This document contains charts and statistics from the Ministry of Electricity and Energy's Public Electricity Corporation Marib Gas Power Generation Station planning department. The first chart shows the number of work permits issued in the first half of 2019 for mechanical, electrical, instrument, and HVAC works from the planning manager (PM), construction manager (CM) and total issued. The second chart displays preventive maintenance statistics for the same periods. The third chart shows corrective maintenance data for the second half of the year.

Uploaded by

ali morisy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
82 views

2019 - Final Report &Statistics-Combination

This document contains charts and statistics from the Ministry of Electricity and Energy's Public Electricity Corporation Marib Gas Power Generation Station planning department. The first chart shows the number of work permits issued in the first half of 2019 for mechanical, electrical, instrument, and HVAC works from the planning manager (PM), construction manager (CM) and total issued. The second chart displays preventive maintenance statistics for the same periods. The third chart shows corrective maintenance data for the second half of the year.

Uploaded by

ali morisy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 25

‫وزارة اﻠﻛﻬﺮﺑﺎء واﻠﻄﺎﻗﺔ‬

‫اﻠﻣﺆﺳﺴﺔ اﻠﻌﺎﻤﺔ ﻠﻟﻛﻬﺮﺑﺎء‬


‫ﻣﺤﻄﺔ ﺗﻮﻟﻴﺪ ﻣﺄرب اﻟﻐﺎزﻳﺔ‬
‫ادارة اﻠﺘﺨﻄﻴﻂ‬

PM CM Issued Permits
Mechanical 150 120 270
Electrical 235 150 385
Instrument 200 101 301
HVAC 450 13 12 25
385
400
350
Work Permits

301
300 270
235
250 200
200 150
PM
150
150 120 101
100
CM
50 13 12 25
0
Mechanical Electrical Instrument HVAC Issued Permits

Department
Ministry of Electricity & Energy ‫ء وا‬ ‫وزارة ا‬
Public Electricity Corporation ‫ء‬ ‫ا‬ ‫ا‬
MARIB Gas Power Generation Station ‫رب ا ز‬
! "# ‫ادارة ا‬

‫"و ت‬ ‫دول ا‬

‫' ت‬ ‫دد ا‬ ‫"وى‬ ‫ا‬ ‫م‬


1st ‫ف ا ول‬ ‫لا‬ ‫زة‬ ‫لا‬ ‫لا‬ %
1 1
Half Year issued works
‫ل ا زة ل ا ف ا ول‬ ‫ا‬ ‫طط ا‬ ‫ا‬
1 2
Issued Works _1st Half Year Statistics
‫ا زة ل ا ف ا ول‬ ‫او‬ ‫ل ا‬ ‫ا‬ ‫طط ا‬ ‫ا‬
1 3
1st Half Year Preventive Maintenance W_ Chart
‫ا زة ل ا ف ا ول‬ "‫ا‬ ‫ل ا‬ ‫ا‬ ‫طط ا‬ ‫ا‬
1
1st Half Year Corrective Maintenance W_ Chart
1st $ ‫ل ا زة ل ا ف ا‬ ‫لا‬ %
1 4
Half Year issued works
$ ‫ل ا زة ل ا ف ا‬ ‫ا‬ ‫طط ا‬ ‫ا‬
1 5
Issued Works_ 2nd Half Year Statistics
$ ‫ا زة ل ا ف ا‬ ‫او‬ ‫ل ا‬ ‫ا‬ ‫طط ا‬ ‫ا‬
1 6
2nd Half Year Preventive Maintenance W_ Chart
$ ‫ا زة ل ا ف ا‬ "‫ا‬ ‫ل ا‬ ‫ا‬ ‫طط ا‬ ‫ا‬
1 7
2nd Half Year Corrective Maintenance W_Chart
9 2019 ‫درة ! م‬ ‫ا‬ ‫او‬ ‫لا‬ ‫_ا‬1 ‫ق‬ 8

6 2019 ‫درة ! م‬ ‫ا‬ "‫ا‬ ‫لا‬ ‫_ا‬2 ‫ق‬ 9

‫ا‬ ‫ا‬
‫د‬ ‫ن‬ /‫م‬ ‫ا ر‬ /‫م‬

‫ما‬
‫راري‬ ‫ؤاد *دا !ز ز ا‬% /‫م‬

‫ظت‬
‫ء وا‬ ‫وزارة ا‬
Work Permits 1st Half Year Statistics ‫ء‬ ‫ا‬ ‫ا‬
From 01-January-2019 To 30-June-2019 ‫رب ا ز‬
! "# ‫ادارة ا‬
PM Works CM Works Issued Works

Mechanical 3 9 12

Electrical 53 18 71

Instrument 51 20 71

HVAC 45 5 50

80 71 71
Work Permits

70
60 53 51 50
50 45 PM Works
40
30 18 20 CM Works
20 12
9 5
10 3
0 Issued Works
Mechanical Electrical Instrument HVAC

Department
‫ء وا‬ ‫وزارة ا‬
2019_1st Half Year Preventive Maintenance Chart ‫ء‬ ‫ا‬ ‫ا‬
‫رب ا ز‬
! "# ‫ادارة ا‬
Issued PM Works Closed PM Works Pinding PM Works

Mechanical 3 1 2

Electrical 53 26 27

Instrument 51 26 25

HVAC 45 35 10

60 53 51
Work Permits

50 45

40 35 Issued PM Works
26 27
30 26 25

20 Closed PM Works
10
10 3 2
1 Pinding PM Works
0
Mechanical Electrical Instrument HVAC

Department
‫ء وا‬ ‫وزارة ا‬
2019_1st Half Year Corrective Maintenance Chart ‫ء‬ ‫ا‬ ‫ا‬
‫رب ا ز‬
! "# ‫ادارة ا‬
Issued CM Works Closed CM Works Pinding CM Works

Mechanical 9 5 4

Electrical 18 9 9

Instrument 20 10 10

HVAC 5 4 1

25
Work Permits

20
20 18
Issued CM Works
15
9 10 10
9 9
10 Closed CM Works
5 4 5 4
5
1
0 Pinding CM Works
Mechanical Electrical Instrument HVAC

Department
‫ء وا‬ ‫وزارة ا‬
Work Permits 2nd Half Year Statistics ‫ء‬ ‫ا‬ ‫ا‬
From 01-July-2019 To 31-December-2019 ‫رب ا ز‬
! "# ‫ادارة ا‬
PM Works CM Works Issued Works

Mechanical 37 19 56

Electrical 6 18 24

Instrument 2 10 12

HVAC 24 12 36

60 56
Work Permits

50
37
40 36 PM Works
30 24 24
18
20 19
12 12
CM Works
10
10 6
2
0 Issued Works
Mechanical Electrical Instrument HVAC

Department
‫ء وا‬ ‫وزارة ا‬
2019_2nd Half Year Preventive Maintenance Chart ‫ء‬ ‫ا‬ ‫ا‬
‫رب ا ز‬
! "# ‫ادارة ا‬
Issued PM Works Closed PM Works Pinding PM Works Previous Closed PM Permits

Mechanical 37 15 22 1

Electrical 6 3 3 10

Instrument 2 1 1 4

HVAC 24 20 4 10

40 37
Work Permits

35 Issued PM Works
30
24
25 22
20 Closed PM Works
20 15
15 10 10 Pinding PM Works
10 6
3 4 4
3
5 1 2 1 1
Previous Closed PM Permits
0
1 2 3 4

Department
‫ء وا‬ ‫وزارة ا‬
‫ء‬ ‫ا‬ ‫ا‬
2019_2nd Half Year Corrective Maintenance Chart ‫رب ا ز‬
! "# ‫ادارة ا‬
Issued CM Works Closed CM Works Pinding CM Works Previous Closed CM Works

