Mod3 Feasibility Study Guidelines
Mod3 Feasibility Study Guidelines
Feasibility Study
January 2015
January 2015
INTRODUCTION
If the District has completed all tasks defined in Module 1 – Eligibility Period and Module
2 – Forming the Project Team, the District may now proceed with the Feasibility Study
as outlined in this Module. Module 3 – Feasibility Study is one of eight MSBA modules
intended to provide a guide to the procedures and approvals needed to work
collaboratively with the MSBA. (The Program Overview and listing of eight modules is
provided in Appendix 3A for reference.)
During the Feasibility Study, the District and its team collaborate with the MSBA to
generate an initial space summary based on the District’s educational program,
document existing conditions, establish design parameters, develop and evaluate
preliminary and final alternatives, and recommend the most cost effective and
educationally appropriate solution to the MSBA Board of Directors. The MSBA Board of
Directors must approve the preferred solution for a project before the preferred solution
may advance into schematic design. See this Module for additional detail.
Module 3 has been provided as a general guide for Districts and their teams to plan their
work in a collaborative effort in accordance with the MSBA’s procedures and
requirements. This Module is not intended to replace and/or supersede the services
required by the OPM and/or Designer contracts. The Designer and OPM each shall be
solely responsible for performing the services required by its contract with the District,
respectively, and nothing in this Module shall be construed as relieving the Designer or
OPM from its duties and responsibilities.
• The Designer as selected locally by the District and approved by the MSBA for
projects estimated to cost less than $5 million or as selected through the MSBA’s
Designer Selection Panel for projects estimated to cost more than $5 million.
• The MSBA, through the assigned MSBA Project Manager and Project
Coordinator.
For each submittal to the MSBA, the Designer and District must submit the required
materials to the OPM. The OPM shall compile the submittal with the items indicated in
the Designer and OPM Contracts, confirm that the District’s School Building Committee
has officially approved the submittal and verify its completeness and conformity to MSBA
requirements. The OPM shall then forward this submittal to the assigned MSBA Project
coordinator under a separate cover letter signed by the OPM, including a certification
from the OPM that the OPM has reviewed and coordinated the materials, and the
submittal is complete, and a confirmation that the District has approved the materials
for submission to the MSBA, in accordance with the OPM Contract which requires the
OPM to assist the Owner in the preparation of all information, material, documentation
and reports that may be required or requested by the Authority.
Preliminary Design Program – Submit one (1) binder with a hard-copy of materials
including one (1) electronic file in PDF format.
Preferred Schematic Report – Submit one (1) binder of materials per this Module
including conceptual floor plans not exceeding 18” x 24”, and one (1) electronic file in
PDF format.
Incomplete submittals or submittals not reviewed by the OPM will not be accepted.
Partial submittals will not be accepted without prior approval by the MSBA.
TABLE OF CONTENTS
3.1.1 Introduction
3.1.2 Educational Program
3.1.3 Initial Space Summary
3.1.4 Evaluation of Existing Conditions
3.1.5 Site Development Requirements
3.1.6 Preliminary Evaluation of Alternatives
3.1.7 Local Actions and Approvals
3.3.1 Introduction
3.3.2 Evaluation of Existing Conditions
3.3.3 Final Evaluation of Alternatives
3.3.4 Preferred Solution
3.3.5 Local Actions and Approvals
APPENDICES
After all tasks defined in Module 1 – Eligibility Period and Module 2 – Forming the Team
have been completed by the District and acknowledged by the MSBA, a District may
proceed with the Feasibility Study. Please remember that an invitation from the MSBA’s
Board of Directors to collaborate on a Feasibility Study is not approval of a project. The
purpose of the Feasibility Study is for the District, its Owner’s Project Manager (“OPM”)
(for projects with estimated construction costs in excess of $1.5 million), its Designer,
and the MSBA to explore potential solutions that meet the requirements of the District’s
Educational Program, and to determine the most cost effective and educationally
appropriate solution to recommend to the MSBA Board of Directors for its consideration
and approval to proceed into schematic design. Moving forward in the MSBA’s process
requires collaboration with the MSBA, and communities that “get ahead” of the MSBA
without MSBA approval will not be eligible for grant funding. To qualify for any funding
from the MSBA, local communities must follow the MSBA’s statute and regulations,
which require MSBA collaboration and approval at each step of the process.
Due to the variety and nature of proposed appropriate solutions (e.g., non-construction
alternatives such as redistricting, grade reconfigurations, repairs to a single building
system, renovations to the entire facility, an addition, or a new school ), each Feasibility
Study will vary slightly as to the specific requirements, scope, cost and schedule. The
particular requirements, scope, cost and schedule of a Feasibility Study will be outlined
in the Feasibility Study Agreement between the District and the MSBA. The requirements
may be based on many factors including the MSBA’s review and evaluation of any
previous studies as well as any meetings and discussions between the District and the
MSBA.
In order to ascertain MSBA input and approval throughout the Feasibility Study process,
the District is required to secure MSBA concurrence and/or approval of each of the
following study reports before finalizing and submitting the next report:
The OPM shall prepare and provide a work plan to the Owner and Authority within
twenty-one (21) days of Design Contract execution.
The Preliminary Design Program shall be provided in the form of a binder with the
following clearly labeled tabs:
• Table of Contents
• Introduction
• Educational Program
• Initial Space Summary
• Evaluation of Existing Conditions
• Site Development Requirements
• Preliminary Evaluation of Alternatives
• Local Actions and Approval Certification
• Appendices
3.1.1 Introduction
The Introduction shall present a brief overview of the reason for the Feasibility Study, a
list of all project participants, an outline of key data that informs the basis of the Study,
and a summary of the process undertaken to examine, analyze, and conclude upon the
findings of this Preliminary Design Program. The following shall be included:
when developing the project schedule. A sample Project Schedule that includes
major project milestones has been provided for reference in Appendix 3B.
The District will work with the Designer to document the existing educational program
offered by the District and to define the proposed educational activities. The Preliminary
Design Program must include documentation of the District’s existing educational
program, and new or expanded educational specifications if applicable. While developing
the Educational Program, the District and the Designer should review the Educational
Profile Questionnaire that was completed by the District during Eligibility Period. The
Preliminary Design Program must include the process of collaboration, outcomes, and
documentation of support among the stakeholders.
