mesh) has been specified
for the SRC-~I process.
(3) Coal is 4ried after fine
crushing during slurrying in
hot recycle solvent. -
I
9 H-Coal 100 percent minus 40 2 wt percent Solvent Slurry 2,700 (1) Coal is dried quring 10
Liquefaction mesh Injection from a pulverizing. [
70 percent minus 200 ·. Slurrying Vessel !
I
mesh
4-9
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
F~r gasification of Pittsburgh Seam, Kentucky No. 9 Seam, and similar coals
by the HYGAS process, a pretreatment operation is required. This pretreat-
ment produces a nonagglomerating char which is then fed to the multistage
HYGAS gasifier. In the pretreatment operation, coal is contacted with air
in a fluidized bed at 750-850°F. This results in coal oxidation which greatly
reduces its tendency to agglomerate at the temperatures used for gasification.
Gasification of Pittsburgh Seam coal by the U-Gas process may also require
pretreatment similar to that required for HYGAS.
Table 4-2 presents design information used to establish ash/slag removal flow
sheets starting (inlet) boundaries and ash/slag characteristics for the nine
coal conversion processes. In the Exxon Donor Solvent, SRC-II, and H-Coal
liquefaction processes some form of fractionation is used tq recover gas and
liquid products from the slurry resulting from coal liquefaction. An addi-
tional product of liquefied coal fractionation is a high boiling point slurry
frequently referred to as bottoms. This slurry (the solid phase consists of
coal mineral matter products and undissolved organics) is gasified to produce
synthesis gas which is used for hydrogen production and in-plant fuel gas.
The EDS process also recovers additional gas and liquid products from
fractionation bottoms using Exxon Flexicoking technology (3). In Table 4-2
the gasifier designs identified for the EDS, SRC-II, and H-Coal processes
are those believed to be currently favored by the respective process de-
velopers, for fractionation bottoms gasification. Different gasifiers
could, however, be used with these processes.
Gasifier ,,
1 U-Gas Nons lagging 1,800-2,000 The U-Gas gasifier is Reported mean particle (1) :iGasifier operating 1,2,11
Fluidized Bed designed to agglomerate sizes for agglomerated temperature is dependent
fine ash particles in a ash range from 6 to on doal ash fusion tem-
specially designed 14 mesh perdture
,[
characteristics.
spout or spouts located Ash agglomerates contain Steam and oxygen fed to
at the bottom of the 5-10 wt percent carbon the !gasifier ash ~gglom-
1
gasifier fludized bed. era~ing spout(s) located
When ash particles grow at the
:I
bottom of the
to sufficient mass they fluidized bed are con-
deentrain from the trolled to maintain ash
fluidized bed and fall par~icles near their
into a water-filled softening temperature.
lock hopper located at (2) Agglomerated ash
the gasifier bottom. size consist depends on
Agglomerated ash-water feedI coal size consist,
.
slurry is periodically gasifier temperature,
discharged from the ash and agglomerating spout
lock hopper. configuration.
I
2 COG AS Fluidized Bed 1,600-1,700 Char from multiple- Granulated slag con- (1) !operation of cyclone 1,3,12
and a Cyclone stage coal pyrolysis is tains less than 0.5 wt combustors is dependent
Char Combustor gasified with steam in percent carbon. upori slag viscosity which
a fluidized bed. Heat is dependent on coal ash
for char gasification composition. Fluxing
is obtained by burning compounds could be re-
char fines in a ver- qui~ed to control slag
tical, cyclone, slag- vis~osity of char pro-
ging combustor operat- duc~d by pyrol~sis of
ing at moderate pres- somE! coals.
sure. Molten slag from
the combustor flows to
a water-filled vessel
located below the com-
bustor where it is
quenched and granu-
lated. Granulated
slag-water slurry is
periodically discharged
from the quench vessel
by means of a valve
system.
4-13
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
Table 4-2 (Continued)
Process Gasifier
Gasifier
Design Operating Gasifier Ash or Slag Ash or Slag
I
References( 2)
Conversion Process Notes
No. Design (1) Temperature Removal Method Characteristics
op
I
3 HYGAS Vertical 1,500-1,800 The HYGAS gasifier pro- Reported char ash con- (1) Ttie HYGAS gasifier 1,4,5,13
'
Multi-stage (Steam-Oxygen duces a high ash char centration is on the is no~-slagging.As a
Fluidized Bed Gasification which can be burned for order of 65 wt percent resul~ coal and char
Stage) steam generation and/or Reported char higher ash fusion temperatures
disposed of as solid heat value is on the must ~e sufficiently
waste. Char removed order of 5,400 Btu/lb, high to prevent slagging
from the steam-oxygen dry basis. or siJtering during
gasification stage is hydrogasification and
water-quenched in the steam~oxygen
gasifier bottom. Char- gasiffcation.
r
water slurry is period-
ically discharged from
the gasifier by means
of a water-filled lock
hopper system.
4 Texaco ·Partial Oxidation Slagging 2,000-2,800 At the temperatures Granulated slag size (1) T~e Texaco Partial 1 '6
Entrained used in this oxygen- consist is coal Oxida~ion gasifier oper-
1
Downflow blown gasifier most dependent ates at a temperature
coal ash is converted Slag carbon concentra- appro~imately .SOF 0 above
to slag. Most of this tion is 2 wt percent coal feed ash fusion
slag is captured, or less tempe~ature. Coals with
quenched, and granu- high ~sh fusion tempera-
lated in the water- tures 1require more oxy-
1
4-15
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
Table 4-2 (Continued)
Gasifier
Process Gasifier Design Operating Gasifier Ash or Slag Ash or Slag
Conversion Process ~otes References(2)
No. DesignCl) Temperature Removal Method Characteristics
OF
5 Exxon Donor Solvent Fluidized Bed N.A. Three types of coke re- Estimated total coke ash (1) Several approaches 7
sult from the EDS is 66 wt percent. for treatment of frac-
Flexicoking approach to Dry Coke Fines: Bulk tionation bottoms are
treatment of liquefaca- Density, 25 lbs/ft3 being eval~ated for
tion process fraction- Size Consist, 100 per- the EDS Process. Other
ation bottoms: dry cent minus 20 microns coke gasification
coke fines, coke Coke Slurry: 60 wt per- processes include
slurry, coke chunks- cent moisture after Texaco Par~ial Oxida-
agglomerates. Dry coke vacuum filtration .
t 1on Gas1.fl.~cat1on.
.
fines are removed by Chunk Coke: Bulk Den- I
I
cyclones from the low- sity, G~ 1L~/fl3 ·:
Btu fuel gas resulting Size Consist, 1/4-1 '
from coke gasification. inch mean size
Coke slurry results
from water scrubbing of
the low-Btu gas result-
ing from coke gasifiGa-
tion •. Coke chunks and
agglomerates are peri-
odically removed from
the gasifier bed.
..I
6 Exxon Catalytic Fluidized Bed 1,300 Char resulting from Not Available (1) This is a relatively 8,14
Gasification gasification is water new gasifi~ation process
quenched at gasifica- and has no~ been devel-
tion pressure and fed oped to the same extent
to ~ digester using a as the other gasifica-
lock hopper system. tion processes consid-
Char is digested at ap- ered in this table.
I>
proximately 300°F with I
7 SRC-I and SRC-II Slagging 2,000-2,800 For development of con- See Process No. 4 (1) For SRy-I Texaco
and Entrained ceptual ash/slag re- Partial Oxidatio~ gasi-
8 Down Flow moval flow sheets fication of coal was
'SRC-II fractionation assumed to'be used for
bottoms are assumed hydrogen production.
gasified using the
Texaco Partial Oxida-
tion (Process No. 4).
SRC-I solids are
removed from liquified
coal by filtration.
4-17
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
Table 4-2 (Continued)
I
Gasifier !
Process Gasifier Design Operating Gasifier Ash or Slag Ash or Slag References (2)
Conversion Process Notes
No. Design (1) Temperature Removal Method Characteristics
OF
4-19
'i
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
gasification. Therefore, for ash/slag removal flow sheets development,
these solids were specified to be disposed of without gasification. Hydro-
gen for SRC-I coal liquefaction was specified as being produced from coal
gasification. The Texaco Partial Oxidation Gasifier is considered a likely
gasifier for this purpose.
Two basic types of gasifiers are identified in Table 4-2; slagging (COCAS
combustor and Texaco Partial Oxidation) and non-slagging (U-Gas, HYGAS,
EDS, and Exxon Catalytic Gasification). Operation of both types are
affected by ash fusion or slagging characteristics. Obviously, in the case
of liquefied coal fractionation bottoms gasification, other factors will
affect gasifier operation, but conversion reactor feed coal mineral matter
composition is probably the most significant. In.the notes portion of
Table 4-2 an attempt is made to qualify coal ash fusion characteristics
effects. However, detailed consideration of the effect of coal ash fusion
characteristici on gasifier operation is outside the scope of this report.
Kentucky Illinois
Pittsburgh
Coal Ash No. 9 No. 5 (1) Seam Coal
Seam Coal Seam Coal
Initial Deformation
Temperature, Op 2,050 1,940 2,000
Softening
Tempel" d. l:u• t:-!, oF 2,140 2,000 2,120
Fluid
Ten1perdtu1. t:, Of 2,4.30 2,230 2,400
NotP.s:
(1) Illinoi~ No. 5 and Kentucky No. 9 are the same coal seam.
(2) Data taken from Reference (5).
4-22
·--~--~.
12N
.: .. ; ' :
0
,, '' 9E IOE
Soolo, •"" 4E 5E OF PITTSBURG
8 2E 3E 6E 7E
EMPERATURES H SEAM COAL(4)
IE 4-1 FORECAST OF ASH-SOFTENING T
Figure .
4-23
eastern Ohio. The Figure 4-1 forecast is based on SO independent mine
samples. The ash softening temperatures of these samples ranged from
1,960°F to 2,940°F. Mean softening temperature for the SO samples was 2,378°F
and their standard deviation was 271F 0 • No large-seale investigation of
ash fusion temperatures, such as that used to develop Figure 4-1, was
located for Kentucky No. 9 Seam coal.
Comparison of the Table 4-3 ash fusion temperatures with the approximate
gasifier design operating temperature~ presented in Table 4-2 indicates
that both coals appear to be compatible with thP. specified gasifiers. Data
for fixed-bed slagging gasification of Pittsburgh Seam coal (6,7) indicates
that the viscosity-temperature characteristics of the slag are acceptable
for the COGAS char cyclone combustor. Inasmuch as Kentucky No. 9 Seam
coal is successfully fired in cyclone utility steam generators, this coal
also appears to be suitable for the COGAS combustor. (Note: the design
operating temperature shown for COGAS in'Table 4-2 is for the fluidized-
bed gasifier, not the char combustor.)
Table 4-1 identifies three basic methods for feeding coal to a pressurized
coal conversion reactor or pretreater: lock hopper system, gas injection,
and slurry injection. Outlet coal boundaries (the points at which the coal
handling-preparation conceptual flow sheets terminate) established for each
of these basic methods are as follows:
4-24
Table 4-4
1, 890 1,910 1,900 2,150 2,160 2,080 2,170 2,170 2. 100 2,485 2,430 2,280
2,020 2,020 ·1, 970 2,230 2,230 2,090 2,260 2,260 2. 115 2,560 2,570 2,260
1, 950 2,030 1, 960 2,290 2,240 2. 100 2,320 2,260 2,130 2,1i20 2,600 2,350
2,000 2,010 1,970 2,150 2,160 2,100 2,200 2,200 2,150 2,320 2,350 2,310
1,960 1 '940 1 '880 2, OL10 2,050 1,960 2,130 2,125 2,000 2,300 2,400 2,100
2,060 2,050 1,980 2,480 2,370 2,265 2,500 2,405 2,280 2,620 2,610 2,480
1,850 2,320 1,850 2,500 2,520 2,310 2,530 2,540 2,340 2,680 2,650 2,600
1,915 1,900 1,975 2,135 2' 150 2' 110 2,155 2' 180 2,140 2,410 2,425 2,360
1,955 2,022 1,936 2,246 2,235 2,126 2,283 2,267 2,156 2,500 2,504 2,342
Notes:
(1) Dat~ are ·for 1~ inch- 0 size range. Illinois·No. 5 and Kentucky No. 9 are
the ~arne coal seam.
(2) LGF- lowest gravity float fraction (1.23 to 1.31 specific gravity).
(3) IGF- intermediate gravity float fraction (1.26 to 1.355 specific gravity).
(4) HGF- highest gravity float fraction (1.60 specific gravity).
.•_\,
Reference:
4-25
• Lock Hopper Coal Feed Systems - The coal inlet of the
vessel or vessels used to provide crushed coal surge
storage for the lock hoppers (Any particulate or other
emission control systems associated with the lock hopper
receiving vessels are not considered part of coal
handling-preparation.)
Except for the EDS process, ash, char, or slag produced by the gasifiers
identified in Table 4-2 is quenched in water at gasifier operating pr.essure
and then periodically r.emoved through a lock hopper ur similar mechani~Al
Most of the ash produced by the EDS process fluidized-bed gasifier leaves
entrained in the synthesis gas. This gas flows through a coke heater and
then to a waste heat boiler. After heat recovery, ash particulates nrc
4-26
removed from the synthesis gas in two stages. First, coarse particles are
removed in a dry collection system. The coarse collected dry ash is
cooled in an indirect solids cooler and then pneumatically conveyed to a
transfer point for transport to disposal. In the second ash removal stage,
wet scrubbing is used to remove fine ash particulates. Slurry resulting
from synthesis gas scrubbing is dewatered on a vacuum filter.
Ash inlet boundaries for the EDS process ash removal flow sheets were
specified to be at the discharge of the dry ash pneumatic transport system
and at the slurry discharge of the wet synthesis gas scrubbing system. A
l-imited amount of coke chunks are periodically removed from the EDS gasi-
fier. These chunks were assumed to be combined with dry ash for transport
to disposal.
4-2'7
Table 4-5
! Sulfur Sulfur
Specific
Gravity
I Percent
Weight Ash
Percent Pyrit:lc Total
HHV
Btu/lb
Weight
Percent
Ash
Percent
I Pyritic Total
HHV
Btu/lb
Percent: Percent I Percent Percent
i I
----- -. ···---
1.5 inch
1-------- ..
38 mm) x 200 mesh
-·· .. iI
I
-1.30 57.85 4.83 0.40 1.77 14,413 57.85 4.83 0.40 1.77 14,413
1 30~1 .liO
1. 40-l. 60
32.08
6.07 I
10.02
19.65
1.10
2. 72
2.47
4.00
I B,630
I 11,682
8Y.Y:J
96.00
I 6.61!
7.50
0.6S
0.82
2.02
2.15
'14,134
13,979
+1.60 4.00
I 51. 7'i 11, 8~
l. 26
12.65
2.57
7. 729 100.00 9.~:;
I 1. 26 2. ~I 11,719
Total lUU.UU
! 9.35 13.729
I
! J/8 inch (9.5 nun) x 200 mesh
!
I
-1.30
1. ~0··1.40
62.13
26.50 I 4. 70
9.98
0.35
1.04
1.77
2.47 I 14,432
13,639
I 62.13
88.63
4.70
6.28
0.35
0.58
). 77
l. 97
14,432
14. 195
l. 40-l. 60 6.35
I 18.99 2.82
12.82
3.91
13.06
11,592
7,228
94.98
100.00
7.13
9.63 iI
0.73
l. 31
2.10
2.65
14,021
13,680
+1. 60
Total
5.02
100.00 I
56.93
9.63 II
I l. 31 2.65 13,680
!
14 mesh ( 1. 4 mm) X 200 mesh
-1.30 59.60 3.90 0.23 l. 62 14,553 59.60 3.90 0.2l 1. E'2 1'1 ,553
1. :.o-1. 40 28.60 I 10. lf:i u.n 2.02 13,612 81!.20 .5.93
I 0.39 l. 75 14,248
1.40-1.60 6.40 II 21.45 2.90 4.12 11,55 7 94.60 6.98
I 0.56 1. 91 14,066
+1. 60 5.40 52.35 12.60 14.69 7,67.1 100.00 9.43 1. 21 2.60 13,718
Total lUU.UU 9.43 1. 21 t,.lin 13,718
Roof Floo
D:~:::oll2o Percenr
by Weirt
+1.90 20.00 73.50 10.50 11.80
4-28
Table 4-6
-1.30 46.28 4.85 0.40 1.77 14,413 46.28 4.85 0.40 1. 77 14,413
1. 30-1.40 :.!5.66 10.02 .1.18 2.47 l3,630 71.94 6.69 0.68 2.04 14,133
1. 40-1.60 4·. 86 19.65 2. 72 4.00 11,682 76.80 7.51 0.81 2 . .15 13,978
1. 60-1. 80 3.20 50.75 9.82 10.62 8,510 80.00 9.24 1. 17. 2.49 13,759
+1. 80 20.00 73.50 10.77 12.09 3,179 100.00 22.09 ).09 4.41 11,643
Total 100.00 22.09 3.09 4.41 11,643
-1. 3o 4<J. 70 4. 70· 0.35 1.77 14,432 49.70 4. 70 0.35 1.77 14,432
1. 30-1.40 21.20 9.98 1. 04 2. 47 13,639 70.90 6.27 0.56 l. 98 14,194
l. 41J-l. 60 5.08 18.99 2.82 3.91 11,592 75.98 7. 13 0. 71 2. 11 14,020
1. 60-1.80 4.02 54.93 9.92 10.62 8,358 80.00 9.53 l. 17 2.54 13,316
+1. 80 20.00 73.50 11.07 12.24 4,759 100.00 22.32 3.15 4.48 lt. 603
Total: 100.00 22.32 3. 15 4.48 11,603
4-29
Table 4-7
Sulfur Sulfur
Specific Weight Ash HHV Weight Ash HHV
Gravity Percent Percent Pyritic Total Btu/lb Percent Percent Pyritic Total Btu/lb
rei"C.efil P~rc~nl Percent Percent
-1.30 43.50. 2.70 0.35 2.81 14,053 43.50 2.70 0.35 2.81 14,053
1. 30-1.40 35.24 7.40 0.84 3.26 13,:178 78.74 ''· 80 0.57 3.01 13,750
J 't.0-1. 60 10.38 19.40 1.77 3.53 11 '766 8'l. I Z 6.50 0.71 3.07 13,519
1.60-19.0 2.25 4.1. 70 1. 93 5.10 9,174 91.37 7,112 0.74 J.l:.! 13,412
+1. YO 8.6) 74.20 4.93 6.69 3,618 100.00 13.18 1.10 3.43 12,255
Total 100.00 13.18 1.10 3:43 12,255
4-30
Table 4-8
Sulfur Sulfur
Specific Weight Ash HHV Weight Ash HHV
Gravity Percent Percent Pyritic Total Btu/lb Percent Percent Pyritic Total Btu/lb
Percent Percent Percent Pe-rcent
- 1.5 inch (38 mm) x 200 mesh
-1.30 41.80 4.10 0.50 3.00 13,880 41.80 4.10 0.50 3.00 13,880
l. 30-l. 40 26.70 9.00 1.14 3. 41 13,397 68.50 6.01 0.75 3.16 13,692
l. 40-l. 60 3.80 21.30 2.65 4.68 10,601 72.30 6.81 0.85 3.24 13,529
l. 60-l. 90 l. 70 36.40 3.46 7. 16 9,124 74.00 7.49 0.91 3.33 13,428
- +1. 90 26.00 74.20- 4.33 6.21 3,618 100.00 24.83 l. 80 4.08 10,878
Total 100.00 24.83 l. 80 4.08 10,878
-1.30 43.90 3.20 0.40 2.89 13,959 43.90 3.20 0.40 2.89 13,959
l. 30-l. 40 23.40 - 8. 60 1.03 3.29 13,193 67.30 5.08 0.62 3.03 13,693
l. 40-l. 60 4.80 18.90 2. 12 4.23 11,755 72.10 6.00 0. 72 3.11 13',564
l. 60-l. 90 1.40 39.60 4.40 5.74 8,629 73.50 6.64 0.79 3.16 13,470
H. 90 2fi.50 74.20 4.68 6.52 3,618 100.00 24.54 l. 82 4.05 10,859
Total 100.00 24.54 l. 82 4.05 10,859
-1.30 34.80 2.70 0.35 2.81 14,053 34.80 2.70 0.35 2.81 14,053
l. 30-l. 40 28.20 7.40 0.84 3.26 13,378 63.00 4.80 0.57 3.01 13,751
l. 40-l. 60 8.30 19.40 l. 77 J.5J 11,766 71.30 6.50 0. 71 3.07 13,520
l. 60-l. 90 l. 80 43.70 l. 93 5.10 9,174 73. 10 7.42 o. 74 3.12 13,413
+1. 90 26.90 74.20 4.92 6.69 3,618 100.00 25.38 l. 83 4.08 10,778
Total 100.00 25.38 l. 83 4.08 10,778
4-31
SPECIFIC GRAVITY
1.8 1.7 1.6 1.5 1.4 1.3
or-------------------------------~r-_,~-T~~--~--~------,
10
20
..