Mechanical 19 7 12 2

Electrical 18 5 13 2

Instrument 10 3 7 2

HVAC 12 10 2 0

19
20 18
Work Permits

18 Issued CM Works
16 13
14 12 12
12 10 10 Closed CM Works
10 7
8 7
5 Pinding CM Works
6 3
4 2 2 2 2
2 0 Previous Closed CM Works
0
1 2 3 4

Department
‫ء وا‬ ‫وزارة ا‬
2019_Issued Works Final Statistics&Chart ‫ء‬ ‫ا‬ ‫ا‬
‫رب ا ز‬
! "# ‫ادارة ا‬
PM Works CM Works Issued Works

Mechanical 40 28 68

Electrical 59 36 95

Instrument 53 30 83

HVAC 69 17 86

100 95
83 86
Work Permits

90
80 68 69
70 59 PM Works
60 53
50 40 36
40 28
30 CM Works
30 17
20
10
0 Issued Works
Mechanical Electrical Instrument HVAC

Department
Work Planned Feed Back
No. Frequency Job Code System KKS Unit Remark
Permit # Date Date

1 PM-MECH-01/19 Quarterly MECH-MBA-Q GT #11 DESICCANT DEHUMIDIFIER 11MBA10AT001 11 06/Feb/19

2 PM-MECH-02/19 Quarterly MECH-MBA-Q GT #12 DESICCANT DEHUMIDIFIER 12MBA10AT001 12 06/Feb/19

3 PM-MECH-03/19 Quarterly MECH-MBA-Q GT #13 DESICCANT DEHUMIDIFIER 13MBA10AT001 13 06/Feb/19

4 PM-MECH-04/19 Quarterly MECH-MBA-Q GT #11 DESICCANT DEHUMIDIFIER 11MBA10AT001 11 12/Jul/19

5 PM-MECH-05/19 Quarterly MECH-MBA-Q GT #12 DESICCANT DEHUMIDIFIER 12MBA10AT001 12 12/Jul/19

6 PM-MECH-06/19 Quarterly MECH-MBA-Q GT #13 DESICCANT DEHUMIDIFIER 13MBA10AT001 13 12/Jul/19

7 PM-MECH-07/19 Quarterly MECH-FFDP1-Q FIRE FIGHTING DIESEL PUMP 10SGA20AP003 10 12/Jul/19

8 PM-MECH-08/19 Quarterly MECH-FFDP2-Q FIRE FIGHTING DIESEL PUMP 10SGA20AP003 10 12/Jul/19

9 PM-MECH-09/19 Quarterly MECH-FFDP3-Q FIRE FIGHTING DIESEL PUMP 10SGA20AP003 10 12/Jul/19

10 PM-MECH-10/19 Other MECH-MBL-Other GT #11 AIR INTAKE SYSTEM 11MBL 11 12/Jul/19

11 PM-MECH-11/19 Other MECH-MBL-Other GT #12 AIR INTAKE SYSTEM 12MBL 12 12/Jul/19

12 PM-MECH-12/19 Other MECH-MBL-Other GT #13 AIR INTAKE SYSTEM 13MBL 13 12/Jul/19

13 PM-MECH-13/19 Yearly MECH-FFDP1-Y FIRE FIGHTING DIESEL PUMP 10SGA20AP003 10 12/Jul/19

14 PM-MECH-14/19 Yearly MECH-FFDP2-Y FIRE FIGHTING DIESEL PUMP 10SGA20AP003 10 12/Jul/19

15 PM-MECH-15/19 Yearly MECH-FFDP3-Y FIRE FIGHTING DIESEL PUMP 10SGA20AP003 10 12/Jul/19

16 PM-MECH-16/19 Yearly MECH-FFDP4-Y FIRE FIGHTING DIESEL PUMP 10SGA20AP003 10 12/Jul/19

FIRE FIGHTING_ BARREL WATER


17 PM-MECH-17/19 Yearly MECH-FFWH-Y 00SGY 10 12/Jul/19
HYDRANT SYSTEM
FIRE FIGHTING WATER SPRAY
18 PM-MECH-18/19 Yearly MECH-FFWS-Y 00SGY 10 12/Jul/19
SYSTEM
FIRE FIGHTING WET ALARM VALVEs
19 PM-MECH-19/19 Yearly MECH-FFAV-Y 00SGY 10 12/Jul/19
SYSTEM
FIRE FIGHTING_FOAM -WATER
20 PM-MECH-20/19 Yearly MECH-FFFWS-Y 00SGY 0 12/Jul/19
SPRINKLER SYSTEM

21 PM-MECH-21/19 Yearly MECH-XKA03-1Y CATERPILLAR GENERATOR _B.S.D.G#3 00XKA03 0 01/Aug/19

22 PM-MECH-22/19 Yearly MECH-XKA04-1Y CUMMINS GENERATOR _B.S.D.G#4 00XKA04 0 20/Aug/19

GT#11 LUBE OIL FAN& FIN FAN


23 PM-MECH-23/19 Monthly MECH-MBV23-M 11MBV23AN011/021/031 11 04/Sep/19
COOLER CELL

24 PM-MECH-24/19 Quarterly MECH-MBA-Q GT #11 DESICCANT DEHUMIDIFIER 11MBA10AT001 11 04/Sep/19

25 PM-MECH-25/19 Quarterly MECH-MOTOR-Q GT #11 LUBE OIL MAIN PUMP 11MBV21AP001 11 04/Sep/19

26 PM-MECH-26/19 Quarterly MECH-MOTOR-Q GT #11 LUBE OIL AUXILIARY PUMP 11MBV21AP002 11 04/Sep/19

27 PM-MECH-29/19 Quarterly MECH-MOTOR-Q GT #11 LUBE OIL LIFTING PUMP 11MBV21AP003 11 04/Sep/19

GT #11 LUBE OIL EMERGENCY DC


28 PM-MECH-28/19 Quarterly MECH-MOTOR-Q 11MBV21AP003-KP01 11 04/Sep/19
PUMP
GT #11 LUBE OIL COOLER FAN & FIN
29 PM-MECH-29/19 Quarterly MECH-MBV23-Q 11MBV23AN011/021/031 11 04/Sep/19
FAN COOLER CELL

30 PM-MECH-30/19 Quarterly MECH-MOTOR-Q GT #11 HYDRAULIC OIL PUMP 11MBX02AP001/002 11 04/Sep/19

31 PM-MECH-31/19 Half Yearly MECH-IGV-H GT #11 IGV SYSTEM 11MBA11S 11 04/Sep/19

32 PM-MECH-32/19 Half Yearly MECH-MBL-H GT #11 AIR INTAKE SYSTEM 11MBL 11 04/Sep/19

GT #11 GENERATOR INLET AIR


33 PM-MECH-33/19 Half Year MECH-MKJ-H 11MKJ15AA00111MKJ17AA001 11 04/Sep/19
DAMPER
GT#11 LUBE OIL COOLER FAN & FIN
34 PM-MECH-34/19 Half Yearly MECH-MBV23-H 11MBV23AN011/021/031 11 04/Sep/19
FAN COOLER CELL