The Educational Program shall include a statement of the teaching philosophy and
methods; a thorough, in-depth explanation of the District’s curriculum goals; and,
objectives of the program elements associated with the subject facility. Through the use
of narratives, figures, and charts, the Educational Program shall describe and include,
but not necessarily be limited to, the following as it relates to the current program,
facility needs and proposed design features:
Based upon the District’s Educational Program as described above and the agreed-upon
enrollment, the District, working with its Designer, must complete the Initial Space
Summary to identify the educational spaces the District believes are needed to deliver its
Massachusetts School Building Authority Module 3 – Feasibility Study
-6-
January 2015
educational program. Once agreed upon by the MSBA, this Initial Space Summary will
help inform the development of alternatives to be studied, upon which the most
educationally appropriate and cost effective solution may be recommended.
The Initial Space Summary must be based on the agreed-upon design enrollment,
supported by the District’s Educational Program and must include the following:
• An itemization of each existing educational space;
• The total gross square footage of the existing facility;
• An itemization of each proposed educational space; and
• A total gross square footage for the proposed renovated/added-to/new facility.
MSBA regulations, 963 CMR 2.00, establish allowable gross square footage per student
for different types of school facilities of varying scale. To assist Districts and their design
teams in developing proposed Initial Space Summaries, the MSBA has created space
summary templates (in Excel format), one each for elementary, K-8, middle, and high
schools. Each template includes three separate columns as follows:
• The first column documents existing conditions;
• The second column documents proposed spaces subdivided by existing spaces
proposed to remain, new spaces, and total; and
• The third column is the MSBA’s guidelines. Other than inserting the agreed upon
enrollment at the bottom, this column is not to be altered.
The Designer will analyze existing conditions of all buildings that comprise the school,
site, and environment. The Designer will assemble sufficient information on the
problems and opportunities with the existing school building(s) and site, so that any
major implications for future requirements and design can be accurately judged. This
information is required to be of a level sufficient enough to assist in the development of
the preliminary alternatives to be evaluated and must include, at a minimum, an outline
of the potential scope, budget, and schedule impacts. The information should include
the following:
• Determination that the District has legal title to the property, or alternatively, the
required actions necessary to obtain clear title or to control, in accordance with
the provisions of 963 CMR 2.05(1), and operate the Assisted Facility and Project
Site for the useful life of the Assisted Facility;
• Determination that the property is available for development;
• Determination of any historic registrations and/or potential local and/or state
interest/requirements regarding historic preservation or infill construction within
a historic district and the associated potential impact on scope and time;
• Determination of any development restrictions that may apply;
• Initial Evaluation of building code compliance for the existing facility;
• Initial Evaluation of Architectural Access Board Rules and Regulations and their
application to a potential project;
• Preliminary Evaluation of significant structural, environmental, geotechnical or
other physical conditions that may impact the cost and evaluation of alternatives;
• Determination for need and schedule for soils exploration and geotechnical
evaluation;
• Environmental site assessments consisting of, at a minimum, a Phase I: Initial
Site Investigation conforming to 310 CMR 40.00, et seq. performed by a licensed
site professional. (Results of the Phase I investigation may require additional
environmental testing); and
• Assessment of the school for the presence of any hazardous materials including,
but not necessarily limited to, lead, lead paint, PCBs, mercury, radon, mold and
asbestos. Destructive testing may be required where hazardous materials
potentially exist behind and within existing construction.
The District will furnish the Designer with all available studies, drawings, surveys,
photographs and subsoil exploration reports of the proposed project's existing buildings
(if any) and the site or sites.
The Designer shall include in the Preliminary Design Program Report a clear, written
statement of the methods and assumptions of, and limitations on the accuracy of, any
information provided. The Designer shall recommend during the course of the Feasibility
Study what further investigatory work should be carried out prior to recommending an
option as the Preferred Solution and what work should be carried out prior to submittal
of the Schematic Design.
In narrative form, the Designer shall describe in general terms project requirements
related to site development to be considered during the preliminary and final evaluation
of alternatives and submit an existing site plan(s) including, but not limited to:
• Structures and fences;
• Site access and circulation;
• Parking and paving;
• Code requirements;
• Zoning setbacks and limitations;
• Accessibility requirements;
• Easements;
• Wetlands and/or flood restrictions;
• Emergency vehicle access;
• Safety and security requirements;
• Utilities;
• Athletic fields and outdoor educational spaces; and
• Site orientation and other location considerations and issues.
Based upon the Educational Program, Initial Space Summary, evaluation of existing
conditions, and site development requirements, the District, working with its Designer,
shall perform a preliminary evaluation of alternatives. To ensure that the Feasibility
Study determines the most cost effective and educationally appropriate solution that can
be supported by the community and the MSBA Board of Directors, it is imperative that
the preliminary evaluation of alternatives is sufficiently comprehensive in scope to
initially consider all possible solutions. Each alternative should satisfy significant
components of the Educational Program, Standards, Policies and Guidelines of the MSBA
to the extent feasible, unless specifically authorized in writing by the MSBA.
The Preliminary Evaluation of Alternatives shall conclude with a list of at least three
distinct alternatives (including at least one renovation and/or addition option that
maximizes use of the existing facility) that are recommended for further development
and evaluation during the Final Evaluation of Alternatives. Alternatives shall retain the
same title and designation between PDP, PSR, and SD submittal, therefore maintaining
clarity in the documentation.
If the Preliminary Design Program does not include conceptual cost estimates or a list of
at least three district alternatives that are being recommended for further development
the MSBA will consider the submittal incomplete and will withhold MSBA review
comments until submitted.
The Preliminary Design Program, as with other submittals to the MSBA, must be
reviewed and approved locally for submittal to the MSBA, in accordance with the state
open meeting law and any other local requirements. Public participation and local
approval procedures and practices may vary by community and by project. Districts are
encouraged to consult with their local counsel to ensure that all applicable requirements
are satisfied. The District must document local approval of the Preliminary Design
Program and its submittal to the MSBA. The MSBA requires Districts to provide a
certified copy of Minutes of the School Building Committee (“SBC”) meeting(s) where
the Feasibility Study related submittals were approved for submittal to the MSBA. The
Minutes must include the specific language of the vote and the results of the vote,
stating the number of SBC members who voted in favor of submittal to the MSBA, the
number opposed, and the number of abstentions, if any.
