Procurement - Log E2
Procurement - Log E2
Division 23 HVAC
23-05-19 HVAC Meters & Gauges. 38 38 3-Sep-99 8-Sep-99 Local 18-Sep-99 25-Dec-99 98
23-05-23 00710 C HVAC Valves. 321 321 20-Aug-99 25-Aug-99 Local 4-Sep-99 25-Dec-99 112
23-05-29 00912 R HVAC Pipes Hangers & Supports. 280 280 3-Sep-99 8-Sep-99 Local 18-Sep-99 25-Dec-99 98
23-05-48 HVAC Vibration Isolators & Inertia Bases. 358 358 3-Sep-99 8-Sep-99 Sea Freight 18-Sep-99 25-Dec-99 98
23-05-93 Testing, Adjusting & Balancing. 1 1 23-Jul-99 28-Jul-99 7-Aug-99 25-Dec-99 140
23-07-00 Duct Adhesive, Sealant & Coating. 1 1 17-Sep-99 22-Sep-99 Local 2-Oct-99 25-Dec-99 84
23-07-00 Duct Thermal Insulation. 4,146 4,146 15-Oct-99 20-Oct-99 Local 30-Oct-99 25-Dec-99 56
23-07-00 Chilled Water Pipe Thermal Insulation. 674 674 15-Oct-99 20-Oct-99 Sea Freight 30-Oct-99 25-Dec-99 56
23-09-00 Building Management System. 1 1 20-Aug-99 25-Aug-99 Sea Freight 4-Sep-99 25-Dec-99 112
23-21-13 Pre-Insulated Chilled Water Pipes & Fittings. 270 270 3-Sep-99 8-Sep-99 Road 18-Sep-99 25-Dec-99 98
23-21-13 Mild-Steel Chilled Water Pipes. 518 518 -48 -43 Local -33 -5 28
23-21-13 Malleable-Steel Chilled Water Fittings. 1 1 12-Nov-99 17-Nov-99 Local 27-Nov-99 25-Dec-99 28
23-21-13 00708 R Carbon-Steel Chilled Water Pipes. 238 238 12-Nov-99 17-Nov-99 Local 27-Nov-99 25-Dec-99 28
Page 1 of 14 R_202_LG_E2_R2
Delivery To Site
Title Purchase Order
B.O.Q / Specif. Ref. Estimated Ordered Shipping Shipping Date Lead Time
Activity ID Submittal Ref. No. Rev. No. Status Reqd. Order Date Required On Job
No. Quantity Quantity Method (Days)
Expected Actual
23-21-13 00709 B Carbon-Steel Chilled Water Fittings. 1 1 17-Sep-99 22-Sep-99 Local 2-Oct-99 25-Dec-99 84
23-21-13 UPVC Condensate Drain Pipies & Fittings. 1 1 12-Nov-99 17-Nov-99 Local 27-Nov-99 25-Dec-99 28
23-21-23 HVAC Pumps. 2 2 23-Jul-99 28-Jul-99 Sea Freight 7-Aug-99 25-Dec-99 140
23-21-23 Expansion Tank 1 1 23-Jul-99 28-Jul-99 Sea Freight 7-Aug-99 25-Dec-99 140
23-21-23 Air Separator. 1 1 23-Jul-99 28-Jul-99 Sea Freight 7-Aug-99 25-Dec-99 140
23-23-00 Refrigerant Copper Tubes & Fittings. 60 60 17-Sep-99 22-Sep-99 Sea Freight 2-Oct-99 25-Dec-99 84
23-25-00 HVAC Water Treatment Unit. 1 1 17-Sep-99 22-Sep-99 Sea Freight 2-Oct-99 25-Dec-99 84
23-31-13 Galvanized-Iron Sheet Metal for Ductwork. 38,000 38,000 29-Oct-99 3-Nov-99 Local 13-Nov-99 25-Dec-99 42
23-31-13 Stainless-Steel Sheet Metal for Kitchen Exhaust Ductwork. 1,968 1,968 1-Oct-99 6-Oct-99 Local 16-Oct-99 25-Dec-99 70
23-31-13 Fire-Rated Duct 2,580 2,580 1-Oct-99 6-Oct-99 Local 16-Oct-99 25-Dec-99 70
23-31-13 Pre-Insulated Round Flexible Duct. 1 1 1-Oct-99 6-Oct-99 Local 16-Oct-99 25-Dec-99 70
23-33-00 Back-Draft & Volume Control Dampers. 458 458 15-Oct-99 20-Oct-99 Sea Freight 30-Oct-99 25-Dec-99 56
23-33-00 Fire & Motorized Fire/Smoke Dampers. 55 55 15-Oct-99 20-Oct-99 Sea Freight 30-Oct-99 25-Dec-99 56
