Procurement - Log E2

This document appears to be a purchase order listing for HVAC equipment and materials for a construction project. It includes over 30 line items with details like item description, quantity, required and order dates, shipping method, and lead time. The majority of the items have a required date of September 18, 1999 and a shipping date of December 25, 1999, with lead times ranging from 28 to 140 days.

Uploaded by

Khalifa Riswan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
1K views14 pages

Procurement - Log E2

This document appears to be a purchase order listing for HVAC equipment and materials for a construction project. It includes over 30 line items with details like item description, quantity, required and order dates, shipping method, and lead time. The majority of the items have a required date of September 18, 1999 and a shipping date of December 25, 1999, with lead times ranging from 28 to 140 days.

Uploaded by

Khalifa Riswan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 14

Delivery To Site

Title Purchase Order


B.O.Q / Specif. Ref. Estimated Ordered Shipping Shipping Date Lead Time
Activity ID Submittal Ref. No. Rev. No. Status Reqd. Order Date Required On Job
No. Quantity Quantity Method (Days)
Expected Actual
Supplier Issued Date Number

Division 23 HVAC

23-05-19 HVAC Meters & Gauges. 38 38 3-Sep-99 8-Sep-99 Local 18-Sep-99 25-Dec-99 98

23-05-23 00710 C HVAC Valves. 321 321 20-Aug-99 25-Aug-99 Local 4-Sep-99 25-Dec-99 112

23-05-29 00912 R HVAC Pipes Hangers & Supports. 280 280 3-Sep-99 8-Sep-99 Local 18-Sep-99 25-Dec-99 98

23-05-48 HVAC Vibration Isolators & Inertia Bases. 358 358 3-Sep-99 8-Sep-99 Sea Freight 18-Sep-99 25-Dec-99 98

23-05-48 Sound Attenuators. 8 8 3-Sep-99 8-Sep-99 Local 18-Sep-99 25-Dec-99 98

23-05-48 Accoutic Lining. 1 1 29-Oct-99 3-Nov-99 Local 13-Nov-99 25-Dec-99 42

23-05-53 HVAC Identification. 1 1 1-Oct-99 6-Oct-99 Local 16-Oct-99 25-Dec-99 70

23-05-93 Testing, Adjusting & Balancing. 1 1 23-Jul-99 28-Jul-99 7-Aug-99 25-Dec-99 140

23-07-00 Duct Adhesive, Sealant & Coating. 1 1 17-Sep-99 22-Sep-99 Local 2-Oct-99 25-Dec-99 84

23-07-00 Duct Thermal Insulation. 4,146 4,146 15-Oct-99 20-Oct-99 Local 30-Oct-99 25-Dec-99 56

23-07-00 Chilled Water Pipe Thermal Insulation. 674 674 15-Oct-99 20-Oct-99 Sea Freight 30-Oct-99 25-Dec-99 56

23-07-00 Aluminium Cladding Sheet. 1 1 15-Oct-99 20-Oct-99 Local 30-Oct-99 25-Dec-99 56

23-09-00 Building Management System. 1 1 20-Aug-99 25-Aug-99 Sea Freight 4-Sep-99 25-Dec-99 112

23-21-13 Pre-Insulated Chilled Water Pipes & Fittings. 270 270 3-Sep-99 8-Sep-99 Road 18-Sep-99 25-Dec-99 98

23-21-13 Mild-Steel Chilled Water Pipes. 518 518 -48 -43 Local -33 -5 28

23-21-13 Malleable-Steel Chilled Water Fittings. 1 1 12-Nov-99 17-Nov-99 Local 27-Nov-99 25-Dec-99 28

23-21-13 00708 R Carbon-Steel Chilled Water Pipes. 238 238 12-Nov-99 17-Nov-99 Local 27-Nov-99 25-Dec-99 28