The District also must list the relevant SBC meeting dates; provide copies of the
agendas of such meetings; briefly describe the materials presented, if applicable; list the
names and affiliations of specific stakeholders in attendance (e.g., representatives of the
local historic commission, school committee members beyond those in the SBC, local
community group representatives, etc.); and, list what materials are available for public
review and where those materials may be viewed. The MSBA also requires Districts to
Refer to Appendix 3D Local Actions and Approvals Certification Template for additional
information. A signed Local Actions and Approvals Certification on District letterhead is
required for MSBA staff to provide review comments regarding the District’s Preliminary
Design Program or to consider inviting the District to present its proposed project to the
MSBA Facilities Assessment Subcommittee.
After a District has submitted a complete Preliminary Design Program that meets the
requirements set forth above, the MSBA will review the Program to determine if it
concurs with the Initial Space Summary, the preliminary evaluation of alternatives and if
it accepts the District’s recommendation of proposed preliminary alternatives to be
further studied as part of the Final Evaluation of Alternatives.
Initial Space Summary:
The MSBA will provide a written response that: provides the MSBA’s evaluation of the
extent to which the initial space summary conforms to the MSBA guidelines and
regulations; states the approval status of the proposed initial space summary; and, if
applicable, lists the specific conditions that the MSBA will be monitoring as the
Statement of Interest moves forward in the grant process.
The MSBA is committed to working with Districts to determine the most cost effective
and educationally appropriate solution to meet their specific needs. To this end, the
MSBA is willing to work with a District to better understand its Educational Program and
any unique needs the District may have. As part of the Preliminary Design Program, the
District should supply a sufficient description and substantiation of the educational
program needs in order for the MSBA to consider variations to MSBA guidelines that are
reasonable, required to deliver the educational curriculum and are likely to be financially
supported by the community. To bolster the likelihood of success, foster a clear
understanding of the MSBA’s willingness to financially participate and define the
conditions upon which alternatives will be developed, it is essential that the MSBA and
the District reach agreement on the initial space summary. Therefore, MSBA approval of
the initial space summary, or potentially a conditional approval, is required for the MSBA
to continue working with the District on the Preferred Schematic Report. The MSBA may
issue a conditional approval of the initial space summary solely for the purposes of
evaluating the preliminary and final alternatives. The final approval of the space
summary and the agreed upon square footages will be determined upon submission of
the Preferred Schematic Report.
Preliminary Evaluation of Alternatives:
The MSBA will review the District’s Preliminary Evaluation of Alternatives to determine if
it is sufficiently comprehensive in scope to initially consider all appropriate solutions that
could be supported by the community and the MSBA Board of Directors for a continued,
more comprehensive, investigation during the Final Evaluation of Alternatives in the
Preferred Schematic Report. The District and the MSBA must agree that the Preliminary
Evaluation of Alternatives is sufficiently comprehensive and represents a scope of work
that is mutually agreeable to both the MSBA and the District to continue working on the
Massachusetts School Building Authority Module 3 – Feasibility Study
- 11 -
January 2015
The purpose of the Preferred Schematic Report is tosummarize the process and
conclusions of the Preliminary and Final Evaluation of Alternatives and substantiate and
document the District’s selection and recommendation of a preferred solution. The
Report should address all concerns and questions raised by the MSBA during its review
of the Preliminary Design Program and clearly identify any changes incorporated by the
District based on further evaluations and considerations.
The District, through its OPM, must submit the Preferred Schematic Report by the
deadline established by the MSBA for a proposed Board action. This schedule is posted
on the MSBA website and should have been incorporated as part of the updated
schedule required in part 3.1.1 of the Preliminary Design Program.
The Preferred Schematic Report shall be provided in the form of a binder with the
following clearly labeled tabs:
• Table of Contents;
• Introduction;
• Evaluation of Existing Conditions;
• Final Evaluation of Alternatives;
• Preferred Solution; and
• Local Actions and Approval Certification
The Preferred Schematic Report shall also be provided as an electronic file in PDF
format. Conceptual Floor Plans and Existing Conditions Plans may be provided in half-
sized (18” x 24”) drawings for legibility when necessary.
3.3.1 Introduction
The Introduction shall summarize the process and conclusions of this Preferred
Schematic Report and shall include:
Refer to the Preliminary Design Program and describe in narratives and graphic form
any changes resulting from additional evaluation or new information that informs the
evaluation of the existing conditions and its impact on the final evaluation of
alternatives. If the changes are substantive, provide an updated Evaluation of Existing
Conditions and identify as final. Identify additional testing that is recommended during
futures phases of the proposed project and indicate when the investigations and analysis
will be completed.
The Final Evaluation shall include at least three potential alternatives. Unless specifically
approved in writing by the MSBA, at least one of the three potential alternatives shall be
renovation and/or addition to existing building(s) that maximizes use of the existing
facility. Include the following for each alternative where appropriate:
The Final Evaluation of Alternatives shall be presented in detailed narratives and tables
as appropriate to present clearly how and to what degree each alternative addresses
each evaluation criteria and shall include a cost comparison table in the format
presented below. This excel file will be provided to the OPM upon request and must be
presented to MSBA in the original format shown below. All construction costs shall
represent marked up construction costs, and costs not directly associated with building
costs shall be described as to what is included (e.g., building demolition/take down, site
costs, hazardous material abatement etc.).
Option4B*** X X X sf X X X sf X X X sf $ $ $
(New ) $/ sf $/ sf $/ sf
Describe the District’s preferred solution using narrative, figures, and charts including:
how the preferred solution meets the District’s educational program, key educational
adjacencies, programmatic spaces, conceptual floor plan(s), site plan(s), and updated
project schedule.
• Educational Program
o Provide an updated Educational Program that addresses all questions and
comments included in the MSBA Preliminary Design Program review.
o Summary of key components of the District’s Educational Program and
how the preferred solution fulfills the stated Educational Program
requirements.
o If the District’s preferred solution is based on a grade configuration that is
different than the District’s existing configuration this section of the
Preferred Schematic Report must include a description of the following
through the use of narratives, figures, and charts:
Current grade configuration and key program elements;
Proposed grade configuration and key program elements;
Variances between the current and proposed grade
configurations;
Educational benefits of changing from the current grade
configuration to the proposed configuration; and
Transition plan including major milestones, staffing, and
community outreach.
o An itemization of the total proposed educational space and the total net
and gross square footage and grossing factor of the proposed facility;
and
o An itemization of the MSBA’s guidelines and the total net and gross
square footage, agreed upon student enrollment, and grossing factor.
Other than inserting the agreed upon enrollment at the bottom, this
column is not to be altered.
• Describe the reason for any variation between the Initial Space Summary and
written comments provided by the MSBA as part of its review of the Preliminary
Design Program.
