0% found this document useful (0 votes)
268 views

Task Description PC Comm. Electrical

The document provides a checklist of tasks to commission electrical, instrumentation, piping, and other equipment. It involves checking equipment and installation quality, performing tests like insulation resistance and pressure tests, calibrating instruments, checking motors and controls, filling systems, and conducting operational tests. The contractor is responsible for performing these tasks to verify proper installation and operation prior to system startup.

Uploaded by

Midha Neer
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
268 views

Task Description PC Comm. Electrical

The document provides a checklist of tasks to commission electrical, instrumentation, piping, and other equipment. It involves checking equipment and installation quality, performing tests like insulation resistance and pressure tests, calibrating instruments, checking motors and controls, filling systems, and conducting operational tests. The contractor is responsible for performing these tasks to verify proper installation and operation prior to system startup.

Uploaded by

Midha Neer
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

Task description PC Comm.

Electrical

Check condition of equipment, quality of installation, and compliance with Project X


drawings, manufacturer’s instructions, safety rules, specifications and good practice
Perform preliminary tests with equipment de-energized, including: X
• Insulation resistance measurements
• Di-electric strength tests
• Loops and circuits continuity tests
• Earthing resistance measurements

Fill in transformers with oil and carry out breakdown test of oil samples X
Control earthing network X
Fill in batteries with electrolyte X
Check installation of emergency and instrument power systems X
Check installation of electrical heat tracing X
Modify connections if wrong direction of rotation X
Check direction of rotation of electrical motors (with assistance of the main contractor if X
required)
Energize and test control power system X
Perform all functional tests, including: X
• Adjustment and testing of protective devices
• Check-out and adjustment of electrical instruments
• Operation of safety devices

Energize and test emergency and instrument power systems X


Start up and test power plant X
Carry out preliminary load test (when possible) X
Energize sub stations after completion of all tests X
Carry out batteries discharge tests X
Test battery chargers, inverters, UPS X
Perform motors four hours no load runs. Test motors ancillary equipment X
Check temperature rise of motors, bearings, transformers, relays, when loaded (if X
possible), vibration
Check operation of manual and auto controls X
Check Essential, Normal and Emergency circuits lighting and intensities X
Energize installation of electrical heat tracing X
Carry out functional test on thyristor controlled heater X
Conduct Operational Tests X
Instrumentation

Check condition of equipment, quality of installation, and compliance with Project X


drawings, MANUFACTURERS instructions, safety rules, specifications and good
practice
Remove all fragile devices before hydro tests X
Perform required pressure tests on: X
• Instrument take-off piping
• Air piping
• Air tubing

Reinstall all fragile devices after pressure tests and flushing of the process lines X
Calibrate all instruments other than F&G detectors prior to installation X
Check continuity of transmission and identification of indication, control and alarm X
Task description PC Comm.

signals
• Perform continuity and insulation tests for instrument cables
• Perform continuity and tightness tests for pneumatic tubing

Install sealing fluids where required X


Calibrate / operate all control valves, on/off valves, lubricate as required X
Install all safety devices e.g. pressure relieve valve after testing X
Check and adjust all safety devices and seals where necessary, with Vendor if required X
Check instrument accessibility for removal, maintenance, routine field adjustment X
Calibrate all F&G detectors, synchronize with F&G panel X
Test marshalling relay boxes, programmable logic controllers, sequential operators and X
all numeric control systems
Carry out loop testing X
Test shutdown systems, interlocks, and sequencers + alarms X
Conduct Operational Tests X
Piping

Check condition of equipment, quality of installation, and compliance with Project X


drawings, manufacturer’s instructions, safety rules, specifications and good practice.
Check condition and quality of installation of gaskets and bolts types X
Install and check spring hangers, pipe anchors and guides X
Alleviate any excess piping stresses that may be imposed on pipes, compressors or X
pump flanges
Install safety valves or temporary spool pieces during construction X
Remove all temporary supports, protections, bracings, sea fastening stops, that were X
installed to prevent equipment damage during shipping, storage and erection
Check packing and packing materials and lubrication of valves; repack and lubricate if X
necessary
Carry-out passing test of all critical valves before installation X
Remove all critical valves prior to hydro test and flushing activities X
Carry out integrity test (hydro test) of piping X
Carry out piping water or air flushing operations X
Perform chemical cleaning where applicable X
Set or check pipe anchors, guides, spring hangers and supports after hydro test. X
Provide cold and hot setting data
Clean strainers after flushing X
Witness flushing and cleaning X
Carry out Gross Air Leak Test (GALT) X
Provide and install all strainers, both temporary and permanent, spectacle blinds and X
temporary blanks required for start-up
Supply and install line identification tags and signs, stencil lines for identification X
Test, set, and tag all safety valves, then carry out safety valves final installation X
Remove as necessary and transport all safety valves to and from test facilities X
Supply car seals or locking devices for block valves and safety equipment X
Provide list and location of all blinds installed X X
Check and record position of all car sealed valves X
Install car seals or locking devices on block valves and safety equipment X
Carry-out passing test of critical valves during leak testing X
Fill in hydraulic unit and network with appropriate oil X
Perform drying-out where applicable X
Carry out Tightness test (HP leak testing) X
Carry out inerting X
Task description PC Comm.

