Project Execution Plan
Project Execution Plan
PROJECT EXECUTION
PLAN
1. OBJECTIVES
A PEP should reflect as much as possible the generally accepted Project Management Best
Practices – see for instance the PMP® handbook.
The PEP is the primary document which defines how the project will be undertaken. It is a
companion document to the Field Development Plan (FDP), which defines what the
COMPANY are trying to achieve.
The PEP details the specific activities, resources and organization to be applied,
demonstrates how the project’s quality and HSE requirements will be achieved, and how the
project objectives will be met by the proposed method of execution.
The PEP represents a key deliverable for the Project’s Sanction Gate.
A PEP is structured to include a number of formal, stand-alone plans for particular areas of
project process, e.g. HSE Management Plan, Quality Plan, Value Management Plan etc..
The typical PEP contents listing are provided in the Annex and include references to such
plans and a proposal for a list of their contents. It is expected that the PEP will provide
simple reference to these formal plans by document number, and that (other than perhaps a
philosophical overview) details of the plans will not be repeated within the body of the PEP.
The latest revision of these individual plans will therefore always be applicable.
The PEP will therefore act as a guidebook to how the project will be managed, providing the
necessary signposts towards other associated documents. The PEP need not itself be a
large document.
The plan for a particular project process may have to be tailored to the phase or to the
project element (e.g. the quality plan for onshore activities may differ in specific details from
the quality plan for offshore activities). Care must therefore be taken to ensure that there is
conformity and lack of conflict between PEPs for sub-projects and sub-elemental areas of a
project. The high level, over-arching PEP for the complete project should be the governing
document and always take precedence.
3. MAIN CHARACTERISTICS AND ACTIVITIES
• Consistency and compliance with the others key project documents (e.g. the Field
Development Plan)
• Multidisciplinary (compiled from stand-alone plans and procedures covering a broad range
of project disciplines)
• Use –10% +15% accuracy on cost and schedule estimates (ideally based on at least 80%
in value from tender responses)
• High level perspective
The PEP is where the strategy for implementing the Execution phase is laid out. The PEP
therefore sets the project management framework and an overall direction for the Project
that has been understood and bought in to both by the Project Team and COMPANY’s
senior Management, as well as by Project stakeholders.
Additionally, at a high level, the PEP provides the reasons for the strategies adopted,
explaining how alternatives have been challenged and how the available resources are to be
optimised to meet project objectives.
Normally, the PEP will cover all activities performed during the Execution Phase of the
project under the management of the Project Team. This typically includes:
Activities which are not normally within the scope of the PEP include:
The PEP is usually approved and owned by the relevant Project Manager and he/she should
approve all document revisions.On all projects there should be a formal document control
mechanism in place and the PEP should be managed as a ‘controlled’ document. The PEP,
together with its referenced standalone plans, should be made available to all project
stakeholders.
The PEP is the highest level project execution document, and is effectively an ‘umbrella’ for
all the individual project plans, procedures, work instructions, or eventually sub-project
PEPs.
It represents the ultimate source of guidance to the project team and should be the starting
point when developing detailed project documentation. The PEP should specifically
reference the relevant lower level documentation such as the individual project plans and
Procedures.
The PEP is also an essential element of the Project HSE Management System and Project
Quality System in that it specifies how these systems will be developed and applied to the
project.
4. TYPICAL PEP TABLE OF CONTENTS
SECTION 3. ORGANISATION
3.1 OWNERSHIP AND CONTRACTUAL OBLIGATIONS
3.2 PROJECT ORGANISATION
3.3 COMPANY AND PROJECT INTERNAL INTERFACES
• The objectives of the PEP: Why we need the document, and the value it adds
• Document ownership
o Who approves the PEP
o Who maintains it
• Location
• Overview of reservoir (STOIIP, Geological description, etc.)
• Development Strategy: Overview of well patterns. Overview description of facilities’,
Phasing of development activities
• Project scope boundaries (battery limits)
• Brief explanation of execution strategy only, demonstrating how and why the
proposed execution strategy and plan will best meet the objectives of the project
• Major risks to project success, plus control mechanisms (i.e. how the execution
strategy controls/mitigates these risks)
• Major outstanding decisions (and timing for these to be made)
• Resources summary (number of work locations, numbers of personnel at each
location, available assets and infrastructures, etc.)
• Ownership structure
• Contractual obligations (PSA and JOA)
• Role of the National Authorities
• Governance Structure: Committees and Sub-Committees, together with their roles
and responsibilities
Brief definition, categorisation and description of COMPANY and project internal interfaces,
highlighting those that are particularly critical for the success of the Execution phase – i.e.,
interface with the Operations team.
