Using AC Optimal Power Flow For DG Planning and Optimisation
Using AC Optimal Power Flow For DG Planning and Optimisation
F OR Distribution Network Operators (DNOs) in fully requirements of the networks in order to produce the best
liberalised electricity markets (e.g., UK), planning the planning strategies. Whatever the particular driver for a given
siting and sizing of Distributed Generation (DG) units is, in DNO, e.g., to allow the connection of more DG capacity or to
many respects, not possible. Due to unbundling rules, DNOs reduce energy losses, these planning tools must take into
cannot invest in generation facilities and are meant to provide account network constraints such as voltage and thermal
DG owners with cost-effective connection means, irrespective limits. The inherent variability of demand and renewable
of the technology or geographical location. In this context, generation (e.g., wind power) is an aspect that must also be
uncertainties due to, for instance, planning consents or considered. In addition, envisaging actively managed
financial support surrounding DG investments pose DNOs networks (as opposed to the current ‘fit and forget’ approach),
with major challenges as to what, where and when to reinforce where Smart Grid-like control schemes employing real-time
the system in order to deliver timely connections without the control and communication systems allow more effective
risk of stranded assets. This lack of certainty and planning management of different network participants, including DG
coordination translates into distribution networks that connect units and voltage regulation devices, need also to be
DG units by adopting a ‘fit and forget’, case-by-case approach accounted for.
where only traditional reinforcements (e.g., new lines or Based on the authors’ previous and ongoing work, this
transformers) are carried out. Thus, any sophisticated solution paper compiles the different DG planning and optimisation
– albeit potentially more cost-effective for society in the long applications to which Optimal Power Flow (OPF) techniques
can be applied. The flexibility provided by a tailored AC OPF
makes it possible to extend the analysis to cater for a number
This work is funded through the EPSRC Supergen V, UK Energy of complex aspects. It can handle multi-periods to deal with
Infrastructure (AMPerES) grant in collaboration with UK electricity network
operators working under Ofgem’s Innovation Funding Incentive scheme – full the variability of demand and renewable generation.
details on http://www.supergen-amperes.org/. Advanced control strategies such as coordinated voltage
The authors are with the Institute for Energy Systems, School of control, adaptive power factor and generation curtailment can
Engineering, University of Edinburgh, Edinburgh, EH9 3JL, U.K. (e-mail:
[email protected], [email protected])
also be incorporated to evaluate potential benefits. More
complex problems resulting from other network constraints to provide/absorb 15 MVA. In the original demand-only case,
commonly overlooked by DG studies, such as fault levels, N- the OLTC at the substation has a target voltage of 1.045pu at
1 security and voltage step change, , are also viable within this the secondary bus. The voltage regulator (VR) and OLTCs on
approach. the 33/11-kV rural distribution transformers have a target
This paper, composed mainly by adapted extracts from [1- voltage of 1.03 pu. Voltage limits are ±6 % of nominal,
5], is structured as follows: First, the maximum connectable reflecting UK practice. The total peak demand is 38 MW.
DG capacity problem [1, 6] is presented in section II. Then, Hourly demand for central Scotland in 2003, as well as two
section III addresses the energy loss minimisation problem [2, different wind sites (named here, WP1 and WP2) derived
6]. Section IV discusses the incorporation of further network from UK Meteorological Office measured wind speed data
constraints such as fault levels [3, 6], N-1 security [4, 7], and [23], are adopted. Six wind generation sites are available.
voltage step change [5]. Finally, section V concludes the Buses 1105, 1106, 1108) are considered to all use the WP1
work. For the benefit of the reader, the framework for profile. The network contains a subsea cable connecting the
handling variable resources and demand, as well as the basic ‘mainland’ with an island on which the other three sites lie
mathematical structure for the multi-period AC OPF, (1113, 1114, 1115). The island enjoys approximately the same
including the incorporation of active network management wind resource as the first group but is sufficiently distinct to
schemes, are briefly included in the Appendix. In all the require the use of WP2.
