NRN KNITTING & GARMENTS LTD - 7TH FUiN Electrical OA - 30072019
NRN KNITTING & GARMENTS LTD - 7TH FUiN Electrical OA - 30072019
On 18/01/2017: Not
Corrected.
On 18/04/2017:Not
corrected.
On 25/07/2017:Not
Corrected
Electrical Single
Amend Electrical SLD On 30/10/2017:Not
Line Diagram This issue under
properly. Mention all the corrected. SLD is available
(SLD) is not proccessing and hope
1 modification there as 3 Months but not as built. 22-Dec-2016 In Progress
amended fully it will be done
present in the factory, and On 14/05/2018:
properly & less within December-2018
get it reviewed by Accord. Not Corrected. SLD is not
informative.
as built.
On 13/02/2019:
Not corrected. Factory is
working on the issue.
On 30-Jul-2019:
Not Corrected.
Page 1 of 20
ELECTRICAL SAFETY FOLLOW UP INSPECTION REPORT (7th)
Maintenance
We are keeping
records don’t
On 18/01/2017:Not maintenance records
reflect actual Maintenance Manager or
Corrected. accurately which reflect
factory Safety Officer must keep
On 18/04/2017:Not actual factory day to day
circumstances; accurate records and ensure
2 2 Months corrected. 22-Nov-2016 operations. Yet it is not Corrected
the records do that they reflect actual
On 25/07/2017:Not accepted to ACCORD.
not detail out all factory day to day
Corrected So expect a clear
the electrical operations.
On 30/10/2017:Corrected. guideline/ format from
equipment/
ACCORD.
machinery
On 18/01/2017:Not
Corrected.
On 18/04/2017:Not
corrected.
On 25/07/2017:Not
Corrected
On 30/10/2017:Not
Factory's service
corrected. No initiative has
cables are Use metallic cable This issue under
been taken yet.
hanging without tray/ladder to support proccessing and hope
3 3 Months On 14/05/2018: 22-Dec-2016 In Progress
support. Cable cables at anywhere to keep fully it will be done
Not Corrected. Factory is
terminals may be cable out of tension within December-2018
not using this line but it is
in tension
live. REB will remove that
cable.
On 13/02/2019:
Not corrected. Factory is
working on the issue.
On 30-Jul-2019:
Not Corrected.
On 18/01/2017:Not
Corrected.
On 18/04/2017:Not
Identify the cause of hot corrected.
Hot spots
spots and take action On 25/07/2017:Not
observed at
accordingly. Do periodic Corrected We have already done
4 terminations Immediate 29-Sep-2016 Corrected
test for your whole On 30/10/2017:Not the issue.
inside panel, (154
electrical system. A test corrected. No records
degree Celsius)
must be done bi-annually. found to rectify hotspots.
On 14/05/2018:
Corrected. No hotspot
found during inspection.
On 18/01/2017:Not
Corrected.
On 18/04/2017:Not
corrected. Major
renovation work is going
Insufficient
Ensure adequate working on. Conditions remain the
maintenance We have already done
5 clearance (at least 1.07m) 3 Months same. 22-Dec-2016 Corrected
clearance around the issue.
around (each) generator. On 25/07/2017:Not
the generator.
Corrected
On 30/10/2017:Not
corrected. Major
renovation work is going
on. Conditions remain
On 18/01/2017:Not
Corrected.
On 18/04/2017:Not
corrected.
On 25/07/2017:Not
Corrected
On 30/10/2017:Not
Use cable tray/ladder for corrected. Major
Power cables are ensuring cable support and renovation work is going
directly laid on protection. Route in such on. Conditions remain We have already done
6 2 Months 22-Nov-2016 In Progress
the floor without way that no damage can be same. the issue.
any support. done by personnel On 14/05/2018:
movement Not Corrected. Newly laid
cable from LT panel.
On 13/02/2019:
Not corrected. Factory
resolved the issue at several
places.
On 30-Jul-2019:
Not Corrected.
On 18/01/2017:Not
Corrected. No earthing at
generator body.
Ensure minimum two On 18/04/2017:Not
Generator body earthing connection for corrected.
has been earthed generator body & use 10-12 On 25/07/2017:Not
We have already done
7 by inadequate/ mm (dia) bare copper 1 Months Corrected 22-Oct-2016 Corrected
the issue
improper sized conductor for earthing or On 30/10/2017:Not
(type) cable consult with your generator corrected. Major
manufacturer renovation work is going
on. Conditions remain
same.
On 14/05/2018:
On 18/01/2017:Not
Corrected.
On 18/04/2017:Not
corrected.
