Substantial Completion Checklist: Project Number: Project Title: Agency: Contractor: Facility: Client Agency Rep
Substantial Completion Checklist: Project Number: Project Title: Agency: Contractor: Facility: Client Agency Rep
A/E* schedules an inspection with the Owner, E&AS PM, and Contractor to
inspect work and remaining punch list items. The A/E adds to contractor's punch
list, creates a single supplemental punch list, and provides to the contractor
8. within 2 business days.
9. Contractor establishes punch list completion schedule
If Prior Occupancy is established, per General Conditions Part 6.08, the areas of
10. prior occupancy are: ___________________________________
12. Notice from the A/E that the work is substantially complete
13. The E&AS PM and Owner determine the Substantial Completion date
14. Certificate of Substantial Completion issued and Warranty Period begins
Notes:
* If no there is no A/E for the project, the E&AS PM will complete Updated July 2019
DIVISION OF ENGINEERING & ARCHITECTURAL SERVICES
PROJECT TITLE:
CONTRACTOR:
A/E CONSULTANT:
OWNER/AGENCY:
DATE OF ISSUANCE:
Part 6, paragraph 6.07, of the General Conditions of the Contract. "Substantial Completion is the stage in the progress of the
Work (or portion thereof designated and approved by Owner) when the construction is sufficiently complete, in accordance
with the Contract Documents, so the Owner can fully occupy the Work (or the designated portion thereof) for the use for which
it is intended."
Work performed under this contract has been reviewed and to the best of our knowledge found to be substantially complete.
The Date of Substantial Completion for the work described above is hereby established as: _____________
The Contractor will complete or correct the work on the list of items attached hereto within _______ calendar days.
RECOMMENDED BY:
RECOMMENDED BY:
APPROVED BY:
ACKNOWLEDGED BY:
Items to be corrected: