MSC Power Transformers - Lecture Material
MSC Power Transformers - Lecture Material
Newcastle
tl UUniversity
i it
MSc Power Distribution Engineering
EEE8054 - Transformers
P f
Professor Dennis
D i J All
Allan FREng
FRE
Th first
The fi t transformer
t f - GANZ - 1886
Three-phase
Three phase core-type
core type transformer
Three-phase shell-type transformer
Core form transformer Shell form transformer
circular leg section rectangular leg section
Basic transformer equations:
Voltage across a winding is given by
E = 4.44 x f x Φ x n
where f is frequency, Φ is total flux
n is number off turns
E/n = 4.44 x f x Φ
= 4.44 x f x B x A
where B is flux density
A is core area
Basic transformer equations:
Ve-f = E f-e = V2
I0 Flux
E d-a = V b-c = V1 If-e = I2
Ve-f = E f-e = V2
I’b-c = n2/n1.I2
Ib-c = I1
Load phase
angle
I0 Flux
I1X1
V1
I1R1
Vb-c I2
I2X2
Ve-f I2R2
V2
I’ I1
Load
phase
g
angle
I0
Flux
Simplified equivalent circuit
2000 MVA
1000
MVA
1150kV
100 1000kV
MVA
10
100kV
MVA
25kV
1
10kV
MVA
150kVA
100 1kV
kVA
1880 1900 1920 1940 1960 1980 2000
R t off development
Rate d l t off transformers
t f
LOSS EVALUATION
Magnetic circuits
P f
Professor Dennis
D i J All
Allan FREng
FRE
Soft Iron Wire
4w/kg
3 /k
3w/kg Iron Sheets
D
Development
l t off low-loss
l l steels
t l
Power loss characteristics of transformer steels
Manufacture
f off
amorphous
strip
i on a
cooled wheel
using
i rapid-
id
cooling
t h l
technology
Construction of single phase transformer with
amorphous metal strip- wound core
Three-phase
p transformer constructed from
amorphous metal strip-wound core
3-phase
p amorphous
p transformer
with laminated strip
Mandrel of Georg cut
cut-to-length
to length line
A Georg cut-to-length line with slit-to-width steel coils
D W Y
Main p
parameters of core
Cruciform core section
Yoke Yoke
Leg Leg
C
Core corner configurations
fi ti
The effect of rolling
direction on power
loss in a transformer
lamination
Core building berth for distribution transformers
Core building berth for small distribution transformers
Th
Three limb
li b core for
f small
ll power distribution
di t ib ti transformer
t f
Core building for 3-phase distribution transformer
Three limbed
core of small
power distribution
transformer
Types of construction of transformer cores
Core configurations
Core configurations
Core configurations
Core building for a single phase transformer
Core building: a 9-leg treble tripler
St l
Step-lapped
d core joint
j i t att top
t off leg
l
Step-lapped core joint
Mitred core with step
step-lapped
lapped joint
C
Core on b
building
ildi berth
b th ready
d to
t be
b lifted
lift d upright
i ht
Typical
yp three-phase
p core-type
yp transformer
of medium power range
Core for 132 kV, 40 MVA transformer
4-leg core for a single-phase generator transformer
5-leg core for a three-phase generator transformer
B-H loop for coresteel
Effect on magnetising current of switching in
at positive voltage peak
Effect on magnetising current of switching in
at voltage zero.