.
'
30
1- 1:
z I:
w I:
~ 40 I:
w
a..
I:
I:
_J
<{ I~
8f- 50
II \:
<{ I : SPECIFIC GRAVITY
g I :.
u..
u..
0 60
0
_J
w : ELEMENTARY
>- I \ SULFUR
70 I :
I :
I :
I I
I .
I
I
I
I
I
1. ELEMENTARY
1 •• ASH
FLOAT
ASH \~a~~JR ·-----_.. . . -.,. ________________
100~----~~----~------~------~----~------~------._----~
5 20 30 40 50 60 70
ASH, PERCENT
4-32
ORNL-DWG 80-4215 ETD
SPECIFIC GRAVITY
1.6
0 -
l
1:
1:
1:
.....
z I:
w I:
u
a:: I~ SPECIFIC
w I:
0.. I: GRAVITY
_j I :
<( I :
8 I :
I :
.....
<(
9 ..
LL..
..
'
LL..
0 ..
0
....J ..
w
>- ..
...
...
... ................ . .
ELEMENTARY ASH
90
ASH, PERCENT
4--33
SPECIFIC GRAVITY
1.9 1.8 1.7 1.6 1.5 •1.4 1.3
0~----------------------------~--r-~~~--~---r--~------,
10
ELEMENTARY
ASH,
20
.1::
''
1:
llI,
I
I
I
1-
I
zw I
u
I
a: I
w
Cl..
_j SPECIFIC GRAVITY
<(
0
u
1-
<(
0
....J
u. ELEMENTARY
u. SULFUR
0
0
..J
w
>-
''
I
''
I _____/
90
\ FLOAT
SULFUR
·-~---
··.,,
'•..
----
- - - - - - - . . : . __ __
.._
\ ',
\
b.
4-34
SPECIFIC GRAVITY
------------------~--------~1~.9--~1.~8~1~.7~~1~.6~~1~.5--~1.~4~1~.3~----~
Or
.
'
. t.
, a:a: ..
·a:
1:a:
. I'I: .'
I:
I:I : SPECIFIC GRAVITY
I-
z
n
I:
w
(.)
'-.1 :.
a: I :
w
Cl..
I :
I :
...J I :
<(
0(.)
I :
.I :
50
I-
<(
g
I:
u. ' \.ELE~ENTARY SULFUR
u..
0 60 .• I \.
0
...J
w I\
>-
70
······....
''
80. '.
'' '
.
'' ..
.
90
100~----~~----~--~--~----~~----~~----~----~~------
30 40 50 60 70
ASH, PERCENT
4 6 8
fOTAL SULFUR, PERCENT
4-35
Coal washabilities based on channel samples have been adjusted to account
for roof and floor dilution during mining. The adjusted washabilities are
presented in Tables 4-6 and 4-8 and plotted in Figures 4-3 and 4-5.
Comparison of the specific gravity, float ash and float sulfu~ curves·
presented in Figures 4-3 and 4-5 shows that both coals as mined have very
similar washability characterisitcs. In general, conclusions regarding
the cleanability of one coal are valid for the other. Because of this,
the washability data presented for the Pittsburgh Seam were used to
develop the coal cleaning flow sheets material balances presented in
Section 5.
1.5, the float ash and sulfur curves become nearly vertical. This means
that cleaning at lower specific gravities would not res11lt in significantly
improved RSh or sulfur removal. Also, at below 1.5 specific gravity yiPld
begins to deteriorate rapidly for both coals. Because of the shape of
the washability curves, use of heavy-medium cleaning would not result in
significantly better cleaning performance than that expected by the cleaning
flow sheets presented in Section 5.
4-36
A considerable amount of research has been performed on both Pittsburgh
and Kentucky No. 9 coals related to ash and sulfur removal using conven-
tional coal cleaning methods. These methods are well developed and have
been used commercially to_clean both coals, but with emphasis on ash
rather than sulfur removal. "Best" sulfur removals reported for both
coals are on the order of 30 percent. Sulfur removal is limited by the
fact that significant amounts.of the sulfur in the two coals is present as
organic sulfur and fine, widely disseminated pyritic sulfur.
10
20
30
0
w
z
<(
1--
w
a:
1-- 60
z
w
u
a: 70
w
11.
4-37
Table 4-9
28 mesh x 0: 10 percent
4-38
Coal cleaning plant annual operation is specified as 250 days per year.
This annual op~ration is consistent with current coal cleaning and mining
practice. If annual mine operation could be increased in the future, a
cleaning plant with a smaller hourly throughput than that result.ing from t~e
Insufficient information was found for two processes: U-Gas and Exxon
Catalytic Gasification. However, from brief review of information for the
proposed Memphis Light, Gas and Water Division- DOE Industrial Fuel Gas
De~o~stration Plant (8) , it appears that the U-Gas process may require only
limited electricity or process steam from a coal-fired power/steam plant.
Estimated conversion processes total steam requirements range from zero for
COCAS which uses extensive process energy recovery to 7.2 billion Btu/hour
4-39
for H-Coal liquefaction. These steam requirement estim~tes do not include
electricity for the coal handling-preparation operations covered by this
report or for coal mining. For SRC-II, an additional 115 ~~ of electricity
is estimated to be required for coal handling-preparation and for operation
of an integrated coal mine complex located adjacent to the conversion plant
site. Total estimated power/steam plant steam generat:i.on requirement for
an SRC-11 plant is 6.8 billion Btu/hour. The quantity of coal required
for such a power/steam plant is estimated to be 15 percent of that supplied
to the conversion plant. This is equivalent to 7,500 tons per day of rnRl.
The 7,500 tons per day coal value has been useci as the pnw8r/steam plant
coal requirement for conceptual flow sheets development.
For the conversion plant steam/power plant, Union Carbide specified use of
an atmospheric pressure fluidized-bed steam generator. This is consistent
with the steam generator design selected for the DOE coal mine-coal conversion
plant interface project. As a result, the basic steam generator perform-
ance data developed for that project was used for preparation of the flow
sheets presented in this report. The interface project steam/power plant
design was based oil information provided directly to Bechtel by Foster
Hhccler Eoetgy Corporation and information presented in the final report
of the Gener>al Electr>ic Ener>gy Conver>sion AUP.rn.at'i.t,~s Study(ECAS) sponsorerl
by ERDA, NASA, anrl the National Sdeuc.;e Foundation (NASA-CR 134949).
4-40
I
I
;Table 4-10
!
SELECTED COAL CONVERSION PROCESSES ESTIMATED
ELECTRICITY AND STEAM REQUIREMENTs(!)
I
2 CO GAS In the current COGAS commercial plant conceptual design all steam required for klectricity
I
15
Fluidized-Bed Gasification generation and process use is obtained from process heat recovery and not from any coal-
~
fired power/steam plant.
3 HYGAS
Fluidized-Bed Gasification
150 5.7 5.4 1,500 925 16.6 16
I
4 Texaco Partial Oxidation 210 3.0 2.9 1,500 925 '14.5 16
•I
Entrained Flow Gasification
9 H-Coal
Liquefaction
790 1.1 0.8 615 488 1-
,
I
17
1.1
4-.41
' '
'i
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
Figure 4-7 presents a _block flow diagram which identifies the coal handling-
preparation operations for which conceptual flow sheets have been developed.
It also shows the relationship between individual flow sheet modules or
operations. Specific operations covered by the block flow diagram are
grouped:into four general areas: coal cleaning, coal storage and blending,
coal fine crushing, and coal pulverizing or grinding. The heavy line run-
ning through the first three areas identifies operations which constitute
the reference SRC-II flow scheme. FS numbers above the coal cleaning
operations ~rea and in other areas over individual operations are flow
sheet numbers c::orresponding to _these operations.
To develop Figure 4-7, three general coal size consist ~lasses.were devel-
oped from consideration of coal feed requirements for the identified con-
version processes and other coal conversion processes. The three classes
are:
Estimated capital investment for a nominal 50,000 tons per day coal conversion
plant is several billion dollars. Most of this cost is associated with
actual coal conversion, product(s) upgrading, and environmental emission
control facilities. · Because of this large investment and the quantity of
product(s) produced, any unplanned interruption in conversion reactor coal
feed would be extremely costly. In fact, this cost is of such magnitude
that substantial investment in high reliability coal handling and prepara- .
tion facilities would be fully justified. Therefore, in developing con-
ceptual flow sheets, high operating reliability achievement was a prime
consideration.
For proven processes, well engineered and constructed plants, and well
managed plants, all of which were postulated, high operating reliability
can be achieved by providing appropriate maintenance time or by equipment
redund~n~y. Both approaches were used. For all operations before coal
live storage (primarily coal cleaning) single conveyor iines, when prac-
tical, were deemed consistent with high operating reliability. These
operations have an annual operating requirement of only 250 days (nominally
5 days per week). This is sufficient time for required maintenance. Also,
the clean coal live storage design capacity specified is sufficient to
accommodate most failures that could occur before live storage.
For coal live storage and all following coal operations redundant equip-
ment is specified. These facilities must operate 365 day~ ~er year,
24 hours per day. The redundancy specitied is believed sufficient to meet
this requirement. Spare equipment and excess equipment capacity would be
used to compensate for equipment out of service for maintenance or un-
scheduled repair.
4-44
NOTES:
REfERENCE FLOW SHEET: FS-1 ALTERNATIVE fLOW SHEETS: FS·1·1 AND FS·1·1 ' ATMOSP ... ERIC
PRESSURE
f"LUIOIZEO 8(0
AUN.OF-UINE COAL- TI-llS COAL IS PROOUCEOSY A LARGE. INTE-
GRATED COAL MINE COMPLEX LOCATED ADJACENT TO THE COAL
TO POWER} STEAM GENERATOR CONVERSION PLANT SITE. AFTER RUN-QF·MINE COAL BREAKING,
-
STE4U PL.IINT
v CLEANING. ,V,D CAlJSHING TO 2 IN. X O. THE COAL HANDLING
AND PREPARATION O~ERATIONS REQUIRED FOR BOTH RlJN-OF·
l
I'
FS-7 F&B
I I. '· I PI!I!DINQ
_f MIN( COAL 4.NO COAl ":RAN!:r'OnTCO TO THE CONVE:RiiiON
r
B'IIITOTAL 0 tAL TERNATE: 1/41N. i· 100 MESH! 161 U.(jAS
I
1(41N. •
I
1/4\N, MO
.I
rl DEAD
STORACE
MOISTURE
TODRV
THERMAL
DRYING 191
3"-. TOTAL
MOISTURE
DRY SCREENING
-1/&IN. I PARTICULATE
COLLECTIONI91
PARTICULATE COAL LOCK
• PRESSURIZED
~LANT SITE JI\RE IDE~TICAL.
J
I eCYCLONE
l OAS
•0 FIED. BROKEN RUN-Of-MINE COAL WOULD BE CONVEYED 01
L!....".R!~.TATNC~
~T -"" ./ - ., COARSE COAL I I FS~ !• I~~~:· PARTICULATE
• HOT FLUE
I
AECTL V TO CRUSI-II"'C "'NO THEN TO COARSE COAL STOR ... GE.
RECEIVINCi
21N. • 0
12g\ ~:~~~~t~~~~G I
COAl..
INJECTION
1•1 COARSE AND FINE COAL CLEANING ALTERNATIVES- CONSID·
J:
PROJECT SCOPE I TOTAL I_
l._(; ~LT~~~~N
SEPARATION ,.JA00L0MERATI0Nj
LOCK
• LOW.PRESSURE
j L
lSI FLUE GAS :SOURCE -FLUE GAS Flt.UUIHt.U 1-UH t'Un ANI.J f'UL·
VERIZEO COAL DRYING AND TRANsPORT IS PROVIDED FROM
THE POWER/STE4M PLANT.
r
TOfiNE '\...,..-
LINE O[:;IGNATIONS
CRU~INCi _./ -----...
FLUEGASI51
CLASSIFICATION
~ , GAS PHASE
CLASSIFIER
~·2'!i.T
A tBRIOUf.TTINCij
OISTURE • PELLETIZING
........
[L_• lO WESH • 0 (ALTERNATE: 20 • 100 MESH! 161 l SLURRYING
FEEDIN(i
I:>OMESH•O
TEKACO
PARTIAL UlTRAFINES SEPAR ... TION ALTERNATIVES- THE ALTERNATE
::0 •<LURRVINO
FS-3, FS ... FS..·I. • SLIJFIRY OXIOATION CONVERSION REACTOR COAL FEED SIZE CONSISTS ARE EST!·.
INJI:CTION
J~~0'~~ATCR I
?r . . . ··-·. ,
AND "S-5 MATES OF 51ZE CONSLST5 THAT MIGHT Elf sPECIFIED IF COA.l
- - SIZED COAL TRANSPORTED TO CONVERSION PLANT SITE Ill
. FINE COAL ULTRAFINES SEPAHATION IS REQUIRED DR ECONOMICALLY
-- RUN 0~ MINi< COAL FRCIW llo MININr':OPFRAT!ON LOCATED ADJACENT
TO THE CONVi:RSION PLAN1 SITE 111 ....lJN.oO I I JUSTIFIED FOR CONVERSION PROCESSES REQUIRING FINE COAL
- - SOLID REFUSE
-+-+-
COARSE COAL fOR ELECTRICITY AND CONVERSION PROCESS
SHAM GENERATION L._c_•_c'_"_'L_L_ __Jr- 8 foH:SII • 0 IAL TtOnNATEI II • 100 MliSHI 161 :~~:~~G 9MfSH ~ (XXON
OONOR
:>ULVLN:
FEED.
L. J
CATIILYTIC
I
1• MESH X 0 AND PARTIALLY DRY IT BEFORE IT IS SWEPT INTO
J
GA~Ir ICA TION
TO WET MESH~ 0 PRESSURIZED THE BALL TUBE MILL.
l
2Q
GRINDING ., eRQQ, LOCK.
,....;l.:Lc:;--"'"''"'"'us,.e_ ~-=:: I HYCAS COAL FEEDING - FOR THE HVGAS GAIIFICATIOfo~ f'i-10·
I
REFUSE
COLLECTION TREATMENT
rs-11
I y SLURRYING
FEEDING
LI1MESH. 0 CESS, COAL IS ASSUMfD TO BE FED TO A PRfTREATMUfT 'VESSEL
70'11. MINUS 200 MESH
ICDAU .I RATHER THAN TO THE HYGAS CONVERSION REACTOR. PRE-
I
AND TRANSPORT TO SOLVE "'T SRCoANO 1
~~g;~liON ~=':::":L:UE:N:::T=-~:2!:~......1
1 • SLURRY SOLVENT TREATMENT IS REQUIRED TO REDUCE COAL AGGLDI'-ERATION
IL____ REFUSE
j+-~=:O....l•OIL
28'-'ESH 0
K
I INJECTION SLURRY DURING GASIFICATION
I:
AGGLOMERATION
t FILTERATION (91 A CVCLONE-GACHOUSE SYSTEM IS PROVIDED FOR .. ARTICULATE
t~F~LU~E~C~AS~IS~;t~~~~·~u~LV~E~Ro~<o~NO~~
l======~t:~o~e!~N~TR~A~I·~-~'N:T:~~,~~-~,N~US~~~~=:~~~===
SLURRYING
t CYCLONING 110'Ji.MINUS COLLECTION. THf COAl FAOiol THE CYCLONES IS fED TO ULTRA·
FEEDING
• CLARIFICATION 100 MESH H.COAL FINES SEPARATION AND COAL PAATICUL.ATE FROM THE a.r.GHOU$1
•f
~-~.;·~U~LV~E;::Ro~zo:;:NG~=====================::;;;;;;;==================================~J:::::~==~
TO
•
21N.•O eSOWLMILL tCVCLONE 100ME511 :::rJ • SLURRY
INJECTIO"' J~~~ENT -I IS TAANSPOATIEDTD UL TRAFINIES AGGLOMERATION.
~1--CO-.-l-ST-O-RA-G-E-~
BAI..L. TUBE MILL 171 t BAG HOUSE SLURRY
J . . - - - - - - - - - - - - - - . , . C O : - , - l - : C - L E : - . , . - , - - - , . - : G : - - - - - - - - - - - - - -... COAL FINE CRUSHING COAL PULVERIZING OR GRINDING
AND BLENDING . igure 4-7
Coal Handling and preparation operations
block flow diagram
4-45
. 'i
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
·'
flow' sheets development. This, however,. does not mean that following live
storage all coal handling-preparation flow sheets consist of five identical,
parallel, equipment trains. When acceptable reliability was judged possible,
less than five ~oal handling-preparation trains are specified for supplying coal
to five conversion reactor coal feed systems. Likewise, when current equip-
ment capacity limitations indicate that more than five coal handling-prepar-
~tion·trains would ~robably.be required, more than five are specified.
Run-of-mine coal received from the adjacent coal mine complex is broken ·
·.
from 12 inch x 0 to 6 inch x 0, conveyed to cleaning plant surge storage,
and then screened at 3/8 inch. Screening at this size results in a coarse
coal size consist that is well suited for a coarse coal cleaning jig. If
screening were not used, minus 3/8 inch coal would reduce coarse coal jig
separation efficiency.
Jigs were the only conventional coarse. coal cleaning method considered.
The other possibility, heavy-medium cleaning, was excluded from consideration.
Three alternatives were considered for fine coal cleaning! fine coal jigs,
water c·yclones, and tabling. Fine coal cleaning flow sheets were developed
for each of these alternatives.
4-48
4.3.2 Coal Storage and Blending
Main coal live and dead storage is provided·after coal cleaning. Not only
is the area required for storage reduced by refuse removal, but coal crushed
to a nominal 2 inch top size is easier to handle and pack than coarser coal.
Coal si6rage-blending facilities could also be ~ocated ahead of coal cleaning
facilities. Advantages associated with this arrangement include reduced
co~l cleaning facilities surge storage· requirement, possibly smaller clean-
ing facilities due to the possibility of longer annual operation, and
cleani~g·of blended coal~ -In some situations, these advantages may outweigh
those associated with live-dead storage after coal cleaning. The flow
schemes·and cle~ning major·equipment list~ presented in this report are
genetally applicable· to both cleaning location alternativ~s.
Blending can improve operation of some types of coal cleaning plants, but those
using cleaning·methods identified in Figure 4-7 are·not significantly improved.
In fact, the identified methods accomplish some blending during cleaning.
Heavy-medium coal clean1ng would benefit most from feeding of blended coal.
For coal' conv~rsion plants where heavy~medium cleaning is justified, the
beneficial effects of cleaning blended coal may be of sufficient magnitude
to justify location of live storage-blending ahead of coal cleaning.
4-49
Because of the live-dead storage economics conclusion resulting from the
interface project, a live storage design capacity of 500,000 tons was
established for conceptual flow sheets development. Analysis of probable
differences between coal production by a mine complex located adjacent _to
a conversion plant site and actual conversion plant· coal consumption on a
daily basis· indicates that this capacity is sufficient to limit any dead
storage facility use to only emergency situations. Emergency situations
are defined as no coal production or below planned production due to labor
grievances, unforeseen mining conditions, or a mine disaster. The actual
analysis was part of the interface project. For the particular conditions
assumed, such as mine complex operation of 250 days per year and conver-
sion plant operation of 365 days per year with 35 days maintenance allow-
ance for individual conversion plant trains, this analysis show~d that at
live storage capacities below approximately 500,000 tons, coal had to be
periodically moved in and out of dead storage to balance mine production
·with conversion plant consumption. This use of dead storage w.as not a
consequence of any emergency situations. A ·graph of how live storage
coal inventory could change with time over a period of 780 days is pres-
ented in the interface project final report. (1).
