The document provides a summary of tasks completed and planned for an electrical project at Aqaba on April 1, 2021. It lists 9 tasks completed for the day including painting steel conduit and installing cable ladder supports. It outlines 5 planned tasks for the next day such as soil resistivity testing and painting conduit accessories. Staffing information is also included.

Uploaded by

Ahmad Dagamseh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
59 views

Day: Date: Department: Project

The document provides a summary of tasks completed and planned for an electrical project at Aqaba on April 1, 2021. It lists 9 tasks completed for the day including painting steel conduit and installing cable ladder supports. It outlines 5 planned tasks for the next day such as soil resistivity testing and painting conduit accessories. Staffing information is also included.

Uploaded by

Ahmad Dagamseh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Project : Aqaba Screening Project

Day : Tuesday
Date : 04.01.2021
Department : Electrical
Tasks Done by Today
1
Painting HDG Steel Conduit
2
Engineering : Quantity and method scaffolding survey for Electrical Works for T09 and Conveyor 501 & 503 Walkway

3
Cable Ladder and Supports installation in level : 36.135 for convoyer 51-29-502
4
Engineering : Follow up with Volt Automation to finalize Dedusting Pending Items
5
IMD For Earthing Busbar and Conduit Clamp.
6

Next Working day

1
Soil Resistivity Internal test to proceed in Earthing work.
2
Engineering: Follow up with Volt Automation to finalize Junction Box Fat Test And Dedusting
3
Painting Conduits Accessories.
4 I&C Cable Ladder Installation.
5

Issues/ Requirements

Staff

Name Daily Working


Hours Over Time Hours
1
Supervisor 8
2
Technician (1) 8
3
helper (2) 8
4

10

11

12

Resp. Engineer: Ahmad Dagamseh