studies the method was coded in the AIMMS optimisation
334 1118 328 342 325 1113
modelling environment [8] and solved using the CONOPT 302 331 332 333
DG
3.14A NLP solver. 329 337 335 336
322 324 1112
1114
interconnector
II. DISTRIBUTION NETWORK CAPACITY ASSESSMENT [1] DG
320 326 1115
Distribution network capacity assessment studies, i.e., the 327 330 1117 DG
VR
evaluation of the spare connection capacity, have been 328 1116
304 321 1111
whereas the non-linear formulation based on the AC Optimal 339 310 1106
LEGEND
1113 Node Index
Power Flow (OPF) problem was adopted in [1, 4-6, 19-21]. DG
The approach proposed by the authors in [1, 6], uses the 305 307 309 1105
DG
non-linear programming (NLP) formulation of a multi-period 306 1103
AC OPF adapted to determine the maximum DG capacity able 308 1104
to be connected to a given network. In addition to effectively Fig. 1 UK GDS EHV1 Network [22] and potential locations for distributed
handling the time-variation of multiple renewable sites and wind power generation.
demand, it also considers a range of active network techniques Maximum 54.6
DG Capacity
to allow maximum absorption of renewable generation 48.8
51.4
53.8
capacity while respecting voltage statutory limits and thermal 46.0
45.2 48.1
constraints. Active network management control algorithms 60 48.1
42.6
including coordinated voltage control of transformers and 45
39.4 44.5 43.0
voltage regulators, adaptive power factor control and energy (MW) 37.4
39.7
32.6 38.3
curtailment are embedded within the formulation. 30
29.6
The objective function corresponding to the maximisation 15
34.1
27.5 10%
of the total active DG capacity p of a set of generators G 5%
0
(indexed by g) across the set of periods M (indexed by m), is PFc 24.3
2%
given by ( ∀m ∈ M ): 0.98 (i) CVC+
CVC
max ∑ pg ,
Unity
g ∈G
(1) 0.98 (c) no CVC
no Curtailment
It is subject to the constraints presented in the Appendix.
Fig. 2 Full EHV 1 Network: Connectable DG capacity (in MW) with ANM
A. Case Study - Full EHV1 Network
strategies (c: capacitive, i: inductive, and PFc: adaptive power factor control).
Fig. 1 shows the EHV1 Network, a 61-bus 33/11-kV radial
distribution system available in [22]. The interconnector, The aggregate DG capacity that can be connected to the six
treated as a PV bus, has a target voltage of 1.00 pu and is able sites has been evaluated for all control modes and the results
3
are shown in Fig. 2. Due to the number of potential locations approaches [20, 21], only peak demand and passive operation
and their corresponding proximity to loads, relatively high of the network were considered.
values of connectable DG capacity were found. It is clear that Here, the AC OPF technique used in the previous section is
the greater flexibility offered by adaptive power flow control tailored to minimise energy losses across a given time
(PFc) leads to the largest wind power generation capacities in horizon. The objective function corresponding to the
all cases. Without coordinated voltage control (‘no CVC’ minimisation of the total energy losses of the network over a
case), PFc alone allows a DG penetration of 85% relative to time horizon comprising m periods, m ∈ M , is given by:
peak demand (an increase of around a fifth over passive ⎛ ⎞
management). The allowable penetration reaches 103% when min ∑ ⎜⎝ ∑ f
m∈M l∈L
+ f l ,2,mP ⎟ ⋅τ m
1, P
l ,m
⎠
(2)
applying CVC, while curtailment, permits progressively 1, P
greater integration of wind capacity, reaching 118% where f l ,m and fl ,2,mP are the active power injections at each
penetration for a limit of 2% and 143% at the 10% curtailment end (denoted 1 and 2) of branch l, l ∈ L ; and, τ m is the
level (i.e., doubling capacity). duration of period m. The difference between the net
Given the detailed modeling of each DG site, it is possible injections at each end of the branch defines the energy loss.
