Mathhhhhh
Mathhhhhh
A. 150
B. 140
C. 130
D. 110
Explanation:
(60/100) * X – 40 = 50
6X = 900
X = 150
85% of a number is added to 24, the result is the same number. Find the number?
A. 150
B. 140
C. 130
D. 160
Explanation:
(85/100) * X + 24 = X
3X = 480
X = 160
60% of a number is added to 120, the result is the same number. Find the number?
A. 300
B. 200
C. 400
D. 500
Explanation:
(60/100) * X + 120 = X
2X = 600
X = 300
A. 0.03375
B. 0.3375
C. 3.375
D. 33.75
Explanation:
A. 600
B. 700
C. 800
D. 900
Explanation:
A. 4
B. 6
C. 9
D. 12
Explanation:
(80/100) * 40 – (4/5) * 25
32 – 20 = 12
A. 18
B. 13
C. 15
D. 20
Explanation:
(60/100) * 50 – (40/100) * 30
30 – 12 = 18
After decreasing 24% in the price of an article costs Rs.912. Find the actual cost of an article?
A. 1400
B. 1300
C. 1200
D. 1100
Explanation:
A. 16%
B. 16 1/3 %
C. 16 2/3 %
D. 16 3/5 %
Explanation:
X=100 y=120
120——20
100——-? => 16 2/3%
A. 25%
B. 50%
C. 75%
D. 33%
Explanation:
If 10 workers can make 10 tables in 10 days, then how many days would it take for 5 workers to make 5 tables?
A. 1
B. 5
C. 10
D. 25
10 workers make 10 tables in 10 days. 1 worker makes 1 table in 10 days. Similarly, 5 workers can make 5 tables in
10 days.
If 6 men take 9 days to complete a work, how many men can complete the work in 3 days?
A. 2 men
B. 12 men
C. 9 men
D. 18 men
Today is khadija’s birthday. After one year, she will become two times as she was ten years ago. current age of Khadija?
A. 19
B. 20
C. 21
D. 22
x+1=2x-20
1+20=2x-x
x=21 years
P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2
days. P alone completed the remaining work. The work was finished in__________days.
A. 12
B. 15
C. 22
D. 20
A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the
remaining work in another 20 days. In how many days A alone can finish the work?
A. 70
B. 50
C. 40
D. 60
A is thrice as good as B in work. A is able to finish a job in 60 days less than B. They can finish the work
in___________days if they work together.
A. 18 days
B. 22 ½ days
C. 24 days
D. 26 days
Amount of work A and B can together do in 1 day = 1/90 + 1/30 = 4/90 = 2/45
Two taps X and Y can fill a tank in 10 hrs. and 15 hrs.respectively. If the both taps are opened together, the tank will be
full in_________?
A. 3 hrs.
B. 4 hrs,
C. 5 hrs.
D. 6 hrs.
A, B and C together earn Rs.150 per day while A and C together earn Rs.94 and B and C together earn Rs.76. The daily
earning of C is:__________?
A. 10 Rs,
B. 15 Rs,
C. 20 Rs.
D. 25 Rs.
If 6 men can make 10 sofas in 2 days, then 8 men can make 8 sofas in__________?
A. 1.8 days
B. 1.5 days
C. 1.2 days
D. 1 day
Time is
directly proportional to number of sofas
inversely proportional to number of people No. of days
= (6/8)*(8/10)*2
= 1.2 days
If 3 men or 4 women can construct a wall in 43 days, then the number of days that 7 men and 5 women take to construct
it is :
A. 12 days
B. 14 days
C. 16 days
D. 18 days
if 6 men can make 10 sofas in 2 days, then 8 men can make 8 sofas in__________?
A. 1.8 days
B. 1.5 days
C. 1.2 days
D. 1 day
Time is
directly proportional to number of sofas
inversely proportional to number of people No. of days
= (6/8)*(8/10)*2
= 1.2 days
If 10 workers can make 10 tables in 10 days, then how many days would it take for 5 workers to make 5 tables?
