No Kegiatan Tergantung Durasi (Minggu) ES EF Float Paling Awal Paling Akhir LS LF

The document provides information on a project with 12 activities (A-L) and their durations, dependencies, and costs. It includes a table with the activity relationships and asks to analyze the critical path, free float, total float, draw a bar chart based on late start and finish times, and draw an "S" curve.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
27 views4 pages

No Kegiatan Tergantung Durasi (Minggu) ES EF Float Paling Awal Paling Akhir LS LF

The document provides information on a project with 12 activities (A-L) and their durations, dependencies, and costs. It includes a table with the activity relationships and asks to analyze the critical path, free float, total float, draw a bar chart based on late start and finish times, and draw an "S" curve.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

2 6 8

4 B 7 10 F 19 19 H 34
10 13 13 22 22 37
3 9 15

9
19 I 23
33 37
1 3 5 4 12
0 A 0 4 C 10 11 E 18 37 L 47
0 0 7 13 11 18 37 47
4 6 7 10 10
28 J 35
30 37
7

4 7 11
4 D 11 18 G 28 28 K 37
4 11 18 28 28 37 Jalur Kritis =
7 10 9

Paling Awal Paling Akhir


No Kegiatan Tergantung Durasi (Minggu) ES EF LS LF Float
1 A - 4 0 0 0 0 0
2 B A,C 3 4 7 10 13 6
3 C A 6 4 10 7 13 3
4 D A 7 4 11 4 11 0
5 E A,D 7 11 18 11 18 0
6 F B,C 9 10 19 13 22 3
7 G D,E 10 18 28 18 28 0
8 H F 15 19 34 22 37 3
9 I F,H 4 19 23 33 37 14
10 J G,K 7 28 35 30 37 2
11 K G 9 28 37 28 37 0
12 L H,I,J,K 10 37 47 37 47 0
LATIHAN 1
Jika diketahui hubungan ketergantungan antara kegiatan seperti pada tabel, gambaran network
diagramnya dengan menggunakan AON. Hitung waktu penyelelesaian proyek, free float , total
float kemudian gambarkan lintasan kritisnya. Gambarkan pula diagram batang dari seluruh
kegiatan yang berdasarkan waktu paling lambat dan kemudian bentuk kurva "S"

Tabel 1. Hubungan Ketergantungan Antara Kegiatan


No Kegiatan Tergantung Durasi (Minggu) Biaya (juta)
1 A - 4 5
2 B A,C 3 13
3 C A 6 16
4 D A 7 11
5 E A,D 7 9
6 F B,C 9 7
7 G D,E 10 16
8 H F 15 20
9 I F,H 4 25
10 J G,K 7 6
11 K G 9 9
12 L H,I,J,K 10 8
Kegiatan Durasi (Minggu) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47
A 4
B 3
C 6
D 7
E 7
F 9
G 10
H 15
I 4
J 7
K 9
L 10
Kegiatan Bobot Kegiatan Minggu Ke -

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47
A 3,448 0,431 1,006 1,006 1,006

B 8,966 0,598 0,930 0,930 0,930 0,930 0,930 0,930 0,930 0,930 0,930

C 11,034 0,736 1,144 1,144 1,144 1,144 1,144 1,144 1,144 1,144 1,144

D 7,586 0,506 1,011 1,011 1,011 1,011 1,011 1,011 1,011

E 6,207 0,517 0,813 0,813 0,813 0,813 0,813 0,813 0,813

F 4,828 0,302 0,377 0,377 0,377 0,377 0,377 0,377 0,377 0,377 0,377 0,377 0,377 0,377

G 11,034 0,581 1,045 1,045 1,045 1,045 1,045 1,045 1,045 1,045 1,045 1,045

H 13,793 0,552 0,736 0,736 0,736 0,736 0,736 0,736 0,736 0,736 0,736 0,736 0,736 0,736 0,736 0,736 0,736 0,736 0,736 0,736

I 17,241 0,690 0,920 0,920 0,920 0,920 0,920 0,920 0,920 0,920 0,920 0,920 0,920 0,920 0,920 0,920 0,920 0,920 0,920 0,920

J 4,138 0,296 0,427 0,427 0,427 0,427 0,427 0,427 0,427 0,427 0,427

K 6,207 0,443 0,640 0,640 0,640 0,640 0,640 0,640 0,640 0,640 0,640

L 5,517 0,368 0,515 0,515 0,515 0,515 0,515 0,515 0,515 0,515 0,515 0,515

Total Bobot = 100,000

0,43 1,01 1,01 2,84 3,09 3,09 3,09 3,09 3,09 3,39 3,98 3,26 3,26 1,19 1,19 1,19 1,19 1,77 2,66 3,08 3,08 3,08 2,70 2,70 2,70 2,70 2,70 3,44 2,72 2,72 2,72 2,72 2,72 2,72 2,72 2,72 3,09 0,51 0,51 0,51 0,51 0,51 0,51 0,51 0,51 0,51 0,51
Bobot Rencana Kegiatan

0,43 1,44 2,44 5,29 8,37 11,46 14,54 17,63 20,72 24,10 28,08 31,35 34,61 35,80 36,99 38,18 39,37 41,14 43,81 46,88 49,96 53,04 55,74 58,44 61,14 63,84 66,54 69,98 72,70 75,43 78,15 80,87 83,59 86,32 89,04 91,76 94,85 95,37 95,88 96,40 96,91 97,43 97,94 98,46 98,97 99,49 100,00
Total Bobot Rencana Kegiatan