Issues With Densol Tender: 1. Missing Scope
Issues With Densol Tender: 1. Missing Scope
1. Missing scope
2. Incorrect quantities
2.4.1 Pier Headstocks - P3 to P9 - Wet m3 435 (123 $0.00
incorrect)
5.2.2 Blow out before pouring concrete - m2 1,200 $0.00
Deck Slab (2,200
incorrect)
3. High Rate
3.1 Abutment Headstocks t 21.8 $ 1,557.38 $0.00
(4356.76 high
rate)
After considering inclusions, exclusions, scope of works, quantities and other relevant
factors, Robemen represents the best selection out of the other subcontractors.
Robeman are not charging for the following items in their tender
- Blow out before pouring concrete - Deck Slab
- Finish & Cure Deck Slab
- Deck slab - Allow Bracket & Walkway along both sides of bridge
The total cost for Robemen’s tender comes down to $3,473,950.29 and if we add the
exclusion at an average price of $398,654.98 the total will be $3,872,605.27. This comes
down to be the cheapest price. Robemen have not missed out on any scope of works and
they have priced the original procurement quantities with reasonable rates. Lamlian have
overpriced a fair amount of the scope and so has Cordem, both of their totals can be seen in
the subcontractor comparison spreadsheet. Densol have the above listed issues with their
tender, therefore it does not represent best selection.