35 PM-MECH-35/19 Yearly MECH-MBL-Y GT #11 AIR INTAKE SYSTEM 11MBL 11 04/Sep/19


Work Planned Feed Back
No. Frequency Job Code System KKS Unit Remark
Permit # Date Date
GT #11 GENERATOR INLET/OUTLET
36 PM-MECH-36/19 Yearly MECH-MKJ-Y 11MKJ15AA00111MKJ17AA001 11 04/Sep/19
AIR DAMPER
GT#11 HVAC UNITS BEARING
37 PM-MECH-37/19 Yearly MECH-SAA-Y 11SAA01AH001 11 04/Sep/19
GREASING #1
GT#11 HVAC UNITS BEARING
38 PM-MECH-38/19 Yearly MECH-SAA-Y 11SAA01AH002 11 04/Sep/19
GREASING #2
GT#11 HVAC UNITS BEARING
39 PM-MECH-39/19 Yearly MECH-SAA-Y 11SAA02AH001 11 04/Sep/19
GREASING #3
GT#11 HVAC UNITS BEARING
40 PM-MECH-40/19 Yearly MECH-SAA-Y 11SAA02AH002 11 04/Sep/19
GREASING #4
Work KKS Planned Feed Back
No. Frequency Job Code System Unit Remark
Permit # Date Date

1 PM-ELEC-01/19 Monthly ELEC-BATTERY-M BSDGs BATTERIES 10 29/Jan/19

2 PM-ELEC-02/19 Monthly ELEC-BATTERY-M CATERPILLAR GENERATOR BATTERIES 10 29/Jan/19

3 PM-ELEC-02/19 Monthly ELEC-BATTERY-M CUMMINS GENERATOR BATTERIES 10 29/Jan/19

4 PM-ELEC-04/19 Monthly ELEC-BATTERY-M FIRE FIGHTING DIESEL PUMP BATTERIES 10 29/Jan/19

11BTA10A/B
5 PM-ELEC-05/19 Monthly ELEC-BATTERY-M GT #11 BATTERY 220 V DC 11 29/Jan/19

12BTA10A/B
6 PM-ELEC-06/19 Monthly ELEC-BATTERY-M GT #12 BATTERY 220 V DC 12 29/Jan/19
13BTA10A/B
7 PM-ELEC-07/19 Monthly ELEC-BATTERY-M GT #13 BATTERY 220 V DC 13 29/Jan/19
00BTA10
8 PM-ELEC-08/19 Monthly ELEC-BATTERY-M SWITCHGEAR BATTERIES ROOM 10 29/Jan/19

9 PM-ELEC-09/19 Monthly ELEC-BATTERY-M SUBSTATIONS BATTERIES 10 29/Jan/19

220 V DC MAIN DISTRIBUTION BOARD (LV 00BUD10 & 00BUE10


10 PM-ELEC-10/19 Half Yearly ELEC-PANEL-H 10 23/Jun/19
ROOM)
00BRA10
11 PM-ELEC-11/19 Half Yearly ELEC-PANEL-H 230 V AC UPS PANEL BOARD (LV ROOM) 10 23/Jun/19
00BRB10
400 V AC MAIN DISTRIBUTION BOARD (LV 00BMB10 & 00BJA10
12 PM-ELEC-12/19 Half Yearly ELEC-PANEL-H 10 23/Jun/19
ROOM)
ADMINISTRATION MAIN & EMERGENCY 00UWC01
13 PM-ELEC-13/19 Half Yearly ELEC-PANEL-H 10 23/Jun/19
DISTRIBUTION PANEL BOARD 00UWC01GH002
00BTL10
14 PM-ELEC-14/19 Half Yearly ELEC-PANEL-H BATTERY CHARGERS #1 & 2 (LV ROOM) 10 23/Jun/19

00SAA30GH001
15 PM-ELEC-15/19 Half Yearly INST-PANEL-H BSDG #1 & 2_400V HVAC MCC PANEL 10 23/Jun/19

16 PM-ELEC-16/19 Half Yearly ELEC-PANEL-H BSDGs BATTERY CHARGER PANEL 10 23/Jun/19

00BRT01/02
17 PM-ELEC-17/19 Half Yearly ELEC-PANEL-H BY PASS PANEL #1 & 2 (LV ROOM) 10 23/Jun/19

00BTL20
18 PM-ELEC-18/19 Half Yearly ELEC-PANEL-H DC REGULATOR #1 & 2 (LV ROOM) 10 23/Jun/19

GT #12 NORMAL & EMERGENCY LIGHTING 12UMB01GP100/200


19 PM-ELEC-19/19 Half Yearly ELEC-PANEL-H 12 23/Jun/19
PANEL
GT #13 NORMAL & EMERGENCY LIGHTING 13UMB01GP100/200
20 PM-ELEC-20/19 Half Yearly ELEC-PANEL-H 13 23/Jun/19
PANEL
HVAC SYSTEM ELECTRICAL PANEL (LV 10SAA00GH001-A/B/C,
21 PM-ELEC-21/19 Half Yearly ELEC-PANEL-H 10SAK10GH001-A/B &
10 23/Jun/19
ROOM)
00SAA10/20GH001
00XKA01GS002 -
22 PM-ELEC-22/19 Half Yearly ELEC-PANEL-H INCOMER BSDGs PANEL (6.6 KV ROOM) 00XKA02GS002 10 23/Jun/19

00BRU01/02
23 PM-ELEC-23/19 Half Yearly ELEC-PANEL-H INVERTER PANEL #1 &2 (LV ROOM) 10 23/Jun/19

00BHA & 00BMA


24 PM-ELEC-24/19 Half Yearly ELEC-PANEL-H MAIN FEEDER LV 400 V ELECTRICAL PANEL 10 23/Jun/19

00BZL55
25 PM-ELEC-25/19 Half Yearly ELEC-PANEL-H OUTDOOR LIGHTING PANEL 10 23/Jun/19
00CPU10
26 PM-ELEC-26/19 Half Yearly ELEC-PANEL-H PANEL FOR BATTERIES (LV ROOM) 10 23/Jun/19

11BAB11
27 PM-ELEC-27/19 Half Yearly ELEC-PANEL-H PCC #11 220 V DC /24V DC CONVERTER 11 23/Jun/19

PCC #11 220 V DC BATTERY CHARGER 11BTL10/20


28 PM-ELEC-28/19 Half Yearly ELEC-PANEL-H 11 23/Jun/19
PANEL
11BUB01/02/03 -
29 PM-ELEC-29/19 Half Yearly ELEC-PANEL-H PCC #11 220 V DC LV SWITCHGEAR PANEL 11 23/Jun/19
11BUC01/02
PCC #11 400 V AC LV EMERGENCY 11BAB11
30 PM-ELEC-30/19 Half Yearly ELEC-PANEL-H 11 23/Jun/19
SWITCHGEAR
11BME01/02/51/52 &
31 PM-ELEC-31/19 Half Yearly ELEC-PANEL-H PCC #11 400 V AC LV SWITCHGEAR 11 23/Jun/19
11BFE01/02/03/04/51/52/5
3/54
11BJL02
32 PM-ELEC-32/19 Half Yearly ELEC-PANEL-H PCC #11 POWER SUPPLY PANEL BOARD 11 23/Jun/19
12BUK01/02
33 PM-ELEC-33/19 Half Yearly ELEC-PANEL-H PCC #12 220 V DC / 24 V DC CONVERTER 12 23/Jun/19

PCC #12 220 V DC BATTERY CHARGER 12BTL10/20


34 PM-ELEC-34/19 Half Yearly ELEC-PANEL-H 12 23/Jun/19
PANEL
12BUB01/02/03
35 PM-ELEC-35/19 Half Yearly ELEC-PANEL-H PCC #12 220 V DC LV SWITCHGEAR PANEL 12 23/Jun/19
12BUC01/02
Work KKS Planned Feed Back
No. Frequency Job Code System Unit Remark
Permit # Date Date
PCC #12 400 V AC LV EMERGENCY 12BME01/02
36 PM-ELEC-36/19 Half Yearly ELEC-PANEL-H 12 23/Jun/19
SWITCHGEAR 12BME51/52
12BFE01/02/03/04
37 PM-ELEC-37/19 Half Yearly ELEC-PANEL-H PCC #12 400 V AC LV SWITCHGEAR 12 23/Jun/19
12BFE51/52/53/54
12BJL02
38 PM-ELEC-38/19 Half Yearly ELEC-PANEL-H PCC #12 POWER SUPPLY PANEL BOARD 12 23/Jun/19
13BUK01/02
39 PM-ELEC-39/19 Half Yearly ELEC-PANEL-H PCC #13 220 V DC / 24 V DC CONVERTER 13 23/Jun/19