Page 1 of 14 R_202_LG_E2_R2
Delivery To Site
Title Purchase Order
B.O.Q / Specif. Ref. Estimated Ordered Shipping Shipping Date Lead Time
Activity ID Submittal Ref. No. Rev. No. Status Reqd. Order Date Required On Job
No. Quantity Quantity Method (Days)
Expected Actual

23-21-13 00709 B Carbon-Steel Chilled Water Fittings. 1 1 17-Sep-99 22-Sep-99 Local 2-Oct-99 25-Dec-99 84

23-21-13 UPVC Condensate Drain Pipies & Fittings. 1 1 12-Nov-99 17-Nov-99 Local 27-Nov-99 25-Dec-99 28

23-21-23 HVAC Pumps. 2 2 23-Jul-99 28-Jul-99 Sea Freight 7-Aug-99 25-Dec-99 140

23-21-23 Expansion Tank 1 1 23-Jul-99 28-Jul-99 Sea Freight 7-Aug-99 25-Dec-99 140

23-21-23 Air Separator. 1 1 23-Jul-99 28-Jul-99 Sea Freight 7-Aug-99 25-Dec-99 140

23-23-00 Refrigerant Copper Tubes & Fittings. 60 60 17-Sep-99 22-Sep-99 Sea Freight 2-Oct-99 25-Dec-99 84

23-25-00 HVAC Water Treatment Unit. 1 1 17-Sep-99 22-Sep-99 Sea Freight 2-Oct-99 25-Dec-99 84

23-31-13 Galvanized-Iron Sheet Metal for Ductwork. 38,000 38,000 29-Oct-99 3-Nov-99 Local 13-Nov-99 25-Dec-99 42

23-31-13 Stainless-Steel Sheet Metal for Kitchen Exhaust Ductwork. 1,968 1,968 1-Oct-99 6-Oct-99 Local 16-Oct-99 25-Dec-99 70

23-31-13 Fire-Rated Duct 2,580 2,580 1-Oct-99 6-Oct-99 Local 16-Oct-99 25-Dec-99 70

23-31-13 Pre-Insulated Round Flexible Duct. 1 1 1-Oct-99 6-Oct-99 Local 16-Oct-99 25-Dec-99 70

23-33-00 Back-Draft & Volume Control Dampers. 458 458 15-Oct-99 20-Oct-99 Sea Freight 30-Oct-99 25-Dec-99 56

23-33-00 Fire & Motorized Fire/Smoke Dampers. 55 55 15-Oct-99 20-Oct-99 Sea Freight 30-Oct-99 25-Dec-99 56

23-33-00 Flexible Duct Connectors. 1 1 17-Sep-99 22-Sep-99 Local 2-Oct-99 25-Dec-99 84

23-33-00 Duct Access Doors. 21 21 15-Oct-99 20-Oct-99 Sea Freight 30-Oct-99 25-Dec-99 56

23-34-13 Fans. 46 46 23-Jul-99 28-Jul-99 Sea Freight 7-Aug-99 25-Dec-99 140

23-37-13 Air Outlets & Inlets. 540 540 1-Oct-99 6-Oct-99 Sea Freight 16-Oct-99 25-Dec-99 70

23-43-00 Kitchen Alr Cleaners. 1 1 20-Aug-99 25-Aug-99 Sea Freight 4-Sep-99 25-Dec-99 112

Page 2 of 14 R_202_LG_E2_R2
Delivery To Site
Title Purchase Order
B.O.Q / Specif. Ref. Estimated Ordered Shipping Shipping Date Lead Time
Activity ID Submittal Ref. No. Rev. No. Status Reqd. Order Date Required On Job
No. Quantity Quantity Method (Days)
Expected Actual

23-57-00 Plate Type Heat Exchangers. 2 2 20-Aug-99 25-Aug-99 Sea Freight 4-Sep-99 25-Dec-99 112

23-73-13 Air Handling Units. 3 3 20-Aug-99 25-Aug-99 Sea Freight 4-Sep-99 25-Dec-99 112