zero
Effect on magnetising current on switching in at
voltage zero with remnant flux in the core
N
Newcastle
tl UUniversity
i it
MSc Power Distribution Engineering
EEE8054 - Transformers
Windings
P f
Professor Dennis
D i J All
Allan FREng
FRE
Copper-foil winding
Foil windings for distribution transformers
Alternative forms of windings in common use
Front-to-front, Back to front
back-to-back
alternate coils reversed
Turns 7-12
7 12 Turns 7
7-12
12 collapsed Turns 7-12
7 12
loosely wound rearranged
200 2.0
er unit)
Weightt (Tonnes)
Costs (pe
150 15
1.5
100 1.0
elative C
Conventional
50 Re 0.5 HTSC1
HTSC2
0 0
40 80 120 160 200 40 80 120 160 200
Rating (MVA) Rating (MVA)
DA-0013
Progressive Reduction of Losses
for a 200 MVA 220 kV Transformer
180 700
140 600
100 500
60 400
20 300
1950 1960 1970 1980 1990 1950 1960 1970 1980 1990
Conceptual view of a
hi h temperature
high t t
superconducting
transformer cooled
using liquid nitrogen
N
Newcastle
tl UUniversity
i it
MSc Power Distribution Engineering
EEE8054 - Transformers
Winding connections
P f
Professor Dennis
D i J All
Allan FREng
FRE
STAR (Y) connection of windings
Advantages
g of Star (Y)
( ) connection:
I0
I0
I0
3I0
I0
I0
3I0
I2
Neutral point
p
• L
Lower voltages
lt to
t earth
th
• Lower cost of tapchanger
Constant LV turns Constant HV turns Variable HV turns
Constant flux Variable LV turns Variable LV turns
LV1
LV1
Core
HV limb HV
LV2
LV2
LV2
Bottom yoke
Transformer construction
P f
Professor Dennis
D i J All
Allan FREng
FRE
Three limb cores ready for coil mounting
Assembling winding onto core of distribution transformer
Mounting windings on a core
F il LV windings
Foil i di assembled
bl d on the
th core
A
Assembly
bl off small
ll power distribution
di t ib ti transformers
t f
HV and
d LV windings
i di assembled
bl d onto
t three
th limb
li b cores
Windings with foil LVs mounted on a core
Inserting top yoke of core after winding assembly
Tank cover mounted small distribution transformer
Internal view
of 2000kVA
distribution
transformer
A typical three-phase
three phase
distribution transformer
with enamel covered
round wire on HV winding
and foil wound LV windings
Assembly of windings on a core
St l
Step-lapped
d core joint
j i t att top
t off leg
l
N ti windings
Nesting i di before
b f mounting
ti on to
t core
3-leg generator transformer
3-leg autotransformer: 1000 MVA at 400 kV
5 leg autotransformer: 1000 MVA at 400 kV
5-leg
5-leg generator transformer: 600 MVA at 400 kV
736 MVA generator transformer with in-tank LTC
5-leg generator transformer: 716 MVA at 525 kV
Lowering a treble-tripler
treble tripler transformer in to the tank
Effectt off water
Eff t content
t t on dielectric
di l t i
strength of transformer oil
Effect of water on the dielectric strength of
cellulose paper
Effect of water content on discharge
inception stress of cellulose paper
Rate of aging
Increase of aging
g g rate with water content of p
paper
p
S
Schematic off vapour phase drying plant
Control board for vapour phase drying system
A 500 kV oil-impregnated
p g
paper bushing for a power
transformer
Drying and filtering the
oil in a transformer
during the oil-circulation
process after oil-filling
p g
Measuring the electric strength of oil samples
Moving a 1000 MVA autotransformer by road
‘Schnabel’
Schnabel type car for transportation by railroad
Tank mounted radiators
Pattern of leakage flux paths in a transformer
Computer model of a 3-limbed core (laminations only)
C
Computer
t model
d l off a 3-limbed
3 li b d core with
ith yoke
k clamps
l
C
Computer
t model
d l off a 3-limbed
3 li b d core with
ith LV windings
i di
Computer model of a 3
3-limbed
limbed core with LV and HV windings
Loss distribution in core clamps due to leakage flux
from windings
Computer model of a 3-limbed core with windings in place