• Sustainability Documents:
o Completed sustainability scorecard from the Designer showing the
attempted credits to be included in the final design; and
o Signed letter from the Designer including the following statements:
“This is an acknowledgement that the ___________School District
has identified a goal of ____% additional reimbursement from the
MSBA High Efficiency Green School Program. As their Designer, I
have submitted a completed ____________scorecard showing all
prerequisites and ____ attempted points, which will meet that
goal.”
“The scope of work for this project will include the construction
elements and performance tasks to achieve that goal, and all
subsequent documents, including but not limited to, specifications,
drawings, and cost estimates will match the scope of work
indicated in the submitted scorecard.”
• Building Plans - Provide conceptual floor plans of the preferred solution, in color
that are clearly labeled to identify educational spaces in the preferred solution.
• Site Plans - Provide clearly labeled site plans of the preferred solution including,
but not limited to:
o Structures and boundaries;
o Site access and circulation;
o Parking and paving;
o Zoning setbacks and limitations;
o Easements and environmental buffers;
o Emergency vehicle access;
o Safety and security features;
o Utilities;
o Athletic fields and outdoor educational spaces (existing and proposed);
and
o Site orientation.
• Budget - Provide an overview of the Total Project Budget and local funding
including the following:
o Estimated total construction cost;
o Estimated total project cost;
o Estimated funding capacity;
o List of other municipal projects currently planned or in progress;
o District’s not-to-exceed Total Project Budget;
o Brief description of the local process for authorization and funding of the
proposed project; and
o Estimated impact to local property tax, if applicable.
• Complete and submit a budget statement for the preferred solution. The overall
goal of the budget statement for preferred solution is to document the total
change in operational costs that the District expects as a result of the proposed
project. To assist in documenting this change the MSBA has developed an Excel
template that includes two tabs, one for expenditures and one for revenues.
Refer to Appendix 3E Budget Statement for Preferred Solution for additional
information
• Provide an updated project schedule depicting all key tasks with durations. The
schedule is to be updated and submitted by the OPM to MSBA as often as is
required to reflect any changes, including any changes to milestone dates, but
must be submitted with each submittal (Schematic Design, Design Development,
60% Construction Documents, 90% Construction Documents). The Schedule is
to incorporate a minimum of 21 day required duration for MSBA review, and a
minimum of 14 days for the project team to address or incorporate MSBA review
comments into the project documents prior to the date of the next submission
and before finalizing project documents for bidding. Thirty five days for each
submission is the minimum acceptable duration; if the project team believes
additional time is required for any or all of the submissions the durations for
these activities are to be increased accordingly. The updated project schedule
shall include as a minimum the following projected dates: (See Appendix 3B for a
Sample Project Schedule)
o MSBA Board of Directors meeting for approval to proceed into Schematic
Design;
o Schematic Design Submittal Date
o MSBA Board of Directors meeting for approval of project scope and
budget agreement and project funding agreement;
o Town/City vote for project scope and budget agreement;
o Design Development submittal date;
o MSBA Design Development Submittal Review (include required 21-day
duration)
o 60% Construction Documents submittal date;
o MSBA 60% Construction Documents Submittal Review (include required
21-day duration)
o 90% Construction Documents submittal date;
o MSBA 90% Construction Documents Submittal Review (include required
21-day duration)
o Anticipated bid date/GMP execution date;
o Construction start;
o Move-in date; and
o Substantial completion.
The Preferred Schematic Report, as with other submittals to the MSBA, must be
reviewed and approved locally for submittal to the MSBA, in accordance with the state
Massachusetts School Building Authority Module 3 – Feasibility Study
- 17 -
January 2015
open meeting law and any other local requirements. Public participation and local
approval procedures and practices may vary by community and by project. Districts are
encouraged to consult with their local counsel to ensure that all applicable requirements
are satisfied.
To document local approval of the Preferred Schematic Report and its submittal to the
MSBA, the MSBA requires the District to provide:
• Certified copies of the Minutes of the School Building Committee (“SBC”) meeting
from the meeting(s) where the Feasibility Study related submittals were
approved for submittal to the MSBA. The meeting minutes must include the
specific language of the vote and the results of the vote, stating the number of
SBC Members who voted in favor of submittal to the MSBA, the number of
opposed and the number of abstentions; and
• A list SBC meeting dates, the agendas, briefly describe the materials presented,
if applicable, specific stakeholders in attendance (e.g., representatives of the
local historic commission, school committee members beyond those in the SBC,
local community group representatives, etc.), what materials are available for
public review and where those materials may be viewed. The MSBA also requires
Districts to provide similar information for public meetings and presentations
conducted in addition to school building committee meetings.
Refer to Appendix 3D Local Actions and Approvals Certification Template for additional
information. A signed Local Actions and Approval Certification on District Letterhead is
required for MSBA staff to forward the proposed project to the MSBA Board of Directors
for its consideration and approval to proceed into schematic design.
In order for the MSBA Board of Directors to consider a District’s preferred solution for
approval to proceed into schematic design, the following must occur prior to the date of
the Board meeting, in accordance with the deadlines established by the MSBA:
• The District, through its OPM, must submit its Preferred Schematic Report to the
MSBA in accordance with the deadlines published on the MSBA’s website
(www.MassSchoolBuildings.org).
• MSBA staff must complete its review of the Report, and the District must submit
responses to any questions or issues raised by the MSBA in a timeframe
adequate to support the schedule for the Board’s meetings.
• The District and its Designer may be required to present an overview of its
Report at an MSBA Facilities Assessment Subcommittee meeting.
• The District and its Designer must respond to any concerns or issues identified at
the MSBA Facilities Assessment Subcommittee in a timely fashion, prior to the
deadline established by the MSBA.
The District and the MSBA shall work in collaboration to determine which of the
solutions studied may be recommended to the MSBA Board of Directors as the preferred
solution in the Preferred Schematic Report. The solution may be phased in order of
Massachusetts School Building Authority Module 3 – Feasibility Study
- 18 -
January 2015
priority of need, if appropriate. It is possible, in some cases, that the study may
recommend a "no-build" solution. If the MSBA and the District cannot agree upon a
preferred solution, no preferred schematic design shall be forwarded to the Board for its
consideration. The MSBA and the District will begin a review of the alternatives
presented to determine if there are actions that can be taken to reach consensus on a
final recommendation.