4-50
4.3.3 Coal Fine Crushing
by feeding coal below the fluidized bed rather than from the bed top.
4-51
4.3.4 Coal Pulverizing and Grinding
Only one process in Table 4-1 requires pulverized coal; H-Coal. There are
two obvious ways to meet this feed requirement: dry pulverizing and solvent
grinding. Of these two approaches, dry coal pulverizing is a well developed
technology, while coal solvent grinding has only been attem~ted experimentally.
Dry pulverizers (mills) are used exclusively for pul~erized coal-fired steam
generators., utility and· industrial; and for many other coal-fired prpcesses. ·
Currently, several different designs of dry coal mills are commercially
available. The individual capacities of these mills for bituminous coals
range up to 100 tons per hour. Further, current dry mill design can prob-
ably be scaled up, when markets st,u;:h as coal conversion exist, to ·c:apac.ities
in the 200 to 300 tons per hour range without sacrificing reliability.
Mills of similar design to coal mills with capacities in excess of 300 tons
per hour are currently used for pulverizing cement.
Conceptual designs and cost estimates were developed for two coal pulveriz-
ing alternatives in the toal mine-coal conversion plant interface project~
The flow sheets and major equipment lists, which are part of .these concep-
tual designs, are believe to be adequate for Union Carbide's coal handling-
preparation equipment requirements survey. Therefore, no additional con-
ceptual coal pulverizing flow sheets were. developed.
4-52
to build very large wet mills could have a direct bearing on the minimhm
number of grinding lines ~n projected conversion plants and on their cor-
responding capital cost.
Wet grtnding is used at the Black Mesa, Arizona, coal mine to prepare coal
for slurry pipeline transport. The coal size consist produced at Black
Nesa is, however, considerably coarser than the 70 percent minus 400 mesh
size consist required for H-Coal and is purposely skewed - 16 to 20 percent
minus 325 mesh and 30 to 35 .percent plus 48 mesh.. To accomplish this special
size consist, open-circuit, rod mill grinding is used. From Black Mesa,
slurried, ground coal is piped 273 miles to the 1,580-MW Mohave power plant.
Here it is dewatered and pulverized further in conventional dry coal mills
~q a nominal size consist of 70 percent minus 200 mesh.
4-53
separation operation. For flow sheets development, the SRC-I solids were
assumed to be disposed of directly, i.e., they were not considered to be
an acceptable gasifier feed.
Figure 4-8 presents possible operations that could be used for ash/slag
removal. In reviewing the ash/slag operations required for each of the
nine specified conversion processes, the possibility of energy recovery
was evaluated. However, in all cases where it appeared warranted, it is
already part of the conversion reactor (see Subsection 4.2). Therefore,
only flow sheets for ash or slag dewatering, when required, and transport
to a disposal site were developed.
4-54
>"
z .
::J
0
•CENTRIFUGE
• SPIRAL
• RAIL CARS
•TRUCKS
• MINEFILL
0
;::.,
<1::0
EXXON
CATALYTIC
ASH-WATER "s~
zo GASIFICATION SLURRY ~
:r
Q~
"'
>-o
~ .. "a:
EXXON DONOR I ff' EXXON DO~OA
SOLVENT
ASH·WATEA
SLURRY
~ ....
SOLVENT
I GASIFIER
DAY ASH
"
~___...,r- 1--,r-
z z
0
0
;::., u;
a:
<1::0
~ ....
TEXACO GRANULATED
zo PARTIAL
F-13
Q~ SLAG·WATEA TRANSPORT
>-o
~ .. OXIDATION
SLURRY
0
u
~ PA~}~f!ooN
SOLID
WASTE
SLURRY PIPELINE
OLIOS TRANSPOR
SOLID
WASTE
IMPOUNDMENT
DISPOSAL
SAC·II
ff' v
v -- - ___,. •SCREEN
SLURRY
• PIPELINE
SLURRY
- e LANDFILL
IJ
• THICKENING
vv •SLURRYING
eFIXATION
14-- • LANDFILL WITH
FIXATION
TEXACO GRANULATED • MINEFILL
PARTIAL
OXIOATICW SLAG·WATER
v
SLURRY
v RECYCLE WATER
H·COAL
v
v
v
COG AS I CHAR COGAS
GASIFIER ~NO
GRANULATED t::
v
I COMBUST DR SLAG-WATER
SLURRY
v
SAC·I Ill
I SOLID WASTES
t::
I v
Fi.,re 4-8
ASH/SLAG REMOVAL OPERATIONS
BLOCK FLOW DIAGRAM (41
THIS PAGE·
WAS INTENTIONALLY
LEFT BLANK
at or near gasifier operating pressure and_could be exposed to high
temperatures. To reliably operate under these severe conditions new
or modified ash/slag crusher or grinder designs may have to be developed
and demonstrated.
Table 4-11
Ash 63.5
Calcium Oxide 14.5
Calt.:ium Sult'ar:~ 20.6
Residual Carbon 1.4
4-59
report. With the possible exception of equipment required .for underground
mine fill dispos.al, existing materials handling equipment, such as doz.ers and
scrapers, are capable of meeting disposal site materials handling requirements.
of ash. These agents can, for some types of wastes; tie ·up physically or
chemically harmful compotinds in a solid matrix from which their leachability
is very low. Use of such agents, some of which are proprietary, for large
quantities of solid wastes is relativelynew, but a considerable amount of
research is currently being done in this area. Fixation of sl11dges produced
by lime and limestone flue gas sulfur oxides control processes is an example
of one area where fixation is being seriously evaluated.
The solid wastes handling conceptual flow sheets are compatible with use
of fixing should its use be required. However, no equipment is provided
for addition and mixing of fixing compounds.
4-60
Section 5
This section \iesc·ribes ·conceptual flow sheets for coal handling and prepa-
ration and ash/slag removal operations that will be required by commercial
c·oal conversion plants. Accompanying these flow sheets are major equipment
lists. Design bases established for the flow sheets ~nd the general approach
used in their development are presented in Section 4.
All flow sheets are keyed ·to ·the coal handling and preparation operations
block flow diagram, Figure 4-7, or the ash/slag removal operations block
flmv diagram, Figure 4....;8, presented in Subsection 4. 3. F S designations
on these· block flow diagrams are flow sheet numbers. These numbers are
located over the coal cleaning general operations area and over individual
operations:· When more than one single dash FS number, such as FS-3 and
FS-4, are shown for an operation, multiple flow sheets are required to
meet the coal feed requirements for· all coal conversion processes. In
general, flow sheets with double dash numbers, such as FS-4-1, are alt·er-
n~tiv~ flo~ sheets for specific operations.
Most flow sheet operations require multiple equipment of the same type.
These are frequently arrange~ into independent trains consisting of several
operations. In such flow sheets, only a single piece of equipment is shown.
··Numbers in parantheses after equipment titles are the actual equipment
quantities required for a specific operation.
5-l
5.1 FLOW SHEETS AND MAJOR EQUIPMENT LISTS GENERAL QUALIFICATIONS
All coal flow sheets presented in this repor.t involve handling and prepara-
tion of very large quantities of material. Only one United States coal
mine, a western strip mine, currently produces the quantity of coal speci-
fied for these conceptual flow sheets; 16.5 million tons per year. None
of the mines currently operating in either the Pittsburgh or Western Kentucky
coal seams have productions which even approach this tonnage. A coal-fired
power plant capabl,e of annually consuming 16.5 million· tons of coal would
have a capacity rating on the: order of 6,200 MV1. This is nearly twice the
rated design capacity of the largest U.S. coal-fired power plants •.
Design of facilities with the capacities dealt wi,th in this report will
require considerable engineering effort. ·Fina~ equipment sP.lPrtions ~ . . ..
and facilities designs will be the result of numerous trade-off studies
involving both technical and economic considera.tions. Flow sheets and
equipment specifications for these facilities will reflect the results of
these studies and detailed engineering.
In comparison with the engineering effort required for actual plant design,
that associated with the flow sheets and equipment lists presented in this
report is small. Further, these flow sheets are not site-specific, provide
cual fur nine different conversion prncesses plus fluidizcd~bed steam gen~
5-2
equipment power, major overall dimensions, recommended materials of con-
struction, specification requirements, and gener.al comments. In the
Specification Requirements and Comments part of these lists, frequent
reference is made to equipment of "standard design." This ter·m is used to
identify equipment that is currently used comme.rcially for coal operations
at or above the equipment's s~ecified design capacit~: No further develop-
ment or demonstration is required for reliable use of equipment so speci-
fied. However, because of capacity requirements, most equipment specified
as standard would not be available as off-the~shelf items. Most would have
to be custom fabricat~d from proven· design d~~a. As a result, purchase
lead times required for standard equipment can be substantial even though
no development or demonstration is required.
For selected major equipment that are repeatedly specified, general perform-
ance requirements specifications were prepared. These.are presented in
Appendix A and equipment covered by them are identified in the equipment
lists. The general performance requirements specifications are for large
belt conveyors (including tripper conveyors), gravimetric belt feeders, and
cage mill fine crushers.
5-3
Actual equipment reliability depends on four main factors, all of which
must be adequate if high reliability is to be achieved. These are:
In some plants, one or more of the latter three factors have been neglected.
As a result, though all equipment is compatible with high operating reli-
ability, high reliability is not achieved. Considering the costs associated
with coal conversion, neglect of any reliability dependent -factors would
probably be economically disastrous.
5-4
equipment such as conveyors. An important consideration in this approach
is the reliability of equipment, such as flop gates, used to alter coal
flow path.
5-5
In the conceptual flow sheets extensive use is made of large-capacity
belt conveyors. Design of conveyor systems of the capacity specified,
like design of storage bins and silos, requires extensive layout studies
and design calculations. In fact, conveyor design is greatly affected
by storage requirements and is a principal cost associated with storage
facilities. Bin and silo heights frequently determine the length of
conveyors and obviously affect conveyor power requirements. Because of
the engineering required to completely specify conveyor systems, conveyor
power requirements presented in the equipment lists are only rough
estimates. Conveyor belt widths are also estimates, but are not as sub-
ject to change as much as the conveyor power estimates.
5-6
consist. Since the first tw~ are plant layout dependent, the baghouse
design capacities and power requirements specified in the equipment lists
are only rough estimates.
5-7
wetting·, penetrating, and spreading properties. It is more effective in
contacting, confining, and agglomerating the micron sized dust than water
alone. Actual design of individual spray systems depends on their location,
the quantity of dust to be suppressed, and whether or not they are used in
combination with other dust control equipment.
Three conceptual flow sheets and major equipment lists were developed for
coal cleaning. One set provides for both coarse and fine coal cleaning.
The other two represent alternative methods for. fine coal cleaning. Mate-
rial balances for these flow sheets are based on the Pittsburgh Seam coal
washability data presented in Table 4-6 and Figure 4-3 in Subsection 4.2.
This washability data is very similar to that developed for KP.ntnrky No. 9
Seam coal. And, as a result, the material balances are also applicable for
the Kentucky No. 9 coal.
The coal cleaning operations, coarse plus fine, are designed·to clean
21.8 million tons per year of ROM coal to produce 16.5 million tons per
year of clean coal. Clean coal is conveyed to live storage-blending or
dead storage. Coal cleaning design conditions are presented in Table 4-9.
Fluw sheet FS-1 presents the flow scheme and material balance developed for
coarse coal breaking, cleaning, and coarse clean coal crushing. It also
presents one alternative for fine eo.:tl cleaning. The inlet boundary for
this fl?w sheet is at thP. rlischar~e point(c) of the int~grated coal mine
complex transport coal receiving facility discharge r.nmrPynr(c:) (iii!Q
Figure 4-7, Coal Handling and Preparation Operations Block Flow Diagram).
This conveyor(s) delivers coal to the breaking operation at a design flow
rate of 4,353 tons per hour, 20 hours per day.
5-8
>--~---- -- ~ -.-- ~
I
I
I
I ~
mtl
FLOTATION
I REAGOe;l~ln
s;~
FLOCCULANT
I ~SYSTEMIII
TO REFUSf COLLECTK:IN I
~
ANO TRAHIPORT
REfUSE
MOISTURE TRAP lilt
TO ~~.TMjOSPHERE
RAW COAL
-..on~
SAM~LE VACUUM
PUMP_!II
RAW COAL
CONVEYOR NO. 2 111
--·
LINE DUIGMAT!O!fl
"'
z
;;
;
u
~
w
z
;;:
CLEAN COAL
2 IN. • 0
CLEAN COAL
SAMPLING STATION 111 UNION CARBIDE CORPORATION- NUCLEAR DIVISION
OAK RIDGE NATIONAL lABORATORY
2 IN. X 0
CLEAN COAL CONVEYOR 111 CONCE."'UAL FLOW SHEEn DEVUQf'MEHT FDA COAL
28MESH X 0 CLEAN COAL
.SAMPLE CONVERSIOH I'UoHT COAL HAHOUNG-PAEPARATIOH
AH0 ASHJSLAG A(M()VAL DP'EAATIONS
CONTRACT NO. lUX- .sn•v'
·- ....
~ 0 0 0 0 0
.....
0 0
......
0
,.
~
...
~
,.
.....,
<&
,.... ~
,.
<& <8> <& <8>
... ~ ·~
... ~,.
0>
...
4} ~ ~ ~ ~
,.
~ ~ ~
..
~ ~ ~
.....
- - - - - - - (036 '·""' -
.....- ..""...- -
-
... I
526 26 2 278 1,707 1.S29 1,649 347 1,182 38 >.038 >.038 324
ORY SOLIDS, TONS/HOUR 2 1,4'19 2,612 254 I .SIS 3"
-
., 2,d58
tl,IIO
50
2.912
..•
'·'""
5,318
i•..lll
-
m
282
"'
>0
7.384
lt.IIOI
75
>.883
070
3.6
5,481
;1!.020
-
,.,.
80
70
5,401
~~.~
- '·""'
-
926
.7,S97
70
3.784
R.1nll
55
2.184
7R10
30
,
>.800 2.383
9.452
-
4.697
12.192
65 30
120
20
4,0S2
p,4$0
" .
""'
220 372
12
>.285
),036
26 ..
2.757
10.444
1,164
'"
It
-
-
-
4.D7S
18,604
""
740
,.
2.220
..
4,23:5
16.384
2!i2
"'
"
467 4.607 4,U4
16.456
585
1,632
iU
250
300
"'
333
1,332
-
...,
3.300
I o.o
752
IG.f
9.515
39,CZ2 8£CKT£t..oa OATE
JULY 1171
IFLOWSHEETNU¥8(111
I fl·1
5-9
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
i
I
MAJOR EQUIPMENT LIST
JIG CO~SE
I
AND FINE COAL CLEANING
REFERENCE FLOW SHEET FS-1
i
Number HP
Equipment Title Design Rating and Description Specification R~quirements and Comments
Required Each
:
COAL BREAKING EQUIPMENT
2 ROM Coal Receiving Hopper - Design Capacity: 150 tons 1
Mass flow bin with lined bottom for even flow
.
promotion. I .
2 ROM Coal Feeder 20 Design Capacity: 2,600 tph Standard design ap'ron type feeder.
2 ROM Coal Grizzly 7~ Design Capacity: 2,600 tph Grizzlies of this ~apacity
are s~andard
equipment.
Nominal Opening: 4-3/4 in. Manganese steel abrasion resistant deck.
Size: 60 in. X 12 ft
2 Rotary Breaker 150 Design Capacity: 600 tph Breakers of this c~pacity are standard equipment.
Diameter: 14 ft Screen material islabrasion resistant steel.
Length: 30 ft
Openings: 6 in.
1 Raw Coal Conveyor No. 1 200 Design Capacity: 5,400 tph See General Conve~or Specification.
Width: 60 in.
Estimated Length: 600 ft
i
1 Coal Breaking Area Baghouse 150 Design Capacity: 50,000 acfm Standard Baghouse ~System.
Dust Collection·system I
I
I
1 Raw Coal Silo Area Baghouse 60 Design Capacity: 20,000 acfm Standard Baghouse System.
Dust Collection System I
I
I·
5-11
I .
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
MAJOR EQUIPMENT LIST
JIG COARSE AND FINE COAL CLEANING
REFERENCE FLOW SHEET FS-1
Number HP !
Equipment Title Design Rating and Description Specification Requirements and Comments
Required Each
16 Raw Coal Screen Feeder 20 Design Capacity: 300 tph Standard Design Vibrlting Feeder.
I
Width: 36 in.
J
16 Raw Coal Screen 30 Design Capacity: 300 tph Standard Design Double Deck Vibrating Screen.
Type: Double Deck Vibrating Rubber deck construction.
Size: 8 ft X 20 ft
Openings: 1~ in. and 3/8 in.
1 Middlings Crusher 250 Design Capacity: 280 tph Standard Design Ha~ermill.
Type: Hammermill i
9 Clean Coal Dewatering Screen 20 Design Capacity: 250 tph Standard Design Single Deck Vibrating Screen
Type: Single Deck Vibrating Stainless Steel Wedge Wire Deck.
Size: 6 ft X 10 ft
2 Clean Coal Crusher 600 Design Capacity: 900 tph Standard Design Four Roll Crusher.
Type: Four Roll Crusher
Size: 36 in. X 60 in. I
I
10 Thickening Cyclone - Diameter: 24 in. Several standard deJigns of coal classifying
cyclones are currently available.
Cast Ni-Hard constrJction with cast
refractory apex noz~les.
I
1 Clean Coal Conveyor 200 Design Capacity: 5,400 tph See General ConveyorI Specification.
Width: 60 in. I
1 Refuse Conveyor 50 Design Capacity: 1,600 tph See General Conveyor Specification.
I
Width: '48 in.
5-13
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
MAJOR EQUIPMENT LIST
JIG qOARSE AND FINE COAL CLEANING
~FERENCE FLOW SHEET FS-1
Number HP
Equipment Title Design Rating and Description Specification ~equirements and Comments
Required Each
3 Fine Coal Jig 350 Design Capacity: 600 tph A three product, Batac, air-pulsed jig is
Size: 180 sq ft specified for finJ coal cleaning due to the
Type: Batac even bed air disttibution achievable with this
jig design. /
The specified jig~has six compartments and
two elevators. ~
600 tph Batac jig~ are currently used for fine
coal cleaning.
·i
3 Fine Refuse Dewatering Screen 10 Design Capacity: 120 tph Standard Design Horizontal Vibrating Screen.
Type: Single Deck Vibrating Stainless Steel Wedge Wire Deck.
Size: 4 ft X 8 ft
6 Fine Clean Coal Dewatering Screen 15 Design Capacity: 165 tph Standard Design Single Deck Vibrating Screen.
Type: Single Deck Vibrating Stainless Steel Wedge Wire Deck.
Size: 8 ft X 20 ft
I
6 Clean Coal Vibrating Centrifuge 75 Design Capacity: 165 tph Standard Basket Type Coal Centrifuge.
I
Stainless Steel Wedge Wire Basket.
I
rl
Size: 2 banks of six cells 1:
:r
1 Clea11 Coal Vacuum Filter 200 Design CAparity: 200 tph Standard Design Disc Vacuum Filter.
Type: Disc Filter
Size: 12~ ft diameter x 13 discs
2 Refuse Solid Bowl Centrifuge 300 Design Capacity: 100 tph Standard Design s.9lid Bowl Centrifuge.
Size: 36 in. X 96 in. II
---
5-15
'i
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
Coal conyeyed to breaking (12 in. x 0) is discharged into receiving hoppers.
From here it is fed by apron feeders onto fixed grizzlies having nominal
bar spacings of 4-3/4 inch. Grizzly oversize, nominally plus 6 inch coal
falls into a rotary breaker where it is reduced to a top size of 6 inches.
Rock and mine debris not crushed are rejected from the breaker. This re-
ject material is discharged to refuse collection and transport.