PCC #13 220 V DC BATTERY CHARGER 13BTL10/20


40 PM-ELEC-40/19 Half Yearly ELEC-PANEL-H 13 23/Jun/19
PANEL
13BUB01/02/03
41 PM-ELEC-41/19 Half Yearly ELEC-PANEL-H PCC #13 220 V DC LV SWITCHGEAR PANEL 13 23/Jun/19
13BUC01/02
PCC #13 400 V AC LV EMERGENCY 13BME01/02
42 PM-ELEC-42/19 Half Yearly ELEC-PANEL-H 13 23/Jun/19
SWITCHGEAR 13BME51/52
13BFE01/02/03/04
43 PM-ELEC-43/19 Half Yearly ELEC-PANEL-H PCC #13 400 V AC LV SWITCHGEAR 13 23/Jun/19
13BFE51/52/53/54
13BJL02
44 PM-ELEC-44/19 Half Yearly ELEC-PANEL-H PCC #13 POWER SUPPLY PANEL BOARD 13 23/Jun/19

13MBV21AP001-01
45 PM-ELEC-45/19 26 Weeks E CH-02 GT #13 MAIN LUBE OIL PUMP MOTOR 13 23/Jun/19

SWITCHGEAR BUILDING NORMAL & 00BZL21


46 PM-ELEC-46/19 Half Yearly ELEC-PANEL-H 10 23/Jun/19
EMERGENCY LIGHTING PANEL 00BZN20
TRANSFORMERS AREA NORMAL LIGHTING 00BZL65
47 PM-ELEC-47/19 Half Yearly ELEC-PANEL-H 10 23/Jun/19
PANEL
13MBV21AP001-02
48 PM-ELEC-48/19 26 Weeks E CH-02 GT #13 AUXILIARY LUBE OIL PUMP MOTOR 13 23/Jun/19

WATER TREATMENT UNIT HVAC PANEL 10SAK18GH001-A


49 PM-ELEC-49/19 Half Yearly ELEC-PANEL-H 10 23/Jun/19
BOARD
WATER TREATMENT UNIT MAIN 00BGJC10
50 PM-ELEC-50/19 Half Yearly ELEC-PANEL-H 10 23/Jun/19
DISTRIBUTION PANEL BOARD
WORKSHOP MAIN DISTRIBUTION PANEL 00BJF10
51 PM-ELEC-51/19 Half Yearly ELEC-PANEL-H 10 23/Jun/19
BOARD
WORKSHOP NORMAL & EMERGENCY 00BZL30
52 PM-ELEC-52/19 Half Yearly ELEC-PANEL-H 00BZN30
10 23/Jun/19
LIGHTING PANEL

53 PM-ELEC-53/19 Half Yearly ELEC-PANEL-H BSDGs BATTERY CHARGER PANEL 10 23/Jun/19

HOUSING COMPLEX TRANSFORMER (33/0.4 00BJT01


54 PM-ELEC-54/19 Yearly ELEC-TRANS#1-Y 10 11/Jul/19
KV)
HOUSING COMPLEX TRANSFORMER (6.6/0.4 00BJT02
55 PM-ELEC-55/19 Yearly ELEC-TRANS#1-Y 10 11/Jul/19
KV)
HOUSING COMPLEX TRANSFORMER (33/0.4 00BJT01
56 PM-ELEC-56/19 Yearly ELEC-TRANS#2-Y 10 11/Jul/19
KV)
HOUSING COMPLEX TRANSFORMER (6.6/0.4 00BJT02
57 PM-ELEC-57/19 Yearly ELEC-TRANS#2-Y 10 11/Jul/19
KV)
00XKA03
58 PM-ELEC-58/19 Yearly ELEC-XKA03-1Y CATERPILLAR GENERATOR _B.S.D.G#3 0 01/Aug/19

00XKA04
59 PM-ELEC-59/19 Yearly ELEC-XKA04-1Y CUMMINS GENERATOR _B.S.D.G#4 0 20/Aug/19
Work Planned Feed Back
No. Frequency Job Code System KKS Unit Remark
Permit # Date Date