The MSBA review process for the Preferred Schematic Report includes:
Upon receipt and review of the Preferred Schematic Report, MSBA staff will schedule the
District for presentation at a Facilities Assessment Subcommittee (“FAS”) Meeting. The
FAS meeting is an informational meeting only and is intended to provide an opportunity
for Districts to further the MSBA’s understanding of the proposed project. The FAS will
not take any votes, and any formal actions required by the MSBA Board of Directors to
fulfill MSBA procedures will be taken at the regularly scheduled Board meetings. FAS
meeting dates are posted on the MSBA website and should be consulted when preparing
the Feasibility Study work plan and schedule.
MSBA staff will notify the District, Designer, and OPM by e-mail of the scheduled FAS
meeting. The e-mail will include an outline of the material that should be presented,
which typically includes an overview of the project, the evaluation conducted to arrive at
the recommended preferred solution, and if applicable, responses to specific questions
regarding potential concerns noted during staff’s review of the Preferred Schematic
Report.
After the District has presented at the Facilities Assessment Subcommittee, if required,
MSBA staff will present the preferred solution to the MSBA Board of Directors for its
consideration and approval of a Preferred Schematic Design. If the Board approves a
District to proceed into schematic design for its preferred solution, as described in the
Preferred Schematic Report, the MSBA shall issue a Board Action Letter, summarizing
the Board’s actions. Upon receipt of the Board Action Letter, the District may proceed
into Schematic Design – see Module 4.
APPENDIX 3A
Program Overview
Program Overview
The Massachusetts School Building Authority’s (“MSBA”) grant program for school
building construction and renovation projects is a non-entitlement competitive program
based on need. The MSBA’s Board of Directors (the “Board”) approves grants based on
need and urgency, as expressed by the City, Town, Regional School District, or
independent agricultural and technical school (“District”) and validated by the MSBA.
Once the MSBA Board of Directors invites a District to participate in the MSBA’s grant
program, the collaborative process includes the following eight Modules:
Module 1 – Eligibility Period: The MSBA Board of Directors votes to invite a District
into the Eligibility Period which initiates a 270-day period for the District to complete
preliminary requirements including a certification of the District’s understanding of the
grant program rules, the formation of a School Building Committee, a summary of the
District’s existing maintenance practices; determination of a design enrollment;
development of an educational profile, community authorization and funding to proceed,
and execution of the MSBA’s standard Feasibility Study Agreement. Districts that are
able to complete these requirements may receive an invitation to collaborate with the
MSBA to Conduct a Feasibility Study.
Module 4 – Schematic Design: The District and its team develop a robust schematic
design of sufficient detail to establish the scope, budget and schedule for the proposed
project. The MSBA generates a Project Scope and Budget Agreement that documents
the project scope, budget, schedule and MSBA financial participation to forward to the
MSBA Board of Directors for their approval.
Module 5 – Funding the Project: Once the MSBA Board of Directors has authorized
the MSBA Executive Director to enter into a Project Scope and Budget Agreement and a
Project Funding Agreement with the District, the District completes steps necessary to
secure community authorization and financial support for the proposed project and
enters into a Project Funding Agreement with the MSBA. With an executed Project
Funding Agreement the District engages OPM and Designer services, and updates
project budgets in Pro - Pay.
Module 8 – Project Closeout: The MSBA performs a final audit to determine final
total grant amounts and release final payment.
E
15 Response Due 1 day Wed 12/17/14 Wed 12/17/14
16 Materials Received by the MSBA 6 days Thu 12/18/14 Tue 12/23/14
17 DSP Meeting Date 0 days Tue 1/13/15 Tue 1/13/15 DSP Meeting Date
18 DSP Interviews Date 0 days Tue 1/27/15 Tue 1/27/15
19 Designer Contract Executed 7 days Wed 1/28/15 Tue 2/3/15
L
20 Designer Contract Received by the MSBA 1 day Wed 2/4/15 Wed 2/4/15
21 Preliminary Design Program 139 days Thu 2/19/15 Wed 7/8/15 Preliminary Design Program
23 Kick Off Meeting 1 day Thu 2/19/15 Thu 2/19/15
24 PDP Submittal Development 90 days Fri 3/13/15 Wed 6/10/15
25 PDP Submittal Date (8 weeks before PSR 0 days Thu 6/11/15 Thu 6/11/15 PDP Submittal Date (8 weeks before PSR date)
date)
P
26 MSBA PDP Review 14 days Thu 6/11/15 Wed 6/24/15
27 Address PDP Comments 14 days Thu 6/25/15 Wed 7/8/15
28 Preferred Schematic Report 105 days Thu 6/11/15 Wed 9/23/15 Preferred Schematic Report
30 PSR Submittal Development 57 days Thu 6/11/15 Thu 8/6/15
31 PSR Submittal Date 0 days Thu 8/6/15 Thu 8/6/15 PSR Submittal Date
32 MSBA PSR Review 14 days Thu 8/6/15 Wed 8/19/15
33 Address PSR Comments 10 days Thu 8/20/15 Sat 8/29/15
34 FAS Presentation 0 days Wed 9/9/15 Wed 9/9/15 FAS Presentation
M
35 Address FAS Comments 14 days Wed 9/9/15 Tue 9/22/15
36 PS Board Approval 0 days Wed 9/23/15 Wed 9/23/15 PS Board Approval
37 Schematic Design 137 days Wed 9/23/15 Sat 2/6/16 Schematic Design
39 SD Submittal Development 79 days Wed 9/23/15 Thu 12/10/15
40 SD Notification Email Sent 1 day Thu 11/26/15 Thu 11/26/15
41 SD Submittal Date 0 days Thu 12/10/15 Thu 12/10/15 SD Submittal Date
42 MSBA SD Review Complete 21 days Thu 12/10/15 Wed 12/30/15
A
43 Address SD Comments 14 days Thu 12/31/15 Wed 1/13/16
44 PS & B Board Approval 0 days Wed 1/27/16 Wed 1/27/16 PS & B Board Approval
45 PSB Agreement Executed 11 days Wed 1/27/16 Sat 2/6/16
46 DESE Review 72 days Thu 12/10/15 Fri 2/19/16 DESE Review
S
48 MSBA Review of DESE Submittal 7 days Thu 12/10/15 Wed 12/16/15