Coal from the rotary breaker discharges onto a conveyor where it combines
with grizzly undersize coal. Broken coal is then conveyed to a sampling
station where it is continuously sampled . . A flow diagram for a typical
coarse coal three stage sampling station is presented in Figure 5-l. As
coal discharges from raw coal conveyor No. 1 onto conveyor No. 2, a primary
sample is cut by a primary sample cutter. This sample is crushed to a top.
size of 3/4 inch in a hammermill. Crushed primary sample is discharged
from a surge hopper onto a belt feeder where it is sampled by a secondary
sample cutter. Excess crushed primary sample is diverted to the main coal
flow. The secondary sample is crushed to 8 mesh x 0 and sampled by a con-
tinuous rotary tertiary sampler. The tertiary samples are statistically
representative of the entire coarse coal flow and are reasonable quantities
for laboratory analysis. To avoid chute plugages during winter operation,
the raw coal sample station should be totally enclosed in an insulated. and
heated building.
silos. These silos at their feed and dishcarge points are equipped with
a baghouse coal dust collection system for particulate emissions control.
Collected coal from the baghouse system is fed to at least one of the
silos. Vibratory-activator feeders located under the raw coal surge
storage silos feed coal onto the coal cleaning plant feed conveyor.
The feeder disch~rge points constitute the outlet boundary for the
cleaning plant surge storage operation identified in Figrire 4-7. The boundary.
5-18
between this operation and the preceding breaking operation is at the raw
coal'sampl.ing.station .. As indicated in Figure 4-7, an alternative raw coal
surge storage method to use of silos is use of an open stockpile.
Only.one method was considered for coarse coal cleaning; jigging followed by
clean coal screen dewatering. Consideration of the other general method
used commercially for coarse coal cleaning, heavy-medium cleaning, was not
part of project scope (see Subsection 4.2.5). An automatic, two-compartment
..
Baum-type jig, is specified for coarse coal cleaning. This jig produces
three products: clean coal, mid~lings, and refuse. Middlings and
refuse are removed from the jig by bucket elevators and do not require
additional dewatering. Refuse is discharged onto:a refuse conveyor.
Middlings are crushed with a hanunermill crusher to 3/8 inch top size,
slurried in water, and pumped to the fine coal cleaning operation.
C.lPRn coal from the coarse coal jigs is dewatered on vibrating screens.
Screen oversize is crushed to 2-inch top si.ze in roll crushers aud
discharge~ onto a clean coal.conveyor. Undersize from the clean coal
dewatering screens, 1/4 inch x 0, are fines created in the jigs or mis-
placed in the initial raw coal screening operation. These fines are
5-19·
pumped to thickening cyclones. Overflow water from these cyclones is
directly reused. Cyclone underflow is combined with crushed middlings
for cleaning in the fine coal cleaning operation.
The clean coal conveyor collects both coarse and fine clean coal and conveys
it to live storage-blending or dead storage. As clean coal discharges from
this convPynr, it is sampled in a sampling station identical to that de-
~.:ribcd for 'rH"T f'nr:~l sampling.
With one exception, all equipment specified in the FS-1 major equipment list
for coal breaking, surge storage, coarse coal screening, and coarse tuul
cleaning are of standard design and are widely used commercially for coal
.cleaning. The vibratory-activator feeders specified for. the raw cual ·silos
are relatively new, but do not require further development. These feeders
represent an improvement over existing vibrating feeders for feeding large
quantities of coarse coal.
Concept11.o~.l flow sheets and major equipment lists Y;'ere ueveloped for three
fine coal cleaning alternatives. These are.: jig fine coal cleaning -
Flow Sheet FS-1; hydrocyclone fine coal cleaning- Flow Sheet FS-1~1; and,
t8hl~ fine coal cleaning- Flow Sheet FS-1-2. All three flow sheets provide
for fine rl~r~n coal dewatering.
The fine coal cleaning circuit presented in FS-1, like the coarse clean~ng
circuit, uses a jig, but of differenl uesign from that used for c.oarse
coal cleaning. Before cleaning, however, fine coal (3/8 inch x 0) is ne.-
slimed at 28 mesh with sieve bends. Deslimihg permits control of the
quantity of water introduced to the fine cleaning operation.
5-20
> FINE COAL
FROM CRUSHED
CL.ASSIFYI.N~r-- I.-
CYCLONE
(20) b--
:)
MIDDLINGS PUMP
FLOW SHEET FS-1
FINE 'Ii
CLEAN
COAL
SECONDARY
HYDROCYCLONE.-~~
(5) ....
DEWATERING
SIEVE
~END (61
l
r-----¥~;._-.....;28::;..,;M;.;.E;;;;S;.;H.;..;.;X:..;0:....._ _ _ _ _ _ _ _"-. MINUS 28 MESH
4
0 ~ .----, ~ ~~ / COAL
~
X
\_/ TO FLOTATION CELLS
z
PRIMARY
HY DROCYC LON;,..;..;;.E._~
' ' . . ~------*<.6~
1,.------l """................
./
!l
FLOW SHEET FS-1
~
X
\7 FINE
z TO CLEAN COAL CONVEYOR
>
'------
WATER
/
FLOW SHEET FS-1
CLEAN COAL
A ~
FLOW SHEET FS-1
~
I
\ (3) 3/81N.X
~"'-'~...,/~~t~·-=-=-~-~J--··--.....;~~9;.__1----------~~------~------------~~2~8~M~ES~H~---)YV~59:.....____________£))~------R-E_Fu_s_E____ -J:>
~ TOREFUSECONVEYOR
I · FLOW SHEET FS-1
J:
I II)
w
I :::!!
re
I
I
~ r+· ~·
PRIM~~ (
HYDROCYCLONE PRIMARY
UNION CARBIDE CORPORATION- NUCLEAR DIVISION
OAK RIDGE NATIONAL LABORATORY
FEED SUMP 111 HYDROCYCLONE
FEED PUMP (2)
CONCEPTUAL FLOW SHEETS DEVELOPMENT FOR COAL
CONVERSION PLANT COAL HANDLING-PREPARATION
AND ASH/SLAG REMOVAL OPERATIONS
CONTRACT NO. 112X - 45724V
r-------------~r---.----,---~----r---.---.---.---.---.---.---.---.---,---~--~--~--~--~----~
STREAM NO.
~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ <& ~ <U> <B>
FLOOR~
SU~P DRY SOLIDS, TONS/HOUR
WET TOTAL, TONS/HOUR
1,429
2,858
278 - 1,751 - 1,360 391
1,303
391
2,650
347
1,156
44 36
790
311
366
1,182
3,377
178
7,827
1,036
1,381
146
1,996
1,036
1,164
ALTERNATIVE: HYDROCYCLONE FINE
COAL CLEANING
426 7229 12,507 1,130 11,204 1.494
WATER, GPM 5,716 2,592 28,916 43,024 4,520 39,376 3,648 9,036 3,236 5,800 3,016 220 8,780 30,596 1,380 7,400 512
BECHTEL NATIONAL. INC.• SAN FRANCISCO 94119
LINE DESIGNATIONS "// //~ . WATER, WT PERCENT 50 70 100 86 100 88 70 86 70 97 95 15 65 98 75 93 89
BECHTEL JOB DATE FLOW SHEET NUMBER
COAL
13022 JULY 1979 FS-1-1
REFUSE AND PARTICULATE COAL
----WATER
5-21
'i
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
MAJOR EQUIPMENT LIST
HYDROCYCLONE FINE COAL CLEANING
'
ALTERNATIVE FLOW SHEET FS-1-1
I
Number HP
Equipment Title Design Rating and Description Specification R~quirements and Comments
Required Each
!
I·
5-23
'i
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
FINE COAL
FINE COAL
15 28MESH XO MINUS
28MESH COAL
TO FLOTATION CELLS
FLOW SHEET FS-1
> WATER
..c.____----=--'
FROM WATER HEAD TANK
>- - .... -- ~------ -~---- ~
87 3/8 IN. X 28 MESH
FLOW SHEET FS-1 REFUSE
TO REFUSE CONVEYOR
0 FLOW SHEET FS-1
I X
~
~
co
I M"
I 88 28MESH X 0
REFUSE
TO REFUSE THICKNER
FINE CLEAN FLOW SHEET FS-1
COAL
DEWATERING
SIEVE
BEND lr----1
(6)
FLOTATION CELLS
FEED PUMP 'I UNION CARBIDE CORPORATION- NUCLEAR DIVISION
OAK RIDGE NATIONAL LABORATORY
STREAM NO.
0 ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ,,
'I
CONCEPTUAL FLOW SHEETS DEVELOPMENT FOR COAL
CONVERSION PLANT COAL HANDLING-PREPARATION
AND ASH/SLAG REMOVAL OPERATIONS
DRY SOLIDS, TONS/HOUR 1,429 278 1,707 1,529 178 347 1,182 311 36 1,036 146 1,036 324 CONTRACT NO. 62X - 45724V
WET TOTAL, TONS/HOUR 2,858 926 8,192 12,193 3,822 8,371 711 1 '156 3,377 366 790 1,381 1,996 817 1,164 10,367
WATER,GPM 5,716 2,592 32,768 41,944 9,172 32,772 2,894" 3,236 8,780 220 3,016 1,380 7,400 868 512 40,172
LINE DESIGNATIONS WATER, WT PERCENT 50 70 100 86 60 98 100 70 50 15 95 25 93 100 11 97
COAL ALTERNATIVE: TABLE FINE COAL CLEANING
s-2s
'i
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
MAJOR EQUIPMENT LIST
TABLE FINE COAL CLEANING
ALTERNATIVE FLOW SHEET FS-1-2
Number HP
Equipment Title Design Rating and Description Specification Requirements and Comments
Required Each
20 Cyclone Classifier Design Capacity: 2,000 gpm slurry Several standard designs of coal classifying
Diameter: 26 in. cyclones are curr~ntly available.
Cast Ni-Hard cons~ruction with cast refractory
apex nozzles. I
60 Shaking Table 3 Design Capacity: 25 tph This table is the .!largest capacity table that
Type: Suspended Double Deck can presently be built due to feeding limitations.
I
Rubber Deck Construction.
I
ii
2 Refuse Spiral Classifier 15 Design Capacity: 160 tph Standard Design Spiral Classifier.
Type: Spiral
Spiral Diameter: 84 in. I
6 Fine Clean Coal Dewatering Sieve Design Capacity: 160 tph Standard Design Ftxed Sieve Bend.
Bend Opening: 28 mesh
i
6 Clean Coal Vibrating Centrifuge 75 Design Capacity: 165 tph Standard Design B~sket Type Coal Centrifuge.
Stainless Steel W~dge Wire Basket.
5-27
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
Jig fine coal cleaning is· accomplished with three parallel, Batac-type
jigs. The specified jigs are each designed to clean 600 tons per ho~r of
coal. These air-pulsed jigs allow even, regular pulsing of the entire jig
width which results in improved bed stratification compared with a Baum-
type jig. Each jig has six air pulse compartments and two bucket eleva-
tors; one elevator for middlings and one for refuse. Clean fine coal over-
flows at the jig ends. Middlings, which are· mainly misplaced material,
are rec~c~ed directly to the jig feed. Refuse~ partially dewatered by
the refuse elevators·, is further dewatered on 28 mesh opening, single-
deck, vibrating screens. Oversize refuse discharges to the refuse con-
veyor~ Uridersi~e refuse flows to an effluerit treatmerit operation.
Cleari ~oai overflowing the fine coal jigs is dewatered to 15-20 wt per-
cent total moisture on 28 m_esh opening, single-deck vibrating dewatering
screens. Oversize from these screens~ 3/8 inch x 28 mesh clean coal, is
further dewatered to approximately 11 wt percent total moisture with vi-
brating basket centrifuges. Dewatered coal is discharged to the clean coal
conveyor where it combines with crushed, clean coal from the coarse coal
cleaning operation. Water removed by the dewatering screens and centrate
is pOmped to effluent treatment.
"Flow Sheet FS-1-1 presents the hydrocycloning fine coal cleaning alternative.
Fine coal from the raw coal screens plus coarse coal cleaning operation
crushed middlings and thickened clean coal dewatering fines are initially
combined in a sump. Sufficient make-up and hydrocyclone circuit recycle water
is added to this sump to proc:h.1ce a coal slurry containing approximately
14 wt percent coal. This slurry is pumped into 25 parallel primary hydro-
cyclones. Underflow from these hydrocyclones is diluted with water and
recleaned in 5 parallel secondary hydrocyclones. Underflow from these
hydrocyclones is refuse. Overflow from the secondary hydrocyclones is
recycled to the primary hydrocyclone· feed sump.
[Preceding pa~e~ank/s-zg
Fine refuse resulting from hydrocycloning. is dewatered on sieve bends in
combination with single-deck vibrating screens. Oversize refuse is dis-
charged onto the refuse conveyor (see FS-1). Undersize refuse, minus 28
mesh, flows to an effluent treatment operation.
Overflow from the primary hydrocyclones, which contains clean fine coal, is
classified at 28 mesh in 20 parallel_classifying cyclones. A minus 28 mesh
coal fraction- is classified into the cyclone overflow and a 3/8 inch x
28 mesh fraction is obtained in the underflow. Underflow is dewaterecl on
parallel sieve bends. Sieve bend oversize, 3/8 inch x 28 mesh, .is further
dewatered to approximately 11 wt percent total moisture in 6, p~ralleL,
5-30
which transport it to 6, parallel~ dewatering sieve bends. Sieve bend
oversize, 3/8 inch x 28 mesh, is further dewatered in six parallel, vi-
brating, basket centrifuges. Cake from the centrifuges is discharged to
the· clean coal conveyor (see FS-1) where it combines with crushed clean
coal from the coarse coal cleaning operation. Centrate flows to the cy-
clone ·feed sump for recovery of any mi·splaced coal.
Undersize from the clean coal dewatering sieve bends, minus 28 mesh coal,
flows to the same sump as the cyclone classifier overflow. From here·it
is pumped to an effluent treatement operation.
Like equipment specified for coarse coal cleaning, equipment for all three
'fine coal cie~ning· alternatives is of standard design and is widely used
co~mercialiy for coal cleaning. Of the three alternatives, all can produce
clean coal of nearly equal quality and at comparable recoveries. Total
dperating cost, including approptiate capital charges, would be the main
factor in selecting a best alternative.·
I
5.2.3 Coal Cleaning Effluent Treatment
Future cbal cleaning plants may require closed loop water systems without
ponds. Effluent emission regulations may not allow release of any polluted
water from such plants. As a result, effluent treatment will be an important
operation in all future coal cleaning plants.
FS-1, in addition to presenting flow schemes for coarse coal cleaning and
one fine coal cleaning alternative, presents a conceptual flow sheet for
one cleaning plant effluent treatment approach. This treatment operation
recovers water for reuse and clean coal. Feed to the effluent treatment
operation is produced by all three fine coal cleaning flow sheets and con-
sists of: slimes (minus 28 mesh raw coal), fine clean coal dewatering under-
flow, and minus 28 mesh refuse. The slimes and clean coal dewatering
underflow are pumped to froth flotation cells for coal r~covery. Minus 28
f .
Float coal from the flotation cells, clean 28 mesh ~ 0 coal, is dewatered
on a disc vacuum filter. Filter cake is conveyed to the cleaning plant
clean coal conveyor where it combines with clean coal from the coarse and
fine cleaning operations. Filtrate is recycled directly to the flotation
cells.
Froth flot~tion is only one of many methods that could conceivably be part of
a system to recover coal and produce recyclable water from cleaning plant
effluents. However, it is the most common approach currently uGed when any
coal cleaning plant effluP.nt. tre8tment is provided. Other po.~.~i.ble t:~~h~
5-32
5.3 COAL STORAGE AND BLENDING CONCEPTUAL FLOW SHEETS
Two basic types of large-capacity coal storage will likely be required for
coal conversion: live storage with or without blending and dead stora&e·
As discussed in Subsection 4.3.2, live storage design capacity was estab-
lished at 500,000 tons and dead storage is intended for emergency use only.
However, differentiation between what constitutes live-and dead storage
for some storage configurations is difficult. As a result, both basic types
of storage are discussed together.
As discussed in Section 4, the need for blending and the degree required
has yet to be quantified for an,y of the nine coal conversion processes
considered. Process in"formation required to dete-rmine the cost savings,
if any, that might be realized for converting blended versus unblended
coal has yet to be developed. Once this information is available, these
·savings can be compared with the cost for different coal blending levels.
Three general blending levels can be considered for coal conversion: simple,
intermedt.ate, and full.
Table 5-l and Figures 5-2 and 5-3 present major alternatives for large-
scale, high-capacity coarse coal storage. The three general blending
levels and equipment required to achieve them are also presented. Two
general storage alternatives are identified: open stockpile storage and
enclosed storage.
For a given storage capacity, open stockpiles are inevitably less expensive
than enclosed stor:age. A primary reason for considering enclosed sto:b;L,ge
for commercial coal conversion plants is fugitive particulates emissions.
Current coal open stockpile fugitive particulates emission regulations are
vague. However, in the future, particularly when the time frame for con-
struction of .commercial coal conversion plants is considered, they are liable
to become more precise and stringent. Further, current methods used to
control open stockpile fugitive emissions appear to be both expensive and
5-33
limited to their ability to achieve significantly lower particulate emis-
sions. If future permitted fugitive particulate emissions are significantly
lower than those specified by current regulations, totally-enclosed live
storage facilities and possibly new dead storage facility designs will likely
be required. This could be particularly true for storage facilit~es as large,
both in the quantities of coal handled and area required, as those judged
required for commercial coal conversion plants. In addition to allowing
better fugitive particulates control, use of enclosed storage in locations
where long or severe winter conditions exist, would reduce problems asso-
ciated with handling of frozen and wet coal.
A'::> :.ngure 5-:L indicates. many npl"n stockpile configut alluns are possible.
Major factors which influence that best suited for a given ~ituaLlnn 1n~l.ude:
• Blending requirements
• Land availability
o Ec:ouuudcs
For open stockpile blending, at least two stockpiles are required; one to
be reclaimed while the other is built. There are two Approaches for buildiug
of blending stockpiles: chevron layering and winclrow layering. ~iml-'1~
blending is achieved when a pile built with a chevron pattern :i.s red.<1imed
in small sections, such as by a bucket wheel reclaimer. When a chevron
stockpile fs reclaimed in full cross section, by·such equipment as a
dn.tm :n~ulnimer, intt!nuediare blending is achieved. Full blending is
achieved when a stockpile built in windrow layer.s is reclaimed in full
5-34
Table 5-l
1. Simple Storage Stationary Stacker with Tele- Bucket Wheel Reclaimer • No Blending Achieved,
scopic Chute Belt or Vibrating Feeders • Dead Portion ReclaimI. Requires Mobile Equipment
Conveyor with Telescopic Mobile Equipment • Stockpile Arrangements:
1
Ramped Pile, Conical,
Lowering Well Kidney-Circular, or Single Wedge
Stationary Stacker with Luffing
Boom(s)
Tripper Conveyor with Tele-
scopic Chute
Mobile Equipment
2. Simple Blending - Chevron Traveling Stacker with Luffing Bucket Wheel Reclaimer • Possible Coal Segregation
Layers Boom(s) Stacker-Reclaimer • Stockpile Arrangeme~ts: Single Wedge, Multiple
Stacker-Reclaimer with Luffing Rotary Plow Wedge, Wedge-Flat Top, Flat Top with Active
Boom(s) .
S ect1on, or S em1-
. Act1ve
I.
Tripper Conveyor with Tele- • For Wedge-Flat Top, Flat Top with Active Section,
scopic Chute and Semi-Active Stodkpiles
I
Mobile Equipment is
Required for Reclaim of Semi-Active and Dead
Portions
3. Intermediate Blending - . Traveling Stacker with Luffing Bridge Type Bucket Wheel • Stacking and Reclai$ing Can Be Highly Automated
Chevron Layers with~ Full Boom(s) Reclaimer • Stockpile Arrangeme~ts: Single Wedge, Multiple
Cross Section Reclaim Scraper Reclaimer Wedge, or Wedge-Flat Top
Drum Reclaimer • For Wedge-Flat Top Stockpile Mobile Equipment is
Required for Reclai~ of.Semi-Active Coal
4. Full Blending - Windrow Layers Traveling Stacker with Luffing Drum Reclaimer • Best Bed Blending
with Full Cross Section Reclaim and Slewing Boom(s) • Entire Blending Operation can be Automated
• Stockpile Arrangeme~ts: Multiple Wedge
4. Wide Span Barn Tripper Conveyor Bridge Type Bucket Wheel • Large Capacity Stor~ge
Traveling Stacker Reclaimer • Intermediate Blending
Drum Reclaimer • Stockpile Arrangemertt: Circular
1.