23-33-00 Duct Access Doors. 21 21 15-Oct-99 20-Oct-99 Sea Freight 30-Oct-99 25-Dec-99 56
23-37-13 Air Outlets & Inlets. 540 540 1-Oct-99 6-Oct-99 Sea Freight 16-Oct-99 25-Dec-99 70
23-43-00 Kitchen Alr Cleaners. 1 1 20-Aug-99 25-Aug-99 Sea Freight 4-Sep-99 25-Dec-99 112
Page 2 of 14 R_202_LG_E2_R2
Delivery To Site
Title Purchase Order
B.O.Q / Specif. Ref. Estimated Ordered Shipping Shipping Date Lead Time
Activity ID Submittal Ref. No. Rev. No. Status Reqd. Order Date Required On Job
No. Quantity Quantity Method (Days)
Expected Actual
23-57-00 Plate Type Heat Exchangers. 2 2 20-Aug-99 25-Aug-99 Sea Freight 4-Sep-99 25-Dec-99 112
23-73-13 Air Handling Units. 3 3 20-Aug-99 25-Aug-99 Sea Freight 4-Sep-99 25-Dec-99 112
23-74-13 Ducted Split DX A/C Units 6 6 17-Sep-99 22-Sep-99 Sea Freight 2-Oct-99 25-Dec-99 84
23-82-19 Fan Coil Units. 43 43 17-Sep-99 22-Sep-99 Sea Freight 2-Oct-99 25-Dec-99 84
21-11-00/ 21-12-00 01015 C Ductile-Iron Pipes & Fittings (Underground). 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99
21-11-00/ 21-12-00/
00713 R Fire Fighting Valves. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99
21-13-13
21-12-00/ 21-13-13 00714 C Galvanized-Iron Pipes & Fittings (Aboveground). 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99
21-12-00/ 21-13-13 Carbon-Steel Pipes & Fittings (Aboveground). 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99
21-12-00/ 21-13-13 00913 R Fire Fighting Pipe Hangers & Supports. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99
21-12-00/ 21-13-13 Fire Fighting Pressure Gauges. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99
Page 3 of 14 R_202_LG_E2_R2
Delivery To Site
Title Purchase Order
B.O.Q / Specif. Ref. Estimated Ordered Shipping Shipping Date Lead Time
Activity ID Submittal Ref. No. Rev. No. Status Reqd. Order Date Required On Job
No. Quantity Quantity Method (Days)
Expected Actual
32-84-00 00775 C UPVC/PE Irrigation/TSE Pipes & Fittings. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99
33-41-00 Ductile-Iron Storm Drainage Pipes & Fittings. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99
33-41-00 00369 B HDPE Pipes & Fittings. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99
22-05-29 Plumbing Pipe Hangers & Supports. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99
22-11-16 00901 R PPR Domestic Water Pipes & Fittings. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99
22-11-16 00902 R PE Domestic Water Pipes & Fittings. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99
Page 4 of 14 R_202_LG_E2_R2
Delivery To Site
Title Purchase Order
B.O.Q / Specif. Ref. Estimated Ordered Shipping Shipping Date Lead Time
Activity ID Submittal Ref. No. Rev. No. Status Reqd. Order Date Required On Job
No. Quantity Quantity Method (Days)
Expected Actual
22-12-23 GRP Potable Water Storage Tanks. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99