On 25/07/2017:Not
Corrected. No of earth pits
are inadequate.
On 30/10/2017:Not
Identify each earth pit and
corrected. No initiative has
mark it for periodic
Earth pits are not been taken yet. Moreover,
maintenance purpose.
identifiable and earth pit resistance record We have already done
10 Increase the number of 3 Months 22-Dec-2016 In Progress
no of earth pits is unavailable. the issue
earth pits for better
are inadequate. On 14/05/2018:
performance of the
Not Corrected. Earth pit
electrical system.
numbers are still
inadequate.
On 13/02/2019:
Not corrected. New Earth
pits are made. But
identification are not done.
On 30-Jul-2019:
Not Corrected.
On 18/01/2017:Not
Corrected.
On 18/04/2017:Not
corrected.
Connect and ensure all the
Manually On 25/07/2017:Not
manually operated
operated Corrected We have already
12 machines with earth using 1 Months 22-Oct-2016 Corrected
machines have no On 30/10/2017:Not completed the issue.
appropriate sized earth
earth connection corrected. Still found few
cables.
machines are without earth
connection.
On 14/05/2018:
Corrected.
On 18/01/2017:Not
Corrected.
On 18/04/2017:Not
Adjust or replace all the
Oversized circuit corrected.
MCCBs/MCBs according
breakers or On 25/07/2017:Not
to cable ampacity We have already
13 Circuit breakers 2 Months Corrected 22-Nov-2016 Corrected
(connected load). Avoid completed the issue.
are not adjusted On 30/10/2017:Not
using different sized cable
accordingly. corrected. Still found at
at the terminals.
some points.
On 14/05/2018:
Corrected.
Cables
On 18/01/2017:Not Construction work of
terminated at
Terminate all the Corrected. generator room is
electrical bus
17 power/earth/neutral cable 1 Months On 18/04/2017:Not 22-Oct-2016 almost finished & we Corrected
bar/MCCB
with proper sized cable lug. corrected. will done within the
without cable
On 25/07/2017:Corrected mention time.
lugs.
On 18/01/2017:Not
Corrected.
On 18/04/2017:Not
corrected.
Organize all the power On 25/07/2017:Not
Cables inside
cables securely inside Corrected
distribution We have already done
19 distribution board thus no 1 Months On 30/10/2017:Not 22-Oct-2016 Corrected
board is the issue
chance of any electrical corrected. Major
disorganized.
hazard. renovation work is going
on. Conditions remain
same.
On 14/05/2018:
Corrected.
On 18/01/2017:Not
Corrected.
On 18/04/2017:Not
corrected.
On 25/07/2017:Not
Corrected
Electrical sockets
Proper typed flexible cable On 30/10/2017:Not
are hanged for This issue under
with secured socket corrected. No initiative has
powering cutting proccessing and hope
20 (Covered) must be used for 2 Months been taken yet. 20-Nov-2016 In Progress
machine using fully it will be done
any kind of manual On 14/05/2018:
improper type within December-2018
operated machine. Not Corrected.
power cable.
On 13/02/2019:
Not corrected. Factory
solved the issue at several
floors.
On 30-Jul-2019:
Not Corrected.
On 18/01/2017:Not
Corrected.
On 18/04/2017:Not
corrected.
On 25/07/2017:Not
Corrected
On 30/10/2017:Not
corrected. LPS drawing is
Lightning Design LPS for your available but not installed
This issue under
Protection factory building following yet, vertical extension is
proccessing and hope
21 System (LPS) has local or international 4 Months going on. 22-Jan-2017 In Progress
fully it will be done
not been installed standard. Then install it on On 14/05/2018:
within December-2018
yet your building. Not Corrected. Not
installed due to
construction work.
On 13/02/2019:
Not corrected. Installation
done but needs several
modification.
On 30-Jul-2019:
Not Corrected.
NRN KNITTING & GARMENTS LTD Page 10 of 20
ELECTRICAL SAFETY FOLLOW UP INSPECTION REPORT (7th)
On 18/04/2017:Not
corrected.
On 25/07/2017:Not
Corrected. Details of
training module is required.
On 30/10/2017:Not
Electrical safety training
corrected. Safety program
New Finding: and awareness program for
is initiated but has no
Electric safety the electrical personnel
influence in the factory.
training program must be initiated. It is a We have already done
22 1 Month On 14/05/2018: 28-Feb-2017 In Progress
has not periodic task which factory the issue
Not Corrected. Need detail
initiated/conduct has to continue to improve
training manual on each
ed. overall electrical safety
topic and also practice it in
situation for the staffs.
the field.