I
·~
I II
i..J
I
J
-:::?'~
m~o
TRAVELING STACKER
TRAVELING STACKER
STACKER-RECLAIMER
MOBILE EQUIPMENT RADIAL STACKER STACKER-RECLAIMER
Sl'OCKPILE CONSTRUCTION METHOD_. DRAG LINE BELT CONVEYOR TRIPPER-CONVEYOR
TRIPPER CONVEYOR
STOCKPILE RECLAIM METHOD ---1•• MOBILE EQUIPMENT LIVE PORTION: BELT OR VIBRATING FEEDERS
DEAD PORTION: MOBILE EQUIPMENT TO LIVE
LIVE PORTION: BELT OR VIBRATING FEEDERS STACKER-RECLAIMER
BUCKET WHEEL RECLAIMER
STACKER-RECLAIMER
BUCKET WHEEL RECLAIMER
DEAD PORTION: MOBILE EQUIPMENT TO LIVE.
PORTION PORTION BRIDGE TYPE BUCKET WHEEL RECLAIMER BRIDGE TYPE BUCKET WHEEL RECLAIMER
BRIDGE TYPE DRUM RECLAIMER BRIDGE TYPE DRUM RECLAIMER
SCRAPER RECLAIMER I $CRAPER RECLAIMER
I
WEDGE-FLAT TOP COMBINATION FLAT TOP WITH ACTIVE SECTION. SEMI-ACTIVE PILE
1111111111~
-
w- w 0
SEMI-ACTIVE z
>~ (I)
w w
-o
t-o
0
0
COMPACTED ..J ..J
ii:
~=
.J u.
0 0
~
~ w
w 0
0
STOCKPILE CONSTRUCTION METHOD_. TRAVELING STACKER TRIPPER CONVEYOR AND MOBILE EQUIPMENT TRAVELING STACKER AND MOBILE TRAVELING STACKER AND MOBILE
STACKER-RECLAIMER EQUIPMENT EQUIPMENT
MOBILE EQUIPMENT REQUIRED FOR SEMI-ACTIVE PORTION
5-37
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
ENCLOSED STORAGE ARRANGEMENTS 4 SILO CIRCULAR BARN GEODESIC DOME WID-E SPAN BARN "V" BUNKER
(MASS FLOW BOTTOM)
I
I
t--- /
///'ii;f/12-
ENCLOSED STORAGE FEED METHOD--+ BELT CONVEYOR BELT CONVEYOR ROTATING BELT CONVEYOR TRAVELING STACKER TRIPPER CONVEYOR
ENCLOSED STORAGE RECLAIM _METHOD_. BELT OR VIBRATING FEEDERS BELT OR VIBRATING FEEDERS BRIDGE TYPE BUCKET WHEEL RECLAIMER BRIDGE TYPE BUCKET WHEEL RECLAIMER ROTARY PLOW
ROTARY PLOW ROTARY PLOW DRUM RECLAIMER
I
Figure 5-3 ENCLOSED COAL STORAGE ALTERNATIVES
5-39
THIS PAGE
WAS INTENTIONALLY
, LEF·T BLANK
cross section. Building of windrow piles is more complicated than chevron
piles due to the sle~ing movement required by the traveling stacker booms.
Booms on stackers for windrow layering are also usually longer than those
on stackers used to build chevron piles.
A conceptual flow sheet has been developed for enclosed coarse coal live
storage-blending. This flow sheet, FS-2-1, is considered as an alternative
to multiple wedge open stockpile storage-blending. It consists of three
V-bunkers. This type of enclosed storage structure and wide span barns
are best suited for storage of the extremely large quantities of coal
judged to be required for coal conversion. As shown in Figure S-3, a
wide span barn is essentially a covered wedge stockpile. It would use
stackers very similar to those used for building open wedge stockpiles.
These rail-mounted stackers would move along one barn side only and, hence,
would have only a single boom. Bridge-type bucket 'wheel and drum reclaimers
used with wide span· barns are identical to those for open stockpiles. Con-
veyor systems required for wide span barns are very similar to those re-
quired for analogous wedge open stockpile facilities. The main deciding
factor between use of V-bunkers and wide span barns for large-capacity
enclosed live storage-blending is cost.
5-42
I.
COAL RECLAIM
ROTARY PLOW FEEDER 131
I
t - t .. . . ., LIVE COAL STOAAG£;
~---.L.--....,....Q \ U,-~-----r-.o \\RECLAIM CONVEYOR 131
I \ -
/I
OPERATION: 7,920 HOURS PER YEAR
DESIGN POWER/STEAM PLANT COAL RECLAIM I ' \I
RATE: 312 TONS/HOUR
DESIGN POWER/STEAM PLANT I
ANNUAL OPERATION: 7,920 HOURS PER YEAR I I
f/\ /\ POWER/STEAM PLANT
TWO-WAY / \ I \FEED CONVEYOR (2)
>
SWITCHOVER BIN (1)
I /... .. } ./.:'\. TO POWER/STEAM PLANT
0
t / oJt/
I
-~
4
z
. . ."---_s~ 2 IN. X 0 COAL
1, - - +
u--o 0t ~ TO FINE COAL CRUSHING,
Jr~--------
Q -
------- }--....:..-~~
0
. . . ,......------P...;U~LVERIZING, > 21N.XO COAL
FLOWSHEETS FS-3
THROUGH FS-11
>
OR GRINUINu
I
SWITCHOVER BIN CONVERSION COAL
RECLAIM BELT FEED CONVEYOR (2)
FEEDER (21
UNION CARBIDE CORPORATION- NUCLEAR DIVISION
OAK RIDGE NATIONAL LABORATORY
5-43
'j
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
I
MAJOR EQUIPMENT LIST
COARSE COAL LIVE STORAGE-V-BUNKERS
ALTERNATIVE FLOW SHEET FS-2-1
I
Number Equipment Title HP
Design Rating and Description Specification Requirements and Comments
Required Each
i
1 Live Coal Storage Feed Conveyor 750 Design Capacity: 4,400 tph See General Conveyqr Specification.
Belt Width: 72 in.
2 Live Coal Storage Feed Transfer 250 Design Capacity: 4,400 tph See General Conveyqr Specification.
Conveyor Belt \-lid th: 72 in. r
t
3 Live Coal Storage Tripper Conveyor 500 Design Capacity: 4,400 tph See General Conveyir Specification.
Belt Width: 72 in.
3 Coal Reclaim Rotary Plow Feeder 30 Design Capacity: 2,400 tph Rotary plow feeder~ of this capacity are avail-
able as standard equipment.
2 Power/Steam Plant Feed Transfer 75 Design Capacity: 400 tph See General Convey9r Specification.
!
Conveyor Belt Width: 36 in.
I
1 Two-Way Switchover Bin Dimensions: 30 ft X 15 ft X 25 ft Mass flow surge bi~.
2 Switchover Bin Reclaim Belt Feeder 50 Design Capacity: 2,400 tph See General Belt F~eder Specification.
Belt Width: 72 in.
2 Power/Steam Plant Feed Conveyor 75 Design Capacity: 400 tph See General Conveyor Specification.
Belt Width: 36 in.
'
2 Conversion Coal Feed Conveyor 300 Design Capacity: 2,400 tph See General Conv·eybr Specification.
Belt Width: 60. in. ·,1
5-45
'i
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
evenly fill each V-bunker. These tripper conveyor systems are located in
the center of the bunker enclosing structure in a conveyor gallery. Coal
is discharged into a bunker on both sides of the tripper car through chute
work and. continuous slots_ in the gallery floor. Continuous seal belts on
th~ floor slots control escape of dust from the actual bunker into the
'
conveyor gallery.
Coal i& reclaim~d from a V-bunker by a rotary plow feeder which travels the
entire length of the bunker. Reclaimed coal is discharged from this feeder
onto a reclaim conveyor located in a tunnel under the bunker. These con-
veyors, one per bunker, discharge to one of two transfer conveyors. These
conveyors can divert coal to either the power/steam plant or to a two-
way switchover bin which feeds coal to conversion. As coal discharges
from the transfer conveyor, it is sampled by a sampling system identical
to that presented in Figure 5-l.
8 Dead pile reclaim - For reclaim, dozers are used to cut a ramp
in a sealed pile nearest a reclaim slot. A r~claim slot con-
sists of a rotary plow feeder capable of reclaiming coal piled·
over it and a below-grade conveyor to which the rotary plow
discharges. Once a ramp is built, scrapers are used to move
coal to the reclaim slot.
Nine conceptual flow sheets and ma.i or equipment lists have been developed ';~
tor coal crushing and grinding. Reasons for development of this number of
firie crushing flow sheets are: eight of the nine coal conversion processes
considered require fine coal feed; the range of different required coal
feed size consists within the fine coal classification; possible alterna-
tive fine coal crushing approaches; and, a possible need to minimize ultra-
fines formation during coal fine crushing. Coal fine crushing equipment
is also required to prepare coal for the power/steam plant atmospheric
pressure fluidi~ed bed (AFB) steam generators. The fee.rl ~o;.~J top size
desirable for AFB steam generators, however, could be as high as 1/2 inch.
Though this is a slightly coarser top size than that defined for fine
coal flow sheets development, it is well within the capabilities of the
type of flow sheets developed to provide 1/4 inch x 0 and 1/8 inch x 0 coal
5-48
for the U-Gas and COGAS processes, respectively. (Fine coal, previously,
defined in Subsection .4.3, is. coal which contains particles not greater
than l/4 inch, but not all smaller than 20 mesh in size. Note: a less
specific definition of fine coal is used in Subsection 5.2, Coal Cleaning
.. ~.
terminology.)
In Table 5-2, the proposed· fine·crushing circuit for each conversion pro-
cess is" that judged, on current technical information, to provide the best
combinat~on of r~liability and operating flexibility. For most processes
this judgement is subjective, could change if ultrafines minimization is
:important, and is not based on direct comparison of actual costs for com-
peting crushing circuits. ·Many factors could result in replacement of a
proposed circuit by an alternative or completely new circuit. These factors
include more definitive conversion reactor coal feed requirements (partic-
ularly for the SRC-1 and SRC-II processes), detailed circuit cost estimates,
conversion proc,ess demonstration plant results, ·and possible advances in
fine crushing technology.
A further principal factor that would determine fine crushing circuit design
and equipment specification for an actual commercial coal conversion plant
is results of a fine crushing test program. Such a test program would be
completely justifiable for crushing facilities of the capacities required
for coal conversion. A possible exception would be when the commercial
plant feed coal is used in a demonstration plant . . In this case a fine
crushing assessment program would be part of the demonstration plant test
5-49
Table 5-2
I, 0 CONVERSION REACTOP
COAL FEED
REQUIREMENTS
1. 1 Size Consist 100 Percent t-tinus lOO Percent ~linus 100 Percent l'linus 100 Percent Minus 100 Percent Minus 100 Percent Hinus
1/4 Inch l/8 Inch 14 Hesh 20 Hesh 8 Hesh 12 Nesh(l)
1.2 Fines Limitations Up to 10 Percent None Reported Minimum Minus Minimum Ultrafines _!ione Reported None Reported
Minus 200 Mesh 100 Hesh
1. 3 Total Moisture As Received (Pitts- Drying is Part of COal is Dried During As Received Dry_ing is Part of Drying is Part of
burgh Seam Coal May Conversion Process Pr~tree.tmli:nt Bcoth Cunval'alon Dotll Ounvll!:t"!:tluu
R~l'lhU'A t'rM.t'P.8tment Processes Processes
to Control
Agp:lome.r.,ti.nn)
2. 0 FINE CRUSHING
CIRCUITS
2 -.
Rec~i:!dt ) Rec~~v~d
2.3 Alternative FlOw
Sheet and Circuit As As (l) -
Single-Stage Clo:~cd ~ingle-Stage C1used-
Circuit Crushing Circuit Cru~hing
Re~:;!~d
2.4 Altem.utve t'low
Sheet and Circuit As ( 2)
Single-Stage Open-
CU'cuit Grinding
3. 0 TYPE OF FINE
C~USHJNG EC}UTPMF..NT
3.1 Proposed Circuit Four 72-Inch, 2-Rov Four 72-Inch, 2-Row First-Stage Crush- First-Stage Crush- Six 72-Inch, 4-Rov Six 72-Inch, 4-Row
Cage Mills, 600 tph Cage Mills, 600 tph ina: Four 72-T.nt:h, ing: Four 72-lnch 1 Cage HUh, 400 tph Cttge HUla, 400 tph
Each Mill Each Mill 2-Row Cage Mills 2-Row Cage Hills Each Hill Each Hill ·
600 tph ~<h Mill 600 rph F.ar.h Mi 11
Secorld-Stage Crush- Second-Staae Crush-
Ana; Eiaht 72-Tnr:.hl ina: Efght 7'l•Tnr;h,
4-Row Cage Mills 4-RotJ Cage Hills
300 tph Each Hill 300 tph Each Mill
3.2 Alternative Four 60-lnch x First-Stage Crush- First-Stage Crush- Six 72-Inch, 2o.Row Six n.- Tnch, 2-Row
Circuit 110- Inch-Wide ing: Six 72-Inch, ing: Six 72-lnch, Cage Mills, 400 tph Cage Hills, 400 tph
Center Feed, 2-Row Cage Mills 2•Ruw Cage Mills Eaeh Hill Each Hill
Reversible Hammer- 400 tph Each Mill 400 tph Each Hill
~!ii(~) 600 tph Each Second-Stage Crush- Second-Stage Crush-
ing: Six 72-Inch ing: Six 72-lnch
'1 Rov Ool&ii UUl.:. 4-ft.uw Cage Mill!!
400 t{'lh F.arh Mt 11 hnn trh ~""J> ~f.11
3.3 Alternative Four /2-lnch, 2-Rov Six 72-lnch, 2-Rnw Siv 77 .. tnr.h, 1 .. v.,...
Nnr.es:
(1) Culf Mineral Resources Co. is cu-rrently evaluating a range of conversion reactor coal feed size consists for SRC-I and SRC-II demonstration plants.
These range from 100 percent minus 6 mesh (approximately 1/8 inch) to 100 percent minuS SO mesh.
(2) As Received coal has a nominal size consist of 2 inch x 0 and can have up to 10 wt percent total moisture.
(3) Flow Sheet FS-7 is for ::oa=-se coa! thcrm.:l1 drybg.
(4) This alternative crushing equipment is for Flow Sheet FS-6.
(S) This alternative crushing equipment is for Flow Sheet FS-8.
5-50
program. A typic~l fine crushing test program would be performed using a
large representativ~ conversion coal sample and involve testing of several
crusher designs, a wide range of crusher operating conditions, and probably
different crushing circuits. Its results would quantify for a specific
coal the.effect of crusher designs and operating cond~tions on crushed
coal size consist. From this information and cost estimates a best crush-
ing circuit design would be achieved.
With.one exception (Flow Sheet FS-10 in Table 5-2), all fine crushing flow
sheets use multi-row cage mills. These mills are well suited to .conversion
coa~ fine crushing because:
• Reliability is high
5-51
• They readily accept 2 inch x 0 and coarser coal
Major cage mill variables which affect final product size consist are:
Hith exception of FS.;..iO, in which wet rod mills are used to produce 100 percent
minus 20 mesh coal slurry, all fine crushing flow sheets use belt conveyors for
coarse and fine coal transport; bins for coal surge storage; gravimetric
5-52
belt feeders for. cage mill feeding; and, cage mills~ Design capacities
established for these components are based on reliability considerations
and the need to provide coal to a postulated five-train coal conversion
plant .. With exception of FS-4, two cage mill capacities were judged to
meet these general requirements: 600 and 400 tons per hour. Use of
these two design capa.cities results in:
Major equipment list specified cage mill power requirements are based on
use of the largest drives (multi-row cage mills require two drivers, one
for each cage, set) recommended by manufacturers for a given mill size.
-Actual mil,l power consump.tion would normally not reach the specified. rates.
However, the. cost savings associated with specifying lower power drives,
such as 1,000 inst.ead of 1,200 hp, is insignificant compared with fine
crushing facillty capital cost and sacrlfices operating flexibility. Speci-
fication of maximum design power for crushers is normal practice in the
minerals beneficiation industry.
The number of cage mills required for a flow sheet establishes the number
of mill feeders and surge bins required. Each mill is supplied by a
single gravimetric belt feeder and a single surge bin. Belt feeders
capable of feeding up to 600 tons per hour of coal appear to be techni-
cally fe~sible. However, ~f necessary multiple feeders could be tised
for ~ single c~ge mill.
5-53
Fine crushing surge bin design capacities are based on providing an approxi-
mate coal residence time of one hour. This is sufficient for the surge
storage filling tripper conveyor systems to maintain bins sufficiently
full at all times. Design of multiple surge bin systems of the types·
presented in the flow sheets is very involved. In addition to the bin
design considerations mentioned in the beginning of this section, it
requires design of the complete system used to sequentially fill all bins.
The bin design capacities presented in the major equipment lists are only
estimates. Detailed engineering and .cost trade-offs could result in
somewhat different bin capacities~
Coal is conveyed to and from all fine crushing operations by belt conveyors.
For both applications two full-capacity conveyor systems are provided.
Each coal conveyor system has a 1.33 equipment design capacity to plant
design capacity ratio. The equipment design capacity is that specified
for equipment procurement. (Equipment design capacities are the capacities
presented in major equipment lists.) Plant design capacity for all fine
crushing flow sheets is 1,771 tons per hour (tph) of coal having a total
moisture concentration of 8.0 wt percent. This is equivalent to 42,500 tons
per day of conversion reactor feed coal or 85 percent of the entire con-
version plant design daily coal t:uusuuilJtion of 50,000 torte per day. 'l'liP
5-54
• A safety margin for off-specification crusher performance
In all coal fine crushing flow sheets, surge storage bins were postulated
as being located in a single row. This configuration is well suited for
providing coal to a conversion plant consisting of five, parallel coal
conversion tr~ins. Efficient transfer of coal to the conversion reactor
feed systems couid be achieved by location of the fine crushing facility
at the coal feed ends of the conversion trains with the surge bin row
perpendicular to the train centerlines. Obviously, many layouts for
matching of coal fine crushing and conversion reactor feed systems are
possible. However, evaluation of such layout alternatives is beyond the
~cup~ of this report.
The coal fin~ crushing flow sheets provide both high operating reliability
and operating flexibility. However, it should be recognized that different
design approaches could result in flow sheets with comparable operating
reliability and flexibility. Actual commercial fine crushing plant designs
are always a compromise between achievement of high reliability, operating
flexibility considerations, capital costs, and operating costs.
Flow Sheet FS-3 is the proposed fine crushing circuit for preparing
8 mesh x p coal (co.al feed for the Exxon Donor Solvent and Exxon Cata-
lytic Gasificqtion Processes) and 12 mesh x 0 coal (coal feed for the
5-55.
SRC-I and SRC-II Processes). These two different crushed coal size dis-
tributions could be obtained by use of different cage mill speeds and
possibly slightly different cage bar spacings. Cage mill design capac-
ities and installed powers would, however, be identical or very similar
for both size distributions.
Fine crushing feed conveyors are provided with tramp iron magnets, and for
non-magnetics removal, electronic type metal dectectors. The tramp iron
magnets are self-cleaning. Removed metal is collected in a bin and period-
ically removed. When a metal detector senses a: sufficiently large piece
of metal it marks its location with a paint spray and sounds an alarm.
Frequently such metal detectors are interlocked with their conveyor to
stop it when metal is detected. Metal is then removed manually. Removal
of tramp metal is important for protection of the cage mills and other
coal handling equipment.