23-74-13 Ducted Split DX A/C Units 6 6 17-Sep-99 22-Sep-99 Sea Freight 2-Oct-99 25-Dec-99 84

23-81-26 Mini-Split AC Units 6 6 17-Sep-99 22-Sep-99 Sea Freight 2-Oct-99 25-Dec-99 84

23-82-19 Fan Coil Units. 43 43 17-Sep-99 22-Sep-99 Sea Freight 2-Oct-99 25-Dec-99 84

Division 21 Fire Fighting

10-44-13 Fire Cabinets. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

10-44-16 Fire Extinguishers. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

21-11-00/ 21-12-00 01015 C Ductile-Iron Pipes & Fittings (Underground). 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

21-11-00/ 21-12-00/
00713 R Fire Fighting Valves. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99
21-13-13

21-11-00 Fire Hydrants. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

21-12-00/ 21-13-13 00714 C Galvanized-Iron Pipes & Fittings (Aboveground). 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

21-12-00/ 21-13-13 Carbon-Steel Pipes & Fittings (Aboveground). 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

21-12-00/ 21-13-13 00913 R Fire Fighting Pipe Hangers & Supports. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

21-12-00 Landing Valves. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

21-12-00 Fire Department Connection. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

21-12-00/ 21-13-13 Fire Fighting Pressure Gauges. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

21-13-13 Breeching Inlets. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

Page 3 of 14 R_202_LG_E2_R2
Delivery To Site
Title Purchase Order
B.O.Q / Specif. Ref. Estimated Ordered Shipping Shipping Date Lead Time
Activity ID Submittal Ref. No. Rev. No. Status Reqd. Order Date Required On Job
No. Quantity Quantity Method (Days)
Expected Actual

21-13-13 Sprinkler Heads. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

21-13-13 Alarm Devices. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

21-13-39 Foam-Water System. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

Division 22 Plumbing 25-Dec-99 25-Dec-99

32-84-00 00775 C UPVC/PE Irrigation/TSE Pipes & Fittings. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

33-41-00 Ductile-Iron Storm Drainage Pipes & Fittings. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

33-41-00 00369 B HDPE Pipes & Fittings. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

33-41-00 Storm Water Attenuation Tanks. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

33-45-00 Submersible Pumps 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

22-05-19 Plumbing Pressure Gauges. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

22-05-23 Plumbing Valves. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

22-05-29 Plumbing Pipe Hangers & Supports. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

22-05-53 Plumbing Identification. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

22-07-00 Rubber Foam Insulation. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

22-11-16 00901 R PPR Domestic Water Pipes & Fittings. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

22-11-16 00902 R PE Domestic Water Pipes & Fittings. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

22-11-16 Plumbing Flexible Connectors. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

22-11-16 Water Meters. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

Page 4 of 14 R_202_LG_E2_R2
Delivery To Site
Title Purchase Order
B.O.Q / Specif. Ref. Estimated Ordered Shipping Shipping Date Lead Time
Activity ID Submittal Ref. No. Rev. No. Status Reqd. Order Date Required On Job
No. Quantity Quantity Method (Days)
Expected Actual

22-11-19 Domestic Water Piping Specialties. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

22-11-23 Domestic Water Booster Pumps. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

22-12-23 GRP Potable Water Storage Tanks. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

22-13-19/ 22-14-23 Sanitary Waste Specialties. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

22-32-00 Cartridge Filters. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

22-33-00 Solar Water Heaters. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

22-33-01 Electric Domestic Water Heaters. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

22-40-00 Sanitary Fixtures & Fittings (Sanitaryware). 12-Aug-99 17-Aug-99 27-Aug-99 25-Dec-99 120

22-47-00 Water Coolers. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

x 22-70-00 Fuel System to Diesel Generators. 26-Oct-20 31-Oct-20 10-Nov-20 30-Dec-20 10-Mar-21 120