and fitted with horizontal flux shunts at winding ends
to control leakage flux
Loss distribution in core yoke clamps when
magnetic shunts are fitted
Computer model of a 3
3-limbed
limbed core with windings fitted
with magnetic shunts and conducting shields
Loss distribution in tank due to leakage flux with
no shunts or shields fitted
Loss distribution in tank due to leakage flux when
magnetic shunts and conducting shields are fitted
Fl shunts
Flux h t
U off magnetic
Use ti shunts
h t tto control
t l stray
t lloss in
i steelwork
t l k
Shadow bars used to control magnetic field of LV leads
Active p
parts of a 234 MVA HVDC converter transformer
rated at 400 kV AC and 215 kV DC (HV-lead side)
Active p
parts of a 234 MVA HVDC converter transformer
rated at 400 kV AC and 215 kV DC (DC-lead side)
HVDC converter transformer in test: 400 kV ac
ac,
star and delta dc circuit windings
200 MVA, 400 kV quadrature booster, series unit
Testing a 2000 MVA,
400 kV quadrature
q
booster with series
and shunt units
connected
t d together
t th
N
Newcastle
tl UUniversity
i it
MSc Power Distribution Engineering
EEE8054 - Transformers
Transformer testing
P f
Professor Dennis
D i J All
Allan FREng
FRE
TESTING OF TRANSFORMERS
Routine tests:
• winding resistance
• winding ratio and phase displacement
• load loss and short circuit impedance
• no-load
no load loss and magnetising current
• dielectric tests
• tests on OLTC
TESTING OF TRANSFORMERS
Type tests:
Special
p tests:
• zero-sequence impedance
Transient voltage
%
distribution along a winding
Transient distribution of voltage along a winding
Transient voltage distribution in windings
Electrostatic shield Interleaving Inter-shielding
Performance in service
P f
Professor Dennis
D i J All
Allan FREng
FRE
PARALLEL OPERATIONS OF TRANSFORMERS
It is possible to parallel
transformers with different
clock hour numbers by
reversing or permutating
connections
Another transformer fire
Burnt out carcase 24 hours after fire
For a fire or explosion to
occur there must be:
22
0 0 10 20 30 40 50
Time in ms
Effect of rate of rise of tank pressure
Mitigating actions to reduce risk of fire:
M
More power even under
d low
l wind
i d conditions
diti d
due tto d
decoupling
li byb DC
New Windgenerator based on Powerformer Technology
Conventional
Gearbox Generator Transformer
Permanent Magnets
- higher efficiency
- less parts
- simple for low-speed
Cable Stator
- Less Corrosion
Windformer Generator - High Voltage output
Results:
- No gearbox
- No transformer
- Less maintenance
- Easy conversion to DC
- Much higher power output
due to new Windformer system
Increase of aging
g g rate with water content of p
paper
p
Drycol refrigerated breather
The Drycol refrigerated breather
Molecular sieve
filtration device for
on-site
i d drying
i off
transformers
Molecular sieve oil
di
driers on a 400kV
transformer
400kV transformer
protected by rubber
bag a
andd ssilica
ca ge
gel
breather
N
Newcastle
tl UUniversity
i it
MSc Power Distribution Engineering
EEE8054 - Transformers
Transformer failures
and protection
P f
Professor Dennis
D i J All
Allan FREng
FRE
Failure of layer-winding due to circulating currents
• Average annual failure rate of all
transformers in service is 2%
• M
Mean time
ti to
t failure
f il is
i 50 years
• Half of all transformers fail within
50 years
y
• Typical life of a generator
transformer is 18-24 years
• Typical life of a transmission
transformer is 40-60 years
35
30
25
20
15 %
10
5
0
Design
g Manufacture Material Operations
Assigned
g causes of transformer failures (CIGRE)
( )
30
25
20
15
%
10
5
0
Windings Core Terminals OLTC Other
• reduced
d d loss
l with
ith new materials
t i l
• lower maintenance costs
• high cost of replacing obsolete parts
Failure modes - technical end