49 DESE Review and Approval 65 days Thu 12/17/15 Fri 2/19/16
50 Project Funding Appropriation 51 days Wed 4/6/16 Fri 5/27/16 Project Funding Appropriation
52 District Vote 0 days Tue 4/5/16 Tue 4/5/16 District Vote
53 Certifications of Votes sent to MSBA 11 days Tue 4/5/16 Fri 4/15/16
54 Project Funding Agreement Sent 18 days Wed 4/20/16 Sat 5/7/16
55 Project Funding Agreement Executed 0 days Mon 5/16/16 Mon 5/16/16 Project Funding Agreement Executed
56 ProPay Training Date #2 1 day Fri 5/27/16 Fri 5/27/16
57 Design Development (DD) 137 days Tue 4/5/16 Fri 8/19/16 Design Development (DD)
59 Design Development 94 days Tue 4/5/16 Thu 7/7/16
60 DD Submission Date 0 days Thu 7/7/16 Thu 7/7/16 DD Submission Date
61 MSBA DD Review 21 days Fri 7/8/16 Thu 7/28/16
62 Address DD Review Comments 21 days Fri 7/29/16 Thu 8/18/16
63 60% Construction Documents (CD) 133 days Fri 7/8/16 Thu 11/17/16 60% Construction Documents (CD)
65 60% CD Development 91 days Fri 7/8/16 Thu 10/6/16
66 60% CD Submission Date 0 days Thu 10/6/16 Thu 10/6/16 60% CD Submission Date
67 MSBA 60% CD Review 21 days Fri 10/7/16 Thu 10/27/16
68 Addresss 60% CD Review Comments 21 days Fri 10/28/16 Thu 11/17/16
69 90% Construction Documents (CD) 108 days Fri 10/7/16 Sun 1/22/17 90% Construction Documents (CD)
71 90% CD Development 68 days Fri 10/7/16 Tue 12/13/16
72 90% CD Submission Date 0 days Tue 12/13/16 Tue 12/13/16 90% CD Submission Date
73 MSBA 90% CD Review 21 days Wed 12/14/16 Tue 1/3/17
74 Address 90% CD Review Comments 21 days Wed 1/4/17 Tue 1/24/17
75 Bidding/CM Selection 291 days Mon 8/15/16 Thu 6/1/17 Bidding/CM Selection
77 Bids due 0 days Wed 3/1/17 Wed 3/1/17 Bids due
78 Notice to Proceed 0 days Wed 3/22/17 Wed 3/22/17 Notice to Proceed
79 Construction 818 days Wed 3/22/17 Mon 6/17/19 Construction
81 Early Site Package Realease (if Applicable) 150 days Sat 11/26/16 Mon 4/24/17 Early Site Package Realease (if Applicable)
82 Construction Phase 515 days Wed 3/22/17 Sat 8/18/18
83 Substantial Completion 0 days Sat 8/18/18 Sat 8/18/18 Substantial Completion
84 Move-In 2 days Sun 8/19/18 Mon 8/20/18
85 Complete Demo - Existing Building 52 days Tue 8/21/18 Thu 10/11/18
86 Project Complete 0 days Tue 6/18/19 Tue 6/18/19 Project Complete
Project: Project1 Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline
Date: Mon 11/24/14 Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Progress
Page 1
Schedule provided for reference only. Dates and task durations may vary by project
Proposed Space Summary- Elementary Schools
PROPOSED
MSBA Guidelines
FILL IN SCHOOL NAME HERE Existing Conditions Existing to Remain/Renovated New Total
(refer to MSBA Educational Program & Space Standard Guidelines)
Music Classroom / Large Group - 25-50 seats 1,200 0 - assumed schedule 2 times / week / student
Music Practice/ Ensemble 75 0 -
MEDICAL 0 0 0 0 310
Medical Suite Toilet 60 1 60
Nurses' Office/Waiting Room 250 1 250
Examination Room / Resting 100 0 -
7/15/10 Page 3C - 1 of 2
Proposed Space Summary- Elementary Schools
PROPOSED
MSBA Guidelines
FILL IN SCHOOL NAME HERE Existing Conditions Existing to Remain/Renovated New Total
(refer to MSBA Educational Program & Space Standard Guidelines)
OTHER 0 0 0 0 0
Other (specify)
2
Total Building Gross Floor Area (GFA) -
1 Includes the net square footage measured from the inside face of the perimeter walls and includes all specific spaces assigned to a particular program area including such spaces as non-communal toilets and storage rooms.
Individual Room Net Floor Area (NFA)
2
Total Building Gross Floor Area (GFA) Includes the entire building gross square footage measured from the outside face of exterior walls
Architect Certification
I hereby certify that all of the information provided in this "Proposed Space Summary" is true, complete and accurate and, except as agreed to in writing by the Massachusetts School Building Authority, in accordance with the guidelines, rules, regulations and policies
of the Massachusetts School Building Authority to the best of my knowledge and belief. A true statement, made under the penalties of perjury.
Date:
7/15/10 Page 3C - 2 of 2
Proposed Space Summary- Elementary - K-8 School
PROPOSED
MSBA Guidelines
ELEMENTARY SCHOOL Existing Conditions Existing to Remain/Renovated New Total
(refer to MSBA Educational Program & Space Standard Guidelines)
Tech. Shop - (E.G. Consumer, Wood) 0 0 0 2,000 0 - Assumed use - 25% Population - 5 times/week
MEDICAL 0 0 0 0 310
Medical Suite Toilet 0 0 0 0 0 0 60 1 60
Nurses' Office/Waiting Room 0 0 0 0 0 0 250 1 250
Examination Room / Resting 0 0 0 0 0 0 100 0 -
7/15/10 Page 3C - 1 of 2
Proposed Space Summary- Elementary - K-8 School
PROPOSED
MSBA Guidelines
ELEMENTARY SCHOOL Existing Conditions Existing to Remain/Renovated New Total
(refer to MSBA Educational Program & Space Standard Guidelines)
Guidance area
General Waiting Room 0 0 0 0 0 0 100 1 100
Guidance Office 0 0 0 0 0 0 150 1 150
Guidance Storeroom 0 0 0 0 0 0 #DIV/0! 1 #DIV/0!
OTHER 0 0 0 0 0
Other (specify) 0 0 0 0 0 0
2
Total Building Gross Floor Area (GFA) GSF of existing GSF new 0 0 #DIV/0! Grades 6-8
#DIV/0!
Grossing factor (GFA/NFA) #DIV/0! (estimate) 1.50
1 Includes the net square footage measured from the inside face of the perimeter walls and includes all specific spaces assigned to a particular program area including such spaces as non-communal toilets and storage rooms.
Individual Room Net Floor Area (NFA)
2
Total Building Gross Floor Area (GFA) Includes the entire building gross square footage measured from the outside face of exterior walls
Architect Certification
I hereby certify that all of the information provided in this "Proposed Space Summary" is true, complete and accurate and, except as agreed to in writing by the Massachusetts School Building Authority, in accordance with the guidelines, rules, regulations and
policies of the Massachusetts School Building Authority to the best of my knowledge and belief. A true statement, made under the penalties of perjury.