On 13/02/2019:
Not corrected. Practical
implementation is needed.
On 30-Jul-2019:
Not Corrected.
On 18/04/2017:Not
corrected.
On 25/07/2017:Not
New Finding: Corrected
Splicing in the power cables
Cables in service On 30/10/2017:Not
shall be avoided; in
are joined corrected. We have already done
24 unavoidable cases splicing, 1 Month 28-Feb-2017 In Progress
(splicing) On 14/05/2018: the issue
must be made following
between Not Corrected.
proper guidance.
terminations. On 13/02/2019:
Not corrected
On 30-Jul-2019:
Not Corrected.
New Finding:
Indicator lights should be
Indicator lights On 18/04/2017:Not
connected by control We have already done
25 are mounted 1 Month corrected. 28-Feb-2017 Corrected
device such as rated fuse or the issues.
without control On 25/07/2017:Corrected
MCB.
device.
On 30/10/2017:Not
corrected.
New Finding: On 14/05/2018:
This issue under
Periodicity of Thermography survey must Not Corrected. Not done
proccessing and hope
30 Thermography be done and recorded at 1 Month yet. 05-Sep-2017 In Progress
fully it will be done
survey is not least twice in a year. On 13/02/2019:
within November-2018
continued. Not corrected
On 30-Jul-2019:
Not Corrected.
On 30/10/2017:Not
corrected. No initiative has
Adequate number of earth
been taken yet. Moreover,
pits must be ensured for
New Finding: earth pit resistance record
the factory with proper This issue under
Number of earth is unavailable.
earth lead and earth proccessing and hope
31 pits are 2 Months On 14/05/2018: 05-Oct-2017 Corrected
electrode size as mentioned fully it will be done
inadequate for Not Corrected.
in BNBC requirements. within November-2018
the factory On 13/02/2019:
mixing all together shall be
Not corrected
avoided.
On 30-Jul-2019:
Corrected.
On 30/10/2017:Not
New Finding:
corrected.
There is no
An electrical maintenance On 14/05/2018:
programmed
program shall be prepared Not Corrected. Need to
schedule for
which will include maintain proper schedule We have already done
32 periodical 1 Month 05-Sep-2017 In Progress
inspections and testing of and checklist. the issue
inspection &
the electrical systems On 13/02/2019:
testing of
(preventive and proactive) Not corrected
electrical
On 30-Jul-2019:
equipment.
Not Corrected.
On 14/05/2018:
Power cables must be
New Finding: Not Corrected. This issue under
supported by cable tray
Power Cables are On 13/02/2019: proccessing and hope
33 (ladder- where needed). 1 Month 30-Nov-2017 In Progress
hanging without Not corrected fully it will be done
Outdoor arrangement must
proper support. On 30-Jul-2019: within December-2018
be covered.
Not Corrected.
On 13/02/2019:
New Finding: Use insulated rubber cap to
Not corrected We have already done
35 Battery terminals cover all the battery 1 Month 25-Jun-2018 Corrected
On 30-Jul-2019: the issue
are left open terminals
Corrected.
New Finding:
All distribution boards,
Distribution On 13/02/2019:
switchboards, sub main
boards have no Not corrected We have already done
38 boards and switches shall 1 Month 25-Jun-2018 In Progress
clear On 30-Jul-2019: the issue
be marked clearly for
identification Not Corrected.
proper identification.
markings.
New Finding:
No working
A working separation
separation
between LT and HT must
between LT (
be ensured. A brick wall
Low Tension) On 30-Jul-2019:
40 will do it; and adequate 2 Months 30-Apr-2019 In Progress
panel/s and HT Not Corrected.
working clearance (1.07m)
(High Tension)
and ventilation must be
unit/s
ensured.
(Transformer,
HT switchgear)
New Finding:
Transformer Oil Transformer oil test
Test (dielectric (dielectric strength test for
42 1 Month 19-Sep-2019
strength test) oil) shall be done once in a
report is year.
unavailable.
New Finding:
Exhaust fan frame and its
Exhaust fan body
enclosure in the production
43 and fan blade 1 Month 19-Sep-2019
area/s shall be connected
enclosure has no
to earth.
earth connection.
New Finding:
Multiple cables
Each power cable must be
connected/termi
45 terminated at any point 1 Month 19-Sep-2019
nated at the bus
using single cable lug.
bar using single
cable lug.
New Finding:
Service cables from
Generator output
generator must be
cables (laid on
46 supported at its own 1 Month 19-Sep-2019
floor) are not
breaker's terminal and with
protected and
cable tray.
supported.