Division 26 Electrical

26-05-13 00437 B Power Cables 7-Dec-20 12-Dec-20 Local 22-Dec-20 30-Dec-20 25-Dec-20 3

26-05-19 00437 UR Electrical Wires 8-Nov-20 13-Nov-20 Local 23-Nov-20 1-Dec-20 26-Nov-20 3

26-05-26 Earthing System. 4-Nov-20 9-Nov-20 Local 19-Nov-20 1-Dec-20 26-Nov-20 7

26-05-33 00775 B PVC Conduits & Accessories 27-Sep-20 2-Oct-20 Local 12-Oct-20 18-Oct-20 13-Oct-20 1

26-05-33 00760 B Galvanized-Iron Conduits 27-Sep-20 2-Oct-20 Local 12-Oct-20 18-Oct-20 13-Oct-20 1

00761 B Glavanized-Iron Accessories 27-Sep-20 2-Oct-20 Local 12-Oct-20 18-Oct-20 13-Oct-20 1

26-05-36 Galvanized-Iron Cable Trays & Ladders 8-Nov-20 13-Nov-20 Local 23-Nov-20 1-Dec-20 26-Nov-20 3

Page 5 of 14 R_202_LG_E2_R2
Delivery To Site
Title Purchase Order
B.O.Q / Specif. Ref. Estimated Ordered Shipping Shipping Date Lead Time
Activity ID Submittal Ref. No. Rev. No. Status Reqd. Order Date Required On Job
No. Quantity Quantity Method (Days)
Expected Actual

26-05-36 Galvanized-Iron Trunking 8-Nov-20 13-Nov-20 Local 23-Nov-20 1-Dec-20 26-Nov-20 3

26-05-46 Utility Light Poles. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

26-06-20 MLTP, MSB, SMSB & DB's. 10-Nov-20 15-Nov-20 Local 25-Nov-20 30-Dec-20 25-Dec-20 30

26-06-20 Feeder Pillars. 9-Feb-20 14-Feb-20 Local 24-Feb-20 30-Mar-20 25-Mar-20 30

26-06-20 Motor Control Centers. 10-Nov-20 15-Nov-20 Local 25-Nov-20 30-Dec-20 25-Dec-20 30

26-27-26 Wiring Devices. 12-Aug-99 17-Aug-99 27-Aug-99 25-Dec-99 120

26-32-00 Diesel Generator. 13-Jun-99 18-Jun-99 28-Jun-99 25-Dec-99 180

26-33-23 Central Battery System. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

26-33-53 Static Uninterruptible Power Supply. 10-Dec-99 15-Dec-99 25-Dec-99 25-Dec-99

26-35-33 Capacitor Banks. 9-Feb-20 14-Feb-20 Local 24-Feb-20 30-Mar-20 25-Mar-20 30

26-36-23 Automatic Transfer Switches. 10-Nov-20 15-Nov-20 Local 25-Nov-20 30-Dec-20 25-Dec-20 30

26-41-00 Lightning Protection System. 3-Dec-20 8-Dec-20 Local 18-Dec-20 30-Dec-20 25-Dec-20 7

26-51-00 Light Fittings. 12-Aug-99 17-Aug-99 27-Aug-99 25-Dec-99 120

00775 B Underground Ducts and Raceways 27-Sep-20 2-Oct-20 Local 12-Oct-20 18-Oct-20 13-Oct-20 1

Division 27 & 28 Low Voltage & Fire Alarm System

28-00-00 Fire Alarm System 6-Aug-99 11-Aug-99 Sea Freight 21-Aug-99 25-Dec-99 126

05-16-00 Structured Cabling System (Network Passive Component) 6-Aug-99 11-Aug-99 Sea Freight 21-Aug-99 25-Dec-99 126