1 PM-INST-01/19 Monthly INST-BATTERY-M PCC #11 BACKUP BATTERY 11CJP01AP1/AP2 11 02/Feb/19

2 PM-INST-02/19 Monthly INST-BATTERY-M PCC #12 BACKUP BATTERY 12CJP01AP1/AP2 12 02/Feb/19

3 PM-INST-03/19 Monthly INST-BATTERY-M PCC #13 BACKUP BATTERY 13CJP01AP1/AP2 13 02/Feb/19

SERVER ROOM (BOP PLC) BACKUP


4 PM-INST-04/19 Monthly INST-BATTERY-M 00CJC01 10 02/Feb/19
BATTERY

5 PM-INST-05/19 2 Months INST-BATTERY-2M FUEL GAS SYSTEM BACKUP BATTERY 10 02/Feb/19

6 PM-INST-06/19 2 Months INST-BATTERY-2M FUEL OIL SYSTEM BACKUP BATTERY 10 02/Feb/19

7 PM-INST-07/19 2 Months INST-BATTERY-2M DMC PANEL BACKUP BATTERY 10 02/Feb/19

8 PM-INST-08/19 2 Months INST-GT.F.F-2M GT11 FIRE FIGHTING SYS 11CYE11 11 02/Feb/19

9 PM-INST-09/19 2 Months INST-GT.F.F-2M GT12 FIRE FIGHTING SYS 12CYE11 12 02/Feb/19

10 PM-INST-10/19 2 Months INST-GT.F.F-2M GT13 FIRE FIGHTING SYS 13CYE11 13 02/Feb/19

11 PM-INST-11/19 2 Months INST-PCC.F.F-2M PCC11 FIRE FIGHTING SYS 11CYE11 11 02/Feb/19

12 PM-INST-12/19 2 Months INST-PCC.F.F-2M PCC12 FIRE FIGHTING SYS 12CYE11 12 02/Feb/19

13 PM-INST-13/19 2 Months INST-PCC.F.F-2M PCC13 FIRE FIGHTING SYS 13CYE11 13 02/Feb/19

14 PM-INST-14/19 Monthly INST-BATTERY-M PCC #11 BACKUP BATTERY 11CJP01AP1/AP2 11 28/Jun/19

15 PM-INST-15/19 Monthly INST-BATTERY-M PCC #12 BACKUP BATTERY 12CJP01AP1/AP2 12 28/Jun/19

16 PM-INST-16/19 Monthly INST-BATTERY-M PCC #13 BACKUP BATTERY 13CJP01AP1/AP2 13 28/Jun/19

SERVER ROOM (BOP PLC) BACKUP


17 PM-INST-17/19 Monthly INST-BATTERY-M 00CJC01 10 28/Jun/19
BATTERY

18 PM-INST-18/19 2 Months INST-BATTERY-2M FUEL GAS SYSTEM BACKUP BATTERY 10 28/Jun/19

19 PM-INST-19/19 2 Months INST-BATTERY-2M FUEL OIL SYSTEM BACKUP BATTERY 10 28/Jun/19

20 PM-INST-20/19 2 Months INST-BATTERY-2M DMC PANEL BACKUP BATTERY 10 28/Jun/19

21 PM-INST-21/19 2 Months INST-GT.F.F-2M GT11 FIRE FIGHTING SYS 11CYE11 11 28/Jun/19

22 PM-INST-22/19 2 Months INST-GT.F.F-2M GT12 FIRE FIGHTING SYS 12CYE11 12 28/Jun/19

23 PM-INST-23/19 2 Months INST-GT.F.F-2M GT13 FIRE FIGHTING SYS 13CYE11 13 28/Jun/19

24 PM-INST-24/19 2 Months INST-PCC.F.F-2M PCC11 FIRE FIGHTING SYS 11CYE11 11 28/Jun/19

25 PM-INST-25/19 2 Months INST-PCC.F.F-2M PCC12 FIRE FIGHTING SYS 12CYE11 12 28/Jun/19

26 PM-INST-26/19 2 Months INST-PCC.F.F-2M PCC13 FIRE FIGHTING SYS 13CYE11 13 28/Jun/19

27 PM-INST-27/19 Half Yearly INST-PANEL-H PCC #11 CONTROL PANEL ET200 11CPA01/02 11 07/Mar/19

28 PM-INST-28/19 Half Yearly INST-PANEL-H GT #11 AUTOMATION (PCC #11) 11CJP01/41 11 07/Mar/19

PCC #11 FIRE DETECTION / CO2 CONTROL


29 PM-INST-29/19 Half Yearly INST-PANEL-H 11CYE11 11 07/Mar/19
PANEL

30 PM-INST-30/19 Half Yearly INST-PANEL-H PCC #12 CONTROL PANEL ET200 12CPA01/02 12 07/Mar/19

31 PM-INST-31/19 Half Yearly INST-PANEL-H PCC #13 CONTROL PANEL ET200 13CPA01/02 13 07/Mar/19

32 PM-INST-32/19 Half Yearly INST-PANEL-H GT #11 AUTOMATION (PCC #12) 12CJP01/41 12 07/Mar/19

GT #11 NATURAL GAS U/STREAM


33 PM-INST-33/19 Yearly INST-PS-Y 11MBP11CP001/002 11 07/Mar/19
PRESSURE SWITCH
PCC #12 FIRE DETECTION / CO2 CONTROL
34 PM-INST-34/19 Half Yearly INST-PANEL-H 12CYE11 12 07/Mar/19
PANEL
PCC #13 FIRE DETECTION / CO2 CONTROL
35 PM-INST-35/19 Half Yearly INST-PANEL-H 13CYE11 13 07/Mar/19
PANEL
Work Planned Feed Back
No. Frequency Job Code System KKS Unit Remark
Permit # Date Date

36 PM-INST-36/19 Half Yearly INST-PANEL-H ELECTRONIC ROOM ELECTRICAL PANEL 00CJC01 10 07/Mar/19

ELECTRONIC ROOM BLACK BOX


37 PM-INST-37/19 Half Yearly INST-PANEL-H 00CPC01/02/03 10 07/Mar/19
CONTROL PANEL ET200
WATER TREATMENT & GAS PROCESS
38 PM-INST-38/19 Half Yearly INST-PANEL-H 00CPD42 10 07/Mar/19
BLACK BOX CONTROL PANEL ET200

39 PM-INST-39/19 Half Yearly INST-PANEL-H DRAIN OIL LOCAL CONTROL PANEL 10GMA20GH001 10 07/Mar/19

BSDG MAIN DISTRIBUTION CONTROL


40 PM-INST-40/19 Half Yearly INST-PANEL-H 10 07/Mar/19
BOARD
WATER TREATMENT UNIT CONTROL
41 PM-INST-41/19 Half Yearly INST-PANEL-H 10 07/Mar/19
PANEL
FUEL OIL TREATMENT ELECTRICAL & 00BJB10GH001NA01
42 PM-INST-42/19 Half Yearly INST-PANEL-H 10 07/Mar/19
LOCAL CONTROL PANEL 10GMA10GH001
PROCESS CONTROL SYSTEM PANEL
43 PM-INST-43/19 Half Yearly INST-PANEL-H 00CRW01/02 10 07/Mar/19
(ELECTRONIC ROOM)

44 PM-INST-44/19 Half Yearly INST-PANEL-H FIRE FIGHTING CONTROL PANEL 10SAK17GH001 10 07/Mar/19

45 PM-INST-45/19 Half Yearly INST-PANEL-H DIGITAL METERING CONTROL PANEL 10 07/Mar/19

46 PM-INST-46/19 Half Yearly INST-PANEL-H FOAM STATION CONTROL PANEL #1 & 2 10 07/Mar/19

BOP_FIRE FIGHTING POWER SUPPLY &


47 PM-INST-47/19 Half Yearly INST-FF-H 10SGY 10 07/Mar/19
PANEL BACKUP BATTERY
GT11_FIRE FIGHTING POWER SUPPLY &
48 PM-INST-48/19 Half Yearly INST-FF-H 11SGY 11 07/Mar/19
PANEL BACKUP BATTERY
GT12_FIRE FIGHTING POWER SUPPLY &
49 PM-INST-49/19 Half Yearly INST-FF-H 12SGY 12 07/Mar/19
PANEL BACKUP BATTERY
GT13_FIRE FIGHTING POWER SUPPLY &
50 PM-INST-50/19 Half Yearly INST-FF-H 13SGY 13 07/Mar/19
PANEL BACKUP BATTERY

51 PM-INST-51/19 Half Yearly INST-WTU-H WATER TREATMENT UNIT 10GB 10 07/Mar/19

52 PM-INST-52/19 Yearly INST-XKA03-1Y CATERPILLAR GENERATOR _B.S.D.G#3 00XKA03 0 01/Aug/19

53 PM-INST-53/19 Yearly INST-XKA04-1Y CUMMINS GENERATOR _B.S.D.G#4 00XKA04 0 20/Aug/19


Work Planned Feed Back
No. Frequency Job Code System KKS Unit Remark
Permit # Date Date