Each fine crushing feed conveyor discharges onto a surge storage tripper
conveyor system. Two independent tripper conveyor systems are provided
for filling of fine crushing surge bins. Each system is similar to those
described in Subsection 5.3 for V-bunkcr live coal s~orage. Each conHiHLs
of a level belt conveyor running over the tops of in-line surge bins and a
self-propelled tripper car. The tripper car can discharge coal from the
conveyor into any bin. When one bin is full the car is moved to anoth~r
bin where coal is required. Tripper cars of the capacities required for
5-56
TO ATMOSPHERE
GRAVIMETRIC 21N. X 0
BELT FEEDER (6) 8WT PERCENT
TOTAL MOISTURE
STREAM NUMBER
0 0 0 CONCEPTUAL FLOW SHEETS DEVELOPMENT FOR COAL
CONVERSION PLANT COAL HANDLING-PREPARATION
AND ASH/SLAG REMOVAL OPERATIONS
COAL- TONS/HOUR - DRY 1,629 271 1,629
CONTRACT NO. 62X - 45724V
PERCENT MOISTURE 8.0 8.0 8.0
TONS/HOUR - WET 1,771 295 1,771
SINGLE STAGE CAGE MILL COAL FINE CRUSHING
SRC I AND II, EXXON DONOR SOLVENT,
AND EXXON CATALYTIC GASIFICATION
5-57
· THIS PAGE
WAS INTENTIONALLY
LEFT BLANK ·
MAJOR
I
EQUIPMENT LIST.
SINGLE-STAGE CAGE MILL COAL FINE CRUSHING
I
FLOW SHEET FS-3
Number HP
Equipment Title Design Rating and Description S pec1'f'1cat1on
. Riequ1rements
. an d Comments
Required Each
'I
2 Fine Crushing Surge Storage 150 Design Capacity: 2,400 tph See General Conveytr Specification.
Tripper Conveyor System Belt Width: 60 in.
6 Fine Crushing Surge Bin Design Capacity: 300 tons Mass flow bin with lined bottom for even flow
1
1:
(1,800 tons, total combined capacity) promotion. '!
~~
1 Fine Crushing Surge Bins Baghouse 60 Design.Capacity: 20,000 acfm Standard Baghouse System.
I
Dust Collection System
6 Fine Crushing Gravimetric Belt 25 Design Capacity: 400 tph See General Gravimetric Belt Feeder Specification.
Feeder Belt Width: 72 in.
6 Coal Fine Crusher 1,400 Design Capacity: 400 tph See General Cage Mill Specification.
Type: Four Row Cage Mill
Size: 72 in. diameter
2 Fine Coal Conveyor 300 Design Capacity: 2,400 tph See General Conveyor Specification.
Belt Width: 60 in.
5-59
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
surge ~tqrage filling would be specially designed. Their design would
provide for such features as minimization of dust genetation during con-
. .
veyor di$Charge, rapid movement, and highly automated, and possible com-
puter controlled, bin filling. Tripper car operation could be monitored
by a closed-circuit television system.
Coal is discharged from the mass flow surge bins by sealed gravimetric
belt feeders. Height of the downspout connecting feeders and bins is
designed to provide a head seal against feeder operating pressure. Each
feeder discharges directly into a cage mill feed chute. Spinning of
mill cages produces a certain amount of air flow which must be controlled.
This is accomplished oy the pressurized, sealed feeders.
Flow sheet FS.,..4 is the propos~d fine crushing circuit for preparing 14 mesh
X 0 coal (HYGAS coal feed) 'and 20 mesh X 0 coal (Texaco Partial Oxidation
Gasification coal feed). , First-st~ge crushing is very s:i,milar to FS-3;
the main difference being use of larger capacity, 2~row-type cage mills.
a second tripper conveyor system which fills eight, in-line second. ~tage
crushing surge bins. Feed of coal from these bins is identical to that
for fi~st-stage crushing. Second-stage crushing is accompl:i.sh~d ~n
Flow sheet FS-5 is an alternative flow sheet for both FS-3 and FS-4. Instead
of open circuit crushing, it uses closed-circuit fine crushing. The main
advantages of this flow scheme are reduced ultrafines production and higher
crushing efficiency, i.e., the power consumption required for closed-circuit
crushing is less than for comparable open-circuit crushing. A disadvantage
is its greater complexity compared with open-circuit crushing and, as a
result, higher cost.
Crushed coal .~ravity flows from each cage mill into the feed spout of an
air classifiet'. Here it: is plcke<.l U[J uy i::l i'ulating di.,tributing plats hub.
Centrifugal force, imparted to the coal particles by rhe hub, Llu:uwl:; Ll~t:~m
5-62
TO ATMOSPHERE
HYGAS: 14 MESH X 0
II::XACO PARTIAL OXIDATION: 20 MESH X 0
I
LINE NO.1 NO.2 i TO CONVERSION REACTOR
FEED SYSTEMS
FINE COAL.
I
STREAM NUMBER
0 0 0 0 0 I
UNION CARBIDE CORPORATION- NUCLEAR DIVISION
OAK RIDGE NATIONAL LABORATORY
CO/\L- TONS/HOUR- DRY 1.629 407 1,629 204 1,629
PERCENT MOISTURE 8.0 8.0 8.0 8.0 8.0
TONS/HOUR- WET 1,771 443 1,771 221 1,771 'CONCEPTUAL I-LOW SHEETS DEV!!LOPMENT FOn COAL
CONVERSION PLANT COAL HANDLING-PREPARATION
AND ASH/SLAG REMOVAL OPERATIONS
CONTRACT NO. 62X - 45724V
1
!
TWO STAGE CAGE MILL COAL FINE CRUSHING
HVGAS AND TEXACO PARTIAL OXIDATION
:
5-63
'i
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
MAJOR;EQUIPMENT LIST
TWO-STAGE CAGE'MILL COAL FINE CRUSHING
FLO\i SHEET FS-4
Number HP
Equipment Title Design Rating and Description Specification Requirements and Comments
Required Each
I
2 First-Stage Fine Crushing Surge 150 .Design Capacity: 2,400 tph See General Conveyor Specification.
Storage Tripper Conveyor System Belt Width: 60 in. I
'I
4 First-Stage Fine Crushing Surge - Design Capacity: 225 tons Mass flow bin with lined bottom for even flow
Bin (900 tons, total combined capacity) promotion. I
I
4 First-Stage Fine Crushing Gravi- 30 Design Capacity: 600 tph See General Gravimetric
I
Belt Feeder
metric Belt Feeder Belt Width: 72 in. Specification. i
j
i
4 First-Stage Coal Fine Crusher 1,200 Design Capacity: 600 tph See General Cage Mill Specification.
Type: Two Row Cage Mill
Size: 72 in. diameter
2 Second-Stage Fine Crushing 500 Design Capacity: 2,400 tph See General Conveyor Specification.
Scissor Conveyor System Belt Width: 60 in.
I
2 Second Stage Fine Crushing Surge 200 Design Capacity: 2,400 tph See General Conveyor Specification.
i
Storage Tripper Conveyor System Belt Width: 60 in.
8 Second-Stage Fine Crushing Surge - Design Capacity: 225 tons Mass flow bin with lined bottom for even. flow
Bin (1,800 tons, total combined capacity) promotion.
8 Second-Stage Fine Crushing Gravi- 20 Design Capacity: 300 tph See General Gravimetric Belt Feeder
metric Belt Feeder Belt Width: 72 in. Specification.
8 Second-Stage Coal Fine Crusher 1,400 Design Capacity: 300 tph See General Cage Mi~l Specification.
Type: 4 Row Cage Mill I
'I
Size: 72 in. diameter ·i
1 Fine Crushing Surge Bins Baghouse 150 Design Capacity: 50,000 acfm Standard Baghouse System.
Dust Collection System I
I
5-65
THIS PAGE
WAS INTENTIONALLY.
LEFT BLANK
TO ATMOSPHERE
21N. X OCOAL
~ CRUSHING SURGE BIN (6)
CONVERSION COAL
CLEAN COAL FINE CRUSHING
FROM COARSE FEED CONVEYOR (2)
COAL LIVE STORAGE-
BLENDING 6
GRAVIMETRIC 21N.XO
BELT FEEDER (6) 8WT PERCENT
TOTAL MOISTURE
0 N0.21
TO CONVERSION REACTOR
FEED SYSTEMS
LINENO.l~------~----------------------------~~~~~~~9------------~------~~~------------'>
0
""'"
FINE COAL CONVEYOR (2)
- FINE COAL
I
UNION CARBIDE CORPORATION- NUCLEAR DIVISION
I OAK RIDGE NATIONAL LABORATORY
STREAM NUMBER
0 ~ 0 '
COAL- TONS/HOUR- DRY 1,629 272 1,629 CONCEPTUAL FLOW SHEETS DEVELOPMENT FOR COAL
PERCENT MOISTURE 8.0 8.0 8.0 CONVERSION PLANT COAL HANDLING-PREPARATION
AND ASH/SLAG REMOVAL OPERATIONS
COAL- TONS/HOUR -WET 1,771 295 1,771
CONTRACT NO. 62X - 45724V
I
5-67
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
i
MAJpR EQUIPMENT LIST
TWO-STAGE edGE MILL COAL FINE CRUSHING
STACKED' CRUSHER ARRANGEMENT
ALTERNATIVE FLOW SHEET FS-4-1
I
Number HP
Equipment Title Design Rating and Description Specification Jequirements and Comments
Required Each
I
2 Fine Crushing Surge Storage Tripper 150 Design Capacity: 2,400 tph I
See General Conve~or Specification.
I
Conveyor System Belt Width: 60 in.
6 Fine Crushing Surge Bin Design Capacity: 300 tons Mass flow bin witJ lined bottom for even flow
(1, 800 tons, to tal a.ombined capacity) promotion.
'I
6 Fine Crushtng Gravimetric Bel.t Feeder 30 Design Capacity: 400 tph See General Gravi~etric Belt Feeder
Belt Width: 72 in. Specification. '
'
6 First-Stage Coal Fine Crusher 1,200 Design Capacity: 400 tph See General Cage Mill Specification.
;
Type: Two Row Cage Mill I
Size: 72 in. diameter
I'
6 Second-Stage Coal Fine Crusher 1,400 Design Capacity: 400 tph See General Cage ~ill Specification.
Type: 4 Row Cage Mill I
Size: 72 in. diameter '
I
I
2 Fine Coal Conveyor 300 Design Capacity: 2,400 tph See General Convey,or Specification.
Belt Width: 60 in. :
1 Fine Crushing Surge Bins Baghouse 60 Design Capacity: 20,000 acfm Standard Baghouse pystem.
Dust Collection System I
I
5-69
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
TO ATMOSPHERE
GRAVIMETRIC 21N. X 0
BELT FEEDER (6) 8WT PERCENT
TOTAL MOISTURE
I
CRUSHED COAL COAL FINE CRUSHING
AIR CLASSIFIER (6)
l RECIRCULATION
SCISSOR CONVEYOR
1 SYSTEM (2)
)~--------------------------------~~~-'~rN~~~·-~~1~----N-
1
! -·-~1~------------------------------------------------~J~---~~~~~
02
>
__
21N.XOCOAL
CLEAN COAL
FROM COARSE
_ CONVERSION COAL
FINE CRUSHING FEED
CONVEYOR (2) LINE NO.
1
NO.2
~
~
V"
;
\ )
CJ~--------------~--------------------------------~------------------4
COALLIVESTORAGE·
BLENDING FINE COAL CONVEYOR (2)
FINECOAL
A-------~ ~- ...
TO CONVERSION REACTOR
HYGAS: 14 MESH X 0
TEXACO PARTIAL OXIDATION: 20 MESH X 0 FEED SYSTEMS i
EXXON DONOR SOLVENT: 8 MESH X 0 I
EXXON CATALYTIC GASIFICATION: 8 MESH X 0 !
STREAM NUMBER
0 0 SCR I AND SCR II: 12 MESH X 0 UNION CARBIDE CORPORATION- NUCLEAR DIVISION
OAK RIDGE NATIONAL LABORATORY
COAL-TON~HOUR-DRY 1,629 1,629
PERCENT MOISTURE 8.0 8.0
TONS/HOUR -WET 1,771 1,771 CONCEPTUAL FLOW SHEETS DEVELOPMENT FOR COAL
CONVERSION PLANT COAL HANDLING·PREPARATION
AND ASH/SLAG REMOVAL OPERATIONS
I
CONTRACT NO. 62X - 46724V
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
MAJpR EQUIPMENT LIST
SINGLE-STA~E CLOSED-CIRCUIT CAGE
MILL ~OAL FINE CRUSHING
TO MINIMIZE ULTRAFINES
IPRODUcT:;:ci~
ALTERNATIVE FLOW SHEET FS-5
,,'
Number HP 'I
Equipment Title Design Rating and Description Specification Requirements and Comments
Required Each 'I ,
I
'I
2 Coal Fine Crushing Recirculation 300 Design Capacity: 2,400 tph See General Conveyrr Specification.
Scissor Conveyor System Belt Width: 60 in.
I
2 Fine Crushing Surge Storage Tripper 200 Design Capacity: 2,400 tph See General Conveypr Specification.
Conv!ilyor System Belt Width: 60 in. '
I
6 Fine Crushing Surge Bin Design Capacity: 300 tons Mass flow bin with lined bottom for even flow
.(1, 800 tons, to tal combined capacity) promotion.
6 Fine Crushing Gravimetric Belt 30 Design Capacity: 400 tons See General Gravimetric Belt Feeder
Feeder Belt Width: 72 in. Specification.
6 Coal Fine Crusher 1,000 Design Capacity: 400 tph See General Cage M~ll Specification.
Type: 2 Row Cage Mill
6 Crushed Coal Air Classifier 400 Design Capacity: 400 tph Air separators of ~p to 24 ft in diameter are
Type: Mechanical Centrifugal currently used for closed-circuit cement
Air Separator grinding.
Size: 22 ft diameter Abrasion resistant steel lined.
2 Fine Coal Conveyor 300 Design Capacity: 2,400.tph See General Conveyor Specification.
Belt Width: 60 in.
1 Fine Crushing Surge Bins Baghouse 60 Design Capacity: 20,000 acfm Standard Baghouse ~ystem;
I
Dust \.oll eC'.tion System
I!
. I
5-73
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
Oversize particles are thrown out of the accelerated ascending air and
settle into the same tailings cone· as the coarses.t particles. From ·here
they are discharged to a recirculation scissor conveyor system by means
of rotary valves and flow switching chute work. Fines swept through secondary
classifi.cation are cycloned in a fines chamber formed by the conical classifier
housing. Removed fines are collected in a fines cone from which they are dis-
charged by rotary valves and flow switching chute work to one of two fine
. '
coal conveyors.
Flow sheet FS-6 is the proposed fine crushing circuit for preparing 1/4 inch
x 0 coal (U-Gas coal feed) arid 1/8 inch x 0 coal (COCAS coal feed). Except
for the number of .parallel trains and fine crusher
.
spec·ification,
.. this flow
sheet is similar to FS-3. The FS-3 general coal flow pattern description
also applies to this flow sheet.
Two crusher alternatives are specified for production of 1/4 inch x 0 coal:
two-row-type cage milis and harnrnermills. Use of harnrnerrnills would result
in more fines, but save in power comsumption. Harnrnerrnills, however, are
not recommended to produce minus 1/8 inch x 0 coal du~ to their excessive
produc·tion of oversize material.
FS-8 is a flow sheet for minimizing ultrafines in 1/4 inch x 0 crushed coal
(U-Gas coal feed). Dried coarse coAl, 2 inch x Ot is ~ii~ened i~ duuble-
ueck, vibrat:ing screens to separate minus 1/4 inch coal. Undersize .-o.al
il::l discharged directly to fine coal conveyors for conveying to thP. n-r:A~
5-76
iMAJOR EQUIPMENT LIST
SINGLE-STAGE CAGE MILL COAL FINE CRUSHING
I FLOW SHEET FS-6
i
Number HP i
Equipment Title Design Rating and Description Specification Requirements and Comments
Required Each I
I
2 Fine Crushing Surge Storage 150 Design Capacity: 2,400 tph See General Convei~r Specification.
Tripper Conveyor System Belt Width: 60 in. I'
I
4 Fine Crushing Surge Bin Design Capacity: 225 tons Mass flow bin witJ lined bottom for flow
(900 tons, total combined capacity) promotion.
I
1 Fine Crushing Surge Bins Baghouse 60 Design Capacity: 20,000 acfm Standard Baghouse:system.
Dust Collection System
4 Fine Crushing Gravimetric Belt 40 Design Capacity: 600 tph See General Gravimetric Belt Feeder Specification.
Feeder Belt Width: 72 in.
4 Coal Fine Crusher 1,200 Design Capacity: 600 tph See General Cage Mill Specification.
Type: Two Row Cage Mill
Size: 72 tn.. diameter
I
4 Alternative U-Gas Process Coal 600 Design Capacity: 600 tph See General Cage Mill Specification.
I
Fine Crusher - Hammermill Type: Center Feed, Reversible i
Size: 60 in. diameter X !
110 in. wide II
-
2 Fine Coal Conveyor 300 Design Capacity: 2,400 tph See General Conveyor Specification.
Belt Width: 60 in.
.
I
5-77
THIS PAGE.
WAS INTENTIONALLY
LEFT BLANK
TO ATMOSPHERE
CLEAN COAL
FROM COARSE COAL 1/4 AND 1/8 IN.
COAL LIVE STORAGE- LINE N0.1 4 FINE CRU:SHING
BLENDING MILL SPECIFICATIONS
f
I
j
U-GAS COG AS
GRAVIMETRIC 21N. X 0 I
BELT FEEDER (4) 0 8 WT PERCENT
TOTAL MOIS'i"URE COAL SIZE CONSIST
MILL SIZE AND TYPE
1/4 IN. X 0 I
FOUR 72 IN. CAGE MILL
1/81N.XO
FOUR 72 IN. CAGE MILL
2 ROW \TYPE 2 ROW TYPE
600TPH EACH 600 TPH EACH
ALTERNATIVE FOUR 60 IN.~ 110 IN. WIDE
HAMMER MILL
CENTER FEED
COAL FINE REVERSIBLE TYPE
CRUSHER (4) 600 TPH EACH
I
CAGE MILL OR
HAMMERMILL
(SEE MILL
SPECIFICATION
DATAl
U-GAS
COG AS
i
lUNION CARBIDE CORPORATION- NUCLEAR DIVISION
: OAK RIDGE NATIONAL LABORATORY
:t
:iTREAM NUMBER
0 .0 0 I CONCEPTUAL FLOW SHEETS DEVELOPMENT FOR COAL
CONVERSION PLANT COAL HANDLING.PREPARATION
AND ASH/SLAG REMOVAL OPERATIONS
COAL- TONS/HOUR - DRY 1,629 407 . 1,629 CONTRACT NO. 62X - 41i724V
PERCENT MOISTURE 8.0 8.0 8.0 I
TONS/HOUR -WET 1,771 443 1,771
I
SINGLE STAGE CAGE MILL COAL FINE CRUSHING
,I
U-GAS AND COGAS
j
5-79
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
MAJOR EQUIPMENT LIST
COARSE COAL THERMAL DRYING
FLOW SHEET FS-7
Number HP
Equipment Title Design Rating and Description Specification' Requirements and Comments
n.equired Each
2 Coal Dryer Surge Bin 100 Design Capacity: 2,400 tph See General Conveyo:r Specification.
Tripper Conveyor System Belt Width: 60 in.
3 Coal Dryer Surge Bin 3 Design Capacity: 135 tons Mass flow bin with lined bottom for even flow
(400 tons, total combined capacity) promotion.
3 Coal Dryer Gravimetric Belt 50 Design Capacity: 600 tph See General Gravime~ric Belt Feeder
Feeder · Belt Width: 72 in. Specification. I
3 Fluid Bed Coal Dryer 2,300 Design Capacity: 850 tph Fluid bed coal drye'rs of this capacity are currently
(Total Size: 16 ft diameter available. 1
System) Use of flue gas from a power/steam plant instead of
direct firing of co.al will require some design
modifications. ·
Dryers of this capacity are all specially engi-
neered and custom
.
f,abricated.
I
18 Coal Dryer Cyclone Design Capacity: 62,500 acfm Cyclones of this size are of standard design.
Size: 84 in. diameter Cyclones are manifolded together in a single
cluster which share a single underflow bin.