to have a breakdown of the connectable generation capacity
across the six sites (Fig. 3). The impact of using coordinated A. Case Study - Full EHV1 Network
voltage control and adaptive power factor control on the The previously described EHV1 Network (Fig. 2), together
available capacity of each location is evident. In the passive with the same data for demand and wind profiles (WP1 and
management case with fixed 0.98 capacitive power factor, WP2), is considered in this analysis. Using the segmented
more than 73% of the total capacity is sited on the mainland demand scenarios (similar to those applied in section II) for
(1108, 1106 and 1105). Adopting the CVC and PFc schemes, the original configuration (no DG) results in an annual
however, it is possible to make much more capacity available consumption of 214 GWh with energy losses of 4.7%
on the island, increasing it by almost three-fold to a 46% share (comparable with typical UK rural networks).
of the total capacity. Fig. 4 presents the minimum percentage energy losses that
can be achieved if wind power generation is optimally
1108
1106
1105
1113
1114
1115
were also considered in [25], where it was presented a multi- no CVC 0.98 (c)
such as minimum and peak demand do not normally coincide considering a three-phase fault at the MV busbar of the
with maximum wind potential. For this reason, more capacity substation. The initial symmetrical short-circuit power at the
than for firm generation can be connected to the network. It MV busbar resulting from the contributions of both the
can also be seen that, again, generation capacity is strongly upstream grid and the DG capacity connected to each feeder
related to the reduction of losses. It is worth pointing out that has to be limited to the design short-circuit capacity of the
while in most cases the CVC scheme only allows a marginal network, SCmax. The IEC 60909 standard is adopted for the
increase in capacity, when DG units are operated at 0.98 corresponding calculations.
capacitive power factor, the gain is much more significant. The fault level constraint incorporated into the single-
This is primarily due to the ability of the CVC scheme to period AC OPF formulation is as follows:
alleviate voltage rise problems. As for the PFc scheme, whilst 64 upstream grid
4744 DG fault contribution
8 644 7448
it does provide lower losses, it is also clear that, for this cmax ⋅Vb 1 2
cmax ⋅ Vb21
network, similar gains can easily be achieved by setting the +∑ ≤ SCmax (3)
Z SYS MV + ZT g∈G Z (b ,b ) + Z g
operation of the generators to unity or capacitive power factor. g 1
0.4
Kirchhoff’s current law describes the active and reactive
0.2
nodal power balance, ∀b ∈ B :
0.0
1.0
1 25 49 73 97 121
d0.7-w0.0
145 16
∑1,2 pbL,m + dbPηm = g∈G∑|β =b pg ωm + x∈X∑|β =b px,m (8)
l∈L| β = b l b g x
0.8
0.6 ∑ q L
b, m + d ηm =
Q
b ∑ pg ωm tan(φg , m ) + ∑ qx , m (9)
(p.u.)
( p , q )b , m
L
0.2
Here are the total power injections into lines at b;
0.0
1 25 49 73 97
Winter: 1st Week of January
121 145 16
and db( P ,Q ) are the peak active or reactive demands at the same
Fig. 6 (Top) Winter week hourly demand and wind power for central
Scotland, 2003 [36]. (Bottom) Discretised data processed before aggregating
bus. In period m, ηm is the demand level relative to peak and
the coincident hours of each demand-generation scenario.
6
BIOGRAPHIES
Luis F. Ochoa (S’01-M’07) is a Research Fellow
in the School of Engineering, University of
Edinburgh, U.K. He obtained his BEng degree from
UNI, Lima, Peru, in 2000, and the MSc and PhD
degrees from UNESP, Ilha Solteira, Brazil, in 2003
and 2006, respectively.
His current research interests include network
integration of distributed energy resources and
distribution system analysis. Dr. Ochoa is also a
member of the IET.