1 PM-HVAC-01/19 Monthly HVAC-SAC-M PCC #11 HVAC PACKAGED UNITS 11SAC02AH81E81/2/3/4 11 06/February/2019

2 PM-HVAC-02/19 Monthly HVAC-SAC-M PCC #12 HVAC PACKAGED UNITS 12SAC02AH81E81/2/3/4 12 06/February/2019

3 PM-HVAC-03/19 Monthly HVAC-SAC-M PCC #13 HVAC PACKAGED UNITS 13SAC02AH81E81/2/3/4 13 06/February/2019

SWITCHGEAR GROUND & FIRST FLOOR 10SAK10AH001/002


4 PM-HVAC-04/19 Monthly HVAC-SAK-M 10 06/February/2019
HVAC UNITS 10SAK10AH005/006

5 PM-HVAC-05/19 Monthly HVAC-SAK-M ADMINISTRATION HVAC UNITS 10SAK13AH001/002 10 06/February/2019

6 PM-HVAC-06/19 2 Months HVAC-2M GT #11 CEMS SPLIT UNIT (1 PCS) 11MBR20 11 06/February/2019

7 PM-HVAC-07/19 2 Months HVAC-2M GT #12 CEMS SPLIT UNIT (1 PCS) 12MBR20 12 06/February/2019

8 PM-HVAC-08/19 2 Months HVAC-2M GT #13 CEMS SPLIT UNIT (1 PCS) 13MBR20 13 06/February/2019

9 PM-HVAC-09/19 2 Months HVAC-2M CONTROL ROOM SPLIT UNIT (6 PCS) 10 06/February/2019

10 PM-HVAC-10/19 2 Months HVAC-2M SWITCHGEAR SPLIT UNIT (2 PCS) 10 06/February/2019

11 PM-HVAC-11/19 2 Months HVAC-2M WORKSHOP SPLIT UNIT (5 PCS) 10 06/February/2019

12 PM-HVAC-12/19 2 Months HVAC-2M LABORATORY SPLIT UNIT (1 PCS) 10 06/February/2019

13 PM-HVAC-13/19 2 Months HVAC-2M STORE SPLIT UNIT (4 PCS) 10 06/February/2019

14 PM-HVAC-14/19 2 Months HVAC-2M WATER TREATMENT SPLIT UNIT (2 PCS) 10 06/February/2019

15 PM-HVAC-15/19 2 Months HVAC-2M FUEL OIL GAS PLC SPLIT UNIT (2 PCS) 10 06/February/2019

16 PM-HVAC-16/19 2 Months HVAC-2M FUEL GAS PLC SPLIT UNIT (2 PCS) 10 06/February/2019

17 PM-HVAC-17/19 2 Months HVAC-2M 400 KV ROOM SPLIT UNIT (2 PCS) 10 06/February/2019

18 PM-HVAC-18/19 2 Months HVAC-2M GATE HOUSE SPLIT UNIT (7 PCS) 10 06/February/2019

19 PM-HVAC-19/19 2 Months HVAC-2M SHIFT IN CHARGE ROOM SPLIT UNIT (1 PCS) 10 06/February/2019

20 PM-HVAC-20/19 2 Months HVAC-2M OPERATION ROOM SPLIT UNIT (1 PCS) 10 06/February/2019

MAINTENANCE CARAVAN SPLIT UNIT (2


21 PM-HVAC-21/19 Half Yearly HVAC-SAK-H 10 06/February/2019
PCS)
MAINTENANCE CARAVAN SPLIT UNIT (2
22 PM-HVAC-22/19 Half Yearly HVAC-SAK-H 10 06/February/2019
PCS)

23 PM-HVAC-23/19 Monthly HVAC-SAC-M PCC #11 HVAC PACKAGED UNITS 11SAC02AH81E81/2/3/4 11 14/May/2019

24 PM-HVAC-24/19 Monthly HVAC-SAC-M PCC #12 HVAC PACKAGED UNITS 12SAC02AH81E81/2/3/4 12 14/May/2019

25 PM-HVAC-25/19 Monthly HVAC-SAC-M PCC #13 HVAC PACKAGED UNITS 13SAC02AH81E81/2/3/4 13 14/May/2019

SWITCHGEAR GROUND & FIRST FLOOR 10SAK10AH001/002


26 PM-HVAC-26/19 Monthly HVAC-SAK-M 10 14/May/2019
HVAC UNITS 10SAK10AH005/006

27 PM-HVAC-27/19 Monthly HVAC-SAK-M ADMINISTRATION HVAC UNITS 10SAK13AH001/002 10 14/May/2019

28 PM-HVAC-28/19 2 Months HVAC-2M GT #11 CEMS SPLIT UNIT (1 PCS) 11MBR20 11 14/May/2019

29 PM-HVAC-29/19 2 Months HVAC-2M GT #12 CEMS SPLIT UNIT (1 PCS) 12MBR20 12 14/May/2019

30 PM-HVAC-30/19 2 Months HVAC-2M GT #13 CEMS SPLIT UNIT (1 PCS) 13MBR20 13 14/May/2019

31 PM-HVAC-31/19 2 Months HVAC-2M CONTROL ROOM SPLIT UNIT (6 PCS) 10 14/May/2019

32 PM-HVAC-32/19 2 Months HVAC-2M SWITCHGEAR SPLIT UNIT (2 PCS) 10 14/May/2019

33 PM-HVAC-33/19 2 Months HVAC-2M WORKSHOP SPLIT UNIT (5 PCS) 10 14/May/2019

34 PM-HVAC-34/19 2 Months HVAC-2M LABORATORY SPLIT UNIT (1 PCS) 10 14/May/2019

35 PM-HVAC-35/19 2 Months HVAC-2M STORE SPLIT UNIT (4 PCS) 10 14/May/2019

36 PM-HVAC-36/19 2 Months HVAC-2M WATER TREATMENT SPLIT UNIT (2 PCS) 10 14/May/2019

37 PM-HVAC-37/19 2 Months HVAC-2M FUEL OIL GAS PLC SPLIT UNIT (2 PCS) 10 14/May/2019
Work Planned Feed Back
No. Frequency Job Code System KKS Unit Remark
Permit # Date Date

38 PM-HVAC-38/19 2 Months HVAC-2M FUEL GAS PLC SPLIT UNIT (2 PCS) 10 14/May/2019

39 PM-HVAC-39/19 2 Months HVAC-2M 400 KV ROOM SPLIT UNIT (2 PCS) 10 14/May/2019

40 PM-HVAC-40/19 2 Months HVAC-2M GATE HOUSE SPLIT UNIT (7 PCS) 10 14/May/2019

41 PM-HVAC-41/19 2 Months HVAC-2M SHIFT IN CHARGE ROOM SPLIT UNIT (1 PCS) 10 14/May/2019

42 PM-HVAC-42/19 2 Months HVAC-2M OPERATION ROOM SPLIT UNIT (1 PCS) 10 14/May/2019

MAINTENANCE CARAVAN SPLIT UNIT (2


43 PM-HVAC-43/19 Half Yearly HVAC-SAK-H 10 14/May/2019
PCS)
MAINTENANCE CARAVAN SPLIT UNIT (2
44 PM-HVAC-44/19 Half Yearly HVAC-SAK-H 10 14/May/2019
PCS)
HOUSING TRANSFORMER AND CIRCUIT
45 PM-HVAC-45/19 Quarterly HVAC-Q 10 30/May/2019
BREAKER BUILDING SPLIT UNITS (2 PCS)

