Bill of Materials

The document provides a bill of materials and cost estimates for the N.C. Yere Water Refilling Station project. It lists 11 categories of materials needed and their quantities, unit costs, and total costs. The total estimated cost of materials is PHP 296,341. Additional costs include PHP 88,902 for labor and PHP 385,243 as the total estimated direct cost.

Uploaded by

Brian Unciano
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
80% found this document useful (5 votes)
2K views2 pages

Bill of Materials

The document provides a bill of materials and cost estimates for the N.C. Yere Water Refilling Station project. It lists 11 categories of materials needed and their quantities, unit costs, and total costs. The total estimated cost of materials is PHP 296,341. Additional costs include PHP 88,902 for labor and PHP 385,243 as the total estimated direct cost.

Uploaded by

Brian Unciano
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Project: N.C.

Yere Water Refilling Station


Owner: Nestor C. Yere, Jr.
Location: Simpatuyo, Sta. Teresita, Cagayan

BILL OF MATERIALS

Description of Material Quantity Unit Unit Cost Total Cost


1. FOUNDATION CONCRETE
COLUMNS, BEAMS AND 134,170.00
CONCRETE HOLLOW
BLOCKS WALLS

Holcim Cement 297 Bag 150 44,550


River Sand 25 Cu.m. 250 6,250
Gravel 18 Cu.m. 200 3,600
Earth Fill 12 Cu.m. 80 960
CHB, 4” 560 Piece 11 6,160
CHB, 6” 1290 Piece 14 18,060
RSB, 12 mm 75 Piece 280 21,000
RSB, 10 mm 298 Piece 110 32,780
Wire no. 16 for Tying 27 Kilo 30 810

2. ROOF FRAMING (Truss,


Purlins and other roofing 15,000.00
materials)
3. ROOFING MATERIALS 13,760

Corrugated G.I. Sheet 45 L.Mtr 220 9,900


G.I. Ridge Roll (Typical) 9 L.Mtr 220 1,980
Vulcaseal Sealant 1 Piece 400 400
Ø3” x 10’ PVC Pipe 4 Piece 320 1,280
Ø3” x 10’ Elbows 4 Piece 35 140
PVC Solvent 1 Piece 60 60

4. PLUMBING FIXTURES AND


ACCESSORIES (Lump Sum 10,000
Estimates)

5. CEILINGS, FLOORS AND 37,425


OTHER INTERIOR WORKS

Typ. Ceramic Tile (40 x 40) 383 Piece 60 22,980


Ceiling joists (2” x 2” x 8’) 267 Bd-ft. 35 9,345
Ceiling (Long-span G.I. Sheet) 30 L.Mtr. 45 1,350
Sink Tiles (20x20) 105 Piece 30 3,150
Tile Grout 2 Kilo 150 300
Holcim Cement mortar 2 Bags 150 300

6. ELECTRICAL MATERIALS 5,000


(Lump Sum Estimates)
7. DOORS, WINDOWS AND
ACCESSORIES (Details in 23,000
drawings)

D-1 1 Piece 4,000


D-2 1 Piece 3,000
W-1 1 Piece 8,000
W-2 1 Piece 5,000
W-3 1 Piece 3,000

8. PAINTING MATERIALS
(Boysen Products) 7,800

Flat LATEX Paint 6 Galloon 550 3,300


Gloss Latex Paint (Finishing) 6 Galloon 750 4,500

9. CARPENTRY WORKS 16,569

2”x2”x12’Lumber 267 Bd.ft 35 9,345


4’x8’ ordinary plywood 21 Sheets 320 6,720
1” CW Nails 1.2 Kgs 120 144
Project: N.C. Yere Water Refilling Station
Owner: Nestor C. Yere, Jr.
Location: Simpatuyo, Sta. Teresita, Cagayan

2 ½” CW Nails 3 Kgs 120 360

10. SCAFFOLDINGS 13,617

2”x2”x12” Lumber 225 Bd.ft 35 7,875


4’8’ ordinary plywood 15 Sheets 320 4,800
#2 ½ CW nails 3.2 Kgs 120 384
#4 CW Nails 4 Kgs 120 480
Finishing nails 1.3 Kgs 60 78

11. MISCELLANEOUS
MATERIALS (Lump Sum 20,000
Estimates)

SUMMARY COST ESTIMATES FOR MATERIALS, LABOR AND OTHER CONSTRUCTION


EXPENSES

A. ESTIMATED COST OF MATERIAL (From the Bill of Materials) 296,341.00

1. FOUNDATION CONCRETE COLUMNS, BEAMS AND 134,170.00


CONCRETE HOLLOW BLOCKS WALLS
2. ROOF FRAMING 15,000
3. ROOFING MATERIALS 13,760
4. PLUMBING FIXTURES AND ACCESSORIES 10,000
5. CEILING, FLOORS AND OTHER 37,425
6. ELECTRICAL MATERIALS 5,000
7. DOORS, WINDOWS AND ACCESSORIES 23,000
8. PAINTING MATERIALS 7,800
9. CARPENTRY WORKS 16,569
10. SCAFFOLDINGS 13,617
11. MISCELLANEOUS MATERIALS 20,000

B. ESTIMATED COST OF LABOR (Including Supervision Fees) 88,902.3

ESTIMATED TOTAL DIRECT COST PHP 385,243.30

Prepared by: Approved:

ENGR. KEVIN CONDE NESTOR C. YERE, Jr.


Civil Engineer
Owner