SECTION 4. MANAGEMENT SYSTEMS, STRATEGIES, PLANS AND PROCEDURES
The PEP should reference among others, the following Management Systems:
• HSE Management System
• Quality Management System
• Procurement Management System
• Operations Management System
• Information Management System
4.2 HSE
Reference should be made to COMPANY HSE Management System. This should describe
the approach taken to manage the HSE aspects of the business to ensure that COMPANY’s
activities are planned, carried out, controlled, and directed so that the HSE objectives are
met.
The HSE strategy should be designed in order to achieve continuous HSE performance
improvement, and to demonstrate that HSE related risks are managed to a level which is as
low as reasonably practicable (ALARP).
The above should also include references to HSE Standards and Guidelines.
The Project HSE Management System should reflect the requirements of the COMPANY
HSE Management System, but where necessary should be tailored to include project
specific requirements.
For smaller projects, a project-specific HSE Management System could not be required. The
Project HSE Management System will include the Project HAZID and Risk Registers.
• Provide a statement of the Project HSE objectives and performance and how they will be
achieved over life of the Project
• Describe Project-specific HSE objectives and targets
• Describe the specific HSE management activities to achieve planned objectives, including
responsibilities and competency assurance
• Describe the contingency and emergency response planning
• Describe special HSE initiatives and programmes
• Describe how Contractors’ HSE management performance will be evaluated prior to
selection and during the execution of the work
The Project HSE Plans should build on the deliverables and standards that are required to
be met by COMPANY, its contractors and their sub-contractors throughout the execution of
the Project.
The Project HSE Plan requires for a Document Management Procedure between the
Contractors and COMPANY to be developed and maintained. This should clearly define the
interface between the various HSE Management Systems, identifying key roles and
responsibilities for each activity defined and its associated tasks, standards and procedures
etc.
Contractors will be required to prepare appropriate HSE plans that ensure that the
requirements set out in the contract and the overall Project HSE Plan are met. Where this is
not possible, suitable interface documentation shall be developed and referred to.
This section should contain the ntegrated Project HSE Audit and Review Schedule,
comprising:
4.4 QUALITY
The COMPANY Quality Management Systems and Procedures shall be referenced. These
normally draw upon the requirements of the ISO 9001:2000 standards, and support the
development process.
The Project Quality Plan should be referenced, which will apply to all activities undertaken by
the Project Team and will comply with COMPANY Quality Systems and Procedures. It will
form the top-level Project document that will be used to cascade the requirements for quality
management throughout the Project (i.e. it will set the frame in which Contractors’ quality
management systems will operate).
Where appropriate, reference should be made to the appropriate terms within the contracts
relative to quality.
The Project Quality Plan will restate the Corporate quality policy and objectives in the
specific context of Project requirements.
The Project Quality Plan will:
• identify the processes and the application of the processes needed to realise the
project goals in accordance with the quality policy and objectives
• indicate the sequence and interaction of the processes
• define how these processes are operated and controlled
• identify the resources required to implement the processes
• identify the primary accountabilities and responsibilities
• monitor, measure and analyse the processes
• define the processes of continuous improvement will be implemented, including
monitoring, measurement, analysis and improvement processes and receipt of
customer feedback
• demonstrate management buy-in and commitment
The Project Quality Plan shall define how the above points will be applied in all the areas of
the project.
4.5 INTERFACES
The Interface Management Plan describes how the internal interfaces identified within the
Project Interface Register (also referenced in the PEP) are going to be managed.
The plan should identify and categorise (critical) internal interfaces, and describe how these
will be managed throughout the execution phase and by whom. It typically describes:
A broad overview of the regulatory requirements related to permits and consents shall be
provided in this section. Major outstanding issues and status of the permitting process are
here described in general terms (together with Key dates for getting the necessary
approvals).
Within this section different plans may be referenced within the umbrella of an overall
permits and consents plan (e.g. compensation plan, land allocation plan, consultation plan,
certification plan, etc.).
Project specific procedures should be referenced in this section.
4.7 VALUE
The Value Management Strategy, which is a top level document that explains the value
management approach to be exercised within the Project and provides references to other
more detailed guidelines and tools, should be referenced.
The strategy will demonstrate compliance with COMPANY Value Management Systems and
Plans.