A. 1
B. 5
C. 10
D. 25
10 workers make 10 tables in 10 days. 1 worker makes 1 table in 10 days. Similarly, 5 workers can make 5 tables in
10 days.
If 6 men take 9 days to complete a work, how many men can complete the work in 3 days?
A. 2 men
B. 12 men
C. 9 men
D. 18 men
Assume that 20 cows and 40 goats can be kept for 10 days for Rs.460. If the cost of keeping 5 goats is the same as the cost of
keeping 1 cow, what will be the cost for keeping 50 cows and 30 goats for 12 days?
A. Rs.1104
B. Rs.1000
C. Rs.934
D. Rs.1210
Given that 5g = c
Hence equation (1) can be written as 10c + 4c = 23 => 14c =23
=> c=23/14
cost of keeping 50 cows and 30 goats for 1 day
= 50c + 30g
= 50c + 6c (substituted 5g = c)
= 56 c = 56×23/14
= 92
Cost of keeping 50 cows and 30 goats for 12 days = 12×92 = 1104
P takes twice as much time as Q or thrice as much time as R to finish a piece of work. They can finish the
work in 2 days if work together. How much time will Q take to do the work alone?
A. 7
B. 8
C. 9
D. 6
Let P takes x days to complete the work
Then Q takes x/2 days and R takes x/3 days to finish the work
Amount of work P does in 1 day = 1/x
Amount of work Q does in 1 day = 2/x
Amount of work R does in 1 day = 3/x
Amount of work P,Q and R do in 1 day = 1/x + 2/x + 3/x = 1/x (1 + 2 + 3) = 6/x
6/x = 2
=> x = 12
=> Q takes 12/2 days = 6 days to complete the work
3 men and 7 women can complete a work in 10 days . But 4 men and 6 women need 8 days to complete the same work . In
how many days will 10 women complete the same work?
A. 50
B. 30
C. 40
D. 13
P, Q and R can do a work in 20, 30 and 60 days respectively. How many days does it need to complete the work if P does the
work and he is assisted by Q and R on every third day?
A. 10 days
B. 14 days
C. 15 days
D. 9 days
tank can be filled by a pipe in 20 min. and by another pipe in 60 min. Both the pipes are kept open for 10 min. and then the
first pipe is shut off. After this, the tank will be completely filled in__________?
A. 10 min
B. 20 min
C. 30 min
D. 40 min
A is thrice as good a work man as B and takes 10 days less to do a piece of work than B takes. B can do the work
in:___________?
A. 15 days
B. 14 days
C. 16 days
D. 30 days
15 men can build a 500m long wall in 30 days. In how many days can 30 men build a 1.2 km long wall?
A. 48 days
B. 24 days
C. 40 days
D. 36 days
No. of days is
directly proportional to the length of the wall and
inversely proportional to the number of men No. of days = (1200/500)*(15/30)*30 = 36 days
If 28 men can finish a work in 15 days, 21 men can finish the same work in___________?
A. 24 days
B. 14 days
C. 15 days
D. 20 days
Time and Men are inversely proportional. Time taken by 28 men to finish the work = 15 days Time taken by a man to
finish the work
= 15*28 days Time taken by 21 men = (15*28)/21 = 20 days
C takes 6 days to complete half of a work and D takes 5 days to complete 1/3rd of the same work. They take turns to
complete the task. If C works for the first 4 days, in how many days will D complete the rest of the work without the help of
C?
A. 10 days
B. 12 days
C. 8 days
D. 9 days
Part of work completed by C in 1 day = 1/12 Part of work completed by D in 1 day = 1/15 Part of work completed by C
in 4 days
= 1/3 Work remaining = 2/3 Time taken by D to complete the work
= (2/3)÷(1/15) = 10 days
P,Q and R together earn Rs.1620 in 9 days. P and R can earn Rs.600 in 5 days. Q and R in 7 days can earn Rs.910. How much
amount does R can earn per day?