end-of-life
of life:
• Leakage
L k fl
flux andd circulating
i l i currents
• Inadequate shielding for electrostatic or
electromagnetic conditions
• Complications
p introduced to ‘simplify’
p y
the design
Local requirements
Company specifications
International standards
• IInsulation
l ti – PD/streamers/tracking
PD/ t /t ki
• Electrical – Open/short circuit, poor contacts,
earthing
thi connections
ti
• Thermal – Overheating, hotspot heating
• Ch i l – Contamination
Chemical C t i ti
• Mechanical – Bending, fracture, vibration,
l
loose jjoints
i t
Actions to improve service performance:
• Turn-to-turn
Turn to turn
• Phase-to-earth
• Phase-to-earth
• C
Core llaminations
i ti
• Core bolts
• Cooler fans and pumps
In-tank faults:
• Oil temperature
• Oil pressure
p
• Gas formation
Transformer protection devices:
• Buchholz relay
• Oil pressure/surge relay
• Gas collection
• L
Low oil
il level
l l
N
Newcastle
tl UUniversity
i it
MSc Power Distribution Engineering
EEE8054 - Transformers
Surveillance and
monitoringg
P f
Professor Dennis
D i J All
Allan FREng
FRE
Aims of transformer surveillance:
• predictive maintenance
p
• life extension
• refurbishment
• replacement strategy
Drivers to install surveillance equipment:
300
SP02: 158.9¡æ
100
100.0¡æ
Tank hotspot
p due to magnetic
g flux
Transformer surveillance:
on-line measurements:
Moisture
Breakdown
2-furfural
Material Condition Gases Symbol
Source of ‘key
key gases’
gases in DGA samples
DGA gas ratios
Duval triangle for DGA analysis
Gases Generated During Breakdown
of Dielectric Oil (Gibeault / Hall / Noirhomme))
HYDROGEN H2
NTS
TITUEN
METHANE CH4
CONST
ETHANE C2 H6
GAS C
ETHYLENE C2 H4
G
ACETYLENE C2 H2
CARBON MONOXIDE CO
TITUEN
CONST
GAS C
• dispersion (RVM)
• leakage inductance
• low frequency
q y impulse
p
• frequency response analysis (FRA)
• F
Fourier
i analysis
l i
• dielectric loss angle
Transformer surveillance:
off-line measurement:
• dispersion (RVM)
• leakage inductance
• low frequency
q y impulse
p
• frequency response analysis (FRA)
• F
Fourier
i analysis
l i
• dielectric loss angle
Special
Spec a transformer
t a s o e tests
FRA measurement
using FRAMIT to
check for transformer
winding displacement
Recovery Voltage
Measurement of
moisture in transformer
solid insulation
Continuous PD monitoring
g
PD signals acquired
at cable earth bonds
using split-core
HFCTs
Transformer surveillance:
intrusive measurement:
• simple
i l
• low cost
• easily maintained
• eliminate the need for experts
Quality of data must be focused on results to:
• preventt problems
bl from
f developing
d l i
• define the severity of any problem
• provide information to take action
• provide on-line
on line and off
off-line
line diagnostics
• enable ‘trending’ of data
• avoid intrusive maintenance
Transformer condition monitoring:
external sensors:
• t
temperature
t (t
(tank
k and
d OLTC)
• partial discharge (electrical and acoustic)
• vibration
• current (loading and fault levels)
• loading (life history)
• voltage (system transients)
• on-line dissolved gas analysis
Transformer condition monitoring:
external
t l sensors:
• t
temperature
t (t
(tank
k and
d OLTC)
• partial discharge (electrical and acoustic)
• vibration
• current (loading and fault levels)
• loading (life history)
• voltage (system transients)
• on-line dissolved gas analysis
The HYDRAN® p
principle
p
MEMBRANE
+V _ SIGNAL
H2
CELL
CO
O2
H2
CO
Case 1: 735/230 kV 370MVA transformer
300
Shut
S ut
250 Load
H2) Equiivalent (PPM)
down
reduced
200 Alarm 1
Phase C
150
Hydran reading
100
Phase A Alarm 2
(H
50
Phase B
0
2/19/91 3/1/91 3/11/91 3/21/91 3/31/91 4/10/91 4/20/91
Load Current
Top Oil Temperature
Fans
Pump
Moisture
HYDRAN®
OLTC
FARADAY TNU DGA Results Display
Transformer Nursing Unit
Duval interpretation
and diagnostic method