26-05-23 Control Cables. 6-Aug-99 11-Aug-99 Sea Freight 21-Aug-99 25-Dec-99 126

Page 6 of 14 R_202_LG_E2_R2
Delivery To Site
Title Purchase Order
B.O.Q / Specif. Ref. Estimated Ordered Shipping Shipping Date Lead Time
Activity ID Submittal Ref. No. Rev. No. Status Reqd. Order Date Required On Job
No. Quantity Quantity Method (Days)
Expected Actual

Physical Security 6-Aug-99 11-Aug-99 Sea Freight 21-Aug-99 25-Dec-99 126

IP Telephone system 6-Aug-99 11-Aug-99 Sea Freight 21-Aug-99 25-Dec-99 126

Public Address System 6-Aug-99 11-Aug-99 Sea Freight 21-Aug-99 25-Dec-99 126

CCTV System 6-Aug-99 11-Aug-99 Sea Freight 21-Aug-99 25-Dec-99 126

Network Active Components 6-Aug-99 11-Aug-99 Sea Freight 21-Aug-99 25-Dec-99 126

Access Control System 6-Aug-99 11-Aug-99 Sea Freight 21-Aug-99 25-Dec-99 126

A/V System 6-Aug-99 11-Aug-99 Sea Freight 21-Aug-99 25-Dec-99 126

SMATV System 6-Aug-99 11-Aug-99 Sea Freight 21-Aug-99 25-Dec-99 126

Page 7 of 14 R_202_LG_E2_R2
Expected PO Lead Time
Remarks
Date (Weeks)

30-Dec-20 12-14 Weeks No BOQ

30-Dec-20 14-16 Weeks No BOQ

30-Nov-20 12-14 weeks

30-Dec-20 12-14 Weeks No BOQ

30-Dec-20 12-14 Weeks No BOQ

30-Dec-20 04-06 Weeks No BOQ

30-Dec-20 08-10 Weeks No BOQ

30-Dec-20 No BOQ

30-Dec-20 10-12 Weeks No BOQ

30-Dec-20 6-8 Weeks No BOQ

30-Dec-20 6-8 Weeks No BOQ

30-Dec-20 6-8 Weeks No BOQ

30-Dec-20 14-16 Weeks No BOQ

4-6 Weeks
30-Nov-20 LOI issued on 27-Oct-20
12-14 Weeks

44195 Ex-stock No BOQ

30-Dec-20 Ex-stock No BOQ

30-Dec-20 Ex-stock No BOQ

Page 8 of 14 R_202_LG_E2_R2
Expected PO Lead Time
Remarks
Date (Weeks)

30-Dec-20 10-12 Weeks No BOQ

30-Dec-20 Ex-stock No BOQ

30-Nov-20 16-20 Weeks

30-Nov-20 18-20 Weeks

30-Nov-20 18-20 Weeks

30-Dec-20 10-12 Weeks No BOQ

30-Dec-20 10-12 Weeks No BOQ

30-Nov-20 4-6 Weeks

30-Nov-20 8-10 Weeks

30-Nov-20 8-10 Weeks

30-Nov-20 8-10 Weeks

30-Nov-20 6-8 Weeks

30-Nov-20 6-8 Weeks

30-Dec-20 8-12 Weeks No BOQ

30-Dec-20 4-8 Weeks No BOQ

30-Nov-20 18-20 Weeks

30-Nov-20 8-10 Weeks

No BOQ

Page 9 of 14 R_202_LG_E2_R2
Expected PO Lead Time
Remarks
Date (Weeks)