A. Rs.40
B. Rs.70
C. Rs.90
D. Rs.100
P and Q can complete a work in 20 days and 12 days respectively. P alone started the work and Q joined him after 4 days till
the completion of the work. How long did the work last?
A. 5 days
B. 10 days
C. 15 days
D. 12 days
P can finish a work in 18 days. Q can finish the same work in 15 days. Q worked for 10 days and left the job. how many days
does P alone need to finish the remaining work?
A. 8
B. 6
C. 4
D. 2
P can lay railway track between two stations in 16 days. Q can do the same job in 12 days. With the help of R, they completes
the job in 4 days. How much days does it take for R alone to complete the work?
A. 9(3/5) days
B. 9(1/5) days
C. 9(2/5) days
D. 10 days
wo pipes X and Y fill a tank in 15 hrs. and 20 hrs. respectively, while a third pipe ‘Z’ can empty the full tank in 25 hrs. All the
three pipes are opened in the beginning. After 10 hrs. Z is closed. In how much time, will the tank be full ?
A. 12 hrs
B. 14 hrs
C. 16 hrs
D. 18 hrs
Explanation:
Part filled in 10 hrs.
= 10[1/15+1/20−1/25]=23/30
8 men can dig a pit in 20 days. If a man works half as much again as a boy, then 4 men and 9 boys can dig a similar pit
in:__________?
A. 12 days
B. 16 days
C. 18 days
D. 20 days
Eficiency of Rashid and Danish are in the ratio 5:8. If Danish takes 51 days less than Rashid to complete the work, find the
time taken by Rashid to complete the work.
A. 85 days
B. 126 days
C. 118 days
D. 136 days
Time taken is inversely proportional to their efficiency. So, time taken is in the ratio 8:5. Time taken by Rashid to
finish the work = 8x Time taken by Danish to finish the work = 5x 8x-5x=51 3x=51 x=17 8x=136
If 12 men work 8 hours a day to complete a work in 10 days, how many men working 12 hours a day
can complete the work in 5 days?
A. 16
B. 4
C. 12
D. 8
12 men work 8 hours for 10 days x men work 12 hours for 5 days x = (12*8*10)/(12*5) = 16 men
If daily wages of a man is double to that of a woman, how many men should work for 25 days to earn
Rs.14400? Given that wages for 40 women for 30 days are Rs.21600.
A. 15
B. 14
C. 16
D. 13
Mansoor-Ul-Haque and Aaqib are working on a special assignment. Mansoor-Ul-Haque needs 6 hours
to type 32 pages on a computer and Aaqib needs 5 hours to type 40 pages. If both of them work
together on two different computers, how much time is needed to type an assignment of 110 pages?
P is able to do a piece of work in 15 days and Q can do the same work in 20 days. If they can work
together for 4 days, what is the fraction of work left?
A. 8/15
B. 7/15
C. 11/15
D. 2/11
A. 30 min
B. 35 min
C. 40 min
D. 45 min
A and B can together do a piece of work in 15 days. B alone can do it in 20 days. In how many days can
A alone do it ?
A. 40 days
B. 50 days
C. 60 days
D. 70 days
Farjan and Kashif can complete a task in 30 days. Farjan leaves after 20 days and Kashif alone
completes it in another 25 days. How many days does Farjan alone take to complete the entire task?
A. 50
B. 75
C. 60
D. 45
Jameel can complete a task in 15 hours and Nasir can complete the same task in 12 hours. Jameel
starts the task at 9:00 am and stops working at 2:00pm. Nasir starts working on the task at 4:00 pm.
At what time is the task completed?
A. 12:00 pm
B. 2:00 am
C. 12:00 am
D. 10:00 pm
Jameel works for 5 hours. So he completes 5/15 = 1/3 of the task Nasir has to complete
2/3rd of the task 12*2/3 = 8 hours are needed. He completes the task at 12:00 am.