For the above areas the Project Value Management Strategy should address:
• the key project value drivers
• specific areas to be a focus for value improvement
• targets for value improvement
• methodology for achieving the targets
• how value gains are to be measured, tracked and reported
• education of the project team in value management techniques and processes
• critical success factors and how these are to be addressed
• the value assurance process to be adopted
The Value Improvement Plan should contain a schedule of those activities such Value
Improving Practices, Value Assurance Reviews, Peer Assists, Peer Reviews, key decisions
requiring application of formal decision making processes and tools, lessons learned
workshops, risk management activities and initiatives. It should identify the resources
required to carry out the activities and the responsibilities of all the parties involved.
4.8 RISK MANAGEMENT
The Project Team has to demonstrate that all risks have been fully identified, understood,
and that a plan has been defined for their management.
Reference should be made to the COMPANY Risk Management Procedures, to the project
specific procedures and to the risk register and the risk management plan
• Identified risks
• Define procedure for Risk categorization, impact area, level, manageability and
priority
The Information Communication Technology (ICT) plan provides a framework for the IT
systems required to support the overall Project life-cycle. The plan should identify:
The ICT Plan should state the life-cycle stages that are supported by the technology
platform(s) in terms of:
• Cost and Schedule Management
• Management Information Reporting
• Materials Management (logistics tracking and expediting of bulks and materials)
• Construction Management (warehouse management, construction planning,
allocation of resources)
• Plant Management
• Commissioning Management (completion management, plant and equipment data
management)
• Health and Safety System Management (tracking of HSE policies)
• Permits, Consents and Approvals Management (database of permitting status,
contracts approved, customs cleared, accepted by warehouse etc.)
• Value and Quality Management
Within each lifecycle stage, the supporting work flows and business process should be
developed to confirm the requirements of the discipline owners.
On the latter point, the interface with Operations is key and should include:
• A strategy for project execution and operation migration
• Identification of Project Technology components that will transfer into Operations (i.e.
EDMS)
• Definition of all deliverables and information structure required for migration to
operations
Define the objectives of the reporting system and the project monitoring criteria, for example:
Describe all type of reports to be produced, including typical content, scope of the report,
frequency of issue.
Describe the project monitoring and reporting system, including how the contractors’ reports
are rolled up into the higher level project reports, and demonstrate how the reporting system
will meet the above objectives. Include information on:
A description of how the Project intends to identify, capture and transfer lessons learned
originating within and outside the COMPANY.
4.10 PROJECT CHANGE MANAGEMENT
• Categories of change and degree of effect on project objectives (e.g. cost and
schedule objectives, etc.):
- Project Change (e.g. emanating from PSA/JOA terms and conditions)
- Design basis change
- Design change
- Scope change
- Regulatory change
• Dependent upon category of change, process and authority level for managing
change
- Description of the appointed Project Change Control Board
- Definition of the levels of project baseline for modification approval
- Reference to variation proposals/orders, company instructions, work
orders and procedures
• COMPANY and contractor methods, systems and procedures for cost management
• Development of Cost Estimates, including explanation of levels of accuracy
• Cost estimate report
• Development of Control Budget
• Cost Budget
• Authorisation for Expenditure (AFE) / Cash Call management
• Requirements for cost collecting and reporting relative to frequency, content and
distribution
• Allocation of responsibilities for cost estimating, reporting and control between
COMPANY and Contractors
- Cost reporting
- Earned value analysis
- Commitments and forecasting
- Cash calls
- Trend control
- Cashflow management
- Feedback of cost data (continuous improvement)
4.11.3 ACCOUNTING
• Reference the Contracting Strategy document, Contracts & Procurement Plan and/or
other detailed procedures.
• Materials Management Plan, which should describe how the Project will manage the
following phases of the Material Management Process:
- Specification of required materials
- Support to purchasing of materials and equipment
- Materials identification unique numbering system
- Inspection, testing, expediting of the produced materials
- Transportation of materials to their destination
- Handling, installation and storage of materials on site
- Provision of materials for operations and maintenance
• Design standards
- COMPANY minimum standards
- Local standards and practices
- Generally Accepted industry standards and practices
- Contractor standards and practices
• Scope of work split between Construction (i.e. mechanical completion and pre-
commissioning) and Commissioning and Start-up.
• Allocation of responsibilities between COMPANY and contractors during
commissioning and start-up operations (including hand-over to Operations)
• Integration of timing, activities and requirements into the overall project plan to
achieve “start-up driven scheduling”
• Co-ordination of planning between team, construction team and Operations
• Special start-up requirements to be reflected in project design or plans
- Unusual need for operator training
- New process or controls technology
- Hazardous materials
- Difficult or complex interface with Operations
- Effluent monitoring and mitigation related to start-up
- HSE issues associated with facility start up sequence
4.19 DECOMMISSIONING
4.20 INSURANCE
Description of how the project is going to transfer risk on third parties along the upcoming
project phases.