3 Coal Dryer Baghouse Design Capacity: 500,000 acfm Baghouse collectors of this capacity are custom
Particulate Coal Collection Area/Baghouse: 250,000 ft2 designed and fabriqated.
System Number of Compartments: 16 The baghouse is eq~ipped with an explosion detec-
Bag Material: Fiberglass tion and suppression system.
The baghouse syste~s include coal collection bins
and interconnecting mass flow conveyors.
6 Fiuid Bed Dryer Induced Draft Included in Design Capacity: 250,000 acfm Fans of this capacity and head are used in power
Fan Fluid Bed Static Pressure: 20 in. wat.er plants for flue ga~.
Dryer Power
I
2 Coal Dryer Discharge 300 Design Capacity: 2,400 tph See General Conveygr Specification.
Conveyor
!I
i
1 Coal Dryer Surge Bin 60 Design Capacity: 20,000 acfm Standard Baghouse System.
Baghouse Dust Collection I
I
System '
5-81
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
TO ATMOSPHERE
GRAVIMETRIC
BELT FEEDER (3)
LINE LINE
FLUE GAS N0.1 NO.2
,.....1..---..1..----.....;r.,__ _.....;r.,__ _ _ _ _ _ _ _ _~---...:.-~ DRY COARSE COAL.
FLUID BED DRYER (3)
COAL DRYER DISCHARGE
CONVEYOR (2)
TO COAL FINE CRUSHING
DRY SCREENING
FLOW SHEET FS-8
OR
SINGLE STAGE FINE CRUSHING
FLOW SHEET FS-6
FLUE GAS- MILLION ACFM - - 1.60 1.07 1.06 BECHTEL NATIONAL, INC., SAN FRANCISCO 94119
TONS/HOUR - DRY - - 2180 2180 2180
TEMPERATURE - - 450 150 145 RF.C:HTF.t .JOB DATE FLOW SHEET NUMBER
ABS. HUMIDITY LBS H20/LB DRY GAS - - 0.038 0.08 0.08 13022 JULY 1979 FS-7
5-83
THIS PAGE
. WAS INTENTIONALLY
LEFT BLANK
I
I MAJOR EQUIPMENT LIST
I SINGLE-STAGE CAGE MILL COAL
~FINE CRUSHING WITH PRESCREENING
I ALTERNATIVE FLOW SHEET FS-8
Number
Equipment Title
HP
Design Rating and Description
I
Specification Requirements and Comments
Required Each I
I
2 Dry Coal Screening Surge Storage 200 Design Capacity: 2,400 tph See General Conveyor Specification.
Tripper Conveyor System Belt Width: 60 in.
8 Dry Coal Screening Surge Bin Design Capacity: 62 tons Mass flow bin with lined bottom for even flow
(500 tons, total combined capacity) promotion.
8 Vibrating Coal Screen 50 Design Capacity: 300 tph This is the largest double deck coal screen
Type: Double Deck currently manufactured in the United States.
Vibrating Low head floor-mounted-type screen.
Size: 10 ft X 24 ft Spring steel woven ;wire deck construction.
Deck Opening Size: 3/4 in. top
5/16 irl. bottom
2 Coal Crushing Scissor Conveyor 500 Design Capacity: 1,700 tph See General Conveyor Specification.
System Belt Width: 60 in.
I
2 Screened Coal Crushing Tripper Design Capacity: 1,700 tph See General Conveyor Specification.
I
Conveyor System Belt Width: 60 in. I
i
4 Screened Coal Crushing Surge Bin Design Capacity: 100 tons Mass flow bin with lined bottom for even flow
I
(400 ton, total combined capacity) promotion.
4 Coal Crushing Gravimetric Belt 30 Design Capacity: 600 tph See General Gravimetric Belt Feeder Specification.
Feeder Belt Width: 72 in. !,·
4 Coal Fine Crusher 1,200 Design Capacity: 600 tph See General Cage Mill
I!
Specification.
Type: Two Row Cage Mill
Size: 72 in. diameter
2 Fine Coal Conveyor 300.: Design Capacity: 2,400 tph See General Conveyqr Specification.
Belt Width: 60 in. t
ir
1 Screening and Fine Crushing Surge 150 Design Capacity: 50,000 acfm Standard Baghouse System.
Bins Baghouse Dust Collection I
System
-·
5-85
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
TO A TMOSPH ERE
21N. X OCOAL
CLEAN COAL
FROM COARSE COAL
THERMAL DRYING
FLOW SHEET FS-7
CRUSHING GRAVIMETRIC
·sCREEN 0 BELT FEEDER (4)
GRAVIMETRIC
BELT FEEDER (8)
LINE !OVERSIZE
NO.1 NO.2
II,(;AS· 1/4 IN X 0
·UNDERSIZE
LINE NO. 1 NO.2 LINE NO.2 TO CONVERSION REACTOR
N0.1 FEED SYSTEMS
FINE COAL
STREAM NUMBER
0 0 0 0 ~ 0 UNION CARBIDE CORPORATION- NUCLEAR· DIVISION
OAK RIDGE NATIONAL LABORATORY
COAL- TONS/HOUR- DRY 1,566 196 59 1,094 274 1,566
PERCENT MOISTUR.E 3.0 3.0 3.0. 3.0 3.0 3.0
TONS/HOUR - WET 1,614 202 61 1,126 282 1,614 CONCEPTUAL FLOW SHEETS DEVELOPMENT FOR COAL
CONVERSION PLANT COAL HANDLING-PREPARATION
AND ASH/SLAG REMOVAL OPERATIONS
CONTRACT NO. 62X - 46724V
5-87
THIS PAGE ·
WAS INTENTIONALLY
LEFT BLANK
Dry coal screenill:g at 1/4 inch represents an approximate practical lower
size limit and requires relatively dry coal. Because of this, FS-8 was only
considered as a possible ultrafines minimization approach for U-Gas and
the coal entering FS-8 was spec~fied as coming from FS-7, Coarse Coal
Thermal Drying._ Screening of coal at sizes finer than 1/4 inch results in
rapidly d~creased scr~en .loadings, i.e., the s~xeen area required increases
rapidly. Also, the amount of coa~ surface moisture that can be tolerated
without deterioration of screen efficiency becomes increasingly smaller.
Coal surface mo~stures on the order of several_percent are sufficient to
blind fine dry screens.
The Texaco Partial Oxidation Gasification Process uses a coal feed system
in which a high solids conc'entration coal-water slurry is injected by posi-
tive dispiacement pumps into an entrained flow gasifier. Gasifier operating
pressure is 500-1,500 psig depending on synthesis·gas requirements arid coal
composition. To produce feed slurry for their gasifier Texaco has proposed
rod mill wet grinding. (Because of rod mill use the term grinding is used
even though the coal size consist produced fits the definition of coal fine
~rushing established in this report. This usage is consistent with current
mineral beneficiation industry terminology.)
The reason for spec1f1carion of rod mills rather than ball mills in fS-10
is that tpey produce a narrower size range product. They produce very
little oversize and few ultrafines. A disadvantage of rod mills and the
reason so many are specified is that they·are capacity limited. Due to
the unavailability of rods that will perform properly in large rod mills
their length is limited to approximately 20 feet. Rods longer than this
will not stay straight during_ grinding and. break into pieces that are dis-
charged from the mill as iarge chunks. The largest rod mills currently
installed are 15 ·teet in diameter.
In FS-9 fine coal is conveyed to a series of surge bins. From each bin it
is fed by a gravimetric belt feeder to an air classifier. These air
classifiers are similar to those described in FS-5, Cage Mill Closed-Circuit
Coal Fine Crushing. The main difference i~ that hot flue gas (450°F) from
the power/steam plant is injected into the ultrafines classifiers to reduce
coal moisture. Ultrafine coal is discharged from each classifier at two
locations: the classifier fines cone and entrained in exiting dry flue
gas. Ultrafines collected in the tines cone are discharged by rotary lock
valves to one of two mass flow conveyors. Ultrafines entrained in the drying
flue gas are removed by cyclones in series with multicompartment baghouses.
Collected coal from both the cyclones and baghouses are discharged to the
same mass flow conveyors as ultrafines coll~~t.ed in tLc ·...:1.:~:..-sifier fines
cones.
5-90
MAJOR EQUIPMENT LIST
FINE COAL ULTRAFINES SEPARATION
FLOW SHEET FS-9
Number HP i
Equipment Title Design Rating and Description SpecificationiRequirements and Comments
Required Each
6 Air Classifier Gravimetric Belt 30 Design Capacity: 400 tph See General Gravim~tric Belt Feeder Specification.
I
Feeder Belt Width: 72 in. I
li
·I
6 Crushed Coal Air Classifier 500 Design Capacity: 400 tph Air Classifiers of: up to 24 ft in diameter are
Type: . Mecharii:cal' :centrifugal currently used fori closed-circuit cement grinding.
Air Classifier with Hot flue gas is ad~ed to control coal surface
Drying Gas Injection moisture for efficient classification.
Size: 22 ft diameter 1. Abrasion resistant steel lined.
24 Air Classifier Exhaust Gas Design Capacity: 20,000 acfm Cyclones of this size are of standard design and
Cyclone Type: Centrifugal Gas Cyclone are widely used for gas particulate separation.
Number of Cyclone Clusters: 6 Cyclones are manifolded together in clusters of
Size: 6 ft diameter four cyclones which have a common underflow bin.
Abrasion resistant steel lined
'
3 Particulate Coal Collection 60 Design Capacity: 200,000 acfm Baghouse collector~ of this capacity are custom
System Multi-Compartment Number of Compartments: 6 designed and fabricated.
Bag house Design Pressure Drop: 8 ~.n. H20 The baghouse is equipped with an explosion detec-
Area: 120,000 ft tion and suppression system.
I
Bag Material: Fiberglass The baghouse systems include coal collection bins
and interconnecting mass flow conveyors.
I
3 Baghouse Induced Draft Fan 1,000 Design Capacity: 200,000 acfm Standard Design F}~e Gas Fan.
II
Design Head: 30 in. H20 'I
2 Fine Coal Conveyor 300 Design Capacity: 1,800 tph See General Conveypr Specification.
Width: 60 in. I
1 Ultrafines Surge Bins Baghouse 150 Design Capacity: 50,000 acfm Standard Baghouse System.
Dust Collection System
5-91
THIS PAGE
WAS.INTENTIONALLY
LEFT BLANK
ORNL-OWG 80-4208 ETO
TO ATMOSPHERE
FINE COAL
AIR CLASSIFIER
GRAVIMETRIC EXHAUST GAS
BELT FEEDER (61 CYCLONE (241
PARTICULATE COAL
COLLECTION
MUL TICOMPAATMENT
CRUSHED COAL BAGHOUSE (31
AIR CLASSIFIER
(61
ROTARY LOCK
ROTARY LOCKS
I
~
L
I
ULTRAFINES
ULTRAFINES
MACC FLOW
CONVEYOR (21 I
HOT FLUE GAS (450°1
~ (~~
I~---------------------~------------~- ' FROMPOWERfflTEAMPLANT
0 l
I FINE COAL
TO CONVERSION REACTOR
FEED SYSTEMS
FINE COAl .. CONVEYOR (2)
Number· HP
Required
Equipment Title
Each
Design Rating and Description Specification R~quirements and Comments
;f
2 Grinding Surge Storage Tripper 200 Design Capacity: ' 2,400 tph :I
S ee Genera 1 Conveyq,r spee~"f"~cat~on.
.
Conveyor System Belt Width: 60 in.
13 Grinding Surge Bin Design Capacity: 140 tons MasS flow bin with !lined bottom for even
(1,800 tons, total combined capacity) flow promotion. I
13 Rod Mill Gravimetric Belt 20 Design Capacity: 180 tph See General GravimJtric Belt Feeder Specification.
i
Feeder Belt Width: 72 in. I
13 Coal Grinding Rod Mill 1,800. Design Capacity: 180 tph \vet rod mills of this size are currently used
Type: Overflow Discharge for ore and coal gtinding.
Size: 14~ ft rliameter. by 20 ft 20 ft is an approx~mate maximum length for a
long rod mill. ·I
Volume Load~ng: 35 percent
Operating Speed: 13 rpm
(64 percent critical speed)
Rod Charge: 200 tons
1 Grinding Surge Bins Baghouse 150 Design Capacity: 50,000 acfm Standard Baghouse ~ystem.
Dust Collection System
i
. 5-95
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
BAGHOUSE DUST COLLECTION SYSTEM (1)
2 IN. X 0 COAL
CLEAN COAL
FROM COARSE COAL
LIVE STORAGE
BLENDING
LINE NO.1
WATER
3716 GPM (TOTAL FOR 13 LINES)
FROM CONVERSION PLANT
WATER TREATMENT
AND SUPPLY COAL GRINDING ROD MILL (13)
TEXACO PARTIAL OXIDATION: 20 MESH xo COAL PRODUCT
9040 GPM (TOTAL 13 LINES.)
I
>
14~ FT DIA. X 20FT. LONG @ 60% SOLIDS Tl) CONVERSION REACTOR
s-·97
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
Ultrafines free GOal is discharged from the air classifiers by rotary lock
valves and flow switching chutes to one of two fine coal conveyors. These
conveyors convey it to conversion reactor coal feed systems.
..
tion of processes for treating ultrafines, however, was not part of the
undertaking covered by this project. Possible ultrafines uses include:
e Direct firing in pulverized coal-fired steam generators
Screw conveyors
·-
g Water or other fluid slurry transport if compatible
with ultrafines utilization
5-100
s·. 5 COAL PULVERIZING AND GRINDING. CONCEPTUAL FLOW SHEETS
The two coal pulverizing alternatives presented in the coal mine-coal conver-
sj_on plant interfCl.ce final report· are: ball tube mill and roller mill coal
puiverizing. In both ~lternatives lat~e qtian~ities oi hot flue gas (450°F)
·frorri the pow~r/steam plant are u.sed.to transport coal.through the mills
arid sim~ltaneoriilj dry it from a~ r~ceived to ~.0 wt percent total ~oisture.
After pulverizing to 70 percent minus 200 mesh, coal is deentrained from
th~·convey1ng~dry{ng flue gas in cyclone clusters iri series with large,
multicompartment baghouses. Specific interface report flow sheets and
,. ·.·. ..
conceptual drawings concerned with coal pulverizing and pulverized coal
separation are:
5-101
Both the ball tube and rollet mills specified in the interface pulverizing
flow sheets are rated at 250 tons per hour of feed coal. To date, the
largest coal ball tube mill is rated at approximately 80 tons per hour
and the largest coal roller mill at approximately 100 tons per hour.
Scale up of both mill designs to the 250 ton per hour range judged re-
quired for commercial coal conversion plants does appear technically
feasible. This conclusion is based on discussions with major, large
coal mill designer-manufacturers; Bechtel experience with dry coal mills
for the utility industry anrl lArge wet and dry mille for the metal~
industry; and, reported experience .with large dry mills in the cement
inductry. Certain design areas, ~atllcularly mill driVe syste~s, will,
however, require additional development and demonstration. To date there
has been no incentive to develop coal mills larger than 100 tons/hour. This,
rather than technical reasons, is why larger coal mills have not been built.
Pulverized coal produced by both interface report flow sheets would have
to be transported from the cyclones and baghouses used to deentrain it
from mill system transport drying flue gas to the H-Coal coal feed system.
Comments in Subsection 5.4.2 concerning ultrafine coAl transport alto apply
to the 70 percent minus 200 mesh, dried coal produced by these flow sheets.
However, in the case of H-Coal the pulverizerl cnal transport distances could
probably be kept short and the need for excessive coal e]evRtion avoided.
5-102
MAJOR EQUIPMENT LIST
SOLVENT COAL GRINDING
FLOW SHEET FS-11
i'
Number
Required
Equipment Title
HP
Each
Design Rating and Description Specification R~quirements and Comments
2 Coal Grinding ·Surge Storage Tripper 200 Design Capacity: 2,400 tph See General Conveyo:r Specification.
Conveyor System Belt Width: 60 in. I
9 Coal Grinding Gravimetric Belt 30 Design Capacity: 300 tph See General Gravime,tric Belt Feeder Specification.
Feeder Belt Width: 72 in.
I
Coarse Coal Crusher 800 Design Capacity: 300 tph See General Cage Min Spe.ctftcat:i.on.
Type: 2 Row Cage Mill
Size: 72 in. diameter I
I
i
9 Crushed Coal Screw Conveyor 40 Design Capacity: 300 tph Screw Conv~yors of :1this capacity are standard
Type: Double Helicoid Flights equipment. I
Flight Diameter: 10 in.
9 Coal Ball Mill 6,000 Design Capacity: 300 tph Wet ball mills of t~is size are currently used for
Type: Overflow Discharge ore grinding, but riot coal.
Size: 18 ft diameter by Solvent coal grindihg has yet to be demonstrated.
28~ ft long Mill system vapor s~aling is an area where devel-
Volume Loading: 40 percent opment is required.,
Operating Speed: 13 rpm
(68.7 percent critical speed)
Ball Charge: 393 tons
9 Ball Mill Discharge Sump - Design Capacity: 300 ft 3 This sump would require a vapor control system.
Construction: Concrete
9 Ball Mill Discharge Pump 75 Design Capacity: 1,800 gpm Pumps for handling '.of pulverized coal-solvent
Type: Horizontal Centrifugal slurry are being de,veloped as part of coal con-
Construction: Ni-Hard Impeller version process deV,elopment and demonstration
and Casing projects. 1
1 Coal Grinding Surge Bins Dust 60 Design Capacity: 20,000 acfm Standard Baghouse System.
Collection System
J
5-103
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
TO ATMOSPHERE
GRAVIMETRIC 21N. X 0
BELT FEEDER (9) 3 WT PERCENT
TOTAL MOISTURE
SOLVENT
~
OAK RIDGI& NATIONAl lABORATORY
STREAM NUMBER
0 0 0
COAL- TONS/HOUR- DRY 1629 181 - 181 CONCEPTUAL FLOI(V SHEETS DEVELOPMENT FOR COAL
PERCENT LIQUID PHASE 3.0 3.0 - 55 CONVERSION PLANT COAL HANDLING-PREPARATION
TONS/HOUR - WET 1,648 183 219 402 AND ASH/SLAG REMOVAL OPERATIONS
I CONTRACT NO. 82X- 45724V
I
'
I
I
SOLVENT COAL GRINDING
H-COA!. PROCESS
5-105
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
In FS-11 dry coal is coriveyed by two, parallel, full design capacity con~
veyors to two, parallel surge storage tripper conveyor systems which dis-
charge it into.in-line surge bins. From here it is discharged by gravi-
metric belt feeders to fine crushing cage·mills~ Surge storage, mill
feeding, and fine crushing operations are very similar to those described
in FS-3~ Single-Stage Cage Mill Fine Crushing. Fine-crushing is used be-
fore grinding to reduce overall conuninution power requirement, Le,, power
required for the approach shown in FS-11 is considerably less than direct
feeding of 2 inch x 0. coal-to a ball mill.
Coal· crushed to 11ominally 1/8 ·inch x 0 is discharged from the cage m;i.lls .
to screw conveyQrs which convey it to 18~foot-diameter ·by 28 1/2 foot-long
ball mills. Estimated installed power requirement for each mill is 6,000
hp. Ball mj_lls of the specified size are currently available conunerc:i;ally.
Two copper concentrators, Bougainville in Papua New Guinea and Pinto Valley
in Arizona, used 18 foot-diameter ball mills for primary grinding. Use of
ore grinding ball mills with diameters in excess of 20 feet and lerigths of
up to 40 feet is anticipated in the near future. The 6,000 hp miJ;l power
specified is slightly higher than that for currently operating ball mills -
5,000 hp, but within the capability of current mill drive systems.
In FS-11 coal is assumed to be. dried .before grinding. The material balance
feed coal total moisture c6ncentration is 3.0 wt percent; one p~rcentage
point more than the H-Coal feed moisture requirement presented in Table 4-1.
This 'difference is not considered significant, but, 'if required, coarse
coal ~ould probably be dried to 2.0 wt percent moisture in FS-7 o~ a similar
drying flow sheet. In the EDS, SRC-1, and SRC-II conversion p.rocesses coal
5-108
5.6 ASH/SLAG REMOVAL CONCEPTUAL FLOW SHEETS
As presented in Table 4-2 and Figure 4-8, ash and slag are discharged from
conversion reactors in two general forms:· as water slurries-and as dry
solids. These are also the two forms considered for moderate distance, on
the order of 5 miles, transport to an ultimate, environmentally acceptable
disposal site. That is, transport as low-moisture concentration solids or
as a water slurry.