22-40-00 Sanitary Fixtures & Fittings (Sanitaryware). 12-Aug-99 17-Aug-99 27-Aug-99 25-Dec-99 120
x 22-70-00 Fuel System to Diesel Generators. 26-Oct-20 31-Oct-20 10-Nov-20 30-Dec-20 10-Mar-21 120
Division 26 Electrical
26-05-13 00437 B Power Cables 7-Dec-20 12-Dec-20 Local 22-Dec-20 30-Dec-20 25-Dec-20 3
26-05-19 00437 UR Electrical Wires 8-Nov-20 13-Nov-20 Local 23-Nov-20 1-Dec-20 26-Nov-20 3
26-05-33 00775 B PVC Conduits & Accessories 27-Sep-20 2-Oct-20 Local 12-Oct-20 18-Oct-20 13-Oct-20 1
26-05-33 00760 B Galvanized-Iron Conduits 27-Sep-20 2-Oct-20 Local 12-Oct-20 18-Oct-20 13-Oct-20 1
26-05-36 Galvanized-Iron Cable Trays & Ladders 8-Nov-20 13-Nov-20 Local 23-Nov-20 1-Dec-20 26-Nov-20 3
Page 5 of 14 R_202_LG_E2_R2
Delivery To Site
Title Purchase Order
B.O.Q / Specif. Ref. Estimated Ordered Shipping Shipping Date Lead Time
Activity ID Submittal Ref. No. Rev. No. Status Reqd. Order Date Required On Job
No. Quantity Quantity Method (Days)
Expected Actual
26-06-20 MLTP, MSB, SMSB & DB's. 10-Nov-20 15-Nov-20 Local 25-Nov-20 30-Dec-20 25-Dec-20 30
26-06-20 Motor Control Centers. 10-Nov-20 15-Nov-20 Local 25-Nov-20 30-Dec-20 25-Dec-20 30
26-36-23 Automatic Transfer Switches. 10-Nov-20 15-Nov-20 Local 25-Nov-20 30-Dec-20 25-Dec-20 30
26-41-00 Lightning Protection System. 3-Dec-20 8-Dec-20 Local 18-Dec-20 30-Dec-20 25-Dec-20 7
00775 B Underground Ducts and Raceways 27-Sep-20 2-Oct-20 Local 12-Oct-20 18-Oct-20 13-Oct-20 1
28-00-00 Fire Alarm System 6-Aug-99 11-Aug-99 Sea Freight 21-Aug-99 25-Dec-99 126
05-16-00 Structured Cabling System (Network Passive Component) 6-Aug-99 11-Aug-99 Sea Freight 21-Aug-99 25-Dec-99 126
26-05-23 Control Cables. 6-Aug-99 11-Aug-99 Sea Freight 21-Aug-99 25-Dec-99 126
Page 6 of 14 R_202_LG_E2_R2
Delivery To Site
Title Purchase Order
B.O.Q / Specif. Ref. Estimated Ordered Shipping Shipping Date Lead Time
Activity ID Submittal Ref. No. Rev. No. Status Reqd. Order Date Required On Job
No. Quantity Quantity Method (Days)
Expected Actual
Public Address System 6-Aug-99 11-Aug-99 Sea Freight 21-Aug-99 25-Dec-99 126
Network Active Components 6-Aug-99 11-Aug-99 Sea Freight 21-Aug-99 25-Dec-99 126
Access Control System 6-Aug-99 11-Aug-99 Sea Freight 21-Aug-99 25-Dec-99 126
Page 7 of 14 R_202_LG_E2_R2
Expected PO Lead Time
Remarks
Date (Weeks)
30-Dec-20 No BOQ
4-6 Weeks
30-Nov-20 LOI issued on 27-Oct-20
12-14 Weeks
Page 8 of 14 R_202_LG_E2_R2
Expected PO Lead Time
Remarks
Date (Weeks)
No BOQ
Page 9 of 14 R_202_LG_E2_R2
Expected PO Lead Time
Remarks
Date (Weeks)
No BOQ
Page 10 of 14 R_202_LG_E2_R2
Expected PO Lead Time
Remarks
Date (Weeks)
No BOQ
Page 11 of 14 R_202_LG_E2_R2
Expected PO Lead Time
Remarks
Date (Weeks)
30-Dec-20 No BOQ
30-Dec-20 No BOQ
Partially Delivered
Partially Delivered
Partially Delivered
Page 12 of 14 R_202_LG_E2_R2
Expected PO Lead Time
Remarks
Date (Weeks)
Page 13 of 14 R_202_LG_E2_R2
Expected PO Lead Time
Remarks
Date (Weeks)
30-Dec-20
Page 14 of 14 R_202_LG_E2_R2