Date:
7/15/10 Page 3C - 2 of 2
Proposed Space Summary - Middle Schools
PROPOSED
MSBA Guidelines
FILL IN SCHOOL NAME HERE Existing Conditions Existing to Remain/Renovated New Total
(refer to MSBA Educational Program & Space Standard Guidelines)
Band / Chorus - 100 seats 1,500 0 - assumed use - 50% population 2 times / week
Music Practice / Ensemble 200 1 200
Tech. Shop - (E.G. Consumer, Wood) 2,000 0 - Assumed use - 25% Population - 5 times/week
MEDICAL 0 0 0 0 310
Medical Suite Toilet 60 1 60
Nurses' Office/Waiting Room 250 1 250
Examination Room / Resting 100 0 -
7/15/10 Page 3C - 1 of 2
Proposed Space Summary - Middle Schools
PROPOSED
MSBA Guidelines
FILL IN SCHOOL NAME HERE Existing Conditions Existing to Remain/Renovated New Total
(refer to MSBA Educational Program & Space Standard Guidelines)
OTHER 0 0 0 0 0
Other (specify)
2
Total Building Gross Floor Area (GFA) 0
1 Includes the net square footage measured from the inside face of the perimeter walls and includes all specific spaces assigned to a particular program area including such spaces as non-communal toilets and storage rooms.
Individual Room Net Floor Area (NFA)
2
Total Building Gross Floor Area (GFA) Includes the entire building gross square footage measured from the outside face of exterior walls
Architect Certification
I hereby certify that all of the information provided in this "Proposed Space Summary" is true, complete and accurate and, except as agreed to in writing by the Massachusetts School Building Authority, in accordance with the guidelines, rules, regulations and policies of the
Massachusetts School Building Authority to the best of my knowledge and belief. A true statement, made under the penalties of perjury.
Date:
7/15/10 Page 3C - 2 of 2
Proposed Space Summary - High Schools
PROPOSED
MSBA Guidelines
Existing Conditions Existing to Remain/Renovated New Total
(refer to MSBA Educational Program & Space Standard Guidelines)
FILL IN SCHOOL NAME HERE
ROOM ROOM ROOM ROOM ROOM
1 # OF RMS area totals 1 # OF RMS area totals 1 # OF RMS area totals 1 # OF RMS area totals 1 # OF RMS area totals Comments
NFA NFA NFA NFA NFA
ROOM TYPE
SPECIAL EDUCATION 0 0 0 0 0
(List classrooms of different sizes seperately)
Self-Contained SPED 950 0 - assumed 8% of pop. in self-contained SPED
Self-Contained SPED Toilet 60 0 -
Resource Room 500 0 - 1/2 size Genl. Clrm.
Small Group Room 500 0 - 1/2 size Genl. Clrm.
Band - 50-100 seats 1,500 1 1,500 Assumed use - 25% Population - 5 times/week
Chorus - 50-100 seats 1,500 1 1,500
Ensemble 200 1 200
Music Practice 75 -1 (75)
Music Storage 500 1 500
Tech Shop - (E.G. Consumer, Wood) 2,000 -1 (2,000) Assumed use - 50% Population - 5 times/week
MEDICAL 0 0 0 0 210
Medical Suite Toilet 60 1 60
Nurses' Office/Waiting Room 250 1 250
Interview Room 100 -1 (100)
Examination Room / Resting 100 0 -
7/15/10 Page 3C - 1 of 2
Proposed Space Summary - High Schools
PROPOSED
MSBA Guidelines
Existing Conditions Existing to Remain/Renovated New Total
(refer to MSBA Educational Program & Space Standard Guidelines)
FILL IN SCHOOL NAME HERE
ROOM ROOM ROOM ROOM ROOM
1 # OF RMS area totals 1 # OF RMS area totals 1 # OF RMS area totals 1 # OF RMS area totals 1 # OF RMS area totals Comments
NFA NFA NFA NFA NFA
ROOM TYPE
OTHER 0 0 0 0 0
Other (specify)
2
Total Building Gross Floor Area (GFA) #N/A
I hereby certify that all of the information provided in this "Proposed Space Summary" is true, complete and accurate and, except as agreed to in writing by the Massachusetts School Building Authority, in accordance with the guidelines,
1 Individual Room Net Floor Area (NFA) rules, regulations and policies of the Massachusetts School Building Authority to the best of my knowledge and belief. A true statement, made under the penalties of perjury.
2
Total Building Gross Floor Area (GFA) Includes the entire building gross square footage measured from the outside face of exterior walls
Architect Certification
I hereby certify that all of the information provided in this "Proposed Space Summary" is true, complete and accurate and, except as agreed to in writing by the Massachusetts School Building Authority, in accordance with the guidelines, rules, regulation
Date:
7/15/10 Page 3C - 2 of 2
January 2015
Appendix 3D
Instructions: Complete the letter and certification set forth below and print on
(City/Town/Regional School District) letterhead. Please submit one original, signed
version of the letter and certification and one electronic version to the MSBA.
[Date]
Since the MSBA’s Board of Directors invited the District to conduct a Feasibility Study on
(insert date of the MSBA Board of Directors meeting), the SBC has held (insert number
of SBC meetings) meetings regarding the proposed project, in compliance with the state
Open Meeting Law. These meetings include:
[Insert a complete list of SBC meetings held to discuss and/or present to the public
material related to the Project and include the following information for each meeting:
the time and location of the meeting, who presented (if applicable), a summary of the
concerns and comments presented, a list of the materials discussed or made available
for public review, a list of votes taken and the results, and when and where notice of
each meeting was posted.]
In addition to the SBC meetings listed above, the District held (insert number of public
meetings) public meetings, which were posted in compliance with the state Open
Meeting Law, at which the Project was discussed. These meetings include:
[Insert a complete list of all public meetings held to discuss and/or present to the public
material related to the Project and include the following information for each meeting:
who hosted the meeting (e.g., School Committee, Board of Selectmen), the time and
location of the meeting who presented (if applicable), a brief summary of the concerns
and comments presented, a list of the materials discussed or made available for public
review, a list of votes taken and the results, and when and where notice of each
meeting was posted.
The presentation materials for each meeting, meeting minutes, and summary materials
related to the Project are available locally for public review at (insert location of
materials (e.g. website, town hall, superintendent’s office etc)).