Define, temporary blanks required for start-up X


Install corrosion probes X
Check steam tracing for tightness and continuity X
Carry out oil and gas-in under control of Company X
Buildings and structures

Check condition of equipment, quality of installation, and compliance with Project X


drawings, MANUFACTURERS instructions, safety rules, specifications and good
practice
Obtain certificate for occupancy and use, if required X
Conduct Operational Tests as applicable X
Air fin coolers

Check condition of equipment, quality of installation, and compliance with Project X


drawings, manufacturer instructions, safety rules, specifications and good practice
Clean inside of the hood and remove all extraneous particles around the air fin cooler X
Set and align fan and driver if applicable. Set V belts, and fan blades pitch. Check fan X
ring clearance
Check satisfactory operation of louvers and variable pitch assembly X
Startup fans and check vibrations, motor loading, and proper operation of auto-variable X
fans
Conduct Operational Tests X
Furnaces, ductwork and stacks

Check condition of equipment, quality of installation, and compliance with Project X


drawings, MANUFACTURERS instructions, safety rules, specifications and good
practice
Perform hydrostatic test on completed furnace coils X
Empty water from coil and air blow if necessary X
Issue furnace dry-out procedure based on vendor / manufacturer recommendations X
Check mechanical operation of soot blowers, dampers, air pre-heaters and burners X
louvers
Prepare furnace and fuel systems for dry-out operation. Ensure tubes are vented X
adequately
Dry out the furnace following the approved procedure X
After drying-out, clean stack and duct, open manholes and other openings for X
inspection. Check operation of dampers and registers. Close stack and duct after
inspection
Obtain and charge liquid heat transfer media, if required X
Conduct light-off, drying, and purging X
Conduct Operational Tests X
Vessels - Towers, reactors and drums

Check condition of equipment, quality of installation, and compliance with Project X


drawings, MANUFACTURERS instructions, safety rules, specifications and good
practice
Install all tower, reactor and drum internals (not already installed in fabrication shop) X
Clean out all vessels X
Properly close up all vessel internal man ways and openings after final inspection or X
after loading of chemicals, catalysts, etc. is completed
Carry out vessels and tower final inspection X X
Issue to Contractor written authority to close up each vessel X
Task description PC Comm.

Perform tray leakage test and levelling adjustments as required in all tower, reactor and X
drum internals
Cure and dry out castable linings X
Inspect all towers and drums for cleanliness and dryness before loading catalysts, etc. X
Load all chemicals after cleaning and dry-out, (including hot oil, amine, glycol, freon, X
inhibitors, etc.), desiccants, catalysts, tower packing’s
Carry out air blowing if required X
Inspect after final loading. Obtain samples of all catalysts loaded X
Conduct Operational Tests as applicable X
Tankage

Check condition of equipment, quality of installation, and compliance with Project X


drawings, MANUFACTURERS instructions, safety rules, specifications and good
practice
Install appurtenances X
Hydrostatic test tank and internal piping, and clean inside tank X
Close man ways X
Strap tank and issue record X
Carry out tank final inspection X X
Issue to Contractor written authority to close up each vessel X
Organize independent calibration of product tanks for custody transfer where required X
by government regulations
Conduct Operational Tests as applicable X
Shell and tube exchangers

Check condition of equipment, quality of installation, and compliance with Project X


drawings, manufacturer’s instructions, safety rules, specifications and good practice
Pumps

Check condition of equipment, quality of installation, and compliance with Project X


drawings, manufacturer’s instructions, safety rules, specifications and good practice
Set and cold align pumps and drivers X
Couple pumps to drivers X
Install temporary strainers in suction piping X
Check that piston seal packaging followers, if any, are correctly tightened X
Check discharge flow dampers are correctly charged and installed X
Check pump gear box oil levels X
Run-in pump in recycle, check pump and motor operation and do any required dowelling X
of the pump driver – check for vibration
Charge the lube oil, seal oil, and oil cooling systems X
Carry out lube and seal oil systems flushing, circulate oil until test patches are clean X
Check oil for presence of chips after no load run X
Check gears, bearings and parts for signs of wear and damage X
Make final hot alignment check X
Conduct Operational Tests X
Gas turbines, compressors and expanders

Check condition of equipment, quality of installation, and compliance with Project X


drawings, manufacturer’s instructions, safety rules, specifications and good practice
Install all piping and make piping corrections as required by VENDOR's tolerances. Set X
and cold align units
Fill lube and seal oil systems X
Task description PC Comm.