15-Dec-20 12-16 Weeks

15-Dec-20 12-16 Weeks

15-Dec-20 10-12 Weeks

15-Dec-20 10-12 Weeks

30-Nov-20 10-12 Weeks

30-Dec-20 16-20 Weeks No BOQ

30-Dec-20 16-20 Weeks No BOQ

30-Dec-20 14-16 Weeks No BOQ

30-Dec-20 20-22 Weeks No BOQ

30-Dec-20 16-20 Weeks No BOQ

30-Dec-20 12-14 Weeks No BOQ

30-Dec-20 12-14 Weeks No BOQ

30-Dec-20 12-14 Weeks No BOQ

30-Dec-20 16-20 Weeks No BOQ

No BOQ

30-Dec-20 8-10 Weeks No BOQ

30-Dec-20 16-20 Weeks No BOQ

Page 10 of 14 R_202_LG_E2_R2
Expected PO Lead Time
Remarks
Date (Weeks)

30-Dec-20 16-20 Weeks No BOQ

30-Dec-20 16-20 Weeks No BOQ

30-Dec-20 16-20 Weeks No BOQ

30-Dec-20 6-8 Weeks No BOQ

30-Dec-20 6-8 Weeks No BOQ

30-Dec-20 6-8 Weeks No BOQ

No BOQ

30-Dec-20 16-18 Weeks No BOQ

30-Dec-20 8-10 Weeks No BOQ

30-Dec-20 20-22 Weeks No BOQ

30-Dec-20 12-14 weeks No BOQ

30-Dec-20 6-8 Weeks No BOQ

30-Dec-20 6-8 Weeks No BOQ

30-Dec-20 8-10 Weeks No BOQ

30-Dec-20 12-14 Weeks No BOQ

30-Dec-20 8-10 Weeks No BOQ

30-Dec-20 10-12 Weeks No BOQ

Page 11 of 14 R_202_LG_E2_R2
Expected PO Lead Time
Remarks
Date (Weeks)

30-Dec-20 8-10 Weeks No BOQ

30-Dec-20 12-14 Week No BOQ

30-Dec-20 12-14 Week No BOQ

30-Dec-20 12-14 Weeks No BOQ

30-Dec-20 12-14 Weeks No BOQ

30-Dec-20 12-14 Weeks No BOQ

30-Dec-20 12-14 Weeks No BOQ

30-Dec-20 12-14 Weeks No BOQ

30-Dec-20 No BOQ

30-Dec-20 No BOQ

30-Dec-20 22-24 Weeks No BOQ

30-Dec-20 22-24 Weeks No BOQ

30-Dec-20 14-16 Weeks No BOQ

Partially Delivered

Partially Delivered

Partially Delivered

30-Dec-20 5-7 Weeks No BOQ

Page 12 of 14 R_202_LG_E2_R2
Expected PO Lead Time
Remarks
Date (Weeks)

30-Dec-20 5-7 Weeks No BOQ

30-Dec-20 16-18 Weeks

30-Dec-20 8-10 Weeks

30-Dec-20 8-10 Weeks

30-Dec-20 8-10 Weeks

30-Dec-20 14-16 Weeks No BOQ

30-Nov-20 20-22 Weeks

30-Dec-20 12-14 weeks No BOQ

30-Dec-20 12-14 Weeks No BOQ

30-Dec-20 8-10 Weeks No BOQ

30-Dec-20 8-10 Weeks No BOQ

30-Dec-20 14-16 Weeks No BOQ

30-Nov-20 16-18 Weeks

30-Nov-20 14-16 Weeks No BOQ

30-Dec-20 10-12 Weeks

30-Dec-20 12-14 Weeks No BOQ

30-Dec-20 8-10 Weeks No BOQ

Page 13 of 14 R_202_LG_E2_R2
Expected PO Lead Time
Remarks
Date (Weeks)

30-Dec-20

30-Dec-20 12-14 Weeks No BOQ

30-Dec-20 12-14 Weeks No BOQ

30-Dec-20 12-14 Weeks No BOQ

30-Dec-20 12-14 Weeks No BOQ

30-Dec-20 12-14 Weeks No BOQ

30-Dec-20 12-14 Weeks No BOQ

30-Dec-20 12-14 Weeks No BOQ

Page 14 of 14 R_202_LG_E2_R2