To the best of my knowledge and belief, each of the meetings listed above complied
with the requirements of the Open Meeting Law, M.G.L. c. 30A, §§ 18-25 and 940 CMR
29 et seq.
If you have any questions or require any additional information, please contact (insert
name, title, and contact information).
By signing this Local Action By signing this Local Action By signing this Local Action
and Approval Certification, I and Approval Certification, I and Approval Certification, I
hereby certify that, to the hereby certify that, to the hereby certify that, to the
best of my knowledge and best of my knowledge and best of my knowledge and
belief, the information belief, the information belief, the information
supplied by the District in supplied by the District in supplied by the District in
this Certification is true, this Certification is true, this Certification is true,
complete, and accurate. complete, and accurate. complete, and accurate.
As reported on the school district’s most recent three end of year information, please updated to the 3 latest fiscal year periods and complete the fields below.
20##-20## 20##-20## 20##-20## Change from Previous Year Post-Constuction Budget New Facility vs. Current
FY20## FY20## FY20##
Category Staff (FTE) Budget Staff (FTE) Budget Staff Budget Staff (FTE) Budget Staff Budget Staff (FTE) Budget
Salaries
Administration
Admin. Secretary 0.00 - 0.00 - 0.00 - 0.00 - 0.00 - 0.00 -
Assistant Principal 0.00 - 0.00 - 0.00 - 0.00 - 0.00 - 0.00 -
Business Office 0.00 - 0.00 - 0.00 - 0.00 - 0.00 - 0.00 -
Curriculum Director/Coord. 0.00 - 0.00 - 0.00 - 0.00 - 0.00 - 0.00 -
Custodians/Maintenance Staff 0.00 - 0.00 - 0.00 - 0.00 - 0.00 - 0.00 -
Executive Secretary 0.00 - 0.00 - 0.00 - 0.00 - 0.00 - 0.00 -
Facilities Manager 0.00 - 0.00 - 0.00 - 0.00 - 0.00 - 0.00 -
Guidance 0.00 - 0.00 - 0.00 - 0.00 - 0.00 - 0.00 -
Adjustment Counselor 0.00 - 0.00 - 0.00 - 0.00 - 0.00 - 0.00 -
Guidance Counselors 0.00 - 0.00 - 0.00 - 0.00 - 0.00 - 0.00 -
Guidance Director 0.00 - 0.00 - 0.00 - 0.00 - 0.00 - 0.00 -
Legal 0.00 - 0.00 - 0.00 - 0.00 - 0.00 - 0.00 -
Nurse 0.00 - 0.00 - 0.00 - 0.00 - 0.00 - 0.00 -
Other 0.00 - 0.00 - 0.00 - 0.00 - 0.00 - 0.00 -
Principal 0.00 - 0.00 - 0.00 - 0.00 - 0.00 - 0.00 -
Special Education Admin 0.00 - 0.00 - 0.00 - 0.00 - 0.00 - 0.00 -
Superintendent/Asst. Superintendent 0.00 - 0.00 - 0.00 - 0.00 - 0.00 - 0.00 -
Transportation 0.00 - 0.00 - 0.00 - 0.00 - 0.00 - 0.00 -
Treasurer 0.00 - 0.00 - 0.00 - 0.00 - 0.00 - 0.00 -
Total Administration 0.00 - 0.00 - 0.00 - 0.00 - 0.00 - 0.00 -
Employee Benefits
All employee-related fringe (health insurance, retirement etc) - - - - - -
Page 3E- 1 of 2
January 2014 Budget Statement for Preferred Schematic - Expenditures
20##-20## 20##-20## 20##-20## Change from Previous Year Post-Constuction Budget New Facility vs. Current
FY20## FY20## FY20##
Category Staff (FTE) Budget Staff (FTE) Budget Staff Budget Staff (FTE) Budget Staff Budget Staff (FTE) Budget
Services
Athletics - - - - - -
Attendance - - - - - -
Food Service - - - - - -
Health Services - - - - - -
Other Student Activities - - - - - -
Psychological Services - - - - - -
School Security - - - - - -
Student Transportation - - - - - -
Total Services - - - - - -
Total Material & Services - - - - - -
Captial Improvements
Captial Improvements - - - - - -
Debt Service
Short-term - - - - - -
Long-term - - - - - -
Total Debt Service - - - - - -
Page 3E- 2 of 2
January 2014 Budget Statement for Preferred Schematic - Revenue
As reported on the school district’s most recent three End of Year Pupil and Financial Reports schedule 1, please update to the 3 latest fiscal year periods and report sources of revenue in the fields below.
FY## End of Year Financial Report FY## End of Year Financial Report FY## End of Year Financial Report
C74 C74 C74
Special Occupation Adult Other Un- Special Occupation Adult Other Un- Special Occupation Adult Other Un-
Regular Day Education al Day Education Programs distributed Total Regular Day Education al Day Education Programs distributed Total Regular Day Education al Day Education Programs distributed Total
A. Revenue from Local Sources
Assessments received by Regional Schools - - - - - - - - - - - - - - - - - - - - -
E&D Fund Appropriations - - - - - - - - - - - - - - - - - - - - -
Tuition from Individuals - - - - - - - - - - - - - - - - - - - - -
Tuition from Other Districts in Comm. - - - - - - - - - - - - - - - - - - - - -
Tuition from Districts in Other States - - - - - - - - - - - - - - - - - - - - -
Previous Year Unexpended Encumbrances (Carry Forward) - - - - - - - - - - - - - - - - - - - - -
Transportation Fees - - - - - - - - - - - - - - - - - - - - -
Earnings on Investments - - - - - - - - - - - - - - - - - - - - -
Rental of School Facilities - - - - - - - - - - - - - - - - - - - - -
Other Revenue - - - - - - - - - - - - - - - - - - - - -
Medical Care and Assistance - - - - - - - - - - - - - - - - - - - - -
Non Revenue Receipts - - - - - - - - - - - - - - - - - - - - -
Total Revenue From Local Sources - - - - - - - - - - - - - - - - - - - - -
3E-1 of 1
January 2014
Appendix 3F
The following checklist has been provided as a general guide for Districts and
consultants in the performance of work associated with the requirements of the
Feasibility Study Agreement, Module 3 – Feasibility Study, OPM and Designer Contracts,
practices, policies, and Project Advisories and is not to be submitted to the MSBA. This
checklist is not intended to supersede the requirements of these documents or statutory
and regulatory requirements.
Item Date