Rizal Technological University: Department of Architecture
Rizal Technological University: Department of Architecture
Mandaluyong City
Professional Practice 3
By:
GROUP 2
Sebastian, Abigael G.
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Department of Architecture
Process Groups
will take, how many staff and resources are required and
responsibilities of staff.
5. Communication
The Project Manager will still need to assign tasks and
responsibilities to the other person.
Communicate plans via email, hard copy, or better still an informal
or formal chat where you discuss the project plan.
If the plan changes- communicate the changes with the project plan.
6. Tracking and Reporting Progress
Consider a 2-person project team- the Project Manager and one
other person.
The project Manager will need to know the progress of the activities
which the other person is working.
7. Change Management
Even on a small project- changes are likely to occur.
Requests for a change usually come from stakeholders and it will be
your responsibility as a Project Manager to assess the impact of
accepting these into the project.
Need to estimate the impact of the change in terms of extra effort
and cost.
Never simply accept the change. Need to fully understand what the
change is and the impact on time and cost.
8. Risk Management
There will be risks- even on a small project.
Ensure that you have thought through the potential risk and the
beginning of the project.
Monitor the risks, on a weekly basis.
Failing to manage risk properly is one of the main reason why
projects fail.
START-UP
If the project is typical, it has been “starting up” for some time- all
though the processes of project definition, acquisition, planning, and
contract negotiation. At this point, however, everything is ready to go, and
it’s time to start performing the contracted professional services.
3.c.1Team briefing and kick-off. One of the first steps is to be sure the
team members are on board and up-to-date with current project
requirements and plans, which may have changed in the negotiation
process. One way to accomplish this is to hold a formal team briefing and
kick-off meeting. Which may include the following elements:
Reviewing project requirements as developed with the client
and by the firm. This may cover project goals, scope, quality,
schedule, budget, codes and regulations, key design and
construction standards, and other project information.
Reviewing the project work plan. Critical tasks,
responsibilities, uncertainties and potential problem areas are
discussed.
Reviewing the schedule and milestone dates.
Reviewing project policies. These include (as relevant) project
responsibilities and authorities, client structure and relationships,
approaches to identifying and resolving problems, team
meetings an communications, project charges and reports, and
other key management ideas.
3.c.2Project Authorization. It is important to get internal mechanisms in
place. Once a proposal becomes a project, for example time changes are
no longer considered part of overhead (marketing costs) but are charged to
the project. Some firms use a formal project authorization form for the
following functions:
Establishing the necessary project accounts.
Providing information on what can be charged to the project and
what cannot, especially reimbursable (and non-reimbursable)
expenses.
Identifying the internal project reports that will be prepared and
distributed.
Providing the accounting department-or the bookkeeper or, in
small firms, the principal-with information about project
milestones deliverables, and billing details.
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Department of Architecture
T
he Project Control Lead/Manager would have his/her own team. Usually,
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Department of Architecture
you might see the team of Cost Estimators, Cost Controllers, and
Planner/Schedulers. Some companies might have Document Controllers
also under Project Controls.
According to the size and complexity of a project, the number of Project
Controllers assigned to a project varies. For example, if you are working on
a big major project, you might see several people working underneath the
Project
Control Lead/ Manager. If there’s a small project, then one or two people
might undertake the roles of several Project Controllers.
Regardless of the size of the Project Control team in a project, the Project
Control Lead/Manager reports directly to the Project Manager, and the
Project Control team interacts directly with all the other team members in
the project.
Since Project Controllers take control of the entire cost and schedule of the
project, they need to know for example how much the budget of the
electrical engineering team is in the project, how they are performing
against that budget, and when they are delivering their key milestones and
deliverable. Therefore, they keep the control and management of the cost
and schedule portion of the entire project. To do so, they need to have
interactions with almost all team members.
3.d.4 Project Controls team analyzes the data received from the
project team members and develops Project Plans, which usually
includes:
Project Cost Estimate
Project Budget
Budget allocation
Resource Plan
Project Schedule
WBS/ CBS
Cost/ Schedule Contingency Plan
Once the project’s cost and schedule are developed, the Project
Control team gets constant inputs from the project team and generate
different kinds of analytical reports such as:
Project Cost and Schedule status and performance
Project Cost and Schedule forecasts
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Department of Architecture
The Project Controls Plan should address the same components in the
Project Controls process plus the application of tools/ software.
Project Controls Plan Components
The following elements need to be addressed in the Project Controls
Plan:
RIZAL TECHNOLOGICAL UNIVERSITY
College of Engineering and Industrial Technology
Department of Architecture
Project Performance Assessment
How cost and schedule performance will be measured
What are the acceptable variance thresholds for project’s cost and
schedule
How project’s cost and schedule variances are measured
How cost forecasting is performed
How schedule analysis and forecasting is performed
Project Control Reporting & Communication
The scope, content, format, and responsibilities for the preparation,
submittal, and approval of the project reports.
Project reporting deliverables and frequency of reporting (Project
Reporting Calendar)
Project Controls meeting requirements and frequency of the
meetings
File structure for storing project files and information.
Project Controls outputs/ deliverables, required for the execution &
management of the project.
Tools/systems used for Project Controls reporting.