46 PM-HVAC-46/19 Quarterly HVAC-Q FIRE FIGHTING ROOM HVAC UNIT 10 13/July/2019

47 PM-HVAC-47/19 Monthly HVAC-SAC-M PCC #11 HVAC PACKAGED UNITS 11SAC02AH81E81/2/3/4 11 17/December/2019

48 PM-HVAC-48/19 Monthly HVAC-SAC-M PCC #12 HVAC PACKAGED UNITS 12SAC02AH81E81/2/3/4 12 17/December/2019

49 PM-HVAC-49/19 Monthly HVAC-SAC-M PCC #13 HVAC PACKAGED UNITS 13SAC02AH81E81/2/3/4 13 17/December/2019

SWITCHGEAR GROUND & FIRST FLOOR 10SAK10AH001/002


50 PM-HVAC-50/19 Monthly HVAC-SAK-M 10 17/December/2019
HVAC UNITS 10SAK10AH005/006

51 PM-HVAC-51/19 Monthly HVAC-SAK-M ADMINISTRATION HVAC UNITS 10SAK13AH001/002 10 17/December/2019

52 PM-HVAC-52/19 2 Months HVAC-2M GT #11 CEMS SPLIT UNIT (1 PCS) 11MBR20 11 17/December/2019

53 PM-HVAC-53/19 2 Months HVAC-2M GT #12 CEMS SPLIT UNIT (1 PCS) 12MBR20 12 17/December/2019

54 PM-HVAC-54/19 2 Months HVAC-2M GT #13 CEMS SPLIT UNIT (1 PCS) 13MBR20 13 17/December/2019

55 PM-HVAC-55/19 2 Months HVAC-2M CONTROL ROOM SPLIT UNIT (6 PCS) 10 17/December/2019

56 PM-HVAC-56/19 2 Months HVAC-2M SWITCHGEAR SPLIT UNIT (2 PCS) 10 17/December/2019

57 PM-HVAC-57/19 2 Months HVAC-2M WORKSHOP SPLIT UNIT (5 PCS) 10 17/December/2019

58 PM-HVAC-58/19 2 Months HVAC-2M LABORATORY SPLIT UNIT (1 PCS) 10 17/December/2019

59 PM-HVAC-59/19 2 Months HVAC-2M STORE SPLIT UNIT (4 PCS) 10 17/December/2019

60 PM-HVAC-60/19 2 Months HVAC-2M WATER TREATMENT SPLIT UNIT (2 PCS) 10 17/December/2019

61 PM-HVAC-61/19 2 Months HVAC-2M FUEL OIL GAS PLC SPLIT UNIT (2 PCS) 10 17/December/2019

62 PM-HVAC-62/19 2 Months HVAC-2M FUEL GAS PLC SPLIT UNIT (2 PCS) 10 17/December/2019

63 PM-HVAC-63/19 2 Months HVAC-2M 400 KV ROOM SPLIT UNIT (2 PCS) 10 17/December/2019

64 PM-HVAC-64/19 2 Months HVAC-2M GATE HOUSE SPLIT UNIT (7 PCS) 10 17/December/2019

65 PM-HVAC-65/19 2 Months HVAC-2M SHIFT IN CHARGE ROOM SPLIT UNIT (1 PCS) 10 17/December/2019

66 PM-HVAC-66/19 2 Months HVAC-2M OPERATION ROOM SPLIT UNIT (1 PCS) 10 17/December/2019

MAINTENANCE CARAVAN SPLIT UNIT (2


67 PM-HVAC-67/19 Half Yearly HVAC-SAK-H 10 17/December/2019
PCS)
HOUSING TRANSFORMER AND CIRCUIT
68 PM-HVAC-68/19 Quarterly HVAC-Q 10 17/December/2019
BREAKER BUILDING SPLIT UNITS (2 PCS)