Solids from the SRC-1 process represent a special case. Solid waste from
this process was postulated to be washed and dried filter cake from pressurized
filtration of SRC-1 liquid."· Further, this filter cake was postulated to
contain significant amounts of unreacted carbon and liquids that could dis-
solve or be extracted by water slurrying. Because of these characteristics,
only transport as a solid was considered practical for SRC-1 solid wastes.
Flow SQeet FS-12 presents two ash and slag dewatering alternatives to
produce· m&terial suitable for transport in trucks, rail cars, or on cross
country conveyors. These two alternatives are vacuum filtration and spiral
separation. Filtration would be used to dewater fine ~sh slurries, such
as those believed to result from the HYGAS, Exxon Donor Solvent, and Exxon
Catalytic Gasification gasifiers. Spiral separators are suited to dewatering
only coarse solids, such as granulated s~ag from the Texaco Partial Oxidation
gasifier and COGAS cyclone char-combustor, and possibly U-Gas agglomerated
ash. Separate material balances are presented for each alternative. The
unlettered balance is for ash-water slurry dewatering and the 'A' balance
applies to granulated slag slurry dewatering~
5-109
In FS-12 ash or slag after dewatering is combined with dry solids produc.ecl
at the power/steam plant. The dry steam generator solids (see Subsection
4.3.5 for estimated composition) would likely be conveyed to the solids
mixing operation by some type of pneumatic conveying system. Such systems
capable of handling the quantities of steam generator solids estimated for
coal conversion are currently available.
Combined gasifier slag or ash and power/steam plant solids are conveyed
to a surge storage silo. Depending on gasifier type, slagging or aoh pro
ducing~ estimated feed to surge storage is 367 or 222 tons per hour of
wastes. This quantity of dewatered solid wastes plus the larger quantity
(1,200 tons per hour) of coal cleaning solid refuse would prob@bly be trans-
ported to a disposal site by either a closed-circuit, dedicated rail system
or a cross country conveyor system. Though technically feasible, trucking
would probably not be economically feasible for a transport distance on the
order of five miles. A very large fleet of trucks would be required to trans-
port the quantity of solid wastes shown in the two FS-12 material balances.
Loadout for rail transport is shown in FS-12. In thP. rrn~=:~=: rm.mtry con-
veying alternative, the surge silo feeder would discharge coal directly to
the conveyor system. Coal cleaning plant refuse would be discharged onto
this conveyor system directly from the coal rleaning plant refuRP rnnvcyor
or ir1termediate conveyors, if required. Cross country conveyor systems of
the capacities required to meet the conditions presented in FS-12 are
currently used for moderate distance transport of coal and ore.
5-110
FILTRATION
DISTRIBUTION
ASH-SLURRY L-r--r-r-""T""' BOX I 1I TO ATMOSPHERE
FROM COAL CONVERSION GASIFIERS:
cl
HYGAS
EXXON DONER SOLVENT (11
FILTRATION FEED
EXXON CATALYTIC GASIFICATION
PUMP (21
ASH-SLURRY (1 OPERATING- FILTER VACUUM PUMP (8)
COLLECTION 1 STAND BY) (6 OPERATING- I
AND MIXING
TA.NK (1) t---++ 2STAND BY) I
COLLECTION AND MIXING I FILTRATE
TANK AGITATOR (11
....__ _ _--t~ TOEMERGENCY FILTRATE PUMP (12) TO RECYCLE OR TO
STORAGE POND (6 OPERATING- CONVERSION PLANT
6STAND BY) WATER TREATMENT
0 NOTE (2)
DRY SOLIDS >------------~-------------------------------------------------------------<QR>-------~~ NOTES:
FROM POWER/STEAM PLANT SOLIDS (1) THE EXXON DONOR SOLVENT PROCESS
MIXER (2) PRODUCES DRY ASH IN ADDITION TO AN
)>--------------<3>~-·---------------------------------------------------------------------
7
>
·I
ASH-WATER SLURRY. THE DRY ASH
COALCLEANING
! WOULD BE HANDLED IN THE SAME WAY
- REFUSE
FROM COAL CLEANING
.
i
I
I
AS SHOWN FOR POWER/STEAM PLANT
DRY SOLIDS.
REFUSE CONVEYOR I
FLOW SHEET FS-1 SOLID (21 DEPENDING ON CONVERSION PROCESS
WASTE GASIFIER, POWER/STEAM PLANT DRY
SAMPLING SOLIDS WOULD BE COMBINED WITH
STATION DEWATERED ASH OR DEWATERED SLAG.
r-------"'----,1
131 THE CONVEYING, SURGE STORAGE, AND
DISPOSAL SITE TRANSPORT FACILITIES
ASH OR SLAG ARE SIMILAR FOR BOTH DEWATERED
SLURRY ASH/SLAG ASH AND SLAG
DISPOSAL
FROM COAL CONVERSION GASIFIERS:
SURGE SILO
U-GAS
~) * J ~ ~~~~EREO >
TEXACO PARTIAL OXIDATION
COG AS
BELT FEEDER I
100 TON HOPPER TO SOLID WASTES
'
RAILICAR LOADING RAIL CARS DISPOSAL SITE
CON~EYOR
ALTERNATIVE: IN PLACE OF RAIL
i CARS A CROSS COUNTRY CONVEYOR
SYSTEM COULD BE USED TO TRANSPORT
DEWATERED SOLIDS TO A DISPOSAL SITE.
DRY SOLIDS, TONS/HOUR 228 228 - 41 269 163 163 - 41 204 1012 ; 1281
PERCENT MOISTURE 60 30 100 0 27 60 10 100 0 8 15 18 ASH AND SLAG DEWATERING
WET TOTAL, TONS/HOUR 570 326 244 41 367 408 181 227 41 222 1200 1567 AND TRANSPORT
5-111
THIS PAGE
WAS INTENTIONALLY-
LEFT BLANK
MAJOR EQUIPMENT LIST
ASH AND SLAG DEWATERING AND TRANSPORT
FLOW SHEET FS-12
Number HP
Equipment Title Design Rating and Description Specification Requirements and Comments
Required Each
6 Ash Vacuum Filter 20 Design Capacity: 46 tph Solids Standard design disc vaccum filter with standard
10 .Type: Disc Vacuum Filter accessories
Disc Size: . 12 ft1 6 in. diameter by
15 discs
Overall Dimensions: 15 ft by 29 ft
by 14 ft 6 in.
6 Ash Vacuum Filter Filtrate - Overall Dimensions: 84 in. diameter Steel construction
Receiver by 84 in. long
12 Ash Vacuum Filter Filtrate 10 Design Capacity: 200 gpm Slurry duty - horizontal filter pump
Pump Design Head: 50 ft Wetted parts to be NiHard
,,
Type: Centrifugal-Slurry Handling
Vacuum Service
Slurry Specific Gravity: 1.0
(turbid)
I
8 Ash Filter Vacuum Pump 400 Design Capacity: 8,000 cfm at Wet type standard v~cuum pump
20 in. of Hg '
i
Type: Horizontal-Centrifugal Slurry I
I
2 Solids Mixer 75 Design Capacity: 500 tph Double-paddle type standard design solids mixer
Several types of solids mixers are available for
this application
5 Dewatering Spiral Separator 15 Pool Area: 200 ft2 Standard design steel
I
tank with hydraulic lift
Spiral Diameter: 60 in. for spiral
Tank Slope: 3 1/2 in./ft Complete with accessories
Pitch: Double
5-113
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
MAJOR EQUIPMENT LIST
ASH SLURRY DEWATERING
FLOW SHEET FS-12
Number HP I .
Equipment Title Each
Design Rating and Description Specification Regu1rements and Comments
Required !
I
40 ft.
15 discs I
I
I
Overall Dimensions: 15 ft X 29 ft
X 14 1/2 ft
:
I
12 Filtrate Receiver - Size: 84 in. X 84 in. i
i
24 Filter Vacuum Pump 400 Design Capacity: 8,000 scfm ,)1
28 ft. long I
I
Tank Slope: 3 1/2 in. /ft
5-115
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
FLOW SHEET FS-12 (Continued)
Number HP
Equipment Title Design Rating and Description Specification Requirements and Comments
Required Each
\
s Overflow Water Pump 10 Design Capacity: 2SO gpm Standard design PUJ!lp
Design Head: 80 ft
Type: Horizontal-Centrifugal
Water Pump
Slurry Specific Gravity 1 (turbid)
I
2 Dewatered Ash/Slag Transfer 10 Design Capacity: 2SO tph See General Conveyor Specification
Conveyor Belt Width: 48 in. I
I
2 Solids l1ixer 7S Design Capacity: soo tph Double-paddle type, standard design solids mixer
Several types of 'solids
,, mixers are available for
this applicatiom
'I
,,
ASH/SLAG SURGE STORAGE AND LOAD OUT ':
2 Ash/Slag Surge Storage Feed so Design Capacity: soo tph See General Conveyor Specification
Conveyor Width: 48 in.
1 Ash/Slag Disposal Surge Silo - Design Capacity: SOO tons Concrete mass flow design
I
1 Ash/Slag Disposal Surge Silo Belt so Design Capacity: 2,000 tph Variable speed stahdard design belt feeder
Feeder Width: 72 in. I
S-117
.'
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
DRY SOLIDS
WATER SUPPLY TANK."
DRY SOLIDS
FROM POWER/STEAM PLANT BIN Ul
COAL CLEANING
REFUSE
ASH OR SLAG
-- ~'""""
HAMMER
MILL
FLOW SHEET FS-1
SLURRY
REFUSE SLURRY
DISPOSAL AREA
• TURN
UNION CARBIDE CORPORATION- NUCLEAR DIVISION
WATeR SUMP
RETURN WATER . . OAK RIDGE NATioNAL LABORATORY
PUMP (21
(1 OPERATING
AND 1 STANDBY) CONCEPTUAL FLOW SHEETS DEVELOPMENT FOR COAL
CONVERSION PLANT COAL HANDLING-PREPARATION
AND ASH/SLAG REMOVAL OPERATIONS
CONTRACT NO. 62X - 45724V
STREAM NUMBER
0 0 0 0 0 ~ 0 0 ~ ~ ~ ~ ~ ~ <& ~
ASH AND SLAG SLURRY
DRY SOLIDS, TONS/HOUR 228 41 101;2 - 1281 - - - 163 41 1012 - 1216 - - - PIPELINE TRANSPORT
PERCENT MOISTURE 60 0 15 100 50 100 100 100 60. - 15 - 50 100 100 100
WET TOTAL, TONS/HOUR 570 41 1200 751 2562 1084 752 332 408 41 1200 783 2432 1034 783 251
- BECHTEL NATIONAL, INC., SAN FRANCISCO 94119
'5-119
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
MAJOR EQUIPMENT LIST
ASH AND SLAG,SLURRY PIPELINE TRANSPORT
FLOW SHEET FS-13
Number HP
Equipment Title Design Rating and Description Specification Requirements and Comments
Required Each
I
1 Slurry Collection Sump Design Capacity: 3,700 gal Standard design with one side sloping with AR
steel liners :
2 Slurry Transfer Pump 60 Design Capacity: 2,100 gpm Wetted parts to be NiHard
Design Head: '50 'ft
Type: Horizontal-Centrifugal
-Slurry
Slurry Specific Gravity: 1. 35
1 Slurry Disposal Sump Agitator. 50 Type: Propeller Rubber lined shaft;and propeller
I
1 Dry Solids Bin Design Capacity: 100 tons Mass flow bin with lined bottom for even flow
promotion
2 Dry Solids Bin Screw Feeder 10 Design Capacity: 25 tph Standard design for dry abrasive solids
1 Coal Cleaning Plant Refuse 800 Design Capacity: 1,250 tph Standard design re~ersible hammermill
Hammermill Feed Size: 3 in. by 0 '
Product Required: 1/8 in. by 0
I
3 sets Ash/Slag Disposal Pump 300 Design Capacity: 2,000 gpm/train Two sets operatingland 1 set standby
Design Head: 5 by 120 ft = 600 ft Wetted parts in Ni~ard
Type: Horizontal-Heavy Duty-
Centrifugal-Slurry Pumps
Number of Pumps/Set: 5
1 Return Water Sump Design Capacity: 65,000 gal '
Concrete construction
2 Return Water Pump 250 Dccign Capacity: 5~500 gpm One operating and ·?ne standby
Design Head: 500 ft :r
Type: Hor.izontal-Mul tis tage Standard design water pump
-Centrifugal Pump
·l
5-121
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
gasification are of significantly lower solids concentration, it could be
practical to concentrate them up ~o 40 wt percent solids or higher. Waste
solids could be concentrated by methods similar to those used in FS-12 or
by use of thickeners~
The impoundm~nt site shown in FS-13 would probably have to be fully lined
with hypalon or similar lining material for impermeability. Decant from
this impoundment could be recovered with a barge and floating pipe system.
From here it would be returned to the conversion plant water treatment
facility or part of it reused directly for solid wastes slurrying.
Equipment identified in flow sheets FS-12 and FS-13 and their major equip-
ment lists are currently available in the presented design capacities.
Areas where additional data would be of value in engineering actuai con-
version plant solid wastes preparationI and transport facilities are:
5-124
GENERAL CAGE MILL SPECIFICATION
1. 0 GENERAL
Cage mills of the capaciti~s specified-i~ the major equip~ent lists would be
purchased from a l~mited number of manufacturers which have provided similar
mills. Each manufacturer has his own proven design, parts of which may be
protected by patents, and fabrication methods. 'Provision of mills. that
depart significantly in design from that used by a given manufacturer is
unlikely and would probably not result in any guarantees.
2.4 Rreaker pl.;ttes and impact bars will be of the reversibie type to
dist~ibute wear evenly.
A-1
2.5 All parts subject to.wear will be cast in wear-resisting steel
alloys.
2.6 Each rotor assembly will be balanced statically and dynamically for
smooth operation.
2. 7 All bearings will be heavy duty and equipped with. taconite dust-
tight seals.
2.8 All welding will be in accordante with the latest issue of the
Structure Welding·Code of the Welding Society- AWS-Dl.
GENERl\1 CONVEYOR SPECIFICATION
1.0 GENERAL
A-3
2. 1.3 _ Hherever possible, all conveyors will be installed in enclosed
galleries and supported from the gallery ceiling. All outside conveyors
operating with rail-mounted stackers and reclaimers will be covered
(except where interference occurs) or equipped with removable windboards.
2. 2 Conveyor- Idlers
0
2.2.2 Carrying idlers will be rigid frame, 35 trough, three equal roll-
type minimum 6-inch~diameter.rolls.
'1..'1...4 Training idlers will be provided, ·as necessary, for belt training
purposes on the carrying side of fabric belts only and will be. installed
so as to prevent disturbance to material flow.
roll "Vee" type, with minimum 15° troughing angle. The idler rolls wi 11
be mounted off-set on their respective frames to minimize build up of
dribble.
A-4
2.3 Pulley Assemblies
2. 3. 2 All conveyor pulleys for steel :cord and fabric belting will be
custom designed to the specific loads and will be flat face type. The
pulleys will be of the rigid and disc design with. hub construction suit-
able for Ringfeder type locking devices. The face of all conveyor pulley~?
will be 8 inches wider than the belt. The face of pulleys for belt feeders
will be 6 inches wider than the be+t.
2. 3. 3 All drive pulleys will have herringbone grooved, 1/2 inch thick,
rubber lagging.
2.4 Take-Ups
2.4.1 Take-ups will be located at the tail pulley wherever possible and
will be carriage-mounted motorized-winch type for take-:up .travel over 4
feet and motorized-screw type for take-up travel of less than 4 feet.
A-5
2.5 Conveyor Drives
2.5.2 All drives and conveyor components will be sized to start the con-
veyor under full design load.
2. 5. 3 All motors 100 hp and below will be squirrel-cage type with fluid
couplings to provide a controlled acceleration.
2.5.4 Conveyor drive motors over 100 11P w:Ul be wound-rotor type ~ompl ete
2.5.5 The average conveyor acceleration torque will not ·exceed 150 per-
cent of the normal running torque.
2.5.6 Where required, the drive unit will have a braking system to con-
trol the coasting time and to prevent roll back.
2.6.2 Belting will provide adequate load support while allowing suffi-
cicnc cran9VCrac flexibility.
A-6
2. 6. 4 Climatic conditions and material characteristics will be given
careful consideration in selection of the belt. All conveyor belts will
be oil and fire resistant and remain flexible at freezing temperatures.
2. 7 Miscellaneous
A-7
2. 7. 3 Adjustable baffle boards will be provided at each transfer chute
to regulate flow trajectory.
2. 7. 6 All conveyor belts which are not installed i.n P.nrlnsed galli!ries
will have removable wind boards;
A-8
GENERAL GRAVIMETRIC BELT FEEDER SPECIFICATION
1. 0 GENERAL
This general $pecification· identifies some major components that are recom-
mended for conversion coal gravimetric feeders. A detailed procurement
specification.would probably contain more design requirements than covered
here. These could include varial;>le speed drive design specification,
control-sensing system design, calibration procedures·, assembly and erec:-
tion procedures, finish details, and performan~e and workmanship guarantees.
A-9
2.3 Gravimetric belt feeders will be heavy duty type, will be horizon-
tally, and designed for a maximum belt speed not exceeing 190 feet per
minute.
2.4 All gravimetric belt feeders will have fixed screw type take-ups
located at the tail pulley.
2.5 Gravimetric feeders will be provided with guide rollers for posi-
tive belt tracking and be designed for rapid belt replacement.
A-10
REFERENCES
GENERAL
R-1
4. Lee, Bernard S., "Current Development of the HYGAS Program," Pro-
ceedings of the Eighth Synthetic Pipeline Gas Sympos1um, Chicago,
Illinois, October 18 - 20, 1976.
5. Bair, Wilford G., "HYGAS Process Update," Proceedings of the Tenth
Synthetic Pipeline Gas Symposium, Chicago, Illinois, October 30 -
November 2, 1978.
6. Confidential reports, Bechtel National, Inc.
7. Exxon Research and Engineering Company, "EDS Coal Liquefaction
Process Development Phase.IIIA," Exxon Donor Solvent Coal Liquefaction
Commercial Plant Study Design, January 1978, FE-2353-13.
R. Furlong, L.E. and Nahas, N.C., 1'Catalytic Coal Gasification-Process
Research and Deve l.opment," P r.oceeding::; of th·e '!'~nth SynthPtic Pipeline
G~s Sympo::lium, C:ltl;:::~go, Illinois, OcLuher 10- November 1, 1978.·
R-2
I
I
TABLE REFERENCES
R-3
11. Patel, J. G., "Clean Fuel From Coal Is Goal of U-Gas Process," The
Oil and Gas Journal, August 1, 1977, Volume 75, No. 31.
12. Eby, R. J., McClintock, N. and Bloom, Jr., R., "The Illinois Coal
Gasification Group Project-COGAS Process," Proceedings of the Tenth
Synthetic Pipeline Gas Symposium, Chicago, Illinois, October 30-
November 1, 1978.
13. Bair, \.J. G., "Status of The HYGAS Program," Proceedings of the Ninth
Synthetic Pipeline Gas Symposium, Chicago, Illinois, October 31-
November 2, 1977.
,,-· .
. ,,
,.
R-4
_'(
ORNL/SUB-79/45724/l
REPORT JOB 13022
INTERNAL DISTRIBUTION
1. P. K.
Carlson 29. M. D. Silverman
2. D. Dyslin
A. 30. 0. W. Thomas
3. D. M.
Eissenberg 31. F. C. Zapp
4. J. Horton
R. 32. ORNL Patent Office
5. J. E. Jones, Jr. 33. Central Research Library
6. w. A. McAuley 34. Document Reference Section
7. R. E. Mac~herson 35-36. Laboratory Records Department
8. B. Niemann 37. Laboratory Records, ORNL RC
9-28. L. F. Parsly
EXTERNAL DISTRIBUTION