Carry out lube and seal oil systems flushing, circulate oil until test patches are clean X
Drain lube and seal oil systems then refill with new oil, if required X
Clean chemically suction and inter stage piping and lube/seal oil piping X
Disassemble above piping for cleanliness inspection as required X
Run in driver (uncoupled) (except for expanders) X
Couple driver and driven unit X
Run in compressor in recycle on air or inert gas, if possible and/or suitable, on gas after X
gas-in otherwise. Check operation
Check hot alignment X
Carry out comprehensive vibration tests X
Check equipment stacks / exhausts skin temperature according to project safety X
specifications
Run unit on stream X
Check plant noise levels X
Check equipment noise levels X
Conduct Operational Tests X
Diesel engines

Check condition of equipment, quality of installation, and compliance with Project X


drawings, MANUFACTURERS instructions, safety rules, specifications and good
practice
Set and cold align units X
Clean lube oil piping X
Fill lube oil system X
Drain lube oil system then refill with new oil, if not required X
Test run Diesel engines and their accessories uncoupled X
Couple diesel engines to driven equipment X
Test run coupled unit and verify all operating parameters X
Carry out noise measurement tests X
Check equipment stacks / exhausts skin temperature according to safety specifications X
Conduct Operational Tests X
Check alignment after operational test X
Miscellaneous mechanical equipment (lube oil, vacuum equipment, weigh scale, materials lifting and
handling equipment, ...)
Check condition of equipment, quality of installation, and compliance with Project X
drawings, MANUFACTURERS instructions, safety rules, specifications and good
practice
Fill-in lube and hydraulic oil systems of lifting equipment X
Load test all pad eyes X
Test lifting equipment in presence of Insurance Inspector or appropriate governmental X
authority
Test vacuum equipment. Check all joint for leaks X
Calibrate all solids weighing and measuring devices in their field-installed operating X
positions. Show that equipment meets specified tolerance for accuracy over full range of
operating conditions
Conduct Operational Tests X
HVAC equipment

Check condition of equipment, quality of installation, and compliance with Project X


drawings, MANUFACTURERS instructions, safety rules, specifications and good
practice
Check alignment of motors/fans and drives X
Task description PC Comm.

Check that tension on drives is correct X


Check that fans and motors rotate manually and run freely X
Check that anti-vibration mountings are correctly installed X
Check that sealing compound of fire dampers is installed correctly X
Check that linkage and blades of dampers operate correctly and freely X
Check that dampers actuators operate correctly X
Check that airflow direction in pre-heaters is correct X
Carry out ductwork leak tests X
Energize and run unit. Test sequences and interlocks. Check vibrations X
Carry out airflow and balancing tests X
Control and adjust rooms temperature and pressurization X
Conduct Operational Tests X
Lifesaving equipment

Check condition of equipment, quality of installation, and compliance with Project X


drawings, MANUFACTURERS instructions, safety rules, specifications and good
practice
Check that all Escape Routes signs are clearly marked to indicate escape ways and X
muster points (such as arrows, numbers, display boards and routes)
Check that escape ways are safe and secure X
Conduct Operational Tests X
Fire-fighting equipment

Check storage locations of all extinguishers X


Function test of extinguishing agent skids with real release X
Conduct Operational Tests of Deluge System, Hydrants, Monitors, Foam, etc. ... X
Conduct specific tests as required by local Authorities X
Telephones (include interphones, intercoms, fax, telex, switchboard, etc.)

Check condition of equipment, quality of installation, and compliance with Project X


drawings, MANUFACTURERS instructions, safety rules, specifications and good
practice
Check especially that EX equipment has been installed in classified areas X
Energize and carry out equipment functional tests X
Test actual operation of all equipment X
Conduct Operational Tests as applicable X
Public address

Check condition of equipment, quality of installation, and compliance with Project X


drawings, MANUFACTURERS instructions, safety rules, specifications and good
practice
Energize and carry out PA loops functional tests X
Test actual operation of loudspeakers and flashing beacons, including check and X
adjustment of operational features on field such as: range/coverage, visibility, etc.
Conduct Operational Tests as applicable X
Radios (include Marine and Aero VHF, MF/UHF SSB, NDB, UHF local network, Tropo-scatter and line of
sight radio links, Multiplex, Radio paging, satellite earth stations, etc.)
Check condition of equipment, quality of installation, and compliance with Project X
drawings, MANUFACTURERS instructions, safety rules, specifications and good
practice
Check connections of antennas, feeders, radio transceivers and associated equipment X
Energize and carry out one in-station test per radio equipment X
Task description PC Comm.

Test radio systems operation X


Perform antenna’s final alignment X
Conduct Operational Tests as applicable X
Telemetry (MTU and RTU's)

Check condition of equipment, quality of installation, and compliance with Project X


drawings, MANUFACTURERS instructions, safety rules, specifications and good
practice
Energize and test data transmission X
Carry out instrument interface tests X
Conduct Operational Tests as applicable X
CCTV systems

Check condition of equipment, quality of installation, and compliance with X


MANUFACTURERS instructions, safety rules, Project drawings, specifications and good
practice
Check free operation of cameras and pan-and-tilt equipment X
Energize and check proper functioning of equipment X
Test System test, scanning, sequencing, etc. X
Conduct Operational Tests as applicable X