69 PM-HVAC-69/19 Quarterly HVAC-Q FIRE FIGHTING ROOM HVAC UNIT 10 17/December/2019


2019 List of Mechanical CM Permits

Work Work Issued Feed Back


No. System KKS Unit Remark
Permit # Request # Date Date

1 CM-MECH-01/19 WR-01/19 BSDG_HVVAC 10 5-Jan-19

2 CM-MECH-02/19 WR-03/19 FEUL OIL SYS 10EGD40AA901 10 9-Jan-19

3 CM-MECH-03/19 WR-09/19 FEUL GAS SYS 10 18-Feb-19

4 CM-MECH-04/19 WR-12/19 FIRE FIGHTING DIESEL PUMP SGY 10 18-Feb-19

5 CM-MECH-05/19 WR-14/19 GT13_LUB OIL SYS 13MBV50 10 26-Feb-19

6 CM-MECH-06/19 WR-17/19 B.S.D.G#3 10 31-Mar-19

7 CM-MECH-07/19 WR-18/19 B.S.D.G#4 10 31-Mar-19

8 CM-MECH-08/19 WR-21/19 F.F ELEC PUMP 10 6-Apr-19

9 CM-MECH-09/19 WR-28/19 WATER TRET SYS 10GKB02AP002 10 20-Apr-19

10 CM-MECH-10/19 WR-51/19 WATER TREATMENT SYS 10 13-Jul-19

11 CM-MECH-11/19 WR-51/19 CAT-GENSET_B.S.D.G#3 00XKA03 0 20-Aug-19

12 CM-MECH-12/19 WR-52/19 GT13_AIR INLET DAMPER 13MKJ15AA001 13 20-Aug-19

13 CM-MECH-13/19 WR-55/19 B.S.D.G COMPENSATION WATER TANKE 00XKA01,02 0 1-Sep-19

14 CM-MECH-14/19 WR-56/19 B.S.D.G#1 PRELUBE PUMP 00XKA01 0 1-Sep-19

00XKA01,00XKA
15 CM-MECH-15/19 WR-62/19 B.S.D.G#1/#2 COOLANT SYS 0 7-Oct-19
02

16 CM-MECH-16/19 WR-63/19 B.S.D.G#4_CUM GENSET 00XKA04 10 7-Oct-19

00XKA01,00XKA
17 CM-MECH-17/19 WR-64/19 B.S.D.G#1/#2 _GEAR BOX 0 7-Oct-19
02

18 CM-MECH-18/19 WR-77/19 B.S.D.G,s_FO TRANSFER PUMPS 10EGC50 0 26-Nov-19

19 CM-MECH-19/19 WR-78/19 GT11_AIR INTAK FLAPS 11MBL20AA10 11 26-Nov-19

20 CM-MECH-20/19 WR-78/19 GT12_AIR INTAK FLAPS 12MBL20AA10 12 26-Nov-19

21 CM-MECH-21/19 WR-78/19 GT13_AIR INTAK FLAPS 13MBL20AA10 13 26-Nov-19

22 CM-MECH-22/19 WR-79/19 GT12_GENERATOR INLET DAMPER 12MKG15AA001 12 26-Nov-19

23 CM-MECH-23/19 WR-80/19 GT11_ ROLLER DOOR ELEC_HOIST 11 26-Nov-19

24 CM-MECH-24/19 WR-80/19 GT12_ ROLLER DOOR ELEC_HOIST 12 26-Nov-19

25 CM-MECH-25/19 WR-80/19 GT13_ ROLLER DOOR ELEC_HOIST 13 26-Nov-19

11MKJ17AA001,,1
26 CM-MECH-26/19 WR-82/19 GEN_INLET/OUTLET DAMPERS 11 8-Dec-19
1MKJ15AA001

12MKJ17AA001,,1
27 CM-MECH-26/19 WR-82/19 GEN_INLET/OUTLET DAMPERS 12 8-Dec-19
2MKJ15AA001

13MKJ17AA001,,1
28 CM-MECH-28/19 WR-82/19 GEN_INLET/OUTLET DAMPERS 13 8-Dec-19
3MKJ15AA001

Page 2 of 6
2019 List of Electrical CM Permits

Work Work Issued Feed Back


No. System KKS Unit Remark
Permit # Request # Date Date

1 CM-ELEC-01/19 WR-07/19 GT13 AIR CRAFT 13MBR20GT01 13 09/Feb/19

2 CM-ELEC-02/19 WR-11/19 GT11_ LIGHTING SYS 11 18/Feb/19

3 CM-ELEC-03/19 WR-11/19 GT13_ LIGHTING SYS 13 18/Feb/19

4 CM-ELEC-04/19 WR-19/19 B.S.D.G#3 10 31/Mar/19

5 CM-ELEC-05/19 WR-20/19 400V SWG ROOM 00BJC10GS001A 10 06/Apr/19

6 CM-ELEC-06/19 WR-22/19 FIRE FIGHTING SYS SGY 10 09/Apr/19

7 CM-ELEC-07/19 WR-24/19 CCR BUILDING HVAC SYS 10 16/Apr/19

8 CM-ELEC-08/19 WR-27/19 400V SWG ROOM 00BJD10 10 19/Apr/19

9 CM-ELEC-09/19 WR-29/19 B.S.D.G#4 10 19/Apr/19

10 CM-ELEC-10/19 WR-39/19 400V SWG_CHARGER& BATTERY BTA 10/20 10 25/May/19

11 CM-ELEC-11/19 WR-40/19 PCC11_ BATTERY VENTILATOR 11BJL02GS003 11 09/Jun/19

12 CM-ELEC-12/19 WR-41/19 NORMAL LIGHTING BOARD_400VSWG 00BZL05 10 16/Jun/19

00BCB10GS021/X032,,,0
13 CM-ELEC-13/19 WR-42/19 INCOMING BUS BAR_33KV SWG 10 16/Jun/19
0BCB10GS021/X034

14 CM-ELEC-14/19 WR-43/19 CAT&CUMMINS GENSET OUTGOING CABLE 00XKA03/04 10 16/Jun/19

15 CM-ELEC-15/19 WR-44/19 OUT DOOR LIGHTING PANEL 00BZL55 10 26/Jun/19

16 CM-ELEC-16/19 WR-45/19 GT11_ S.CH CABLE TRAYS 11 26/Jun/19

17 CM-ELEC-17/19 WR-45/19 GT13_ S.CH CABLE TRAYS 13 26/Jun/19

18 CM-ELEC-18/19 WR-46/19 400V SWG 10 26/Jun/19

19 CM-ELEC-19/19 WR-48/19 FIRE FIGHTING DIESEL PUMP CONTROL PANEL 10SGY 10 03/Jul/19

20 CM-ELEC-20/19 WR-49/19 GT11_ LUB OIL LIFTING PUMP 11MBV30AP001 11 13/Jul/19

21 CM-ELEC-21/19 WR-50/19 11GSU_PROTECTION PANELS 11CHA30 11 13/Jul/19

22 CM-ELEC-22/19 WR-50/19 12GSU_PROTECTION PANELS 12CHA30 12 13/Jul/19

23 CM-ELEC-24/19 WR-50/19 13GSU_PROTECTION PANELS 13CHA30 13 13/Jul/19

24 CM-ELEC-25/19 WR-53/19 GT11_LIGHTING SYS 11 20/Aug/19

25 CM-ELEC-26/19 WR-53/19 GT12_LIGHTING SYS 12 20/Aug/19

26 CM-ELEC-27/19 WR-53/19 F.O _LIGHTING SYS 12 20/Aug/19

27 CM-ELEC-28/19 WR-53/19 WATER TREATMENT_LIGHTING SYS 10 20/Aug/19

28 CM-ELEC-29/19 WR-54/19 400SWG INVERTER 00BRU02,, 00BRU02 0 01/Sep/19

29 CM-ELEC-30/19 WR-59/19 B.S.D.G#4_CB 00XKA04_00BJB10GS 0 18/Sep/19

30 CM-ELEC-31/19 WR-65/19 400V SWG_CB 00BJC10GS001A 0 07/Oct/19

31 CM-ELEC-32/19 WR-67/19 SWG_AUX TRANS 00BMT,,00BHT 0 10/Nov/19

Page 3 of 6
2019 List of Electrical CM Permits

Work Work Issued Feed Back


No. System KKS Unit Remark
Permit # Request # Date Date

32 CM-ELEC-33/19 WR-68/19 CCR_NORMAL/EMERENCY LIGHTING SYS 0 10/Nov/19

33 CM-ELEC-34/19 WR-69/19 F.F BUILDING LIGHTING SYS 00SGY 0 10/Nov/19

34 CM-ELEC-35/19 WR-69/19 GSU13_PHOTOCELL 13BTA 13 10/Nov/19

35 CM-ELEC-36/19 WR-70/19 F.F_JOCKY PUMP 10SGA20AP001B 0 10/Nov/19

36 CM-ELEC-37/19 WR-72/19 B.S.D.G#4 00XKA04 0 23/Nov/19

Page 4 of 6
2019 List of Instrument CM Permits

Work Work Issued Feed Back


No. System KKS Unit Remark
Permit # Request # Date Date

1 CM-INST-01/19 WR-02/19 APPLICATION SERVER CRY01GJ60 10 09/Jan/19

2 CM-INST-02/19 WR-04/19 GT11_FEUL GAS SYS 11MBP13CP101 11 09/Jan/19

3 CM-INST-03/19 WR-05/19 WATER TREATMENT GAY 10 09/Feb/19

4 CM-INST-04/19 WR-06/19 WATER TREATMENT GAY 10 09/Feb/19

5 CM-INST-05/19 WR-13/19 WATER TR BREAK TANK 10 26/Feb/19

6 CM-INST-06/19 WR-15/19 400kv ROOM 10 25/Mar/19

7 CM-INST-07/19 WR-16/19 400kv ROOM PANELS 10 25/Mar/19

8 CM-INST-08/19 WR-23/19 DMC 10 09/Apr/19

9 CM-INST-09/19 WR-24/19 CCR ROOM FINGER PRINT 10 15/Apr/19

10 CM-INST-10/19 WR-25/19 CCR ROOM F.F SYS 10 18/Apr/19

11 CM-INST-11/19 WR-26/19 DCS ROOM 00CRY01 10 18/Apr/19

12 CM-INST-12/19 WR-33/19 SWG F.F SYS 10 22/Apr/19

13 CM-INST-13/19 WR-36/19 AP1/AP2 PLC 10 16/May/19

14 CM-INST-14/19 WR-37/19 CCR&400KV SWG _ FM200 F.F SYS 10 22/Apr/19

16 CM-INST-16/19 WR-47/19 FUEL GAS HEATER SKID#2 10EKC02 10 25/Jun/19

18 CM-INST-09/19 WR-24/19 CCR ROOM FINGER PRINT 10 15/Apr/19

19 CM-INST-10/19 WR-25/19 CCR ROOM F.F SYS 10 18/Apr/19

20 CM-INST-11/19 WR-26/19 DCS ROOM 00CRY01 10 18/Apr/19

21 CM-INST-12/19 WR-33/19 SWG F.F SYS 10 22/Apr/19

22 CM-INST-14/19 WR-37/19 CCR&400KV SWG _ FM200 F.F SYS 10 22/Apr/19

Page 5 of 6
2019 List of HVAC CM Permits

Work Work Issued Feed Back


No. System KKS Unit Remark
Permit # Request # Date Date

1 CM-HVAC-01/19 WR-08/19 TELE COMMUNICATION ROOM UCY 10 9-Feb-19

2 CM-HVAC-02/19 WR-31/19 PCC13 HVAC SYS 10 7-May-19

3 CM-HVAC-03/19 WR-32/19 DCS ROOM HVAC UCY 10 9-Feb-19

4 CM-HVAC-04/19 WR-34/19 SWG AHU_HVAC SYS 10 9-May-19

5 CM-HVAC-05/19 WR-35/19 SWG AHU_HVAC SYS 10 9-May-19

6 CM-HVAC-06/19 WR-58/19 HOUSING _A.H flat 0 1-Sep-19

7 CM-HVAC-07/19 WR-60/19 PCC11_ AHU SYS 11 18-Sep-19

8 CM-HVAC-08/19 WR-60/19 PCC12_ AHU SYS 12 18-Sep-19

9 CM-HVAC-09/19 WR-60/19 PCC13_ AHU SYS 13 18-Sep-19

10 CM-HVAC-10/19 WR-61/19 400KV_HVAC SYS 10 18-Sep-19

11 CM-HVAC-11/19 WR-61/19 INSTRUMENT OFFICE_HVAC SYS 10 18-Sep-19

12 CM-HVAC-12/19 WR-61/19 F.O PLC ROOM_HVAC SYS 10 18-Sep-19

13 CM-HVAC-13/19 WR-61/19 CHEMICAL MATERIAL _STOR ROOM_HVAC SYS 10 18-Sep-19

14 CM-HVAC-14/19 WR-66/19 D.C.S ROOM_HVAC SYS 10 10-Oct-19

15 CM-HVAC-15/19 WR-74/19 SWG AHU_HVAC SYS 10 26-Nov-19

16 CM-HVAC-16/19 WR-75/19 400KV_HVAC SYS 10 26-Nov-19

17 CM-HVAC-17/19 WR-76/19 DCS ROOM_HVAC SYS 10 26-Nov-19

Page 6 of 6